Reclaimed Water Master Plan

Page 1

Final Report

RECLAIMED WATER MASTER PLAN

City of Fort Myers November 2005

Independent Environmental Engineers, Scientists and Consultants


CITY OF FORT MYERS RECLAIMED WATER MASTER PLAN TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY ...........................................................................................ES-1 1.0

INTRODUCTION ............................................................................................... 1-1 1.1 Purpose and Scope ................................................................................... 1-1 1.2 Previous Reclaimed Water Planning ....................................................... 1-2 1.2.1 1992 Reclaimed Water Master Plan ............................................ 1-2 1.2.2 Effluent Resource Planning Report, March 2001 ........................ 1-3 1.3 Planning Area........................................................................................... 1-4

2.0

REGULATORY FRAMEWORK ....................................................................... 2-1 2.1 Regulatory Background ........................................................................... 2-1 2.2 Treatment Parameters .............................................................................. 2-2 2.3 Federal Requirements .............................................................................. 2-4 2.4 State Requirements .................................................................................. 2-6 2.4.1 Florida Department of Environmental Protection........................ 2-6 2.4.2 FDEP Permit Requirements......................................................... 2-9 2.4.3 South Florida Water Management District ................................ 2-13 2.5 City of Fort Myers Code of Ordinances Requirements ......................... 2-14

3.0

FORT MYERS RECLAIMED WATER SYSTEM ............................................ 3-1 3.1 Wastewater Treatment Facilities.............................................................. 3-1 3.1.1 General......................................................................................... 3-1 3.1.2 Wastewater Treatment Capacity .................................................. 3-1 3.1.3 Treatment Process........................................................................ 3-2 3.2 Reclaimed Water Production Facility...................................................... 3-3 3.2.1 General......................................................................................... 3-4 3.2.2 Treatment Capacity...................................................................... 3-4 3.2.3 Treatment Process........................................................................ 3-4 3.2.4 Onsite Finished Storage ............................................................... 3-5 3.2.5 Distribution System ..................................................................... 3-5 3.3 Existing Reclaimed Water Use ................................................................ 3-6 3.3.1 Existing Users .............................................................................. 3-6 3.3.2 User Characteristics ..................................................................... 3-8 3.3.3 Historical Reclaimed Water Use.................................................. 3-9 3.3.4 Seasonal Trends ......................................................................... 3-11 3.3.5 Historical Potable Water Irrigation Use..................................... 3-12

City of Fort Myers Reclaimed Water Master Plan Table of Contents

Malcolm Pirnie, Inc. i


CITY OF FORT MYERS RECLAIMED WATER MASTER PLAN TABLE OF CONTENTS (Continued) PAGE 3.4

Existing System Configuration .............................................................. 3-14 3.4.1 Perceived System Deficiencies .................................................. 3-14 3.4.2 Planned Improvements............................................................... 3-15 3.4.3 Billing Rates............................................................................... 3-16

4.0

EVALUATION OF EXISTING SYSTEM ......................................................... 4-1 4.1 Distribution System Hydraulic Model ..................................................... 4-1 4.2 System Performance Criteria ................................................................... 4-2 4.2.1 CAWWTP and CRWPF Capacity Limitations............................ 4-2 4.2.2 Distribution Pump Capacity......................................................... 4-3 4.2.3 System Storage............................................................................. 4-3 4.2.4 Distribution System Pressure Requirements................................ 4-3 4.2.5 Distribution System Head Loss Requirements ............................ 4-3 4.3 Demand Allocation .................................................................................. 4-4 4.3.1 Existing Distribution System Model............................................ 4-5 4.3.2 Model Calibration ........................................................................ 4-7 4.4 Identification of Existing System Deficiencies........................................ 4-8 4.5 CAWWTP and CRWPF Effluent Flow Analysis .................................. 4-12

5.0

FUTURE RECLAIMED WATER SUPPLY AND DEMANDS ....................... 5-1 5.1 Future Reclaimed Water Supply.............................................................. 5-1 5.1.1 Treatment Capacity...................................................................... 5-1 5.1.2 Reclaimed Water Availability...................................................... 5-2 5.2 Identification of New Potential Reclaimed Water Users ........................ 5-2 5.2.1 Previous Studies Review.............................................................. 5-3 5.2.2 Discussions with City Staff.......................................................... 5-3 5.2.3 Correspondence with City Departments and Developers ............ 5-4 5.3 Future User Demands .............................................................................. 5-4 5.3.1 Calculation of Future User Maximum Demands ......................... 5-4 5.3.2 Future Reclaimed Water Users by Service Areas........................ 5-7 5.3.3 Demand Patterns .......................................................................... 5-9 5.4 Excess Water Storage and Disposal Options ......................................... 5-11 5.4.1 Excess Treated Effluent and Reclaimed Water Produced ......... 5-11 5.4.2 Discharge to the Caloosahatchee River ..................................... 5-12 5.4.3 Rapid Infiltration Basins ............................................................ 5-13 5.4.4 Shallow Aquifer Recharge Injection Wells ............................... 5-14 5.4.5 Deep Injection Wells.................................................................. 5-14 5.4.6 Aquifer Storage and Recovery (ASR) ....................................... 5-15 5.4.7 Discharge through Regional Interconnections........................... 5-16

City of Fort Myers Reclaimed Water Master Plan Table of Contents

Malcolm Pirnie, Inc. ii


CITY OF FORT MYERS RECLAIMED WATER MASTER PLAN TABLE OF CONTENTS (Continued) PAGE 6.0

MODEL EVALUATION OF FUTURE DISTRIBUTION SYSTEM................ 6-1 6.1 Model Performance Criteria .................................................................... 6-1 6.2 2009 Model .............................................................................................. 6-2 6.2.1 Piping Required for the 2009 Model ........................................... 6-3 6.2.2 2009 Model Pressures .................................................................. 6-6 6.2.3 Potential 2009 Interconnection Location ..................................... 6-7 6.2.4 Excess Wastewater Effluent and Reclaimed Water Produced..... 6-7 6.3 2024 Model .............................................................................................. 6-7 6.3.1 Piping Required for the 2024 Model ........................................... 6-8 6.3.2 2024 Model Pressures ................................................................ 6-11 6.3.3 Potential 2024 Interconnection Locations ................................. 6-13 6.3.4 Excess Wastewater Effluent and Reclaimed Water Produced... 6-13

7.0

COST ESTIMATE FOR FUTURE IMPROVEMENTS..................................... 7-1 7.1 Basis of Cost ............................................................................................ 7-1 7.2 5-Year Improvements .............................................................................. 7-2 7.2.1 Production Improvements............................................................ 7-2 7.2.2 Interconnection ............................................................................ 7-2 7.2.3 Distribution Piping....................................................................... 7-3 7.3 20-Year Improvements ............................................................................ 7-5 7.3.1 Production Improvements............................................................ 7-5 7.3.2 Interconnection ............................................................................ 7-6 7.3.3 Distribution Piping....................................................................... 7-7 7.4 Reclaimed Water Revenue Projection ..................................................... 7-9 7.5 Cost Savings Attributed to the Use of Reclaimed Water....................... 7-11 7.6 Funding Sources..................................................................................... 7-11 7.6.1 FDEP State Revolving Fund Load Program.............................. 7-12 7.6.2 SFWMD Alternate Water Supply (AWS) Grant Program ........ 7-12 7.6.3 Funding Strategy........................................................................ 7-13

8.0

SUMMARY OF CONCLUSIONS AND RECOMMENDATIONS .................. 8-1 8.1 Findings and Conclusions ........................................................................ 8-1 8.1.1 Existing Reclaimed Water System............................................... 8-1 8.1.2 Regulatory Summary ................................................................... 8-2 8.1.3 Historic and Projected Reclaimed Water Demands..................... 8-3 8.1.4 Operational Control ..................................................................... 8-5 8.1.5 Reliability of Reclaimed Water ................................................... 8-6

City of Fort Myers Reclaimed Water Master Plan Table of Contents

Malcolm Pirnie, Inc. iii


CITY OF FORT MYERS RECLAIMED WATER MASTER PLAN TABLE OF CONTENTS (Continued) PAGE 8.1.6 8.2

Costs and Improvements associated with Future Reclaimed Water Improvements.................................................................... 8-6 Recommendations.................................................................................... 8-7 8.2.1 Future Planning Initiatives........................................................... 8-7 8.2.2 Future Infrastructure Requirements ........................................... 8-10

LIST OF TABLES Table No. Description

Following/On Page

ES.1 Existing User Average and Maximum Demands..............................................ES-2 ES.2 Existing and Future Reclaimed Production Capacity .......................................ES-3 ES.3 Future Projected Demands and Capacities........................................................ES-3 ES.4 Future Distribution System Costs .....................................................................ES-4 ES-5 Interconnection Costs for 2009..........................................................................ES-5 ES-6 Interconnection Costs for 2010 through 2024 ...................................................ES-5 ES-7 Costs for New Piping Needed by 2009..............................................................ES-6 ES-8 Piping Costs for 2010 through 2024 ..................................................................ES-7 1.1 1992 Master Plan Projected Buildout Wastewater and Reclaimed Flows........... 1-3 2.1 Inorganic and Organic Constituents of Concern in Reclaimed Water................. 2-3 2.2 Federal Guidelines for Various Types of Reuse Applications............................. 2-5 2.3 Secondary Treatment Standards from 40 CFR Part 133...................................... 2-4 2.4 FAC Chapter 62-600, Requirements for Domestic Wastewater Facilities .......... 2-7 2.5 Monitoring Schedule for Wastewater Treatment Plant Effluent ......................... 2-8 2.6 Existing Effluent Quality Requirements for Surface Water Discharge ............. 2-10 2.7 Existing Effluent Quality Requirements for Reuse and Land Application for the Central AWWTF .................................................................................... 2-11 2.8 Summary of Reclaimed Water Effluent Analysis Reports for the Central RWPF.................................................................................................... 2-12 2.9 Applicable Regulations as Stated in the City’s Code ........................................ 2-14 3.1 Approximate Length of Existing Reclaimed Water Distribution Piping............. 3-6 3.2 Existing User Characteristics............................................................................... 3-9 3.3 Historical Reclaimed Water Use.......................................................................... 3-9 3.4 Annual Average Reclaimed Water Demands for Existing Users ...................... 3-10 3.5 Monthly Potable Water Irrigation Meter Demands for 2003............................. 3-13 4.1 Model Performance Criteria ................................................................................ 4-2

City of Fort Myers Reclaimed Water Master Plan Table of Contents

Malcolm Pirnie, Inc. iv


CITY OF FORT MYERS RECLAIMED WATER MASTER PLAN TABLE OF CONTENTS (Continued) LIST OF TABLES (Continued) Table No. Description 4.2 4.3 4.4 4.5 4.6 5.1 5.2 5.3 5.4 5.5 5.6 5.7 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 7.1 7.2 7.3 7.4 7.5 7.6 8.1 8.2 8.3

