California 20 2009 - CEG

Page 1

97

Crescent City

395 139

5

101 299 89

Burney Eureka 299 Rio Dell

CALIFORNIA STATE SUPPLEMENT

395

299 44

44 36

101

89

Leggett

99

395

70

Chico

Oroville

5

49

Fort Bragg Point Arena 20 1

89

80 Tahoe City Auburn 50 South Lake Sacramento Tahoe

65

101

70 5

Santa Rosa

505 80

99

395 49

680

San Francisco

Sonora

Berkley 580 Oakland 280

120 120

120

6

Modesto

880

San Jose

140

99

41

5

101 1

395 152

Madera

Santa Cruz Montery

Fresno

33

180

190

198 1

September 26 2009

Death Valley Junction

King City Lucia

198

65

101 127 46

178 15

14

San Luis 33 Obispo Santa Maria

Bakersfield

Baker

395

58

5

Barstow

101

Vol. IV • No. 20

40

15

1

14

Santa Barbara

Ventura

95

Glendale San Bernadino Los Angeles Riverside Santa Monica Santa Ana 10 Palm Springs Long Beach 1

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

101

10

5

15

86

Oceanside

Your California Connection – Frank Strazzulla – 1-877-7CEGLTD – fstrazzulla@cegltd.com

San Diego 8

Confusion Hill Realignment Project Nearly Complete By Erik Pisor CEG CORRESPONDENT

For more than a decade, a portion of Route 101 in Mendocino County, Calif., has experienced regular winter road delays due to landslides and slipouts. These often five-hour plus delays have affected travelers and the transportation of goods and services into the area. The landslides also have caused multiple-day road closures, which from 1997 to 2006 resulted in more than $33 million in maintenance and restoration expenses to Caltrans. This winter however, delays and closures along the portion of Route 101 known as Confusion Hill will be a thing of the past, as the $65 million Confusion Hill Roadway Realignment Project is nearly complete. The project involved relocating approximately 1.5 mi. (2.4 km) of Route 101 by constructing a 255-ft. (77 m) tall, three span, cast-in-place segmental bridge; and a 142-ft. (43 m) tall, three span, cast-in-place concrete box girder bridge above the Eel River, according to Evan Paine, project manager for Sacramento-based MCM construction. Construction of a short section of new highway, which involved an approximately 400,000 cu. yds. (305,800 cu m) rock cut and the installation of two steel soldier pile retaining walls, also was part of the Federal Highway Administration-funded project that began in June 2006. However it was the bridgework that set the project apart. “Each bridge has a unique design due to time and cost restraints placed on project development,” said Phil Frisbie, public information officer for Caltrans District 1. The south, segmental bridge has 30-degree slant legs that allowed the foundations to stay above the 100-year flood plain and reduced environmental permit requirements. “The segmental bridge is only the sixth of its kind built in

Pictured is the completed South Bridge.

California,” Paine said. Sloping piers, are a feature of the north, box girder bridge, which because of steep and rugged site access required an 80-ft. (24 m) high, 300-ft. (91 m) long work trestle to construct. The main cranes utilized by MCM for the bridgework included a Maintowoc 4000, a Maintowoc 3900, a Link-Belt

LS-518 and a Link-Belt LS-338, according to Paine, who added a pair of self-launching travelers were used during construction of the south, segmental bridge. All the crane equipment was owned by MCM, who was selected based on being the lowest qualified bidder. The three-span, south segmental bridge has a main span see CONFUSION page 6

California Leads Nation With More Than $2B in Federal Funds Gov. Arnold Schwarzenegger announced that more than $2 billion in Recovery Act funding has now been federally obligated to 620 highway transportation infrastructure projects statewide. Focused on pumping Recovery funding into the California economy quickly, effectively and responsibly, California has obligated more Recovery Act funding federally designated for highway transportation infrastructure than any other

state in the nation. “We are working around the clock with the federal government to ensure President Obama’s Recovery funding is pumped into California quickly, effectively and responsibly,” said Schwarzenegger. “California is the first state in the nation to obligate $2 billion of this funding, which will improve our state’s transportation infrastructure for generations to come while stimulating our econ-

omy, creating jobs and helping drive California down the road to economic recovery.” Under the Recovery Act, states were given 120 days to obligate half of their federal stimulus transportation funding to projects — which California completed more than two months ahead of federal deadline. California also was the first state in the nation to obligate $1 billion in stimulus

funding to improve its highways, local streets, public transit and airports. “From day one, our focus has been and continues to be ensuring that California gets the maximum benefit from federal stimulus funding,” said Caltrans Director Randy Iwasaki. “With the help of billions in stimulus dollars, we’re putting people to work and building better roads, bridges, and transit for Californians.”


