N6 Designs Quality Control CUM Client Support Sheet

Page 1

QASCON-N6

Quality & Assessment System for Construction by N6 Designs

N6 Designs ensures quality for each project through a proprietary assessment and reporting system called QASCON (Quality & Assessment for Construction by N6 Designs) The objective of QASCON is to do things right the first time.

Salient Features:

QASCON has over 300 unique quality checks for construction.

Under QASCON, our project management team manages the project and our site engineer visits about twice a week to assess the quality using the checklist.

These checks generate the QASCON score for each project to mitigate any issues at the right time

QASCON-N6 score for construction is the sum of points awarded to the four components in each category of building construction

1) Civil work

● Excavation and Foundation

● Plinth level work

● Wall, column and plastering

● Beam-Slab and stairs

2) Architectural work

● Flooring

● Painting

● Doors and windows

● Elevation and floor plan

3) Electrical and Plumbing

● Plumbing work

● Electrical work

4) Project management

● Arranging all required drawings and other documents

● Managing materials and labor

● Quality of construction

● Adherence to package cost

● Adherence to time

QASCON Checklist:

QASCON CHECKLIST

Mandatory Checks

Sr. No. Title

Descripon

A Reinforcement Check if the steel available at the site is as per the brand and the grade specified in the contract.

B Cement Check if the cement stored at the site is as per the Brand and Grade as per the contract.

C Cement Check if the manufacturing date of cement bags is within the past three months

D Cement Check if the cement stored at the site is adequately protected from ingress of moisture and if there are no lumps formed in the cement.

E Concrete Blocks Check if there is no complete breakage on dropping from a height of 1 5 m on natural ground or earth

F Manufactured sand Check if M-Sand - Free from impuries, presence of foreign maers, dust etc.

G Informatory Sign

N6 Designs Construcon Informatory Sign to be present at the site

1 Checklist for Drawings Project

1 1 Work schedule

QASCON CHECKS

Check if the contractor has adhered to N6 melines

1.2 Floor plan

Check if the contractor is using the final revised drawing if any changes made to the original drawing

1 3 Excavaon drawing, if required to Check excavaon size is as per approved layout

1.4 Level Check

Check the level of the plot with respect the nearest road

1.5 Level Check Check the level of the plot with respect the nearest drain

1.6 Foong layout

Check for size(plan area) & depth of foong. Dia of bars for foong in X & Y direcon, spacing of bars, development length, Binding of bars, clear cover (50mm)

1.7 Plinth beam layout Check for c/s area, dia of bars, number of bars, extra bars, Día of srrups, spacing of srrups, development length, Binding of bars, clear cover (25mm)

1 8 Column schedule

Check for width,depth, diagonals,dia of longitudinal bars, number of bars, staggered lapping, dia of es, spacing of es, development length, Binding of bars, clear cover (40mm)

1.9 Slab reinforcement details

1.10 Beam schedule

Check for dia of bars, spacing of bars, anchorage length, development length crank length, clear cover (20mm)

Check for dia of bars, number of bars, extra bars, dia of srrups, spacing of srrups, development length, Binding of bars, clear cover (25mm) on all the sides of formwork

2 Checklist for excavaon

2.1 PRE-EXECUTION CHECKS

2 2 GFC drawings

2 3 Grid line

2 4 Safety

2.5 Dewatering

Check if contractor / vendor is working with relevant working drawings

Marking boundaries to be established for centre line marking

Check safety measures required for the neighbouring construcon acvies or not

Check If dewatering is required or not.

CHECKS DURING EXECUTION

2.6 Layout & Alignment

2 7 Dimensions

2.8 Dressing & Levelling

2 9 Marking pillars

2.10 Blasng works

Check if the layout and alignment are as per the floor plan and if deviaons are within the permissible limit.

Check if the Length, Breadth, and Depth of the excavated pits are as per the structural drawing

Check for dressing of loose soil, compacted and levelled for PCC

Check whether Marking boundaries to be established for centre line marking is properly barricaded

Check if blasng is required for excavaon or can it be done with excavators and other tools

3 ACTIVITY: SIZE STONE MASONRY

PRE-EXECUTION CHECKS

3 1 GFC drawings

3.2 Dressed stones availability

3 3 Stacking

3 4 Safety

3.5 Excavaon

3.6 Marking pillars

Check if contractor / vendor is working with relevant working drawings

Check whether the stones are dressed properly, even shaped and available in required quanty

Check for the proper stacking of stones for masonry

Check safety measures required for the neighbouring construcon acvies or not

Check depth of excavaon is carried out as per structural drawing recommendaons

Check whether Marking boundaries to be established for centre line marking is properly barricaded

CHECKS DURING EXECUTION

3.7 Alignment

3.8 Mix proporon

3.9 Mortar thickness

3 10 Raking & Poinng

Check whether the stone masonry is aligned in line and plumb

Check whether the mix proporon of cement and sand is as per standards and water is added to required workability

Check if the mortar thickness is within permissible limits.

Check if the raking and points of joints have been done adequately with at least 5 mm depth from the surface of the wall

3.11 Weep Holes

3.12 Plumb & Line

Check if the weep holes are provided at the required locaons.

Check if the blockwork constructed is as per plumb and line at all locaons.

POST-EXECUTION CHECKS

3 13 Curing

3.14 Retaining wall

Check whether adequate curing has been carried out or not

Check for waterproof coang if retaining wall is constructed

4 Checklist for PCC

4 1 Surface preparaon

4 2 PCC

4.3 Marking

4.4 Level of PCC

4.5 Surface finish

4 6 Ramming

4.7 Thickness

4.8 Curing

Check for the dressing of loose soil, compacted and leveled for PCC

Check whether the loose soil has been compacted properly for laying PCC

Check proper arrangements has been made to check the PCC thickness

Check for the top level of PCC

Check that the top surface of PCC is rough enough

Check if the PCC is properly rammed and compacted

Check if the thickness of the PCC provided is as per the contract and structural design provided

Check whether adequate curing has been carried out or not

5 Checklist for An termite treatment for soil and flooring

PRE-EXECUTION CHECKS

5.1 Surface preparaon

5.2 Applicaon

5.3 Safety

Check whether the area which undergoes treatment is cleaned and leveled

Check whether the method of applicaon is as per standards

Check whether safety measures adopted before applicaon CHECKS DURING EXECUTION

5.4 Applicaon personnel

5 5 Method of an applicaon

Check whether the applicaon is done by trained personnel

Check whether the chemical has been poured along the perimeter of the building at specified intervals and depth

POST-EXECUTION CHECKS

5.6 Protecon

Check whether the treated surface is covered ll it gets dry

6 Check List for UG Sump

6 1 Dimensions

6 2 GI Mesh

6.3 Applicaon of plaster coat

6.4 Joints of sump wall

6.5 Leakage

6 6 Water Proofing

Check if the internal dimensions of the sump and the quanty of the sump is as per contract

Check if the chicken mesh is provided at all joints and properly fixed

Check whether Plastering has been completed at one stretch to avoid cracking

Check whether fillet corners / Haunch been provided on the inside of tank

Check whether leakage test has been conducted or not

Check whether waterproofing has done for the tank as per the manufacturer's specificaon

Check whether the inside plaster is made smooth 7 Checklist for foong

6.7 Plastering

REINFORCEMENT

7.1 GFC drawings

7.2

Column marking

7 3 Surface preparaon for rebar placing

Check if contractor/vendor is working with relevant working drawings

Check whether the column marking has been done before placing longitudinal bars of column

Check whether PCC surface is free from any soil, impuries before placing rebars

7.4 Visual check for reinforcement

7 5 Check for main bars (Foong)

7.6 Check for main bars (Column foong)

Check whether the reinforcement is free from oil, mud, grease and other forms of contaminaon

Check whether the dia of bars in both the direcon spacing of bars and clear cover (50mm) provided as per structural drawing

Check for size(plan area) & depth of foong the dia of longitudinal bars, number of bars, dia of lateral es, spacing of es, development length of column bars within foong & cover for column (40mm)

7 7 Development length

7.8 Cung length

7.9 Column plumb

FORMWORK

7.10 Quality of forms

7 11 Form oil

7.12 Gap between shuers

7.14 Cover blocks

CONCRETING

7 14 Cement bags

7 15 Level marking

7 16 Quality of materials

7.17 Compacon

7.18 water cement rao

Check whether the development length of bars for column been provided for a minimum length of 300mm

Check whether the cung length of bars for lateral es is as per the standard

Check whether the column reinforcement is checked for vercality (plumb)

Check whether the forms used are of superior quality or not

Check whether the forms oil used is of good quality or not

Check whether the gap between shuers are closed to avoid leakage of slurry

Check for the cover blocks in order to avoid rebars geng corroded thereby increasing the durability of structure

Check whether the required number of cement bags available on site (or)adequate quanty of RMC been ordered

Check whether the top level of foong been marked on form sides to ensure that foong is of required depth

Check whether the materials used for concrete is of good quality and passed all the standard tests conducted

Check whether the concrete been compacted properly with vibrators to avoid air voids aer deshuering

Check whether grade of concrete used is as per structural drawing & water cement rao is as per the required grade of concrete used.

