Connect 2 ACES Newsletter Aug 2012

Page 1

September 2012

A QUARTERLY PUBLICATION BY THE ASSOCIATION OF CONSULTING ENGINEERS SINGAPORE

05

LTA Academy-ACES Seminar

11

ACES Site Visit to Gardens by the Bay Marina South

03

President’s Message

09

BIM E-Submission in Singapore

“The new council will continue to address major issues that are close to our hearts, such as matters in relation to the ever competitive nature of the business, the route towards greater productivity, the change to Eurocode and the investment into BIM technology.”


connect2aces A QUARTERLY PUBLICATION BY THE ASSOCIATION OF CONSULTING ENGINEERS SINGAPORE

In This Issue

September 2012 issue

Editor:

Er. Yeow Mei Leng

President’s Message

3

ACES 41st AGM

4

New Council Session 2012/2013

4

ACES Appreciation Dinner

5

LTA Academy- ACES Seminar

5

3rd Dialogue session with City Gas

6

LTA-ACES-IES Dialogue Session

6

MICA No. MICA (P) 189/07/2012

Dialogue session with Green Mark Task Force

7

Please send queries and feedback to: E-mail: secretariat@aces.org.sg Tel: 6324 2682 Address: Thomson Road Post Office, PO Box 034, Singapore 915702

BIM E-Submission in Singapore

9

Editorial Team: Ms. Charmaine Fang Er. Yow Cheong Hoe Ms. Lilian Lean Contributors for this issue:

Er. Ling Shiang Yun Er. Callan Lam Er. M. Sivakumaran BCA Er. Lim Peng Hong JIB Specialist Consultants Pte. Ltd. RSP Architects Planners & Engineers (Pte.) Ltd.

‘Connect2ACES’ is published quarterly by the Association of Consulting Engineers Singapore. The publisher and the editor are unable to accept any liability for errors or omissions that may occur, although every effort has been taken to ensure that all information is correct at the time of going to press. This publication may not be reproduced in part or in whole, without the written permission of the publisher.

Designed by: ArtNexus Design Pte Ltd Printed by: GPS Print Media Pte Ltd

Formation of M&E RE / RTO Registry

10

past EVENTS / seminars

11

Upcoming Events

12


President’s Message “Out of the nine vacancies in the council, seven existing council members were re-elected together with two new elected members.”

Er. Koh Boon Liang President

ACES 41st AGM & Election This year AGM was held on the 22nd June 2012 at the Furama Riverfront Hotel. We were indeed glad to have a very large turnout and support from members for this annual event. Out of the nine vacancies in the council, seven existing council members were re-elected together with two new elected members. The new council will continue to address major issues that are close to our hearts, such as matters in relation to the ever competitive nature of the business, the route towards greater productivity, the change to Eurocode and the investment into BIM technology. Many more activities to support the industry on the above will be conducted for our members during the coming year. The proposed amendments in the constitution was deferred and the new council will discuss further on another time to table the amendments. BIM Moving forward, the mandatory BIM format e-submission for regulatory approval will be introduced by

Building and Construction Authority (BCA) in the phases: • From 1 July 2013, all architectural plans, starting with DC submissions, for new building projects more than 20,000 sqm • From 1 July 2014, all engineering plans for new building projects more than 20,000 sqm • From 1 July 2015, all plans for new building projects more than 5000 sqm To assist members in getting ready for BIM implementation by July 2014, ACES has in the pipeline, seminars on BIM awareness, BCA funding and hand-on workshops in the coming months. Eurocode The Eurocodes signal a new beginning in the design of buildings and civil engineering structures. The Building and Construction Standards Committee (BCSC), with the support of the Building and Construction Authority (BCA) and other key partners started the development of SS based on the Eurocodes and UK National Annexes. This followed the announcement by BCA on 20

October 2006 to adopt Eurocodes in Singapore. A series of SS Eurocodes and National Annexes were subsequently published from 2008 onwards to facilitate the adoption of Eurocodes in Singapore. In line with this, ACES will be organising seminars on Eurocode – C&S and Geotechnical in coming months. The recent Bugis Downtown Line (DTL) accident on 18 July 2012, where two workers were killed in a scaffolding collapse, again reminded us of the heavy responsibilities put on the shoulders of all stakeholders, we must constantly be vigilant in performing our role and duties together with stakeholders. ACES will continue to support all our members so that collectively we are able to communicate with the various authorities and other stakeholders in the built environment to help make our business a sustainable and rewarding one.