Page 2 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

226 CAT SKID STEER LOADER ®

303 CAT COMPACT EXCAVATOR

$823/month* $1,087/month* 0% for 42 months with a 36 month warranty.

0% for 42 months with a 36 month warranty.

289 CAT COMPACT TRACK LOADER

$1,666/month* 0% for 42 months with a 36 month warranty.

WITH INDUSTRY-LEADING PERFORMANCE AND PRODUCTIVITY, NO OTHER PRODUCT LINE CAN COMPARE TO THE FULL LINE OF CAT COMPACT EQUIPMENT AND WORK TOOL ATTACHMENTS FROM JOHNSON MACHINERY. AND NOW WITH SPECIAL FINANCING THERE’S NO BETTER TIME TO GET A CAT MACHINE ON YOUR JOBSITE. Stop by or call us today for more details on these offers or to demo a Cat Skid Steer Loader, Compact Track Loader, or Compact Excavator today. See how to ppropel p your y business into higher productivity and add to your bottom line with Cat Equipment and

say so long to John and Bob.

©2009 Caterpillar All rights reserved. CAT, CATERPILLAR, their respective logos, “Caterpillar Yellow,” the “Power Edge” trade dress as well as corporate and product identity used herein, are trademarks of Caterpillar and may not be used without permission. *Price includes tax and a bucket. Terms and conditions may apply. Offers expire 10/31/09. OAC.

www. johnson-machinery.com

FONTANA INDIO RIVERSIDE TEMECULA VICTORVILLE

951-686-4560


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 3

Former Helicopter Pilot Gets Up to Speed With MC2 Dozer Spartakoss Valverdini is a retired Marine colonel and a former Apache helicopter pilot. He likes speed…the faster, the better. Speed is not what he expects when working as a finish blade operator in the construction industry. But speed is what he experienced on a John Deere 750J dozer during a recent hands-on demonstration of the fastest machine control technology on the market today. Topcon Positioning Systems’ (TPS) 3DMC2 technology, according to published information and accounts from end-users, allows a dozer operator to go “twice as fast with twice the accuracy” of a regular 3DGPS system, and four to five times as fast as a dozer without any machine control system. Valverdini, a finish blade operator versed in the use of laser grade control, GPS and ATS systems, and a member of the Operating Engineers Union, said, “3D-MC2 allows you to go fast all right. But that’s just part of the job. More importantly, it gives you the smooth, accurate, finish grade of a grader…with a dozer. I’ve never seen anything like it.” After minimal instructions and a couple of passes on a football field-size test site near the company’s headquarters in Livermore, Calif., John Dice, TPS senior training man-

ager, put Valverdini behind the joystick controls of the dozer. Valverdina made a slow pass in manual, then a return pass at about the same speed, still in manual control. Grading at about 1.8 to 2 mph., his passes were “acceptable,” he later said. Engaging the 3D-MC2 system, his third and fourth passes were at about 4 mph. The cuts were definitely smoother…finish grade quality. The fifth pass had Valverdini pushing the Deere dozer wide open, between 6 and 7 mph. The cut, trimmed on both sides by the dozer tracks was ultra-smooth. A level demonstration showed it was “on bubble.” “That was something,” Valverdini said. “I have read about 3D-MC2 technology, and listened to what John Dice said. But until you actually run it, it does not compute what he can actually do.” He admitted that is was “hard to jump the dozer up as fast as I finally did. Operators are not used to doing that. We are used to controlling the dozer, not the dozer controlling the cut regardless of the speed.” Dice complimented Valverdini’s performance, saying, “He’s a good operator at any speed. But just because he’s a good operator, he didn’t close his mind to the possibilities of

Spartakoss Valverdini is a retired Marine colonel and a former Apache helicopter pilot.

After minimal instructions and a couple of passes on a football field-size test site near the company’s headquarters in Livermore, Calif., John Dice (R), TPS senior training manager, put Spartakoss Valverdini behind the joystick controls of the dozer.

what 3D-MC2 can do. If you accept the premise this machine can make you more productive, thus saving time and money, it’s a natural progression from running with no machine control system, or even a GPS-only system, to running with 3D-MC2.” With normal GPS machine control having 10 and 20 grade corrections per second, it’s “hard to believe you can jump from that to

100 corrections per second,” Valverdini said. “But all you have to do is make a couple of passes, and look at the finish grade you get at that speed and it makes you a believer in a hurry.” To think, he said, “that you can use one dozer to do the work of two, and do finish grade work equal to that of a grader…is unbelievable.”

Spartakoss Valverdini (2nd from L) discusses specs with the other attendees in front of a John Deere 750J dozer.