7 19 Curing

Check whether adequate curing has been carried out or not

for dia of bars, number of bars, extra bars, dia of srrups, spacing of srrups, development length, Binding of bars, clear cover (25mm) 8 6

for quality of ply/MS board, oiliness of forms, size as per drawing, supports, ghtness of form 9.2

center line marking

for alignment and straightness of column w.r.t adjacent columns by tying a string between columns coming in line 9.3

size

for column width, depth & diagonals

whether the gap between shuers is closed to avoid leakage of slurry 9 5

9.4 Gap between shuers

blocks Check for the cover blocks in order to avoid rebars geng corroded thereby increasing the durability of structure 9 6 Cover

if at least 40 mm cover block is provided at all locaons between the steel reinforcement and the shuer

7.20 Deshuering
of formwork Check
8 Checklist for plinth and soil filling
1 Bed concrete Check
on soil 8 2 Size stone masonry Check
8.3 Formwork Check for Line, level
Size of plinth beam Check
Reinforcement
Check
Check
Curing Check
Filling
Check
Checklist
FORMWORK
Formwork
Column
/ stripping
deshuering has been done as per the standards
8
whether 100 mm thick bed concrete has provided for SSM
whether minimum three course of SSM below GL placed
and plumb 8.4
for Length, width & depth of beam 8.5
for plinth beam
Concrete
whether the approved grade of concrete been used for concreng 8 7
whether adequate curing has been carried out or not 8 8
& compacon
whether the filling has done in layers and compacon been done using rollers or rammers 9
for column formwork, reinforcement & Concreng
9 1
Check
Column
Check
Check
Check
Cover
Check

REINFORCEMENT

9.7 GFC drawings

9.8 Surface preparaon for rebar placing

9.9 Stacking of rebars

9.10 Visual check for reinforcement

9 11 Staggered Lapping

9 12 Column main bars

Check if contractor/vendor is working with relevant working drawings

Check whether PCC surface is free from any soil, or impuries before placing rebars

Check whether the reinforcement is kept on wooden runners or not. Direct contact on soil should be avoided

Check whether the reinforcement is free from oil, mud, grease and other forms of contaminaon

Check whether the lapping is staggered or not

Check for the dia of longitudinal bars, number of bars, dia of lateral es, spacing of es, development length of column bars within foong & cover for column (40mm)

9 13 Cover blocks

9 14 Overlap length

9.15 Cung length of bars

CONCRETING

9 16 Cement bags

9 17 Level marking

9 18 Quality of materials

9.19 Compacon

9.20

Water cement rao

9 21 Curing

9.22 Deshuering / stripping of formwork

Check whether 40mm cover blocks are provided on all the sides of forms

Check whether the overlap length is as per standards or not

Check whether the cut length of bars for es is as per standards allowing required hook length

Check whether the required number of cement bags available on site? (or)adequate quanty of RMC been ordered

Check whether the reference level has been marked on rebars to ensure that the column is concreted to the required height

Check whether the materials used for concrete are of good quality and passed all the standard tests conducted

Check whether the concrete has been compacted properly with vibrators to avoid air voids aer de shuering

Check whether the grade of concrete used is as per the structural drawing & water-cement rao is as per the required grade of concrete.

Check whether adequate curing has been carried out or not

Check deshuering has been done as per the standards

10

PRE-EXECUTION CHECKS

10 1 Cement blocks

10 2 Hacking

10 3

Cement slurry

10.4

Finished floor level

10.5

Reference marking

Checklist for Block Masonry

Check whether the required number of blocks is available or not Also check for size of blocks

Check is the concrete columns are adequately hacked before blockwork is done

Check whether the cement slurry is applied over hacked surface before the start of masonry

Check whether the marking of finished floor level been transferred to walls/floors

Check whether the markings for reference lines transferred on walls / columns

CHECKS DURING EXECUTION

10.6 Alignment

10 7 Base course

10.8 Mortar mixing

10 9 Dimensions & diagonals

10.10

Mortar thickness

10.11

10.12

10 13

10.14

Racking & poinng

RC Band

Maximum course of wall in a day

Packing of last course

Check for alignment, plumb in both horizontal and vercal direcon using aluminium straight edge

check for the correctness of base course by measuring size (length & breadth) and diagonal lengths.

Check whether the mixing been done on a clean surface or not

Check whether diagonals & dimensions have been checked as soon as base course is laid

Check for the thickness of mortar to ensure it don't exceed 15 mm

Check whether the poinng has been done or not

Check for RC band beam of 100mm thick done for 4-inch-thick walls

Check for the height of wall constructed in single day since maximum course is restricted to 5 (or) 1 2 mts

Check whether the last course is of full block touching the concrete beam and packed properly

10.15 Openings in walls

Check whether the provision has been made for openings in walls for Doors, windows, venlators or any other openings required for architectural purposes

POST-EXECUTION CHECKS

10.16 Curing

10.17 Inspecon

Check whether adequate curing has been carried out or not

Check whether the joint has sufficient strength or not by driving a nail aer 7 days of blockwork

11 Checklist for Beam-Slab and Staircase: centering, reinforcement and concreng

11 1 Beam boom Beam boom line, level and width should be checked

11 2 Beam sides Beam side's line, level and plumb should be checked

11.3 Beam measurements Beam to Beam measurements (Lengths),width & depth shall be checked as per Structural Drawings

11.4 Beam depth and slab thickness Slab thickness should be checked by tying a rope on a reference marking all along length, breadth & diagonally. Using tape required top level can be measured. Beam depth should be checked in a similar fashion as that of slab before placing beam rebars.

