Cloud for europe projekt ja hange

Page 1

Cloud for Europe – challenging the European market for public administrations Marit Lani, Norien Kuiper Tallinn, 27 November 2014

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Agenda 1. 2. 3. 4. 5. 6.

2

Project objectives Main deliverables and expected results Pre-commercial procurement tender Tender timeframe What is in it for Estonia? How to engage?

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Elevator Pitch

Public sector cloud use as a collaboration between public authorities and industry through pre-commercial procurement 4

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Our Mission Cloud for Europe brings together public authorities and industry to support public sector cloud use. • Identify obstacles for cloud use in the public sector • Define services that overcome those obstacles • Procure research from industry to find innovative solutions for cloud services

5

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Who we are

6

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


1. Project Objectives • Enable public sector cloud adoption in open dialogue between public sector and industry • Address concerns on data protection, security, legal and contractual aspects

• Support related research from industry • Use of pre-commercial procurement as an instrument for innovation in the public sector

7

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


2. Major Public Deliverables (1/2) • Legal studies • Legal implications of cloud computing on public authorities (May 2014) • Legal conclusions of the PCP process (November 2016)

• Gap analyses • Standards, Normalisation and Certifications Associated (May 2014) • Public sector study (coming soon) • Study of market vendors’ offering and public administrations’ requirements (coming soon)

8

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Major Public Deliverables (2/2) • PCP tender • Services catalogue (March 2014) • Tender pre-information notice (May 2014) • Public cloud PCP tender documentation (coming soon)

• Validation • Certification framework & evaluation methodology (2015) • Evaluation reports for solution selection, prototypes and test products (2015-2016)

• Dissemination • Communication packages for industry and public sector (October 2014 + yearly updates) 9

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Expected Outcomes • Public sector in Europe is empowered to procure cost-effective, secure and reliable cloud services • Pre-commercial procurement terms, do's and don'ts, opportunities and pitfalls are understood • Industry prepared through the PCP research and experience to meet public sector needs

10

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Public Sector Needs

Public sector can challenge industry to develop new and better solutions that respond to public sector needs for which there is no cut-and-dry answer yet

11

Modernise internal operations of public services to make them run more efficiently

Improve the external quality of public services to the citizens

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Initial Service List Overview Piloting Services 1. Basic Communication 2. Document Mgmt & Collaboration 3. Customs Supply Chain 4. Customs Data Pipeline 5. Legislation-Aware Storage 6. European Citizen Initiative 7. Archive as a Service 8. Secure Personal Data and Document Vault 9. Documents and Files Interoperability Node 10. eDocument Service 11. Restful Secure Distributed Collaboration Tools 12. Legislation Executing Cloud Services 13. Personal Digital Asset Service 12

Horizontal Services 1. 2. 3. 4. 5. 6.

7.

eID as a Service Encryption as a Service Independent Third Party Assurance Public Administration Cloud Services Broker Cloud Certification as a Service Resilient OpenSource Cloud Services Stack Changing the Cloud Provider

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Final Services Selection • Federated Certified Services Brokerage for EU Public Administration Cloud • Secure Legislation-Aware Storage • Legislation Execution

13

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Federated Certified Brokerage Status quo

Issues to be solved

• Cross-border cloud services must be secure in terms of country and EU legislation, privacy protection and security

• Interoperability (service governance, data portability, identity propagation)

• Current fragmentation can be overcome by federated EU public administration cloud • Dynamic real time crossborder service certification monitoring

14

• Service certification (architecture of components, automated certification) • Legislation awareness (legislation compliance, definition and assessment, interface for legislative changes propagation)

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Secure Legislation-Aware Storage Status quo • Limited service offers for legislation awareness and security mechanisms to ensure integrity • Encryption performed by the user or cloud provider claims to encrypt • Cloud storage offering often not clearly perceived as legislation compliant • Multi-legislation requirements difficult and expensive to satisfy 15

Issues to be solved • Establish trust by contractual means • Simplify selection/procurement of legislation compliant cloud (storage) services

• Create tools to manage citizen access rights to personal data in a legislation compliant way • Tackle multiple regulations concerning the storing of data: archiving, disclosure, and restricted access to backups

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Legislation Execution Status quo

Issues to be solved

• Some legal barriers lead to no-go decisions for cloud adoption

• Developing a cloud service that meets requirements imposed upon cloud actors by national or international legislation

• For sensitive data only private or community clouds are used

• Example: no automatic notification of unauthorised access to data owner and service provider

Possible solutions

• A framework (methodology, guidelines, specifications) • Generic services to be combined with business services

• Services, integrated with business services 16

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


3. Pre-Commercial Procurement (PCP)

PCP is one particular approach for procuring R&D services only, which enables public procurers to:

Develop solutions for concrete public sector needs, whilst comparing/validating alternative solution approaches

17

Share risks and benefits with participating companies in a way that does not involve State Aid

Create optimal conditions for wide commercialisation of R&D results

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Project Phases Tender preparation (14 months)

PCP operation (18 months)

Sharing (6 m.)

18

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


PCP Operation Tender prep (14 months)

PCP operation (18 months)

1. Solution exploration (4 months)

Sharing (6 m.)

• Tendered through functional specification • Framework contract governs all 3 phases

• Industry keeps IPR

Consortium A

2. Prototype (8 months)

Consortium B

Consortium A

Company C

Company C

Consortium A

Company D

Company D

Company C

19

3. Test Products / Pilot (6 months)

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Solution Design Tender release (OPEN PROCEDURE)

Between tender release and phase 1

1. Solution exploration

Consortium A • Submission of offers • Appointment of evaluation committees • Initial offer evaluation • Selection of companies/consortia

Consortium B

Company C Company D

20

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Prototype Development 1. Solution exploration (3 months)

Consortium A

Consortium B Company C

Company D

21

Between phase 1 and 2

• Invitation letter to submit a technical offer for phase 2 (Prototyping) RESTRICTED PROCEDURE • Appointment of evaluation committees • Selection of companies/consortia

2. Prototype

Consortium A

Company C

Company D

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


First Test Series Production 2. Prototype (7 months)

Consortium A

Company C Company D

22

Between phase 2 and 3

• Invitation letter to submit a technical offer for phase 3 (test products/pilot) RESTRICTED PROCEDURE • Appointment of evaluation committees • Selection of companies/consortia

3. Test products / Pilot

Consortium A Company C

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Joint cross-border PCP Combining the procurement actions of all the contracting authorities

Only one tender published on behalf of all participating authorities (in English)

Only one entity awarding the resulting R&D service contracts for all PCP phases on behalf of all participating authorities (Lead Procurer: AGID, Italy)

23

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Risk-Benefit Sharing • IPRs shared: ownership rights for companies – free usage rights and right to license for public procurers • Payment: awarded bidders are paid for each phase • No state aid: the aid element should be excluded through the contract – when the public purchaser buys R&D services at market price, there are no advantages

24

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Shorter time to market Wider market size

Shared risks and benefits

25

Better quality products Opportunity to share development risks with suppliers – license free use for procurers

FOR CITIZENS & POLITICIANS

International leadership in new markets

FOR PUBLIC PROCURES

FOR INDUSTRY

Benefits Quality and efficiency of public services Highly qualified employment Attracting foreign investment Optimising public R&D spending

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


4. Timeframe Joint PCP Procedure Phase

Month

Tender pre-notice

May 2014

Tender release

November 2014

Initial offer evaluation

26

Solution selection

~ 4 months

Prototype selection

~ 8 months

First test product selection

~ 6 months

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


5. What is in it for Estonia? Estonia: • Can learn from our experience with PCP • Can use project deliverables, which are publicly available on the Cloud for Europe website • Can, in the end, buy and use the products that come out of the PCP for the three lots • Can use the Cloud for Europe network of people and information resources • Can inform the Cloud for Europe partners on cloud computing in Estonia 27

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


6. How to engage? • Visit www.cloudforeurope.eu • Join Cloud for Europe stakeholder mailing list www.cloudforeurope.eu/stakeholder-area • Send questions to info@cloudforeurope.eu • Follow us and engage in discussions @cloudforeurope group: Cloud for Europe

28

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Contact Linda Strick Project Coordinator Phone: +49 (0)30 3463 7224 Email: linda.strick@fokus.fraunhofer.de Fraunhofer FOKUS, Berlin www.fokus.fraunhofer.de/en/elan Norien Kuiper IT architect Phone: + 31(0)6 1859 6886 Email: ej.kuiper@belastingdienst.nl Netherlands Ministry of Finance Tax and Customs Administration 29

Marit Lani Project Manager Phone: +372 5656 8420 Email: marit.lani@ega.ee e-Governance Academy

. This project is partially funded by the European Union’s Seventh Framework Programme: FP7-ICT-2013-10 and Grant agreement no: 610650


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.