Following/On Page

Existing Reclaimed Water Distribution System Customer Model Scenario Demands .............................................................................................................. 4-4 Existing Reclaimed Model Pipes ......................................................................... 4-6 Summary of Model Output vs. Performance Criteria ......................................... 4-8 Pressures for Reclaimed Water Users for the Maximum Demand Scenario ..... 4-10 Summary of Effluent Volumes from the CAWWTF and CRWPF for the Average and Maximum Demand Scenarios ...................................................... 4-12 Future Wastewater Treatment and Reclaimed Water Production Capacities...... 5-2 Projected Wastewater AADF and Maximum Possible Reclaimed Water Production ............................................................................................................ 5-2 Future Reclaimed Water Customers .................................................................... 5-5 Total Potential Reclaimed Water Demand .......................................................... 5-7 Future Maximum Demands By Service Area...................................................... 5-7 New User Demand Patterns ............................................................................... 5-10 Summary of Projected Excess Wastewater Effluent and Excess Reclaimed Water Supply ..................................................................................................... 5-12 Model Performance Criteria ................................................................................ 6-2 Existing Piping Used in the 2009 Model ............................................................. 6-3 New Piping Needed for the 2009 Model ............................................................. 6-4 Minimum Distribution Pressures for the 2009 Model ......................................... 6-6 Total 1-week Flow Volumes for the 2009 Model................................................ 6-7 Existing Piping Used in the 2024 Model ............................................................. 6-8 New Piping Needed for the 2024 Model ............................................................. 6-9 Minimum Distribution Pressures for the 2024 Model ....................................... 6-11 Total 1-week Flow Volumes for the 2024 Model.............................................. 6-13 Cost Estimate for the Gateway Interconnection .................................................. 7-3 Costs for Piping Needed by 2009 ........................................................................ 7-3 Interconnection Costs for 2010 through 2024 ..................................................... 7-6 Piping Costs for 2010 through 2024 .................................................................... 7-8 Existing and Projected Revenue from Reclaimed Water Billing......................... 7-9 Projected Revenue Potential from Interconnections.......................................... 7-10 Historical and Projected Minimum Three-Month Rolling Average Wastewater Flows.................................................................................................................... 8-4 Historical and Projected “Lowest� Three Month Average Wastewater Flows ... 8-5 Recommended City Parks for Reclaimed Water Irrigation ................................. 8-8

City of Fort Myers Reclaimed Water Master Plan Table of Contents

Malcolm Pirnie, Inc. v


CITY OF FORT MYERS RECLAIMED WATER MASTER PLAN TABLE OF CONTENTS (Continued) LIST OF FIGURES Figure No. Description ES.1 ES.2 1.1 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 5.1 5.2

Following/On Page

Existing and Proposed Reclaimed Water Users.................................................ES-3 Future Reclaimed Water Distribution Piping Grid ............................................ES-4 Reclaimed Water Service Areas ......................................................................... 1-4 Wastewater Treatment Facility Locations .......................................................... 3-1 Organization Chart for the Central and South AWWTP’s ................................. 3-2 Aeration Tank at the South AWWTP .................................................................. 3-2 Five-Stage Bardenpho Treatment Process Schematic ......................................... 3-3 Clarifiers at the Central AWWTP........................................................................ 3-3 CAWWTP Filter Building ................................................................................... 3-4 Reclaimed Treatment Process Schematic ............................................................ 3-4 Central RPF Storage Tank and Effluent Pumping............................................... 3-5 Existing Reclaimed Water Users and Distribution System Configuration.......... 3-6 J.B. Schultz City Nursery..................................................................................... 3-7 Lee County Resource Recovery Facility ............................................................. 3-7 Median Irrigation on Dr. Martin Luther King Jr. Blvd........................................ 3-8 Annual Average Reclaimed Flows .................................................................... 3-10 Monthly Reclaimed Average Flows .................................................................. 3-11 Seasonal Trends 1997 through 2003.................................................................. 3-12 2003 Monthly Potable Water Irrigation Demand .............................................. 3-13 Water and Sewer Main Replacement Project .................................................... 3-16 Existing Reclaimed User Demand Factors .......................................................... 4-5 Existing Average and Maximum Scenario Model Demands............................... 4-6 Existing Reclaimed Water Distribution Model Pipe Diameters and Nodes Elevations........................................................................................... 4-6 Comparison of Model and Actual Hourly Flows................................................. 4-7 Flow Info and Out of the CPWPF Storage .......................................................... 4-9 CRWPF Tank Levels ........................................................................................... 4-9 Existing Maximum Demand Scenario Pressure and Head Loss........................ 4-10 Pressure at the LCRRF....................................................................................... 4-11 Hydraulic Grade Line from the CRWPF to the LCRRF.................................... 4-11 Existing and Proposed Reclaimed Water Users................................................... 5-7 Interconnection and ASR Locations Identified by SFWMD in the RIDS Plan ................................................................................................ 5-16

City of Fort Myers Reclaimed Water Master Plan Table of Contents

Malcolm Pirnie, Inc. vi


CITY OF FORT MYERS RECLAIMED WATER MASTER PLAN TABLE OF CONTENTS (Continued) LIST OF FIGURES (Continued) Figure No. Description 6.1 6.2 6.3 6.4

Following/On Page

2009 Future Distribution Piping Phases .............................................................. 6-3 2009 Future Distribution Piping Diameters......................................................... 6-4 2024 Future Distribution Piping Phases .............................................................. 6-8 2024 Future Distribution Piping Diameters......................................................... 6-8

LIST OF APPENDICES Appendix A B C D

Description Previous Reclaimed Water Planning Recommended Improvements Reclaimed Water or Effluent Analysis Report, 2001-2003 City of Fort Myers Code of Ordinance, Chapter 26, Article V City of Fort Myers Code of Ordinance, Chapter 26, Article X

City of Fort Myers Reclaimed Water Master Plan Table of Contents

Malcolm Pirnie, Inc. vii


EXECUTIVE SUMMARY Malcolm Pirnie has completed this Reclaimed Water Master Plan to review the existing infrastructure and recommend system improvements for the City of Fort Myers reclaimed water production and distribution system for short term (5-year) and long term (20-year) planning horizons. The City plans to expand the reclaimed water treatment capacity at the Central AWWTP and construct new production capacity at the South AWWTP for a total reclaimed production capacity of 15 mgd.

Plans to build a third wastewater treatment

plant in the East side of the City will also provide additional reclaimed water capacity to the City. The current reclaimed water distribution system will be expanded to maximize reclaimed water utilization within the City. Malcolm Pirnie also plans to train City staff to use the GIS model that was prepared for this report of the distribution system production and piping network for future infrastructure planning efforts. Existing Reclaimed Production and Distribution System The 2.0 mgd capacity Reclaimed Water Production Facility (RWPF) currently produces approximately 700,000 gallons per day of high quality reclaimed water from their Central Advanced Wastewater Treatment Plant (CAWWTP). Secondary effluent generated from the CAWWTP is filtered through sand filters and disinfected with chlorine. A 1-MG ground storage reservoir and 75-horsepower, 150-ft TDH, 1,400 gpm pumps are controlled by variable frequency drives to provide storage and pumping capacity for the distribution system, which currently serves seven users. Nearly 28 miles of irrigation piping have been installed, but not all of the piping is presently serving customers.

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Malcolm Pirnie, Inc. ES-1


Existing System Model The existing reclaimed water distribution system was modeled for the average and peak demands of the current seven users to determine if any existing system deficiencies are present. The average and peak demands of the existing seven reclaimed water users included in the model are summarized in Table ES.1.

Table ES.1: Existing User Average and Maximum Demands Average Demand (mgd)

Maximum Demand (mgd)

Red Sox Minor League Facility

0.051

0.148

J. B. Schutz City Nursery

0.046

0.106

City of Fort Myers, WTP

0.006

0.028

Lee County Resource Recovery Facility

0.555

1.014

Buckingham Community Park Medians on Dr. Martin Luther King Jr. Blvd. Housing Authority Total Existing Demands

0.031

0.075

0.019

0.087

0.009

0.026

0.717

1.484

User Name

The model results showed that the current reclaimed production and distribution system can meet the peak demands of existing City customers and maintain pressure of 45 psi to the Lee County Resource Recovery Facility. The production facilities and piping distribution network for the existing model were then expanded to serve future customers for the future 5-year (2009) and 20-year (2024) model scenarios. Future Production Improvements For the 5-year future model, the reclaimed water production at the Central Reclaimed Production Facility is expanded to 6.0 mgd capacity and a new 9.0 mgd capacity is built at the South AWWTP. For the 20-year future model an additional wastewater treatment facility with 8.0 mgd reclaimed capacity is built at a new East AWWTP location. The City’s future reclaimed production capacity assumed for the existing and future reclaimed models are summarized below in Table ES.2.

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Malcolm Pirnie, Inc. ES-2


Table ES.2: Existing and Future Maximum Reclaimed Production Capacity Reclaimed Production Facility

Reclaimed Production Capacity

Central RWPF

South RWPF

East RWPF

Total Reclaimed Capacity

Existing

2.0 mgd

N/A

N/A

2.0 mgd

2009

6.0 mgd

9.0 mgd

N/A

15.0 mgd

2024

6.0 mgd

9.0 mgd

8.0 mgd

23.0 mgd

Future Users Forty-eight additional reclaimed water users were identified and included as future customers within the City limits. The future proposed reclaimed water customers consist of: • • • • • •

City parks Golf courses New residential developments New commercial developments Some existing residential and commercial customers along reclaimed water piping routes Expansion of the Lee County Resource Recovery Facility

The names and locations of the future reclaimed users are shown in Figure ES.1. The total reclaimed user demand does not equal the maximum reclaimed capacity for the future scenarios. The maximum identified reclaimed user demands and excess reclaimed capacities for the future 2009 and 2024 scenarios are summarized in Table ES.3.

Table ES.3: Future Projected Demands and Capacities

Future Scenario

Maximum Reclaimed User Demands

Excess Reclaimed Treatment Capacity

2009

6.26 mgd

8.74 mgd

2024

15.15 mgd

7.85 mgd

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Malcolm Pirnie, Inc. ES-3


Legend

Parcels

36 - Seminole Park

Reclaimed Users

38 - Ft. Myers Country Club

1 - Buckingham Community Park

2 - Lee County Resource Recovery Facility 3 - City Nursery

4 - Housing Authority 5 - Medians on MLK

50 51 53 49 52 47 45

39

39

41

42

4

38

33

37

63

60 34

0

5

59

8 - Eastwood Golf Course

3 6

13

7 8 64 6566 67 58

26 27

9

10

11

29 28

30

7 - City of Fort Myers, WTP

9 - Lee County Resource Recovery Facility Expansion

31

32

40

35

36 62

48

46

6 - Red Sox Minor League Facility

54 61 55

71 68 69 70 25

15 72

12

14

73 16 56

11 - Eastwood Golf Course Expansion

1

12 - Forum Development (Omni) 13 - Orchard

57

17

14 - Development S of 82, E of Treeline Extension 15 - Colonial Plaza 16 - Sherwood

17 - Pelican Preserve Golf Courses 18 - Pelican Preserve

19

19 - Colonial Golf & Country Club (Golf Course)

20 23

24

2

10 - Heritage Lakes

18

20 - Colonial Golf & Country Club (Residential) 21 - Arborwood Course

22 - Arborwood Residential

23 - Palomino Reflection Isles

21

24 - Paseo

25 - Pratt Commercial Users

26 - Heritage Palms Golf Course

22

27 - Heritage Palms 28 - Province Park 29 - Berkshire

30 - Colonial Properties DRI 31 - Dupree Park 32 - Dunbar Park

33 - Winkler Neighborhood

34 - Fleishman Little League Ball field 35 - McGregor Boulevard

City of Fort Myers Reclaimed Water Master Plan

Existing and Proposed Reclaimed Water Users

37 - Jefferson Park

39 - West of McGregor 40 - Coronado Park 41 - Lions Park

42 - Red Sox Main Field 43 - Yawkey Park

44 - Five Points Park 45 - Centennial Park 46 - Downtown

47 - East Downtown 48 - Clemente Park

49 - Cook Lake Park 50 - Riverside Park 51- Freemont Park

52 - Shady Oaks Park 53 - Terry Park

54 - Police Athletic(Billy Bowlegs Park) 55 - Dean Park

56 - Zemel South

57 - Lee Blvd Plaza

58 - Cypress Woods

59 - Colonial Plantation

60 - Proposed Residential 61 - Casa La Linda

62 - McGregor Oaks Townhomes 63 - Lennar Homes/Matera 64 - International College

65 - Golden Corral Restaurant 66 - Walmart at Colonial 67 - Lowes

68 - Watermen Development 69 - Winkler 39

70 - Cypress Point Commercial 71 - Bernwood

72 - Olympia Point 73 - Apex/Publix

Figure ES.1 October 2005


Future Distribution Modeling The future modeling was completed for future 5-year and 20-year scenarios. The production improvements listed above were included.

