Milestones
Construction Start: May 2021
Stage 1A: 100 Avenue and 100 Street intersection sanitary sewer installation (1 week duration, May)
Stage 2: 100 Avenue - 100 Street to 99 Street intersection (Mid-May to end of August)
Stage 1B: 100 Avenue and100 Street intersection underground and above-ground work. (Beginning of July to beginning of August)
Stage 3: 100 Avenue - 99 Street to 98 Street (Mid-August to end of October)