Part 6 – Project Timeline The anticipated timeline for completion of this Planning Proposal is as follows: Dates
Project timeline
September 2021
Report Matter to Local Planning Panel, consideration by Council and Council decision
March 2022
Submit Planning Proposal to DPE for Gateway Determination
June 2022
Gateway Determination
October 2022
Complete any changes required by Gateway Determination (pre-exhibition)
November 2022
Commencement and completion of public exhibition period
December 2022
Consideration of submissions
February 2023
Post-exhibition review and additional studies
April 2023
Council meeting to consider outcomes of exhibition (Date to be confirmed)
May 2023
Submission to the Department for finalisation
August 2023
Gazettal of LEP amendment