September 2012 • 3


ACES st

41 AGM 22 June 2012

T

his year ACES 41st Annual General Meeting was held on 22 June 2012 at Furama Riverfront Hotel, Level 5, Mercury Room I & II. The turn out was good and saw a total of 44 members in attendance. The President gave an update of the activities that had been organized by ACES, and the different initiatives that had developed during the last session. The President thanked all the members and fellow council members for their tremendous support on all the events. The key items in the agenda and the audited financial report were adopted

By Er. Yeow Mei Leng

and approved. There were interesting discussions on the proposed amendments to the Constitution, where opposing views were discussed at lengths. As no eminent resolution could be reached, the meeting agreed to delay this amendments to a later date. This year saw 9 council members retiring from the Council, and new elections would have to be done to fill the vacancies. This year also saw the highest number of nominations, and many new faces stepping forward to serve. It was indeed encouraging and demonstrated that the consulting practice saw the need to engage

the industry with their participation and to elevate the status of the engineering profession. There were a total of 14 nominations vying for 9 positions and each nominee is as strong as the other. The final 9 who were nominated are, and not in any order: 1. Koh Boon Liang 2. Loh Wah Kay 3. Yeow Mei Leng 4. Lim Hung Tjung, Henry 5. Sivakumaran Murugesu 6. Wan Fook Sing 7. Cheang Mun Keong, Thomas 8. Chua Tong Seng 9. Han Kim Siew, Vincent

New Council Session 2012/2013 ACES COUNCIL SESSION 2012 TO 2013

I

n accordance with clause 9 of the President, Honorary Secretary and ACES COUNCIL SESSION EXECUTIVE COUNCIL Constitution, the new ACES council Honorary Treasurer were elected will consist of 13 members made EXECUTIVE from theCOUNCIL council members in the up of 3 remaining members, 9 newly 1st council meeting, and the various elected members and the immediate portfolios were also assigned to each past president. The President, Vicecouncil members.

ACES COUNCIL SESSION 2012 TO 2013

President

Er. Koh Boon Liang ACESCOUNCIL Council Session 2012/2013 Vice-President President EXECUTIVE Er. Koh Boon Liang

EXECUTIVE COUNCIL

President Er. Koh Boon Liang President

Er. Koh Boon Liang

COMMITTEE CHAIRMAN

Hon. Secretary/

M&E Practice (Mech.) Publications Er. Yeow Er. Callan LamMei Leng

two members into the Council to help with some of the portfolios. The make up of the Council is shown below.

Vice-President Er. Ling Shiang Yun

Hon. Secretary

Er. Ling Shiang Yun CHAIRMAN Er. Yeow Mei Leng COMMITTEE

COMMITTEE CHAIRMAN COMMITTEE CHAIRMAN

Vice-President Er. Vice-President Ling Shiang Yun

Er. Ling Shiang Yun

The TO Council also agreed to appoint 2012 2013

Hon. Secretary Hon. Treasurer Er.M Yeow Mei Leng Er.&Loh Wah Kay &E Practice (Mech.) M E Practice (Elect.)/

(Mech.) Er. Callan Lam M&E Practice IT Development (Elect.) Er.Practice Wan Fook Sing Er.M&E Callan Lam

M&E Practice (Mech.) Er. Callan Lam

Er. Wan Fook Sing

C&S Practice C&S Practice Hon. Treasurer/ M&E Practice M&E Practice (Elect.) C&S Practice Er.(Geotechnical) M.Sustainability) Sivakumaran (Geotechnical) Premises C&S Practice (Geotechnical) (Green & C&S Practice Business Practice Er.Er.Wan Sing Er. Sivakumaran Er. Chua Tong Seng Loh Fook Wah Kay Seng Er. Tong Vincent Han Er. Chua Er. Chua Seng Er. Tong Russell Cole

