OUR SAVIOR LUTHERAN CHURCH Monthly Project Summary Summary Date: February 2, 2018
Building on a foundation of Integrityâ„¢
TABLE OF CONTENTS
OUR SAVIOR LUTHERAN CHURCH
01
OWNERSHIP TEAM
02
BUSH CONSTRUCTION TEAM
03
DESIGN TEAM
04
CONTRACTORS
05
PROJECT ACTIVITY HIGHLIGHTS
06
PROJECT PHOTOS
OWNERSHIP TEAM | OUR SAVIOR LUTHERAN CHURCH OUR SAVIOR LUTHERAN CHURCH JOHN OVERBEEKE Bettendorf, IA P. 563-424-0019 jobettendorf@gmail.com
HEATHER SCHEUERMANN Parish Administrator P. 563-332-5141 oslcparishadmin@mediacombb.net
BUSH CONSTRUCTION TEAM OUR SAVIOR LUTHERAN CHURCH PROJECT EXECUTIVE A.J. Loss P. 563-344-3793 M. 563-271-6562 Email: ajloss@bushconstruct.com PROJECT MANAGER Ryan Dean P. 563-441-2142 M. 563-594-9267 Email: rdean@bushconstruct.com PROJECT SUPERINTENDENT Gary Swift M. 563-449-2309 Email: gswift@bushconstruct.com SAFETY & QUALITY CONTROL MANAGER Rene del Fabro M. 563-949-5126 Email: rdelfabro@bushconstruct.com PROJECT COORDINATOR Leslie Wells P. 563-344-3780 Email: lwells@bushconstruct.com
DESIGN TEAM
OUR SAVIOR LUTHERAN CHURCH ARCHITECT Novak Design Group, PLC Gary M Landhauser AIA P. 319-393-9334 glandhauser@novakdesigngroup.com CIVIL ENGINEER McClure Engineering Loren Rains P. 309-792-9305 l.rains@mcclureengineering.com STRUCTURAL ENGINEER M2B Structural Engineers Lynn Boettcher P. 319-364-0666 lboettcher@m2bengineers.com ELECTRICAL ENGINEER IEFM Marty Valentine P. 309-799-5150 mvalentine@iefmconsultingengineers.com MECHANICAL ENGINEER IEFM Jeff Newcomb p. 309-799-5150 jnewcomb@iefmconsultingengineers.com
SUBCONTRACTORS + SUPPLIERS OUR SAVIOR LUTHERAN CHURCH B&B MASONRY Masonry
RIVER CITY CUTTING & CORING Selective Interior Demolition
CARPETLAND Flooring
SAUDER WORSHIP SEATING Pews
COLOR, INC. Painting
SHAW ELECTRIC Electrical
COOPMAN TRUCKING & EXCAVATING Earthwork & Site Utilities
STERLING COMMERCIAL ROOFING Metal Wall Panels/Roofing/Sheet Metal
CRAWFORD HVAC
SUBSURFACE CONSTRUCTORS Aggregate Piers
CRAWFORD Plumbing
SUMMIT CONCRETE Building & site concrete
EAST MOLINE GLASS Aluminum Entrances & Storefronts
TAYLOR RIDGE PAVING Asphalt
GREENSPACE ASSOCIATES Landscaping
HORIZON GROUP Architectural Woodwork
IRWIN SEATING COMPANY Fixed Seating
MID-STATES CONCRETE INSUSTRIES Precast concrete
INDUSTRIAL STEEL ERECTORS Steel Erection
PELLA WINDOWS Awning/Casement Windows
PRIME CONSTRUCTION Gypsum Board & Operable Partitions
VEGTER STEEL Structural Metals
PROJECT ACTIVITY HIGHLIGHTS OUR SAVIOR LUTHERAN CHURCH KEY MILESTONE ACHIEVEMENTS
SAFETY •
•
Bush Construction, Novak Design Group and all subcontractors/suppliers are successfully using a web-based software called Plan Room for submittal, RFI and meeting minute updates.
QUALITY CONTROL •
Bush Construction is in constant contact with each trade contractor and all third party inspectors to ensure that performed services and materials adhere to the defined set of quality criteria per the project documents.
•
Foreman meetings are conducted on site weekly with all foreman working on the project. Safety is the first item discussed at these meetings. Tool Box Talks are conducted weekly by all prime contractors and second tier subcontractors working onsite.
•
Weekly Safety Inspection by the Superintendent
•
Number of Lost Time Incidents on this Project – 0
•
Number of Recordable Incidents on the Project - 0
RECENT ACTIVITY • • •
•
• • •
KEY INSPECTIONS •
•
Inspections by the City of Bettendorf Building Department will be conducted as necessary to ensure the building construction is being performed to applicable codes. Terracon is and will be conducting testing/inspection procedures on building compaction, concrete, steel welds and bolt connections.
Overhead inspections by the City of Bettendorf were passed in both Area A & B. Ceiling tiles in both Area A & B are installed. Custom stained doors for both areas were delivered. Bush carpenters have been hanging these doors and installing hardware. The first shipment of casework arrived for both areas. Volunteers from the church have begun installing casework in Area B with Bush focusing on Area A. All flooring materials were delivered. Carpetland is focusing their efforts on installing carpet tile in Area A. Decorative paint was completed on the column capitals in the gathering space with vinyl wall coverings due up next to install. Design for audio visual systems us currently underway with the intent to provide competitive bidding to achieve lowest price.
KEY SCHEDULE MILESTONES • •
Both building additions are projected to be complete by March 2018. The renovation space, planned for early summer of 2018, is projected to be complete by August 2018.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
Woman's 105 C floor tile set.
Bathroom 105 C tile complete partitions complete.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
Classrooms 103 A and 103 B Carpet complete.
Stairs 101 F leading to basement storage.
PROJECT PHOTOS
OUR SAVIOR LUTHERAN CHURCH
Corridor 104 A just finished the carpet.
Room 103 B casework.