11 5 Supports

Check for support props for slab & beam booms should be in line & plumb Bamboo bracing should be done at around 4' ht from floor level. Support props for double staging terraces shall be carefully checked.

11 6

Beam-column juncon Beam & column juncon should be checked for water ghtness

11.7 Staircase formwork Formwork of staircase shall be checked for dimensions of tread and riser, level of treads, plumb of risers.

11.8 Reinforcement for Roof Beam & Slab

Beam should be checked for number of bars at top & boom, dia of bars, development length of bars, clear cover length of curtailed bars, binding of bars, dia of srrups, spacing of srrups, number of srrups, cung length of bars. Slab should be checked for dia of bars in both direcons, spacing of bars, concrete cover, cung lengths, anchorage lengths, development lengths, crank length, binding of bars, chairs, top and boom cover Addional bars if, any

11.9 Clear cover

Check for the presence of cover blocks at regular intervals

11.10

Electrical Brands, numbers, Electrical points, electrical piping (conduits)/fan hooks shall be checked as per drawing.

11 11 Chairs

11.12 Dowel bars

11.13

Reference marking

11.14

Beams (Hidden / inverted/ canlever)

11 15 Sunken slab

11 16 Concreng

11 17 Compacon

11.18

Post concreng

Check for the presence of chairs at regular intervals

Dowels (if any) required to be provided for elevaonal features / future extensions should be checked

Check whether the markings for reference lines transferred on columns

Hidden beams/inverted beams / canlever beams should be checked.

Check for the sunk if any as per the approved drawings

Check whether the concreng is done as per standards or not Concreng shall be done for the beams first &then slabs

Check whether compacon is carried out or not compacon of concrete shall be done by vibrators &tamping rods

Check that the top level of the slab shall be finished by mason in level without any undulaon & no damage should be made to the freshly laid concrete.

11.19

Curing

11 20 Deshuering

11.21

Honeycombs

11.22

11.23

11 24

Hacking of concrete surface

Parapet wall

waterproofing

Check that curing of slab shall be done with ponding method by making ponds in cement sand mortar of required size. Curing of beams and slabs shall be done for 7 to 10 days.

Check deshuering / stripping of formwork has been done as per IS specificaons

Finishing of Honeycomb shall be done with proper recficaon methodology as per the instrucons of Engineer -in-charge

Check whether hacking of the beam sides, beam booms, slab booms has been done within 1 or 2 days from deshuering

Check whether parapet wall being constructed to a height as per specificaon

Check whether waterproofing work has been carried out as per manufacturer's specificaon

12 Checklist for External Plastering

PRE-PLASTERING

12.1

prerequisite

12.2 Hacked surface

12.3 Buon / Bull marks

12.4 Galvanised iron mesh

12.5

Openings

12 6 Electrical works

12.7

Plumbing works

12.8 Electrical works

12.9

Curing

12 10 Surface preparaon

12.11

Finishing

Check whether access available for starng plastering

Check concrete surface beam/column hacked with a minimum of 80 hackings/sq. Ft

Check whether the bull marks placed at required intervals

Check whether the GI mesh been nailed at all juncons of RCC & masonry members

Check whether openings of doors & windows been fixed

Check whether the electrical conduing works completed or not before plastering

Check whether PHE piping works in toilets & kitchen completed or not

Check that all electrical boxes are covered properly by dummy plates or by other means

Check if the blockwork cured for at least 7 days

Check that the surface to be plastered is free from all contaminants, made wet and sufficient curing has been done

Check for the proper roughening of first coat so that it can achieve proper bonding with second / final coat

DURING PLASTERING

12.12

Mortar mixing

12 13 Line & level

12.14

Specificaon

12 15

Plastering on los

12.16

Edges of doors & windows-Finish

12.17

Corner finish

12.18 Electrical

Check whether the mixing been done on a clean surface

Check that plastered surface is in proper line & vercality

Check whether that wall is plastered to a specified mix proporon, to line and true plumb without any undulaons

Check that plastering has been done above & below all plaorms and los

Check for the edges of window frames & door frames perfectly vercal by using aluminium straight edge or using spirit level & it should be at right angle to each other.

Check if the corners are sharp and orthogonal

Check whether switch boxes are in posion and properly finished

12.19

Skirng

12.20 Finished surface

12.21 Type of finish

12.22 Type of finish

POST PLASTERING

12.23

Curing

12.24

Grooves, drip moulds, mortar beds

12 25 Cleaning

Check if plastered surface cut properly for skirng

Check the finished surface smooth and straight as required

Check for rough finish if le applicaon will be done on plastered surface

Check for smooth & even finish if textured coangs done on plastered surface

Check whether curing has been carried out for a minimum of 07 days, with the date of plastering on the wall?

Check whether grooves/drip mould /mortar bands have been provided. If required.

