Residents Consultation 4 - An introduction to the proposed updates to High Land Estate What this consultation is about
This page indicates how we are delivering this consultation and provides a summary of its contents. Find out how you are able to feedback your views and suggestions. 1
2
Following the latest Government guidelines regarding the COVID-19 outbreak, we have replaced our ‘face to face’ Residents Workshop 4 with a postal - website consultation. This document provides a summary of the design development following the Ballot in December 2018 and Residents Workshop 3 (RW3) in November 2019. The document also sets out a timeline for delivering your new homes.
L D F IE M AY
We welcome your feedback on the current designs for the new Avenue, proposed buildings, new homes and landscaping. Please also send your suggestions for naming the new Avenue, Estate and building blocks. Please provide your feedback by contacting London Borough of Ealing’s Regeneration Team or emailing Rydon /LBE to provide. Please provide your personal details and confirm where you currently live on the estate.
S D EN GA R
HL
A
EN
UE
UE EN AV
HIG
AV ND
D OR NF EE GR
MAYFIELD PRIMARY SCHOOL
urt
Colne
Court
o Tyne C urt
Dee Co
urt
r Co Humbe
urt
Co Tweed
r & Stou IrwellCourt
s Court
urt
Thame
Tess Co
BRENT VALLEY PARK
To Hanwell and Drayton Green Station
Footpath to Hanwell Station
Above: aerial view of the existing High Lane Estate and surrounding area
DRAFT WIP 15.07.2020
High Lane Estate - Residents Consultation 4, 15 July 2020
Previous Residents Workshop 3 - Nov 2019 regeneration plan, phasing boundaries with update notes Main changes since the previous consultation
We continue to develop the proposals in response to our more detailed understanding of the site and feedback received at previous consultation events. The post-it notes highlight the main areas where the design has evolved from the ballot scheme and your latest feedback. High Lane Gardens suggested as a new name for the Estate. What are your thoughts?
unity comm d at d n a cate hop The s s will be lo ite near s space st of the m High e r w f e e c o es and th d ntran the e ctive faca vided A ro lane. eillance p Mayfield surv the park, ew ds he N towar ool and t as many h c s ant. intain e. Ma s is import u n e v A g tree existin
Buildings arranged as simple, rectangular forms which work with the slope of the site. This makes them simpler and quicker to build as well as providing enhanced elevations, retaining structures and drainage.
We ha v small e removed and re flat blocks h the more f placed them ere am w overlo ily sized ho ith Space oking the O uses p is bas . The new la en ed aro y und fa out Londo milia nS provid treet patte r surveil ing improv rn e lance and sa d fety
We have increased the number of gaps between buildings. This helps the estate to feel more spacious and reduces overshadowing of the main street and houses to the north.
We have increased the depth of the gardens to make them more useful and enjoyable for residents
Received positive res ponse from residents on the masterplan changes, improved light and openness between the blocks. The new sha pe of the buildings with pit ched roofs allows them to look more at home in the wider neighbourhood.
e3
Phas CENTRAL POCKET PARK/ PLAY
The existing MUGA will be re-provided on the other side of High Lane adjacent to the school. The provision of a MUGA is being investigated by LBE along with discussions with Ealing Parks and Sports England. Residents will be consulted to understand the need for a MUGA (or an alternative amenity provision).
AVENUE
E AVENU
e2
Phase 1
Phas vehicular and pedestrian route
CENTRAL POCKET PARK/ PLAY
Green lane
All flats benefit from good aspect and internal daylight levels. This is an improvement with better quality of views and daylight for all flats.
pe
s de
Comm kept ope unal gardens allowin n at both end enter theg more sunlight s, to space fo the day. r more of The new taken in designs have to the dista consideration nce betw een p areas an d homes lay .
Key
Houses
Lobby Area
Bike Store
Flats
Lift / Stairs
Plant
Shop/Community
Bin Store
High Lane Estate - Residents Consultation 4, 15 July 2020
Green
nr tria oute park er central Much larg ble for all area availa . The park to use residents irectly uildings d lots b o n s a h ng ri su n e th, to the sou reaches the t h lig of sun e day. most of th the space for d e m o lc e w Residents hing the open c a re t sunligh spaces
Lane
d share ents ti-social id s e an er Som s about enclosed rn e e h t c n s in co iour d garden We v a h r . a be d y e t s r cou ly propo making s y u b io d v pre sponde ore open . re m ut have e spaces in and o s s w e th vie clear with
We’ve been looking at ways to introduce more greenery and planting into the parking courts. The pedestrian southern route ‘Green lane’ will be overlooked, providing passive surveillance and well lit areas.
Three traffic calming raised tables introduced at entrances to parking courts and one at the site’s central pocket park /play area. Residents welcomed the inclusion of speed reduction measures on the central spine road to prevent it being used as a rat run.
The Proposed New Avenue - showing key views within the development The below proposed plan shows how the tree lined Avenue would improve permeability and connectivity to High Line Estate. This is in line with key urban design principles and the competition Planning Brief. The Level of support for the connected route from residents needs to be understood. Please do let us know?
