KCI
NEW TERMINAL cover A world-class experience…coming soon
AGENDA • Project Updates • Project Timeline • Procurement Activities • Groundbreaking
PROJECT UPDATES
KANSAS CITY STRATEGIC PARTNERSHIP PROGRAM • Graduation: Thursday, April 4, 2019 @ Grand Street Cafe 11:15 AM • 25 graduates
EARLY SITE TESTING • Part of Early Enabling Work • Placing Auger-cast Test Piles • Load Capacity Testing for Deep Foundations under the Terminal and other Structures
TIMELINE
NEW TERMINAL TIMELINE
New Terminal Groundbreaking Ceremony
Schematic Design Begins
MOU Approved
2017
2018
Design Validation Complete
Environmental Assessment Begins
Environmental Assessment Approval
Terminal A Demolition, Utility Work, Road Work
2019
Complete Roadway Detours and build permanent roads to Terminals B & C Begin Garage Construction Start Elevated Roadway Construction
2020 2021 2022 2023
Structural Work Begins
Concept Design Complete Finalize Development Agreement
New Terminal Grand Opening
Construction Begins on New Terminal
Complete Demolition of Terminal A
Complete Procurement of all major procurement packages
Completed Activities Finalize Financing Plan
Execute Airlines Use & Lease Agreement
Future Activities
DESIGN SCHEDULE MILESTONES MILESTONE
DATE
Schematic Design
August 2019
Underground Concrete & Waterproofing Bid Package
August 2019
Structure & Enclosure Bid Packages
September 2019
Civil Airside & Landside Bid Packages
November 2019
Design Development
December 2019
CONSTRUCTION SCHEDULE MILESTONES MILESTONE
DATE
Demolition
April 2019
Roadway Work Starts
April 2019
Utility Work Starts
May 2019
Auger Cast Piles
July 2019
Below Grade Concrete & Underground Utilities
August 2019
Elevated Structure
November 2019
• Video
PROCUREMENT
LOCAL PROJECT PARTNERS EG Tech
MJ Builders Transformation Consultants, Inc.
Kansas City Industrial Development Authority
Astra Enterprises
Michele & Associates
Craig T. Watson, AIA Whatever It Takes Electrical Contractors, LLC
Group 2 Procurement Awards – Approx. $7 M & 55% M/WBE Demolition & Abatement of Terminal A and Garage Richardson Hauling WBE - Fuel Supply
WBE - Off-site Trucking
MBE/WBE - Off-site Trucking, Labor, Supervisions, & Grading
MBE Trash Dumpsters
MBE - Cut, Cap, and Make-Safe Utilities WBE - Construction Entrance & Erosion Control WBE - Fencing and Maintenance of Traffic MBE - Temp. Electric and Data Service
PROCUREMENT OPPORTUNITIES Group #
Name/Type
Bid Due Date
2A
Earthwork, Utilities, General Conditions
Closed
2A
Excavation & Boring for Mechanical Piping
Closed
2A
Boring for Electrical Ductbanks
Closed
3A
Baggage Handling System
Closed
3
Auger Cast Test Piles
Closed
3
Auger Cast Piles
April
4
Elevators, Retaining Walls, Landside Roadways
June 2019
5
Subgrade Concrete
August 2019
6
Steel, Curtain Wall, Low Voltage, MEP Equipment
September 2019
7
Precast Road, Sitework, CUP
October 2019
8, 9, 10
Drywall, Finishes, Metals, Millwork, etc.
Q1 2020
GROUNDBREAKING