SITE SELECTION

PROJECT INFORMATION

LITERATURE REVIEW

PROCESS DESIGN

CASE STUDY

ARCHITECTURE DESIGN


SUSTAINABLE CONCEPT

CONSTRUCTION BUILDING

MECHANICAL SYSTEM

COST ESTIMATE

CONSTRUCTION PROCESS

SUMMARY


PROJECT

INFORMATION TERM OF REFERENCE OBJECTIVE OF PROJECT TARGET GROUP CONCEPT AND SELLPOINT CONSUMER PROFILES USER OF PROJECT AERA REQUIREMENT


01 PROJECT INFORMATION

TERM OF REFERENCE

PROJECT INFORMATION ARCHITECTURAL

T O R THE STANDARD

HOSPITAL

GOALS

EIA

o

o

o

o

o o

o

LEED GOLD


01 PROJECT INFORMATION

THE SILVER ECONOMY


01 PROJECT INFORMATION

MEDICAL ECONOMIC SITUATION

SINGAPORE

THAILAND


01 PROJECT INFORMATION

REGENERATIVE MEDICINE

1 2

3


01 PROJECT INFORMATION

LIVELY

YOUNG AT HEART ENERGETIC

GROW


01 PROJECT INFORMATION

TARGET GROUP


01 PROJECT INFORMATION

SELL POINT


01 PROJECT INFORMATION


01 PROJECT INFORMATION

USER ANALYSIS


01 PROJECT INFORMATION

MAIN USER


01 PROJECT INFORMATION

MAIN USER


01 PROJECT INFORMATION

MAIN USER


01 PROJECT INFORMATION

SUB USER


01 PROJECT INFORMATION

MAIN USER


01 PROJECT INFORMATION

MAIN USER

TARGET

ELDERLY TOURIST


01 PROJECT INFORMATION


01 PROJECT INFORMATION


01 PROJECT INFORMATION


01 PROJECT INFORMATION

FROM STANDARD


01 PROJECT INFORMATION

เวชศาสตร์ ฟื้นฟู


01 PROJECT INFORMATION

MAIN FUNCTION AREA REQUIREMENT EMERGENCY ROOM

DIAGNOSTIC AND THERAPEUTIC DEPARTMENT ส่วนวิเคราะห์และบาบัดรักษา

TOTAL AREA

OUT-PATIENT DEPARTMENT ส่วนผู้ป่วยนอก

TOTAL AREA

• • • • • • • • • • • •

• •

• •

REHABILITATION UNIT

TOTAL AREA

TOTAL AREA


01 PROJECT INFORMATION

MAIN FUNCTION

TOTAL AREA

REHABILITATION UNIT

PHYSICAL THERAPY

• • •


01 PROJECT INFORMATION

MAIN FUNCTION

TOTAL AREA

REHABILITATION UNIT

ELECTRICAL STIMULATION (ES)

ANTI - AGING • •

• • • • •

• •


01 PROJECT INFORMATION

MAIN FUNCTION

TOTAL AREA

REHABILITATION UNIT

PSYCHIATRIC DEPARTMENT

• • • • •

• • •


01 PROJECT INFORMATION

MAIN FUNCTION

TOTAL AREA

REHABILITATION UNIT

THAI TRADITION MEDICINE

CHINESE TRADITION MEDICINE

• • •


01 PROJECT INFORMATION

MAIN FUNCTION AREA REQUIREMENT IN PATIENT DEPARTMENT

TOTAL AREA

TOTAL AREA

TOTAL AREA

TOTAL AREA


01 PROJECT INFORMATION

SUPPORT FUNCTION

SUB FUNCTION

AREA REQUIREMENT

AREA REQUIREMENT

SUPPORTIBG SERVICE DEPARTMENT ( medical )

TOTAL AREA

SUPPORTIBG SERVICE DEPARTMENT (Maintenance )

ADMINISTRATION DEPARTMENT

TOTAL AREA

TOTAL AREA


01 PROJECT INFORMATION

SUB FUNCTION AREA REQUIREMENT SUPPORTIBG SERVICE (Commercial)

TOTAL AREA

PARKING

TOTAL AREA


01 PROJECT INFORMATION

SUB FUNCTION

AREA SUMMARY AREA REQUIREMENT

SUPPORT FUNCTION

MAIN FUNCTION


01 PROJECT INFORMATION

NET SALE AREA AREA REQUIREMENT


LITERATURE REVIEW LAW AND REGULATION DESIGN STANDARD LITERATURE REVIEW


02 LITERATURE REVIEW

LAW & REGULATION


02 LITERATURE REVIEW

DESIGN STANDARD


02 LITERATURE REVIEW

JCI STANDARD

4 SECTION 7 Edition


STAND ARD

02 LITERATURE REVIEW


SITE

SELECTION CRITERIA OF SITE SELECTION SITE SELECTION SITE ANALYSIS


0 SITE SELECTION

INTERESTED COUNTRY.

THAILAND

CHIANGMAI

KHONKAEN NAKHON RATCHASIMA CHONBURI

HUB IN EACH REGION

NAKHON SI THAMMARAT THAILAND POLICY

PHUKET

MEDICAL HUB

CRITERIA : OCCUPANCY RATE

TRANSPORTATION

POPULATION/TOURIST

POLICY


03 SITE SELECTION

CRITERIA OF SITE SELECTION


03 SITE SELECTION

CRITERIA OF SITE SELECTION


03 SITE SELECTION

CRITERIA OF SITE SELECTION

• • • •

• • •


03 SITE SELECTION

CHIANGMAI.


03 SITE SELECTION

SITE SELECTION

CHAINGMAI


03 SITE SELECTION

SITE SELECTION


03 SITE SELECTION

CRITERIA OF SITE SELECTION


03 SITE SELECTION

A

PROS CONS

SITE SELECTION IN CHIANGMAI

33,420 sq.m.

33,360 sq.m.

SITE SELECTION IN CHIANGMAI

B

PROS CONS


03 SITE SELECTION

C

PROS CONS

SITE SELECTION IN CHIANGMAI

sq.m.

SITE SELECTION IN CHIANGMAI

D

PROS PROS CONS CONS


03 SITE SELECTION

C

SITE C


03 SITE SELECTION

SITE ANALYSIS

SITE


03 SITE SELECTION

SITE ANALYSIS

SET BACK


03 SITE SELECTION

SITE ANALYSIS


03 SITE SELECTION

SITE ANALYSIS


SUCCESSFUL HOSPITAL HIGHLIGHTS OF HOSPITALS FUNCTION AND PLANNING STUDY CONCEPTUAL ATTRACTIVE DESIGN AND STRUCTURE DESIGN GUILDELINE

CASE

STUDY


0 CASE STUDY

CASE STUDY LAYOUT

DESIGN / STRUCTURAL

DESIGN

PROGRAMING

GUIDELINE

COMPETITORS


0 CASE STUDY

DESIGN GUIDELINE COMPETITORS

COMPLETE MEDICAL CENTER

PROGRAMMING

CHARACTERISTIC DESIGN AS SELL POINT

WELL-BEING ACTIVE LIVING + HEALING ENVIRONMENT

COMFORT ROOM For standard to premier room type with safety and comfort design

ACTIVE ACTIVITY TO REDUCE THE ATMOSPHERE OF A HOSPITAL.

SEPARATE PART ELDERLY / GENERAL


0 CASE STUDY

DESIGN GUIDELINE LAYOUT

CURVE FORM TO REDUCE STRENGTH OF VOID PATTERN

DESIGN STRUCTURE

SPLIT BY LEVEL CREATE VOLUMETRIC OF MASS

OPEN COURT

OBLIQUE COLUMN VIA 57 West

TO COMBINE NATURE INTO BUILDINGS

SUSTAINABLE + ICONIC FORM

EXPANDS BOTH HORIZONTALLY/VERTICALLY

Hospital Manta / PMMT

SIMPLE COMPACT MASS

INTERPOLATE CONTEXT NATURAL LIGHT NATURAL HEALING

PREFABRICATION VOID PATTERN


0 CASE STUDY

COMPETITORS Malaysia

Singapore

Chiangmai


0 CASE STUDY

PROGRAMING

SUCCESSFUL THAILAND HOSPITAL

REF#Statista

REF#Ontoplist.co


0 CASE STUDY

PROGRAMING

SUCCESSFUL ELDERLY MEDICAL CENTER IN THAILAND BANGKHUNTIAN Geriatric Hospital , Bangkok

RATCHAPHRUEK Hospital , Khonkaen

TYPE

TYPE

SIZE

SIZE

BUDGETS

BUDGETS -


0 CASE STUDY

PROGRAMING FUNCTION PLANNING STUDY

RATCHAPHRUEK Hospital Khonkaen

LAYOUT PLAN

2nd FLOOR PLAN

3rd FLOOR PLAN

4th FLOOR PLAN

SECTION

SECTION


0 CASE STUDY

PROGRAMING FUNCTION PLANNING STUDY

RATCHAPHRUEK Hospital Khonkaen

RELATIONSHIP


0 CASE STUDY

PROGRAMING

JIN WELLBEING


0 CASE STUDY

LAYOUT

MASS LAYOUT AND DAYLIGHTING ทาให้เกิดพื้นที่ใช้งานที่เปิดโล่งใต้อาคาร รวมไปถึงการนาแสงธรรมชาติสอดแทรก เข้ามาภายในอาคาร

MASS LAYOUT AND SPLIT LEVEL PLANNING ทาให้เกิดพื้นทีo ่ pen space ระหว่างแมสที่ ปิดล้อมซึ่งสามารถนามาช่วยแก้ไขปัญหา อาคารที่มีลักษณะเป็นแนวยาว

CLUSTER + LINEAR PLAN

There is a court in each department.


0 CASE STUDY

LAYOUT

New North Zealand Hospital Denmark

There is a court in each department.

ZONING DIAGRAM

CLUSTER + LINEAR PLAN


0 CASE STUDY

DESIGN / STRUCTURAL


0 CASE STUDY

DESIGN

TOWER

Terrace apartments in Aarhus

400 CHANNELSIDE BY GENSLER

OPEN VIEWS AND SHAPING COURT APARTMENT : 26500 m2 HEIGHT: 70 meter

SPLIT / CANTILIVER OFFICE : RETAIL : HEIGHT:

40365 m2 9861 m2 92 meter


PROCESS MASS ALTERNATIVE PRELIMINARY DESIGN MASS DEVELOP AND PROCESS HOW CONCEPT WORK

DESIGN


05 PROCESS DESIGN

ELDERLY MEDICAL CENTER

TARGET

USER TARGET


05 PROCESS DESIGN

CONCEPTUAL FUNCTION


05 PROCESS DESIGN

CONCEPTUAL CRITERIA

YOUNG AT

HEART DIFFERENT BUT NOT DIVIDE

ZONING

LIVELY

SOFT NATURAL GEOMETRY

FORM SMOOTHLY CONNECT

COMFORTLY FLOW

HEART OF PROJECT

SPACE

GROW

ACTIVE PARK

ENERGETIC

PASSIVE PARK

REHABILITATION AREA

CIRCULATION


05 PROCESS DESIGN

ACTIVE PARK


05 PROCESS DESIGN


05 PROCESS DESIGN

SCHEMATIC DIAGRAM-CONCEPT 1

2

3


05 PROCESS DESIGN

MASS DEVELOPMENT


05 PROCESS DESIGN

MASS DEVELOPMENT

MASS 01

ACTIVE COURT

MORE PRIVACY!!!

SAME SPHERE


05 PROCESS DESIGN

ALTERNATIVE MASS

MASS

01

MASS SUMARY 01


05 PROCESS DESIGN

MASS DEVELOPMENT

MASS 02


05 PROCESS DESIGN

ALTERNATIVE MASS

MASS

02

MASS SUMARY 02


05 PROCESS DESIGN

ALTERNATIVE MASS

MASS 03

REHABITATION

CONNECTING COURT

LONG DROP-OFF CANOPY


05 PROCESS DESIGN

ALTERNATIVE MASS

MASS

03

MASS SUMARY 03


05 PROCESS DESIGN

ALTERNATIVE TOWER

TOWER ANALYSIS


05 PROCESS DESIGN

MASS DEVELOP

MASS SUMARY


05 PROCESS DESIGN

MASS SUMMARY


05 PROCESS DESIGN

MASS SUMMARY


05 PROCESS DESIGN

MASS SUMMARY


ARCHITECTURAL DESIGN SECTION ZONNING DIAGRAM PLAN

ELEVATION SECTION PERSPECTIVE


06 ARCHITECTURE DESIGN

ICU

DELIVERY

ER+RECREATION


06 ARCHITECTURE DESIGN

ICU

DELIVERY

ER+RECREATION


06 ARCHITECTURE DESIGN

ICU

DELIVERY

ER+RECREATION


06 ARCHITECTURE DESIGN

ICU

DELIVERY

ER+RECREATION


06 ARCHITECTURE DESIGN

ICU

DELIVERY

ER+RECREATION


06 ARCHITECTURE DESIGN

ICU

DELIVERY

ER+RECREATION


06 ARCHITECTURE DESIGN

ICU

DELIVERY

ER+RECREATION


06 ARCHITECTURE DESIGN

Core


06 ARCHITECTURE DESIGN

Core


06 ARCHITECTURE DESIGN

FL 01


06 ARCHITECTURE DESIGN

FL 01


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN

FL 01


06 ARCHITECTURE DESIGN

FL 01



06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN

FL 01


06 ARCHITECTURE DESIGN

FL 01


06 ARCHITECTURE DESIGN

FL 02


06 ARCHITECTURE DESIGN

FL 02


05 ARCHITECTURE DESIGN

FL 02


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN

FL 02


06 ARCHITECTURE DESIGN

FL 02


06 ARCHITECTURE DESIGN

FL 03


06 ARCHITECTURE DESIGN

FL 03


06 ARCHITECTURE DESIGN

FL 03


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN

FL 03


06 ARCHITECTURE DESIGN

FL 03


06 ARCHITECTURE DESIGN

FL 04


06 ARCHITECTURE DESIGN

FL 04


06 ARCHITECTURE DESIGN

FL 04


06 ARCHITECTURE DESIGN

FL 04


06 ARCHITECTURE DESIGN

FL 05


06 ARCHITECTURE DESIGN

FL 05


06 ARCHITECTURE DESIGN

FL 05


06 ARCHITECTURE DESIGN

FL 06


06 ARCHITECTURE DESIGN

FL 06


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN

FL 06


06 ARCHITECTURE DESIGN

FL 08


06 ARCHITECTURE DESIGN

FL 09


06 ARCHITECTURE DESIGN

FL 10 17


06 ARCHITECTURE DESIGN

FL 18


06 ARCHITECTURE DESIGN

FL 19 25


06 ARCHITECTURE DESIGN

FL 26


06 ARCHITECTURE DESIGN

Standard Ward

Luxury Ward

Standard Long Term

Luxury Long Term

30.24 sq.m.

60.48 sq.m.

43.20 sq.m.

64.80 sq.m.


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN


06 ARCHITECTURE DESIGN



161

06 ARCHITECTURE DESIGN



163

06 ARCHITECTURE DESIGN


CONSTRUCTION BUILDING


07 CONSTRUCTION BUILDING


07 CONSTRUCTION BUILDING


07 CONSTRUCTION BUILDING

CONSTRUCTION TECHNOLOGY CONSIDERED MODULAR CO ORDINATION

STRUCTURAL DESIGN

STRUCTURAL SYSTEM

STRUCTURE FOR SUPPORT SEISMIC

WIDE SPAN SEMINAR

RIGID FRAME

CHIANGMAI

BOX TRUSS CANTILIVER EAVES

BASIC MODULE

SPAN

0.60 m

7.20 m 8.40 m 12.00 m

BASIC MODULE

FL to Ceiling

CANTILIVER DROPOFF

LIFT UP TOWER

COMBINE COLUMN

REQUIRE BY FUNCTION / CHARACTER

GUIDE LINE STRUCTURE SYSTEM WITH TOUGH ANTI-FLEX FRAME WITH SHEAR WALL WITH SPECIAL DETAILING.


07 CONSTRUCTION BUILDING

PRIMARY

STRUCTURE

DETAIL - DIMENSION ISOLATED FOOTING

MAT FOUNDATION

FOUNDATION


07 CONSTRUCTION BUILDING

STRUCTURAL SYSTEM

DETAIL DIMENSION

PODIUM

FLOOR – WALL SYSTEM


07 CONSTRUCTION BUILDING

STRUCTURAL SYSTEM

DETAIL DIMENSION

PARKING

FLOOR – WALL SYSTEM


07 CONSTRUCTION BUILDING

STRUCTURAL SYSTEM

DETAIL DIMENSION

V COLUMN

STRUCTURAL CONCEPT


07 CONSTRUCTION BUILDING

STRUCTURAL SYSTEM

DETAIL DIMENSION

OBLIGUE COLUMN

STRUCTURAL CONCEPT


07 CONSTRUCTION BUILDING

STRUCTURAL SYSTEM

BOXTRUSS

STRUCTURAL CONCEPT

DETAIL DIMENSION

0.80 m


07 CONSTRUCTION BUILDING

STRUCTURAL SYSTEM

GREEN ROOF

STRUCTURAL CONCEPT

DETAIL DIMENSION

0.80 m


07 CONSTRUCTION BUILDING

STRUCTURAL SYSTEM

FACADE

STRUCTURAL CONCEPT

DETAIL DIMENSION

0.80 m


OVERALL SYSTEM POSTION BUILDING AUTOMATION SYSTEM SANITARY SYSTEM ELECTRIC SYSTEM HVAC SYSTEM VERTICAL CIRCULATION SYSTEM FIRE PROTECTION SYSTEM SECURITY SYSTEM

MECHANICAL SYSTEM

MEDICAL GAS SYSTEM

GARBAGE DISPOSAL SEMINAR SYSTEM WIRELESS INTERNET & LOCAL AREA NETWORK LIGHTING PROTECTION SOLAR CELL SYSTEM ROOF GARDEN SYSTEM MAINTENANCE PROTECTION


00 OVERALL SYSTEM


08 MECHANICAL SYSTEM

OVERALL SYSTEM

OVERALL SYSTEM

Garbage Disposal

FIRE PUMP

Electrical System

Medical Gas System

Sanitary System

SANITARY SYSTEM

SANITARY SYSTEM (Underground) ELECTRIC SYSTEM HVAC SYSTEM VERTICAL CIRCULATION SYSTEM FIRE PROTECTION SYSTEM LIGHTIENING PROTECTION SYSTEM SECURITY SYSTEM WIRELESS INTERNET & LOCAL AREA NETWORK MEDICAL GAS SYSTEM GARBAGE DISPOSAL MAINTENANCE PROTECTION

HVAC

Vacuum

Security

Oxygen

SPECIFICATION

Sanitary System (Underground)

POSITION LAYOUT


08 MECHANICAL SYSTEM

BUILDING AUTOMATION SYSTEM


01 SANITARY SYSTEM


08 MECHANICAL SYSTEM

SANITARY SYSTEM

WATER SUPPLY

SYSTEM

RAIN WATER MANAGEMENT SYSTEM

WASTEWATER TREATMENT SYSTEM

FIRE WATER SYSTEM

SANITARY SYSTEM


08 MECHANICAL SYSTEM

SANITARY SYSTEM

SANITARY SYSTEM LAYOUT

C

B

F บ่อตรวจ สอบคุณ ภาพน้า

A A

D

B E

C LAYOUT EXTENSION C

B

A


08 MECHANICAL SYSTEM

SANITARY SYSTEM

SANITARY SYSTEM LAYOUT

C

B

F บ่อตรวจ สอบคุณ ภาพน้า

D A

D

F

E D

F E

LAYOUT EXTENSION

E


08 MECHANICAL SYSTEM

SANITARY SYSTEM

WATER USE


08 MECHANICAL SYSTEM

SANITARY SYSTEM

SANITARY EQUIPMENT

SAVEWATER

70%

Water Faucet

SAVEWATER

20%

Shower

SAVEWATER

30%

Flush Tank


08 MECHANICAL SYSTEM

SANITARY SYSTEM WATER SUPPLY SYSTEM

LIST A B C

Transfer Pump Roof Tank Booster Pump

Pressure Reducing Valve Cold Water Pipe ⌀1/2” Waste Water Pipe ⌀ 2” SOIL WATER Pipe ⌀ 6”

WATER SUPPLY SYSTEM LAYOUT


08 MECHANICAL SYSTEM

SANITARY SYSTEM Cold Water Pipe ⌀1/2”

WATER SUPPLY SYSTEM

Waste Water Pipe ⌀ 2” SOIL WATER Pipe ⌀ 6”