The new distribution piping

diameters were sized to reduce cost while providing adequate pressure to the reclaimed users for a one week simulation period. The piping routes were chosen for the perceived path of least resistance. The model also included storage for potential interconnections with Lehigh Acres and Gateway, located between the Gateway and Arborwood developments, and with Cape Coral, located at the east end of the Mid Point Bridge. These interconnections were also locations for offsite storage. The proposed piping grid and interconnection locations for the 2009 and 2024 future scenarios are shown in Figure ES.2.

Costs A summary of the production capacity upgrades, distribution system piping improvements as per the modeling results, and the potential interconnection costs are presented in Table ES.4. A breakdown of the costs for the interconnections and new piping are listed in Tables ES.5, ES.6, ES.7 and ES.8. The production capacity cost for the 5-year planning period includes upgrades to the CRWRF and SRWRF. For the 20year planning period, the production capacity cost accounts for construction of a new East RWPF.

Table ES.4: Future Distribution System Costs Planning Horizon

Production Capacity ($ in millions)

Distribution System Piping ($ in millions)

Interconnections ($ in millions)

5-year

$17

$10.5

$0.7

20-year

$13

$5.3

$1.8

Total

$30

$15.8

$2.5

Grand Total

City of Fort Myers Reclaimed Water Master Plan Executive Summary

$48.3

Malcolm Pirnie, Inc. ES-4


Future Reclaimed Water Distribution Piping Grid

Prepared By: Malcolm Pirnie, Inc.

City of Fort Myers Reclaimed Water Master Plan

Figure ES.2


Table ES.5 Interconnection Costs for 2009 Cost per Unit

Item

Quantity

Units

Estimated Costs

Gateway Interconnection 12-inch Diameter Pipeline

$60

5,700

Control Valve

$10,000

1

valve cost

Flow Meter

$20,000

1

meter cost

Engineering Design Fee

10%

$3,592,000

Contingency

20%

$3,592,000

$5,000

1

Operations and Maintenance

ft

$342,000

Subtotal pump station cost pump station cost years

$10,000 $20,000 $372,000 $359,200 $718,400 $5,000

Total Cost Estimate for the Gateway Interconnection

$1,454,600

Table ES.6: Interconnection Costs for 2010 through 2024 Item 16-inch pipeline from the SRWPF 16-inch pipeline across the Caloosahatchee River Control Valve Flow Meter

Cost per unit Quantity Cape Coral Interconnection

Units

Estimated Costs

$80

6,100

ft

$488,000

$200

10,000

ft

$2,000,000

$15,000 $30,000

1 1

valve cost meter cost Subtotal pump station Engineering Design Fee 10% $2,533,000 cost pump station Contingency 20% $2,533,000 cost Operations and Maintenance $10,000 10 years Total Cost Estimate for the Cape Coral Interconnection Lehigh Acres Interconnection Control Valve $15,000 1 valve cost Flow Meter $30,000 1 meter cost Subtotal pump station Engineering Design Fee 10% $45,000 cost pump station Contingency 20% $45,000 cost Operations and Maintenance $5,000 14 years Total Cost Estimate for the Lehigh Acres Interconnection Gateway Interconnection Operations and Maintenance $5,000 15 years Total Cost Estimate for the Gateway Interconnection Total Interconnection Costs from 2010 through 2024

City of Fort Myers Reclaimed Water Master Plan Executive Summary

$15,000 $30,000 $2,533,000 $253,300 $506,600 $100,000 $3,392,900 $15,000 $30,000 $45,000 $4,500 $9,000 $70,000 $128,500 $75,000 $75,000 $3,596,400

Malcolm Pirnie, Inc. ES-5


Table ES.7 Costs for New Piping Needed by 2009

Street Location

Length (ft)

Diameter (in)

Carrell Service Area Carrell Road 18,500 24 5,300 16 Veronica Shoemaker Boulevard 1,100 10 Subtotal Carrell Service Area Piping Cost Downtown Service Area Central Avenue 500 10 Edison Avenue 700 6 First Street 1,700 8 Jackson Street 1,100 4 Lafayette Street 2,100 8 McGregor Boulevard 800 4 US 41 700 4 Subtotal Downtown Service Area Piping Cost McGregor Service Area Carrell Road 1,600 24 DeLeon Street 8,300 24 Edison Avenue 1,400 6 Euclid Avenue 500 6 FTM Golf to DeLeon 1,300 24 1,900 12 Ft. Myers Country Club 1,200 24 Victoria Avenue 800 6 Subtotal McGregor Service Area Piping Cost Dr. Martin Luther King Service Area 2,200 8 Cranford Avenue 800 6 Edison Avenue 2,600 16 High Street 1,400 6 Indian Street 2,000 6 Michigan Street 600 10 Palm Avenue 700 6 Ford Street 5,300 16 Veronica Shoemaker Boulevard 7,800 16 Subtotal Dr. Martin Luther King Service Area Piping Cost

Total Approximate Cost $ $ $ $

2,931,000 560,000 73,000 3,564,000

$ $ $ $ $ $ $ $

33,000 28,000 90,000 30,000 111,000 22,000 19,000 333,000

$ $ $ $ $ $ $ $ $

254,000 1,315,000 56,000 20,000 206,000 151,000 191,000 32,000 2,225,000

$ $ $ $ $ $ $ $ $ $

117,000 32,000 275,000 56,000 80,000 40,000 28,000 560,000 824,000 2,012,000

\

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Malcolm Pirnie, Inc. ES-6


Table ES.7 Costs for New Piping Needed by 2009 (Continued)

Street Location

Colonial Boulevard

Length (ft) Diameter (in) East Service Area 2,600 20 900 16

Treeline Avenue

Subtotal East Service Area Piping Cost Southeast Service Area 100 16 5,700 12 100 12 2,700 16 700 10 3,500 20 5,700 16

Ben C. Pratt Parkway

Subtotal East Service Area Piping Cost South Service Area 100 16

Colonial Country Club Gateway Interconnection Pelican Preserve South Treeline Avenue

Total Approximate Cost

Subtotal East Service Area Piping Cost

$ $

344,000 96,000

$

440,000

$ $ $ $ $ $ $

11,000 452,000 8,000 286,000 47,000 462,000 602,000

$

1,868,000

$

11,000

$ 11,000 $ 10,453,000

Total 2009 System New Piping Costs

Table ES.8: Piping Costs for 2010 through 2024

Street Location

Length (ft)

Diameter (in)

Carrell Service Area Broadway Solomon 3000 Schoolhouse Road 700 Colonial Boulevard from Veronica 2200 Veronica Shoemaker Boulevard 900

1st Street Palm Beach Boulevard

4 10 4 6

Subtotal Carrell Service Area Downtown Service Area 3100 8 1300 8 Subtotal Downtown Service Area

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Approximate Cost $ $ $ $

80,000 47,000 59,000 36,000

$

222,000

$ $ $

164,000 69,000 233,000

Malcolm Pirnie, Inc. ES-7


Table ES.8: New Piping Costs for 2010 through 2024 (Continued) Street Location

Length (ft) Diameter (in) McGregor Service Area Arthur Avenue 700 4 Barkley and Royal Palm Square 5100 20 Coronado Road 1900 4 Cortez Boulevard 2200 4 Jefferson Avenue 400 8 La Palma Lane 800 12 McGregor Boulevard 900 16 Matera 1200 4 Princeton Avenue 900 10 Shadow Lane 1800 6 Winkler Avenue 600 10 Subtotal McGregor Service Area Dr. Martin Luther King Service Area Dupree Street 900 4 1800 4 Edison Avenue 4100 10 Marsh Avenue 3100 4 Michigan Street 2800 8 Veronica Shoemaker Boulevard 2000 10

Approximate Cost

Subtotal Dr. Martin Luther King Service Area East Service Area Colonial Boulevard 5400 20 Lee Boulevard 2100 20 Lee Boulevard to Buckingham Road 2300 20 North Treeline Avenue 2400 8 Subtotal East Service Area

$ $ $ $ $ $ $ $ $ $ $ $

19,000 674,000 51,000 59,000 22,000 64,000 96,000 32,000 60,000 72,000 40,000 1,189,000

$ $ $ $ $ $

24,000 48,000 271,000 82,000 148,000 132,000

$

705,000

$ $ $ $

713,000 278,000 304,000 127,000

$

1,422,000

Southeast Service Area Arborwood to Reflection Isles

5,100

10

$

337,000

Reflection Isles

3,000

10

$

198,000

Reflection Isles to Paseo

3,800

10

$

251,000

$

786,000

Subtotal Southeast Service Area

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Malcolm Pirnie, Inc. ES-8


Table ES.8: New Piping Costs for 2010 through 2024 (Continued) Street Location

Length (ft)

Diameter (in)

Approximate Cost

Palm Beach Service Area 4700

8

$

249,000

Bell Street

1000

6

$

40,000

East Riverside Drive

1300

4

$

35,000

700

8

$

37,000

2400

4

$

64,000

1100

4

$

30,000

Palm Beach Boulevard

3000

6

$

119,000

Royalston Avenue

2500

4

$

66,000

Terry Avenue

600

4

$

16,000

Veronica Shoemaker Boulevard

900

10

$

60,000

$

716,000

$

5,273,000

Marion Avenue

Subtotal South Service Area Total 2024 System New Piping Costs

Funding The projected revenues from reclaimed users total $19.8 million over the next 20 years.

The city will need to increase reclaimed rates to cover the cost of the

improvements, or will need to investigate other methods of funding including State Revolving Funds, grants. The cost estimates assume that Lehigh Acres, Lee County, and the City of Cape Coral will contribute 50% of the costs to construct interconnections. The City could have residential developers complete the installation of some reclaimed transmission mains in return for reduced taxes until the cost of the mains are reimbursed. Recommendations We recommend the City move forward with reclaimed water production capacity as required by their water and wastewater permits. The distribution of reclaimed water to customers and adjacent municipalities should be maximized by completion of the infrastructure improvements listed above.

