AVIATION CHRIS JOHNSON VP, Aviation Market Lead
303.437.1112 chris.johnson@flintco.com
Tulsa International Airport Concourse A This project renovated Concourse A to modernize its building systems, bring in more natural light, and create better views toward the airfield. Visitors now enjoy new shopping and dining options, renovated restrooms, a business center, new seating and an updated USO lounge. 3
We performed Value Analysis exercises, which resulted in more than $1 million in savings for the owner. As a result, the owner was able to make improvements to gate locations, skylight glass upgrades, and modifications to Concourse B.
LOCATION
Tulsa, OK
COMPLETION DATE
June 30th, 2015 COST
$ 6,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Albuquerque Sunport Terminal Renovations The Sunport, New Mexico’s largest airport, serves 5 million travelers a year and has a $1.9 billion economic impact on the Albuquerque metro area. The terminal renovation project elevates customer experience with new ticketing and 4
baggage claim areas, seating and a new waiting area for shuttle customers. Other improvements include raised ceilings with faux skylight features and improvements to the arrival and departure curbs.
LOCATION
Albuquerque, NM COMPLETION DATE
July 29, 2019 COST
$ 30,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Indianapolis International Terminal & Concourse Expansion At the time of construction, this project was the largest the city of Indianapolis had ever undertaken. It featured construction of a modern terminal built in the “midfield� area of the existing airport between two main runways consisting of a 1.3 million SF terminal and two 130,000 SF concourses. 5
Given the challenging design of the project, an exhaustive preconstruction process was required. Efficient plans were developed and refined for issues such as; a quality control process, methods for quick field connection of the structural members, and methods to transport the pieces to the site.
LOCATION
Indianapolis, IN COMPLETION DATE
January 1st, 2007 COST
$ 13,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Portland Airport Baggage Handling System Demolition of existing conveyor system, installation of new baggage handling system, maintenance of existing conveyors were included as part of the new system and testing of conveyors.
6
Alberici, a parent company of Flintco, installed more than three miles of conveyor and six claim devices. Alberici conducted extensive load testing with sand bags. Sort and rate testing using luggage were also performed as part of our commissioning duties.
LOCATION
Portland, OR COMPLETION DATE
July 1st, 2011 COST
$9,100,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Lester B. Pearson Baggage Handling System Upgrades To accomplish 100% screening of passenger baggage, approximately 8,000 linear feet of baggage handling conveyor complete with support steel, headers, 16,000 SF of catwalks and maintenance platforms, building reinforcement and miscellaneous structural steel, 800 new conveyor drives, 43 motor control 7
panels were installed in and around existing conveyors. Integrated within the system were 16 new high resolution x-ray machines, uninterruptable power systems and 3 baggage tilt tray sorters (the first of their kind at Toronto Airport).
LOCATION
Toronto, ON, CA COMPLETION DATE
June 1st, 2017 COST
$ 25,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Detroit Metro Airport Baggage Handling Installation of baggage handling, in-line Explosive Detection Systems (EDS), and related equipment in the McNamara Terminal/Northwest WorldGateway at Detroit Metropolitan Wayne County Airport (DTW). 8
Scope of work also included extensive modifications to the baggage handling control system and installation of more than 1.2 miles of conveyors. Alberici, Flintco’s parent company, self-performed all mechanical and equipment installation.
LOCATION
Detroit, MI
COMPLETION DATE
January 31st, 2009 COST
$ 8,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
FedEx Main Screening Facility The new structure is a main point of entry into the FedEx Memphis Hub, connected by bridge which spans over 5-lanes of Democrat Road and accommodates approximately 7,000 employees twice a day. This LEEDÂŽ Silver certified project features many sustainable components including 44 folded transparent screens 9
that make up the bridge which consist of sheets of perforated aluminum-this metal skin reduces glare and solar heat gain by day. The project consists of a 4,000 SF lobby, a 30,000 SF screening building, and a 235-foot pedestrian bridge connecting the two buildings.
LOCATION
Memphis, TN COMPLETION DATE
June 29th, 2012 COST
$ 13,100,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Tulsa International Airport Rental Car Facility Expansion Flintco completed an addition of a third level to the existing Tulsa Airport parking garage/rental car facility including renovation to existing entrances, construction of new entrances, three canopies and five elevators. 10
The project was scheduled in four phases while the parking garage remained in service Also, included in this project are vertical vehicle circulation ramps, vertical circulation cores housing new elevators and stairs, and new roadway crossing fabric canopies.