This page shows the Avenue with good connections
NS
ARDE
LD G AYFIE
M
Mayfield
s den gar
k bac
3 s
house
back
gardens b
b shop
a
c
k
g
k
c
a
r
g
a
d
U E E N V A
r
d
e
n
Mans
s
POCKET PARK/ PLAY
houses
s
house
ion
growing
n
area
ion Mans
A V E N U E n
garde
ion
Mans
Mansion Block
parking court
Mansion Block
4
s
s house
ion
HIGH LANE
n
ion
a
houses
1
Playground
e
garden
Mansion
courtyard
Block
parking court
Mansion Block
2 POCKET PARK/ PLAY
ion
Mans
g parkin court
Mans
g parkin court
Block
garde
yard court
Block
rd urtya
Block
Block
g parkin court
gre
co
Block
Mans
en
lan
D LAN HIGHAVE
e
Block
gre
en
lan
e k bac
s den gar
green lane
back
gardens
ND RD
A STUDL
1 Artist impression of Avenue from High Lane
2 Artist impression of Pocket park/play
High Lane Estate - Residents Consultation 4, 15 July 2020
3 Photo of existing Hanway
4 Photo of existing Hanway
The current proposal for an Avenue with a ‘through route’ for vehicles GENERAL NOTES: This drawing is © 2019 Pollard Thomas Edwards LLP (PTE). Use figured dimensions only. DO NOT SCALE.
The next two pages explore the main vehicle route through the proposed development and the pros and cons of either the current proposal for a ‘through route’ or for an alternative design ‘no through route’ for vehicles between High Lane and Highland Avenue. 168
P\R ht 0.5m
Wall ht 0.7m
Wall ht 0.6m
Wall ht 0.6m
Wall ht 0.5m
172
High Lane
149
137
C\P ht 1.8m
P
Block
Block L
O
I\R ht 1m
Avenue
Block M
Block
Block L
Block
N parkin
High Lane
Block M Block
Pocket Park / Play P\R ht 0.5m
garden
Sp
Hand rail ht 1.1m
parkin
gar W ht 1.4m
Block
Block A
parkin
Block A Block B
parking court
Block B
garden courtyard
court UTR Cover Stuck
I
ard courty
g cou
Block
rtyard den cou
g cou
idated Dilap Fence
F
Block C
parking court
NOTES:
Green Pocket
rt
E Block
Block C
C\P ht 1.7m
rt
G
C\P ht 1.7m
Lane Green
Block D C\P ht 1.7m
Green Lane
C\P ht 1.7m C\P ht 1.7m
C\P ht 1.7m
C\P ht 1.7m
C\P ht 1.7m
C\P ht 1.8m
C\P ht 1.7m
72
El Sub Sta
78 Wall ht 0.9m
The proposed spine road has been designed to encourage low vehicle speeds and naturally enforce the 20mph suggested speed through the provision of:
Wall ht 1.2m
70
Stubland
Hedge ht 2.1m
D RD UDLAN
DPC 16.99
DPC 17.36
Wall ht 0.8m
Wall ht 0.5m
Wall ht 1m
ST
Wall ht 0.8m
20
Stubland
• Traffic-calming designs such as raised tables on the approach to three of the car parking courts provide natural breaks for vehicles to help prevent rat-running.
Road
Wall ht 0.5m
Stubland Road
Wall ht 0.7m
Wall ht 0.7m
103
Wall ht 0.5m
Wall ht 1m
DPC 17.91
layouts may be sub
This drawing must be read in conjunction Parking & and refuse st all6. other relevant drawings specifica from the Architect and other consultants.
7.
Substation location to be fur
8.doubt, ask. Elevations If in
Wall ht 1.1m
5
5
0
10
Metres
P\R ht 0.3m
99
Wall ht 1.1m
DPC 17.65
AOV's positions ind All5. dimensions are in millimetres unless otherwise. consultant on the fir
Wall ht 0.2m
120
132
136
Ground Levels / Le retaining structures
developed. GENERAL NOTES: This is © 2019 Pollard Thomas k 2.drawingProposed material Edwards LLP (PTE). 3.figured External PVsDO/ NOT Plan Use dimensions only. SCALE. 4. RWP positions indi
Wall ht 1.1m
87
Wall ht 0.5m
Wall ht 0.7m
DPC 16.47
Wall ht 0.4m
Wall ht 0.7m
83
Wall ht 0.7m
DPC 16.19
DPC 16.00
69
Wall ht 0.5m
148
DPC 15.07
Wall ht 0.7m
65
Lane High
152 DPC 14.95
Wall ht 0.5m
DPC 18.64 Wall ht 0.7m
102
106
166
P\R ht 1.1m
90
1.
Wall ht 0.2m
Wall ht 1m Wall ht 0.4m
Wall ht 0.5m
P\R ht 1m
65a
92
The plans need to b Rydon ER documen The apartment plan cladding to floor Le
Ps
Wall ht 0.8m
Sap
Road
Wall ht 0.6m
Wall ht 0.8m
Wall ht 0.8m P\R ht 1.1m
Wall ht 0.8m Wall ht 0.8m
Wall ht 0.6m Wall ht 0.9m
Wall ht 1m Wall ht 0.7m
Wall ht 0.7m
Wall ht 0.4m
44
46 Wall ht 0.8m
54
60
62
48a 48
63
Substation
Sp
48b 48c
50c 50b
60a
Substation
36
40
45
Green Pocket
Green Pocket
The layouts and arr further once informa strategies, Daylight requirements, MEP zone requirements.
38
42
Pocket Park / Play
The curvature of the highway at the eastern end of the estate together with the surface treatment and provision of traffic-calming design will discourage drivers from using the estate as a through-route.
D
LAN HIGHAVE UTR Cover Stuck Invert level obtained through vent holes in cover
H Block
Wall ht 1.0m
F\P ht 1.2m
g
J
24
26 28
41
Block K
Avenue
This east to west road alignment follows a similar pattern of surrounding residential roads. This helps minimise cul-de-sac arrangements, provides easy access for delivery, servicing and emergency vehicles.
C\L ht 1.2m
C\P ht 1.7m
Block K
W ht 1.4m
UTR Screws Rusted
Road Hanway
Block
Sp
Private property Sureveyed using reflectorless methods
Q
31
155 157
151 153
125
Block
117
W\P ht 1.8m
P\R ht 1m
Wall ht 1.2m
Wall ht 1m
Wall ht 1m
Wall ht 0.7m
Wall ht 0.7m
ENS
GARD
rdens ld Ga Mayfie
107
HIGH LN
Wall ht 1.2m
Wall ht 0.6m W\P ht 1.8m
Railings ht 0.5m
27
Bridge Avenue
Sap
IELD
MAYF
Sap
Wall ht 0.5m
Wall ht 1.1m
Wall ht 1.2m
Scaffolding obscured ridge
23 25
Wall ht 0.5m
D
LOCATION KEY
95
W\P ht 1.4m
M
C
No further visible pipes
108 Wall ht 0.4m
B
83
118
Wall ht 0.5m
Wall ht 2.7m
Wall ht 1.2m
79
Wall ht 1m
L
A
65
W ht 1m
The proposed development centres around a new spine road which will provide a through-route between High Lane to the west and Highland Avenue to the east with access to the five new parking courts within the development.
Wall ht 1.3m
Mayfield Gardens Wall ht 1.2m
10
y Railwa ers Sleep ht 0.7m
Option 1 - Current through route proposal
N 1
Communal Refuse Store
Private/Individual Refuse Store
Ground Floor Masterplan
Scale: 1 : 500
Refuse Vehicle Servicing Route
WORK IN
Fire servicing diagram 168
108
Sap
IELD
Sap
172
Wall ht 0.5m
Wall ht 1.2m
Wall ht 0.7m
Wall ht 0.7m
P\R ht 0.5m
Wall ht 0.7m
Wall ht 0.6m
High Lane
ENS
GARD
Wall ht 1.2m
rdens ld Ga Mayfie
project
Wall ht 1m
High Lane Estate
Wall ht 0.5m
149
137
117 P
Blo
Block K
Block L
ck O
I\R ht 1m
Avenue
Block M
Block
High Lane
Block L
Block
N parkin
Block M Block
Pocket Park / Play P\R ht 0.5m
Avenue
garden
Sp
Block
Hand rail ht 1.1m
F\P ht 1.2m
Wall ht 1.0m
parkin
garden W ht 1.4m
Block
Block A
parkin
Block A Block B
parking court
Block B
garden courtyard
Block
Block C
Block C
parking court
g cou
Block
ard courty
g cou
g cou
UTR Cover Stuck
ard courty
C\P ht 1.7m
rt
G idated Dilap Fence
F
NOTES:
Green Pocket
rt
C\P ht 1.7m
Lane Green
C\P ht 1.7m
C\P ht 1.7m
C\P ht 1.7m
C\P ht 1.7m
C\P ht 1.7m
72
El Sub Sta
78 Wall ht 0.9m
Wall ht 1.2m
70
62 Wall ht 0.4m
Stubland
Hedge ht 2.1m
148
DPC 15.07 Wall ht 0.5m
DPC 16.00 Wall ht 1.1m
Wall ht 1m
Wall ht 0.5m
DPC 16.19 Wall ht 1m
DPC 16.47
136
132 DPC 16.99
DPC 17.36
DPC 17.65 Wall ht 0.5m
DPC 17.91 Wall ht 0.8m
A STUDL
Wall ht 0.8m
20
Stubland Stubland Road
Wall ht 0.4m
Wall ht 0.7m
Wall ht 1m
1.
Wall ht 0.2m
Wall ht 1.1m
Ground Levels / Le retaining structures developed. Proposed material k External PVs / Plan RWP positions indi AOV's positions ind consultant on the fir layouts may be sub Parking & refuse st Substation location Elevations to be fur
2. 3. 4. 5.
Wall ht 0.4m
6. 7. 8.
Wall ht 0.2m
ND RD
Road
Wall ht 0.5m
Wall ht 1.1m
Wall ht 0.7m
103
Wall ht 0.7m
P\R ht 1m
Wall ht 0.7m
P\R ht 0.3m
99
Wall ht 0.7m
Road Wall ht 0.5m
Wall ht 0.7m
102
120
Sap
87
DPC 14.95 Wall ht 0.5m
Wall ht 0.5m
The plans need to b Rydon ER documen The apartment plan cladding to floor Le
Ps
Wall ht 0.8m
83
152
DPC 18.64 Wall ht 0.7m
Wall ht 0.8m
Wall ht 1m Wall ht 0.7m
Wall ht 0.7m Wall ht 0.6m
69
Lane High
106
166
90
Wall ht 0.6m Wall ht 0.9m
54
60
65
92
44
46 Wall ht 0.8m
Wall ht 0.8m
Wall ht 0.8m P\R ht 1.1m
48a 48
Wall ht 0.8m
65a
C\P ht 1.7m
48b 48c
50c 50b
60a
36
40
63
Green Lane
C\P ht 1.7m
38
42
Substation
Substation
The layouts and arr further once informa strategies, Daylight requirements, MEP zone requirements.
E
Block D
Green Pocket
C\P ht 1.8m
J
H
Green Pocket
Sp
D LAN HIGHAVE UTR Cover Stuck Invert level obtained through vent holes in cover
45
Cons
24
26 28
rt
I
Pocket Park / Play
P\R ht 1.1m
C\L ht 1.2m
C\P ht 1.7m
W ht 1.4m
• Non-residential vehicles can use this spine road. • Provides an additional vehicle route to Mayfield Primary School from Greenford Avenue. • Limits the amount of green / recreational space provided within the centre of the estate.
UTR Screws Rusted
41
155 157
151 153
125
107 Block
Block K
HL
Private property Sureveyed using reflectorless methods
Q Block
Sp
C\P ht 1.8m
drawi
drawing title
Ground Floor Masterplan
Wall ht 0.6m
S
y Railwa ers Sleep ht 0.7m
HIGH LN
MAYF
Wall ht 1m
W\P ht 1.8m
P\R ht 1m
Issued for coordination description
LOCATION KEY
Diespeker Wharf 38 Graham Street London N1 8JX 020 7336 7777 forename.surname@ptea.co.uk @ptearchitects www.pollardthomasedwards.co.uk
Railings ht 0.5m Scaffolding obscured ridge
31
Wall ht 0.5m
Wall ht 0.4m
Wall ht 0.5m
Wall ht 1.2m
27
Bridge Avenue
118
Wall ht 1.2m No further visible pipes
122
126
95
W\P ht 1.4m
Wall ht 1m
20.11.19 date
M
C D Issued for information Issued for information Issued for Information
Wall ht 0.6m W\P ht 1.8m
83
130
Wall ht 1.1m
Road Hanway
Permeable east to west route for all modes of travel. Mirrors the pattern of surrounding residential roads. Easy access for servicing, delivery vehicles and emergency vehicles. Traffic-calming design and soft landscaping to emphasize the priority for pedestrians and cyclists over vehicles and to manage vehicle speeds. • Promotes connectivity and inclusion.
98
136
Wall ht 1.2m
79
W ht 1m
• • • •
Wall ht 1.3m
Mayfield Gardens Wall ht 1.2m
rev
B
65
Pros
Sp
Wall ht 2.7m
13.03.20 04.03.20 29.11.19
drawing status
88 Wall ht 0.5m
20
I\R ht 1.8m
A
-
53
Wall ht 1m
W\P ht 2m
C B A
1m Wall ht 1m
El Sub Sta
L
Phase 1
76
23 25
• Soft landscaping and pocket parks along the spine road encourages travel on foot or by bicycle and helps drivers keep to low speeds.
K
25
• Shared surface style highway provided with appropriate surface treatment and soft landscaping to control and manage traffic flows.
53
Sp
Wall ht 1.2m
Wall ht 0.5m
122
126
20
I\R ht 1.8m
88
130
5
0
Metres
1m Wall ht 1m
98
136
5
Phase 1
76 Wall ht 1m
W\P ht 2m
If in doubt, ask.
K
Refuse servicing diagram El Sub Sta
This drawing must be read in conjunction all other relevant drawings and specifica from the Architect and other consultants.
25
Two options for the new Avenue. Which one do you prefer?
All dimensions are in millimetres unless otherwise.
N
Fire Vehicle Access Route
1
Ground Floor Masterplan
Scale: 1 : 500
WORK IN C B A
13.03.20 04.03.20 29.11.19
rev
20.11.19 date
Issued for information Issued for information Issued for Information Issued for coordination description
drawing status
High Lane Estate - Residents Consultation 4, 15 July 2020
S
Diespeker Wharf 38 Graham Street London N1 8JX 020 7336 7777 forename.surname@ptea.co.uk @ptearchitects www.pollardthomasedwards.co.uk project
High Lane Estate drawing title
Ground Floor Masterplan
drawi
HL
An alternative proposal for an Avenue with a ‘no through route’ for vehicles This page shows the alternative option 2 for the Avenue
This page explores the pros and cons of a spine road that does not allow vehicles to go through Do you have a preference between the current proposal and the alternative proposal set out over these two pages? Through route Avenue Existing tree
Option 2 - Alternative no through route proposal This option is similar to the ‘through route’ but with turning heads and retractable bollards either side of the central park to restrict the route to a ‘no through’ route for vehicles. Access to High Lane Estate would either be from High Lane or Hanway Road.
under 5s gated natural play area houses
Similar to the existing layout of the High Lane Estate, there will be no vehicle through-route from east to west across the site. However, retractable bollards will be provided on either side of the green space to allow access for emergency vehicles and scheduled refuse collections.
under 12s play area houses
community growing area
Avenue
Existing tree Avenue
shared surface
Whilst there will be no through-route for vehicles, the retractable bollards and landscaping of the green space will create a continuous permeable route for active travel for pedestrian and cyclists, providing a continuous well-lit link from High Lane to Hanway Road.
Lawn with play features seating walls
The two blocks will be designed to encourage low vehicle speeds and naturally manage the 20mph speed limit. With no vehicle through-route provided, the majority of vehicles using the site will either be residents or visitors with occasional delivery and servicing trips.
Mansion
planting
Block
ion
Mans
Block
Lawn with play features
Pro’s • Eliminates rat-running, residential only traffic. • Acts as a natural traffic calming measure, helps to reinforce low vehicle speeds. • Pedestrian and cycles have a continuous link for active travel. • A linear central ‘green space’ without traffic passing across it. • Prioritises pedestrians and cyclists over vehicle movements. • Retractable bollards allow continuous ‘through route’ to the central green space for emergency and refuse collections.
No through route Avenue Existing tree
under 5s gated natural play area houses
High Lane Estate - Residents Consultation 4, 15 July 2020
houses
community growing area
Con’s • Cul-de-sacs are best suited to low density residential areas. • Funnels all traffic through a single point of access at either ends of the estate. • Creates extended cul-de-sac with few turning points. • Dedicated turning heads required at the end of each cul-de-sac. • Prevents a continuous route for servicing and delivery vehicles. • A proportion of the turning heads would be provided as a shared surface. • Rising bollards require maintenance. • Rising bollards reliability may force emergency and refuse vehicles to stack on the public highway if faulty.
under 12s play area
Existing tree Avenue
Avenue
shared surface
Lawn with play features seating walls Mansion Block
planting
ion
Mans
Lawn with play features
Block
Materials and appearance - indicative building material palettes across the development These are the types of materials we are looking at
These are some of the key materials and colours we are looking at. Do you have any preferences? Materials have been carefully chosen to help integrate the proposal into the surrounding area by complementing the existing materials. Residents were pleased with the appearance of the proposed buildings during the last residents meeting in November 2019; they liked that we were proposing bricks in a variety of colours/tones. They also welcomed the introduction of pitched roofs.
