Triboro Banner, July 23, 2015

Page 1

25

c

ThE TRIBORO

s

t en

Serving Taylor, Old Forge, Moosic & Surrounding Areas

Around Town

School News

What’s going on with your favorite student. Page x

Community Calendar

Plan some fun for the family this weekend Page x

Times-shamrock communiTy newspapers 149 Penn Avenue Scranton, PA 18503 Phone: (570) 207-3473 Fax: (570) 207-3448 e-mail: triborobanner@ timesshamrock.com

July 23, 2015

thetriborobanner.com

rebuilding roadways

ON THe iNSide The latest happenings in our area Page x

BANNER

PennDOT makes progress on Triboro-area roads by Stephanie Longo

SPECIAL TO THE TRIBORO BANNER

Moosic’s main streets are under construction, according to PennDOT officials. Main Street, Spring Street and Birney Avenue are seeing their share of construction equipment this summer as the roadways are about to receive necessary upgrades. “We are currently working on the replacement of the Main Street Bridge over Spring Brook Creek,” said Mike Taluto, PennDOT safety press officer. “The new structure is anticipated to be a single-span steel girder on the same alignment with framing and it will also include a raised sidewalk. It should be completed this fall.” The Main Street Bridge replacement project costs a total of $1.42 million and detours will be used to maintain the flow of traffic during construction. “There have been issues over the past several years with each project in the area,” Taluto said. “The Main Street Bridge detour has been in place for more than three years and the detours have been issues for the residents and business in the area.” Along with the Main Street Bridge project, PennDOT is also working on a $2.98 million bridge replacement on Spring Street in Moosic that crosses over the Lackawanna River. This project is scheduled for completion in November and will also include new pavement, new guiderails, sidewalks, pavement markings and other enhancements. There are detours in place. Besides the two bridge replacements, PennDOT is also working on improving a stretch of Birney Avenue between Hollenback and Corey streets in the vicinity of Birney Plaza, costing $2.46 million. “For the Birney Avenue project, we’re looking at installing a traffic signal, a retaining wall, and full-depth bituminous pavement, as well as pavement widening, excavation, landscaping, pavement markings, upgrades to drainage, concrete curbing and sidewalks with

TS_CNG/TRIBORO/PAGES [T01] | 07/22/15

09:01 | CORNELLCHR

Signs show the closure of Spring Street in Moosic while PennDOT works to complete a $2.98 million bridge replacement project over the Lackawanna River. The project is slated for completion this fall. PHOTO COURTESY MIKE TALUTO/PENNDOT

handicapped-accessible ramps and other upgrades, “Taluto said. “This project should be completed by Oct. 31.” While the Moosic projects are proving difficult for area residents needing to seek detours or whose commutes have been delayed by the roadwork, Taluto said that PennDOT’s largest undertaking in the Triboro area is actually in Taylor. PennDOT is working on a stretch of Keyser Avenue between Keyser Creek and Lucky Run Creek that has been combined with work

being performed on the roadway beginning near Ferdinand Avenue in Scranton. The $15.5 million project will be completed before the end of July and the remaining paving work is currently underway. Taluto said that the project entails working on a retaining wall, four traffic signals, paving, demolition of two structures, drainage, sidewalks and curbing. For more information or to check on the progress of any PennDOT project, visit neparoads.com.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.