Construction Starts on Key SoCal Freeway in San Bernardino SAN BERNARDINO, Calif. (AP) Construction has begun on a freeway widening project through downtown San Bernardino that’s received $128 million in federal stimulus funding and promises to create thousands of jobs. Federal Highway Administrator Victor Mendez, state and

local officials celebrated the groundbreaking of the latest phase of the Interstate 215 project Sept. 14. Officials say it’s the largest stimulus-funded freeway project to begin construction. They say the money will support

about 2,000 jobs per year for the next four years in a region that has some of the nation’s worst unemployment and foreclosure rate. The full project is expected to finish in 2013 for about $800 million.


Page 4 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

H U S K I E

H Y D R A U L I C

H A M M E R

y a S e W n Whe . . . ” r e v e r “Fo

r! e v e r o F n a We M e Protected By Lifetime Warranty * Profits get hammered two ways. First, when your breaker falls apart, you’re not working. Second, some parts are so expensive that it’s better to cut into your bottom line and buy a new hammer to get a fresh warranty. That’s the way it is with most hammers and their warranties. But, Huskie is really different. If you own a Huskie Hydraulic Hammer, you are covered front cap to back cap by Huskie’s industry-leading LIFETIME Limited Warranty*. • LIFETIME Coverage for Front Cap, Back Cap and Main Body • THREE YEAR Protection for All Components except • TWO YEAR Warranty for All Seals • UNLIMITED HOURS of Use Forever is a long time. But, if you own a Huskie Hammer, that’s how long you can expect to run it 24/7 and still be covered by the revolutionary Huskie Lifetime Warranty. Ask your dealer for a demo.

6188 Paramount Blvd. Long Beach, CA 90805 Phone: 562-272-7400 Fax: 562-272-7444 12435 Foothill Blvd. Sylmar, CA 91342 Phone: 818-890-3353 Fax: 818-890-5013

3216 Westminster Santa Ana, CA 92703 Phone: 714-265-5500 Fax: 714-265-5505

1930 E. Lockwood St. Oxnard, CA 93036 Phone: 805-485-2106 Fax: 805-485-7963

1950 Roemer Place Santa Maria, CA 93454 Phone: 805-922-8329 Fax: 805-922-4582

888 East Ave. L-4 Lancaster, CA 93535 Phone: 661-948-9993 Fax: 661-723-5613

4252 Saco Road Bakersfield, CA 93308 Phone: 661-399-3600 Fax: 661-399-8782

*Limited warranty. Normal wear items are not covered. See warranty statement for details and exceptions. Effective on all Huskie Hydraulic Hammers purchased after July 1, 2005. The Huskie logo and Huskie Hydraulic Hammer are registered trademarks of IPC Industries, Inc. © 2008 IPC-Huskie Hydraulic Hammer

Caltrans Reopens Bay Area Bridge After Repairs Completed By Sudhin Thanawala ASSOCIATED PRESS WRITER

SAN FRANCISCO (AP) The San Francisco-Oakland Bay Bridge reopened Sept. 8 just in time for the start of the work week after transit officials hastily announced that crews were able to make a crucial repair a day ahead of schedule. “Traffic seems to be flowing smoothly,” California Department of Transportation spokesman Bart Ney said after the bridge reopened just before 7 a.m. “I think it’s still a surprise.” Officials had pushed the reopening to 5 a.m. Sept. 9 after crews discovered a crack Sept. 5 while conducting seismic upgrades on the 73-year-old bridge. The bridge, which carries about 260,000 vehicles a day between San Francisco and heavily populated cities to its east, was closed over the Labor Day weekend so a football-field-sized, 3,300-ton (2,993 t) section of the eastern span could be cut out and replaced with a new double-deck section. The new section connects the bridge with a short detour that will be used until a new east span is completed by 2013. Crews used the opportunity to inspect the bridge and found a 2-in. (5 cm) -thick steel

link cracked halfway through. Ney said a contractor worked throughout the night to make a replacement part and complete the work. An inspection following the repair “went without a hitch,” he said. “The bridge has been inspected and it’s safer than it was when we closed it,” said Caltrans director Randy Iwasaki. The bridge shut down the night of Sept. 3, and other bridges and public transportation systems were able to accommodate extra riders Sept. 4, the first time that the bridge was closed on a working day since a major earthquake in 1989. Meanwhile, the Sept. 8 morning rush hour was still heavy on several other Bay Area roadways including the Golden Gate Bridge, said Sgt. Trent Cross, spokesman for the California Highway Patrol’s Golden Gate division. “I think most motorists weren’t aware or didn’t know that the bridge was open,” Cross said. Public transit also was busier than usual despite the early reopening. Bay Area Rapid Transit spokesman Jim Allison said the commuter rail line could still set a record. Officials expected some 7,700 more passengers than the previous week. It averages about 340,000 commuters a day.

