SOPenv We invest in the environment. We invest in the future
MINISTRY OF ENVIRONMENT AND FORESTRY OI SOP ENVIRONMENT CLUJ NAPOCA REGION 6 NORTH-WEST
SECTORAL OPERATIONAL PROGRAMME “ENVIRONMENT” 2007 - 2013 THE EXTENSION AND REHABILITATION OF DRINKING/WASTE WATER INFRASTRUCTURE
Cluj Napoca - 23 october 2012
SOP ENV- PRIORITY AXES Overall objective of SOP Environment – protect and improve the environment and living standards in Romania, focusing in particular on meeting the environmental acquis.
Specific objective 1
Specific objective 2
Specific objective 3
Improve the quality and access to water and wastewater infrastructure
Development of sustainable waste management systems
Reduction of negative environmental impact caused by urban heating plants
Priority axis 1
Priority axis 2 Development of integrated waste management systems and rehabilitation of historically contaminated sites
Priority axis 3
Priority axis 4
Priority axis 5
Rehabilitation of urban heating systems towards energy efficiency targets
Implementation of adequate management systems for nature protection
Implementation of adequate infrastructure for natural risk prevention
ca 934 millions Euro (FEDR)
ca 229 millions Euro (FC)
ca 172 millions Euro (FEDR)
ca 270 millions Euro (FC)
Extension and modernization of water and wastewater systems
ca 2776 millions Euro (FC)
Priority axis 6
Technical Assistance ca 130 millions Euro (FEDR)
Specific objective 4
Specific objective 5
Protection and improvement Reduction of the incidence of biodiversity and of natural disasters natural heritage affecting the population
Financial plan SOP ENV Axes
Fund
UE contribution Mil. Euro
Priority axis 1
FC
2.776
490
3266
85%
Priority axis 2
FEDR
934,2
233,5
1167,7
80%
Priority axis 3
FC
229
229
458
50%
Priority axis 4
FEDR
172
42,9
214,9
80%
Priority axis 5
FC
270
59,1
329,1
82%
Priority axis 6
FEDR
130,5
43,4
173,9
75%
TOTAL
FEDR+FC
4.512
1.098,4
5.610,8
80,42%
National contribution Mil. Euro
Total SOP Mil. Euro
Co-financing rate UE
Priority axis 1
Extension and modernization of water and wastewater systems
Current situation - Until now the water and sewage services have been provided to the population by small water operators. In some regions in Romania : - Drinking water doesn’t have the proper quality due to the improper treatment schemes; - There is no sewerage or wastewater treatment; - Frequent interruptions occur in the water supply due to the age of the distribution networks; - Only 52% of Romania’s population is connected to both water and sewage services. Without financing, most small water operators will not be able to comply with the acquis.
Romania’s commitments to the EU Following the negotiations for the accession to the EU, through Chapter 22 "Environment", Romania has a number of strong commitments, involving investments in the water and wastewater sector, over relatively short periods of transition. Through the Accession Treaty, transition periods have been granted to Romania in order to comply with the acquis communautaire regarding the collection, discharge and treatment of municipal wastewater as follows: - the year 2015 for 263 agglomerations of more than 10,000 equivalent inhabitants; - the year 2018 for 2346 agglomerations from 2 000 up to 10 000 equivalent inhabitants. In order to comply with the Directive 98/83 on drinking water quality the year 2015 has been obtained as a period for compliance.
Priority axis 1 – SOP ENV The extension and modernization of water and wastewater systems Financial allocation
-2,776 millions Euro – EU contribution (Cohesion Fund) -490 millions Euro – national contribution (State Budget)
Recipients Local Authorities (County Councils and Local Councils) through Regional Water Operators
Objectives • Providing water and sanitation services, at affordable prices • Providing adequate water for all human agglomerations • Improving the quality of water courses • Improving sludge management resulted from wastewater treatment plants • Creating innovative and effective structures for water management
Priority axis 1 – SOP ENV at national level – year 2012 The number of projects approved at national level The number of projects being prepared The total value of the projects being prepared The total amount allocated through SOP ENV Total value of the projects in the NW Region North-West Region: Cluj - Sălaj; Turda – Câmpia Turzii; Bistriţa-Năsăud; Satu-Mare; Bihor; Maramureş
41 3 552,7 mil. Euro 3260 mil. Euro 740 mil. Euro
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
Project Title The extension and modernization of water and wastewater systems in the Counties of Cluj and Sălaj Beneficiary
S.C. COMPANIA DE APĂ Someş S.A.
Value
197 mil. Euro
Project area Cluj County - Cluj-Napoca, Dej, Gherla, Huedin. Sălaj County - Zalău, Şimleul Silvaniei, Jibou, Cehu Silvaniei.