M&E Practice

M&E Practice (Elect.) (Green Sustainability) M&E&Practice Er. Vincent HanSing Er. Wan (Green & Fook Sustainability) Er. Vincent Han

Business Practice

Er. Russell Cole Business Practice Prof. Development Thomas Cheang Er.Er. Russell Cole

Hon. Secretary Er. Yeow Mei Leng

Hon. Treasurer Er. Loh Wah Kay

IMMEDIATE PAST PRESIDENT

M&E Practice

PPP, BIM (Green & Sustainability) C&S Practice

Lim Peng Hong Er.Er.Vincent Han

Er. Sivakumaran

Development ITProf. Development Thomas Cheang Er.Er. Wan Fook Sing

APPOINTED COUNCIL MEMBERS

C&S Practice (Geotechnical) Er. ChuaMembership Tong Seng Dev. Er. Serena Yap

Prof. Development Social Development Prof. Development IT Development Publications Social Development Business Practice Er. Thomas CheangPublications Er. Henry Lim Er. Yeow Mei Leng Er. Thomas Cheang Er. Wan Fook Er. Henry LimSing Er.C& Russell Cole S Practice (Eurocode)

4 • Connect2aces

Er. Joanne Wong

Er. Yeow Mei Leng

APPOINTED COUNCIL MEMBERS

Premises

Social Development Er. Loh Wah Kay Er. Henry Lim

APPOINTED COUNCIL MEMBERS

Hon. Treasure Er. Loh Wah K

Premises Er. Loh Wah Kay

C&S Practice Er. Sivakumar

IT Developme Er. Wan Fook S


ACES

Appreciation Dinner

By Er. Yeow Mei Leng

A

CES held its yearly appreciation dinner for members who had volunteered and committed their time and resources in representing ACES in a myriad of activities which affect the consultancy practice and the building construction industry as a whole.

A total of 53 participants had made time to attend the appreciation dinner held at Dragon Phoenix Restaurant, 177 A, River Valley Road Level 6, Novotel Clarke Quay Singapore (Liang Court) on 9 May 2012. Certificates of appreciation were presented to all the volunteers

9 May 2012

serving in various external committees. The Council members were also included. In this round, token of appreciation in the form of pewter plaques and thank you letters were presented to a total of 20 contributors, who had donated to ACES Premises fitting-out works.

LTA Academy - ACES Seminar By Er. Ling Shiang Yun

F

ire in rail and road tunnels can be devastating and catastrophic. Because they are enclosed spaces, smoke and toxic gases can quickly spread along the tunnels making condition untenable for people trapped inside. Temperature in the tunnels can also rise very quickly due to rapid development of the fire and can cause extensive damage to the tunnel structures and installations resulting in prolonged closure of the tunnels for repairs and restoration.

On 10 July 2012, the LTAA-ACES seminar held at LTA auditorium drew the response of about 170 participants. This seminar has provided the participants with an overview of the fire protection system, and rail & road tunnels ventilation system. 1st speaker, Er. Yeo Swee Khiank (Sereca Fire Consulting Ltd) on the topic ‘Overview of Fire and Life Safety provisions in Road and Rail tunnel’. Er. Yeo presented his experiences on the fire protection system and the fire and life safety provision for rail and road tunnels to mitigate the risks and consequences of fire. The topics included road & tunnel exit provisions, fire incident detection system, fire suppression system, monitor and evacuations signage in tunnels and communication system. 2nd speaker, Er. Lim Lean Wan (LTA) on the topic ‘Ventilation of Road and Tunnel’. Er Lim gave an insight on the rail and road tunnels ventilation, fire incident management, smoke management system, and emergency exercise activities undertaken by LTA. The objectives are to provide safe and acceptable environment for road and tunnel users, and control smoke movement during emergency fire condition. The topic also covered Integrated Traffic and Plant Management System (ITPMS), road tunnel operation and response and recovery. Participants found the topic interesting and very informative as the presentation were filled with practical illustrations.