Building Materials Palette 1 Clay plain tile Hanging tile (indicative profile) PC metalwork cills and copings GREY clay facing brick - soft multi AS ABOVE WITH PROJECTING BURNED HEADERs Dark Umber PC metalwork, windows and rainwater goods
Building Materials Palette 2 Clay plain tile Hanging tile (indicative profile) PC metalwork cills and copings Red clay facing brick - soft mud, multi AS ABOVE WITH PROJECTING BURNED HEADERs Dark Umber PC metalwork, windows and rainwater goods
Building Materials Palette 3 Clay plain tile Hanging tile (indicative profile) PC metalwork cills and copings Red clay facing brick - soft mud, multi Brown clay facing brick - selected dark facings AS ABOVE WITH PROJECTING BURNED HEADERs Dark Umber PC metalwork, windows and rainwater goods
Building Materials Palette 4 Clay plain tile Hanging tile (indicative profile) PC metalwork cills and copings BUFF clay facing brick - selected dark facings AS ABOVE WITH PROJECTING BURNED HEADERs Dark Umber PC metalwork, windows and rainwater goods
Elevation Studies - Site Arrangement
High Lane Estate - Residents Consultation 4, 15 July 2020
Elevation Bay Study - Palette 2
Artists Impressions of the new proposal Artists impressions depicting key views of the regeneration layout. Pitched roofs help create a more domestic feel.
This page shows some of the proposed new views
Do these images capture a more domestic within the proposal? How do you feel about these views? The images below show the developing proposals and viewpoints on the location key.
1 View towards flat blocks and shared gardens
2 View of pocket park
3 View of central park
4 View from High Lane Looking East
5 View of shared gardens
6 View towards flat blocks and shared parking closes
4
6 1 2
5
3
High Lane Estate - Residents Consultation 4, 15 July 2020
Your new homes The typical plans below illustrate some of the typical developed homes which incorporate key dimensions, indicative furniture layouts, white goods, partially closed off kitchens where possible and radiators. Washing machines located in separate utility cupboards.
This page shows proposed home layouts
3 Bedroom 5 Person Flat 1050
Family bathroom and additional, separate WC
WM
2320
St
R
R
B1 Ba Bs D H K L R Rs St Tr UC WC WM
Tr
WC
UC/ St
H
R R R
R B2
What are your thoughts? Spacious, well proportioned rooms / Plenty of storage / Generous entrances and circulation space
Direct access to private balcony.
(9.3m²)
B1
L
Generous bedrooms with plenty of room for furniture.
B3
(12.3m²)
4315
Spacious and bright living room
4320
We think these are some of the important qualities to consider in the design of your new homes.
900
Ba K/D
(16.2m²)
Large separate kitchen with plenty of room for a dining table
Key 1480
2200
2945
6040
(12.3m²)
(16.3m²)
2850
3780
2850
Bedroom (by number) Bathroom Bike Store Dining Room Hall Kitchen Living Radiator Refuse Store Storage Towel Rail Utility Cupboard Toilet Cloakroom Washing Machine
2150
(8m²)
Lots of natural daylight / Views out onto green spaces (dual aspect where possible)
4 Bedroom 6 Person House
Private balconies / Well insulated homes for thermal comfort and privacy Spacious modern bathrooms / Tall floor to ceiling heights / Convenient bin & bike storage
GardenGarden Garden
(min 40m²-(min 40m²- (min 40m²max 52m²)max 52m²) max 52m²)
4737
4737
1 Bedroom 2 Person Flat
4737 2387
2 Bedroom 4 Person Flat
2387
2387 2250
2250
2250
R
Direct access to private balcony.
High Lane Estate - Residents Consultation 4, 15 July 2020
B2
B2
4737
4737
(14.2m²) (14.2m²)
2500
Bs
2500
2500
4737
1910 1050
1910 1050
1910 1050
4595
St R
St
2730
2730 1360 4737
1360 650 4737
8410
8410
8410
9900
9900
9900
B2
(14.2m²)
B1
3760
Separate kitchen dining room with south facing windows.
B1
1490
R
B1
(13.5m²) (13.5m²)
3760
UC/ St
K/D
(15.7m²)
(13.5m²)
St
1490
R R
St
Ba
St
1490
St
Ba
3005
Generous double bedrooms with plenty of room for furniture.
K/D
K/D
(15.7m²) (15.7m²)
St
2100
Ba
St
St
Tr
WM
Large double bedroom on the second floor with generous storage.
R
4595
R
2100
Family bathroom adjacent to children’s bedrooms
R
St
St
R
R
R
B3
(10.3m²)
2100
WC
B3
3005
WC
2770 9900
WC
R B4
3760
Downstairs WC 2770 9900
Tr
R
B4
(8.1m²) B3 (8.1m²) (10.3m²) (10.3m²)
4595
3400
3400
B4
(8.1m²)
3280
R
L
(16.1m²)
3280
Tr
Spacious and bright kitchen/ living /dining area.
L
3005
Large, welcoming entrance lobby with plenty of useful storage.
UC/
L
(16.1m²) (16.1m²)
WM UC/
2770 9900
R
3280
WM
3400
R
Separate living room with door opening onto private garden.
