CAPACITY RISK PPA Cost Reflective Tariff Granted (December 2023) (YES)
CURRENCY RISK PPA+GIA Currency Guarantees (Still Pending On Currency Risk) (NO)
IMPLEMENTATION RISK GIA (GPSA) Current GIA’s Are Not Bankable (Still Pending On Currency Risk) (NO)
DEVELOPERS
NDS1 TARGET: TOTAL ENERGY SECURITY
TO END LOAD SHEDDING AND POWER IMPORTS BY DECEMBER 2025
NEW POWER GENERATION PROJECTS UNDER CONSTRUCTION:
DEVELOPERS (IPP+CPP)
Kariba Floating Solar (IPP) Project
Hwange
SUMMARY OF CONSTRUCTION PROGRESS
Total Construction in Progress (3 000MW)
Awaiting Ground Breaking Ceremonies (1 020MW)
Awaiting ZIDA + Cabinet Approvals (450MW)
Now Concluding Financial Close (800MW)
TOTAL BY DECEMBER 2025 (2 500MW) (New)
INVESTMENT
PARTNER PRODUCTS OR SERVICES INVESTMENT STRUCTURE APPROVAL STATUS CONTRACT
DELIVERY DATE CURRENT STATUS
A Power Cables and Conductor Manf.. PPP (EPC + F) JV Established (Evaco Cables (Pvt) Limited) July 2025 Plant Design, Board Appointed
B Smart Meters and Low Cost Laptops PPP (EPC + F) MOU Signed and EOI Submitted. August 2025 Development of Detailed Proposal.
B Solar Parabolic Troughs Manf.. PPP – (EPC) Agreement Signed at COP 28 June 2025 SPOC+ PRAZ Review and Feasibility Study
C Distrib. Products and Smart Meters PPP + Technology Transfer MOU Signed Awaiting ZIDA and PPP March 2025 Plant Design, Feasibility DueDiligence Underway
D Distrib..+ Manf.. of Lithium Ion Batteries International Distributorship MOU Signed. March 2025 Agreement Under Negotiation
E Inverters and Energy Storage International Distributorship MOU signed. March 2025 Agreement Under Negotiation
F Assembly of Heavy Duty EV Trucks International Distributorship MOU signed March 2025 Agreement Under Negotiation
G HV Transmission + Distribution Line PPP (EPC + F), Subcontracting .
BATOKA HYDRO POWER PROJECT
ZAMBIA - ZIMBABWE
Investment Risk Matrix and Legal Framework for x-Border IPP and BOT Investments
A Case Study in Africa Country Risk with Available Mitigation 2400MW Batoka Hydro Power Project
Presentation By DR SYDNEY ZIKUZO GATA - EXECUTIVE CHAIRMAN
ZESA HOLDINGS - ZIMBABWE 2022
Industry
Restructuring
Political Force
Majeure
Enforcement Risk (***)
Inflation and Monetary Policy
Interest Rate
Currency Exchange and Repatriation
Policy
Legal and Regulatory Risk
Permits and Licences
Plant and Equipment
Breakdown
Market and Trading System
Market Demand
PPA: Revenue Risk
Transmission and Trading Cost
Business and Economic Risk
Operation Risk
Fuel Supply
Fuel Price
PPA: Currency Risk
Escalation and Exchange
Rates
Project-Quality & Performance
Construction
Period Risk
Local TechnoIndustrial Capacity Risk Zambezi Hydrological Risk (***)
Environmental And Emissions Compliance O&M Cost Escalation O&M
Permitting Consents and Approvals
Construction Cost
Completion Risk
Program Over-run
Debt
BATOKA(Genco): Generates and Sells Electricity Units to Electricity Market Operators (“EMOs”)
Power ZESCO-ZESA-SAPP Bulk Purchasers; Transmission and Trading Companies For ALL SAPP Electricity Trading.(“EMOs”)
Power Cash Markets (*) ZESCO + ZESA Prepayment Markets + SAPP Bilaterals
Post Payment Markets (**) (Maximum Demand) High Capacity Consumers:-: Large Commercial, Mining And Industrial Companies
Imports at 9USc/kWh
Bankable PPA’s
Competent Power Producers (Genco): Generates And Sells Electricity
Units to Competent Markets
Dispatch Wheeling
ZESCO-ZESA-EDM Bulk Dispatch And
Transmission System Operators And Wheeling Companies
Dispatch
Competent Primary Anchor Markets (*)
Dependable Revenues
Wheeling
High Capacity Consumers:Large Commercial, Mining, Smelting And Industrial Companies Secondary Markets
Public Utility Prepayment Markets + SAPP Bilaterals
Transmission UOS Service Charges
Legal, Regulatory and Environmental Risk Mitigation
• “Measures On Africa Country Risk”
• Upgrade current “IPP POLICY FRAMEWORKs” into IPP Laws.
• ‘
• Ring-fence and Quarantine IPP Projects from legal & regulatory risk through a “SPECIAL IPP LAWs” which carry “ Direct Authority of Parliament and The Constitution”.
• Dispute Resolution Process and Procedure which has provisions for realistic compensation, executed in a “NEUTRAL JURISDICTION”. with upfront agreement on ”ALLOCATION & PRICING “ of Risk.