CASINO, PERFORMANCE HALL, AND FERRY TERMINAL SANDUSKY, OHIO
SYNTHESIS
ENCLOSURE
HEATING + COOLING
PLUMBING + ELECTRICAL
OCCUPANCY EGRESS COST CONTROL STRUCTURE
BETH MIKON CONSTRUCTION II: LAB WINTER 2009
First Level Plan Second and Third Level Plans Fourth Level Plan
EGRESS
2.01 2.02 2.03 2.04
First Level Plan Second and Third Level Plans Fourth Level Plan Axonometric Diagram
COST CONTROL
3.01 3.02 3.03 3.04 3.05
Casino Cost Estimate Performance Hall Cost Estimate Ferry Terminal Cost Estimate Restaurants Cost Estimate Cost Estimate Summary
STRUCTURE
4.01 4.02 4.03
Plan Axonometric Diagram Section and Details
PLUMBING + ELECTRICAL
5.01 5.02
Plan Axonometric Diagram
HEATING + COOLING
6.01
Plan
ENCLOSURE
7.01
Elevation, Section, and Details
SYNTHESIS
8.01
Reduced Cost Estimate
Student: Beth Mikon Unique Name: bmikon Date of Submission: 04.15.09 LAB Instructor: Steven Christensen
1.01 1.02 1.03
Sandusky Casino, Terminal, and Performance Hall Table of Contents
OCCUPANCY
3
4
10
5
6
First Level 16 32
27
128
Scale: 1’ =1/64” North
7 26
9
64
Student: Beth Mikon Unique Name: bmikon Original Date: 01.14.09 Date Revised: 04.12.09 LAB Instructor: Steven Christensen
2
8 19 18
11
A-1 A-2 A-3 B F-1 M S-1 U 1- HR 2-HR 3-HR
23
16
21
12
25
13
22
24
20
17
14 15
Program/Level Casino 1 Casino 1 Casino 1 Casino 1 Casino 1 Casino 1 Casino 1 Casino 1 Casino 1 Casino 1 Terminal 1 Terminal 1 Terminal 1 Terminal 1 Terminal 1 Terminal 1 Performance 1 Performance 1 Performance 1 Performance 1 Performance 1 Performance 1 Performance 1 Performance 1 Performance 1 Performance 1 Performance 1
Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Room Meeting Spaces 1.0 Meeting Spaces 1.1 Meeting Spaces 1.2 Meeting Spaces 1.3 Meeting Spaces 1.4 Offices Restaurant/Bar 1.0 Restaurant/Bar 1.1 Kitchen 1.0 Gaming Floor 1.0 Immigration Screening Immigration Office Lobby Tickets/Check-in Operation Office Concessions Lobby 1.0 Shop Dressing Area 1.0 Dressing Area 1.1 Office/Lounge 1.0 Office/Lounge 1.1 Rehearsal 1.0 Rehearsal 1.1 Green Room Storage 1.0 Mechanical
Area Title Business Business Business Business Assembly: Unconcentrated Business Assembly: Unconcentrated Assembly: Unconcentrated Assembly Assembly: Gaming Business Business Assembly Business Business Mercantile: Grade Assembly: Concentrated Industrial Business Business Business Business Exercise Exercise Business Accesory Storage Mechanical Equipment
Size (Square Feet) 647 768 682 809 1454 1438 1938 1938 2020 26560 1243 511 3108 573 772 928 2922 4217 772 772 456 351 898 618 579 374 6594
Occupany Type B B B B A-3 B A-2 A-2 A-2 A-3 B B A-3 B B M A-3 F-1 B B B B A-3 A-3 B S-1 U
Factor (SF/occupant) Total # of occupants 7 100 gross 8 100 gross 7 100 gross 9 100 gross 98 15 net 100 gross 15 15 net 130 15 net 130 15 net 135 11 gross 2416 100 gross 13 100 gross 6 7 net 446 100 gross 6 100 gross 8 60 gross 16 5 net 585 100 gross 43 100 gross 8 100 gross 8 100 gross 5 100 gross 4 50 gross 19 50 gross 13 100 gross 6 300 gross 1 300 gross 22 Total Occupancy Level 1
4164 occupants
Sandusky Casino, Terminal, and Performance Hall First Level, 1’ = 1/64”
1
01.01
Student: Beth Mikon Unique Name: bmikon Original Date: 01.14.09 Date Revised: 04.12.09 LAB Instructor: Steven Christensen
41
42
34 39
28 28
29
40 33
36 37 30
38 35
32
Second Level
0
16 32
64
Third Level
128
0
Scale: 1’ =1/64” North
Program/Level Casino 2 Casino 2 Casino 2 Casino 2 Casino 2 Casino 2 Casino2 Performance 2 Performance 2 Performance 2 Performance 2 Performance 2 Performance 2 Performance 2
Number 28 29 30 31 32 33 34 35 36 37 38 39 40 41
16 32
64
Scale: 1’ =1/64” North
Room Meeting Spaces 2.0 Meeting Spaces 2.1 Security and A/V Lounge/Lunchroom Cash Operations/Vault Gaming Floor 2.0 Gaming Floor 2.1 Lobby 2.0 Office Tickets Coats Performance Hall 2.0 Performance Hall 2.1 Storage 2.0
Area Title Size (Square Feet) 3137 Assembly: Unconcentrated 1578 Assembly: Unconcentrated Business 1054 Assembly 941 Business 790 21731 Assembly: Gaming Assembly: Gaming 6511 Assembly: Concentrated 5944 Business 275 Business 574 Business 306 Assembly 5235 Assembly 4169 Accessory Storage 553
Occupany Type A-3 A-3 B A-2 B A-3 A-3 A-3 B B B A-1 A-1 S-1
Factor (SF/occupant) 11 gross 11 gross 100 gross 15 net 100 gross 11 gross 11 gross 5 net 100 gross 100 gross 100 gross 7 net 12 gross 300 gross
Total # of occupants 286 144 11 63 8 1976 592 1189 3 6 4 748 348 2
Total Occupancy Level 2 Program/Level casino 3
Number 42
128
Room Gaming Floor 3.1
Area Title Assembly
Size (Square Feet) 21930
Occupany Type A-3
Factor (SF/occupant) 11 gross
5380 occupants
Total # of occupants 1994
Total Occupancy Level 3
1994 occupants
A-1 A-2 A-3 B F-1 M S-1 U 1- HR 2-HR 3-HR
Sandusky Casino, Terminal, and Performance Hall Second and Third Level, 1’ =1/64”
31
01.02
16 32
46
64
128
Scale: 1’ =1/64” North
44 48 47
Program/Level shopping 4 shopping 4 shopping 4 shopping 4 shopping 4 shopping 4
Number 43 44 45 46 47 48
Total Occupancy Level 1 Total Occupancy Level 2 Total Occupancy Level 3 Total Occupancy Level 4 Total Occupancy
Room Restaurant/Bar 4.0 Restaurant/Bar 4.1 Kitchen 4.0 Kitchen 4.1 Store 4.0 Store 4.1
4164 occupants 5380 occupants 1994 occupants 575 occupants 12113 occupants
