Coordination Essential to Complex FAA Project

The Paving Lady relies on experience to complete complicated traffic control parking lot project, winning them Pavement’s 2022 Paving: Parking Lot Award

Any project for the Federal Aviation Administration (FAA) is not going to be easy and contractors who bid these jobs know that going into it. When you’re presented with a 1,000 page bid package, you either accept the challenge or walk away.

At the beginning of 2021, Mauro Comuzzi, president at The Paving Lady and John Provenzano, estimator, took on one such challenge with Parsons, a global general contractor. The company won the bid to reconstruct the Miami Air Route Traffic Control Center (ARTCC) parking lot and for their efforts, won Pavement’s 2022 Paving: Parking Lot award as well.

“The Miami ARTCC is the fifth busiest ARTCC in the USA and handles over 2 million aircraft operations a year,” Comuzzi says. “We were approached by Parsons to come in and mill and pave their entire facility, which was mostly parking lots and side roads. We were also asked to complete the

At the beginning of 2021, Mauro Comuzzi, president at The Paving Lady and John Provenzano, estimator, won the bid to reconstruct the Miami Air Route Traffic Control Center (ARTCC) parking lot and for their efforts, won Pavement’s 2022 Paving: Parking Lot award as well.

concrete sidewalk, curbing, ADA repairs and striping throughout the site.”

Before their bid was accepted, the company had to be vetted. They needed to show certified payrolls, complete background checks for all team members and provide bonding for the project. Comuzzi and Provenzano didn’t shy away from the job because of these requirements.

“I have a background in construction management and John has completed Port Authority work, so we went into this project with a very aggressive outlook,” Comuzzi says.

Given their experience and licensing as a State Certified General Contractor, the company also decided they would act as the general contractor for the project instead of as a paving sub-contractor.

“We felt that as a paving contractor, we were going to have the edge if we took it on as a general contractor,” Comuzzi adds. “We typically do not act as a GC but on this project, 90% of the scope was paving, so it was an easy decision for us to act as the prime contractor and that worked out very well for us.”

WHO IS THE PAVING LADY?

In 1985, Janice Potter started The Paving Lady to serve communities in South Florida. When she retired in 2016, Mauro Comuzzi took over as president and saw untapped potential for the company.

“Janice did a phenomenal job of establishing this company and the reputation of the quality of this business,” Comuzzi says. “When we took this company over, it was like a thoroughbred horse that wanted to run but wasn’t being allowed to run.

“We took what Janice started and marketed it a different way. She was mostly into private work when she retired and we took the company into municipal, government, private and commercial. We also started doing a lot of site work and new construction work for site work contractors. So we diversified what we do and that allowed the company to flourish quickly”

Today, the company has four times more employees than in 2016 and has grown 20-30% each year.

“We are growing in a controlled way, our team is our number one asset and we want to protect them, but we see nothing to stand in the way of our growth,” Comuzzi says.

EFFICIENT PROJECT PHASING Acting as the GC, The Paving Lady could also help guide how the work was done.

The original bid would have had the team working in 10 different phases to complete the work in what the facility deemed as “manageable chunks” that would keep the facility open and operational, and allow the ARTCC team to maintain security protocol.

“That would have spread the timeline of the work out to be over 90 days,” Comuzzi says. “They wanted us to come in and mill, pave, stripe and open one segment of the lot and then move on to the next area and mill, pave and stripe.

ETNYRE’S NEW 2022NEW NEXT GENERATION

LIVE BOTTOM

TESTED FRAME DESIGNED FOR A MINIMUM 10-YEAR FATIGUE LIFE 10” DIA BELT PULLEYS MAKE FOR LONGER BELT LIFE AND IMPROVED TRACTIVE EFFORTS

NEW FLASHING RETAINING SYSTEM FOR BETTER PERFORMANCE & MAINTENENCE REDESIGNED DOOR HINGE VASTLY REDUCES ASPHALT BUILD-UP

Etnyre has always prioritized the customer experience during our 125 year existence. Customer satisfaction was also at the forefront of our newest project, the rebuild of the Etnyre Falcon Live Bottom Trailer.

This ground-up rebuild, with the help of an independent engineering firm, has led to a product that is more efficient, safer, and durable than any previous Etnyre Live Bottom model.

This is a product we are proud to offer.

INTERNATIONAL

bearcatmfg.com etnyre.com resroadsaver.com

1333 S Daysville Rd. Oregon, IL 61061 www.etnyre.com (815) 732-2116

No two phases of work could be done at the same time with their original plan.”

The team at The Paving Lady instead proposed doing all work in three or four segments and they would then move on to the next area. Comuzzi said their background of working with housing associations gave them an edge in their phasing operations.

“We went in and had a pre-construction meeting and suggested a different way of doing the job,” Comuzzi says. “This would allow us to get the work done quicker so we would be there less time, and they really liked that idea.”

The new plan would move the project forward efficiently and keep in line with the security regulations.

“Our guys needed to be within eyesight of the ARTCC staff at all times,” Comuzzi says. “They couldn’t drive a machine around the corner without someone going with them. We proposed a plan that would allow them to manage their security team, while also completing the work in a timely manner.”

Oh and by the way, the entire bid process was done without anyone on the team actually seeing the site due to COVID protocols.

OVERCOMING OBSTACLES & STAYING ON TASK Once the proposed plan was accepted, crews got to work. Upon entry and exit to the site, all vehicles and personnel were searched by security forces. Two resident engineers were on site continuously monitoring the work and the staff to assure compliance with the project specifications and FAA regulations.

Each day, the ARTCC team required 24-hour advance notice of every employee that was going to be on site. Not just their team, but team members on all the sub-contractors as well.

“The process was cumbersome because we would have to come up with this list of the people that were going to be there and if you weren't on that list, and you showed up, you were not getting in,” Comuzzi says.

The adaptability of the crew is what made this project successful.

“Any good contractor could do what we did on this job,” he says. “We were contracted to mill and pave, anybody can do that. But it takes a certain amount of teamwork and coordination to do it successfully like this. I think the people involved on our side, our team that we had involved in this, is the reason that this job went so well.”

The crew used a Wirtgen 7-ft. mill to remove 2400 tons of material. They chose a Weiler P385 for the paving so the team would be able to maneuver within the tighter areas. The crew milled and paved the 28,654 square yard area on time and under budget.

UNPLANNED WORK ADDED TO PROJECT About 45 days into the work, The Paving Lady crew was 90% completed with the work. ARTCC asked the Parsons team if it would be possible to construct two brand new parking lots, something that was not mentioned on the bid, but work the team felt comfortable with.

“This is one of the busiest air traffic control centers in the United States so you can imagine, there was mechanical equipment every two feet. That’s a maze of equipment that we had to pave and sealcoat around,” Comuzzi says. “And if you hit something, you never knew the consequences, so we had to be very careful anywhere we were digging.”

Before they could begin work on the lot, the team had to use ground penetrating radar equipment to see if there was anything below ground and mark everything that was there.

“We don't typically like getting into new construction, other than paving new construction, but on this, we felt that we had the right subcontractors and the right people with us that we could do it and we did our jobs very well.”

Their experience and ability to adapt to project demands outside the scope of their daily tasks is what made this project successful.

“I don’t think any contractor has the processes or procedures in place that will give you an edge in these types of projects,” Comuzzi says. “I think it's all about the people that you have working for you.” ■

See all 2022 Pavement Award winners at ForConstructionPros.

com/21992866

PAVING: PARKING LOT RUNNERS UP

Maul Paving Sealcoating and Concrete, Naperville, IL Ruston Paving, Durham, NC

This article is from: