Setting Reassessment Intervals R

Page 1

Reassessment Intervals

Tom Bubenik, CC Technologies , a DNV Company April 2008


Outline 

Basic considerations

Reassessment intervals for external corrosion - Bases for corrosion rate estimates - Regulations and Industry Standards - Basis for reassessment intervals - POE - In-line inspection comparisons - Other methods

Reassessment intervals for other defect types

Action items

Close

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 2


Basic considerations 

Philosophies - Justify a minimum reassessment interval - Set a performance based reassessment interval

Reassessment intervals based on … -

External corrosion Internal corrosion Seam weld defects/fatigue SCC Mechanical damage

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 3


Bases for corrosion rate estimates ď Ž

Regulations (49CFR195). An operator must: Assess the line pipe at specified intervals Conduct a periodic evaluation as frequently as needed to assure integrity Base the frequency on risk factors specific to its pipeline Establish five-year intervals, not to exceed 68 months, for continually assessing integrity - Establish intervals based on the factors specified, the analysis of the results from the last assessment, and the information analysis.

-

ď Ž

49CFR195 also says an operator may: - Justify an engineering basis for a longer interval, where the justification must be supported by a reliable engineering evaluation combined with the use of other technology that provides an equivalent understanding of the condition of the line pipe

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 4


Bases for corrosion rate estimates ď Ž

API 1160 states that the inspection intervals may be: - Based on actual depths of metal loss, and subsequent reinspections, the operator may be able to estimate a corrosion rate. - Based on estimated rates, reinspection intervals should be not more than half the remaining life of the deepest unremoved or unrepaired corrosion metal loss

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 5


Bases for corrosion rate estimates ď Ž

API 570 says: - These formulas may be applied in a statistical approach to assess corrosion rates and remaining life calculations for the piping system. Care must be taken to ensure that the statistical treatment of data results reflects the actual condition of the various pipe components. Statistical analysis employing point measurements is not applicable to piping systems with significant localized unpredictable corrosion mechanisms.

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 6


Bases for corrosion rate estimates ď Ž

NACE RP0502 (ECDA standard) says: - The corrosion growth rate shall be based on a sound engineering analysis. - When the operator has measured corrosion rate data that are applicable to the ECDA region(s) being evaluated, actual rates may be used. - In the absence of measured corrosion rate data, the values and methods provided in Appendix D should be used for rate estimates. These corrosion rates have been based on the free corrosion of ferrous material in various soil types.

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 7


Bases for corrosion rate estimates ď Ž

NACE RP0502 Appendix D also says - When other data are not available, a pitting rate of 0.4 mm/y (16 mpy) is recommended. - This rate represents the upper 80% confidence level of maximum pitting rates for long term (up to 17-year duration) underground corrosion tests of bare steel pipe coupons without CP in a variety of soils including native and nonnative backfill. - The corrosion rate may be reduced by a maximum of 24% provided it can be demonstrated that the CP level of all pipelines or segments being evaluated have had at least 40 mV of polarization (considering IR drop) for a significant fraction of the time since installation. - Polarization Resistance Measurements and coupons can be used under limited circumstances

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 8


Corrosion Rate Summary 

49CFR195 allows an operator to provide an engineering basis for a reassessment interval

API 1160 allows intervals based on estimated corrosion rates

API 570 allows use of a statistical approach to assess corrosion rates

NACE RP0502 allows the use of actual rates determined from successive in-line inspection runs, LPR measurements, or coupons

But what is the “real” corrosion growth rate…?

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 9


Bases for reassessment intervals 

In general, OPS looks for two things when establishing reassessment intervals: - A basis for the assumed degradation (corrosion growth) rate - A way to account for uncertainties in the initial assessment results

CC Technologies experience - OPS accepts most methods proposed to estimate corrosion growth rates – straight line, fixed values, etc. - OPS is more interested in how the uncertainties from the initial assessment (pig run) are addressed - OPS is prone to adding conservatisms on top of conservatisms (e.g., use a conservative growth rate estimate, coupled with an assumed maximum flaw size that takes into account tool error, to calculate a half-life that is then used as a basis for the interval)

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 10


Using corrosion growth rates to set re-assessment intervals 

Corrosion growth rates, whether they are deterministic or probabilistic, can form the basis for justifying a minimum reassessment interval or, eventually, establishing “performance based” intervals

Approaches used: - Deterministic - Probabilistic

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 11


Deterministic Models 

Approach - Calculate when the first defect will “fail” - Fixed growth rate, or rate based on pit-to-pit matching (or similar

