CONNELL NEWS
autumn 2018
ROTOKAURI bulk watermain The Rotokauri Bulk Watermain project covers nearly three kilometres, running from Pohutawaka Drive to the intersection of Aorangi Road and Te Wetini Drive in northern Hamilton. Watermains, stormwater utilities, wastewater and other services like power, gas and telecommunications exist in the area, which makes placing the new watermain a challenge. Key project features include approximately 827m of open trenching, 1898m of horizontal directional drilling, a sleeve under the railway and six connections to existing pipework. Drill Section Sub-contractors, CDS New Zealand Ltd, have done a brilliant job with three shots now complete. This has brought us from the end of Te Wetini Drive right through to Pukete Road, meaning more
than three-quarters of the total distance has been covered. The drilling so far hasn’t been without its issues, of course, but the team has stepped up, developing appropriate solutions every time. At one point during the project we dealt with sections selling after welding the 800m pipe string weighing a total of 78 tonnes. This meant we had to cut the pipe and use two of the 30 tonne excavators to manoeuvre and squash it into two sections, stretch it out and reweld it, before we could pull it in. On the first shot (400m long) the pulling head pulled off. The second shot (600m long) saw the pipe get stuck at 6m deep. On the third shot (800m long) it happened again, when the pipe got stuck 30m from completion. CDS’s crew, along with Connell’s staff, worked through the night and into the following day to get this string in. Racing against
the clock to get this pipe in the ground and avoid large penalties from property owners, CDS put their thinking caps on and with a few sheetpiles and a bit of concrete the drill rig was reset and the last 30m finally came in. This was a mammoth effort and a great result. The pull was one of the longest pulls in New
PIPELINES
Continued on page 2...
|
STRUCTURES
|
CIVIL
www.connellcontractors.co.nz