A-1 A-2 A-3 B F-1 M S-1 U 1- HR 2-HR 3-HR Area Title Assembly Assembly Assembly Assembly Mercantile Mercantile
Size (Square Feet) 3444 1664 1076 1266 2520 2050
Occupany Type A-2 A-2 A-2 A-2 M M
Factor (SF/occupant) Total # of occupants 15 net 230 15 net 111 15 net 72 15 net 85 60 gross 42 60 gross 35 Total Occupancy Level 4 575 occupants
Sandusky Casino, Terminal, and Performance Hall Fourth Level, 1’ = 1/64”
Fourth Level
43
Student: Beth Mikon Unique Name: bmikon Original Date: 01.14.09 Date Revised: 04.12.09 LAB Instructor: Steven Christensen
45
01.03
3
4
First Level
0 LONGEST PATH OF EGRESS 228’
5
6
41 ’ 7
9
16 32
64
128
Scale: 1’ =1/64” North
10 27
83’
26
8 19 18
11
16
23 21
12
25
13
14
22
24
20
17
15
Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Room Meeting Spaces 1.0 Meeting Spaces 1.1 Meeting Spaces 1.2 Meeting Spaces 1.3 Meeting Spaces 1.4 Offices Restaurant/Bar 1.0 Restaurant/Bar 1.1 Kitchen 1.0 Gaming Floor 1.0 Immigration Screening Immigration Office Lobby Tickets/Check-in Operation Office Concessions Lobby 1.0 Shop Dressing Area 1.0 Dressing Area 1.1 Office/Lounge 1.0 Office/Lounge 1.1 Rehearsal 1.0 Rehearsal 1.1 Green Room Storage 1.0 Mechanical
Occupany Type B B B B A-3 B A-2 A-2 A-2 A-3 B B A-3 B B M A-3 F-1 B B B B A-3 A-3 B S-1 U
Total # of occupants 7 8 7 9 98 15 130 130 135 2416 13 6 446 6 8 16 585 43 8 8 5 4 19 13 6 1 22
Total Occupancy Level 1
PUBLIC WAY
4164
Required Exits 1 1 1 1 2 1 2 2 2 4 1 1 2 1 1 1 3 1 1 1 1 1 1 1 1 1 1
Total Exits
4+
Student: Beth Mikon Unique Name: bmikon Original Date: 01.21.09 Date Revised: 04.04.09 LAB Instructor: Steven Christensen
2
Maximum Travel Distance without sprinklers (ft) with sprinklers (ft) 200 250 200 300 300 400
Sandusky Casino, Terminal, and Performance Hall First Level Egress, 1’ = 1/64”
1
occupancy A,F-1,M,S-1 B U
02.01
Student: Beth Mikon Unique Name: bmikon Original Date: 01.21.09 Date Revised: 04.04.09 LAB Instructor: Steven Christensen
41 LONGEST PATH OF EGRESS 192’
34
42
39 28
29
LONGEST PATH OF EGRESS 191’
40
33 36 37 30
38 35
32
Second Level
0
16 32
Third Level
64
0
128
Number 42
Room Meeting Spaces 2.0 Meeting Spaces 2.1 Security and A/V Lounge/Lunchroom Cash Operations/Vault Gaming Floor 2.0 Gaming Floor 2.1 Lobby 2.0 Office Tickets Coats Performance Hall 2.0 Performance Hall 2.1 Storage 2.0
Room Gaming Floor 3.1
64
128
Scale: 1’ =1/64” North
Scale: 1’ =1/64” North
Number 28 29 30 31 32 33 34 35 36 37 38 39 40 41
16 32
Occupany Type Total # of occupants Required Exits A-3 286 2 A-3 144 2 B 11 1 A-2 63 1 B 8 1 A-3 1976 4 A-3 592 3 A-3 1189 4 B 3 1 B 6 1 B 4 1 A-1 748 3 A-1 348 2 S-1 2 1 Total Exits Total Occupancy Level 2 4+ 5380 Occupany Type A-3 Total Occupancy Level 3
1994 1994
4 Total Exits
4
occupancy A,F-1,M,S-1 B U
Maximum Travel Distance without sprinklers (ft) with sprinklers (ft) 200 250 200 300 300 400
Sandusky Casino, Terminal, and Performance Hall Second and Third Level Egress, 1’ = 1/64”
31
02.02
occupancy A,F-1,M,S-1 B U
Fourth Level
0 43
16 32
Scale: 1’ =1/64” North
46 44 48
64
128
Number 43 44 45 46 47 48
Room Restaurant/Bar 4.0 Restaurant/Bar 4.1 Kitchen 4.0 Kitchen 4.1 Store 4.0 Store 4.1
Maximum Travel Distance without sprinklers (ft) with sprinklers (ft) 200 250 200 300 300 400
Occupany Type A-2 A-2 A-2 A-2 M M
Total # of occupants 230 111 72 85 42 35
Total Occupancy Level 4
575
Required Exits 2 2 2 2 1 1
Total Exits 2
Student: Beth Mikon Unique Name: bmikon Original Date: 01.21.09 Date Revised: 04.04.09 LAB Instructor: Steven Christensen
45
47
Sandusky Casino, Terminal, and Performance Hall Fourth Level Egress, 1’ = 1/64”
LONGEST PATH OF EGRESS 197’
02.04
02.04
Sandusky Casino, Terminal, and Performance Hall Egress Axonometric Diagram
Student: Beth Mikon Unique Name: bmikon Original Date: 01.21.09 Date Revised: 04.12.09 LAB Instructor: Steven Christensen
Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
105396 Union No Year 2009 $146.86 $15,479,000
A Substructure A1010
Standard Foundations
Carpet, padding, add to above, maximum C3030 D Services D1010
D2010 % of Total Cost Per S.F. 4.00% $4.36 $1.66
Cost $459,500 $174,500
A2010 A2020
Excavate and fill, 30,000 SF, 4' deep, sand, gravel, or common earth, on site storage Basement Walls
$2.29 $0.09 $0.33
32.90%
B2010
Steel column, W12, 400 KIPS, 10' unsupported height, 79 PLF Floor, composite concrete slab on fireproofed W beam, 5.5" slab, 25'x25' bay, 24.5" total depth, 125 PSF superimposed load, 200 PSF total Roof Construction Floor, composite slab on steel beam, 25'x25' bay, 4.5"slab, 20.5" total depth, 40 PSF superimposed load, 99 PSF total load Exterior Walls
B2020
Exterior wall, precast concrete, flat, 8" thick, 8' x 8', white face, low rise Exterior Windows
$36.15 $18.23
$241,500 $9,000
$3,810,000 $1,921,500
$10.55
$3,680,625
$180,500
Water cooler, electric, floor mounted, dual height, 14.3 GPH Domestic Water Distribution
$0.16
$16,500
D2040
Gas fired water heater, commercial, 100< F rise, 200 MBH input, 192 GPH Rain Water Drainage
$0.06
$6,500
$18.03
$1,900,500
$2.43
$256,000
$0.54
$56,500
$11.82
$1,245,500
$2.29
$241,000
$0.15
$15,500
$0.00 $0.00 $0.00 $0.00
$0 $0 $0 $0
D3050
Roof drain, CI, soil,single hub, 5" diam, for each additional foot add Terminal & Package Units
D4010
Rooftop, multizone, air conditioner, schools and colleges, 25,000 SF, 95.83 ton Sprinklers