LIST A

Transfer Pump B Roof Tank C Booster Pump Pressure Reducing Valve

PARKING

SEMINAR 8%

8%

IPD 47%

BACK OF HOUSE 22%

OPD 15%


08 MECHANICAL SYSTEM

SANITARY SYSTEM

WASTEWATER TREATMENT LAYOUT

BLACK WATER

บ่อตรวจ สอบคุณ ภาพน้า

WASTEWATER TREATMENT SYSTEM

LIST RWP = Raw Water Pump A = Submersible Aerator Pump M = Mixer Pump Sludge SP = Sewage Pump SLP = Sludge Pump

EP = Effluent Pump

ออกสู่ภายนอกโครงการ


08 MECHANICAL SYSTEM

SANITARY SYSTEM WASTEWATER TREATMENT SYSTEM

LIST RWP = Raw Water Pump A = Submersible Aerator Pump M = Mixer Pump Sludge SP = Sewage Pump SLP = Sludge Pump EP = Effluent Pump SOIL WATER Pipe ⌀ 6”


08 MECHANICAL SYSTEM

SANITARY SYSTEM WASTEWATER TREATMENT SYSTEM

Cold Water Pipe ⌀1/2” Waste Water Pipe ⌀ 2” SOIL WATER Pipe ⌀ 6”

WASTEWATER TREATMENT LAYOUT


08 MECHANICAL SYSTEM

GREY WATER

SANITARY SYSTEM WASTEWATER TREATMENT SYSTEM

RO (REVERSE OSMOSIS)

MF / UF (MICRO

Cold Water Pipe ⌀1/2”

FILTRATION ULTRA FILTRATION MEMBRANE)

Waste Water Pipe ⌀ 2” SOIL WATER Pipe ⌀ 6”

MF / UF TANK

RO


08 MECHANICAL SYSTEM

SANITARY SYSTEM

RAIN WATER MANAGEMENT LAYOUT

บ่อตรวจ สอบคุณ ภาพน้า

RAIN WATER MANAGEMENT SYSTEM

น้าฝนจากถนน

Cold Water Pipe ⌀1/2” Waste Water Pipe ⌀ 2” น้าฝนจากถนน

SOIL WATER Pipe ⌀ 6”


08 MECHANICAL SYSTEM

SANITARY SYSTEM RAIN WATER MANAGEMENT SYSTEM

RO

TANK

นำ้ ชักโครก


08 MECHANICAL SYSTEM

SANITARY SYSTEM RAIN WATER MANAGEMENT SYSTEM

RAIN WATER MANAGEMENT LAYOUT

LIST

บ่อตรวจ สอบคุณ ภาพน้า


08 MECHANICAL SYSTEM

SANITARY SYSTEM RETENTION POND

𝑥=

5,590 𝑥 85 100


08 MECHANICAL SYSTEM

SANITARY SYSTEM

VACUUM PUMP VACUUM PUMP

DRY CLEW VACUUM PUMP


08 MECHANICAL SYSTEM

SANITARY SYSTEM BOILER


08 MECHANICAL SYSTEM

SANITARY SYSTEM

DETAIL PLAN

SANITARY SYSTEM

Cold Water Pipe ⌀1/2” Waste Water Pipe ⌀ 2” SOIL WATER Pipe ⌀ 6”


08 MECHANICAL SYSTEM

SANITARY SYSTEM

STANDARD WARD PLAN SANITARY SYSTEM

Cold Water Pipe ⌀1/2” Waste Water Pipe ⌀ 2” SOIL WATER Pipe ⌀ 6”


08 MECHANICAL SYSTEM

SANITARY SYSTEM

STANDARD WARD PLAN SANITARY SYSTEM

Cold Water Pipe ⌀1/2” Waste Water Pipe ⌀ 2” SOIL WATER Pipe ⌀ 6”


08 MECHANICAL SYSTEM

02 ELECTRIC SYSTEM


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM ELECTRICAL SYSTEM

EMERGENCY ELECTRICAL SYSTEM

LIGHTING SYSTEM


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

ACCESSIBILITY OF ELECTRIC SYSTEM


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM 1,054 kVA

ZONING

OF ELECTRIC SYSTEM

1,218 kVA 1,003 kVA การใช้งาน 24 ชม.

1,054 kVA 1,037 kVA 1,064 kVA

1,434 kVA

การใช้งาน 8.00-20.00 น. 13 ชม.


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

ELECTRIC SYSTEM LAYOUT

LIST

INCOMING PEA 3 PHASE (24 kVA) INCOMING PEA 3 PHASE (24 kVA)


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

TRANSFORMER

VIP WARD 1

MDB-1

1054 kVA

ZONING

LOAD (kVA)

3 - Phase Transformer

Transformer

VIP WARD 1

1,054

1,500 kVA

1

1,218 kVA

VIP WARD 2

1,218

1,500 kVA

1

STANDARD WARD

STANDARD WARD

1,003

1,500 kVA

1

MDB-3

LONG TERM WARD

1,233

1,500 kVA

1

917

1,500 kVA

1

24/7

1,287

1,500 kVA

1

OPD REHAB

1,428

1,500 kVA

1

สารอง 1

1,500 kVA

1

สารอง 2

1,500 kVA

1

VIP WARD 2

MDB-2

1,003 kVA LONG TERM WARD

MDB-4

1,233 kVA RETAIL, CSSD, DOCTOR LOUNG

MDB-5

917 kVA 24/7

MDB-6

1, 287 kVA OPD REHAB

MDB-7

1,428 kVA

TOTAL LOAD

10,493 kVA (8,395 Watt)

RETAIL, CSSD, DOCTOR LOUNG

TOTAL

9


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM EQUIPMENT

ELECTRIC SYSTEM

MDB

TRANSFORMER

EMDB GENERATOR

UPS

LOAD ESTIMATE CALCULATION

LIST

TOTAL LOAD 10,493 kVA DB-5 (From MDB-5)

DB-3 (From MDB-3)

LP (From DB-5)

LP (From DB-3)

DB-1 (From MDB-1)

DB-2 (From MDB-2)

LP (From DB-1)

LP (From DB-2)


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

RING MAN UNIT (RMU) GENERATOR TRANSFORMER OIL TYPE UPS EMDB

Emergency Main Distribution Board

ATS

Automatic Transfer System

MDB

Main Distribution Board

LOAD PANEL DB (Distribution Board)

LOAD PANEL DB (Distribution Board) LOAD PANEL DB (Distribution Board) LOAD PANEL DB (Distribution Board) LIFT


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM MDB-1

MDB-2

MDB-3

1,054 kVA

1,218 kVA

1,003 kVA

LOAD ESTIMATE CALCULATION

F23 – 25 – VIP WARD

ZONING F7 – OFFICE F8 – DOCTOR DORM , NURSE DORM F9 – F17 – STANDARD WARD

F18 F19 – 22 – VIP WARD

θ)


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM LOAD ESTIMATE CALCULATION MDB-4

1,218 kVA

ZONING

F1 – F2 – F3 F4 -

RETAIL LONG - TERM LONG - TERM LONG - TERM

θ)


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

LOAD ESTIMATE CALCULATION

MDB-5

917 kVA

ZONING

F1 – F2 – F3 F4 -

RETAIL RETAIL DOCTOR LOURGE, LIBRARY CSSD , LAUNDRY

θ)


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

LOAD ESTIMATE CALCULATION

MDB-6

1,287 kVA

θ)

F1 – F5 F6 -

ER, Medical Record, Pharmacy, Radiology Department DELIVERY ICU


LOAD ESTIMATE CALCULATION

ELECTRIC SYSTEM MDB-7

1,428 kVA

F2 – F3 – F4 –

OPD OPD OPD


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

LOAD ESTIMATE CALCULATION

MDB-7

1,428 kVA

F2 – F3 – F4 –

REHABILITATION REHABILITATION REHABILITATION


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM LOAD ESTIMATE CALCULATION MDB-7

1,428 kVA

F1 – OUTDOOR LIGHTING F2 – PARKING F3 – PARKING F4 – SEMINAR


08 MECHANICAL SYSTEM

EMERGENCY AND STANDBY POWER

ELECTRIC SYSTEM

SYSTEMS

EMERGENCY SYSTEM EMDB

แผนกที่ต้องการการสารองไฟฉุกเฉิน (ใช้ UPS)

UPS

ATS

GENERATOR

Automatic Transfer Switch

EMERGENCY AND STANDBY POWER EQUIPMENT

Normal Loads Normal Source

UPS

FIRE PROTECTION

UPS

Emergency Source

UPS

Standalone Smoke Detector

G UPS

ATS

Emergency Loads

Battery life : Approximately 10 year(*)

FIRE MAN LIFT SERVER ROOM FIRE ALARM

Heat Detector Notifier Stand Alone Battery life : Approximately 10 year(*)

FIRE PUMP CCTV ELECTRIC SYESTEM

F1 F2 F3 F4 F5 F6 F7 F8 F9 -22 F23 - 25

= = = = = = = = = =

265 186 196 96 54 137 22 22 157 134

ตัว ตัว ตัว ตัว ตัว ตัว ตัว ตัว ตัว ตัว

PARKING - F2 = PARKING - F3 = PARKING - F4 =

95 ตัว 75 ตัว 57 ตัว


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

TOTAL LOAD

1,854 kVA

EMERGENCY SYSTEMS 24/7 ZONE

24/7 ICU , OR 24/7 DELIVERY

θ)

ER , RADIOLOGY 24/7

EMDB – 1 24/7 ZONE 1,207 kVA

เผื่อโหลด 10% =

1,327 kVA

UPS - 1

1500 kVA Back Up Time

3 Hours


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

TOTAL LOAD

EMERGENCY EMERGENCYSYSTEMS SYSTEMS

516 kVA

HEMODIALYSIS ENDOSCOPY θ)

FIRE MAN LIFT

LAB SURGERY DEPARTMENT

EMDB - 2 ELECTRIC SYSETEM FIRE PROTECTION SYSTEM

24/7 ZONE 515.74 kVA เผื่อโหลด 10% =

567 kVA

UPS - 2

1000 kVA Back Up Time

3 Hours


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM EMERGENCY AND STANDBY POWER SYSTEMS

TOTAL LOAD WARD

LOAD 1,400 kVA ไฟฟ้าสว่าง ไฟฟ้ากาลัง

LIFT

ELECTRIC SYSETEM FIRE PROTECTION SYSTEM

OPD AND REHAB

24/7 ICU , OR

WARD

ER , RADIOLOGY 24/7

LONG TERM WARD

24/7 DELIVERY

OPD AND REHAB

LONG TERM WARD

LOAD 7,100 kVA ระบบปรับอากาศ

ELECTRIC SYSETEM FIRE PROTECTION SYSTEM

OPD AND REHAB

24/7 ICU , OR

WARD

ER , RADIOLOGY 24/7

LONG TERM WARD

24/7 DELIVERY

24/7

ELECTRIC SYSTEM


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM STANDBY POWER SYSTEMS

TOTAL LOAD

LOAD 1,400 kVA

การจัดลาดับความสาคัญการจ่ายโหลด ของระบบไฟฟ้าสารอง

WARD

LIFT

24/7

OPD AND REHAB

TOTAL LOAD

LOAD 7,100 kVA ระบบปรับอากาศ

LONG TERM WARD

GENERATOR 3000 kVA

ELECTRIC SYSTEM


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM LIGHTING SYSTEM


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM LIGHTING SYSTEM

𝐹 𝐴

𝐹𝑥𝑛 𝑥𝑀 𝐴

𝐸𝑥𝐴 𝐹𝑥𝑀

θ)


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM OPD


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

1 FLOOR PLAN

LIGHTING SYSTEM LAYOUT

EE LP DB

REHABIRITATION HALL


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

1 FLOOR PLAN


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

1 FLOOR PLAN

LIGHTING SYSTEM LAYOUT

OUT PATIENT DEPARTMENT HALL

LP

DB

EE A

A


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

1 FLOOR PLAN

A

A


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

1 FLOOR PLAN

LIGHTING SYSTEM LAYOUT

EMERGENCY ROOM A A

A


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

1 FLOOR PLAN


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

6 FLOOR PLAN

LIGHTING SYSTEM LAYOUT

SEMINAR

DB LP


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

6 FLOOR PLAN


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

9-17 FLOOR PLAN 19-25 FLOOR PLAN

LIGHTING SYSTEM

VIP

LAYOUT

STANDARD

INPATIENT WARD EE

s

LP

STANDARD WARD

SYSTEM ,PARKING, SEMINAR ZONE

EE LP

VIP WARD


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM

9-17 FLOOR PLAN 19-25 FLOOR PLAN VIP

STANDARD

STANDARD WARD

VIP WARD


08 MECHANICAL SYSTEM

ELECTRIC SYSTEM LANDSCAPE LIGHTING Active Court

L1 In-ground Up light

L2

Bollard Light

L3 Bollard Light

L4

ระยะห่างระหว่างตัวโคมไฟไม่เกิน 4-6 เมตร

LIGHTING CONTROL TIMER CONTROL

Auto System PHOTO SENSOR CONTROL

Light Column


03 SOLAR CELL SYSTEM


08 MECHANICAL SYSTEM

SOLAR CELL SYSTEM


08 MECHANICAL SYSTEM

SOLAR CELL SYSTEM


04 HVAC SYSTEM


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM Ward VIP / Long Term : VRV System

Podium + ward standard : Central Air System

Isolate : Split Type


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM

7

LIST

VRF SYSTEM

6

CENTRAL AIR SYSTEM

3 1

4

2 5


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM Central Controller

Indoor Unit 1 Indoor Unit 2

VRV SYSTEM Indoor Unit 3

Controller

Indoor Unit 3

Controller

Controller

Controller

Condensing Unit Branch Controller

Branch Controller

Condensing Unit

Indoor Unit

CONDENSING UNIT

Long Term

COOLING CAPACITY 39,560 – 60,700 BTU/hr.