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the Counties of Cluj and Sălaj
CONTRACTS WITHIN THE PROJECT(I): 1. Technical assistance for the project management (including water and sewerage network modeling, advertising) 2. Technical assistance for verifying the projects 3. Technical assistance for the supervision of works 4. Wastewater treatment plant in Şimleu Silvaniei, Jibou and Cehu Silvaniei 5. Wastewater treatment plant in Zalău 6. Water treatment plant in Varsolt, Huedin and works at the water sources in Jibou, Cehu Silvaniei and Huedin 7. Wastewater treatment plant in Cluj-Napoca 8. Wastewater treatment plant in Dej 9. Wastewater treatment plant in Gherla and Huedin 10. Rehabilitation works in operational buildings – NOT ELIGIBLE
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the Counties of Cluj and Sălaj
CONTRACTS WITHIN THE PROJECT(II): 11. Water and sewerage networks. Reservoirs and pumping stations in Şimleu Silvaniei and Huedin 12. Water and sewage networks in Jibou and Cehu Silvaniei 13. Water and sewage networks in Zalău 14. Water transmission main Livada-Dej 15. Water and sewage networks in Dej and Gherla 16. Reservoirs and pumping stations in Cluj-Napoca (rehabilitation) 17. Extension of water and sewage in Cluj-Napoca 18. Rehabilitation of water and sewage in Cluj-Napoca 19. Acquisition of flow and leak detection equipment 20. Acquisition of sewer cleaning machines and operational vehicles 21. Acquisition of SCADA
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the Counties of Cluj and Sălaj
Works within the project: • adduction pipe Livada-Dej • water / sewer network Şimleul Silvaniei-Huedin • water / sewer network Zalău • water / sewer network Jibou, Cehu Silvaniei • water / sewer network Dej Gherla • water / sewer network Cluj Napoca • treatment plant rehabilitation Zalău • treatment plant rehabilitation Dej
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the Counties of Cluj and Sălaj Absorbtion of structural funds : 38,62% Deadline: 01.12.2013 Investments allocated for water supply MU Length /Number New adduction pipes
Km
22
Rehabilitation of adduction pipes
Km
19
Extension of water distribution networks
Km
70
Rehabilitation of water distribution networks
Km
73
Extension and rehabilitation of water pumping stations
No
10
Rehabilitation of water treatment plants
No
1
Rehabilitation of water sources
No
3
Extension and rehabilitation of new reservoirs
No
14
SCADA System
No
1
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the Counties of Cluj and Sălaj Investments allocated for collection and treatment of watewater
MU
Length/Number
New collecting pipelines
Km
2
Rehabilitation of collecting pipelines
Km
16
Extension of sewage networks
Km
71
Rehabilitation of sewage networks
Km
31
Overflow rooms
No
7
Expansion and rehabilitation of wastewater pumping stations
No
23
Rehabilitation of wastewater treatment plants
No
8
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
Project Title The extension and modernization of water and wastewater systems in the region of Turda – Câmpia Turzii Beneficiary
S.C. COMPANIA DE APĂ Arieş S.A.
Value
80 mil. Euro
Turda, Câmpia Turzii, Luna, Mihai Viteazu, Project area Sănduleşti, Viişoara
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the region of Turda – Câmpia Turzii
CONTRACTS WITHIN THE PROJECT(I): 1. Technical assistance for project management (including water and sewerage network modeling, advertising) 2. Technical assistance for the supervision of works 3. Rehabilitation of operational buildings and workshops - not eligible 4. Purchase of water meters 5. Acquisition of sewer cleaning machine and operational vehicles 6. Acquisition of SCADA 7. Rehabilitation of capture sources and chlorination stations in Turda 8. Measures in the water supply network
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the region of Turda – Câmpia Turzii
CONTRACTS WITHIN THE PROJECT (S): 9. Rehabilitation of sewage networks Turda 10. Extension of water and sewage networks 11. Extension of sewage networks Turda 12. Rehabilitation of water supply and water treatment plant in Câmpia Turzii 13. Rehabilitation of water and sewage systems in the municipality of Câmpia Turda 14. Extension of water and sewage systems in Câmpia Turzii 15. Rehabilitation treatment Câmpia Turzii 16. Sewerage network in villages (Viişoara, Mihai Viteazu, Luna and Sănduleşti)
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in the region of Turda – Câmpia Turzii
Works within the project: - wastewater treatment plant Turda - Câmpia Turzii; - water treatment plant Câmpia Turzii; - water / sewage networks Câmpia Turzii ; - water / sewage networks Turda ; - sewage networks in villages (Mihai Viteazu,Luna, Sănduleşti şi Viişoara ). -
Absorption of structural funds: 49,69% Deadline: 22.09.2013
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