September 2012 • 5


3rd Dialogue session with

City Gas 28 March 2012

By Er. Callan Lam & Er. Yeow Mei Leng

T

he 3rd dialogue session with City Gas was held on 28 March 2012. Issues raised by ACES and City Gas/Power Gas/EMA responses were as follows:

A. Designated Representative’s consent ACES asked whether the Building’s Designated Representative (DR) or the building owner should issue the written consent if the building tenant was not the owner of the gas installation. Power Gas pointed out that the responsible person for the gas installation to issue written consent could mean any person such as the building owner, the DR, the MCST or the main contractor of the project depending on whether the person had been empowered to be the responsible person or not. EMA further confirmed that under the Gas (Supply) Regulations, the applicant has to obtain the consent from the responsible person so long as he or she has been empowered to be the responsible person to act for the gas installation owner. City Gas reiterated that the applicant must obtain the consent from the responsible person prior to the commencement of gas service work if the applicant was not the owner of the gas installation to be connected to. B. b. Procedures for Gas Turn On ACES put forward the current procedures to City Gas and Power Gas and suggested to streamline the whole process to enable easy submission of applications for gas supply and gas connection. ACES suggested to

combine the application forms for gas connection and gas supply in the handbook into one single form. EMA stated that the procedures for admittance of gas and turn-on of gas supply were two different processes. It was not advisable to combine both forms into a one common form. In addition, there are more than one gas retailers in the gas industry. Each gas retailer is required by the Gas Supply Code to establish and publish a Handbook on Gas Supply to provide a comprehensive guide to developers, consultants, professional engineers and licensed gas service workers in the application of gas supply. City Gas added that the application for gas connection shall be made to gas transporter and application for gas supply to be submitted to gas retailer. Gas transporter and gas retailer were two different licensees. City Gas reiterated that the current forms were appropriate. It was not recommended to reduce the form for safety reasons. C. c. Relocation of gas meters for HDB flats EMA replied that SCDF is the approving authority for the fire safety requirements, based on the circular issued by SCDF on 7 Jun 2011. The PE(Mechanical) would have to submit to SCDF a declaration form that the proposed meter location was in compliance with SCDF fire safety requirements and would notify City Gas before commencement of work. After completion of work, QP would request City Gas to turn on the gas supply to the premises.

LTA-ACES-IES Dialogue Session

D

uring the Dialogue session held on 24 July 2012, LTA announced the following two major steps undertaken to assist consultants who carry out external works submission to LTA DBC:-

1. Expansion of Lodgment Scheme for Street Plans to include Development by Road Reserve Line.

by Er.M.Sivakumaran

2. Streamline Process for coordinated reply with traffic and street lighting requirements. LTA sought feedback from the practice with regards to regulations on the Road Structures Safety Zone introduced by LTA DBC. Feedback form Practice regarding various issues received by ACES & IES were brought to LTA’s attention.

6 • Connect2aces


Dialogue session with

Green Mark Task Force 11 June 2012

By Er. Callan Lam & Er. Yeow Mei Leng

A. ACES feedback Arising from the implementation of Green Mark version 4, the industry had been experiencing some compliance issues. These issues were collated and raised with the Green Mark Task Force Team in a meeting with BCA on 11 June 2012. The dialogue session was a fruitful one and through it all, BCA has replied and confirmed on certain requirements and practices that is helpful to our ACES’ members, please refer to the table below. B. Baseline for small fan systems According to BCA, there will be no energy savings claims for small fan systems less than 4 kW under version 4. Excluding the small fans, projects like hotels with many small FCUs, the difference in the overall energy savings can be quite significant. After much deliberation, the taskforce agreed to adopt the baseline of 0.17kW/CMH for fan power less than 4kW; ducted fans with fan power less than 4kW will be studied further. The taskforce also confirmed that the total fan

system power only refers to the supply fan motor and does not include fresh air and exhaust fan power. C. Nameplate power ACES’s feedback on the use of absorbed power instead of nameplate power for fan in the energy modelling. There are many energy modelling software do not allow direct input of nameplate power for computation. BCA suggested two options for task force consideration: ASHRAE 90.1 Table: 6.5.3.1.1A Fan Power Limitation Option Constant Volume Option 1: kW ≤ L/Ss . 0.0017 Fan System Motor Nameplate kW Option 2: Input kWi ≤ L/Ss . Fan System input KW 0.0015 + A

Variable Volume kW ≤ L/Ss . 0.0024 Input kWi ≤ L/Ss . 0.0021 + A

The taskforce agreed that Option 2 is acceptable as it will have a more stringent baseline and provide more flexibility with the use of absorbed power.

Green Mark Advisory Committee - Taskforce Meeting on Review of Gm Version 4.0 - Energy Efficiency Requirement Item ACES’ Descriptions ACES’ Feedbacks & Recommendations 1 BCA is not accepting the energy BCA to allow savings but basing on 0.17 w/cmh. savings for motors < 4kW, which they claim that there is no benchmark set in clause 14.2.1 SS553. 1a

Fan power less than 4kW

1b

Fan power : Request clarification as to which systems 0.667 W/CMH as benchmark (variable flow) can be applied to for MV systems

2

BCA to review the energy savings % for developments served by district cooling plants. Currently for Platinum rating, developments on DCS plants have to prove energy savings of 33%. If the receptacle load for this development is high, which it usually is (as such buildings usually have data centres/banks/ IT companies as their tenants) the absence of the chiller plant in this equation is a penalty on the energy savings.

Taskforce’s Conclusion Use the baseline of 0.17W/CMH for all fan systems for fan power less than 4kW. In particular, if the fan efficiency is worse than 0.17W/CMH for the case of ducted FCU and AHUs, ‘negative’ saving will not be accounted for. As above.

Why should the benchmark be 0.17 W/CMH – what is the basis for this? This sub 4kW fan issue is one of the biggest problems in the GM process at present but it is not appropriate to propose that the basis shall be 0.17 W/CMH for all. It may be possible for FCU systems (requires better definition) less than 4kW to adopt 0.17 W/CMH. There are many MV systems and AHU systems which fall into a category less than 0.4kW for which the real pressure requirements mean that a higher benchmark is required. Can BCA consider a higher benchmark like 0.22 W/CMH? There seems no basis why a variable flow MV To adopt only one baseline for constant system has a higher benchmark (for AC systems flow and variable flow/speed for MV fan, there is at least rational for this difference) i.e. 0.47 W/CMH. Any saving via CO sensor will be calculated and reflected under the criterion of Energy Efficient Features. For buildings without chiller plant, the energy Saving of 33% exclude the consumption savings should be 30% or lower. At the moment, of chiller. If the receptacle load is high, for chilled water tapping from DCS plant, BCA the receptacle load will be capped at 25% requires 33% based on audit requirements. of the total building consumption with baseline chiller. BCA will include a clearer FAQ on website to explain this.

September 2012 • 7


Dialogue session with Green Mark Task Force

Item ACES’ Descriptions ACES’ Feedbacks & Recommendations 3 BCA does not accept energy savings BCA to accept energy savings calculations calculation worked out by lift suppliers substantiated by the lift suppliers for to substantiate the savings for regenerative lifts and gearless lifts. regenerative lifts and gearless lifts. Currently regenerative lifts energy savings is capped at 18%, and no savings to be claimed for gearless lifts.

4

5

6

6a

7.

8

9

Currently for areas where the lighting power budgets are not defined in SS530, no savings could be claimed. Hence not much “push” factor for the development to concentrate on the lighting power budget for such areas. Currently the verification stage process is not too clear yet. The developer does not know when to call the auditors in to conduct the verification stage, what information to provide, how many months of data logging is required, when should the data logging commence, etc. In the current practice, only the base building’s Mechanical and Electrical PEs are required to endorse on GM application although the documentation is prepared the GM consultant.

Taskforce’s Conclusion The saving cap of regenerative lift of 18% is on top of VVVF system and sleep mode. VVVF system and sleep mode will be able to claim 10% energy saving. If the regenerative have VVVF system and sleep mode as well, they will be able to claim a maximum of 18% + 10% = 28% energy saving. Assessors will also review on other innovative lift systems and saving on caseby-case basis. For items not in the SS530, BCA assessors BCA should consider to come up with a list of lighting power budget for such typical areas that are willingly to accept other reasonable are not covered under SS530 (toilets, M&E plant baseline for reliable sources, such as rooms, kitchens, etc). ASHRAE. BCA should clearly document and inform all projects on the requirements as part of the BCA Green Mark Certification Standard document.