Advantages - Quick and easy (deepest or most severe defect drives the analysis) - Can consider both leak and rupture with suitable model

Disadvantages - No clean way to address pig uncertainties, arbitrarily adding a tolerance to the reported depth (e.g., 10%) can be overly conservative - Pit-to-pit matching often leads to problems due to - Lack of correlation between runs - Reported depths that both increase and decrease - “Outliers” produce unrealistic growth rates

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 12


Probabilistic Models 

Approach - Growth rates can be deterministic, based on pit-to-pit matching (or similar), based on statistical comparisons of pig runs (SAC), or modeled statistically (Monte Carlo simulation) - Statistical model of pig accuracy (POE)

Advantages - Realistic treatment of pig inaccuracies - POE readily accepted by regulators

Disadvantages - More complex, requires “expertise” to establish corrosion growth rates - Same problems with pit-to-pit matching - SAC and Monte Carlo modeling not as well accepted by regulators

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 13


POE 

Probability of Exceedance (POE) - Simple model – assumes pig call list includes all relevant features (potential defects) - Bayesian model – considers probabilities of detection, identification, etc.

Simple POE model -

Most often used by CC Technologies and other contractors Considers all reported metal loss defects Grows defects using deterministic growth rates Uses accuracy of the pig to calculate the likelihood a defect depth or severity will exceed a threshold value - Pig accuracy can be based on published specifications or on dig data. - Establishes a baseline likelihood that a leak or rupture today - Estimates likelihood a leak or rupture will occur in the future based on operator’s repair strategy following an in-line inspection.

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 14


Pig Accuracy Estimate

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 15


Pig Accuracy Estimate 

A regression is used to establish pig bias based on dig results - Individual depths are adjusted based on regression or performance spec - Various approaches can used for regressions: - Linear, piece-wise linear, weighted, other

Same regression used to estimate error bands (e.g., standard deviation) - Standard deviation used to estimate likelihood defect depth or severity reaches a threshold for each pig call - “Leaks” predicted when depth reaches 80, 90, or 100% wt - Rupture predicted when failure pressure equals operating pressure - MOP typically used - Discrete point pressures can be incorporated - Results combined to give overall likelihood or likelihood along pipeline

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 16


Likelihood of Exceeding a Threshold

The probability that an in-line inspection call of 50% is really 70% or deeper is numerically equal to the area under the curve to the right of 70%

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 17


Combined results

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 18


Output ď Ž

Basic results are typically given as plots of likelihood versus time

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 19


Reassessment Interval 

POE = function of repair strategy and time

Interval based on a target POE - Consider target POE relative to current likelihood of leak or rupture

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 20


Bayesian POE 

Not covered in detail in this presentation

Uses probability of detection and sizing accuracy to recreate the most likely set of defects for a set of pig calls - Contains more defects than pig calls, especially for more shallow defects - Can account for missing data (e.g., due to a sensor bank failing during the inspection)

Can also handle incorrect identifications (e.g., metal loss due to corrosion reported as mechanical)

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 21


POE Developments (Simple or Bayesian) 

Segmented POE as a function of location along the line, discrete point pressures, and number and severity of pig calls - Using a “sliding window” approach to identify highest priority areas

Variable corrosion growth rates based on SME judgment - Commonly used by most contractors and pipeline companies

Corrosion growth rates determined from successive in-line inspection results. - Should provide operators with realistic corrosion growth rates provided inherent errors in pig calls are addressed

Multiple (successive) POEs used to “adjust” corrosion growth rates - … by comparing POE calculated from most recent inspection to that from an earlier inspection …

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 22


ILI based approaches


In-line inspection comparisons 

Most practitioners agree that pit-to-pit depth matching is not reliable when based on feature lists

Matching signals sometimes works but even PII’s RunCom™ has had significant difficulties

These difficulties are inherent in the inspection methodologies due to: -

Changes in tools and analysis algorithms Sensor position relative to defect Variations in magnetic properties Remanent magnetization, etc. etc.

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 24


Why use statistically based ILI comparisons? 

Corrosion is a constantly changing process - Local environments set up and change as the corrosion process takes place - It’s nearly impossible to predict

Pig data have been successfully used for years (decades) to identify and remove corrosion defects from pipelines. - “Normal” emphasis is on properly detecting and sizing the most significant defects - Results from successive inspections show trends - Comparing groups “windows” of inspection results can identify where corrosion growth is most likely: - Statistically Active Corrosion - Sliding-window analyses

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 25


Statistically Active Corrosion (SAC) 

For successive ILI runs, identify locations with sufficient statistical evidence of active corrosion growth

Performed by progressively moving a specified window length along the pipeline and evaluating pig call depths within each window.