Check whether the mortar spillage has been cleaned or not

13 Checklist for internal Plastering

PRE-PLASTERING

13.1 prerequisite

13.2

Hacked surface

13.3

Buon / Bull marks

13 4 Galvanised iron mesh

13 5 Openings

13.6

Electrical works

13 7

Plumbing works

13.8 Electrical works

13.9

Curing

13 10 Surface preparaon

Check whether access available for starng plastering

Check concrete surface beam/column hacked with a minimum of 80 hackings/sq.

Check whether the bull marks placed at required intervals

Check whether the GI mesh been nailed at all juncons of RCC & masonry members

Check whether openings of doors & windows been fixed

Check whether the electrical conduing works completed or not before plastering

Check whether PHE piping works in toilets & kitchen completed or not

Check that all electrical boxes are covered properly by dummy plates or by other means

Check if the blockwork cured for at least 7 days

Check that the surface to be plastered is free from all contaminants, made wet and sufficient curing has been done

DURING PLASTERING

13.11 Mortar mixing

13 12 Line & level

13 13 Specificaon

13.14

Plastering on los

13.15

Edges of doors & windows-Finish

13.16 Corner finish

13.17 Electrical

13 18

13 19

13.20

13.21

Skirng

Thickness

Type of finish

Type of finish

Check whether the mixing been done on a clean surface

Check that plastered surface is in proper line & vercality

Check whether that wall is plastered to a specified mix proporon, to line and true plumb without any undulaons

Check that plastering has been done above & below all plaorms and los

Check for the edges of window frames & door frames perfectly vercal by using aluminium straight edge or using spirit level & it should be at right angle to each other

Check if the corners are sharp and orthogonal

Check whether switch boxes are in posion and properly finished

Check if plastered surface cut properly for skirng

Check if the plaster is 12-15 mm thick

Check for rough finish if le applicaon will be done on plastered surface

Check for smooth & even finish if textured coangs done on plastered surface

POST PLASTERING

13 22 Curing

13 23

13.24

13.25

Grooves, drip moulds, mortar beds

Applicaon of lime coat

Cleaning

Check whether curing been carried out for a minimum of 07 days, with the date of plastering on the wall?

Check whether grooves/drip mould /mortar bands has provided If required

Check whether the lime coat been properly applied, if required.

Check whether the mortar spillage has been cleaned or not

14

Checklist for Floor ling

14.1

14.2

14.3

14 4

14.5

14.6

14.7

PRE-TILING CHECKS

Surface preparaon

Surface preparaon

Level Markings

Precursory

Soaking of le

Thickness of mortar bed

Size & Brand of Tiles

CHECKS DURING TILING

14.8 Slope

14.9

14.10

Coang of cement slurry

Tapping of le

Check that floor surface to be cleared before start of work

Check that the surface where flooring to be done is free from all contaminants & made wet prior ling

Check if the level markings are provided at mulple places in a room

Check whether all the preceding works completed before the start of ling

Check that files have been soaked for at least 30 minutes

Check for the thickness of mortar bed

Check if the Tiles stacked at the site are of the approved design, and are of correct size and brand, colour as per the contract.

14.11

14.12

14 13

14 14

14.15

14.16

POST TILING CHECKS

Cleaning of Joints

Alignment

Hollowness of le

Finished floor level

Covering of les

Groung

Check whether the required slope has been provided during ling

Check that back of the ceramic les is completely coated with cement slurry

Check that les have been gently tapped aer laying on the mortar bed

15

Check that the joints been cleaned to remove loose mortar

Check that joints are properly aligned

Check that No hollow sound on the le when tapped

Check that the finished floor level is as per the bubble tube

Check that laid floor les are covered properly

Check that groung is only done aer 24hrs of laying of les

Checklist for Wall ling

15.1

15 2

15 3

15.4

PRE-TILING CHECKS

Surface preparaon

Surface preparaon

Seng out

Quality of cement

CHECKS DURING TILING

15 5 Moist les

15.6 Edges of les

15.7 surface of les

15 8

Coang of cement slurry

Check that wall surface to be cleared before start of work

Check that the surface where flooring to be done is free from all contaminants & made wet prior dadoing or ling

Check that the seng out work has been done

Check for cement to be used is less than 3 months old, free from lumps, brand, Grade and ISI mark

15.9

Tapping of le

15 10

Arrangement of les

Check that the les are kept moist before placing in mortar

Check that the edges been checked for straightness

Check for the finish(texture & paern) of the surface as required

Check that back of the ceramic les is completely coated with cement slurry

Check that les have been gently tapped aer laying on the mortar bed

Check that the les used are from the same batch and from the same box

15 11

15.12

15.13

POST TILING CHECKS

Thickness of joint

Alignment

Hollowness of le

15 14 Edges of les

15.15

15.16

15.17

Covering of les

Groung

Plumb of le surface

Check that joints are properly aligned

Check that No hollow sound on the le when tapped

Check that the edge of les should be sharp and straight

Check that laid floor les are covered properly

Check that groung is only done aer 24hrs of laying of les

Check that the surface of le is in plumb

15.18

Joint filling

Check that the seng of joints been done only aer a minimum of 24 hours

16

PRE-PAINTING CHECKS

16 1 Prerequisite

16 2

Approval of materials

16.3 Colour

16.4

Cleaning

16 5

Damages

Checklist for Painng

Check for wall cracks, dampness etc before applicaon of primer

Check the brand is as per contract

Check colour shade approved

Check that walls to be painted should be cleaned, free from impuries

Check for the presence of cracks, dampness, leakages if any, to be recfied before proceeding with primer