BCA to insist that a qualified GMP to endorse on the GM application and submission in addition to the Base Building’s PE Endorsement. The base building’s PE should only be responsible for the M&E equipment and systems. The GMP is responsible for the computation, analysis , modelling , EEI and all other requirements for achieving the GM. BCA has been requested the The PE’s should have a responsibility to confirm Mechanical & Electrical PE’s to endorse the basis of the GM submission and calculation that building operational energy is consistent with the building design. The PE’s (specifically kW/RT for cooling systems) do not operate the building and have control of will meet specific targets. the usage and decisions made by the building operator, so such an endorsement is not appropriate to the PE’s responsibility. Nameplate power in respect of energy modelling. In assessments, BCA is adopting nameplate power as the basis for fan and pump systems in energy models. Appendix B of the GM Certification Standard (V4) has contradictions in applying nameplate power to worked examples. BCA expresses that the use of nameplate power, rather than absorbed power, is a means to prevent overdesign. For a large fan or for a chilled water pump, the difference between the absorbed power and the next step in available motor size can be considerable, up to 40% and this is unreasonable in predicting energy usage. The basis for the EEI Calculation described in Appendix E of the BCA GM Certification Standard for New Buildings includes a factor for vacancy rate (VCR) General changes to GM requirements and implementation. BCA has imposed requirements on developers which are not stated within the GM Certification Standard or other referred codes. For example energy savings associated with small fans. A number of features of the V4 requirements were also required to be adopted by V3 projects

8 • Connect2aces

BCA will draft up a clear guideline and make it available on website. It will also be reflected under FAQ.

To remain status quo due to 1. GMP may not have the capability to undertake the design. 2. PE will have take responsibility on the changes in design and proposal recommended by GMP.

BCA will publish verification guideline on website to help building owners to understand what is required during verification. Concerns will also be addressed under FAQ. Building owners need not engage the same PE that design for the building system to endorse on the building operational energy efficiency. Propose that the methodology be revised to: Project team is allowed to use option 2 Use nameplate power for compliance with SS553 under ASHRAE 90.1 2007 Clause 6.5.3.1 and Table G3.1.2.9 which uses input power in terms of maximum power/flow for air side with better baseline for energy simulation. and water side systems (ie, cap the over design situation) -Use absorbed power for equipment (air side and water side) for energy simulations for the proposed building (which are compared against a reference benchmark which does not get penalised by ‘nameplate rating’)

This factor should be zero for new building modelling. It comes about historically where EEI figures are used as a benchmark for measuring the actual energy consumption of a building in use (where the EEI will be higher if a vacancy rate is applied). Suggest that changes to the administration of GM projects need to be advised publically and then a stand down period (likely one year) be applied prior to the implementation of changes.

VCR to keep.

BCA will issue circulars in advance to reflect important decisions and critical changes.


BIM E-Submission in Singapore By BCA,coordinated by Er. Lim Peng Hong

G

lobally, a common strategy adopted by governments to encourage BIM adoption in the industry is to set a deadline for mandatory use of BIM for projects of a certain size or complexity. For example, by 2016 it will be mandatory for the use of BIM in all UK government projects over £5 million. Besides leveraging on the use of public procurement policy to drive BIM adoption, Singapore will capitalize on the use of the CORENET system, which is already embraced by the industry, to speed up the use of BIM. In January 2011, BIM e-Submissions were officially accepted for the architectural discipline; and also for the engineering disciplines in April 2011. Under BCA leadership, 12 regulatory agencies work together to allow BIM-ready Qualified Persons (QP) to submit their BIM for various aspects of regulatory approvals via the CORENET system. Singapore became the first country in the world to accept full BIM electronic submissions for regulatory approval, and starting from July 2013, BIM e-submissions will be mandatory for certain projects and disciplines. To help industry professionals with BIM e-submission, a set of BIM e-submission guidelines and templates have been developed by CORENET participating agencies in 2010. They play an important role in standardizing the way BIM models are being prepared across the industry. This is similar to how

