Appendix 26 & Systems installation

Aruna Mylvaganam

• Smokescreen above escalators to Chief Post Office entrance installed

• Righthand elevator at Chief Post Office entrance returned to the public

• Elevator upgrades at southern end underway – scheduled to be complete in September

• Civil and architectural fit out of basement rooms, including mechanical, electrical, fire and hydraulics (MEHF) work complete and handed over to systems team

• Systems now being installed in basement rooms

• Excellent progress on platform raising –scheduled for completion in September

• Civil and architectural fit-out substantially complete

• Switchover to permanent power connection 9 July – a milestone we’re really proud of!

• Mechanical, electrical, fire and hydraulics (MEFH) installation progressing well –scheduled to complete all testing works by middle September

• Additional systems fit-out being carried out in the Eastern Equipment Rooms in preparation for energisation – expected to take place in Q4

Inside the tunnels between Waitematā and Te Waihorotiu stations

• Overhead line installed in both tunnels

• Cable trays installed in both tunnels

• Systems – including signalling and electrical – fit-out underway including signalling, traction power, communication, lighting and power

• Concrete pours alongside rail tracks inside MC20 underway

• In August we’ll begin bringing in railway track via Zephr to Platform 1 to start fitting out MC20 & remaining part of MC30

• From September to late-2023 we’ll continue cable pulling including for low voltage & communications cables