2730 4737
650 1360
650
Comparing the new proposed homes with the existing homes The existing plans on the right depict the thin building fabric that overheats in summer and provides little insulation in winter. The home layouts include room sizes (imperial and metric) to enable comparison with existing plans.
Comparing the proposed new homes to the existing homes
Existing 2 Bedroom 4 Person Flat Flat Plan ST
Kitchen/Dining 13.8m2 (148sq.ft)
How do you feel the new homes compare with the existing?
BathWC room
ST Bedroom 2
Living
18m2 (194sq.ft)
Proposed 2 Bedroom 4 Person Flat
Proposed 2 Bedroom 4 Person Flat
75.3m2
Flat Plan
Bedroom 1
73.1m2
Entrance
Bedrooms
Flat Plan
B1 12.6m2 Balcony 7m2 (75sq.ft)
ST Bedroom 1
Entrance
+
(135sq.ft)
Bedroom 2
Kitchen
70m2
Living
Dining
Storage
WC
Bathroom
+
(755sq.ft)
Bedroom 1
(133sq.ft)
Room Sizes
Existing Area
ST
B2 12.4m2
13.8m2
18m2
1.6m2
1.4m2
2.7m2
(148sq.ft)
(193sq.ft)
(17q.ft)
(15sq.ft)
(29sq.ft)
Bathroom Living/Dining/Kitchen 27.3m2 (294sq.ft)
Existing 2 Bedroom 4 Person Maisonette
Balcony
Living/Dining/Kitchen Bedroom 2
32.1m2 (345sq.ft)
7m2 (75sq.ft)
W
Bathroom ST
Living
Bathroom
16m2 (172sq.ft)
ST
W WC
ST
Bedroom 2
Entrance ST
ST Kitchen/Dining 9.4m2 (102sq.ft)
Bedrooms
W
Bedrooms
Bedroom 1
Entrance
B1 13.5m2
+
(145sq.ft)
Minimum Area Size, set by planning policy - the Nationally Described Space Standards
70m2
(753sq.ft)
B2 12.7m2
15m2
(136sq.ft)
(162sq.ft)
Room Sizes Kitchen
Living
+
Dining
Storage
B1
Bathroom
+ 32.1m2
3.3m2
4.4m2
(345sq.ft)
(35sq.ft)
(47sq.ft)
Minimum Area Size, set by planning policy - the Nationally Described Space Standards
70m2
(753sq.ft)
+
B2
Lower Level
Upper Level
13.6m2 (146sq.ft)
Bedrooms
Room Sizes Kitchen
Living
+
Dining
Storage
Bathroom
B1
+
14.4m2
27.3m2
2.1m2
4.5m2
(294sq.ft)
(22sq.ft)
(48sq.ft)
+
(155sq.ft)
Existing Area
74m2
(796sq.ft)
B2 11.2m2 (120sq.ft)
Room Sizes Kitchen
Living
Dining
Storage
WC
Bathroom
+ 2
9.4m
16m2
4.0m2
1.2m2
2.6m2
(102sq.ft)
(172sq.ft)
(43q.ft)
(13sq.ft)
(28sq.ft)
NOTE: Some assumptions have been made regarding internal layouts. Furniture arrangements are indicative. Existing floor areas measured off original microfiche imperial measurements and are likely to feature inaccuracies.
High Lane Estate - Residents Consultation 4, 15 July 2020
Comparing the new proposed homes with the existing homes How do you feel the new homes compare with the existing?
Comparing the proposed new homes to the existing homes
Existing 3 Bedroom 5 Person Flat Flat Plan Living
Kitchen/Dining
17.8m2 (191sq.ft)
13.8m2 (148sq.ft)
Entrance ST ST
Proposed 3 Bedroom 5 Person Flat 94.6m
ST
Proposed 4 Bed 6 Person House 126.6m
2
Bathroom
2
W Bedroom 3
Flat Plan
WC
Bedroom 2
Bedroom 1
House Plan
Bedrooms
Balcony 7m2 (75sq.ft)
B1 12.6m2
+
(135sq.ft)
Bedroom 2
Living
Living
16.1m (173sq.ft) 2
16.3m2 (175sq.ft)
Bedroom 4
Bedroom 3
Bedroom 1
82m
Bedroom 1
Kitchen/Dining
ST
16.2m2 (174sq.ft)
Bathroom
Kitchen
Dining
13.8m2
1.8m2
1.4m2
2.7m2
(191sq.ft)
(148sq.ft)
(19q.ft)
(15sq.ft)
(29sq.ft)
15.7m2 (169sq.ft)
Kitchen/ Dining
Bedroom 2
Bedroom 3
9.4m2 (119sq.ft)
Entrance Living
B1 12.3m2
+
(145sq.ft)
(753sq.ft)
Kitchen
Dining
Living
B2 12.3m2 (153sq.ft)
Storage
+
B1
B3 9.3m2
13.5m2
(100sq.ft)
(145sq.ft)
Bathroom
Minimum Area Size, set by planning policy - the Nationally Described Space Standards
16.2m2
16.3m2
4m2
4.4m2
112m
(174q.ft)
(175q.ft)
(43sq.ft)
(47sq.ft)
(1205sq.ft)
14.2m2 (153sq.ft)
+
B3 10.3m2 (110sq.ft)
+
B4 8.1m2 (87sq.ft)
Bedroom 1
Bathroom
Entrance
ST
WC
WC
Lower Level
Upper Level
Bedrooms
Room Sizes Living
2
+
+
B2
Bedroom 2
ST
16m2 (153sq.ft)
Bedrooms
Bedrooms
86m
Bathroom
Existing 3 Bedroom 6 Person Maisonette
Entrance
2
WC
Kitchen/ Dining ST
Minimum Area Size, set by planning policy - the Nationally Described Space Standards
Storage
17.8m
2
ST
Bathroom
(100sq.ft)
+
(880sq.ft) WC
ST
Living
2
Bedroom 3
(133sq.ft)
B3 9.3m2
Room Sizes
Existing Area
ST
+
B2 12.4m2
Kitchen
Dining
Storage
Bathroom
B1
+
14.9m2
+
(160sq.ft)
16.1m2
15.7m2
12.6m2
4.7m2
(173sq.ft)
(169sq.ft)
(135sq.ft)
(51sq.ft)
Existing Area
92m2
(998sq.ft)
B2 11.4m2 (123sq.ft)
+
B3 11.2m2 (120sq.ft)
Room Sizes Kitchen
Dining
Living
Storage
WC
Bathroom
16m2
9.4m2
2.4m2
1.3m2
2.6m2
(172q.ft)
(101q.ft)
(26q.ft)
(14sq.ft)
(28sq.ft)
+
NOTE: Some assumptions have been made regarding internal layouts. Furniture arrangements are indicative. Existing floor areas measured off original microfiche imperial measurements and are likely to feature inaccuracies.
