1 minute read

On-time Project Delivery In the Time of Pandemic

o Early pull planning to incorporate material lead times into fast-track design schedule o Design-Assist trade partners were able to release materials during design o Used choosing by advantages not just 1st cost to inform design decisions o Teaming with design team to review submittals while design was progressing o Incorporated prefabrication into design to minimize the number of onsite workers o Receiving and storing materials early offsite to allow for just in time delivery to the site o Daily huddles and material trackers to monitor any changes in lead time or manpower o Consistent refinement of pull plan to keep end date

This article is from: