OUR SAVIOR LUTHERAN CHURCH Monthly Project Summary Summary Date: July 6, 2017

Building on a foundation of Integrityâ„¢


TABLE OF CONTENTS

OUR SAVIOR LUTHERAN CHURCH

01

OWNERSHIP TEAM

02

BUSH CONSTRUCTION TEAM

03

DESIGN TEAM

04

CONTRACTORS

05

PROJECT ACTIVITY HIGHLIGHTS

06

PROJECT PHOTOS


OWNERSHIP TEAM | OUR SAVIOR LUTHERAN CHURCH OUR SAVIOR LUTHERAN CHURCH JOHN OVERBEEKE Bettendorf, IA P. 563-424-0019 jobettendorf@gmail.com

HEATHER SCHEUERMANN Parish Administrator P. 563-332-5141 oslcparishadmin@mediacombb.net


BUSH CONSTRUCTION TEAM OUR SAVIOR LUTHERAN CHURCH PROJECT EXECUTIVE A.J. Loss P. 563-344-3793 M. 563-271-6562 Email: ajloss@bushconstruct.com PROJECT MANAGER Ryan Dean P. 563-441-2142 M. 563-594-9267 Email: rdean@bushconstruct.com PROJECT SUPERINTENDENT Gary Swift M. 563-449-2309 Email: gswift@bushconstruct.com SAFETY & QUALITY CONTROL DIRECTOR Skipp Jacobsen M. 563-949-5204 Email: sjacobson@bushconstruct.com PROJECT COORDINATOR Leslie Wells P. 563-344-3780 Email: lwells@bushconstruct.com


DESIGN TEAM

OUR SAVIOR LUTHERAN CHURCH ARCHITECT Novak Design Group, PLC Gary M Landhauser AIA P. 319-393-9334 glandhauser@novakdesigngroup.com CIVIL ENGINEER McClure Engineering Loren Rains P. 309-792-9305 l.rains@mcclureengineering.com STRUCTURAL ENGINEER M2B Structural Engineers Lynn Boettcher P. 319-364-0666 lboettcher@m2bengineers.com ELECTRICAL ENGINEER IEFM Marty Valentine P. 309-799-5150 mvalentine@iefmconsultingengineers.co m MECHANICAL ENGINEER IEFM Jeff Newcomb p. 309-799-5150 jnewcomb@iefmconsultingengineers.com


SUBCONTRACTORS + SUPPLIERS OUR SAVIOR LUTHERAN CHURCH B&B MASONRY Masonry

PRIME CONSTRUCTION Gypsum Board & Operable Partitions

CARPETLAND Flooring

RIVER CITY CUTTING & CORING Selective Interior Demolition

COLOR, INC. Painting

SAUDER WORSHIP SEATING Pews

COOPMAN TRUCKING & EXCAVATING Earthwork & Site Utilities

SHAW ELECTRIC Electrical

CRAWFORD HVAC

STERLING COMMERCIAL ROOFING Metal Wall Panels/Roofing/Sheet Metal

CRAWFORD Plumbing

SUBSURFACE CONSTRUCTORS Aggregate Piers

EAST MOLINE GLASS Aluminum Entrances & Storefronts

SUMMIT CONCRETE Building & site concrete

GREENSPACE ASSOCIATES Landscaping

HORIZON GROUP Architectural Woodwork

IRWIN SEATING COMPANY Fixed Seating

MID-STATES CONCRETE INSUSTRIES Precast concrete

INDUSTRIAL STEEL ERECTORS Steel Erection

PELLA WINDOWS Awning/Casement Windows

MCCARTHY IMPROVEMENT Asphalt

VEGTER STEEL Structural Metals


PROJECT ACTIVITY HIGHLIGHTS OUR SAVIOR LUTHERAN CHURCH KEY MILESTONE ACHIEVEMENTS

KEY INSPECTIONS •

Bush Construction, Novak Design Group and all subcontractors/suppliers are successfully using a web-based software called Plan Room for submittal, RFI and meeting minute updates. Footings and foundations at Area A – Gathering Addition were completed last week.

Inspections by the City of Bettendorf Building Department will be conducted as necessary to ensure the building construction is being performed to applicable codes. Terracon is and will be conducting testing/inspection procedures on building compaction, concrete, steel welds and bolt connections.

SAFETY QUALITY CONTROL •

Bush Construction is in constant contact with each trade contractor and all third party inspectors to ensure that performed services and materials adhere to the defined set of quality criteria per the project documents.

Foreman meetings are conducted on site weekly with all foreman working on the project. Safety is the first item discussed at these meetings.

Tool Box Talks are conducted weekly by all prime contractors and second tier subcontractors working onsite.

Weekly Safety Inspection by the Superintendent

Number of Lost Time Incidents on this Project – 0

Number of Recordable Incidents on the Project - 0

RECENT ACTIVITY •

• •

Sanitary sewer connections were made to the existing sewer lines that now exit through the city sewer rather than the old septic tank. Area B – Classroom Addition soil has been stripped and back-filled with rock and is ready for footing excavations to begin. New storm sewer piping has begun at Area B which connects to roof drains at Area A and Area B additions Structural steel was delivered and erected at Area A. Precast panels are being delivered Monday 8/7 and the remaining structural steel will be set shortly after precast is installed. The stained glass window at the front of the church was cut down so the roofing can tie into the building. Brick infill is scheduled to take place this week.

KEY SCHEDULE MILESTONES • •

Both building additions are projected to be complete by March 2018. The renovation space, planned for summer of 2018, is projected to be complete by September 2018.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

Waterproof membrane, insulation with drainage channels and rock backfill.

Sanitary man hole # 3 heading to tie in location near area B.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

Window W-30 was shortened for new roof tie-in. There will be brick infill from existing brick to bottom of window.

New sanitary tie in location. The Septic tank is gone.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

Footings and foundation walls at the new main entrance.

Beams and columns being unloaded for area A.