We also recommend that the following

initiatives be pursued by the City:

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Malcolm Pirnie, Inc. ES-9


• • • • • • •

Encourage reclaimed water for new developments Implement reclaimed water irrigation at select City parks Require storage at user locations to reduce peak demands As reuse system is implemented, seek to reduce quantity of effluent discharged to the Caloosahatchee River from the CAWWTP and SAWWTP Expedite reclaimed water storage and pumping facilities at the East AWWTP location to have storage and pumping capacity by 2009. Install RIBs or deepwell injection at the East AWWTP for disposal of excess effluent and reject reclaimed water Explore the opportunity to construct interconnections in partnership with Gateway, Lehigh Acres, and the City of Cape Coral

City of Fort Myers Reclaimed Water Master Plan Executive Summary

Malcolm Pirnie, Inc. ES-10


1.0 INTRODUCTION Malcolm Pirnie has prepared this Reclaimed Water Master Plan report for the City of Fort Myers as part of our contract to provide professional engineering services for master planning of the City’s potable water, wastewater, and reclaimed water systems. This Master Plan is based on an independent evaluation of the reclaimed water distribution system facilities, and provides the City with a plan to prepare for the expansion of the reclaimed treatment and distribution system through the year 2024. The City of Fort Myers (City) currently produces approximately 700,000 gallons per day of high quality reclaimed water from their 2.0 mgd capacity Reclaimed Water Production Facility (RWPF) located at their Central Advanced Wastewater Treatment Plant (CAWWTP). The CAWWTP and South Advanced Wastewater Treatment Plant (SAWWTP) have a combined wastewater capacity of 23 mgd AADF and currently treat a combined average of 13 million gallons of sewage each day from both the City and County residents. The City plans to expand the reclaimed water treatment capacity at the Central AWWTP and construct new production capacity at the SAWWTP for a total future reclaimed production capacity of 15 mgd. Plans to build a third wastewater treatment plant in the East side of the City will provide additional reclaimed water capacity to the City. The current reclaimed water distribution system will be expanded to maximize future reclaimed water utilization within the City.

1.1

PURPOSE AND SCOPE This Master Plan will assist the City in planning for increased wastewater effluent

quantities from the City’s treatment facilities, as well as future requirements for an increased effluent disposal through an expanded reclaimed water distribution system. This Master Plan will provide a guide and a phased system improvements implementation schedule for expanding the City’s reclaimed water system over the next 5 and 20-year planning periods. The purpose of the Master Plan is to develop practical and economical strategies for expanding service and increasing the reclaimed water system customer base, both in the near-term and the long-term. City of Fort Myers Reclaimed Water Master Plan Section 1: Introduction

Malcolm Pirnie, Inc. 1-1


The goals and objectives of the Reclaimed Water Master Plan project generally include the following: • • • •

Identification of potential future reclaimed water customers. Projection of future reclaimed water supply, quality, and demands. Identification of the City of Fort Myers’ costs to serve new customers. Prioritization of potential customers based on cost to provide service and the volume of use.

A key component of this master planning effort was the development of an interactive GIS model of the City’s reclaimed water distribution system using H2OMAP software. The model was used to analyze existing deficiencies and plan for future demands associated with system growth for 5-year and 20-year milestones. Malcolm Pirnie worked with City planning and growth staff to determine applicable criteria for future modeling scenarios, such as location of future customers, corresponding demands, and City-wide storage requirements.

The model will be turned over to the City at the

end of the Master Planning effort. Malcolm Pirnie will also provide training to City staff for their use of the modeling software. This Master Plan provides recommendations on distribution storage and pumping requirements and the required pipeline routing to provide service to future customers. A cost estimate is also included for the recommended storage, pumping, and piping improvements.

1.2

PREVIOUS RECLAIMED WATER PLANNING Previous master planning efforts were performed within the City of Fort Myers

that provided the City with a substantial amount of information in regards to a future potential for reclaimed water demand throughout the City.

Future customers were

identified and a basis for reclaimed water demand within the City was established.

1.2.1

1992 Reclaimed Water Master Plan

The City of Fort Myers Reclaimed Water Master Plan was prepared in 1992 by Boyle Engineering. This master plan identified potential reclaimed water demand for various types of users (irrigation, indoor, industrial, and fire), and also determined the

City of Fort Myers Reclaimed Water Master Plan Section 1: Introduction

Malcolm Pirnie, Inc. 1-2


facility and distribution system modifications necessary for inclusion of a reclaimed water production facility. The projected wastewater and reclaimed production flows at buildout condition from the 1992 Master plan are summarized below in Table 1.1. The report included recommendations for plant upgrades and interconnections between the plants. Table 1.1: 1992 Master Plan Projected Buildout Wastewater and Reclaimed Flows Flow (mgd) 1992 Wastewater Treatment AADF Capacity Future Wastewater AADF Capacity Maximum Reclaimed Production Wet Weather Reclaimed Demand Dry Weather Reclaimed Demand

CAWWTP

SAWWTP

New East AWWTP

Total

11

12

N/A

22

11

16

10

37

4

16

10

30 16.8 28.0

This Master Plan was the first step toward developing a comprehensive program to initiate the use of reclaimed water by the City; however few of the recommendations were implemented. Table A.1 provided in Appendix A summarizes the improvements recommended in the 1992 Reclaimed Water Master Plan report.

1.2.2

Effluent Resource Planning Report, March 2001

The City of Fort Myers Effluent Resource Planning Report was prepared by Camp, Dresser, & McKee in March 2001. This document provided an update of the existing reuse supply commitments and identified potential reuse customers to satisfy the estimated future reclaimed water demands. Eighteen potential reclaimed water users were identified, providing a total demand of approximately 7.4 mgd, in addition to the City’s existing 0.7 mgd of reclaimed water demand. Projected reclaimed water demand for 2005 and 2010 was estimated to be 3.8 mgd and 8.1 mgd, respectively. The effluent disposal alternatives of deep well injection and aquifer storage and recovery were evaluated for different combinations of wastewater, reclaimed water, and reverse osmosis concentrate produced at the City’s water treatment plant. Table A.2 provided in Appendix A lists the improvements recommended in the 2001 Effluent Resource Planning Report. This 2001 Planning Report served as the basis for developing this Reclaimed Water Master Plan. City of Fort Myers Reclaimed Water Master Plan Section 1: Introduction

Malcolm Pirnie, Inc. 1-3


1.3

PLANNING AREA The City wishes to limit the reclaimed planning area to the existing City limits.

Existing reclaimed water piping exists throughout the City and was installed during initial road and development construction. Due to the City’s current priority to target large, bulk users of reclaimed water, some of the pipes are not currently being used to provide flow to customers. The reclaimed service area has been divided into named service areas, as shown in Figure 1.1, and described below by its bordering streets: • • • • • • • •

Downtown Service Area - downtown area including East and West First Street, the area north of Edison Avenue and west of Evans Avenue. McGregor Service Area - the area west of Cleveland Avenue and south of Downtown. Palm Beach Service Area – east of Evans Avenue and north of Michigan Avenue. Dr. Martin Luther King Jr. Service Area – south of Michigan Avenue and north of Edison Avenue, east of Evans Avenue and to the west of Ortiz Avenue. Carrel Service Area - east of Cleveland Avenue, west of Interstate 75, north of Colonial Boulevard, and south of Canal Street. South Service Area - west of Interstate 75 and south of Colonial Boulevard East Service Area - east of Veronica Shoemaker Boulevard, north of Colonial Boulevard and south of Canal Street. Southeast Service Area - south of Colonial Boulevard and east of Interstate 75 consists of the Southeast service area.

City of Fort Myers Reclaimed Water Master Plan Section 1: Introduction

Malcolm Pirnie, Inc. 1-4



2.0 REGULATORY FRAMEWORK The City’s Reclaimed Water Production Facility and reclaimed water distribution system are governed by numerous Federal, State, and local laws, regulations, policies, and agreements. The reclaimed water system is subject to the regulatory requirements of the United States Environmental Protection Agency (USEPA), the Florida Department of Environmental Protection (FDEP), and the South Florida Water Management District (SFWMD). The reclaimed water system must comply with standards set by the State and the City’s Code of Ordinances including the use of properly treated wastewater effluent, wherever possible. 2.1

REGULATORY BACKGROUND The City of Fort Myers Wastewater Treatment Division consists of two regional

Advanced Wastewater Treatment Plants. The Central Advanced Wastewater Treatment Plant (CAWWTP) is located at 1501 Raleigh Street and is designed to treat 11 million gallons of wastewater per day.

The South Advanced Wastewater Treatment Plant

(SAWWTP), located at 1618 South Drive, is designed to treat 12 million gallons per day. These plants treat wastewater from all of the City of Fort Myers and much of Lee County. The majority of the treated effluent from the two plants is discharged to the Caloosahatchee River. However, a portion of the Central Plant effluent is diverted to the Central Reclaimed Water Production Facility (CRWPF), located at the CAWWTP, and further treated to reclaimed water standards for irrigation and industrial process purposes. The CRWPF has a permitted maximum month treatment capacity of 2 million gallons per day (mgd) and a permitted annual average daily flow capacity of 1.51 mgd. The existing system serves 7 customers with high quality reclaimed water that is used for both industrial and irrigation purposes. Provisions for the CRWPF to be upgraded to a capacity of 6 mgd are currently under way. In addition, design of a South Reclaimed Water Production Facility (SRWPF) with a 9 mgd capacity is currently in the works. According to the City’s 2000 Water Use Permit, this 15 mgd of reclaimed capacity will satisfy the permit requirements and continue to keep the City in compliance until the year 2015. City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-1


The current CAWWTP permit allows for an annual average discharge of 11 mgd to the Caloosahatchee River and a 1.51 mgd annual average daily flow capacity for the reuse system. The current SAWWTP permit allows for an annual average discharge of 12 mgd to the Caloosahatchee River.

The current wastewater facility permits for

CAWWTP and SAWWTP expire on May 1, 2005 and March 21, 2005, respectively.

2.2

TREATMENT PARAMETERS The Central Reclaimed Water Production Facility performs biological nutrient

removal, tertiary filtration, and high-level disinfection to achieve reclaimed water quality. The effluent undergoes sample testing to determine the pH and total residual chlorine concentration following disinfection, and the pre-chlorination total suspended solids (TSS) concentration. If each parameter satisfies the regulated limits (pH=6.0-8.5, TSS ≤ 5mg/L, Cl2 ≼ 1mg/L), the effluent is discharged into the reclaimed water storage tank, from where it is withdrawn based on distribution system demand. If these regulated limits are not met, the effluent is sent back to the filter influent. The typical constituents found in reclaimed water are presented in Table 2.1. Conventional constituents found in raw wastewater can be treated to reclaimed water quality with most conventional wastewater treatment processes and non-conventional constituents may have to be removed or reduced using enhanced wastewater treatment processes. Numerous Federal, State, and local policies establish requirements for the operation and treatment of municipal wastewater treatment plants. Various operating parameters and corresponding effluent limitations are regulated and monitored on a regular basis to protect water resources.

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-2


Table 2.1 Inorganic and Organic Constituents of Concern in Reclaimed Water Constituent

Measured Parameters

Reason for Concern

Conventional Constituents

Suspended Solids

Volatile and fixed solids

Organic contaminants, heavy metals, etc. are absorbed on particulates. Suspended matter can shield microorganisms from disinfectants. Solids can cause plugging in irrigation systems.

Biodegradable Organics

Biochemical oxygen demand, Chemical oxygen demand, Total organic carbon

Organics provide food for microorganisms, adversely affect disinfection processes, make water unsuitable for some industrial uses, consume oxygen, and may result in health effects if reclaimed water used for potable purposes.

Nutrients

Nitrogen, Phosphorus, Potassium

When discharged to an aquatic environment, nitrogen and phosphorus can lead to growth of undesirable aquatic life. When applied in excessive levels on land, nitrogen can lead to build-up of nitrate in the groundwater.

Hydrogen Ion Concentration

pH

The pH affects disinfection, coagulation, metal solubility, and alkalinity of the soils. Normal range in municipal wastewater is pH = 6.5 - 8.5.

Residual Chlorine

Free and combined chlorine

Excessive amount of free available chlorine (>0.05 mg/L) may cause damage to some sensitive crops. Chlorinated organics may cause toxicity in groundwater.