RDO Equipment Co. Acquires B&B Heavy Equipment in Calif. RDO Equipment Co. has acquired B&B Heavy Equipment Sales & Rentals Inc., one of the largest heavy equipment rental suppliers servicing southern California and beyond. “We are thrilled to have B&B Equipment Rental join our company. They are an established business with excellent employees, a great reputation in the region, and superb customer service,” said Christi Offutt, RDO Equipment Co. chief executive officer. “The combination of B&B Equipment Rental and RDO Equipment Co. will be able to provide customers an expanded rental equipment offering through more locations in southern California and Arizona.” Bob Wheelington, B&B Equipment Rental’s former president and newly appointed vice president and general manager, will provide the day-to-day leadership for the rental operation.

“Becoming part of the RDO Equipment Co. family is an exciting transition for us,” he said. “We will be better able to provide customers with the equipment, parts, and service solutions they need.” About RDO Equipment Co. Founded in 1968, RDO Equipment Co. is a family-owned and operated company dedicated to provide and support John Deere (agriculture, construction, lawn and garden) and Vermeer customers. The corporation’s headquarters are in Fargo, N.D. The company has 55 locations in nine U.S. states, and employs more than 1,400 people. For more information about B&B Equipment Rental, visit www.BBRental.com. For more information about RDO Equipment Co., visit www.rdoequipment.com.


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 5

From humble beginnings in 1945, JCB has grown to become one of the largest equipment manufacturers in the world and still remains family owned. Not only do we produce the world’s best selling backhoe loaders and telescopic handlers, we also offer complete equipment solutions from skid steer loaders to mass excavators and everything in between. Discover how JCB and your local JCB dealer are committed to Helping You Get the Job Done!® CONTACT YOUR LOCAL JCB DEALER TODAY TO FIND OUT ABOUT CURRENT OFFERS.

Kern Machinery 310 High St. Delano, CA 93215 661-725-3841 Fax: 661-725-0377

24526 Lerdo Highway Buttonwillow, CA 93206 661-746-6363 www.kernmachinery.com

Muniquip

N & S Tractor

3000 W. Capitol Ave. West Sacramento, CA 95691 866-417-4302 Fax: 916-375-2048 www.muniquip.com

1215 W. Glenwood Ave. Turlock, CA 95380 209-634-1777 Fax: 209-634-3128 www.nstractor.com

520 S. Mt. Vernon Ave. Bakersfield, CA 93307 661-833-9900

For more information about the full range of JCB Construction Equipment and to find the dealer nearest you, please visit www.jcb.com


Page 6 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Confusion Hill Realignment Target to Finish by October CONFUSION from page 1

of 571 ft. (174 m) and end spans of 348 and 436 ft. (106 and 132 m). The structure depth varies from 31.5 ft. (9.6 m) at the piers to 11.5 ft. (3.5 m) at the midspans and abutments, Paine said. The bridge is comprised of more than 15,000 cu. yds. (11,470 cu m) of concrete, some of which is high, early strength concrete, and nearly 5 million lbs. (2.2 million kg) of reinforcement. The foundations consist of 11 piles, each 5 ft. (1.5 m) in diameter and approximately 100 ft. (30.5 m) long, at each of the two piers. At each of the abutments are 16-in. (40 cm) diameter piles. During bridge pours a concrete delivery system pumped concrete approximately 255 vertical ft. (77 m) and another 285 horizontal ft. (86 m) at the extreme lengths, Paine said, adding a mobile concrete batchplant was located onsite. The pile caps at the bridge’s pier footings are nearly 50 by 36 ft. (15 by 10.9 m) and 10.5 ft. (3.2 m) deep. The architectural piers are nearly 25 by 19 ft. (7.6 by 5.8 m) at the base, but vary as they stair step in at two locations. The majority of the bridge’s deck is on a 5 percent incline with a 2 percent cross slope, according to Paine, who said at the peak of construction MCM had more than 60 employees working onsite. As of July 7 of this year, southbound traffic began using the new segmental bridge and new alignment, according to Frisbie. The northbound, three-span, box girder bridge has a main span of 229.3 ft. (69.8 m), end spans of 175.8 ft. (53.5 m) and was open for commuter use in late August. More than 4,400 cu. yds. (3,360 m) of concrete and more than 1.5 million lbs. (700,000 kg) of reinforcement comprise the bridge. The piers of the bridge were sloped 30 degrees from vertical and varied in dimensions from about 17 by 7 ft. (5 by 2.1 m), at the base, to about 17 by 14 ft. (5 by 4.2 m) at the top of the pier, Paine said. Because of the slope and the bridge cur-

