Construction Start: May 2021

Stage 1A: 100 Avenue and 100 Street intersection sanitary sewer installation (1 week duration, May)

Stage 2: 100 Avenue - 100 Street to 99 Street intersection (Mid-May to end of August)

Stage 1B: 100 Avenue and100 Street intersection underground and above-ground work. (Beginning of July to beginning of August)

Stage 3: 100 Avenue - 99 Street to 98 Street (Mid-August to end of October)

Construction Completion: End of October 2021