D5010
$3.31
$349,000
(.75)=$261,750
$1.22
$128,500
(.75)=$96,375
Wet pipe sprinkler systems, steel, light hazard, each additional floor, 10,000 SF Electrical Service/Distribution Service installation, includes breakers, metering, 20' conduit & wire, 3 phase, 4 wire, 120/208 V, 600 A Feeder installation 600 V, including RGS conduit and XHHW wire, 600 A
D5020
Switchgear installation, incl switchboard, panels & circuit breaker, 600 A Lighting and Branch Wiring Receptacles incl plate, box, conduit, wire, 8 per 1000 SF, .9 W per SF, with transformer
$40,000
B3010
Door, aluminum & glass, without transom, bronze finish, hardware, 3'-0" x 7'-0" opening Roof Coverings
$2.45
$258,000
Wall switches, 2.0 per 1000 SF
(.75)=$30,000
Miscellaneous power, 1.2 watts Central air conditioning power, 4 watts
Roofing, asphalt flood coat, gravel, base sheet, 3 plies 15# asphalt felt, mopped
Motor installation, three phase, 460 V, 15 HP motor size
Insulation, rigid, roof deck, composite with 2" EPS, 1" perlite
Motor feeder systems, three phase, feed to 200 V 5 HP, 230 V 7.5 HP, 460 V 15 HP, 575 V 20 HP
Roof edges, aluminum, duranodic, .050" thick, 6" face
D5030
Flashing, aluminum, no backing sides, .019" Gravel stop, aluminum, extruded, 4", mill finish, .050" thick Roof Openings
$0.01
$1,500
$24.03 $4.12
$2,533,000 $434,500
C1020
21.90% Partitions Metal partition, 5/8"fire rated gypsum board face, 1/4" sound deadening gypsum board, 2-1/2" @ 24", same opposite face, no insulation Interior Doors
$6.06
$638,500
C2010
Door, single leaf, kd steel frame, hollow metal, commercial quality, flush, 3'-0" x 7'-0" x 1-3/8" Stair Construction
$1.22
$129,000
C3010
Stairs, CIP concrete, w/landing, 20 risers, with nosing Wall Finishes
$2.12
$223,000
2 coats paint on masonry with block filler Painting, interior on plaster and drywall, walls & ceilings, roller work, primer & 2 coats
Carpet, tufted, nylon, roll goods, 12' wide, 36 oz
$1.71
Roof drain, CI, soil,single hub, 5" diam, 10' high
$1,111,500
$0.38
Vinyl wall covering, fabric back, medium weight Floor Finishes
$852,000
Wet pipe sprinkler systems, steel, light hazard, 1 floor, 10,000 SF
Glazing panel, plate glass, 1/4" thick, clear Exterior Doors
C3020
$8.08
D2020
$34,500
B2030
C Interiors C1010
$4,770,500
Lavatory w/trim, vanity top, PE on CI, 19" x 16" oval
Aluminum flush tube frame, for 1/4"glass,1-3/4"x4", 5'x6' opening, no intermediate horizontals
Skylight, plastic domes, insulated curbs, 30 SF to 65 SF, single glazing
$45.26
Urinal, vitreous china, wall hung
Service sink w/trim, PE on CI, corner floor, 28" x 28", w/rim guard
Floor Construction
$443,000
Water closet, vitreous china, tank type, 2 piece close coupled
Changes
Spread footings, 3000 PSI concrete, load 300K, soil bearing capacity 6 KSF, 7' - 6" square x 25" deep
Slab on grade, 4" thick, non industrial, reinforced Basement Excavation
B3020
Hydraulic passenger elevator, 2500 lb., 2 floor, 125 FPM Plumbing Fixtures
Kitchen sink w/trim, countertop, stainless steel, 19" x 18" single bowl
Foundation wall, CIP, 4' wall height, direct chute, .148 CY/LF, 7.2 PLF, 12" thick
41.20%
1 - Moving stairs, escalator type, 10FT ht, 48" width, metal balustrade Elevators and Lifts
Strip footing, concrete, reinforced, load 5.1 KLF, soil bearing capacity 3 KSF, 12" deep x 24" wide Spread footings, 3000 PSI concrete, load 400K, soil bearing capacity 6 KSF, 8' - 6" square x 27" deep Slab on Grade
B1020
Acoustic ceilings, 3/4" fiberglass board, 24" x 48" tile, tee grid, suspended support
$4.20
8 - Hydraulic, passenger elevator, 2000 lb, 2 floors, 100 FPM
A1030
B Shell B1010
Vinyl, composition tile, maximum Ceiling Finishes
Student: Beth Mikon Unique Name: bmikon Original Date: 01.28.09 Date Revised: XXX LAB Instructor: Steven Christensen
Square Foot Cost Estimate Report Casino College, Student Union with Precast Concrete Panel / Steel Frame TOLEDO, OH 2 15
$6.31
$665,000
Fluorescent fixtures recess mounted in ceiling, 3 watt per SF, 60 FC, 15 fixtures @40 watt per 1000 SF Communications and Security Communication and alarm systems, includes outlets, boxes, conduit and wire, sound systems, 12 outlets Communication and alarm systems, fire detection, non-addressable, 25 detectors, includes outlets, boxes, conduit and wire Communication and alarm systems, includes outlets, boxes, conduit and wire, master TV antenna systems, 12 outlets
Internet wiring, 8 data/voice outlets per 1000 S.F. Other Electrical Systems Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire, 277/480 V, 11.5 kW E Equipment & Furnishings 0.00% E1090 Other Equipment F Special Construction 0.00% G Building Sitework 0.00% D5090
SubTotal Contractor Fees (General Conditions,Overhead,Profit) Architectural Fees User Fees Total Building Cost
100% 25.00% 7.00% 0.00%
$109.80 $11,573,000 $27.45 $2,893,500 $9.61 $1,012,500 $0.00 $0 $146.86 $15,479,000 $15,349,625
Sandusky Casino, Terminal, and Performance Hall Casino Cost Estimate
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.):
03.01
Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
49713 Union No Year 2008 Quarter 1 $138.19 $6,870,000
A Substructure A1010
Painting, masonry or concrete, latex, brushwork, addition for block filler C3020
Parameters ar
ecommended by RSMeans.