Project Title The extension and modernization of water and wastewater systems in Bistriţa-Năsăud County
Beneficiary Value Project area
S.C. AQUABIS S.A. Bistriţa 83 mil. Euro Bistriţa, Beclean, Năsăud, Sângeorz Băi, Telciu, Feldru
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems The extension and modernization of water and wastewater systems in Bistriţa-Năsăud County
CONTRACTS WITHIN THE PROJECT: 1. Technical assistance for project management 2. Services for the supervision of works 3. Rehabilitation of water distribution and sewage networks in Bistrita, water distribution networks and adductions in localities within the Zonal Water Supply System Bistrita 4. Wastewater treatment plant and transfer collectors for clusters in Bistrita, Beclean, Salva, Sangeorz-Bai 5. Rehabilitation and extension of transport pipelines and drinking water adductions in the Zonal Water Supply System Bistrita 6. Expansion of water distribution and sewage networks in the service area of Beclean 7. New treatment plant for the city Beclean 8. Rehabilitation and extension of water and sewage networks in the cities Nasaud Salva, Sangeorz Bai and Maieru; drinking water adducts for the cities Maieru and Rebra-Nasaud 9. Expansion of water distribution and sewage networks and wastewater treatment plant in Feldru
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems The extension and modernization of water and wastewater systems in Bistriţa-Năsăud County
Absorption of structural funds– 4,07% Deadline: 31.12.2013 Investments allocated for water distribution
MU
Length/Number
Rehabilitation of drinking water treatment plants
No
1
Extension of adduction pipelines
Km
61
Rehabilitation of adduction pipelines
Km
51
Extension of water distribution networks
Km
39
Rehabilitation of water distribution networks
No
35
New reservoirs
No
8
Rehabilitated reservoirs
No
5
New pumping stations
No
5
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
The extension and modernization of water and wastewater systems in Bistriţa-Năsăud County Investments allocated for the collection and treatment of wastewater
MU
Length/Number
New collectors for wastewater
No
15
Extension of sewage networks
Km
73
Rehabilitation of sewage networks
Km
11
New pumping stations
No
13
New wastewater treatment plants and rehabilitation
No
5
New projects approved in 2011 – 2012 1. The extension and modernization of water and wastewater systems in Bihor County 2. The extension and modernization of water and wastewater systems in MaramureĹ&#x; County 3. The extension and modernization of water and wastewater systems in Satu Mare County
Total value - 380 millions Euro
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
Project Title The extension and modernization of water and wastewater systems in Bihor County Beneficiary Value
S.C. COMPANIA DE APĂ Oradea S.A. 103 mil. Euro
Oşorhei, Sântandrei, Girişu de Criş, Nojorid, Project area Biharia, Tinca, Beiuş Absorption of structural funds: 3,30 % Deadline: 31.12.2014
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
Project Title The extension and modernization of water and wastewater systems in Maramureş County Beneficiary S.C. VITAL S.A. – Baia Mare Value
149 mil. Euro
Baia Mare, Sighetu Marmaţiei, Borşa, Vişeu de Project area Sus, Seini, Târgu Lăpuş, Cavnic. Absorption of structural funds: 0,27% Deadline: 31.12.2015
ONGOING PROJECTS in North-West Region PRIORITY AXIS 1 – SOP ENV The extension and modernization of water and wastewater systems
Project Title The extension and modernization of water and wastewater systems in Satu Mare County Beneficiary S.C. APASERV Satu Mare S.A. Value
128 mil. Euro
Satu Mare, Botiz, Păuleşti, Lazuri, Odoreu, Project area Carei, Foieni, Negreşti Oaş, Tăşnad, Livada, Ardud, Căpleni Absorption of structural funds: 0,19% Deadline: 30.06.2015
CONCLUSIONS The projects intended for the expansion and the modernization of the water and wastewater infrastructure, financed through SOP ENV, will have a crucial contribution to the quality of water and sewage services provided to the population in the project area. In terms of signed financing contracts, Romania ranks first in the EU. 95% of the total financing agreements through SOP Environment have been signed. In the project implementation phase involving beneficiaries, local authorities, is essential for the success of the projects and the increase in the absorption rate of EU funds. In 2012 the grant contracts will be signed also for last projects under preparation within SOP Environment 2007-2013. SOP Environment projects must be implemented by 2015.
Thank you for your attention!
MINISTRY OF ENVIRONMENT AND FORESTRY INTERMIDIATE BODY Sectoral Operational Programme “ENVIRONMENT” Cluj-Napoca Region 6 – North-West
consultant ing. Nicu ROZENBERG
Str. Minerilor, nr. 47, nicu.rozenberg@posmediu.ro Tel: 0264 418714 Fax: 0264 481110 www.posmediu.ro