A median and other statistically valid measures are calculated for each valid window in each of the selected ILI pig runs using extreme value statistics.

Valid windows are then matched across the selected pig run combination, and for these matched windows a corrosion rate is determined using the median values and the time interval between the pig runs.

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 26


Statistically Active Corrosion (SAC) (cont’)

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 27


Statistically Active Corrosion (SAC)

•For each window, fit an extreme value distribution to the max pig call depth in each 1 foot window. To use SAC, a minimum number of pig calls is needed •Determine the median value and move on to the next foot window © Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 28


Statistically Valid Corrosion 

Deterministic or statistically described corrosion growth rates along the pipeline could be incorporated in the POE process.

Not yet implemented

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 29


Multiple ILI Run Analysis 

Use initial summaries for general comparison - If the overall results aren’t consistent, the local results won’t be

Perform joint matching and data alignment - Most pig runs can be aligned each other using girth welds locations - Aligning pig data with as-builts also straightforward - Aligning data with aboveground measurements often problematic - GoogleEarth™ or similar programs help greatly even when survey data are not well GIS’ed

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 30


Line wide comparisons 

Orphan Joints: Matched

2004 Orphan

2007 Orphan

2004 MFL

2007 MFL

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 31


Line wide comparisons 

Orphan joints are expected, especially as newer tools increase their sensitivity to smaller defects

Analyze orphans in both runs - Joints in first inspection but not the second should be (mostly) explainable - Joints in second inspection but not first must be analyzed - Depth, length, width, area

Using average or “typical” comparison metrics helps identify outliers - For example, if the new inspection has 5 times the number of calls as the first, but some joints have 100 times the first, the latter must be evaluated

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 32


Multiple ILI Run Comparisons 

High-Level Comparison

Overview Category Date Tot. Length Tool Velocity Tool Coverage Tool Technology Min. Reporting Threshold #Joints #Ext. ML Calls #Int. ML Calls # Dents # Ovalities # Appurtenances # AGMs # Bends # Casings SMYS MAOP/MOP Min Burst Pressure (0.85dl) (psi) Min Burst Pressure (EA) (psi) Quality # Deposits # Echo Loss # Ext ML with quality issue # Int ML with quality issue # Dents with quality issue # Ovalities with quality issue # Bends with quality issue # Casings with quality issue # Other

© Det Norske Veritas AS. All rights reserved

External Metal Loss

Laminations

Total Ext. Calls Top Side Ext. Calls Bottom Side Ext. Calls Max Ext ML Calls in one joint # Calls w/in 2ft of GW # of ERF values > 1 # of ERF values > 1 when MAOP = 72%SMYS Max Ext. CGR based on linear growth since manufacture Minimum Remaining Life # Immediate Condtions (CFR 195) # 60-Day Conditions (CFR 195) # 180-Day Conditions (CFR 195) # 60-Day Conditions (CFR 195)

Internal Metal Loss

Total Features # Joints w/Laminations # Laminations per mile # Laminations making surface contact # Laminations associated with a GW # Laminations w/in 2 ft of GW Max # Laminations per joint

Ovalities Total Features # Joints w/Ovalities # Ovalities per mile # Top Side (above 4-8:00) # Bottom Side (below 4-8:00) # <2% OD # >2% OD # W/ML in Prox (+/- 3ft)

Appurtenances

Total Int. Calls Top Side Int. Calls Bottom Side Int. Calls Dents Max Int ML Calls in one joint Total Features # Calls w/in 2ft of GW # Joints w/Dents # of ERF values > 1 # Dents per mile # of ERF values > 1 when MAOP = 72%SMYS # Top Side (above 4-8:00) Max Int. CGR based on linear growth since manufacture # Bottom Side (below 4-8:00) Minimum Remaining Life # <2% OD # Immediate Condtions (CFR 195) # >2% OD # 60-Day Conditions (CFR 195) # W/ML in Prox (+/- 3ft) # 180-Day Conditions (CFR 195) # Multidents # 60-Day Conditions (CFR 195) # 60-Day Coniditions (CFR-195) # 180-Day Coniditions (CFR-195)

