OUR SAVIOR LUTHERN CHURCH - Building project update - August

Page 1

OUR SAVIOR LUTHERAN CHURCH Monthly Project Summary Summary Date: September 11, 2017

Building on a foundation of Integrityâ„¢


TABLE OF CONTENTS

OUR SAVIOR LUTHERAN CHURCH

01

OWNERSHIP TEAM

02

BUSH CONSTRUCTION TEAM

03

DESIGN TEAM

04

CONTRACTORS

05

PROJECT ACTIVITY HIGHLIGHTS

06

PROJECT PHOTOS


OWNERSHIP TEAM | OUR SAVIOR LUTHERAN CHURCH OUR SAVIOR LUTHERAN CHURCH JOHN OVERBEEKE Bettendorf, IA P. 563-424-0019 jobettendorf@gmail.com

HEATHER SCHEUERMANN Parish Administrator P. 563-332-5141 oslcparishadmin@mediacombb.net


BUSH CONSTRUCTION TEAM OUR SAVIOR LUTHERAN CHURCH PROJECT EXECUTIVE A.J. Loss P. 563-344-3793 M. 563-271-6562 Email: ajloss@bushconstruct.com PROJECT MANAGER Ryan Dean P. 563-441-2142 M. 563-594-9267 Email: rdean@bushconstruct.com PROJECT SUPERINTENDENT Gary Swift M. 563-449-2309 Email: gswift@bushconstruct.com SAFETY & QUALITY CONTROL DIRECTOR Skipp Jacobsen M. 563-949-5204 Email: sjacobson@bushconstruct.com PROJECT COORDINATOR Leslie Wells P. 563-344-3780 Email: lwells@bushconstruct.com


DESIGN TEAM

OUR SAVIOR LUTHERAN CHURCH ARCHITECT Novak Design Group, PLC Gary M Landhauser AIA P. 319-393-9334 glandhauser@novakdesigngroup.com CIVIL ENGINEER McClure Engineering Loren Rains P. 309-792-9305 l.rains@mcclureengineering.com STRUCTURAL ENGINEER M2B Structural Engineers Lynn Boettcher P. 319-364-0666 lboettcher@m2bengineers.com ELECTRICAL ENGINEER IEFM Marty Valentine P. 309-799-5150 mvalentine@iefmconsultingengineers.co m MECHANICAL ENGINEER IEFM Jeff Newcomb p. 309-799-5150 jnewcomb@iefmconsultingengineers.com


SUBCONTRACTORS + SUPPLIERS OUR SAVIOR LUTHERAN CHURCH B&B MASONRY Masonry

PRIME CONSTRUCTION Gypsum Board & Operable Partitions

CARPETLAND Flooring

RIVER CITY CUTTING & CORING Selective Interior Demolition

COLOR, INC. Painting

SAUDER WORSHIP SEATING Pews

COOPMAN TRUCKING & EXCAVATING Earthwork & Site Utilities

SHAW ELECTRIC Electrical

CRAWFORD HVAC

STERLING COMMERCIAL ROOFING Metal Wall Panels/Roofing/Sheet Metal

CRAWFORD Plumbing

SUBSURFACE CONSTRUCTORS Aggregate Piers

EAST MOLINE GLASS Aluminum Entrances & Storefronts

SUMMIT CONCRETE Building & site concrete

GREENSPACE ASSOCIATES Landscaping

HORIZON GROUP Architectural Woodwork

IRWIN SEATING COMPANY Fixed Seating

MID-STATES CONCRETE INSUSTRIES Precast concrete

INDUSTRIAL STEEL ERECTORS Steel Erection

PELLA WINDOWS Awning/Casement Windows

MCCARTHY IMPROVEMENT Asphalt

VEGTER STEEL Structural Metals


PROJECT ACTIVITY HIGHLIGHTS OUR SAVIOR LUTHERAN CHURCH KEY MILESTONE ACHIEVEMENTS

KEY INSPECTIONS •

Bush Construction, Novak Design Group and all subcontractors/suppliers are successfully using a web-based software called Plan Room for submittal, RFI and meeting minute updates. All steel for Area A Gathering Addition is complete and will soon be ready for roofing.

SAFETY

QUALITY CONTROL • •

Bush Construction is in constant contact with each trade contractor and all third party inspectors to ensure that performed services and materials adhere to the defined set of quality criteria per the project documents.

Inspections by the City of Bettendorf Building Department will be conducted as necessary to ensure the building construction is being performed to applicable codes. Terracon is and will be conducting testing/inspection procedures on building compaction, concrete, steel welds and bolt connections.

Foreman meetings are conducted on site weekly with all foreman working on the project. Safety is the first item discussed at these meetings.

Tool Box Talks are conducted weekly by all prime contractors and second tier subcontractors working onsite.

Weekly Safety Inspection by the Superintendent

Number of Lost Time Incidents on this Project – 0

Number of Recordable Incidents on the Project - 0

RECENT ACTIVITY • •

• •

Area A exterior stud walls are nearly finished and a good portion of sheathing is installed. Waterproofing on exterior walls is complete on a portion of the back and side of Area A. Insulation will soon be installed as part of the insulation finishing system. Concrete floor slab was poured throughout Area A. Ready to begin laying out interior walls. All footings and foundations have been poured at Area B. CMU block continues at Area B. After structural block is complete, steel joists and decking will be installed with roofing to follow. The door and frame that were added for access to the courtyard is installed and painted.

KEY SCHEDULE MILESTONES • •

Both building additions are projected to be complete by March 2018. The renovation space, planned for summer of 2018, is projected to be complete by September 2018.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

All concrete footings have been installed for Area B Classroom Addition.

Concrete foundations for structural concrete masonry will begin next.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

The exterior sheathing for the south wall of Area A Gathering Addition is complete. Ready for weatherproofing and EIFS.

Underground piping for bathrooms are complete inside the Gathering Addition. Ready for concrete floor slab.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

More phots of progress at Area B. CMU block walls are being built at the exterior of the building.

Progress of metal stud framing and sheathing at the front of Area A.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.