VA National Energy Progress Report

Page 1

Progress Report

onal Energy Progress Report

Department of Veterans Affairs/DeMaria Building Company

Na

DeMaria Building Company, Inc. reserves the right to alter content of this publication at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document. 2012 DeMaria Building Company, Inc. All rights reserved.


DeMaria Building Company, Inc. it’s about the PEOPLE, the PROCESS and the RESULTS


Table of Contents

Togus VA Medical Center Co-Generation Plant Augusta ME

pgs 4-5

VA Battle Creek Boiler Plant Replacement Battle Creek, MI

pgs 6-7

VA Battle Creek Co-Generation Plant Battle Creek, MI

pgs 8-9

VA Ann Arbor Co-Generation Plant Ann Arbor, MI

pgs 10-11


Togus VA Medical Center Co-Generation System Augusta ME

VA 701-RA-0044 Delivery Method: Design/Build

Project Team Contractor: DeMaria Building Company Architect: HGA Project Executive: Mark Brimmeier Project Manager: Ryan Molitor Project Superintendent: Tom LaMay Project Engineer: Zach Vizena Project Estimator: Brian Kelly BIM Coordinator: Aaron Tassell

Progress Report Safety: 0 Incidents 0 Lost Time 360 days without lost time incident

Schedule: Notice to Proceed: 9/01/02010 Contract Duration: 674 Calendar Days Contract Completion: 7/05/2012 Current percent complete: 80%

Current Status: Exterior: Metal Panels Complete except 18’ section left open for access Brick and glazing complete Interior: ESP installation is 90% complete Gasifier installed, including duct and trim items. Refractory installation is complete Economizer installed Grinder installed Dust collector installed Interior conveyors-Receiving conveyors installed

Upcoming Milestones:

4

Boiler hydro test 2nd week of April Phase 1 Electrical switch over in last week of March Catwalk steel starting last week of March


BIM Coordination Model

BIM Clash Detection Session

Exterior Elevation

Boiler, dust collection system and economizer

Exterior Elevation

Gasifier and Boiler

5


VA Battle Creek Boiler Plant Replacement Battle Creek, MI

W911XK-09-C-0036-FY09 Delivery Method: Design/Bid/Build

Project Team Contractor: DeMaria Building Company Architect: HGA Project Executive: Mark Brimmeier Project Manager: Eric Winquist Project Superintendent: Ken Kersanty Project Engineer: Rob Rowe Project Estimator: Brian Kelly

Progress Report Safety: 0 Incidents 0 Lost Time 844 days without lost time incident

Schedule: Notice to Proceed: 11/23/2009 Contract Duration: 1,100 Calendar Days Contract Completion: 11/16/2012 On-Schedule

Current Status: Steam tunnel to Vault 7 complete All Boiler set in place Excavation to Vault 10 complete Boiler observation platform construction underway Steam piping above catwalk on-going

6


Looking West at the New Boiler Plant

East elevation of new Boiler Plant with CoGen foundations

Looking West at the New Boiler Plant

Placing backfill over the steam tunnel east of Vault #3.

Placing concrete for steam tunnel walls from Vault to building

High and medium pressure steam piping along East catwalk

New Boiler and heating hot water piping

7


VA Battle Creek Co-Generation Plant Battle Creek, MI VA 701-C-0107 Delivery Method: Design/Build

Project Team Contractor: DeMaria Building Company Architect: HGA Project Executive: Mark Brimmeier Project Manager: Eric Winquist Project Superintendent: Ken Kersanty Project Engineer: Don Haueter Project Estimator: Brian Kelly

Progress Report Safety: 0 Incidents 0 Lost Time 60 days without lost time incident

Schedule: Notice to Proceed: 3/21/2011 Contract Duration: 630 Calendar Days Contract Completion: 12/20/2012

Current Status: Foundation Walls started Construction Documents at 90% BIM coordination started

8


BIM Coordination Model

Column line L

Start of Foundation Walls

Column line L south of fuel pit

Foundation

Fuel elevating pit 9


VA Ann Arbor Co-Generation Plant Ann Arbor, MI

VA 701-C-0177 Delivery Method: Design/Build

Project Team Contractor: DeMaria Building Company Architect: SSOE Project Executive: Mark Brimmeier Project Manager: Ryan Molitor Project Superintendent: TBD Project Engineer: Don Haueter Project Estimator: Tom Allen

Progress Report Safety: NA

Schedule: Notice to Proceed: 9/06/2011 Contract Duration: 630 Calendar Days Contract Completion: 7/26/2013

Current Status: Documents at 30% completion and being reviewed Authorization to move equipment inside existing plant

Upcoming Milestones: Approval of 30% design from SSOE 60% design submission by DeMaria Building Company

Â

10


Main Level Overall Floor Plan at 30% Design

11


www.demariabuild.com

DeMaria Building Company, Inc. reserves the right to alter content of this publication at any time without notice, and is not responsible for typographical or graphical errors that may appear in this document. 2012 DeMaria Building Company, Inc. All rights reserved.