CHECKS DURING PAINTING

16 6 Primer

16 7 Wall Puy

16 8 Wall Puy

16.9

16 10

16.11

Damages & Undulaons

Sanding of surface

Cleaning

16 12 First coat of paint

16.13 Final coat of coat

Check that primer has applied which acts as a bonding agent between plastered wall and paint

Check that puy been applied aer 24 hours of primer applicaon

Check that 2nd coat of puy been applied aer the 1st coat has completely dried

Check that all broken edges, cracks, undulaons have been covered using wall puy

Check that sanding of the surfaces have been done properly to render a smooth surface

Check that the dust from the surface been thoroughly Wiped off aer sanding the pued surface

Check that the first coat of paint is applied and finished with roller Make sure that paint used is as per the contract

Check that the final coat is applied aer 4 to 6 hours of first coat

16.14

16.15

POST EXECUTION CHECKS

Surface protecon

Quality of work

16 16 Fings

16 17

16.18

Level

Floor polish

Check that painted surface is protected by proper means

Check that the painng is free from any cracks and defects

Fing aer painng to be checked

Check that the finished surface is as per the bubble tube

Check for floor polishing before final coat (in case of Marble flooring)

17

BEFORE LAYING

17.1

17.2

Surface preparaon

Bull marking

Checklist for Granite/Marble flooring

Check that floor slab been prepared for granite work

Check that bull marking has been done at regular intervals

DURING LAYING

17.3

17 4

17 5

17.6

17.7

Right angles

Moist floor

Levelling

Joint filling

Tapping of le

Check for the right angles of corresponding walls before laying Granite / marble

Check that floor is kept moist and provided with cement slurry for bonding

Check that the levelling been done with an aluminium straight edge and rubber hammer

Check that the seng of joints been done only aer a minimum of 24 hours

Check that les have been gently tapped aer laying on the mortar bed

AFTER LAYING

17 8 Joints

17 9

17.10

Alignment of joints

Plumb and horizontality

Check that the seng of joints been done only aer a minimum period of 24 hours

Check that joints are aligned properly

Check that work is carried out to true plumb and horizontality

17.11

17.12

17.13

Covering / Protecon

Hollowness of le

Groung

Check that laid floor surface is properly covered or not

Check that No hollow sound on the le when tapped

Check that groung is only done aer 24hrs of laying of les

18

18 1

Plumbing and sanitary works

18.2 Electrical work

18.3

18 4

18 5

18.6

Earthing

Pressure test

Electrical work

Overhead tank

Check for Plumbing, Electrical Work

Check for Plumbing and sanitary works as per Drawings

Check whether electrical works are as per Drawings

Check for proper earthing done.

Check for Pressure Test of Piping System

Check for electrical wires, switches & sockets as per menoned Brand and quality in the specificaons

Check for overhead tanks as per quality and capacity menoned in specificaons

18.7

Electrical work

Check for the brand of Electrical items as per specificaon 19

Check for Doors & windows

Check that brands of doors and windows are as per contract 19.2 Size

19 1 Brand

Size of doors, windows and the gauge of the grill as per the contract

19 3

Specificaon

19.4 Damages

Check that Specificaons are as per contract

Check for the presence of cracks, knots, wraps, sap etc.

20

20 1

Storm water drain

20.2 Rain water storm

20.3 Steps

Final inspecon checklist

Check for Storm water drain has been closed using the suitable materials/methods

Check that Rain water drain has been connected to the drain/sewer

Check that Steps are properly finished at the corners

20.4 Main entrance steps Check that Main entrance steps are as per the specificaon and well finished at the corners and joints

20 5 Rain water harvesng

Check that Rain water harvesng is done and is as per contract and standards

20.6 Kerbs and pathways Check that Kerbs and pathways are cleaned and well finished and without any damages

20.7 Walls

20.8 Sealant

20 9

Finish of walls

20 10 Wall plastering

20 11 Painng

20.12

Finish of painng

20 13 Finish of painng

20 14 Plastering

20.15

Finish of plastering

20.16

Finish of plastering

20.17 Finish of plastering

20 18 Corner finish

20 19

20.20

20.21

Check that Walls are free from the cracks and to plumb

Check that If cracks are present, has crack sealant been applied?

Check that Finishing of the wall is good at the corners

Check that Plastering on the wall is even and free from undulaons

Check that Painng is done and is as per the specificaon

Check that Painng finishing is even and free from patches

Check that Painng looks uniform and even

Check that Plastering done is as per the specificaon

Check that Plastering surface is level and free from undulaons

Check that Plastered surface looks uniform

Check that Plastered surface is free from water or any patches

Check that Corner finishing uniform and symmetrical at the corners

Finish of plastering Check that Plastered surface is free from cracks

Finish of plastering

Finish of plastering

20.22 Painng

20.23 Painng

20.24

Finish of painng

Check that in case of cracks, sealant has been applied and finished?

Check that Plastered surface is true and in plumb with a proper degree of smoothness

Check that Painng is done and as per the specificaon

Check that Painng looks uniform in colour

Check that Painng is free from patches / water seepage marks

20.25 Finish of painng Check that Painted surface free from stains

20.26 Finish of painng

20.27 Doors / windows / venlators

20.28

Material specificaon

20.29 Doors / windows / venlators specificaon

20.30 Doors / windows / venlators

20 31 Doors / windows / venlators

20 32 Doors / windows / venlators

20 33 Doors / windows / venlators

20.34 Doors / windows / venlators

20.35 Doors / windows / venlators

20.36 Doors / windows / venlators

20.37 Doors / windows / venlators

20 38 Doors / windows / venlators

20 39 Doors / windows / venlators

20 40 Doors / windows / venlators

20.41 Doors / windows / venlators

20.42 Doors / windows / venlators

Check that Painng has the right degree of smoothness

Check that Door/Windows/Venlator are placed as per the drawings and the sill height is good

Check that Material used is standard and adheres with the specificaon

Check that Doors/windows/venlators are as per specified size and design

Check that Doors/windows are defect/crack free

Check that Doors/windows/venlators shuers are fine, in level and latches when closed

Check that Doors/windows/venlators are cleaned and free from patches/stains/dust/mortar/or any other foreign material

Check that Doors/windows/ venlator frames are painted well

Check that Doors/windows/ venlator grills are fixed and painted

Check that Doors/ windows/ venlator grill fixing finishing is uniform

Check that Doors/ windows/ venlator frames are fixed without any gaps

Check that Joints at the Door/Window/ venlator frames are well sealed using the suitable sealant

Check that Door/window/ venlator is painted at top and boom

Check that Doors locks are working fine

Check that Doors are fixed to all the hinges with screws

Check that Door stopper installed

Check that Screws have been fixed to the striker plate

20.43 Doors / windows / venlators

20 44 Doors / windows / venlators

20.45 Doors / windows / venlators

20.46 Electrical works

20.47

Electrical works

20 48

20 49

Electrical works

Electrical works

20.50 Electrical works

20.51 Flooring

20 52 Flooring

20.53

Flooring

20 54 Flooring

20.55 Flooring

20.56 Flooring

20 57 Flooring

20.58 Parapet wall

20.59 Plastering

20 60 Flooring

20 61 Parapet wall

20.62 Plumbing works

20.63 Parapet wall

20.64 Parapet wall

Check that Door margins are uniform and without the gaps

Check that Door does not rub onto the frame/ door shuer rates when opened or closed

