Appendix 26 & Systems installation
Aruna Mylvaganam
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/222d0cb4d8c4531414b32689c80f946c.jpeg?width=720&quality=85%2C50)
• Smokescreen above escalators to Chief Post Office entrance installed
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/da3dd6a30ce551cbdc6a1bb3371f5e08.jpeg?width=720&quality=85%2C50)
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/ee3e719fe09c3817aec6e6ec54e2cb76.jpeg?width=720&quality=85%2C50)
• Righthand elevator at Chief Post Office entrance returned to the public
• Elevator upgrades at southern end underway – scheduled to be complete in September
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/54bab475548a2b9808a13ba31e4f6131.jpeg?width=720&quality=85%2C50)
• Civil and architectural fit out of basement rooms, including mechanical, electrical, fire and hydraulics (MEHF) work complete and handed over to systems team
• Systems now being installed in basement rooms
• Excellent progress on platform raising –scheduled for completion in September
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/7f5553c29394db587d45c2f74391d2ba.jpeg?width=720&quality=85%2C50)
• Civil and architectural fit-out substantially complete
• Switchover to permanent power connection 9 July – a milestone we’re really proud of!
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/0206f023b3f54cc9df3470b107242fa0.jpeg?width=720&quality=85%2C50)
• Mechanical, electrical, fire and hydraulics (MEFH) installation progressing well –scheduled to complete all testing works by middle September
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/3511550cee48d7428dc6f4fa95a1bb04.jpeg?width=720&quality=85%2C50)
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/32b9f79761aced99416245393545afd7.jpeg?width=720&quality=85%2C50)
• Additional systems fit-out being carried out in the Eastern Equipment Rooms in preparation for energisation – expected to take place in Q4
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/b8bbe241d782de7aa259d464fa2634d8.jpeg?width=720&quality=85%2C50)
Inside the tunnels between Waitematā and Te Waihorotiu stations
• Overhead line installed in both tunnels
• Cable trays installed in both tunnels
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/a9e9b62be35908f4a1a4576b1b3b324b.jpeg?width=720&quality=85%2C50)
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/3f9398d21900a42507bc1bb4ef11bc2b.jpeg?width=720&quality=85%2C50)
• Systems – including signalling and electrical – fit-out underway including signalling, traction power, communication, lighting and power
![](https://assets.isu.pub/document-structure/230716220400-353c7c2d72117a3e02973f1a196c9ebb/v1/8aeecafacc115b458767fe26245aad0c.jpeg?width=720&quality=85%2C50)
• Concrete pours alongside rail tracks inside MC20 underway
• In August we’ll begin bringing in railway track via Zephr to Platform 1 to start fitting out MC20 & remaining part of MC30
• From September to late-2023 we’ll continue cable pulling including for low voltage & communications cables