High Lane Estate - Residents Consultation 4, 15 July 2020
Landscape Strategy - overall site layout Since the last workshop we have developed the landscape plan to show: • An idea of the design for the central pocket park areas including lawns, paths, planting, play equipment and natural play features
This page shows the layout of the streets, parking, gardens and open spaces
• Fenced and gated natural play area for under 5s • Dedicated community growing area • A play trail aimed at the under 12s and a fitness trail for over 14s-adults along the Green Lane • Screening planting for privacy in front of balconies, front gardens and ground floor windows
How would you and your family use these outdoor spaces? Do you have any comments? ns rde Ga
Mayfield
back
k bac
gardens b
k
c
a
a
g
r
d
s den gar
e
n
s
house
s
U E E N A V
s
house b
a
c
k
g
a
r
d
e
n
s
POCKET PARK
shop Cafe / Shop
s
house
houses
houses
growing area
Lane High
Playground
A V E N U E arden
Commnity space
Man Mansion sion Bloc Blockk
parking court
Man Mansion sion Bloc Blockk
garden
Mansion Block
courtyard
Mansion Block
POCKET PARK
ion Mans Block
g parkinrt cou
g
ion Mans Block
gre
en
yard gre
lan
e
gardens
d Roa
S t ub land
High Lane Estate - Residents Consultation 4, 15 July 2020
g parkinrt cou
yard
court
court
green lane back
ion Mans Block
ion Mans Block
ion Mans Block
n garde
k bac
s den gar
en
lan
e
g parkinrt cou
ion Mans Block
Landscape Spaces in Detail - gardens and green spaces How would you or your family use these outdoor spaces? Do you have any comments? Pocket Park
This page shows gardens and green spaces
The main features of the Pocket Park are:
Main features of garden courtyards:
Garden Courtyards
• Central location in the estate acccessible to everyone
• Semi-formal gardens
• Connected to walking routes
• Lawns with trees and planted borders
• Large existing mature trees are focal points
• Partially enclosed by clipped hedges
• Sunny central areas
• Places to sit
• New trees, planting and lawns
• Simple play features for for small children
• Includes attractive and fun play equipment for younger children • A small gated natural play area for very young children • Places to sit • Raised allotment beds for residents’ growing
Existing tree
houses
houses
under 12s play area
under 5s gated play area
on street car parking
houses
on street car parking
Avenue community growing area
Examples - naturalstic pocket park with play
on street car parking Precedent image - Mansion Block Frontage with hedges
hedge
Avenue
Existing tree
Avenue
on street car parking
hedge
shared surface
Example images - Raised beds for community growing
planting
Block
n
io Mans
Mansion
planting
Mansion
Lawns with seating and small scuptural play features
Block
paths
Block
seating wall
Block
Example of Mansion Block courtyard garden in Hammersmith
planting
hedge
Lawn with play features
Existing tree
Mansion balconies/entrances
seating walls
balconies/entrances
houses
planting
Existing trees gree
ne n la
play trail feature Example image - lawns, trees and planting
green lane
green lane
back gardens to properties on Stubland Road
Example image - sculptural play feature in lawn
Green Lane The main features of the Green Lane are: • Pedestrian route along the southern boundary, which connects to garden courtyards and parking courts • Play trail features for children along the route (balancing, stepping etc.) • Fitness trail features along the route (pull ups, sit ups, step ups) and walking/jogging distance markers • Low level lighting from dusk to dawn for wayfinding and safety Walking route
High Lane Estate - Residents Consultation 4, 15 July 2020
Typical fitness trail feature
Typical play trail equipment
Landscape Spaces in Detail - parking and streets Do you have any comments? This page shows parking and streets
Parking Courts
Main parking court features are:
Avenue
Main Avenue features are: • A clear east-west vehicle and pedestrian route through the estate with dawn to dusk street lighting • Lined with semi-mature trees
• Shared surface for vehicles and pedestrians
• Parallel on-street parking for cars between new street trees
• Block paving in silver grey to compliment the buildings
• Shared surface raised tables (block paving) at some entrances to parking courts to slow traffic
• Partially enclosed by clipped hedges
• Generous pavement
• New trees and hedges for greenery and privacy
• Planting in front of ground floor windows adjacent to footpaths for privacy • Front doors of houses and the community room open onto the avenue supporting an ‘active street’ • Level access (no steps or ramps) for pedestrians to front doors, the parking courts and garden courtyards
Artists impressions
houses
on street car parking on street car parking
Avenue
Raised Table
(traffic calming)
on street car parking
on street car parking
hedge
45
Artist’s impression -parking court
Pollard Thomas Edwards
High Lane, Hanwell Regeneration — GLA Meeting 1, 11 December 2019
Artist’s impression - Avenue
Example image - shared pedestrian and vehicle surface
hedge
parking
hedge
bays
parking bays
hedge Example image - night time view
NOTES: - Do not scale from this drawing - All dimensions to be verified on site prior to ordering
No.