Check that Window glasses are defect free

Check that Electrical fixtures used are as per the specificaon

Check that Switch boards and sockets are clean and free from stains

Check that Switches and sockets are funconal

Check that Electrical fings are defect free

Check that Electrical fixing is well finished and free from any gaps at ceiling

Check that Flooring is done as per the specificaon

Check that Juncons of the floor and wall plaster/skirng/dado is rounded off

Check that Flooring surface is properly cleaned polished and finished

Check that Any chipping/damaged les present

Check that All the stains from the flooring is been removed

Check that Any presence of les which are dummy

Check that All the flooring joints have been grouted/sealed

Check that Parapet wall is constructed as per the specificaon

Check that Plastering is even and well finished

Check that Parapet wall is free from the cracks

Check that Parapet wall is painted and the has the right degree of smoothness

Check that CP fings and sanitary ware are as per the specificaon

Check that Leakage in the pipeline I present

Check that Water seepage is observed

20.65 Flooring / wall ling / dadoing Check that Tiles which are damaged 20 66 Flooring / wall ling / dadoing Check that Any le joints missing grout 20.67 waterproofing Check that Waterproofing is done 20.68 Flooring / wall ling / dadoing Check that All the Chipped le has been replaced 20 69 Plumbing works Check that Any CP fing which is Damaged has been replaced 20 70 Miscellaneous Check that Bathroom floors have been cleaned with acid wash? 20.71 Plumbing works Check that Health faucets provided are as per specificaon and funconal 20.72 Plumbing works Check that Plumbing fixtures are free from leakages 20 73 Plumbing works Check that the Plumbing line is free from seepage 20 74 Plumbing works Check that Sewer gully trap has collar joint 20 75 Miscellaneous Check that Debris has been removed 20.76 Miscellaneous Check that Acid wash for the flooring and common areas been done 20 77 Miscellaneous Check that Contractor’s junk has been removed from the site premises 20 78 Miscellaneous Check that Site surroundings are cleaned and well maintained 20.79 Miscellaneous Check that Any damage done by the contractor to client’s property has been recfied
ClientName Projecttype ProjectDescription Tobedecided NotRequired ToBeDone Category Services 3D&CAD 3DDesign Services 3DRendering 3DElevations 2DDrawings 3Dwalk Through VirtualReality Augmented Reality Architect FloorPlans Home Rennovation Designs Home Extension Designs Home Restoration Designs CostEfficient Homes Architectural Design Design Consultation Carpenter Wooden Furniture WoodCutting Furniture Manufacturing Carpentry Works WoodenDoor Frames Wooden WindowFrames WoodenArt Works WoodCarving Computerised WoodCarving Woodenbed Cots WoodenDining Table DoorCarving Engraving works CivilEngineer SiteSurveying SitePlanning Project Estimation Project Consultation Project Supervision MEPDrawing Permit Drawings Electrical Drawings Architectrual Consulting Structural Consulting BoundaryWall Design Contractor Civil Contractor Building Contractor Labour Contractor Drainage Contractors Commercial Contractor Residential Contractor Home Rennovation Contractor Maintainence Works Contractor Building Foundation works BoundaryWall Contractor FencingService Contractor PlotLevelling withJCB Contractor Concrete Cuttingwork Contractor Building Demoltion Contractor SingleRoofing PergolaRoofing TileRoofing Thatched Roofing RoofingWorks ElectricWorks Electrical Repairs& Fixes ElectricWiring Electrical Installation SolarSystem ElectricalWorks Lightingworks Fabrication&Welding MetalLaser Cutting CNCCutting Aluminium Fabrication Weldingworks Steel Fabrication works SSFabrication MSFabrication StudWelding GateDesign Handrails Pargola SteelDoors& Gates CustomBlinds Shades RollingGates StainlessSteel gates SlidingShutters Canopyworks Roofingtruss works Extra Carpoarch works WPCDoors Aluminium Doors SteelWindows UPVCWindows ZebraBlinds Mosquitonets Flooring Granite Marble Tiles Epoxy GranitePolish Marble Polishing Mosaic Repolish PUFlooring 3DFlooring Custom Floooring Earthen Flooring FllorLevelling Wooden Flloring Laminate PVC Oxychloride Terrazo Flooring WPC Gardening& Landscaping Plantssupply pondssetup irrigation systemsetup gardenfixtures andlights Garden& Landscape Manintainence PestDisease Control Vertical Gardening Fountainworks GardenCement Design Stonework Landscape Design GardenDesign Garden Walkways Interlocktiles outdoortiles Gardenstone laying NaturalStone works Glazier SpiderGlazing Bathroom Shower Partition GlassHandrails ACPElevation Toughened GlassWorks GlassWorks ACPWall Cladding Structural Glazing HVACWork AC Repair/Service ACInstallation AC Maintainence Heater Repair/Service DuctCleaning DuctRepair HVAC Maintainance DUCT,Grills, Diffuser, Damper Installations HomeAutomation Home Theaters Automatic Gates Automatic SensorsDoors CCTV Garden Automation HomeSecurity Services IntruderAlarm FingerPrint DoorAccess Remote Shutters SmartLighting InteriorDesign Modular Kitchen Interior Decoration Wardrobe Works HomeInterior Plywood lamination TVUnits WallDecorative Design StainlessSteel modularkitchen Custom Furnitures Custom Wardrobes CustomBeds Custome Bookcases KidsBedroom Design WallArtDesign Uphoistery Work GypsumFalse Ceiling PVCFalse Ceiling CementFiber BoardCeiling VeneerBoard works POP gypsum FalseCeiling GridFalse Ceiling Aluminiumfalse ceiling AcousticFalse VBoard Partitionworks PartitionWalls Mason Plastering WallCladding Gysum Plastering AntiTermite Treatment FerroCement works Readymix Plastering SandFree Plastering CementArt Works PaintingWork WallPainting GypsumPaint 3DWallPapers Customised WallPapers Paintingworks Colour Consulting Decorative Painting Texture Painting Exterior Painting InteriorPainting MuralPainting Commercial Painting WhiteWashing PressureWater Cleaning SprayPainting Putty WoodPolishing PUPainting Plumber PipelineDirt Cleaning WaterTank Works SanitaryPipes &FittingWorks Plumbing Works Bathroom Fittings SwimingPoolWork SwimingPool Construction Swimingpool treatment SwimingPool AMC WasteManagement SepticTank Works Watertreatment Installation Waste Management services WaterProofing RoofWater Proofing Waterproofing Coating Bathroom Waterproofing RubberRoofing APP Membrance WaterProofing Fibreglass meshWater proofing Polyurethance WaterProofing PU) Pressure Grouting Well/Borewell WellDrilling Cement ConcreteWell Rings BorewellDrilling Services WellCleaning Services Photographer Architecture Photography Interior Photography Architecture Videography Interior Videography Architecture portfolio Interiorportfolio RealEstate ImageEditing Other Incinerator Vasthu Consultance Corporation approval BankLoan Services

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.