Standard Foundations
C3030
% of Total Cost Per S.F. 4.40% $4.51 $0.73
Cost $224,000 $36,500
Changes
D Services D1010 D2010
A2010
Slab on grade, 6" thick, non industrial, reinforced Basement Excavation
$0.07
$3,500
A2020
Excavate and fill, 30,000 SF, 4' deep, sand, gravel, or common earth, on site storage Basement Walls
$0.99
$49,000
Floor Construction
31.10%
Steel column, W8, 100 KIPS, 20' unsupported height, 40 PLF Floor, concrete, slab form, open web bar joist @ 2' OC, on bearing wall, 30' span, 24.5" deep, 125 PSF superimposed load, 172 PSF total load Floor, concrete, slab form, open web bar joist @ 2' OC, on bearing wall, 5/8" gypsum board fireproofing on metal furring, add Roof Construction Roof, steel joists, 1.5" 22 ga metal deck, on bearing walls, 30' bay, 23.5" deep, 40 PSF superimposed load, 60 PSF total load Roof, steel joists, 1.5" 22 ga metal deck, on bearing walls, 100' bay, 57.5" deep, 40 PSF superimposed load, 65 PSF total load Roof joist, light gauge, 14 ga Exterior Walls
B2020
Exterior wall, precast concrete, flat, 8" thick, 20' x 10', white face, low rise Exterior Windows
$32.17 $1,599,500 $2.60 $129,500
$4.21
$16.47 $4.42
$1,251,525
D2020
Water cooler, electric, wall hung, wheelchair type, 7.5 GPH Domestic Water Distribution
$0.16
$8,000
D2040
Gas fired water heater, commercial, 100< F rise, 75.5 MBH input, 63 GPH Rain Water Drainage
$0.39
$19,500
Roof drain, DWV PVC, 4" diam, diam, 10' high
$209,500
$819,000 $219,500
$1.69
$84,000
D3050
Roof drain, DWV PVC, 4" diam, for each additional foot add Terminal & Package Units
$11.45
$569,000
D4010
Rooftop, single zone, air conditioner, restaurants, 10,000 SF, 50.00 ton Sprinklers
$2.63
$130,500
D5010
Wet pipe sprinkler systems, steel, light hazard, 1 floor, 10,000 SF Electrical Service/Distribution
$2.23
$111,000
$11.00
$547,000
$3.07
$152,500
$1.17
$58,000
$4.11 $4.11
$204,500 $204,500
$0.00 $0.00
$0 $0
Feeder installation 600 V, including RGS conduit and XHHW wire, 800 A
(.69)=$565,110 (.69)=$151,455
D5020
Switchgear installation, incl switchboard, panels & circuit breaker, 800 A Lighting and Branch Wiring Receptacles incl plate, box, conduit, wire, 8 per 1000 SF, .9 watts per SF Miscellaneous power, 1 watt
(.69)=$57,960
Central air conditioning power, 3 watts Motor installation, three phase, 200 V, 15 HP motor size
$2.60
Motor feeder systems, three phase, feed to 200 V 15 HP, 230 V 15 HP, 460 V 40 HP, 575 V 50 HP
$129,500
Roofing, asphalt flood coat, gravel, base sheet, 3 plies 15# asphalt felt, mopped
D5030
Insulation, rigid, roof deck, composite with 2" EPS, 1" perlite
Fluorescent fixtures recess mounted in ceiling, 3 watt per SF, 60 FC, 15 fixtures @40 watt per 1000 SF Communications and Security Communication and alarm systems, includes outlets, boxes, conduit and wire, sound systems, 30 outlets
Roof edges, aluminum, duranodic, .050" thick, 6" face Flashing, aluminum, no backing sides, .019"
Communication and alarm systems, includes outlets, boxes, conduit and wire, fire detection systems, 25 detectors Other Electrical Systems Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire, 277/480 V, 100 kW E Equipment & Furnishings 4.00% E1090 Other Equipment D5090
Gravel stop, aluminum, extruded, 4", mill finish, .050" thick Roof Openings
$0.17 22.50%
$8,500
$23.24 $1,155,500 $3.22 $160,000
C1020
Concrere block (CMU) partition, light weight, hollow, 6" thick, no finish Interior Doors
$2.06
$102,500
C2010
Door, single leaf, kd steel frame, hollow metal, commercial quality, flush, 3'-0" x 7'-0" x 1-3/8" Stair Construction
$1.77
$88,000
C3010
Stairs, steel, cement filled metal pan & picket rail, 20 risers, with landing Wall Finishes
$3.76
$187,000
Painting, masonry or concrete, latex, brushwork, primer & 2 coats
$199,000
Wall switches, 2.0 per 1000 SF
Door, steel 18 gauge, hollow metal, 2 doors with frame, no label, 6'-0" x 7'-0" opening Roof Coverings
2 coats paint on masonry with block filler
$4.00
Service installation, includes breakers, metering, 20' conduit & wire, 3 phase, 4 wire, 120/208 V, 800 A
Glazing panel, plate glass, 1/4" thick, tempered Exterior Doors
Partitions
Hydraulic passenger elevator, 4500 lb., 2 floor, 125 FPM Plumbing Fixtures
$39.29 $1,953,000 $3.19 $158,500
Shower, stall, fiberglass 1 piece, three walls, 36" square
Door, aluminum & glass, without transom, narrow stile, double door, hardware, 6'-0" x 7'-0" opening
C Interiors C1010
38.00%
Service sink w/trim, PE on CI, corner floor, 28" x 28", w/rim guard
Aluminum flush tube frame, for insulating glass, 2" x 4-1/2", 5'x20' opening,3 intermediate horizontals
Roof hatch, with curb, 1" fiberglass insulation, 2'-6" x 3'-0", aluminum
Elevators and Lifts
Lavatory w/trim, wall hung, PE on CI, 18" x 15"
Roof joist, light gauge, 12 ga B2010
Acoustic ceilings, 3/4" fiberglass board, 24" x 48" tile, tee grid, suspended support
Urinal, vitreous china, stall type $135,000
Foundation wall, CIP, 4' wall height, direct chute, .197 CY/LF, 9.44 PLF, 16" thick
Underlayment, plywood, 5/8" thick Ceiling Finishes
Water closet, vitreous china, bowl only with flush valve, wall hung $2.72
B3020
$173,500
Add for sleepers on concrete, treated, 24" OC, 1"x2" .
A1030
B3010
$3.49
Vinyl tile, maximum
Spread footings, 3000 PSI concrete, load 100K, soil bearing capacity 6 KSF, 4' - 6" square x 15" deep Slab on Grade
B2030
$444,500
Carpet, padding, add to above, maximum
spread footings, 3000 PSI concrete, load 50K, soil bearing capacity 6 KSF, 3' - 0" square x 12" deep
B1020
$8.94
Carpet, tufted, nylon, roll goods, 12' wide, 36 oz
Strip footing, concrete, reinforced, load 6.8 KLF, soil bearing capacity 3 KSF, 12" deep x 32" wide
B Shell B1010
Wall coatings, epoxy coatings, maximum Floor Finishes
Student: Beth Mikon Unique Name: bmikon Original Date: 01.28.09 Date Revised: XXX LAB Instructor: Steven Christensen
Square Foot Cost Estimate Report Auditorium Auditorium with Precast Concrete / Steel Frame TOLEDO, OH 2 24
20 - Sound system, speaker, ceiling or wall 6 - Sound system, amplifier, 250 W 711 - Auditorium chair, fully upholstered, spring seat F Special Construction G Building Sitework SubTotal Contractor Fees (General Conditions,Overhead,Profit) Architectural Fees User Fees Total Building Cost
0.00% 0.00% 100% 25.00% 7.00% 0.00%
$103.32 $5,136,500 $25.83 $1,284,000 $9.04 $449,500 $0.00 $0 $138.19 $6,870,000 $6,522,025
Sandusky Casino, Terminal, and Performance Hall Performance Hall Cost Estimate
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.):
03.02
Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
7492 Union No Year 2009 $152.09 $1,139,500
A Substructure A1010
Standard Foundations
D Services D2010
Plumbing Fixtures
26.00%
$29.56 $3.07
$221,500 $23,000
Water closet, vitreous china, bowl only with flush valve, wall hung Urinal, vitreous china, stall type Lavatory w/trim, wall hung, vitreous china, 18" x 15" Service sink w/trim, PE on CI, corner floor, wall hung w/rim guard, 24" x 20" .