vature, the pier was trapezoidal rather than rectangular. Aside from bridge construction, a thru cut that removed of more than 400,000 cu. yds of rock and soil was required in order to construct a new portion of highway. Blasting also was required to make way for the new highway realignment. During the thru cut and blasting, Cat 735 trucks hauled rock and soil across the completed north bridge. The Cat 735s were either rented or owned by subcontractor Ladd and Associates, who was responsible for structure excavation/backfill and roadway rock excavation, Paine said. Construction of the new highway also included the installation of two, steel soldier pile retaining walls with tieback anchors. The first wall is nearly 375 ft. (114 m) long and varies in lagging height, which reached as high as 20 ft. (6 m). The wall includes more than 300 ft. (91 m) of wide flange soldier pile and 43 tiebacks, and received an architectural sur-

face resembling rock formations. The second wall is 504 ft. (153 m) long and has a lagging height of up to 40 ft. (12 m). This wall contains 62 wide flange soldier piles, with a combined length of 3,100 ft. (944 m), and utilized concrete whalers to anchor each of the 77 tiebacks. At the point where the existing Route 101 meets new the alignment, MCM and Caltrans used nearly 3,748 tons (3,400 t) of shredded tires to raise the old highway to the height of the newly constructed highway. Known as tire derived aggregate, the recycled material is about half the weight per cubic foot of rocky soil and has a lower cost than other lightweight alternatives, such as expanded polystyrene blocks. The lower weight allowed the large arched culvert below the highway to handle the added road height without reinforcement. Reinforcing the culvert would have increased the project cost, and increased the development time, which would have delayed the start of construction, according

to a Caltrans release. Because the project site was in a remote area and involved the construction of 1.5 mi. (2.4 km) of new bridges and roadways, the project had little impact on the surrounding community. All aspects of the realignment project will be complete by the middle of October, Paine said. Besides Ladd & Associates, other subcontractors on the project included: CMC Fontana Steel, furnish/place reinforcement; Schwager Davis Inc, prestressing; Mercer Fraser, furnish concrete, base, and AC paving; Drill Tec, soldier pile walls; Pacific Coast Drillers, bridge CIDH piles; Finley Engineering Group, segmental construction engineering; Roadway Electrical Works, underground and bridge electrical and seismic; Apex Fence Company, metal beam guard rail installation and removal; and Traffic Solutions, striping and rumble strips. (This story also can be found on Construction Equipment Guide’s Web site at www.constructionequipmentguide.com.) CEG

Pictured is the completed North Bridge.

Hawthorne CAT, Laser West Positioning Form New Alliance Hawthorne CAT, an authorized Caterpillar dealer, and Laser West Positioning Inc., a Global Positioning Systems (GPS) and equipment company, recently formed a new alliance to offer GPS technology and service to contractors in San Diego and Hawaii. Based in Vista, Calif., Laser West Positioning Inc. sells GPS systems and laser machine control guidance equipment to contractors. The company also is the local distributor of Trimble products. Trimble is a provider of advanced positioning solutions that maximize productivity and enhance

profitability. Though best known for GPS technology, Trimble integrates a wide range of positioning technologies including GPS, laser, optical and inertial technologies with application software, wireless communications, and services to provide complete commercial solutions. Its integrated solutions allow customers to collect, manage and analyze complex information faster and easier, making them more productive, efficient and profitable. “This alliance will accelerate the introduction of solutions that will enable contractors to better manage the work site

and all the machines in their fleet,” said Tom Butler, owner and president of Laser West Positioning. “The teaming of our two organizations will further enhance and support our customer’s experience, productivity and profitability. Tom is extremely well respected in our industry and this alliance will produce tremendous customer satisfaction in support of our machine control and guidance initiative,” said Steve Sager, Hawthorne’s vice president of corporate sales and rental. For more information, visit www.hawthornecat.com.


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 7

Quality Used Power... Ready to Ship. Sold Worldwide.

0OWER 0LANTS s 81 S s ,OADBANKS s 0ORTABLE 0OWER s HZ HZ %NGINES #ATERPILLAR s $ETROIT $IESEL s #RESTCHIC s #UMMINS s 7AUKESHA

Email us for a complete inventory list of generator sets, individual engines and marine engines.

*OHN $UTCH

Jim Fellis

Used Equipment Sales Manager Phone: 858-974-6804 Email: jdutch@hawthornecat.com

Used Equipment Project Manager Phone: 858-974-6835 Email: jfellis@hawthornecat.com

% 7HEEL 4RACTOR 3CRAPERS 1997, CAB w/ AC, Push Pull, Good Condition, Ready to Work, 50% plus Tires SN: 5YR00239 5YR00240 5YR00248 5YR00251

&OUR AT EACH

Quality Used Equipment... Ready to Ship. Sold Worldwide.