8

Tower

INDOOR UNIT


08 MECHANICAL SYSTEM

WARD VIP

VRV SYSTEM

LONG TERM

AIR CONDITIONING SYSTEM


08 MECHANICAL SYSTEM

SYSTEM

CENTRAL AIR SYSTEM Cooling Tower Heat Pump

Condenser

Compressor

Expansion Valve

Evaporator

Chiller

AHU

AHU

Fan Coil Unit

Fan Coil Unit

Fan Coil Unit

Fan Coil Unit


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM AHU

CENTRAL AIR SYSTEM AHU

AHU COOLING TOWER

AHU

AHU

AHU

AHU

AHU

WATER CHILLER


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM WATER CHILLER Podium Tower

5 เครื่อง

COOLING TOWER

COOLING TOWER 5 เครื่อง

OZONE SYSTEM

WATER CHILLER


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM SUPPLY AIR GRILLE

COOLING TOWER

Jet Nozzle Diffuser

Ceiling Diffuser

Ceiling Diffuser

WATER CHILLER


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM

CENTRAL

AIR SYSTEM

LIST


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM

CENTRAL

AIR SYSTEM

LIST


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM LIST


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM

1

4

Ward : Split Type • • 4

• • • •

Negative Pressure

1

2 3

Negative Pressure Room

3 1 4 2

Positive Pressure


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM HEAT PUMP

Ozone Cooling Tower

Hot Water Tank

Heat Pump

นอกจากนี้ ยังใช้ Heat Pump ในเรื่องการ ควบคุมความชื้นของอากาศในห้องต่างๆ เช่น ห้องผ่าตัด ห้อง ICU

SURGERY 30-60% RH

OPD

<60% RH

Chiller

Isolate room 60% RH

ER

<60% RH

ICU

30-60% RH


08 MECHANICAL SYSTEM

AIR CONDITIONING SYSTEM PRE-COOLED UNIT FRESH AIR

PRESSURE CONTROL + POSITIVE PRESSURE > + 2.5 Pa

ICU

Surgery

ISOLATE room < -2.5 pa

ER < -2.5 pa

Morgue < -2.5 pa

Lab > - 2.5 pa

NEGATIVE PRESSURE

เป็ น การดู ด อากาศกลั บ และเติ ม อากาศเข้าเพื่อ ควบคุมความดันของห้อ ง ต่ า งๆ โดยมี จ ุ ด ประสงค์ เ พื ่ อ ป้ อ งกั น การ กระจายเชื้อทางอากาศ

Endoscopic < -2.5 pa


05 VENTILATION

SYSTEM


08 MECHANICAL SYSTEM

VENTILATION SYSTEM

ISOLATE ROOM แรงดัน การถ่ายเทอากาศ เติมอากาศ

< -2.5 Pa. > 12 ACH > 2 ACH

ICU WARD แรงดัน การถ่ายเทอากาศ เติมอากาศ

CENTRIFUGAL SYSTEM

> +2.5 Pa. > 6 ACH > 2 ACH

OR ROOM แรงดัน การถ่ายเทอากาศ เติมอากาศ

> +2.5 Pa. > 25 ACH > 5 ACH

แรงดัน การถ่ายเทอากาศ เติมอากาศ

> 6 ACH > 2 ACH

แรงดัน การถ่ายเทอากาศ เติมอากาศ

< -2.5 Pa. > 12 ACH > 2 ACH


08 MECHANICAL SYSTEM

VENTILATION SYSTEM

ISOLATE ROOM

FRESH AIR

DUCT SILENCER


08 MECHANICAL SYSTEM

VENTILATION SYSTEM ICU WARD

FILLER AHU

FRESH AIR


08 MECHANICAL SYSTEM

VENTILATION SYSTEM OR ROOM

DUCT SILENCER

AHU FILTER

FRESH ARE


08 MECHANICAL SYSTEM

VENTILATION SYSTEM

OPD


08 MECHANICAL SYSTEM

VENTILATION SYSTEM ER ROOM /

AHU

FRESH AIR


08 MECHANICAL SYSTEM

VENTILATION SYSTEM HEPA (High Efficiency Particulate Air Filter (H13))

OPD

ER

REHAB

LAB

Medical Record

Pharmacy

ICU

OR

WARD

Delivery

CSSD


08 MECHANICAL SYSTEM

HEPA

VENTILATION SYSTEM


08 MECHANICAL SYSTEM

VENTILATION SYSTEM JET FAN SYSTEM Fresh Air Supply

Jet Fans Main Fans Motorized Dampers Sensors Fan Control Unit

Jet Fan

Jet Fan

Exhaust Air


08 MECHANICAL SYSTEM

VENTILATION SYSTEM Cross Flow Fan Double Input

Fresh Air Intake

Intake Fan (for air input) Exhaust Fan (for air discharge)

Exhaust Fan

Outdoor to Indoor Air Flow Indoor Air Flow Indoor to Outdoor Air Flow

Cross Flow Fan


06 VERTICAL CIRCULATION

SYSTEM


08 MECHANICAL SYSTEM

VERTICAL CIRCULATION SYSTEM ELEVATOR 1 1.90 ม.

2

IPD CORE 2.90 ม. 2.90 ม.

1.90 ม.

C A A A

OPD OR ICU CORE

3 Long-term CORE

Rehab CORE

4

C D

C

B B

Seminar

2.90 ม. 1.90 ม.

C

5

C

2.90 ม.

1.90 ม.

B B

D A

1.90 ม.

A A

A

Basic Specification

5

1

2

3 4


08 MECHANICAL SYSTEM

VERTICAL CIRCULATION SYSTEM ELEVATOR

1 1.90 ม.

A A A

2 OPD OR ICU

IPD CORE

CORE

2.90 ม.

C C C

2.90 ม.

1.90 ม.

2.90 ม.

C D

B B

C

3 Long-term 4 Rehab CORE CORE

2.90 ม. 1.90 ม.

B B

1.90 ม.

D A A

5 Seminar 1.90 ม.

A A

Basic Specification


08 MECHANICAL SYSTEM

VERTICAL CIRCULATION SYSTEM ESCALATOR

3rd Floor Rehabilitation Zone

1

1

2nd Floor Rehabilitation Zone

3

2 2nd Floor OPD Zone

1st Floor OPD Zone

ESCALATOR POSITION ISOMATRIC FLOOR PLAN

2


08 MECHANICAL SYSTEM

VERTICAL CIRCULATION SYSTEM ESCALATOR 1

2, 3

2-3rd Floor Rehab Zone

1-2nd Floor OPD Zone

1

3

1 ข้อมูลทั่วไป

2-3rd Floor Rehab Zone

2 ข้อมูลทั่วไป

1-2nd Floor OPD Zone

Speed (m/s)

0.5 m/s

Speed (m/s)

0.5 m/s

Angle of Inclination

30.00

Angle of Inclination

30.00

Step width

1.00 m.

Step width

1.00 m.

Flat step length

0.80 m.

