Bro brca regionofpeel energy august2014

Page 1

C O M P A N Y O V E R V I E W


Region of Peel, Twinning Trunk Sewer Project

Double Vision: Twinning the R West Trunk Sewer

The project is one of Canada’s largest linear wastewater pr Written by: Kevin Smead

Produced by: Michael Magno


g of the West

Region of Peel’s

rojects in both size and scope.

3


C O M PA N Y N A M E

The Regional Municipality of Peel’s motto is “Working for you.” With its West Trunk Sewer project, that’s exactly what they’re doing. Located in Southern Ontario, Peel Region is currently home to one of the largest linear wastewater projects in all of Canada. Through the Region’s Water and Wastewater Master Plan, the Region identified 4

a need to upgrade its current wastewater infrastructure and it hopes to do so in a way that ensures future upgrades are not needed for the next 50 to 100 years. The project spans a great length at nearly 14.5 kilometers and runs from Highway 401 in the North, to just north of Queen Elizabeth Parkway in the City of Mississauga


SECTOR

An environmental assessment completed in 2009 found that Twinning the existing West Trunk Sewer system the best course of action. The process of “twinning� is as simple as adding another pipe, but of course is much more complicated than that in a project with as many factors as this one. The existing system is almost 50 years old and is in need of serious rehabilitation. Development pressure within the Region and a push for infill

Simon HoptonDirector, Wastewater Division

w w w. p e e l r e g i o n . c a

5


REGION OF PEEL intensification also are driving factors behind the project. The existing sewer pipe capacity is also nearing its maximum capacity and leaving no room for new growth. By twinning the sewer—and essentially adding a second pipe— capacity will be greatly increased.

C Class EA, often reserved for complicated and large-scale construction of new facilities or major expansions to existing facilities, the project went through a five-phased environmental planning process. This takes into account not only the environmental impact of the project, but the socioeconomic Community Involvement impacts to the public and local With the scale and scope of the economy as well. project, public input is extremely Essentially, the project began important. Because the construction with a problem statement. Various area is 14.5 km long and runs alternatives were explored until a through densely populated portions short list was developed. This is of Mississauga, the project has when stakeholders were engaged, potential to impact the public. such as Canadian Pacific Railway, Minimizing impact was a main Ministry of Transportation and the focus when planning the project. Credit Valley Conservation Authority, The project team decided against since they would be directly open-cut construction, which would impacted by the construction. significantly affect traffic. There are also a number of crossings in the Ensuring Successful project area, including creeks, river, Construction highways, and rail crossings. Various The construction itself is also quite stakeholders were engaged early on the feat, as it is being completed in the planning stages for their input entirely underground. Using two and approval. different types of tunnel boring As it is, the project underwent a machines—rock and earth pressure Schedule C Class Environmental balance—crews working at a depth Assessment process For a Schedule up to 55 meters underground


ENERGY

will have to tunnel through solid shale bedrock and mixed ground conditions to twin the sewer. The construction is being tendered under two contacts, the first of which was awarded to McNally Construction Inc. and is currently under construction. The second contract will be tendered sometime later this summer. WSP Canada Inc. is the Design Consultant for the project and is also providing contract administration and inspection services during the construction phase.

Golder Associates Ltd. is providing the geotechnical services relating to this project. During the geotechnical investigation, it was discovered that methane gas was present in some pockets of the shale bedrock, adding a layer of complexity to the construction. The gas’ presence at the construction’s depth is not uncommon, but the pressure at which it was released is. Golder had to coordinate with the Ministry of Natural Resources to drill special bore holes to verify the extent of the presence of the w w w. p e e l r e g i o n . c a

7


REGION OF PEEL

DANYLE GROUP INC.

WE SPECIALIZE IN EARTH HAULING. 51 Shorncliffe Rd. Unit #3 Toronto, ON M8Z 5K2

P: 416.239.2009 F: 416.234.1260 danylegroup.com 8

methane gas and analyze the impact it would have on the proposed tunnel construction. Based on the geotechnical findings special electrical classifications for the tunnel boring machines were specified for. This ensures that if the contractor hits gas in the tunneling process, there would be sufficient protections in place to ensure the safety of the construction workers, infrastructure and the public. Of course, safety is a top priority for a successful implementation of any construction project.


ENERGY

Company Information INDUSTRY

Water Project / Infrastructure HEADQUARTERS

Ontario, Canada EMPLOYEES

50+

This is one of most expansive project relating to wastewater collection system in Canada, costing around $160 million. Upon completion, sewage will begin flowing into the trunk’s system, thus achieving the project’s goal. Key personnel on the project include Peel Region’s Project Manager Ajay Puri, McNally Construction’s Jeff Reid, and WSP Canada’s Project Manager Chad Stephen. Both contracts are expected to be completed in summer/fall of 2016.

w w w. p e e l r e g i o n . c a

9


Region of Peel Tel. 905-791-7800 www.peelregion.ca


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.