#!4 $ 4 4RACK 4YPE $OZER 2006, 475 hrs., Tier 3, CAB w/ AC, SU Blade, Ripper

Email us for a complete inventory list of used equipment.

S/N 0KPZ01351

Ingersoll Rand (YDRAULIC #RAWLER $RILL 2005, 2554 Engine hrs, 669 Drifter Hrs, Dust Collector, Water Injection, Cummins 6CTAA 8.3 Liter Engine, 260 hp, 2 level drilling controls, Cab w/ AC. S/N 009278BA

© 2009 Caterpillar All Rights Reserved. CAT, CATERPILLAR, their respective logos, “Caterpillar Yellow” and the “POWER EDGE” trade dress, as well as corporate and product identity used herein, are trademarks of Caterpillar and may not be used without permission.

#RAIG "AKER

Jim Gilchrist

Ass’t Used Equipment Mgr. Tel: 858-674-7131 Email: cbaker@hawthornecat.com

Used Equipment Sales Rep. Tel: 858-674-7046 Email: jgilchrist@hawthornecat.com

www.hawthornecat.com


Page 8 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Placer • Siskiyou • Shasta Butte• Marin • Solano • Sonoma • Calaveras • Tuolumne • Kern • Glenn • Nevada • Orange • San Diego • Riverside •California... Los Angeles • San Bernardino • Santa Cruz • Trinity • Stanislaus • Inyo • Imperial • Fresno • Mendocino • Santa Barbara • El Dorado • Yolo • Contra Costa • Merced • Marin • Placer • Siskiyou • Shasta Butte• Marin • Solano • Sonoma • Calaveras • Tuolumne • Kern • Glenn • Nevada • Orange • San Diego • Riverside • Los Angeles • San Bernardino • Santa Cruz • Trinity • Stanislaus • Inyo • Imperial • Fresno • Mendocino • Santa Barbara • El Dorado • Yolo • Contra Costa • Merced • Marin Placer • Siskiyou • Shasta Butte• Marin • Solano • Sonoma • Calaveras •

‘Golden State’ Highway Lettings

The California Department of Transportation received bids for transportation-related improvement projects. Following is a list of some of the projects let. Counties: Orange, Riverside Contract Number: 12-0G0404. Location: In Anaheim, Yorba Linda and near Corona. Project: Widen freeway and bridges. Number of Working Days: 665. Contractors and Bid Amounts: • Brutoco Engineering and Construction Inc., Fontana, Calif. — $40,855,853. • Sema Construction Inc., Lake Forest, Calif. — $42,656,351. • Flatiron West Inc., San Marcos, Calif. — $42,672,469. • C.C. Myers Inc., Rancho Cordova, Calif. — $44,651,172. • Griffith Co., Santa Ana, Calif. — $45,552,886. • Skanska USA Civil West California District Inc., Riverside, Calif. — $46,650,867. • Riverside Construction Co. Inc., Riverside, Calif. — $47,781,072. • Chumo Construction Inc., Baldwin Park, Calif. — $49,256,254. • Diablo Contractors Inc., San Ramon, Calif. — $51,994,167. County: Shasta Contract Number: 02-378904. Location: Near Lakehead from 0.2 mi. north of Antler Summit overcrossing to 0.3 mi. north of Antler underpass. Project: Bridge replacement. Number of Working Days: 1300. Contractors and Bid Amounts: • Tutor Saliba Corp., Sylmar, Calif. — $124,677,700. • Flatiron Manson A Joint Venture, Benicia, Calif. — $142,510,910. • Balfour Beatty Infrastructure Inc. Golden State Bridge Inc., Fairfield, Calif. — $146,163,925. • M.C.M. Construction Inc., North Highlands, Calif. — $149,771,124. • Kiewit Pacific Co., Concord, Calif. — $157,069,098. County: Stanislaus Contract Number: 10-0G7704. Location: In Newman from Inyo Avenue to 0.1 mi. south of Jensen Road and in Patterson from Sperry Avenue to Ward Avenue. Project: Rehabilitate roadway. Number of Working Days: 45. Contractors and Bid Amounts: • Knife River Construction, Stockton, Calif. — $1,303,729. • Granite Construction Co., Watsonville, Calif. — $1,395,956. • George Reed Inc., Sonora, Calif. — $1,513,168. • Teichert Construction, Turlock, Calif. — $1,536,647.

