OUR SAVIOR LUTHERAN CHURCH Monthly Project Summary Summary Date: June 2, 2017
Building on a foundation of Integrityâ„¢
TABLE OF CONTENTS
OUR SAVIOR LUTHERAN CHURCH
01
OWNERSHIP TEAM
02
BUSH CONSTRUCTION TEAM
03
DESIGN TEAM
04
CONTRACTORS
05
PROJECT ACTIVITY HIGHLIGHTS
06
PROJECT PHOTOS
OWNERSHIP TEAM | OUR SAVIOR LUTHERAN CHURCH OUR SAVIOR LUTHERAN CHURCH JOHN OVERBEEKE Bettendorf, IA P. 563-424-0019 jobettendorf@gmail.com
HEATHER SCHEUERMANN Parish Administrator P. 563-332-5141 oslcparishadmin@mediacombb.net
BUSH CONSTRUCTION TEAM OUR SAVIOR LUTHERAN CHURCH PROJECT EXECUTIVE A.J. Loss P. 563-344-3793 M. 563-271-6562 Email: ajloss@bushconstruct.com PROJECT MANAGER Ryan Dean P. 563-441-2142 M. 563-594-9267 Email: rdean@bushconstruct.com PROJECT SUPERINTENDENT Gary Swift M. 563-449-2309 Email: gswift@bushconstruct.com SAFETY & QUALITY CONTROL DIRECTOR Skipp Jacobsen M. 563-949-5204 Email: sjacobson@bushconstruct.com PROJECT COORDINATOR Leslie Wells P. 563-344-3780 Email: lwells@bushconstruct.com
DESIGN TEAM
OUR SAVIOR LUTHERAN CHURCH ARCHITECT Novak Design Group, PLC Gary M Landhauser AIA P. 319-393-9334 glandhauser@novakdesigngroup.com CIVIL ENGINEER McClure Engineering Loren Rains P. 309-792-9305 l.rains@mcclureengineering.com STRUCTURAL ENGINEER M2B Structural Engineers Lynn Boettcher P. 319-364-0666 lboettcher@m2bengineers.com ELECTRICAL ENGINEER IEFM Dan Mount P. 309-799-5150 dmount@iefmconsultingengineers.com MECHANICAL ENGINEER IEFM Jeff Newcomb p. 309-799-5150 jnewcomb@iefmconsultingengineers.com
SUBCONTRACTORS + SUPPLIERS OUR SAVIOR LUTHERAN CHURCH B&B MASONRY Masonry
PRIME CONSTRUCTION Gypsum Board & Operable Partitions
CARPETLAND Flooring
RIVER CITY CUTTING & CORING Selective Interior Demolition
COLOR, INC. Painting
SAUDER WORSHIP SEATING Pews
COOPMAN TRUCKING & EXCAVATING Earthwork & Site Utilities
SHAW ELECTRIC Electrical
CRAWFORD HVAC
STERLING COMMERCIAL ROOFING Metal Wall Panels/Roofing/Sheet Metal
CRAWFORD Plumbing
SUBSURFACE CONSTRUCTORS Aggregate Piers
EAST MOLINE GLASS Aluminum Entrances & Storefronts
SUMMIT CONCRETE Building & site concrete
GREENSPACE ASSOCIATES Landscaping
HORIZON GROUP Architectural Woodwork
IRWIN SEATING COMPANY Fixed Seating
MID-STATES CONCRETE INSUSTRIES Precast concrete
INDUSTRIAL STEEL ERECTORS Steel Erection
PELLA WINDOWS Awning/Casement Windows
MCCARTHY IMPROVEMENT Asphalt
VEGTER STEEL Structural Metals
PROJECT ACTIVITY HIGHLIGHTS OUR SAVIOR LUTHERAN CHURCH KEY MILESTONE ACHIEVEMENTS
KEY INSPECTIONS •
•
•
Bush Construction, Novak Design Group and all subcontractors/suppliers are successfully using a web-based software called Plan Room for submittal, RFI and meeting minute updates. Ground breaking ceremony was held Sunday May 21, 2017 in between church services.
•
Inspections by the City of Bettendorf Building Department will be conducted as necessary to ensure the building construction is being performed to applicable codes. Terracon is and will be conducting testing/inspection procedures on building compaction, concrete, steel welds and bolt connections.
SAFETY •
Foreman meetings are conducted on site weekly with all foreman working on the project. Safety is the first item discussed at these meetings.
•
Tool Box Talks are conducted weekly by all prime contractors and second tier subcontractors working onsite.
QUALITY CONTROL •
Bush Construction is in constant contact with each trade contractor and all third party inspectors to ensure that performed services and materials adhere to the defined set of quality criteria per the project documents.
•
Weekly Safety Inspection by the Superintendent
•
Number of Lost Time Incidents on this Project – 0
•
Number of Recordable Incidents on the Project - 0
RECENT ACTIVITY • • •
•
Bush Construction mobilized on site with site fencing, a dumpster and our project work trailer. Coopman Trucking has been bringing in truck loads of rock to bring the building pad up to finished floor level. The existing porte cochere was removed and hauled away to make room for the new building addition/front entrance. Site utilities, including fire hydrant replacement, storm and sanitary sewer will begin the first full week in June.
KEY SCHEDULE MILESTONES • •
Both building additions are projected to be complete by March 2018. The renovation space, planned for summer of 2018, is projected to be complete by September 2018.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
Ground breaking ceremony.
Ground breaking ceremony
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
Cross being dug during the ground breaking ceremony.
1979 cornerstone with time capsule discovered during demolition.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
Remove sod at building area A.
Prepare building site A for granular fill.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
Bringing building pad up in lifts compacted to at least 95% per lift.
Location of basement – Building A.