% of Total Cost Per S.F. 12.70% $14.42 $2.74
Cost $108,000 $20,500
spread footings, 3000 PSI concrete, load 25K, soil bearing capacity 3 KSF, 3' - 0" square x 12" deep A1030
spread footings, 3000 PSI concrete, load 50K, soil bearing capacity 3 KSF, 4' - 6" square x 12" deep Slab on Grade
$7.01
$52,500
A2010
Slab on grade, 6" thick, light industrial, reinforced Basement Excavation
$0.27
$2,000
A2020
Excavate and fill, 10,000 SF, 4' deep, sand gravel, or common earth, on site storage Basement Walls
$4.40
$33,000
Foundation wall, CIP, 4' wall height, pumped, .148 CY/LF, 7.2 PLF, 12" thick
B2010
34.20% Roof Construction Floor, steel joists, beams, 1.5" 22 ga metal deck, on columns, 25'x25' bay, 22" deep, 30 PSF superimposed load, 50 PSF total load Floor, steel joists, beams, 1.5" 22 ga metal deck, on columns, 25'x25' bay, 22" deep, 30 PSF superimposed load, 50 PSF total load, add for column Exterior Walls
B2020
$38.91 $10.28
$291,500 $77,000
Water cooler, electric, wall hung, wheelchair type, 7.5 GPH Domestic Water Distribution
$1.20
$9,000
D2040
Electric water heater, commercial, 100< F rise, 50 gallon tank, 9 KW 37 GPH Rain Water Drainage
$0.93
$7,000
Roof drain, DWV PVC, 4" diam, diam, 10' high D3050
Roof drain, DWV PVC, 4" diam, for each additional foot add Terminal & Package Units
$10.28
$77,000
D4010
Rooftop, single zone, air conditioner, banks or libraries, 10,000 SF, 41.67 ton Sprinklers
$3.60
$27,000
D5010
Wet pipe sprinkler systems, steel, ordinary hazard, 1 floor, 10,000 SF Electrical Service/Distribution
$2.74
$20,500
$7.07
$53,000
$0.27
$2,000
$0.40
$3,000
$1.40 $1.40
$10,500 $10,500
$0.00 $0.00
$0 $0
Service installation, includes breakers, metering, 20' conduit & wire, 3 phase, 4 wire, 120/208 V, 400 A Feeder installation 600 V, including RGS conduit and XHHW wire, 400 A D5020
Switchgear installation, incl switchboard, panels & circuit breaker, 400 A Lighting and Branch Wiring Receptacles incl plate, box, conduit, wire, 8 per 1000 SF, .9 watts per SF
$242,450
Miscellaneous power, .8 watts Central air conditioning power, 8 watts
$13.41
$100,500
(.70)=$70,350
Exterior wall, precast concrete, flat, 8" thick, 6' x 18', smooth gray, 2" rigid insulation, low rise Exterior Windows
$6.81
$51,000
(.70)=$35,700
B2030
Glazing panel, plate glass, 3/8" thick, tinted Exterior Doors
$1.60
$12,000
(.70)=$8,400
B3010
Door, aluminum & glass, with transom, narrow stile, double door, hardware, 6'-0" x 10'-0" opening Roof Coverings
$6.81
$51,000
Roofing, asphalt flood coat, gravel, base sheet, 3 plies 15# asphalt felt, mopped
D2020
Changes
Strip footing, concrete, reinforced, load 11.1 KLF, soil bearing capacity 6 KSF, 12" deep x 24" wide
B Shell B1020
Acoustic ceilings, 3/4"mineral fiber, 12" x 12" tile, concealed 2" bar & channel grid, suspended support
Fluorescent fixtures recess mounted in ceiling, 1 watt per SF, 20 FC, 5 fixtures @40 watts per 1000 SF Communications and Security Communication and alarm systems, fire detection, non-addressable, 25 detectors, includes outlets, boxes, conduit and wire D5090 Other Electrical Systems Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire, 277/480 V, 7.5 kW E Equipment & Furnishings 1.20% E1090 Other Equipment D5030
1 - Turnstiles, economy, electric, 1-way, 4 arm, 46" dia 1 - Parking equipment, ticket spitter with time/date stamp, standard 1 - Directory boards, plastic, glass covered, 30" x 20" F Special Construction G Building Sitework
Insulation, rigid, roof deck, composite with 2" EPS, 1" perlite Roof edges, aluminum, duranodic, .050" thick, 6" face
0.00% 0.00%
Flashing, aluminum, no backing sides, .019" C Interiors C1010
Gravel stop, aluminum, extruded, 4", mill finish, .050" thick Partitions
25.90%
$29.43 $6.21
$220,500 $46,500
C1020
Concrere block (CMU) partition, light weight, hollow, 8" thick, no finish Interior Doors
$5.67
$42,500
C3010
Door, single leaf, kd steel frame, hollow metal, commercial quality, flush, 3'-0" x 7'-0" x 1-3/8" Wall Finishes
$2.40
$18,000
$8.81
$66,000
$6.34
$47,500
Glazed coating Wall coatings, acrylic glazed coatings, minimum C3020
Wall coatings, acrylic glazed coatings, maximum Floor Finishes Vinyl, composition tile, minimum Vinyl, composition tile, maximum Tile, quarry tile, mud set, minimum
C3030
Tile, quarry tile, mud set, maximum Ceiling Finishes
Student: Beth Mikon Unique Name: bmikon Original Date: 01.28.09 Date Revised: XXX LAB Instructor: Steven Christensen
Square Foot Cost Estimate Report Terminal Bus Terminal with Precast Concrete Panels / Steel Frame TOLEDO, OH 1 14
SubTotal Contractor Fees (General Conditions,Overhead,Profit) Architectural Fees User Fees Total Building Cost
100% 25.00% 7.00% 0.00%
$113.72 $852,000 $28.43 $213,000 $9.94 $74,500 $0.00 $0 $152.09 $1,139,500 $1,090,450
Sandusky Casino, Terminal, and Performance Hall Ferry Terminal Cost Estimate
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.):
03.03
16182 Union No Year 2008 Quarter 1 $141.27 $2,286,000
A Substructure A1010
Standard Foundations
Urinal, vitreous china, wall hung Lavatory w/trim, vanity top, PE on CI, 20" x 18" Kitchen sink w/trim, countertop, stainless steel, 44" x 22" triple bowl Service sink w/trim, PE on CI, corner floor, wall hung w/rim guard, 24" x 20" Shower, stall, baked enamel, terrazzo receptor, 36" square
.