Release of a Mandatory BIM E-Submission circular to the industry on 2 July 2012 Date*

Discipline

Project GFA

Project type

July 2013

Architectural

> 20,000 m only

New Construction only

July 2014

Engineering (C&S, M&E)

> 20,000 m only

New Construction only

July 2015

All of the above

> 5,000 m2 only

New Construction only

2 2

* Only applicable to projects whose DC submissions occur after this date

Schedules for 2012 Monthly Free Workshops on BIM E-Submissions Discipline

Date

Venue

Time

Contacts for enquiries and registration (one week in advance)

Architecture 3 Aug, 7 Sept, 5 Oct, 2 Nov, 7 Dec

Centre for 2:30 pm Construction IT, –5:30 pm BCA Academy

Ms Soon Lay Kuan soon_lay_kuan@ bca.gov.sg

M&E

29 Aug, 26 Sept, 31 Oct, 12 Nov

IT Room 3, BCA Academy

2:30 pm – 5:30 pm

Mr Liu Ziwen liu_ziwen@bca. gov.sg

C&S

30 Aug, 13 Sept, 23 Oct, 9 Nov

IT Room 3, BCA Academy

9:00 am – 12:00 pm

Mr Sonny Andalis sonny_andalis@ bca.gov.sg

2D CAD standards (CP 83) had resulted when CORENET was first introduced in 2001. Such a standard helps to improve data sharing and collaboration among the project team members. Leading to the mandatory dates, a series of monthly free workshops on BIM esubmissions have been arranged by the BCA’s Centre of Construction IT (CCIT) to train Qualified Persons (QPs) on the BIM e-submission

requirements. Hand-holding will also be provided to firms that are doing BIM e-submissions for the first time. Besides getting QP firms ready to prepare BIM e-submissions, CCIT will also solicit feedback from the firms to refine the e-submission guidelines and templates. Together with the QP firms, CCIT also hopes to identify a set of BIM based software utilities that are useful to the QP in automating computations (e.g. Concrete Usage September 2012 • 9


Update on BIM from Steering Committee

Index, Buildability Score and Constructability Score) needed to meet the regulatory requirements. The capacity of the CORENET system will also be closely monitored by

the CORENET infrastructure team to ensure that there is sufficient capacity to handle BIM models, which is normally bigger in file size as compared to 2D drawings.

1. BCA, CBPU, CityGas, FSSD, HDB, IDA, JTC, LTA, NEA, NPark, PUB and URA 2. Available online at http://www.corenet. gov.sg/integrated_submission/bim/bime_ submission.htm

Formation of

M&E RE / RTO Registry

By Er. Callan Lam & Er. Yeow Mei Leng

T

o improve the quality and competence of the resident site staff for building services, the M&E Practice committee had mooted the idea of a Registry of M&E RE / RTO.

The intention was also to have the Joint Accreditation Committee (JAC), which is administered by both ACES and IES, to maintain both the registers. The JAC besides administration, will be also looking

A similar Seminar cum Awards Night has been proposed for the future M&E RE / RTO Registry.

10 • Connect2aces

after registrations for practitioners in other engineering fields. ACES and IES had several meetings and discussions on the process of setting up the M&E RTO / RE registry, and to work out the selection criteria, qualifications, works experiences etc. The application forms are now ready and ACES / IES is planning to launch the M&E RE / RTO Registry in September 2012. JAC will be targeting at least 200 M&E RE / RTO. Members are requested to encourage their site staff to submit their applications and to remain in the register. In the long run, this register can be used as a reference for members who wished to engage M&E site staff.


ACES Site Visit to Gardens by the Bay Marina South

past EVENTS / seminars

05 Apr 2012

T

his site visit held on 5 April 2012 was supported by National Parks with a total 32 participants. The three invited speakers were Er. Johnny Lim, Er. Russell Cole and Er. Thomas Cheang.

