OUR SAVIOR LUTHERAN CHURCH Monthly Project Summary Summary Date: September 11, 2017
Building on a foundation of Integrityâ„¢
TABLE OF CONTENTS
OUR SAVIOR LUTHERAN CHURCH
01
OWNERSHIP TEAM
02
BUSH CONSTRUCTION TEAM
03
DESIGN TEAM
04
CONTRACTORS
05
PROJECT ACTIVITY HIGHLIGHTS
06
PROJECT PHOTOS
OWNERSHIP TEAM | OUR SAVIOR LUTHERAN CHURCH OUR SAVIOR LUTHERAN CHURCH JOHN OVERBEEKE Bettendorf, IA P. 563-424-0019 jobettendorf@gmail.com
HEATHER SCHEUERMANN Parish Administrator P. 563-332-5141 oslcparishadmin@mediacombb.net
BUSH CONSTRUCTION TEAM OUR SAVIOR LUTHERAN CHURCH PROJECT EXECUTIVE A.J. Loss P. 563-344-3793 M. 563-271-6562 Email: ajloss@bushconstruct.com PROJECT MANAGER Ryan Dean P. 563-441-2142 M. 563-594-9267 Email: rdean@bushconstruct.com PROJECT SUPERINTENDENT Gary Swift M. 563-449-2309 Email: gswift@bushconstruct.com SAFETY & QUALITY CONTROL DIRECTOR Skipp Jacobsen M. 563-949-5204 Email: sjacobson@bushconstruct.com PROJECT COORDINATOR Leslie Wells P. 563-344-3780 Email: lwells@bushconstruct.com
DESIGN TEAM
OUR SAVIOR LUTHERAN CHURCH ARCHITECT Novak Design Group, PLC Gary M Landhauser AIA P. 319-393-9334 glandhauser@novakdesigngroup.com CIVIL ENGINEER McClure Engineering Loren Rains P. 309-792-9305 l.rains@mcclureengineering.com STRUCTURAL ENGINEER M2B Structural Engineers Lynn Boettcher P. 319-364-0666 lboettcher@m2bengineers.com ELECTRICAL ENGINEER IEFM Marty Valentine P. 309-799-5150 mvalentine@iefmconsultingengineers.co m MECHANICAL ENGINEER IEFM Jeff Newcomb p. 309-799-5150 jnewcomb@iefmconsultingengineers.com
SUBCONTRACTORS + SUPPLIERS OUR SAVIOR LUTHERAN CHURCH B&B MASONRY Masonry
PRIME CONSTRUCTION Gypsum Board & Operable Partitions
CARPETLAND Flooring
RIVER CITY CUTTING & CORING Selective Interior Demolition
COLOR, INC. Painting
SAUDER WORSHIP SEATING Pews
COOPMAN TRUCKING & EXCAVATING Earthwork & Site Utilities
SHAW ELECTRIC Electrical
CRAWFORD HVAC
STERLING COMMERCIAL ROOFING Metal Wall Panels/Roofing/Sheet Metal
CRAWFORD Plumbing
SUBSURFACE CONSTRUCTORS Aggregate Piers
EAST MOLINE GLASS Aluminum Entrances & Storefronts
SUMMIT CONCRETE Building & site concrete
GREENSPACE ASSOCIATES Landscaping
HORIZON GROUP Architectural Woodwork
IRWIN SEATING COMPANY Fixed Seating
MID-STATES CONCRETE INSUSTRIES Precast concrete
INDUSTRIAL STEEL ERECTORS Steel Erection
PELLA WINDOWS Awning/Casement Windows
MCCARTHY IMPROVEMENT Asphalt
VEGTER STEEL Structural Metals
PROJECT ACTIVITY HIGHLIGHTS OUR SAVIOR LUTHERAN CHURCH KEY MILESTONE ACHIEVEMENTS
KEY INSPECTIONS •
•
•
Bush Construction, Novak Design Group and all subcontractors/suppliers are successfully using a web-based software called Plan Room for submittal, RFI and meeting minute updates. All steel for Area A Gathering Addition is complete and will soon be ready for roofing.
•
SAFETY
QUALITY CONTROL • •
Bush Construction is in constant contact with each trade contractor and all third party inspectors to ensure that performed services and materials adhere to the defined set of quality criteria per the project documents.
Inspections by the City of Bettendorf Building Department will be conducted as necessary to ensure the building construction is being performed to applicable codes. Terracon is and will be conducting testing/inspection procedures on building compaction, concrete, steel welds and bolt connections.
Foreman meetings are conducted on site weekly with all foreman working on the project. Safety is the first item discussed at these meetings.
•
Tool Box Talks are conducted weekly by all prime contractors and second tier subcontractors working onsite.
•
Weekly Safety Inspection by the Superintendent
•
Number of Lost Time Incidents on this Project – 0
•
Number of Recordable Incidents on the Project - 0
RECENT ACTIVITY • •
•
• •
•
Area A exterior stud walls are nearly finished and a good portion of sheathing is installed. Waterproofing on exterior walls is complete on a portion of the back and side of Area A. Insulation will soon be installed as part of the insulation finishing system. Concrete floor slab was poured throughout Area A. Ready to begin laying out interior walls. All footings and foundations have been poured at Area B. CMU block continues at Area B. After structural block is complete, steel joists and decking will be installed with roofing to follow. The door and frame that were added for access to the courtyard is installed and painted.
KEY SCHEDULE MILESTONES • •
Both building additions are projected to be complete by March 2018. The renovation space, planned for summer of 2018, is projected to be complete by September 2018.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
All concrete footings have been installed for Area B Classroom Addition.
Concrete foundations for structural concrete masonry will begin next.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
The exterior sheathing for the south wall of Area A Gathering Addition is complete. Ready for weatherproofing and EIFS.
Underground piping for bathrooms are complete inside the Gathering Addition. Ready for concrete floor slab.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
More phots of progress at Area B. CMU block walls are being built at the exterior of the building.
Progress of metal stud framing and sheathing at the front of Area A.