% of Total Cost Per S.F. 6.80% $7.14 $0.90
Cost $115,500 $14,500
Changes
D2020
Water cooler, elec, floor mounted, refrigerated compartment type, 1.5 GPH Domestic Water Distribution
$1.70
$27,500
D2040
Gas fired water heater, commercial, 100< F rise, 500 MBH input, 480 GPH Rain Water Drainage
$0.83
$13,500
Roof drain, CI, soil,single hub, 3" diam, 10' high Roof drain, CI, soil,single hub, 3" diam, for each additional foot add
Strip footing, concrete, reinforced, load 11.1 KLF, soil bearing capacity 6 KSF, 12" deep x 24" wide
Roof drain, CI, soil,single hub, 4" diam, 10' high
A1030
spread footings, 3000 PSI concrete, load 25K, soil bearing capacity 3 KSF, 3' - 0" square x 12" deep Slab on Grade
A2010
Slab on grade, 4" thick, non industrial, reinforced Basement Excavation
$0.46
$7,500
A2020
Excavate and fill, 4000 SF, 4' deep, sand, gravel, or common earth, on site storage Basement Walls
$1.27
$20,500
B Shell B1020
$4.51
Foundation wall, CIP, 4' wall height, direct chute, .148 CY/LF, 7.2 PLF, 12" thick
B2010
17.70% Roof Construction Roof, steel joists, 1.5" 22 ga metal deck, on bearing walls, 35' bay, 25.5" deep, 40 PSF superimposed load, 60 PSF total load Exterior Walls
B2020
Brick wall, composite double wythe, standard face/CMU back-up, 8" thick, perlite core fill Exterior Windows
$73,000
$18.66 $4.23
$302,000 $68,500
$4.63
$75,000
(.94)=$70,500
$3.83
$62,000
(.94)=$58,280
D3050
Roof drain, CI, soil,single hub, 4" diam, for each additional foot add Terminal & Package Units
$31.58
$511,000
D4010
Rooftop, multizone, air conditioner, restaurants, 3,000 SF, 15.00 ton Sprinklers
$2.63
$42,500
D5010
Wet pipe sprinkler systems, steel, light hazard, 1 floor, 10,000 SF Electrical Service/Distribution
$1.24
$20,000
$9.36
$151,500
$0.53
$8,500
$0.31
$5,000
$7.01 $7.01
$113,500 $113,500
$0.00 $0.00
$0 $0
Service installation, includes breakers, metering, 20' conduit & wire, 3 phase, 4 wire, 120/208 V, 400 A
$289,490
Feeder installation 600 V, including RGS conduit and XHHW wire, 400 A D5020
B2030
Miscellaneous power, 1.8 watts Central air conditioning power, 6 watts
$4.42
$71,500
Door, aluminum & glass, without transom, full vision, double door, hardware, 6'-0" x 7'-0" opening Door, aluminum & glass, with transom, non-standard, double door, hardware, 6'-0" x 10'-0" opening B3010
Door, steel 18 gauge, hollow metal, 1 door with frame, no label, 3'-0" x 7'-0" opening Roof Coverings
$1.51
$24,500
$0.03
$500
$17.92 $2.19
$290,000 $35,500
Insulation, rigid, roof deck, fiberglass, 3'x4' or 4'x8' sheets, 15/16" thick, R3.70 Gutters, box, aluminum, .027" thick, 5", enameled finish B3020 C Interiors C1010
Downspout, aluminum, rectangular, 2" x 3", embossed mill finish, .020" thick Roof Openings Skylight, plastic domes, insulated curbs, nominal size to 10 SF, double glazing
17.00%
Partitions Wood partition, 5/8"fire rated gypsum board face, none base,2 x 4,@ 16" OC framing,same opposite face, 0 insul
C1020
$1.85
$30,000
C1030
Door, single leaf, wood frame, 3'-0" x 7'-0" x 1-3/8", birch, hollow core Fittings
$0.68
$11,000
C3010
Toilet partitions, cubicles, ceiling hung, plastic laminate Wall Finishes
$0.96
$15,500
Painting, interior on plaster and drywall, walls & ceilings, roller work, primer & 2 coats Ceramic tile, thin set, 4-1/4" x 4-1/4" Floor Finishes
$6.40
$103,500
$5.84
$94,500
$54.88 $6.70
$888,000 $108,500
Tile, quarry tile, mud set, minimum Tile, quarry tile, mud set, maximum Ceiling Finishes
D Services D2010
Acoustic ceilings, 3/4"mineral fiber, 12" x 12" tile, concealed 2" bar & channel grid, suspended support 52.00% Plumbing Fixtures
Fluorescent fixtures recess mounted in ceiling, 2 watt per SF, 40 FC, 10 fixtures @40 watt per 1000 SF Communications and Security Communication and alarm systems, includes outlets, boxes, conduit and wire, fire detection systems, 25 detectors D5090 Other Electrical Systems Generator sets, w/battery, charger, muffler and transfer switch, gas/gasoline operated, 3 phase, 4 wire, 277/480 V, 15 kW E Equipment & Furnishings 6.60% E1090 Other Equipment 3 - Refrigeration Rooms, prefab walk-in, aluminum, 6' x 6' O.D. nominal, 7' 6" h, incl. doors & floors, excl. partitions or refrigeration D5030
6 - Range, commercial kitchen equipment, restaurant type, 6 burners & 1 standard oven, 36" wide 3 - Ice cube maker, commercial kitchen equipment, 50 lbs per day 3 - Freezers, commercial kitchen equipment, reach-in, 44 C.F. 3 - Food warmer, commercial kitchen equipment, counter, 1.2KW 3 - Cooler, commercial kitchen equipment, reach-in, beverage, 6' long 3 - Coffee urn, commercial kitchen equipment, twin, 6 gallon 3 - Broiler, commercial kitchen equipment, without oven, standard 20 - Booths, banquet booths, upholstered seat & back, "L" or "U" shape, minimum 80 - Booths, banquet booths, upholstered seat & back, straight, minimum 4 - Restaurant furniture, bar, built-in, back bar
Carpet tile, nylon, fusion bonded, 18" x 18" or 24" x 24", 35 oz
C3030
(.94)=$67,210
3 - Dishwasher, commercial kitchen equipment, 10 to 12 racks per hour
5/8" gypsum board, taped & finished, painted on metal furring Interior Doors
C3020
Switchgear installation, incl switchboard, panels & circuit breaker, 400 A Lighting and Branch Wiring Receptacles incl plate, box, conduit, wire, 10 per 1000 SF, 1.2 watts per SF
Aluminum flush tube frame, for 1/4"glass,1-3/4"x4", 5'x6' opening, no intermediate horizontals Glazing panel, plate glass, 1/4" thick, tempered Exterior Doors
Student: Beth Mikon Unique Name: bmikon Original Date: 01.28.09 Date Revised: XXX LAB Instructor: Steven Christensen
Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
Water closet, vitreous china, tank type, 2 piece close coupled
4 - Restaurant furniture, bar, built-in, front bar F Special Construction G Building Sitework SubTotal Contractor Fees (General Conditions,Overhead,Profit) Architectural Fees User Fees Total Building Cost
0.00% 0.00% 100% 25.00% 7.00% 0.00%
$105.61 $1,709,000 $26.42 $427,500 $9.24 $149,500 $0.00 $0 $141.27 $2,286,000 $2,273,490