Counties: Kings, Tulare Contract Number: 06-3568U4. Location: Approximately 0.5 mi. east of Hanford. Project: Convert two lane highway. Number of Working Days: 500. Contractors and Bid Amounts: • Flatiron West Inc., Benicia, Calif. — $45,178,321. • Granite Construction Co., Watsonville, Calif. — $45,849,382. • De Silva Gates Construction, Dublin, Calif. — $46,734,866. • R and L Brosamer Inc., Walnut Creek, Calif. — $48,832,380. • Coffman Specialties Inc., San Diego, Calif. — $48,865,000. • Teichert Construction, Turlock, Calif. — $49,029,348. • Security Paving Co. Inc., Sun Valley, Calif. — $49,596,165. • Diablo Contractors Inc., San Ramon, Calif. — $50,812,453. • Top Grade Construction Inc., Livermore, Calif. — $51,498,226. • Agee Construction Corp., Clovis, Calif. — $51,975,576. • Lees Paving Pave Tech JV, Visalia, Calif. — $54,568,289. • Emmetts Excavation Inc., Clovis, Calif. — $55,168,964. • Berry Wood JV, Selma, Calif. — $55,612,745. County: Kern Contract Number: 06-442534. Location: Near Lost Hills on Route 46 and Route 33. Project: Widen Route 46 and realign Route 33. Number of Working Days: 320. Contractors and Bid Amounts:

• Griffith Co., Bakersfield, Calif. — $22,999,250. • Security Paving Co. Inc., Sun Valley, Calif. — $23,114,827. • Papich Construction Co. Inc., Pismo Beach, Calif. — $24,280,820. • W. Jaxon Baker Inc., Redding, Calif. — $24,396,952. • Granite Construction Co., Watsonville, Calif. — $25,105,463. • Sukut Construction Inc., Riverside, Calif. — $25,320,405. • Teichert Construction, Fowler, Calif. — $25,547,195. • Sim J. Harris Inc., San Diego, Calif. — $25,705,000. • Sierra Nevada Construction Inc., Sparks, Nev. — $25,947,007. • John Madonna Construction Co. Inc., San Luis Obispo, Calif. — $26,566,133. County: Sonoma Contract Number: 04-4A8704. Location: Near Kellogg at Maacama Creek Bridge from 0.2 mi. west to 0.3 mi. east of Redwood Creek Bridge. Project: Replace bridges. Number of Working Days: 260. Contractors and Bid Amounts: • Viking Construction Co. Inc., Rancho Cordova, Calif. — $5,033,181. • Gordon N. Ball Inc., Alamo, Calif. — $5,112,449. • Golden State Bridge Inc., Martinez, Calif. — $5,306,393. • Granite Construction Co., Watsonville, Calif. — $5,396,537. • M.C.M. Construction Inc., North Highlands, Calif. — $5,666,666. • Shasta Constructors Inc. and Argonaut Constructors JV, Redding, Calif. — $5,767,612. • Disney Construction Inc., Pacifica, Calif. — $5,990,739.


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 9

>

Think. Big. Serious productivity demands serious thinking. Many of the numerous improvements in the K-Series came from the brightest minds in the industry - loader owners and users such as yourself. Armed with fresh insights from this Customer Advocate Group, we enlarged the cab, redesigned the cooling, enhanced the hydraulics, refined the ergonomics, and offered even more options. All with the goal of increasing productivity and uptime, while lowering daily operating costs. Owners, operators, and maintenance personnel will all benefit from big ideas found in the 844K loader.

Stop in today to your local California John Deere Dealer to see why this isn't just another loader.

N o t h i n g r u n s l i k e a D e e r e .™

COASTLINE EQUIPMENT www.coastlineequipment.com 6188 Paramount Blvd. Long Beach, CA 90805 562-272-7400 • Fax: 562-272-7444 12435 Foothill Blvd. Sylmar, CA 91342 818-890-3353 • Fax: 818-890-5013 1930 E. Lockwood St. Oxnard, CA 93036 805-485-2106 • Fax: 805-485-7963

888 East Ave. L-4 Lancaster, CA 93535 661-948-9993 • Fax: 661-723-5613 3216 Westminster Santa Ana, CA 92703 714-265-5500 • Fax: 714-265-5505

RDO EQUIPMENT www.rdoequipment.com 83-300 Avenue 45 Indio, CA 92201 760-342-8900 13625 Danielson Street Poway, CA 92064 800-905-1150

1950 Roemer Place Santa Maria, CA 93454 805-922-8329 • Fax: 805-922-4582

3275 Hwy 86 Imperial, CA 92251 800-464-4331

4252 Saco Road Bakersfield, CA 93308 661-399-3600 • Fax: 661-399-8782

20 Iowa Ave Riverside, CA 92502 800-494-4863

PAPE MACHINERY www.papemachinery.com Newark 800-231-2060 • 510-790-3600 Fax: 510-790-9120 Sacramento 800-227-3399 • 916-922-7181 Fax: 916-922-4532 French Camp 800-619-6319 • 209-983-8122 Fax: 209-983-1105

