Projects Workshop - ZESA

Page 1


ZIMBABWE ELECTRICTY SECTOR

ZESA HOLDINGS STRATEGIC RESPONSE TO

AGENDAFOR VISION 2030

ENERGY SECURITY INVESTMENTS:

THE NEED TO ADDRESS THE POWER PROJECT INVESTMENT RISK MATRIX

STATUS OF MITIGATION MEASURES

CAPACITY RISK PPA Cost Reflective Tariff Granted (December 2023) (YES)

CURRENCY RISK PPA+GIA Currency Guarantees (Still Pending On Currency Risk) (NO)

IMPLEMENTATION RISK GIA (GPSA) Current GIA’s Are Not Bankable (Still Pending On Currency Risk) (NO)

CAPACITY AND CURRENCY RISKS

RETAIL TARIFF TREND ANALYSIS 2019-2023

THE VISION 2030:

NDS1 TARGET: TOTAL ENERGY SECURITY

TO END LOAD SHEDDING AND POWER IMPORTS BY DECEMBER 2025

NEW POWER GENERATION PROJECTS UNDER CONSTRUCTION

DEVELOPERS

THE VISION 2030:

NDS1 TARGET: TOTAL ENERGY SECURITY

TO END LOAD SHEDDING AND POWER IMPORTS BY DECEMBER 2025 NEW

GENERATION PROJECTS UNDER CONSTRUCTION:

THE VISION 2030:

NDS1 TARGET: TOTAL ENERGY SECURITY

TO END LOAD SHEDDING AND POWER IMPORTS BY DECEMBER 2025

NEW POWER GENERATION PROJECTS UNDER CONSTRUCTION:

DEVELOPERS (IPP+CPP)

Kariba Floating Solar (IPP) Project

Hwange

SUMMARY OF CONSTRUCTION PROGRESS

Total Construction in Progress (3 000MW)

Awaiting Ground Breaking Ceremonies (1 020MW)

Awaiting ZIDA + Cabinet Approvals (450MW)

Now Concluding Financial Close (800MW)

TOTAL BY DECEMBER 2025 (2 500MW) (New)

TO ABBREVIATIONS

TRANSMISSION PROJECTS FOR VISION 2030

INVESTMENT

PARTNER PRODUCTS OR SERVICES INVESTMENT STRUCTURE APPROVAL STATUS CONTRACT

DELIVERY DATE CURRENT STATUS

A Power Cables and Conductor Manf.. PPP (EPC + F) JV Established (Evaco Cables (Pvt) Limited) July 2025 Plant Design, Board Appointed

B Smart Meters and Low Cost Laptops PPP (EPC + F) MOU Signed and EOI Submitted. August 2025 Development of Detailed Proposal.

B Solar Parabolic Troughs Manf.. PPP – (EPC) Agreement Signed at COP 28 June 2025 SPOC+ PRAZ Review and Feasibility Study

C Distrib. Products and Smart Meters PPP + Technology Transfer MOU Signed Awaiting ZIDA and PPP March 2025 Plant Design, Feasibility DueDiligence Underway

D Distrib..+ Manf.. of Lithium Ion Batteries International Distributorship MOU Signed. March 2025 Agreement Under Negotiation

E Inverters and Energy Storage International Distributorship MOU signed. March 2025 Agreement Under Negotiation

F Assembly of Heavy Duty EV Trucks International Distributorship MOU signed March 2025 Agreement Under Negotiation

G HV Transmission + Distribution Line PPP (EPC + F), Subcontracting .

BATOKA HYDRO POWER PROJECT

ZAMBIA - ZIMBABWE

Investment Risk Matrix and Legal Framework for x-Border IPP and BOT Investments

A Case Study in Africa Country Risk with Available Mitigation 2400MW Batoka Hydro Power Project

Presentation By DR SYDNEY ZIKUZO GATA - EXECUTIVE CHAIRMAN

ZESA HOLDINGS - ZIMBABWE 2022

Industry

Restructuring

Political Force

Majeure

Enforcement Risk (***)

Inflation and Monetary Policy

Interest Rate

Currency Exchange and Repatriation

Policy

Legal and Regulatory Risk

Permits and Licences

Plant and Equipment

Breakdown

Market and Trading System

Market Demand

PPA: Revenue Risk

Transmission and Trading Cost

Business and Economic Risk

Project Risk Matrix

Operation Risk

Fuel Supply

Fuel Price

PPA: Currency Risk

Escalation and Exchange

Rates

Project-Quality & Performance

Construction

Period Risk

Local TechnoIndustrial Capacity Risk Zambezi Hydrological Risk (***)

Environmental And Emissions Compliance O&M Cost Escalation O&M

Permitting Consents and Approvals

Construction Cost

Completion Risk

Program Over-run

BATOKA

Debt

CURRENT ELECTRICITY TRADING STRUCTURE (Commercial Risk Mitigation)

BATOKA(Genco): Generates and Sells Electricity Units to Electricity Market Operators (“EMOs”)

Power ZESCO-ZESA-SAPP Bulk Purchasers; Transmission and Trading Companies For ALL SAPP Electricity Trading.(“EMOs”)

Power Cash Markets (*) ZESCO + ZESA Prepayment Markets + SAPP Bilaterals

Post Payment Markets (**) (Maximum Demand) High Capacity Consumers:-: Large Commercial, Mining And Industrial Companies

FAILED ELECTRICITY TRADING STRUCTURE

Commercial Risk)

Imports at 9USc/kWh

EMERGING ELECTRICITY MARKET STRUCTURE (Commercial Risk Mitigation)

Bankable PPA’s

Competent Power Producers (Genco): Generates And Sells Electricity

Units to Competent Markets

Dispatch Wheeling

ZESCO-ZESA-EDM Bulk Dispatch And

Transmission System Operators And Wheeling Companies

Dispatch

Competent Primary Anchor Markets (*)

Dependable Revenues

Wheeling

High Capacity Consumers:Large Commercial, Mining, Smelting And Industrial Companies Secondary Markets

Public Utility Prepayment Markets + SAPP Bilaterals

Transmission UOS Service Charges

Legal, Regulatory and Environmental Risk Mitigation

• “Measures On Africa Country Risk”

• Upgrade current “IPP POLICY FRAMEWORKs” into IPP Laws.

• ‘

• Ring-fence and Quarantine IPP Projects from legal & regulatory risk through a “SPECIAL IPP LAWs” which carry “ Direct Authority of Parliament and The Constitution”.

• Dispute Resolution Process and Procedure which has provisions for realistic compensation, executed in a “NEUTRAL JURISDICTION”. with upfront agreement on ”ALLOCATION & PRICING “ of Risk.

THE Security package

THE END

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.