Sandusky Casino, Terminal, and Performance Hall Restaurants Cost Estimate
Building Type: Location: Story Count: Story Height (L.F.):
Square Foot Cost Estimate Report Restaurants Restaurant with Face Brick with Concrete Block Back-up / Steel Joists TOLEDO, OH 1 12
Estimate Name:
03.04
Restaurants Restaurant with Face Brick with Concrete Block Back-up / Steel Joists TOLEDO, OH 1 12 16182 Union No Year 2008 Quarter 1 $141.27 $2,273,490
Building Type: Location: Floor Area (S.F.): Cost Per Square Foot: Building Cost:
Total Casino, Terminal, and Performance Hall SANDUSKY, OH 178783 $141.15 $25,235,590
Student: Beth Mikon Unique Name: bmikon Original Date: 01.28.09 Date Revised: XXX LAB Instructor: Steven Christensen
Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
F. Contractor Fees
B. Shell
rnishings
E. Equipment and Fu
C. Interiors D. Services
Sandusky Casino, Terminal, and Performance Hall Cost Estimate Summary
Terminal Bus Terminal with Precast Concrete Panels / Steel Frame TOLEDO, OH 1 14 7492 Union No Year 2009 $152.09 $1,090,450
cture
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
A. Substru
Performance Hall Auditorium with Precast Concrete / Steel Frame TOLEDO, OH 2 24 49713 Union No Year 2008 Quarter 1 $138.19 $6,522,025
$907,000 $5,561,340 $4,199,000 $7,833,000 $328,500 $4,818,000 $1,686,000
ees
Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
Breakdown A. Substructure B. Shell C. Interiors D. Services E. Equipment and Furnishings F. Contractor Fees G. Architectural Fees
ctural F
Casino College, Student Union with Precast Concrete Panel / Steel Frame TOLEDO, OH 2 15 105396 Union No Year 2009 $146.86 $15,349,625
ite G. Arch
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
03.04
bay: 28’-10” by 36’-7“ (1 x 1.26) column: 10” x 6“ (taller than 12’, tributary area from second floor and roof: 2100 SF) girder: 28‘-10” span, 18“ depth beam: 36’-7” span, 22” depth
column girder beam vierendeel truss shear wall
SITE-CAST CONCRETE
First Level
0
16 32
64
128
Scale: 1’ =1/64” North
STEEL STRUCTURAL SYSTEMS
* * * *
pros lightweight members precise and quick construction can support multiple cladding systems framing system can be used in comubstible and noncombustible construction reliance on on-site fabrication makes this sytem a good choice for irregular form tubes and pipes are more resistant to buckling forces and can be employed as columns in long-span steel structures steel floor decking can span 6-15 FT composite construction possible to reduce cost
cons fire-resistive assemblies or coatings could have significant impoact on the architectural use some form of wall board or panel material needed to stabilize slender members against buckling beam orientation can be determined by cells in the decking due to electrical/communication wiriring distribution
* most important considerations for choosing a steel framing system
pros can achieve variety of span and load-carrying capacity posttensioning can be employed to increase span and reduce depth inherent fire-resistive qualities allow system to be partially exposed in a finished building monolithic and plastic qualities give concrete unique architectural potential easy integration of building mechanical and electrical services into exposed structure higher strength concrete and greater amounts of reinforcing can be used to maintain columns of more practical size sitecast concrete columns may be used in both combustible and noncombustible construction concrete walls can be used for construction below grade, building structural cores, and shear walls in steel or concrete frame construction sitecast concrete walls can be used as shear walls to help stabilize buildings against wind and seismic forces walls can meet fire-resistance requirements without coating desirable for multiple dwelling building types such as apartments or hotels
cons extensive use of posttensioning may limit ease with which structure can be modified added cos tand difficulty of achieving acceptable levels of finish quality and dimensional accuracy with exposed concrete increased quanity and weight of material must be used for taller buldings or longer spans columns sizes should remain consistent more material needed for taller structures and heavier loads column bays are most eficient when they are square or close to square
Student: Beth Mikon Unique Name: bmikon Original Date: 01.21.09 Date Revised: 04.13.09 LAB Instructor: Steven Christensen
beam
r girde
Sandusky Casino, Terminal, and Performance Hall Framing Plan, First Level, 1’ = 1/64”
deck:14’-5” x 18‘-3” sheets perpendicular to beams
04.01
Sandusky Casino, Terminal, and Performance Hall Structure Axonometric Diagram
column girder beam vierendeel truss shear wall forces
04.02
Student: Beth Mikon Unique Name: bmikon Original Date: 02.11.09 Date Revised: 04.13.09 LAB Instructor: Steven Christensen
5” concrete slab on 2” steel deck
18” girder 22” beam
10” by 6” column
18” girder 22” beam
10” by 6” column
concrete slab on grade
Student: Beth Mikon Unique Name: bmikon Original Date: 02.18.09 Date Revised: 04.13.09 LAB Instructor: Steven Christensen
steel column W8
Sandusky Casino, Terminal, and Performance Hall Section 1’ = 1/32”, Details 1’ = 1/4”
enclosure
04.03
16 32
64
128
Scale: 1’ =1/64” North
54”
60”
mechanical transformer vaults and switchgear room fire pumps
5000 SF 900 SF 240 SF
required SF 6140 SF actual SF 6594 SF
60”
Total # of occupants 7 8 7 9 98 15 130 130 135 2416 13 6 446 6 8 16 585 43 8 8 5 4 19 13 6 1 22 286 144 11 63 8 1976 592 1189 3 6 4 748 348 2 1994 230 111 72 85 42 35 Total
Male Water Closets 1.000 1.000 1.000 1.000 0.784 1.000 1.733 1.733 1.800 19.328 1.000 1.000 0.892 1.000 1.000 0.032 1.170 0.430 1.000 1.000 1.000 1.000 0.152 0.104 1.000 0.010 0.000 2.288 1.152 1.000 0.840 1.000 15.808 4.736 9.512 1.000 1.000 1.000 5.984 2.784 0.020 15.952 3.067 1.480 0.960 1.133 0.084 0.070 113.039
