OUR SAVIOR LUTHERAN CHURCH BETTENDORF - BUILDING UPDATE SEPTEMBER 2017

Page 1

OUR SAVIOR LUTHERAN CHURCH Monthly Project Summary Summary Date: October 6, 2017

Building on a foundation of Integrityâ„¢


TABLE OF CONTENTS

OUR SAVIOR LUTHERAN CHURCH

01

OWNERSHIP TEAM

02

BUSH CONSTRUCTION TEAM

03

DESIGN TEAM

04

CONTRACTORS

05

PROJECT ACTIVITY HIGHLIGHTS

06

PROJECT PHOTOS


OWNERSHIP TEAM | OUR SAVIOR LUTHERAN CHURCH OUR SAVIOR LUTHERAN CHURCH JOHN OVERBEEKE Bettendorf, IA P. 563-424-0019 jobettendorf@gmail.com

HEATHER SCHEUERMANN Parish Administrator P. 563-332-5141 oslcparishadmin@mediacombb.net


BUSH CONSTRUCTION TEAM OUR SAVIOR LUTHERAN CHURCH PROJECT EXECUTIVE A.J. Loss P. 563-344-3793 M. 563-271-6562 Email: ajloss@bushconstruct.com PROJECT MANAGER Ryan Dean P. 563-441-2142 M. 563-594-9267 Email: rdean@bushconstruct.com PROJECT SUPERINTENDENT Gary Swift M. 563-449-2309 Email: gswift@bushconstruct.com SAFETY & QUALITY CONTROL DIRECTOR Skipp Jacobsen M. 563-949-5204 Email: sjacobson@bushconstruct.com PROJECT COORDINATOR Leslie Wells P. 563-344-3780 Email: lwells@bushconstruct.com


DESIGN TEAM

OUR SAVIOR LUTHERAN CHURCH ARCHITECT Novak Design Group, PLC Gary M Landhauser AIA P. 319-393-9334 glandhauser@novakdesigngroup.com CIVIL ENGINEER McClure Engineering Loren Rains P. 309-792-9305 l.rains@mcclureengineering.com STRUCTURAL ENGINEER M2B Structural Engineers Lynn Boettcher P. 319-364-0666 lboettcher@m2bengineers.com ELECTRICAL ENGINEER IEFM Marty Valentine P. 309-799-5150 mvalentine@iefmconsultingengineers.co m MECHANICAL ENGINEER IEFM Jeff Newcomb p. 309-799-5150 jnewcomb@iefmconsultingengineers.com


SUBCONTRACTORS + SUPPLIERS OUR SAVIOR LUTHERAN CHURCH B&B MASONRY Masonry

PRIME CONSTRUCTION Gypsum Board & Operable Partitions

CARPETLAND Flooring

RIVER CITY CUTTING & CORING Selective Interior Demolition

COLOR, INC. Painting

SAUDER WORSHIP SEATING Pews

COOPMAN TRUCKING & EXCAVATING Earthwork & Site Utilities

SHAW ELECTRIC Electrical

CRAWFORD HVAC

STERLING COMMERCIAL ROOFING Metal Wall Panels/Roofing/Sheet Metal

CRAWFORD Plumbing

SUBSURFACE CONSTRUCTORS Aggregate Piers

EAST MOLINE GLASS Aluminum Entrances & Storefronts

SUMMIT CONCRETE Building & site concrete

GREENSPACE ASSOCIATES Landscaping

HORIZON GROUP Architectural Woodwork

IRWIN SEATING COMPANY Fixed Seating

MID-STATES CONCRETE INSUSTRIES Precast concrete

INDUSTRIAL STEEL ERECTORS Steel Erection

PELLA WINDOWS Awning/Casement Windows

MCCARTHY IMPROVEMENT Asphalt

VEGTER STEEL Structural Metals


PROJECT ACTIVITY HIGHLIGHTS OUR SAVIOR LUTHERAN CHURCH KEY MILESTONE ACHIEVEMENTS

KEY INSPECTIONS •

• •

Bush Construction, Novak Design Group and all subcontractors/suppliers are successfully using a web-based software called Plan Room for submittal, RFI and meeting minute updates. All structural steel, joists and decking are complete at Area A and B. Outside of a couple minor flashings, all roofing is complete at Area A & B.

Inspections by the City of Bettendorf Building Department will be conducted as necessary to ensure the building construction is being performed to applicable codes. Terracon is and will be conducting testing/inspection procedures on building compaction, concrete, steel welds and bolt connections.

SAFETY QUALITY CONTROL •

Bush Construction is in constant contact with each trade contractor and all third party inspectors to ensure that performed services and materials adhere to the defined set of quality criteria per the project documents.

Foreman meetings are conducted on site weekly with all foreman working on the project. Safety is the first item discussed at these meetings.

Tool Box Talks are conducted weekly by all prime contractors and second tier subcontractors working onsite.

Weekly Safety Inspection by the Superintendent

Number of Lost Time Incidents on this Project – 0

Number of Recordable Incidents on the Project - 0

RECENT ACTIVITY • • • •

• • • •

Area A interior stud walls are installed and a good portion of them are ready for sheet rock. Plumbing and electrical trades are all roughed in inside the stud walls and inspections passed in Area A. Nearly all ductwork is hung in Area A. EIFS at side and back of Area A are ready for color. Front waterproofing and insulation are currently being installed. Area B exterior/bearing block walls are complete. Area B steel joists and deck are complete. Brick work is well over half complete and looking to be done by end of next week at Area B. Concrete floor slabs are currently being poured at Area B with interior block walls due to be installed next.

KEY SCHEDULE MILESTONES • •

Both building additions are projected to be complete by March 2018. The renovation space, planned for summer of 2018, is projected to be complete by September 2018.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

Exterior sheeting at new main entrance.

Metal stud framing, ductwork and plumbing rough-in at Gathering room.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

Exterior sheeting and Tyvek commercial wrap at front of Area A building.

Base coat of EIFS system applied to South side of Area A.


PROJECT PHOTOS

OUR SAVIOR LUTHERAN CHURCH

Exterior brick complete on West side of Area B.

Lisa Piotter coordinated the installation of artificial grass at the playground.