Waitematā Station CLG Agenda

• Welcome + Intro – Alex Vaineritua, Senior Stakeholder and Communications Advisor

• Martinus works update – Nigel Lambourne, Martinus Project Manager

• Link Alliance works update - Aruna Mylvaganam, Link Alliance Construction Manager

• Any questions?

City Rail Link Project Update

• Wider project is progressing well – practical completion November 2025

• Western Line returns to dual running through Maungawhau Station

• All mined tunnelling is completed

• Station and tunnels fit out phase has begun

• CRL was awarded the highest possible rating for infrastructure sustainability at the Infrastructure Sustainability Council (ISC)

Re-Constructing Waitematā (Britomart) Station

Milestones achieved in the last 3 months

• Completed planting to Britomart Place/Scene Lane corner

• Re-established the traffic island to Britomart Place

• Completed paving around the glass box at Britomart Place

• Continued with an excellent standard of safety management and control

• Over 100,000 safe working hours completed over the Britomart projects in the last year

Milestones continued Platform 5 upgrade works

Ballast being removed from Platform 5

Completed new tracks having final clean down for completion

• Completed track improvement works to Platform 5, Waitematā (Britomart) Station

• Commenced track and signalling improvement works for Waitematā (Britomart) tunnel

What’s planned for the next 3 months?

• Form temporary track alignment at Platform 5 for work train access

• Continue track improvement works for the Waitematā (Britomart) tunnel

• Complete cable containment works for the new signalling system

• Commence new traction power works requirements

Appendix 26 & Systems installation

Aruna Mylvaganam

• Smokescreen above escalators to Chief Post Office entrance installed

• Righthand elevator at Chief Post Office entrance returned to the public

• Elevator upgrades at southern end underway – scheduled to be complete in September

• Civil and architectural fit out of basement rooms, including mechanical, electrical, fire and hydraulics (MEHF) work complete and handed over to systems team

• Systems now being installed in basement rooms

• Excellent progress on platform raising –scheduled for completion in September

At the western end of the station

• Civil and architectural fit-out substantially complete

• Switchover to permanent power connection 9 July – a milestone we’re really proud of!

• Mechanical, electrical, fire and hydraulics (MEFH) installation progressing well –scheduled to complete all testing works by middle September

• Additional systems fit-out being carried out in the Eastern Equipment Rooms in preparation for energisation – expected to take place in Q4

At the eastern end of the station

Inside the tunnels between Waitematā and Te Waihorotiu stations

• Overhead line installed in both tunnels

• Cable trays installed in both tunnels

• Systems – including signalling and electrical – fit-out underway including signalling, traction power, communication, lighting and power

• Concrete pours alongside rail tracks inside MC20 underway

• In August we’ll begin bringing in railway track via Zephr to Platform 1 to start fitting out MC20 & remaining part of MC30

• From September to late-2023 we’ll continue cable pulling including for low voltage & communications cables

Questions?