Flat step length

0.80 m.

Basic Specification

2


08 MECHANICAL SYSTEM

VERTICAL CIRCULATION SYSTEM

1

SERVICE ELEVATOR 1

IPD CORE

E

E

F F

2

Basic Specification Service Lift

Long-term CORE D

D

Seminar

E

Dirty lift

E

Clean lift

Dumbwaiter Lift

E

F

Dirty lift

E

F

Clean lift

2


08 MECHANICAL SYSTEM

VERTICAL CIRCULATION SYSTEM

1

SERVICE ELEVATOR 1

E

IPD CORE

E

F F

2

Basic Specification Service Lift

Long-term CORE D

Seminar D

E

E

5

E E

D

2 E

E

1

D

E

Dirty lift

E

Clean lift

Dumbwaiter Lift F

Dirty lift

F

Clean lift

2


07 FIRE PROTECTION

SYSTEM


08 MECHANICAL SYSTEM

OVERALL FIRE PROTECTION SYSTEM Heat Detector

SITE

Fire Department Connection


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

FIRE PROTECTION PROCESS

Fire escape


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE ALARM SYSTEM

FIRE PROTECTION EQUIPMENT


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

LIST


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

FIRE ALARM SYSTEM LAYOUT

Smoke Detector

Heat Detector

LIST Heat Detector Smoke Detector Manual Call Point (A) Fire Alarm Control Panel

1st Floor


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

FIRE ALARM SYSTEM LAYOUT

Smoke Detector

Heat Detector

LIST Heat Detector Smoke Detector Manual Call Point (A) Fire Alarm Control Panel

2nd Floor


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

FIRE ALARM SYSTEM LAYOUT

Smoke Detector

Standard Ward

Heat Detector

10-17th Floor

LIST Heat Detector Smoke Detector Manual Call Point (A) Fire Alarm Control Panel

VIP Ward

19-22th Floor


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM SPRINKLER SYSTEM

SPRINKLER

(Up-right)

Pendent)

(Side-wall)


08 MECHANICAL SYSTEM

STANDPIPE AND FIRE HOSE CABINET SYSTEM

FIRE PROTECTION SYSTEM

NFPA 14 Standard for the Installation of Standpipe and Hose Systems

Sprinkler

Fire Water Tank

Fuel Tank

Generator

Stand Pipe & FHC

Sprinkler

Fire Pump Sprinkler

Fire Truck

Fire Department Connection

Fire Department Connection


FIRE PROTECTION SYSTEM

FIRE PROTECTION LAYOUT

LIST Standpipe 500 GPM

Standpipe 250 GPM

FHC

FIRE PUMP

Fire Department Connection

FIRE TANK

LIST


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

LIST Sprinkler Fire Fire Hose Cabinet Fire Department Connection Isolate Valve Fire Pump

Fire Tank


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

FIRE ALARM SYSTEM LAYOUT

SYSTEM DIAGRAM Fire Water Tank

Fuel Tank

Sprinkler

Stand Pipe & FHC Sprinkler

Generator

Fire Pump

Fire Truck

Fire Department Connection

Sprinkler

FIRE PROTECTION EQUIPMENT Fire Sprinkler

FHC (Fire Hose Cabinet) And Standpipe

1 st F L O O R P L A N


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

FIRE ALARM SYSTEM LAYOUT

SYSTEM DIAGRAM Fire Water Tank

Fuel Tank

Sprinkler

Stand Pipe & FHC Sprinkler

Generator

Fire Pump

Fire Truck

Fire Department Connection

Sprinkler

FIRE PROTECTION EQUIPMENT Fire Sprinkler

FHC (Fire Hose Cabinet) And Standpipe

2 th F L O O R P L A N


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE ALARM SYSTEM

SYSTEM DIAGRAM Fire Water Tank

LAYOUT

Stand pipe

Fuel Tank Generator

Fire Pump

Fire Truck

Fire Department Connection

FIRE PROTECTION EQUIPMENT 1 0 - 1 7 TH F L O O R P L A N

FHC

Sprinkler


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE ALARM SYSTEM

SYSTEM DIAGRAM Fire Water Tank

LAYOUT

Stand pipe

Fuel Tank Generator

Fire Pump

Fire Truck

Fire Department Connection

FIRE PROTECTION EQUIPMENT 1 9 - 2 2 ND F L O O R P L A N

FHC

Sprinkler


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM Portable Fire Extinguisher A (Foam)

B

C

(Water Pressure)

Carbon dioxide)

(Dry Chemical Powder)


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE ESCAPE CIRCULATION


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE ESCAPE CIRCULATION


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

FIRE ESCAPE SYSTEM LAYOUT

FIRE PROTECTION EQUIPMENT FIRE EXIT

ASSEMBLY POINT

FIRE ALARM

FIRE EXTINGUISHER FIRE ESCAPE POSITION 1 st F L O O R P L A N


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE ESCAPE SYSTEM LAYOUT

FIRE PROTECTION EQUIPMENT


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM

Fire-Resisting Damper

Smoke Damper

Smoke Exhaust Fan

Pressurized Fan


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE COMPARTMENT Passive Fire Protection