Mansion Block
Mansion Block
Hazard
Work Element
1.
s
house
2.
21000 CAR PARKING
17400 GARDEN
3.
houses
4. 5. Be Safe - Refer to Full Designers Risk
Existing tree
Assessment
e Avenu
2000.0
hedge
parking bays
parking bays
(block paving)
PRINCIPAL HAZARDS:
MANSION BLOCK
2000.0
balconies/entrances
balconies/entrances
Shared surface
hedge
MANSION BLOCK
Avenue - No Through Road Option - what do you think? - All works to be carried out in accordance with all relevant codes of practice and British Standards
Avenue (west)
s
bollard
shared surface
turning space
(east)
ce
g spa
turnin
(access for emergency vehicles only) bollards
Fitness trail feature green lane
Existing tree
green lane
HEDGE
PARKING BAY
AISLE
PARKING BAY
HEDGE
HEDGE LAWN FOOTPATH
LAWN
Mansion Block D
FOOTPATH LAWN HEDGE
FFL+ 16100.0
1500
1200
4800
6000
4800
1200
POCKET PARK
ion Manosck l B E
1500 1500
1000 1000
1600
1600
1000 1000
1500
Typical Section looking South through parking court
• This plan shows the option for the Avenue to be a no-through road with a central pedestrian space Blackhouse Studio Ipswich - IP9 1JN
tel: 01473 781994 web: www.area-la.com
• Turning space is provided for cars and service vehicles at the ends of the eastern and western sections of the Avenue landscape architects
project:
High Lane Hanwell
• A route for emergency vehicles is provided, accessed by lockable drop bollards Rydon client:
drawing title:
Landscape Section- Mansion Blocks Ph 1 status:
scale
preliminary
1:500
revision:
date
paper size
-
23/01/2020
A3
drawing number:
236_SK_304
revision notes:
-date
High Lane Estate - Residents Consultation 4, 15 July 2020
--
xxxxxxxx
drawn revision description
-
xx rev
checked
Cafe / shop Proposals This page updates on the proposed cafe / shop
ideration Careful cons avoid to on design haviour antisocial be ive ss through pa and surveillance ing en op d lle ro nt co hours.
The images below show the current designs and how they have been developed in response to your feedback. The previous times we met, you gave us some ideas for your new cafe /shop. Is there anything you would like to add to this?
Majorit appea y of residen the ide red to supp ts o a or a c of small sh rt af o for eld ĂŠ, particula p rly e reside rly/less able n furthe ts and those st awa y fr existin g shop om s.
Connection to the wider community is important, it should be located at the west of the site near the entrance from High lane.
1 Artists Impression of the new Cafe /shop from High Lane
2
Artists Impression of the new Cafe /shop
to Flats Above
Location Key
1
Cycle stands
Gym trail. Sit up bench
Consultation Boards presented during Residents Steering Group meeting 2 and which include residents feedback.
Ground Floor Plan - Cafe / Shop
Note: Comments above collated from residents feedback received at RSG meeting 2 (05.12.17) and RSG meeting 3 (28.11.19).
Note: Proposed Shop/ CafĂŠ subject to an operator taking the space. In order to achieve the best chance of survival we propose the shop opens once all the residents have moved in.
High Lane Estate - Residents Consultation 4, 15 July 2020
2
Community Space - how this sits within the new proposal The images below show the current designs and how they have been developed in response to your feedback. The community space is located in the heart of the development, near High Lane and over one floor for easier accessibility. Is there anything you would like to add to this?
This page updates on the proposed community space Potential uses for the community room: Cookery classes, stay & play, youth club, after school club, conversation club, coffee mornings, disco....
Some reside nts exp interes ressed an t in re nting t space h otherw when its no e t ise in use. (e childre g. n’s bir partie thday s).
The space should be flexible, bright and spacious, welcoming and a space for everyone. It should be located near the west side and be visible from High Lane.
without “Residents mputer co or et rn inte uld use co e m ho at ions such provis here.”
1 Artists Impression of new community space from avenue
AVENUE
2 Artists Impression of the new community space
Main Entrance
Location Key
1
2 Terrace
Consultation Boards presented during Residents Steering Group meeting 2 and which include residents feedback.
Ground Floor Plan - Community space
Note: Comments above collated from residents feedback received at RSG meeting 2 (05.12.17) and RSG meeting 3 (28.11.19).
High Lane Estate - Residents Consultation 4, 15 July 2020
Project Timeline This page shows the project timeline
Summer 2023 Phase 2 site enabling works
2020 Nov 2019 design workshop 3 for residents
Summer 2023 Phase 1 construction works complete
September 2020 design consultation 4 for residents
September 2020 exhibition for residents and wider public
October 2020 submit planning application
2019
2024
2023
Autumn 2025 Phase 2 construction works complete Winter 2026 Phase 3 site enabling works
2026
2021 Aug 2020 Ealing planning committee
2025
2022
Aug 2021 Phase 1 site enabling works
2028
High Lane Estate - Residents Consultation 4, 15 July 2020
Autumn 2028 – Phase 3 construction works complete