04 September 2009

Total Features # Launcher # Receiver # Flanges # Valves # Taps # Tees # Other

Slide 33


Pit-to-pit matching 

Ground rules need to be established - Clustering rules and depth thresholds must be considered

Types of matches - One to One - One to Multi - Multi to Multi

( to ) ( to ) ( to )

Considerations: - Tool tolerances - Tool orientation shift - Anomaly origin

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 34


Other considerations 

Most successive inspections show indications that grow and shrink (often in similar numbers)

Any outliers should be evaluated (those that grow substantially as well as those that shrink substantially) - Significant differences mean the defects did change or the defects were hard to analyze or the signals changed for some unidentified reason

Basing corrosion growth rates on this type of comparisons will require active learning - Pit-to-pit matching, if successful, would allow a statistical description to be made of the corrosion growth rates

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 35


“Binning” can be used to further quantify corrosion rates 

Is corrosion preferentially attacking welds? (girth or longitudinal seam) Do isolated pits growth faster than more generalized corrosion?

ML Dist to GW 10%

5%

MP 517 Int ML -- Individual & Clusters Cluster GW

12:00

GW

Individual

0%

11:00

0-1ft

10:00

1-2ft

2-3ft

3-4ft

4-5ft

5-6ft

9:00

Orientation (hh:mm)

8:00

7:00

6:00

5:00

4:00

3:00

2:00

1:00

0:00 517.379

517.382

517.384

517.387

517.389

517.392

Line Mile Post

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 36


“Report Card”

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 37


Further Capabilities (con’t) 

60%

Customizable, scrollable charts

y = 0.8682x + 0.0593 R2 = 0.6628 50%

If field data available, can match tool to field measurement

Field

40%

30%

20%

10%

- Linear regression can give Probability of Exceedence (POE)…

0% 0%

10%

20%

30%

40%

50%

Reported

Depth (%)

Ext ML Depth Comparison

75%

2003 2004

50% 25% 0% 28000

28800

29600

30400

31200

32000

Chainage (ft) © Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 38


Integrating ILI Data with Other Data Sets 

Aboveground Survey Data - Use ILI data in conjunction with CIS (and DCVG) data to broadly categorize the pipeline - For example, use the data to identify the xx% of the line that is not likely to corrode faster than, say, 2 to 4 mills per year. - These pits, unless very deep to begin with, are not likely to fail or significantly impact POE values

Soils Data - Certain soil pH, texture, drainage, etc. characteristics can lead to coating degradation

Pressure Data - Creating pressure profiles throughout the pipeline based on elevation. - Used to define failure pressures along the line for POE calculations - Hydrotest results could also be incorporated

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 39


Robust Data Integration

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 40


Other rationale for reassessment intervals 

All methods require unusual circumstances to be identified and treated separately - Stray current corrosion - MIC

Linear polarization resistance measurements - Produces local information on corrosion rates without cathodic protection. - Rules of thumb used to address CP

Coupon monitoring (internal and external) - Placement critical, especially for internal corrosion

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 41


Reassessment intervals for other conditions 

SCC - separate presentation - Accepts/allows “chicken scratch” as non critical - If you look hard enough, you will eventually find some - Sets reassessment and/or other mitigation as a function of conditions found - Disbonded coating only - Disbonded with reduced pH electrolyte - Non significant SCC - Significant SCC - Method is evolving - Lessons learned need to be fed back into the selection process for exploratory excavation programs

NACE SCCDA provides limited guidance - Finding SCC usually triggers a hydrotest requirement

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 42


Reassessment intervals for other defects 

Seam weld defects - Gas guys use a one time test as basis for not reassessing - “We don’t cycle our lines” (right) - Liquid guys base assessment intervals on rules of thumb or fatigue analyses - Rules of thumb: - Baker categories of fatigue loading severity and/or - Using ASME type criteria - Fatigue analyses - Deterministic. Generally based on worst case conditions; corresponding reassessment intervals are very conservative - Probabilistic. - Basic PCStat and similar use one pressure distribution and an initial defect population based on the most recent hydrotest, etc. - More advanced methods use discrete point pressure conditions and attempt to quantify defect population present from day 1. -

© Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 43


Reassessment intervals for mechanical damage ď Ž

Some operators are attempting to use one ILI (caliper) run to remove all dents meeting OPS repair requirements, then considering the remaining dents to be static.

ď Ž

Few operators have programs in place to match subsequent pig runs to initial runs, looking for changes

Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 44


Š Det Norske Veritas AS. All rights reserved

04 September 2009

Slide 45


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.