Expansion and rehabilitation of water and waste water infrastructure, Mureş County Cecilia Urzică – Project Manager Project Implementation Unit S.C. AQUASERV S.A. Company,Tîrgu-Mureş

Forumul Romanesc al Apei - 2012


Project location: MureĹ&#x; County and Cristuru Secuiesc town in Harghita County Beneficiary population: approximately 300.000 inhabitants Execution period: 08.04.2011 – 31.12.2015 Estimate value of predicted investments in the Master Plan: approximately 1,2 Billion Euro Value of project for which the application was made: 110.875.965 Euro 467.065.003 Lei

Forumul Romanesc al Apei - 2012


Forumul Romanesc al Apei - 2012


Main parts of the project (1): Rehabilitation of waste water treatment works in the towns: Sighişoara şi Cristuru Secuiesc; output 162,3 l/ s respectively 59,7 l/ s - value 6.377.157 Euro Rehabilitation of waste water treatment works in the town Târnăveni; output 130 l/ s – value 4.365.826 Euro Rehabilitation of waste water treatment works in Luduş şi Iernut; output 77 l/ s respectively 46, 5 l/ s – value 5.168.944 Euro Execution of water treatment works in the town of Miercurea Nirajului output 38,2 l/ s – value 1.528.272 Euro Forumul Romanesc al Apei - 2012


Main parts of the project (2): Expansion of water networks in the town of Tîrgu-Mureş, length 10,4 km, rehabilitation of 34,4 km - value 8.274.319 Euro Expansion of water networks in the town of Sighişoara, length 5,2 km, rehabilitation of penstock 5,2 km - value 2.882.513 Euro Expansion of water networks in the town of Luduş, length of 8,7 km value 1.278.705 Euro Expansion of water networks in the town of Iernut, length 3,8 km value 669.052 Euro Forumul Romanesc al Apei - 2012


Main parts of the project (2): Rehabilitation of the Voiniceni-Sărmaş penstock, length 46 km value 10.004.778 Euro Execution of Valea Nirajului penstock, length 33 km - value 4.587.446 Euro Execution of Band-Pănet penstock, length 19,3 km – value

2.826.788 Euro

Forumul Romanesc al Apei - 2012


Main parts of the project (3): Rehabilitation of waste water treatment works in the town of Cristeşti (Tîrgu-Mureş): Daily Q medium output = 1200 l/ s; sludge line Estimated value: 6.725.374 Euro, Contracted value: 28.006.726 Lei

Rehabilitation of waste water treatment works in the town of Reghin: Daily Q medium output = 107 l/s; Steps: mechanical, biological, tertiary Estimated value: 5.756.361 Euro, Contracted value: 22.978.101 Lei

Forumul Romanesc al Apei - 2012


Main parts of the project (4): Rehabilitation of waste water treatment works in the town of Târnăveni: Daily medium Q output = 62,5 l/s, steps: mechanical, biological, tertiary Estimated value: 5.173.032 Euro Rehabilitation of waste water treatment works in the town of Iernut: Daily medium Q output = 13,5 l/ s, steps: mechanical, biological Estimated value: 2.492.370 Euro Execution of waste water treatment works in the town of Luduş: Daily medium Q output = 33 l/ s, steps: mechanical, biological, tertiary Estimated value: 5.935.408 Euro Forumul Romanesc al Apei - 2012


Current stage (1): Until this date the following contracts have been tendered: MS-TM-Yb-01 Tîrgu-Mureş – Rehabilitation of waste water treatment plants – sludge line, awarded to the joint-venture Sociedad Anonima de Orbas y Servicios, Copasa – AIN Active S.L.- S.C. Lasprom S.R.L. MS-RG-YB-02 Reghin – Rehabilitation and expansion third stage for the waste water treatment plant, awarded to Passavant Roediger GmbH MS-SG&CS-YB-04 Sighişoara and Cristuru Secuiesc – Rehabilitation of waste water treatment plants : in tender MS-TA-YB-05 Târnăveni – Rehabilitation of waste water treatment plant: in tender Forumul Romanesc al Apei - 2012


Current stage (2): Until this date the following contracts have been tendered: MS-L&I-YB-06 Luduş şi Iernut – Rehabilitation of waste water treatment plants, published on SEAP, in tender MS-TA-YB-07 Târnăveni – Rehabilitation of waste water treatment plant, the awarding procedure Report was developed and forwarded MS-L&I-YB-08 Luduş – Execution of waste water treatment plant Iernut – Rehabilitation of waste water treatment plant, AQUASERV S.A. Company acted in the Court of Appeal - 3 appeals were forwarded before CNSC (by the same objector, ranking second in the tender), and following the last CNSC decision, the beneficiary decided to attack in the Court of Appeal.

Forumul Romanesc al Apei - 2012


Contracts under the project planned to be tendered by the end of the contract (1): MS-Ser-02 Provision Audit Medium POS, envisaged date: July 2012 MS-MN-YB-03 Miercurea Nirajului – Catchment and waste water treatment plant, envisaged dat: Sept 2012 MS-VS-RB-01 Voiniceni-Sărmaş Penstock – Rehabilitation of the penstock pipeline, pumping stations and blue water tanks, envisaged date: July 2012 MS-TM-RB-02 Tîrgu Mureş – rehabilitation/extension of blue water supply system and sewage system, blue water pumping stations, waste water pumping stations and discharge pipes, SCADA system, envisaged date: July 2012

Forumul Romanesc al Apei - 2012


Contracts under the project planned to be tendered by the end of the contract(2): MS-SG&CS-RB-03 Sighişoara şi Cristuru Secuiesc – Rehabilitation of the penstock pipeline, extension of blue water networks and sewage, pumping stations for blue water, pumping stations for waste water and discharge pipes, envisaged date: July 2012 MS-B&P-RB-04 Band-Pănet Penstock– Execution of penstock pipeline, blue water pumping stations, blue water tank Pănet, envisaged date: Sept 2012 MS-RG-RB-05 Reghin – Extension of the sewage network, waste water pumping stations and discharge pipes, envisaged date: August 2012 Forumul Romanesc al Apei - 2012


Contracts under the project planned to be tendered by the end of the contract(3): MS-VN-RB-06 Valea Nirajului – Penstock pipeline, envisaged date: August 2012 MS-TA-RB-07 Târnăveni – Extension of the sewage network, waste water pumping stations and discharge pipes, envisaged date: Sept 2012 MS-L&I-RB-08 Luduş/Iernut – Extension of blue water supply systems and sewage systems, blue water pumping stations, waste water pumping stations and discharge pipes, envisaged date: August 2012 Forumul Romanesc al Apei - 2012


Contracts under the project planned to be tendered by the end of the contract(3): MS-VN-RB-06 Valea Nirajului - Penstock pipeline, envisaged date: August 2012 MS-TA-RB-07 Târnăveni – Extension of the sewage network, waste water pumping stations and discharge pipes, envisaged date: Sept 2012 MS-L&I-RB-08 Luduş/Iernut – Extension of blue water supply systems and sewage systems, blue water pumping stations, waste water pumping stations and discharge pipes, envisaged date: August 2012

Forumul Romanesc al Apei - 2012


For more information, please contact us! S.C. AQUASERV S.A. Company Tîrgu-Mureş, No.1, Koos Karoly Street Head of Project Implementation Unit, Törzsök Sándor Telephone: 0265 208 809 Fax: 0265 208 862 E-mail: storzsok@aquaserv.ro

Thank you for your attention! Forumul Romanesc al Apei - 2012