LOCATION
Tulsa, OK
COMPLETION DATE
December 31st, 2016 COST
$ 27,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Memphis International Airport Ground Transportation Center The project consisted of the expansion of the existing garage by approximately 3,900 spaces. The phase includes a seven-level “Squeelix� structure for vehicular circulation and three open stair towers for pedestrian circulation. Also included was a 6,000 SF state-of-the-art 11
toll plaza and parking office and a fourcar elevator tower directly in line with the center of the terminal. This 1,940,000 SF facility houses rental car counters, service functions and up to 1,250 rental cars on the bottom two floors.
LOCATION
Memphis, TN COMPLETION DATE
June 16th, 2014 COST
$ 90,200,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Memphis International Airport Air Traffic Control Tower This 336-foot tower replaced an existing air traffic control tower and is the third tallest in the South. At the base is a 24,850 SF facility that includes administrative offices, training areas and an expanded radar approach for controlling traffic. The project also 12
included a parking lot, environmental support building, roadways and perimeter security. Work on the project also included the demolition of the existing cast-inplace concrete tower and the single story TRACON base building with a full basement.
LOCATION
Memphis, TN COMPLETION DATE
January 1st, 2010 COST
$ 57,300,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Greenwood-Leflore Airport Air Traffic Control Tower This 80-foot tall facility includes a modern cab layout equipped to control all airfield operations from one seated location, more than 2,100 square feet of space for training for FAA administration and a
sleeping berth for air traffic controllers who are off-duty. The tower has over 2,000 square feet of space to be in-filled for future expansion.
LOCATION
Greenwood, MS COMPLETION DATE
September 15th, 2011 COST
$ 1,700,000 13
FLINTCO, LLC | AV IAT ION PORT FOLIO
Gulfport/Biloxi Air Traffic Control Tower 116’ Airport Traffic Control Tower and a 13,000 square feet TRACON base building along with all associated site work, a parking lot, sidewalks, landscaping, and a security system to provide facility monitoring from the interior of the building. 14
The project also included all required utilities including power, gas, water, and sanitary sewer as well as internal systems including fire suppression and security.
LOCATION
Gulfport, MS COMPLETION DATE
May 30th, 2012 COST
$ 13,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
March Airfield Control Tower and Base Operations Center The 130-foot control tower replaces an older outdated control tower and includes a base operations center at the ground level. With the addition of 4,000 SF, the new complex incorporates more office space for air crew intelligence briefings, radar approach control, radar and radio 15
maintenance and transient alert, which handles logistics for departing and arriving crews and passengers. Also included are a crew lounge, break room and offices on the lower levels of the tower itself.
LOCATION
March Air Reserve Base, CA COMPLETION DATE
January 11th, 2015 COST
$ 17,400,00 FLINTCO, LLC | AV IAT ION PORT FOLIO
Tennessee Air National Guard 164th Airlift Wing Relocation The Tennessee Air National Guard 164th Airlift Wing relocation project consisted of multiple projects completed in multiple phases. Flintco’s role included the Administration Building Package and the Industrial Building Package. 16
The Industrial Building Package included the completion of three new facilities including a combined Fire Station/Base Civil Engineering Building, a Vehicle Maintenance & Aircraft Support Equipment Building, a future Munitions Storage Area, and related site improvements.
LOCATION
Memphis, TN COMPLETION DATE
August 30th, 2009 COST
$ 56,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Tennessee Air National Guard Administrative Building The Tennessee Air National Guard 164th Airlift Wing relocation project consisted of multiple projects completed in multiple phases. Flintco’s role included the Administration Building Package and the Industrial Building Package. 17
The Administration Building Package was a 185,000 SF project that encompassed four buildings–the Communication and Security Building; the Base Supply and Aerial Port Building; the Operations and Training Building; and the Squadron Operations and Simulator Building.