Female Water Closets 1.000 1.000 1.000 1.000 1.508 1.000 1.733 1.733 1.800 37.169 1.000 1.000 0.892 1.000 1.000 0.032 1.170 0.430 1.000 1.000 1.000 1.000 0.292 0.200 1.000 0.010 0.000 4.400 2.215 1.000 0.840 1.000 30.400 9.108 18.292 1.000 1.000 1.000 11.508 5.354 0.020 3.538 3.067 1.480 0.960 1.133 0.084 0.070 158.439
electrical room women’s bathroom men’s bathroom
30” 48”
Student: Beth Mikon Unique Name: bmikon Original Date: 03.04.09 Date Revised: 04.13.09 LAB Instructor: Steven Christensen
Room Occupany Type Meeting Spaces 1.0 B Meeting Spaces 1.1 B Meeting Spaces 1.2 B Meeting Spaces 1.3 B Meeting Spaces 1.4 A-3 Offices B Restaurant/Bar 1.0 A-2 Restaurant/Bar 1.1 A-2 Kitchen 1.0 A-2 Gaming Floor 1.0 A-3 Immigration Screening B Immigration Office B Lobby A-3 Tickets/Check-in B Operation Office B Concessions M Lobby 1.0 A-3 Shop F-1 Dressing Area 1.0 B Dressing Area 1.1 B Office/Lounge 1.0 B Office/Lounge 1.1 B Rehearsal 1.0 A-3 Rehearsal 1.1 A-3 Green Room B Storage 1.0 S-1 Mechanical U Meeting Spaces 2.0 A-3 Meeting Spaces 2.1 A-3 Security and A/V B Lounge/Lunchroom A-2 Cash Operations/Vault B Gaming Floor 2.0 A-3 Gaming Floor 2.1 A-3 Lobby 2.0 A-3 Office B Tickets B Coats B Performance Hall 2.0 A-1 Performance Hall 2.1 A-1 Storage 2.0 S-1 Gaming Floor 3.1 A-3 Restaurant/Bar 4.0 A-2 Restaurant/Bar 4.1 A-2 Kitchen 4.0 A-2 Kitchen 4.1 A-2 Store 4.0 M Store 4.1 M
Sandusky Casino, Terminal, and Performance Hall Plumbing/ Electrical, First Level, 1’ = 1/64”
First Level
Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
05.01
Sandusky Casino, Terminal, and Performance Hall Plumbing/Electrical Axonometric Diagram
womenâ&#x20AC;&#x2122;s bathroom menâ&#x20AC;&#x2122;s bathroom mechanical + electrical rooms
05.02
Student: Beth Mikon Unique Name: bmikon Original Date: 03.04.09 Date Revised: 04.12.09 LAB Instructor: Steven Christensen
16 32
64
Scale: 1’ =1/64” North
vertical chase supply return structure
128
VARIABLE AIR VOLUME pr os mi nim ize ope ra ting cost ma xim ize control of ai r veloc ity and ai r qual ity ma xim ize ind ividua l con trol over tem pe ra tu re mi nim ize sys tem noise mi nim ize visual ob trusivene ss ma xim ize flexibility of rental spa ce mi nim ize sys tem ma inten an ce econ omical to operat e virtua lly self-balancing con s first cost expensive requ ire s lo ts of floor sp ac e requ ire s l arge floor to f loor heig ht do es no t ma xim ize speed of construction lim ited in the ran ge of hea ting or co oling de ma nd that m ay be accomm oda ted w ith a sin gl e syst em
MAJOR COMPONENTS boi lers an d chim ne y chilled wa ter pla nt cooling to w er fan room outd oor fresh air an d exha ust louvers vertica l supp ly an d return ducts ho rizo ntal supp ly an d return ducts VA V cont rol box for ea ch zone supp ly diffuser s retur n grilles
SIZING cooling cap acit y: 700 t ons 2 tot al s p ace f or boile r r oo m and ch illed w at er pla nt : 5,000 ft 2 sp ace f or c ooling tow ers : 900 ft cooling a ir volum e: 300 ,000 CFM 2 area o f m ain sup ply o r return du ct s: 175 f t 2 area o f b ran ch suppl y or ret ur n d uc ts : 300 f t 2 area o f fa n r ooms : 300 ft 2 area o f fresh a ir l ouvers : 600 ft 2 area o f exh aust a ir l ouvers : 600 ft
Student: Beth Mikon Unique Name: bmikon Original Date: 04.13.09 Date Revised: 04.13.09 LAB Instructor: Steven Christensen
First Level
Audi to riu m, The at er : Va riab le Air Volum e (VAV) Sin gle D uct C onstant Air Volume (C AV) Mul tizo ne Arena s, Exh ibit ion Ha lls: VAV CAV , Fan -Coil ter min als Office s: VA V, V AV ind uc tion Mul tizo ne Air Wa te r Ind uc tion (infrequently us ed) Hy dronic conve ctor s (for hea ting onl y)
Sandusky Casino, Terminal, and Performance Hall Heating and Cooling, First Level, 1’ = 1/64”
GENERAL NOTES
06.01
window
operable louver louver substructure
clip steel panels gympsum board panel substructure Elevation and Section, 1’ =1/8”
moisture barrier Section Details, 1’ =1/2”
rain 1-2” gap
4”
Moisture Detail, 1’ =1/4”
prevents moisture intrusion through porous exterior cladding, air cavity, drainage layer, and air-tight structure
operable steel panles control heat gain serving as shading devices
Solar/Thermal Detail, 1’ =1/2”
Student: Beth Mikon Unique Name: bmikon Original Date: 04.01.09 Date Revised: 04.13.09 LAB Instructor: Steven Christensen
batt insulation
Sandusky Casino, Terminal, and Performance Hall Enclosure: Elevation,Section, and Details
5/8” exterior sheathing
07.01
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
Performance Hall Auditorium with Precast Concrete / Concrete Frame TOLEDO, OH 2 20 43177 Union No Year 2008 Quarter 1 $121.00 $5,224,417
Strategy Reduce story height by 4' throughout Eliminated Performance Hall 2.0 to reduce SF by 1.15% (6536 SF) Savings $1,297,608
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
Terminal Bus Terminal with Precast Concrete Panels / Concrete Frame TOLEDO, OH 1 14 7492 Union No Year 2009 $141.00 $1,056,372
Strategy Concrete Frame and Cheaper Finsihes (-$11/SF) Savings $34,078
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
Restaurants Restaurant with Face Brick with Concrete Block Back-up / Steel Joists TOLEDO, OH 1 12 16182 Union No Year 2008 Quarter 1 $130.00 $2,103,660
Strategy Cheaper Finishes (-11/SF) Savings $169,830
Estimate Name: Building Type: Location: Floor Area (S.F.): Cost Per Square Foot: Building Cost:
Total Casino, Terminal, and Performance Hall SANDUSKY, OH 165931 $122.18 $20,274,049
Total Savings $4,961,541 (approximately 20%)
Strategy Reduce SF by 1.06% (6316 SF) * Replace steel frame with concrete frame (-$11/SF) Savings $3,460,025
*concrete frame would require reduced cantilevers
Student: Beth Mikon Unique Name: bmikon Original Date: 04.07.09 Date Revised: XXX LAB Instructor: Steven Christensen
Casino College, Student Union with Precast Concrete Panel / Concrete Frame TOLEDO, OH 2 15 99080 Union No Year 2008 Quarter 1 $120.00 $11,889,600
Sandusky Casino, Terminal, and Performance Hall Reduced Cost Estimate
Estimate Name: Building Type: Location: Story Count: Story Height (L.F.): Floor Area (S.F.): Labor Type: Basement Included: Data Release: Cost Per Square Foot: Building Cost:
08.01