Non-Conventional Constituents Stable Organics

Specific compounds (e.g., pesticides, chlorinated hydrocarbons)

Some are resistant to conventional wastewater treatment methods. Some are toxic in the environment and they may limit the suitability of reclaimed water for irrigation or other uses.

Dissolved Inorganics

Total dissolved solids, electrical conductivity, specific elements (e.g., Na, Ca, Mg, Cl, and B)

Excessive salinity may damage some crops. Specific ions such as chloride, sodium, boron are toxic to some crops. Sodium may pose permeability problems.

Heavy Metals

Specific elements Cd, Zn, Ni and Hg)

Some heavy metals accumulate in the environment and are toxic to plants and animals. Their presence may limit the use of the reclaimed water for irrigation or other uses.

(e.g.,

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-3


2.3

FEDERAL REQUIREMENTS There are currently no Federal regulations directly governing reclaimed water use.

However, the USEPA regulates many aspects of wastewater treatment and drinking water quality, and the majority of states in the U.S. have established criteria or guidelines for the beneficial use of recycled water. The EPA developed a technical document entitled Guidelines for Water Reuse, which contains such information as a summary of state requirements, and guidelines for the treatment and uses of recycled water. Federal water reuse guidelines are summarized in Table 2.2 below for three different reuse scenarios. In addition to the reuse guidelines, the EPA also developed secondary treatment regulations in response to the Clean Water Act requirements.

The EPA evaluated

performance data for treatment plants practicing secondary treatment. Reclaimed water is limited to secondary treatment standards established by the EPA. These standard regulations, which are specified in 40 CFR Part 133, apply to the biological treatment component of a municipal wastewater treatment plant and represent the minimum level of effluent quality attainable by secondary treatment, as reflected in terms of BOD5 demand and TSS removal.

Secondary treatment standards, therefore, are defined by the

limitations provided in Table 2.3.

Table 2.3 Secondary Treatment Standards from 40 CFR Part 133 Parameter

30-Day Average

7-Day Average

CBOD5

30 mg/l

45 mg/l

TSS

30 mg/l

45 mg/l

pH

6 - 9 s.u. (instantaneous)

–

Removal

85% CBOD5 and TSS

–

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-4


Table 2.2 Federal Guidelines for Various Types of Reuse Applications Types of Reuse Urban Reuse Landscape irrigation, vehicle washing, toilet flushing, fire protection

Treatment • • •

Secondary Treatment Filtration Disinfection

Reclaimed Water Quality • • • • •

Agricultural Reuse Nonfood crops, animal pasture, fiber and seed crops

• •

Secondary Treatment Disinfection

• • • • •

Indirect Potable Reuse Groundwater recharge by spreading into potable aquifers

• • •

Site specific Secondary Treatment and Disinfection (min.) May also need filtration and/or advanced wastewater treatment

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

• •

Reclaimed Water Monitoring

pH = 6 – 9 ≤10 mg/L biochemical oxygen demand (BOD) ≤2 turbidity units (NTU) No detectable fecal coliform/100 mL 1 mg/L chlorine (Cl2) residual (min.)

• • • • •

pH - weekly BOD – weekly Turbidity – continuous Coliform – daily Cl2 residual - continuous

pH = 6 – 9 ≤30 mg/L BOD ≤30 mg/L total suspended solids (TSS) ≤200 fecal coliform/100 mL 1 mg/L Cl2 residual (min.)

• • • • •

pH - weekly BOD – weekly TSS – daily Coliform – daily Cl2 residual - continuous

Site specific Meet drinking water standards after percolation through vadose zone

• • • • •

pH - daily Turbidity – continuous Coliform – daily Cl2 residual – continuous Drinking water standards – quarterly Other – depends on constituent

Malcolm Pirnie, Inc. 2-5


2.4

STATE REQUIREMENTS This section discusses the various regulations and permit requirements set forth

by FDEP and SFWMD. State regulations and guidelines govern the required effluent quality for surface water discharge and reuse of reclaimed water. The FDEP is responsible for issuance or denial of operation permits for domestic wastewater facilities based on wastewater effluent quality monitoring and reporting requirements. The following sections of the Florida Administrative Code (FAC) apply to the supply, treatment, and distribution of reclaimed water. • • • • •

2.4.1

Chapter 62-600 Domestic Wastewater Facilities Chapter 62-601 Domestic Wastewater Treatment Plant Monitoring Chapter 62-610 Reuse of Reclaimed Water and Land Application Chapter 62-620 Wastewater Facility and Activities Permitting Chapter 62-40 Water Resource Implementation Rule

Florida Department of Environmental Protection

The FDEP is responsible for development and maintenance of rules governing water reuse activity within the state. Reclaimed water treatment, quality, and use are all regulated by the FDEP. The primary document utilized for regulation of reclaimed water is Chapter 62-610 of the FAC. Within this document, guidelines are provided to ensure the level of treatment required for specific uses of reclaimed water, the required reclaimed water monitoring frequencies, and the criteria for land application systems. All reuse and land application systems must be operated and maintained in accordance with Chapter 62-610. Detailed requirements for the design and operational criteria of a wide range of reuse and land application systems are consistent with EPA's Guidelines for Water Reuse, as discussed in Section 2.1 and shown in Table 2.2. Discharge of reclaimed water or domestic wastewater effluent into waters of the state is regulated by the FDEP.

Both the Central and South AWWTPs currently

discharge the majority of their effluent to the Caloosahatchee River, with the Central plant also discharging part of its effluent into the reclaimed system. FAC Chapter 62-600 contains design, operation, and compliance requirements for all domestic wastewater facilities. Treatment levels, disinfection requirements, and pH requirements also are City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-6


contained. Domestic wastewater must meet, at a minimum, a treatment standard of secondary treatment, basic disinfection, and pH control in order to be reused as reclaimed water. Table 2.4 summarizes the requirements of FAC Chapter 62-600.

Table 2.4 FAC Chapter 62-600, Requirements for Domestic Wastewater Facilities Standard

Parameter

Requirement

Secondary Treatment (surface water disposal to Class III waters)

CBOD5

20 mg/l

TSS

20 mg/l

Secondary Treatment (surface water disposal via ocean outfall)

CBOD5

30 mg/l

TSS

30 mg/l

Basic

0.5 mg/L

Single Sample: Fecal ≤ 800 per 100 mL of sample

High Level

1.0 mg/L

Single Sample: TSS ≤ 5 mg/L (prior to disinfection) Fecal ≤ 25 per 100 mL of sample

Intermediate

1.0 mg/L

Single Sample: Fecal ≤ 86 per 100 mL of sample

Low Level

-

pH

6 – 8.5

Disinfection (after 15 min. contact time, at peak hourly flow rate)

pH

Notes or 90% removal

or 85% removal

Single Sample: Fecal ≤ 2400 per 100 mL of sample After disinfection

Chapter 62-601 of the FAC establishes the minimum requirements for monitoring of domestic wastewater facilities. Monitoring of various effluent wastewater parameters must be conducted according to the specified frequencies. This regulation ensures that domestic wastewater facilities conduct required monitoring, maintain accurate records, and submit required reports in accordance with the monitoring schedule. Table 2.5 summarizes the minimum schedule required for sampling and testing of wastewater treatment plant effluent.

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-7


Table 2.5 Monitoring Schedule for Wastewater Treatment Plant Effluent Parameter

Monitoring Frequency

Flow

Continuous

pH

Continuous

Dissolved Oxygen

7 days/wk

Suspended Solids

5 days/wk

CBOD5

5 days/wk

Nutrients

5 days/wk

Total Residual Chlorine (disinfection)

Continuous

Total Residual Chlorine (dechlorination)

7 days/wk

Fecal Coliform

5 days/wk

The FDEP protects surface water bodies by requiring justification for discharge of wastewater effluent rather than another approved means of effluent disposal. The FDEP Antidegradation Policy is contained in Chapter 62-4 FAC, titled Permits, and Chapter 62302, titled Surface Water Quality Standards.

Compliance with the FDEP

Antidegradation Policy must be justified prior to issuance of a permit by FDEP for any new or expanded surface water discharge. The Antidegradation Policy requires a utility, proposing to construct a new discharge or expansion of an existing discharge, to demonstrate that an alternative disposal method such as reuse of domestic reclaimed water is not feasible in lieu of a discharge to surface water, and that the receiving water body will not be adversely impacted by the discharge. FAC Chapter 62-620 includes permitting requirements for reclaimed water treatment and distribution. Chapter 62-620 offers guidance on the permit for addition of a major user of reclaimed water and the application required for permission to place a public access reuse system in operation. A major user of reclaimed water is defined as anyone using 100,000 gpd or more, based on annual average. All major users must have a FDEP permit authorizing capacity based on type of use or application area. The LCRRF and Eastwood Golf Course are the only two major users currently permitted to receive reclaimed water within the City’s reclaimed water distribution system. The Eastwood Golf Course, however, is a recent addition and is not yet using reclaimed water. City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-8


A public access reuse system involves irrigation of areas that are intended to be accessible to the public, such as residential lawns, golf courses, cemeteries, parks, landscape areas, and highway medians. The City’s CRWPF is currently permitted as a slow-rate public access reuse system (Part III of FAC 62-610), consisting of landscape irrigation of City property, commercial property, and industrial uses. Reclaimed water, at a minimum, must meet secondary treatment and high-level disinfection standards to be allowed for use in public access areas. Filtration must also be provided for control of suspended solids. Prior to disinfectant application, the suspended solids content must be no more than 5 mg/L. The City is currently authorized by the FDEP to provide reclaimed water for “Other Landscape Irrigation and Industrial Uses (cooling water, process water, and wash water at industrial facilities).” The City currently does supply reclaimed water to the Housing Authority, which irrigates residential homes; however, it is under the control of the development and not the individual homeowner. In the future, as more reclaimed water customers are added to the system, many will be residential developments. Therefore, upon expansion of the system and addition of new users, it will be necessary for the City to gain permission for residential irrigation by the individual homeowners. For those residential areas that will be newly constructed, the City can make arrangements to supply reclaimed water to an end user, who will then be required to provide it to the entire development. This will allow the City to provide a given quantity of reclaimed water, without the burden of providing storage and pressure for distribution.

2.4.2

FDEP Permit Requirements

Issuance of a Domestic Wastewater Facility Permit by the FDEP constitutes authorization to discharge to waters of the state within limits of the NPDES program. The FDEP also monitors wastewater effluent quality through enforcement of annual Reclaimed Water or Effluent Analysis Reports.

The following discussion briefly

summarizes the CAWWTP and SAWWTP effluent quality requirements for both surface water discharge and reclaimed water usage.

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-9


Surface Water Both the CAWWTP and the SAWWTP currently discharge the majority of their effluent to the Caloosahatchee River, which is a Class III marine water body. Discharges to the River must meet water quality requirements set forth in each facility’s operating permit, issued by the FDEP. The operating permits for the facilities are issued for 5-year terms and must be renewed upon their expiration. The current wastewater permit for the CAWWTP expires on May 1, 2005. The SAWWTP operating permit expires on March 21, 2005. Both the Central and South wastewater treatment plants provide advanced wastewater treatment (AWT). Treatment to AWT standards is required to reduce the total nitrogen and phosphorus concentrations regulated for surface water discharge. Table 2.6 outlines the NPDES permit requirements for both the Central and South plants for surface water discharge.

Table 2.6 Existing Effluent Quality Requirements for Surface Water Discharge Central AWWTP and South AWWTP Annual Monthly Weekly Unit Average Average Average

Parameter

Daily Average

Single Sample

Monitoring Frequency

Flow

mgd

-

11.0

-

-

-

Continuous

CBOD5

mg/L

20

25

40

-

60

5 days/wk

Suspended Solids

mg/L

20

30

45

-

60

5 days/wk

Total Nitrogen

mg/L

3

3

4.5

-

6

5 days/wk

Total Phosphorus

mg/L

0.5

0.5

0.75

-

1.0

5 days/wk

Total Residual Chlorine

mg/L

-

-

-

-

0.01

Daily

Dissolved Oxygen

mg/L

-

-

-

5.0

Daily

pH unit

-

-

-

-

#/100 mL

200

4.0 6.5 to 8.5 800

pH Fecal Coliform Whole Effluent Toxicity

Monthly 90th percentile = 400

Continuous 5 days/wk

Bioassay - species based on salinity of the effluent

Reclaimed Water Wastewater reuse permits, developed and monitored by the FDEP, specify the quantity and quality of effluent to be used as reclaimed water. State regulations currently specify minimum water quality criteria for individual reuse classifications falling within

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-10


the general categories of landscape irrigation and industrial uses. These water quality criteria are currently limited to numeric standards for biochemical oxygen demand, suspended solids, pH, and total residual chlorine limits. Table 2.7 outlines the reclaimed water quality requirements for the Central AWWTF. Table 2.7 Existing Effluent Quality Requirements for Reuse and Land Application for the Central AWWTF

Parameter

Central AWWTF Annual Unit Average

Monthly Average

Weekly Average

Single Sample

Monitoring Frequency

Flow

mgd

1.51

2.0

-

-

Continuous

CBOD5

mg/L

20

30

45

60

5 days/wk

Suspended Solids

mg/L

-

-

-

5

Daily

Total Residual Chlorine

mg/L

-

-

-

1.0

Continuous

pH unit

-

-

-

6.5 to 8.5

Continuous

pH Fecal Coliform

75 % of values below the detection limit

Daily

Monitoring requirement only

Continuous

Giardia

Monitoring and recording requirements only

Biannual

Cryptosporidium

Monitoring and recording requirements only

Biannual

Turbidity

Effluent Analysis During the period of operation authorized by the facility’s operating permit, reclaimed water or effluent should be monitored annually for primary and secondary drinking water standards. Twenty-four hour composite sample results should be reported to the FDEP annually for analysis on the Reclaimed Water or Effluent Analysis Report, Form 62.620.901(15). The City of Fort Myers Central AWWTP and RWPF analysis reports from 2000 to 2003 are included in Appendix B. Table 2.8 provides a summary of the effluent analysis conducted each year.

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-11


Table 2.8 Summary of Reclaimed Water Effluent Analysis Reports for the Central RWPF Parameter

Standard

Arsenic Barium Cadmium Chromium Fluoride Lead Mercury Nitrate (as N) Selenium Silver Sodium

0.05 1.0 0.010 0.05 4.0 0.05 0.002 10 0.01 0.05 160

Ethylene dibromide Para-dichlorobenzene Vinyl chloride 1,1-dichloroethane 1,2-dichloroethane 1,1,1-trichloroethane Carbon tetrachloride Trichloroethene Tetrachloroethene Benzene

0.02 75 1 7 3 200 3 3 3 1

Total THM

100

Endrin Lindane Methoxychlor Toxaphene 2.4-D 2.4.5-TP (Silvex)

0.02 4 100 5 100 10

Gross alpha excl. radon and uranium Radium-26 and Radium228 combined Chloride Copper Iron Manganese Sulfate Zinc pH (units) TDS Foaming Agents

15 5 250 1 0.3 0.05 250 5 6.5-8.5 500 0.5

2001 Analysis Units Results Inorganics mg/L <0.0028 mg/L <0.0001 mg/L <0.0002 mg/L <0.001 mg/L 0.6 mg/L <0.001 mg/L <0.001 mg/L 0.09 mg/L 0.0017 mg/L <0.001 mg/L 166 Volatile Organics ug/L <0.01 ug/L 0.83 ug/L <0.29 ug/L <0.1 ug/L <0.02 ug/L <0.21 ug/L <0.29 ug/L <0.02 ug/L <0.21 ug/L <0.00005 Trihalomethanes ug/L 130 Organic Chemicals ug/L <0.01 ug/L <0.024 ug/L <0.25 ug/L <0.5 ug/L <0.362 ug/L <0.025 Radiologicals pCi/L

<1.8 0.2 pCi/L <1.0 Secondary Chemicals mg/L 220 mg/L <0.0012 mg/L <0.030 mg/L 0.0165 mg/L 108 mg/L 0.072 mg/L 6.55 mg/L 740 mg/L 0.8

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

2002 Analysis Results

2003 Analysis Results

<0.0028 <0.0001 <0.002 <0.001 S0.461 <0.001 <0.001 0.15 <0.0016 <0.001 142

0.005 0.007 0.003 0.004 0.44 0.002 <0.001 0.86 0.003 <0.001 131

<0.01 <0.02 <0.29 <0.1 <0.02 <0.21 <0.29 <0.02 <0.21 <0.05

<0.005 <0.5 <0.5 <0.3 <0.2 <0.3 <0.3 <0.2 <0.2 <0.5

214

260

<0.01 <0.05 <0.25 <0.5 <0.100 <0.200

<0.1 <0.06 <0.05 <0.5 <0.5 <0.05

<2.4

<3.5

0.6

2.3

177 <0.0012 <0.030 0.0134 86 0.022 7.1 564 0.046

170 0.006 0.175 0.023 75 0.025 7.12 536 <0.05

Malcolm Pirnie, Inc. 2-12


2.4.3

South Florida Water Management District

Each of the state’s five water management districts has developed its own series of rules designed to implement reclaimed water programs authorized by Chapter 373 of the Florida Statutes and by Chapter 62-40 of the FAC. The SFWMD governs the Fort Myers area and plays a key role in the Water Reuse Program. The SFWMD encourages and directs water users and utilities to use reclaimed water and implement reuse programs.

The SFWMD also offers funding programs that can be used to finance

reclaimed water infrastructure. Chapter 62-40, entitled the Water Implementation Rule, presents the overall state water policy, providing guidance for issuing consumptive use permits.

This Rule

requires the SFWMD to designate critical water supply areas that either have existing water resources problems or areas in which water resource problems are projected to develop during the next twenty years. Lee County is included in this critical water supply designation. Under the City’s Consumptive Use Permit, issued in 2000 for supply to the Water Treatment Plant, the City is required to satisfy certain conditions in order to be in compliance. Conditions within the permit commit the City to make available and utilize 100-percent of the reclaimed water produced within the Fort Myers wastewater service area based on three-month low-flow conditions by March 2005, with a re-evaluation process every 5 years. The permit also requires the City to participate in the design of a regional reclaimed water distribution system as described in the Lower West Coast Regional Water Supply Plan (2000). The SFWMD has implemented a comprehensive approach to encourage water reuse, including water supply planning, regulation, coordination, and funding. SFWMD completed four regional water supply plans encompassing the land area within the SFWMD jurisdiction.. Each plan contains region specific recommendations on the use of reclaimed water. The SFWMD requires all applicants for Water Use Permits to evaluate the feasibility of implementing water reuse, and it coordinates its reuse activities at the state, local, and water user levels. In addition, the SFWMD has an alternative water supply funding program. The SFWMD has provided over $26 million in alternative

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-13


water supply grants for 113 projects since 1995, including water reuse projects, use of brackish water sources, and aquifer storage and recovery projects. 2.5

CITY OF FORT MYERS CODE OF ORDINANCES REQUIREMENTS The City of Fort Myers Code, Chapter 26: Public Facilities provides several rules

that pertain to reclaimed water use and distribution. Article 5, entitled Reclaimed Water Program, states the procedures and requirements for obtaining reclaimed water service and establishing a connection to the system. The methodology used for installation, sizing, and funding of the reclaimed water system is also included. Chapter 26, Article V of the City’s Code is attached in Appendix C. The City’s Ordinance states that the sources of reclaimed water shall comply with certain FDEP regulations as they may apply to the project. The sources of reclaimed water must also comply with state and local health department regulations and should gain approval prior to utilization. Table 2.9 lists various subparts within Chapter 17-6 of the FAC, as presented in the City’s Code of Ordinances. Table 2.9 Applicable Regulations as Stated in the City’s Code FAC

Subject

Chapter 17-6.060 Chapter 17-6.070 Chapter 17-6.080 Chapter 17-6.110 Chapter 17-6.140 Chapter 17-6.180

Effluent limitations Treatment plants Reuse and Effluent disposal (land application) Treatment plants and effluent disposal systems Permits required Enforcement

Chapter 17 is titled Department of Environmental Regulation, with 17-6 relating more specifically to Wastewater Facilities. The Department of Environmental Regulation in 1993 merged with the Department of Natural Resources to form the FDEP. Currently, the FDEP regulates wastewater facilities through Chapter 62 of the FAC, as described in Section 2.4.1, which includes updated information of that contained in Chapter 17. The City’s Code of Ordinances states that the City shall develop and maintain a reclaimed water master plan, which should include areas where construction and use of a reclaimed water system and pipeline transmission system are encouraged. The use of City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-14


reclaimed water is separately metered for each connection and appropriate rates are established by the City Council. Currently, City infrastructure exists to supply reclaimed water to developments for lawn irrigation, parks, golf courses, and open space in and adjacent to the City. However, for new development areas, a separate reclaimed water distribution system shall be installed in accordance with City engineering and construction standards. Identification of the reclaimed water system must include special considerations to avoid cross connections with the potable water system. Cross connection control is addressed in the City’s existing Code of Ordinances, Chapter 26. Chapter 26-211 states that: The reclaimed water distribution system shall include special considerations to avoid cross connections with the potable water system. The following features shall be included in reclaimed water systems to protect the public health: (1) (2) (3) (4) (5)

Reclaimed water distribution systems shall be constructed with brown PVC pipe or purple with yellow block letters color-taped ductile iron pipe. Square valve box covers painted brown to distinguish from round potable water system valve boxes. Brown strip on street curb to identify reclaimed water customer. Backflow preventers installed on potable water service connection. Reclaimed water meters color coded with tape to distinguish from potable water meters (where applicable). Meters, covers and meter box covers should be cast to indicate reclaimed water.

Chapter 26, Article X: Cross Connection Control Standards, is provided as Appendix D. This section does not specifically address reclaimed water concerns, and should be updated with similar language to Chapter 26-211. Also, additional standards should be developed to have double check valves, or reduced pressure backflow prevention devices installed at locations that have high risks for cross connections. The City should develop a schedule to periodically inspect reclaimed water services to assure that the cross connection requirements are being followed. Enhanced inspection efforts and education efforts will be required before residential or small commercial reclaimed water users are served by the City, as per the FDEP requirements in FAC 62-610.470 and 62-555.360.

City of Fort Myers Reclaimed Water Master Plan Section 2 Regulatory Framework

Malcolm Pirnie, Inc. 2-15


3.0 FORT MYERS RECLAIMED WATER SYSTEM The City of Fort Myers operates two wastewater treatment facilities. Only the CAWWTP currently has reclaimed water production capabilities. Currently, reclaimed water is used for landscape irrigation and industrial use. This section describes the existing reclaimed water system, identifies the current Fort Myers reclaimed water users, and describes the City’s public involvement and community education activities related to the reclaimed water program.

3.1 WASTEWATER TREATMENT FACILITIES The City’s two treatment facilities process wastewater from all of the City of Fort Myers and much of Lee County. Figure 3.1 illustrates the general location of both the South and Central advanced wastewater treatment facilities.

3.1.1

General

The CAWWTP and SAWWTP each have eleven operators, over a total of three shift periods, allowing for operation of the plant 24 hours per day, seven days per week. In addition to the treatment operators, each plant has necessary staff to assist with the maintenance of the facility. The Central plant staff, with the exception of the residuals operators, also work with the reclaimed CRWPF when necessary. The Organization Chart in Figure 3.2 shows the staffing allocation at the Central and South treatment plants.

3.1.2 Wastewater Treatment Capacity The CAWWTP currently has a permitted treatment capacity of 11 mgd. From January 1997 to May 2003 the annual average flow for the Central plant was around 6.6 mgd. The SAWWTP currently has a permitted treatment capacity of 12 mgd. From October 1997 through May 2003 the annual average flow was around 6.9 mgd.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-1



Figure 3.2 Organization Chart for Central and South AWWTPs

Central AWWTP Central AWWTP and RWPF staff South AWWTP staff

3.1.3 Treatment Process South Wastewater Plant Following

screenings

and

grit

removal at the SAWWTP, the mixed liquor travels through a 3.25 million gallon aeration tank, where nutrient removal takes place using the Bardenpho process. Figure 3.3 shows the South plant aeration tank. A basic diagram of the five-stage Bardenpho treatment process is shown in Figure 3.4.

Figure 3.3 Aeration Tank at the South AWWTP

Addition of aluminum sulfate (AlSO3) prior to clarification allows for the precipitation of phosphorus. The solids are then settled within the clarifiers and the clear effluent is disinfected with chlorine, dechlorinated, and finally discharged to the Caloosahatchee River. The solids removed from the clarification process are stabilized in aerobic digesters, dewatered using belt filter presses, and land applied as fertilizer.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-2


Figure 3.4 Five-Stage Bardenpho Treatment Process Schematic

Secondary Clarifier

Central Wastewater Plant Following screenings and grit removal at the CAWWTP, the mixed liquor travels through a 2.5 million gallon aeration tank, where nutrient removal

takes

place

using

the

five-stage

Bardenpho process (as shown in Figure 3.4). Next, the removal of phosphorus is performed through the addition of aluminum sulfate (AlSO3). The solids are then settled within the clarifiers and

Figure 3.5 Clarifiers at the Central AWWTP

are either returned to the process or dewatered and disposed of through land application. Figure 3.5 shows a picture of the clarifiers at the Central plant. The clear effluent from the clarifiers is disinfected with chlorine, dechlorinated, and either discharged to the Caloosahatchee River or sent to the on-site Reclaimed Water Production Facility (discussed in Section 3.2). The solids removed from the process are stabilized in aerobic digesters, dewatered using belt filter presses, and land applied as fertilizer.

3.2 RECLAIMED WATER PRODUCTION FACILITY The City of Fort Myers operates the Central Reclaimed Water Production Facility (CRWPF), located at the CAWWTP, which is currently the City’s only reclaimed water production facility. The City is currently planning for expansion of the Central RWPF and for the construction of a second reclaimed water facility at the South AWWTP. Figure 3.1 illustrates the general location of both the Central and South reclaimed water production facilities, once completed.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-3


3.2.1

General

The reclaimed water system operation began in 1994, and has grown to an annual demand of approximately 253 MG of reclaimed water in 2003.

3.2.2

Treatment Capacity

The CRWPF is designed for 2.0 mgd and also has a maximum month permitted capacity of 2.0 mgd and an annual average permitted capacity of 1.51 mgd.

3.2.3

Treatment Process

Secondary effluent generated from the CAWWTP enters the CRWPF and is filtered through sand filters. Filter effluent is disinfected with chlorine for public-access irrigation and distribution to various reuse sites. Figure 3.6 shows a picture of the filter building. A basic diagram of a reclaimed water treatment process and potential end users is

Figure 3.6 CAWWTP Filter Building

shown in Figure 3.7.

Figure 3.7 Reclaimed Treatment Process Schematic

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-4


3.2.4

Onsite Finished Storage

Onsite ground storage at the Central RWPF provides 1-MG of storage capacity. Figure 3.8 shows the storage tank and corresponding effluent piping. The storage tank measures 90 feet in diameter and has a maximum water depth of 20 feet.

3.2.5

Distribution System

Reclaimed water is pumped from the 1-MG storage tank into the distribution system using variable speed pumps. Two 75-horsepower, 150-ft TDH, 1,400 gpm pumps

are

controlled

by

variable

frequency drives, which vary the pump impeller revolutions per minute and flow to maintain a constant discharge pressure. Typically, the distribution system pressure

Figure 3.8 Central RPF Storage Tank and Effluent Piping

is maintained at 63 pounds per square inch (psi). The piping network supplies golf courses, City parks, landscaping, and industrial users with reclaimed water throughout the distribution system. The distribution system network consists primarily of 28 miles of pipelines ranging in diameter from 4 to 24 inches. The piping consists of mainly polyvinyl chloride pipe (PVC) and ductile iron pipe (DI), with the smaller diameter piping being PVC.

Table 3.1 shows the

approximate length of the distribution network piping classified by diameter and material.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-5


Table 3.1 Approximate Length of Existing Reclaimed Water Distribution Piping

Pipe Diameter (in.) 4 6 8 10 12 16 20 24

3.3

Pipe Material PVC PVC PVC DI DI DI DI DI Total (ft.)

Length of Existing Piping (ft.) Pipes supplying Pipes installed, but Total Existing customers from not currently in Pipes RWPF service (dry lines) 2,000 2,000 7,000 7,000 3,000 47,000 50,000 5,000 5,000 7,000 14,000 21,000 9,200 19,800 29,000 23,500 9,500 33,000 1,000 1,000 43,700 104,300 148,000

EXISTING RECLAIMED WATER USE 3.3.1

Existing Users

The Central Reclaimed Water Production Facility currently provides reclaimed water to seven customers in the City’s service area. Each of the seven users and their corresponding usage schedules are described in the following paragraphs. Figure 3.9 illustrates the general location of each of the existing users, as well as the existing distribution pipelines that supply each of the users with reclaimed water.

Red Sox Training Park The Red Sox training facility irrigates on Monday, Wednesday, Friday, and Saturday. There are ten zones that irrigate the infield and sidelines four times a week for approximately 10 minutes each. The facility also has forty zones that irrigate the outfield four times a week for approximately 15 minutes. The facility also has six zones that serve the common grounds around the ball fields that run for approximately 15 minutes, four times a week. Watering begins at around 9 pm for each of the zones.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-6



J.B. Schultz City Nursery The City Nursery uses reclaimed water three times a week between the hours of 7 am and 11 pm. Figure 3.10 shows the nursery during an irrigation cycle. Plants are watered Monday, Wednesday, and Friday mornings, as needed.

During periods of heavy rain, the Wednesday

cycle is eliminated. This location will be moved to the East on Buckingham Road in the future (at the time of the future

Figure 3.10 J.B. Schultz City Nursery

Eastwood Golf Course expansion, discussed in Section 5.3).

City of Fort Myers Water Treatment Plant The City’s Water Treatment Plant uses reclaimed water for site irrigation only. A twenty-six zone sprinkler system operates for approximately thirty minutes each day. Each zone operates on a five minute delay and therefore operation begins as early as 7 pm and finishes around 8:30 am.

Lee County Resource and Recovery Facility (LCRRF) This facility uses reclaimed water twenty-four hours per day, seven days a week. Figure 3.11 shows the LCRRF. The LCRRF uses the reclaimed water for such purposes as processing, washing, and cooling within the facility. The facility has 15,600 gallons of storage onsite. Upon completion of a new expansion in 2005, the reclaimed water consumption will increase by one-third. The LCRRF is currently the only

Figure 3.11 Lee County Resource and Recovery Facility

industrial user of reclaimed water; however, it accounts for the largest portion of reclaimed water use within the City of Fort Myers. It is also the only current reclaimed customer permitted as a major user (greater than 100,000 gpd).

Buckingham Community Park The use of reclaimed water at Buckingham Park consists of irrigation of the baseball field, football field, and various other landscaping throughout the park. An City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-7


estimated 15 minutes per cycle and two cycles per day allows for the baseball and football fields to be watered 6 days per week, Sunday through Friday. The general landscape irrigation consists of 15 to 30 minute cycles, once per day, for 6 days a week, Sunday through Friday.

Dr Martin Luther King Jr. (MLK) Median Irrigation The reclaimed irrigation system in operation on Dr. Martin Luther King Jr. Boulevard operates on Monday, Wednesday, and Friday. Irrigation lasts for 10 to 15 minutes per zone during the early morning hours. During periods of heavy rain, the Wednesday cycle is eliminated. Figure 3.12 shows a section of MLK where irrigation is performed using reclaimed water.

Figure 3.12 Median Irrigation on Dr. Martin Luther King Jr. Blvd.

Housing Authority The Housing Authority waters for irrigation purposes solely. A twenty-four zone system alternates so that twelve zones are watered each morning.

Operation lasts

between 12 am and 6 am.

3.3.2

User Characteristics

Each of the current seven reclaimed water customers primarily use reclaimed water for irrigation purposes. Only five of the users were originally accounted for in the Central AWWTF permit issued in May of 2000.

The remaining three users were

previously identified and have since become included in the City’s reclaimed water system. Table 3.2 provides a summary of each of the users and their corresponding acreage and permit capacity information from the CAWWTP operations permit.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-8


Table 3.2 Existing User Characteristics Type

CAWWTP Permit Capacity* (mgd)

Estimated Total Acreage

Irrigated Acreage

Red Sox Minor League Facility

Irrigation

0.07

46.7

32.5

J.B. Schultz City Nursery

Irrigation

0.04

5.0

5.0

City of Fort Myers, WTP

Irrigation

0.03

67.3

6.0

Lee County Resource Recovery Facility

Industrial

1.3

Buckingham Community Park

Irrigation

0.07

135.6

15.6

Medians on Dr. Martin Luther King Jr. Blvd.

Irrigation

6.9

Housing Authority *Data from CAWWTF permit.

Irrigation

30.0

User Name

3.3.3

Historical Reclaimed Water Use

Table 3.3 shows historical annual average reclaimed water usage by user for the years 1998 through 2003. Among the current users, the most common use for reclaimed water within the City is irrigation of public parks and landscaping. However, the largest user of reclaimed water is Lee County’s Resource and Recovery Facility. In 2003, the LCRRF accounted for the majority of all reclaimed water use. The remainder of the reclaimed users, practicing reuse through irrigation, accounted for less than 15 percent of the total reclaimed water use.