LOCATION
Memphis, TN COMPLETION DATE
August 30th, 2009 COST
$ 39,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
FedEx Air Operations Training Center (AOTC) Expansion The FedEx Air Operations Training Center (AOTC) is a 250,000 SF state-of-the-art facility that houses 12 flight simulators, four fixed training devices, classrooms and office space. Phase II consisted of the build out of 42,000 SF within the AOTC to create the FedEx Experience Center. 18
The Experience Center houses an exhibit hall for multi-use purposes and gatherings, as well as a state-of-the-art auditorium that also serves as a support facility for flight training operations. The project achieved LEED certification.
LOCATION
Memphis, TN COMPLETION DATE
May 1st, 2014 COST
$ 51,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Boeing St. Louis Hangar 66/245 Upgrades During construction of Hangar 66, Alberici replaced nine 50-by-40 aircraft door panels and performed all associated electrical installation, fire protection, and field painting. All work was performed while the hangars, administrative, and operational areas remained in full operation. 19
On Building 245, the scope of work included construction of a 13,000 SF addition and installation a new 75-foot autoclave that housed the Advanced Ultrasonic Scanning System (AUSS), Advanced Machining Center, and installation of new hangar doors.
LOCATION
St. Louis, MO COMPLETION DATE
November 15, 2013 COST
$ 20,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
KC-46A Hangar Complex McConnell Air Force Base This project was a joint venture with Archer Western Aviation and included construction of a three-bay general purpose hangar, two-bay corrosion control/fuel cell hangar, general maintenance hangar, and aircraft parking apron along the existing flightline. 20
The project also features demolition of eight existing buildings, extensive site work, complex utility installation, and construction of a 6,000 SF composite shop.
LOCATION
McConnell AFB, KS COMPLETION DATE
August 28, 2017 COST
$ 154,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
KC-46A Two-Bay Hangar Construction of a new two-bay hangar to provide aircraft corrosion control, fueling maintenance and program depot maintenance (PDM) activities for the U.S. Air Force’s new KC-46A refueling aircraft within a 118,000 SF two-dock hangar facility. Each of the two aircraft 21
bays are 43,000 SF and are adjoined by an additional 32,000 SF of low bay office, administrative, and storage space. Alberici/Flintco is self-performing all of the concrete foundations and non-airfield concrete flatwork.
LOCATION
Tinker AFB, OK COMPLETION DATE
October 8th, 2019 COST
$ 120,800,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
C-5 Hangar Complex For 164th Airlift Wing Alberici constructed more than 331,000 SF of new hangars, including a 166,887 SF maintenance hangar, 79,970 SF corrosion control hangar, and 84,491 SF fuel cell hangar for the Tennessee Air National Guard’s 164th Airlift Wing at Memphis International Airport. 22
The hangar complex was executed in close proximity to active military and commercial runways and taxiways. In addition to concurrent work from adjacent contractors, multiple measures were taken to ensure operations at the commercial airport went uninterrupted.
LOCATION
Memphis, TN COMPLETION DATE
September 1st, 2008 COST
$ 142,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Boeing Hangar 375 Upgrades This 600,000 SF Hangar 375 is recognized as the largest active freestanding aircraft hangar in the world by the Guinness Book of World Records. It serves as Boeing’s Global Services & Support’s repair facility for a variety of military, commercial, and private aircraft. 23
Scope of work includes concrete demolition and replacement, extensive structural modifications, reinforcement of the existing structure, new entrance, exterior upgrades, interior modifications, and utility upgrades, including electrical, mechanical, and fire suppression systems.
LOCATION
San Antonio, TX COMPLETION DATE
April 3rd, 2019 COST
$ 37,000,000 FLINTCO, LLC | AV IAT ION PORT FOLIO
Tulsa Community College Jones Riverside Airport Aviation Center This nine month, fast-track project was staged on the campus of an active airport. Work included demolition of an existing 23,000 SF, two-story office space. The new space includes five classrooms for general education and training, and three simulator classrooms with an air traffic control simulator, a radar simulator, and 24
three flight simulators. Updated interiors include miscellaneous and structural steel, pipework, ductwork, paint, and epoxyfinished floors. The existing 27,000 SF hangar had a manual dividing wall added, separating the space into an east and west hangar space.
LOCATION
Tulsa, OK
COMPLETION DATE
December 14th, 2015 COST
$ 3,770,000 FLINTCO, LLC | AV IAT ION PORT FOLIO