Er. Russell Cole’s presentation focused on the design of the biomes' shell structure. The two biomes were designed stimulating coolmoist or cool-dry environment housing a variety of plants from different climate regions. Er. Russell highlighted the role of Arup’s facade engineering in these enclosures, touching on forms, modulation studies, geometry resolution and typical glass and glazing systems. He also shared with the participants on how the shading devices contribute to the indoor climate control of the biomes for plants to strive and how the maintenance access was developed for this state of the art structure. Er. Johnny Lim and Er. Thomas Cheang further shared with participants on the mechanical & electrical aspects of sustainable engineering technologies and design principles deployed in Gardens by the Bay Marina South such as the type of façade, slab cooling, shade control, liquid desiccant system, PV system, biomass and bio-diesel co-generation system.

ACES In-House Seminar: BIM Experience in Implementation 19 Apr 2012

T

his in-house seminar on BIM was held at ACES Premises on 19 April 2012 with 41 participants. The three invited speakers shared their experiences on BIM implementation and lessons learned along the way.

Mr. Phil Lazarus, Arup gave an introduction on BIM and his experience on BIM-C&S implementation, covering the fundamentals of BIM and how it affects building projects. He also provided detailed examples of BIM implemented in several large construction projects in Singapore and around Southeast Asia. Mr. Bryan, Beca shared his experience on the implementation of BIM-MEP on one of their recent projects and outlined some of the key challenges (internal and external) faced by the design team during project implementation phase. Lessons learnt provided useful information for industry practitioners considering implementing BIM technology in their projects. Lastly, Mr. Vijay Raina, Autodesk demonstrated how the transition from CAD into BIM benefits its application in the design and analysis aspects for structural engineers.

September 2012 • 11


past EVENTS / seminars

ACES-YPC Coffee Table Chit-Chat Session 25 Apr 2012

T

his informal chit-chat session 1 was held at Mott MacDonald’s premises on 25 April 2012. 15 young engineers attended the session where experience was shared by Mr. Muzzamil Rizwan for building damage assessment and Er. Yow Cheong Hoe for structural assessment of an old building. All attendees had

a great time sharing knowledge and building friendship. The event started at 7:30pm and ended at 9:00pm. The YPC Committee hoped to gather more and expand the session for 25 attendees in the next round.

Upcoming Events 28 Aug 2012

(Date TBC)

ACES – Autodesk BIM Seminar (1st)

ACES-Vnix Joint Seminar (Dell Solutions)

18 Sin Ming Lane #06-01 Midview City Singapore 573960

18 Sin Ming Lane #06-01 Midview City Singapore 573960

19 Sep 2012

Details to be provided nearer to the date

ACES-Fluke South East Asia Seminar (Predictive Maintenance Make Easy)

17 Nov 2012

18 Sin Ming Lane #06-01 Midview City Singapore 573960

Details to be provided nearer to the date

5 Oct 2012

Networking Night

Details to be provided nearer to the date

(Date TBC)

LTA Academy – ACES Joint Seminar Block 5, LTA Auditorium, No. 1 Hampshire Road, Singapore 219428

Details to be provided nearer to the date

30 & 31 Oct 2012 (Tue/Wed)

ACES DfSC Course (2-days course) 18 Sin Ming Lane #06-01 Midview City Singapore 573960

Details to be provided nearer to the date

(Date TBC) ACES C&S Seminar on Eurocode Speakers: Dr. Tan TH

Details to be provided nearer to the date

12 • Connect2aces

ACEM-ACES 8th Dialogue Kuching, Sarawak

Dialogue between the Councils of ACEM and ACES

Nov 2012 (Date TBC)

Schneider-Electric Low voltage protection 18 Sin Ming Lane #06-01 Midview City Singapore 573960

Details to be provided nearer to the date

Nov 2012 (Date TBC)

ACES – Autodesk BIM Seminar (2nd) 18 Sin Ming Lane #06-01 Midview City Singapore 573960

Details to be provided nearer to the date

Dec 2012 (Date TBC)

PPP Roundtable Discussion TBC

Details to be provided nearer to the date

Dec 2012 (Date TBC) RE & RTO Seminar cum Awards Night Details to be provided nearer to the date


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.