RFP%20Review%20-%20October%2023%202012

Page 1

RFP - Demolition of the Paramount Building and Ewert Building Project - Proposal Review CEPCO received three Proposal in response to the RFP All Proposals received met all mandatory requirements required by the RFP Following is the Schedule of Prices provided by the winning Proposal: 1 2 3 4

Bonding & Insurance Removal of Paramount sign and transportation to storage yard Demolition of Paramount Theater Building Demolition of the Ewert Building Total Guaranteed Maximum Price (not including HST)

$7,155.00 $5,000.00 $343,000.00 $130,000.00 $485,155.00

Following is a further cost breakdown for each building as provided by the winning Proponent: Demolition of Paramount Theater Building Hazardous material removal and disposal - Paramount Theater Total

$269,000.00 $74,000.00 $343,000.00

Demolition of Ewert Building Hazardous material removal and disposal - Ewert Building Total

36,000.00 $94,000.00 $130,000.00

Note: All costs shown do not include HST.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.