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE COMPARTMENT 1st Floor

FIRE COMPARTMENT 2nd Floor


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE COMPARTMENT 3rd Floor

FIRE COMPARTMENT 4th Floor


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE COMPARTMENT 5th Floor

FIRE COMPARTMENT 6th Floor


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE COMPARTMENT 8th Floor

FIRE COMPARTMENT 9th Floor


08 MECHANICAL SYSTEM

FIRE PROTECTION SYSTEM FIRE COMPARTMENT 10-17th Floor

Standard Ward

FIRE COMPARTMENT 19-22th Floor

VIP Ward


08 SECURITY SYSTEM


08 MECHANICAL SYSTEM

BARRIER GATE

Standard Camera

Infrared Camera

Dome Camera

Speed Dome Camera

FACESCAN

• •

• •

• • •

CCTV SYSTEM

GUARD

CCTV EQUIPMENT

CCTV & SECURITY SYSEM

SECURITY SYSTEM

IP Camera • •


08 MECHANICAL SYSTEM

SECURITY SYSTEM CCTV POSITION 1st FLOOR


08 MECHANICAL SYSTEM

SECURITY SYSTEM CCTV POSITION 2nd FLOOR


08 MECHANICAL SYSTEM

SECURITY SYSTEM CCTV POSITION 3rd FLOOR


08 MECHANICAL SYSTEM

SECURITY SYSTEM CCTV POSITION WARD FLOOR

F9-F17 – STANDARD WARD

F19-F25 – VIP WARD


09 MEDICAL GAS SYSTEM


08 MECHANICAL SYSTEM

MEDICAL GAS SYSTEM


08 MECHANICAL SYSTEM

MEDICAL GAS SYSTEM


08 MECHANICAL SYSTEM

MEDICAL GAS SYSTEM


10 GARBAGE DISPOSAL


08 MECHANICAL SYSTEM

GARBAGE DISPOSAL


11 SEMINAR SYSTEM


08 MECHANICAL SYSTEM

SEMINAR SYSTEM SEMINAR ACOUSTIC & SOUND SYSTEM

NOISE CRITERIA (NC) 30-35

SOUND SYSTEM

REVERBERATION TIME (RT) 1.4-1.9 Sec

ABSORBTION WALL

ACOUSTIC SYSTEM


08 MECHANICAL SYSTEM

SEMINAR SYSTEM SEMINAR ACOUSTIC & SOUND SYSTEM

ตีฟ

SEMINAR MATERIAL FLOOR

WALL

CEILING


12 WIRELESS INTERNET & LOCAL AREA NETWORK


08 MECHANICAL SYSTEM

SOUND SYSTEM


08 MECHANICAL SYSTEM

SOUND SYSTEM


08 MECHANICAL SYSTEM

NETWORK SYSTEM PATIEN ROOM NURSE STATION

SEATING & HALL SOUND AND VISUAL

WAITING AREA OPD AND MEDICAL SYSTEM


08 MECHANICAL SYSTEM

TELEPHONE SYSTEM

IP-PBX SERVER NURSE STATION WARD SERVER

LAN

OTHERS SERVER

OPD SERVER

TELEPHONE

OPD & IPD OFFICE & ADMINSTRATION

RETAIL


08 MECHANICAL SYSTEM

TELEVISION SYSTEM

Ultra High Defination


08 MECHANICAL SYSTEM

NURSE CALL SYSTEM


08 MECHANICAL SYSTEM

NURSE CALL SYSTEM


1 LIGHTNING PROTECTTION


08 MECHANICAL SYSTEM

EXTERNAL LIGHTNING PROTECTION SYSTEM


08 MECHANICAL SYSTEM

EXTERNAL LIGHTNING PROTECTION SYSTEM


08 MECHANICAL SYSTEM

EXTERNAL LIGHTNING PROTECTION SYSTEM

Surge Protection Device : SPD


1 ROOF GARDEN SYSTEM


08 MECHANICAL SYSTEM

GREEN ROOF SYSTEM


08 MECHANICAL SYSTEM

GREEN ROOF SYSTEM


1 MAINTENANCE PROTECTION


08 MECHANICAL SYSTEM

MAINTENANCE PROTECTION SYSTEM EQUIPMENT MAINTENANCE POSITION CONSIDERED MAINTENANCE CENTER/ MEDICAL GAS / MDB – G. Fl. COOLING TOWER – Roof parking SOLARCELL – Podium A roof GREEN ROOF – Podium B roof

Width > 6.00 m / Turning radius 12.00 m

FACADE CLEANING CONSIDERED


SUSTAINABLE CONCEPT LEED SCORE OTTV EIA


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE

7/9

4/9

3/4

11/11 5/6 21/35 13/16 8/19


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE

(P) Construction Activity Pollution Prevention


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE

(17) Optimize Energy Performance


09 SUSTAINABLE CONCEPT

ENERGY SAVING Δ Δ

Δ

Δ


09 SUSTAINABLE CONCEPT

LEED

(P) Construction and Demolition Waste Management Planning

FOR HEALTHCARE

05 MATERIALS AND RESOURCES

(P) Storage and Collection of Recyclables

(2) BPDO : Environmental Product Declaration

(2) Construction and Demolition Waste Management


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE

(2) Indoor Air Quality Assesment

(2) Enhanced Indoor Air Quality Strategies • • •

(2) Quality Views

(2) Daylight (3) Low-Emitting Materials เลือกใช้ผลิตถัณฑ์ที่ได้ มาตรฐาน PCD หรือการ ควบคุมมลพิษ

คานวณแสงธรรมชาติที่มา ใช้กับอาคารผ่านโปรแกรม


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE

07 Innovation in Design

08 Regional Priority


09 SUSTAINABLE CONCEPT

LEED

FOR HEALTHCARE

GOLD 72/109


09 SUSTAINABLE CONCEPT

EIA GUIDELINE


CONSTRUCTION PROCESS CONSTRUCTION SITE LAYOUT

SECURITY IN VARIOUS PARTS

CONSTRUCTION SITE ISOMETRIC

EQUIPMENT PLANING CONSTRUCTION PROCESS


10 CONSTRUCTION PROCESS

CONSTRUCTION

MANAGEMENT


10 CONSTRUCTION PROCESS

CONSTRUCTION

MANAGEMENT FIELDWORK COMPONENTS

CONSTRUCTION SITE LAYOUT 1 2 3 4 5 6 7

55 6 6 PHASE I

3

2 2 66

PHASE II

55 4 4

11

44

33

2 2 1 1

7 7


10 CONSTRUCTION PROCESS

CONSTRUCTION

MANAGEMENT CONSTRUCTION PROCESS

B

A

INTERIOR

STRUCTURE

A

ARCHITECTURAL

C

LANDSCAPE

D

ENGINEERING SYSTEM

SITE PREPARING

SITE

PROGRAM ANALYSIS

B C

TOR REQUIREMENT

D

>36 month

CONSTRUCTION PERIOD ESTIMATED

24-26 month


10 CONSTRUCTION PROCESS

CONSTRUCTION

MANAGEMENT MONTH

CONSTRUCTION PROCESS SITE PREPARING / UNDER GROUND STRUCTURE

01

MONTH

02

-

03

MONTH

04

-

07

MONTH


10 CONSTRUCTION PROCESS

CONSTRUCTION

MANAGEMENT MONTH

CONSTRUCTION PROCESS ONGROUND STRUCTURE PODIUM A

08

MONTH

09

10

-

MONTH

11

12

MONTH

13


10 CONSTRUCTION PROCESS

CONSTRUCTION

MANAGEMENT MONTH

CONSTRUCTION PROCESS ONGROUND STRUCTURE - ARCHITECTURAL TOWER ,PODIUM B / ENGINEERING SYSTEM

14

MONTH

16

17

-

MONTH

19

20

MONTH

22


10 CONSTRUCTION PROCESS

CONSTRUCTION

MANAGEMENT MONTH

CONSTRUCTION PROCESS LAND SCAPE / COMMISSIONING TEST

23

MONTH

24

25

26

MONTH

MONTH


COST ESTIMATE FREASIBILITY

COST ESTIMATE

S – CURVE


11 COST ESTIMATE

COST ESTIMATE

BOQ

2,487,170,109.00


11 COST ESTIMATE

COST ESTIMATE


11 COST ESTIMATE

COST ESTIMATE


11 COST ESTIMATE

COST ESTIMATE


11 COST ESTIMATE

COST ESTIMATE


11 COST ESTIMATE

COST ESTIMATE


11 COST ESTIMATE

COST ESTIMATE


11 COST ESTIMATE

COST ESTIMATE


11 COST ESTIMATE

COST ESTIMATE


S - CURVE

11 COST ESTIMATE


SUMMARY


SUMMARY


REFERENCE

PROJECT REFERENCE • •

• •

• • •

• •

• •

• •

• •

• •

• • • • • •

• • • • •

• •




Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.