Fowler 559-834-4774 Fax: 559-834-4754 Rohnert Park 800-325-9401 • 707-584-9161 Fax: 707-584-4786 Gilroy 800-848-4150 • 408-848-4150 Fax: 408-848-5163 Redding 530-241-4555 Fax: 530-241-0619


Page 10 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Calif. Approves HUSS MK Retrofit System for Volvo Iron In late 2008, Volvo Construction Equipment entered into a strategic partnership with HUSS LLC to provide retrofit systems for Volvo construction equipment that will significantly reduce exhaust emissions. The HUSS MK system now has final approval from California for Volvo Tier III IEGR-equipped machines in that state. The HUSS MK system, approved for use on Volvo engines utilizing V-ACT technology with internal exhaust gas recirculation (IEGR), meets California’s CARB Level 3+ requirements. Volvo equipment owners can utilize the system to help comply with the “In-Use Off-Road Diesel Vehicle Regulation,” or to provide the best available control technology (BACT) for the newest machines in owners’ fleets. Previously, engines using any type of EGR had been excluded from applying exhaust retrofit technology in California. This has now changed with the recent system verification by the state. The HUSS retrofit system for Volvo equipment is capable of collecting up to 99 percent of diesel particulate matter (PM) emissions, substantially exceeding the California CARB requirements, according to the manufacturer.

time swapping filters due to the clogging and cleaning cycle of misapplied passive systems, according to the manufacturer. HUSS LLC, Palm Springs, Calif., is a specialist in exhaust aftertreatment for diesel engines with more than 20 years of experience in the manufacturing and servicing of diesel particulate filtration systems. HUSS

The Volvo/HUSS emissions reduction retrofit system may be installed on all Volvo equipment in customer fleets and in addition to improving the environment, customers using the system may be able to realize thousands of dollars in savings by keeping machines in their current fleets.

www.coastlineequipment.com 6188 Paramount Blvd. Long Beach, CA 90805 562-272-7400 • Fax: 562-272-7444

3216 Westminster Santa Ana, CA 92703 714-265-5500 • Fax: 714-265-5505

12435 Foothill Blvd. Sylmar, CA 91342 818-890-3353 • Fax: 818-890-5013

1950 Roemer Place Santa Maria, CA 93454 805-922-8329 • Fax: 805-922-4582

1930 E. Lockwood St. Oxnard, CA 93036 805-485-2106 • Fax: 805-485-7963

4252 Saco Road Bakersfield, CA 93308 661-399-3600 • Fax: 661-399-8782

888 East Ave. L-4 Lancaster, CA 93535 661-948-9993 • Fax: 661-723-5613

How the Retrofit System Works The retrofit system is equipped with a HUSS control unit that constantly monitors filter function to precisely control diesel PM loading and regeneration. This is an active filter regeneration system, accomplished through an integrated fuel burner system. Regeneration typically takes place after approximately 8 to 10 operating hours and is completed during breaks or shift change in 5 to 35 minutes with no external support needed. Engine exhaust backpressure is set to Volvo requirements. In addition to the reduction of 99 percent PM, there is no increase of NO2 or other secondary emissions. The HUSS technology is adaptable to low and high-horsepower equipment (up to 700 hp) providing reliable installations for both rubber tired and tracked machines. With the active system, there is no need to be concerned with exhaust temperature profiles, changing duty cycles, ULSD fuel, stocking extra filters or incur undue down-

was one of the first to have ARB verification and to establish system sales, technical support and components warehousing in California to serve the North American marketplace. A recent moving to upgraded facilities will now serve the North American market even better. Applications of the HUSS systems include construction and mining equipment, industrial and refuse trucks, transit and school buses, heavy-duty on-highway vehicles and stationary generator sets. A Cleaner Environment The Volvo/HUSS emissions reduction retrofit system may be installed on all Volvo equipment in customer fleets and in addition to improving the environment, customers using the system may be able to realize thousands of dollars in savings by keeping machines in their current fleets and avoiding the costly process of total engine replacement. They also may be eligible for state and federal grants and incentives by meeting ever-increasing emissions requirements. Retrofit now, receive available funding and earn double credits in some areas. For more information, call 828/650-2000 or visit www.volvo.com.


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • September 26, 2009 • Page 11

®

S DON'T MIS THE NEXT IA CALIFORN ENT! SUPPLEM ctober 15th O : g in s lo C tober 24th c O : g in h s li b Pu

THE CALIFORNIA STATE EDITION

ately Approxim

9,00i0 ed Qualif rs Buye

Introducing Construction Equipment Guide’s Newest Western Sales Manager, Frank Strazzulla. Call for Advertising or Editorial Information.

Toll Free 877-7CEGLTD 949-459-1767 • Fax: 949-203-2859 E-Mail: fstrazzulla@cegltd.com


Page 12 • September 26, 2009 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.