When ‘It wasn’t my fault, so pay me the
Pieter Oomens and Effie Dimos | July 2013 | Commercial Disputes and Transactions
A recent case shows that an otherwise straight forward claim arising from the sale and delivery of goods might be undone so as to thwart winding up proceedings. Creditors should be aware that standard form trading terms cannot deal with every possibility and agreeing to a customer’s supply schedule might have significant ramifications. A creditor’s statutory demand which refers to a debt which is not genuinely disputed may nonetheless be the subject of an offsetting claim which will make the demand ineffective. The plaintiff in the case, In the matter of GO Electrical Pty Limited [2013] NSWSC824, Class Electrical Services Pty Limited (‘CES’) was able to obtain an order to set aside a creditor’s statutory demand that was served on it by the defendant, GO Electrical Pty Limited (‘GO’). The application was successful not on the ground that there was a genuine dispute between the parties about the existence or the amount of the debt, but because it was found that CES had an offsetting claim arising from delays and other problems caused not by GO, but by the suppliers to GO. The case is also important because it gave an insight into the attitude of the Court in assessing an offsetting claim.
Background: In 2006, CES entered into a contract to purchase goods on credit from GO. Years after establishing the account, CES, which was an electrical contractor, ordered goods from GO so that it might install them on a building project. CES had been engaged on the project by the builder, Cockram. Commencing in mid-2011 and continuing until early 2012, CES placed in excess of $2 million worth of orders with GO. Critically, when placing orders with GO, CES indicated its required delivery times. GO prepared a schedule which it provided to its suppliers and sourced the goods from two particular suppliers.
TurkAlert
money!’ doesn’t quite cut it…
There were delays in the delivery of goods by GO’s suppliers such that the delivery times set by CES were not met. Additionally, Cockram advised CES that some of the goods which it had installed were faulty, not fit for purpose and required replacement. Cockram subsequently wrote to CES indicating that it would be withholding a substantial amount of money on the project and the cost of the audit and replacement of the faulty fittings would be withheld from monies outstanding to CES. Further, Cockram informed CES that it would no longer award any further work to CES as a consequence of CES’s failure to meet Cockram’s requirements on this project. CES alerted GO to the fact that it believed that it had a claim against GO because of the issues complained of by Cockram. At the same time, CES proposed a payment schedule (although that payment schedule contemplated that there would be some compensation to CES thereby reducing the amount of GO’s claim).
1