BALANCE RESILIENCE AND REDEVELOPMENT IMPLEMENTATION PLAN
Short–term 0-4 years
Evaluate vulnerabilities on the west side of Main St, and north and south of current project area
Targeted outreach to property owners most vulnerable to flooding on the south side of Main Street
Identify commercial relocation sites for business
Floodproof green buildings and feasible yellow buildings not amenable to voluntary buyout
Design/Permitting of Sponge Park Phase I, including a vegetated berm at elevation 8.6
Adopt a design guide for future redevelopment
Mid-term 4-7 years
Acquire and re-develop red properties. Redeveloped buildings will be set back from Main St and elevated by hybrid of mounded earth, piles, and/or dry floodproofing
Provide a floodable pavilion, which can serve as a farmer’s market, modular retail, or event center, as an anchor at the park.
Construct expanded Sponge Park Phase I
Mid-term 10-20 years
Assess previous adaptations and continue to reevaluate the plan
As floodproofed structures end useful life, redevelop with a hybrid setback, mounded grade, pile, and/or dry floodproofing
Sponge Park Phase II – Increase the elevation of Sponge park vegetated edge where site constraints allow
Long-term 20+ years
Assess previous adaptations and continue to reevaluate plan
Elevate Main St (coordinate with bridge replacement)