Table 3.3 Historical Reclaimed Water Use Historical Annual Average Water Use (gpd)

User Name Red Sox Minor League Facility J.B. Schultz City Nursery City of Fort Myers, WTP Lee County Resource Recovery Facility Buckingham Community Park Medians on Dr. Martin Luther King Jr. Blvd. Housing Authority Eastwood Golf Course1 TOTAL (gpd) Note:

1

1998

1999

2000

2001

2002

2003

70,142 52,084 1,237 457,376 -

63,914 61,009 6,550 513,585 -

81,430 53,253 14,025 495,682 -

58,268 32,769 5,472 562,162 22,838

19,286 47,826 3,460 611,246 35,560

11,064 29,379 5,437 687,272 35,334

-

-

-

-

29,060

8,294

580,840

645,059

644,389

681,509

1,158 747,598

16,993 793,773

0.75

0.79

TOTAL (mgd) 0.58 0.65 0.64 0.68 Not currently using reclaimed water, however connected to system.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-9


It is estimated that the total reclaimed water demand, from the seven existing users, will increase to approximately an annual average of 1.3 mgd, as a result of Eastwood Golf Course’s demand. Table 3.4 summarizes the average demand, maximum individual user monthly demands, and the demands used during the overall maximum month for each user. Figure 3.13 shows the annual average reclaimed water demand from 1998 through 2004 for each of the existing customers. Table 3.4 Annual Average Reclaimed Water Demands for Existing Users

Red Sox Minor League Facility

0.051

Maximum Individual Monthly Demands (mgd) 0.148

J.B. Schultz City Nursery

0.046

0.106

0.010

City of Fort Myers, WTP

0.006

0.028

0.011

Lee County Resource Recovery Facility

0.555

1.014

0.985

Buckingham Community Park

0.031

0.075

0.060

Medians on Dr. Martin Luther King Jr. Blvd.

0.019

0.087

0.022

Housing Authority

0.009

0.026

0.025

TOTAL = * Maximum month was March 2003

0.717

1.484

1.155

Average Demand (mgd)

User Name

Demand During Maximum Month* (mgd) 0.042

Figure 3.13 Annual Average Reclaimed Flows 700,000

600,000

500,000

Flow (gpd)

LCRRF Red Sox Facility

400,000

City Nursery Buckingham Park

300,000

MLK medians 200,000

City WTP Housing Authority

100,000

1998

1999

2000

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

2001 Year

2002

2003

2004

Malcolm Pirnie, Inc. 3-10


Evaluating each of the various reclaimed users and their peak month demands over the course of January 1998 to February 2004, revealed that the maximum month of reclaimed use (the combined demand for each user) was in March of 2003. The total reclaimed usage was approximately 1.15 mgd. Figure 3.14 depicts the proportional distribution of reclaimed usage during the maximum month with respect to each of the current users.

Figure 3.14 Monthly Reclaimed Average Flows (for maximum month March 2003)

City Nursery 3.6%

Dr. Martin Luther King Blvd, Jr. Median Irrigation 1.0%

Red Sox Minor League Facility 1.9% City of Fort Myers WTP 0.9% Housing Authority 2.1% Buckingham Community Park 5.2%

Lee County Resource Recovery Facility 85.3%

3.3.4

Seasonal Trends

In many areas, the amount of reclaimed water use varies each year based on the time of year and the corresponding rainfall conditions. Generally, in Florida, the summer months would correspond to a lower reclaimed demand due to the higher amount of rainfall. However, since the largest reclaimed user for the City of Fort Myers, the

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-11


LCRRF, demands reclaimed water year around, regardless of seasonal conditions, the seasonal rainfall induced trend in reclaimed water use is mitigated. Figure 3.15 shows the monthly trends for 1997 through 2003.

Figure 3.15 Seasonal Trends 1997 through 2003 1.30

1997 1999 2001 2003 Overall Avg. minus LCRRF Avg.

1.20 1.10 1.00

1998 2000 2002 Overall Average

Average Flow (mgd)

0.90 0.80 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0.00 Jan

Feb

March

April

May

June

July

August

Sept

Oct

Nov

Dec

Month

The variation in flow for each particular year corresponds to specific user demand fluctuations. The existing reclaimed water customers obtain reclaimed water directly from the system whenever a demand exists. The LCRRF receives a continuous flow of reclaimed water each day of the year at much larger quantities than the other users. Therefore, the depicted trend tends to only mirror the LCRRF usage, being that its demand is approximately an order of magnitude larger than the demand of the other users. In the future, as additional non-industrial users are added, a seasonal trend may become more evident.

3.3.5

Historical Potable Water Irrigation Use

The City currently supplies potable water to its users for irrigation purposes through approximately 564 metered connections that are strictly for irrigation. Table 3.5

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-12


summarizes the monthly potable water irrigation demand seen in 2003. Figure 3.16 shows the 2003 potable water irrigation quantities graphically.

Table 3.5 Monthly Potable Water Irrigation Meter Demands for 2003 Month

Demand (gpd)

January February March April May June July August September October November December

11,882 13,676 13,326 14,172 23,996 19,730 10,716 11,238 9,210 14,496 17,580 14,478

Figure 3.16 2003 Monthly Potable Water Irrigation Demand 30,000

25,000

Demand (gpd)

20,000

15,000

10,000

5,000

Jan

Feb

March

April

May

June

July

Aug

Sept

Oct

Nov

Dec

Month

Most of the potable water used for irrigation is provided through residential and commercial connections. The quantity of potable water used for City-wide irrigation can be reduced through expansion and connection to the reclaimed water distribution system. Many of the City properties currently being irrigated with potable water, such as golf

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-13


courses and residential neighborhoods, can be irrigated using reclaimed water, creating a substantial savings for the City.

3.4

EXISTING SYSTEM CONFIGURATION This section discusses the system deficiencies, planned improvements to the

system, and the current rate structure for reclaimed water.

3.4.1

Perceived System Deficiencies

The following concerns were evaluated to be production capacity and distribution system deficiencies.

Production Facilities Currently, the only source of reclaimed water for the City is the Central RWPF. The SAWWTP, although not currently producing reclaimed water quality effluent, will in the near future contribute to the reclaimed water distribution system. However, until that time the South plant will remain the only facility within Lee County, treating greater than 100,000 gpd, which does not produce any reclaimed water. Within the City’s Consumptive Use Permit, it is required that the City utilize 100percent of the reclaimed water produced by 2005. Currently this requirement is not being met, however by 2005, the City should plan for implementation of a regional reclaimed water distribution system to achieve complete utilization. The existing reclaimed water production facility at the Central plant is designed for an annual average flow of 1.51 mgd. Therefore, the City must also consider the equipment upgrades necessary at the CRWPF to produce future reclaimed water at 100percent.

Distribution System It is important for the City to operate the reclaimed water production facility to maintain system storage at or near maximum levels to minimize fluctuations in system storage. Those reclaimed water systems supporting users who require reclaimed water at

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-14


various times of the day, typically require a large amount of system storage and/or extra treatment and production capacity to meet higher peak demands. Those reclaimed water systems supporting users with onsite storage rely on customer storage to dampen peak demands on the system, and, thus, typically require less system storage and production capacity. Currently the City delivers reclaimed water to seven customers, only one of which has onsite storage capabilities, the Lee County Resource and Recovery Facility. The LCRRF, also the largest current reclaimed water user, maintains onsite storage allowing them to meet daily peaks without relying on the reclaimed water distribution system to deliver water to them at their peak flow rate. The CAWWTP site, unfortunately, does not allow for construction of additional system storage due to space constraints. Future expansion of the reclaimed water system, production and distribution, will require construction of storage facilities to accommodate peak demands on the system. Additional reclaimed water storage will be necessary in the distribution system for expanded distribution system supply.

3.4.2

Planned Improvements

Capital improvements to the reclaimed water treatment and distribution system are budgeted annually through the City of Fort Myers Capital Improvement Program (CIP). The current CIP includes expansion of the City’s reclaimed water facilities, connection of additional reclaimed water users, and miscellaneous system-wide renovations of the sewer collection mains, each of which are discussed below.

Production Facilities Reclaimed water expansion at the CAWWTP is estimated to be complete before the end of 2006 and construction of a new reuse facility at the SAWWTP is estimated to be complete by 2010. During this reclaimed water system upgrade, many of the plant components will be expanded and/or constructed. New transmission and distribution piping and possibly new system storage will expand and improve operation of the Citywide reclaimed water system.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-15


Distribution System As the capacity of the reclaimed water production facilities increase, the City will need to begin to bring more and more reclaimed water users online.

Within the

upcoming CIP, the City plans to add reclaimed water service to the Heritage Palms area. Also on the CIP is a multi-phased water and sewer rehabilitation and replacement program addressing aging water and wastewater system components. Figure 3.17 shows the City’s repair and replacement scheduled Phases. Several areas have already been rehabilitated, and all work scheduled should be completed by the end of 2010. For those upcoming water and sewer rehabilitation Phases III C, and IV through VII, the City should consider installation of the proposed reclaimed water pipelines within those areas simultaneously to avoid multiple infrastructure repairs. For example, Phase IV of the rehabilitation program, to be completed in 2008, will take place in the area around the Fort Myers Golf Course, where installation of reclaimed water piping is proposed. Construction of the reclaimed water transmission pipes in conjunction with the water and sewer system modifications will allow for fewer disturbances to the City’s roadways and City’s residents.

3.4.3

Billing Rates

The use of reclaimed water is separately metered for each connection, as is the case for potable water, and appropriate rates are established by the City Council for the use of reclaimed water. Applicants requesting reclaimed water service shall submit the appropriate application form to the public works administrator.

Review of each

application is performed and a determination is made as to the adequacy of existing reclaimed water production facilities. The applicant is notified if a sufficient quantity of reclaimed water exists and connection to the system is possible. The current rate for reclaimed water is $0.5748 per 1000 gallons used. Expansion of the reclaimed water system and connection of additional users may result in an increase in the current billing rate. The billing rate should be reevaluated upon completion of the production facility expansions, as well as following expansion of the distribution system. The current billing rate, $0.5748 per 1000 gallons, for reclaimed water within the City of Fort Myers is slightly higher than that of other utilities in the area. The reclaimed City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-16


FIGURE 3.17


water billing rate for residential users in Collier County is approximately $0.42 per 1000 gallons and the average billing rate for all counties in Florida is approximately $0.34 per 1000 gallons. Although the City’s rate appears to be high compared to other utilities, it is significantly lower than the City’s potable water rate of $3.03 per 1000 gallons. Various sources of funding are available in the form of loans and grants from the FDEP, SFWMD, and the EPA. Funding available through the FDEP includes the State Revolving Fund Loan Program, providing low-interest loans for planning, design, and construction of wastewater facilities. The SFWMD provides grants to those utilities that develop cost-effective reclaimed water supplies. Finally, the EPA makes funds available for water supply projects through its State and Tribal Assistance Grant program. Receipt of any form of this funding would contribute to the initial project capital costs and allow for a reduced customer billing rate.

City of Fort Myers Reclaimed Water Master Plan Section 3 Fort Myers Reclaimed Water System

Malcolm Pirnie, Inc. 3-17


4.0 EVALUATION OF EXISTING SYSTEM The existing distribution system was modeled and evaluated for a one week simulation period using demands and weekly demand patterns specific to each user. Each of the existing pressurized pipes transmitting water to the City’s seven existing reclaimed customers was included in the model. This evaluation includes a comparison of the average and peak flow showing the following: • • • • •

4.1

A graphical representation of the hydraulic grade line from the plant to Buckingham Park. A graph of pressures at the LCRRF. A system pressure and pipeline head loss model output snapshot at peak demand time. A table showing minimum, maximum and average pressures at each user. An graphical comparison of effluent flow from the Central AWWTP, the treatment capacity of the RWPF and the amount of treated wastewater that is discharged to the Caloosahatchee river.

DISTRIBUTION SYSTEM HYDRAULIC MODEL

Modeling of the City’s reclaimed water distribution system was completed using H2OMAP software by MWH Soft, Inc. The H2OMAP software simulates hydraulic behavior of the reclaimed water system by simulating various elements based on time of day, tank water levels, system pressure, node demands, pipe size, roughness, and minor losses. The model was built by compiling the following data: • • • • • • • • •

Reclaimed water metering and billing information Elevation data GIS land parcel data Future planned development data Existing infrastructure CAD drawings As-built construction drawings Historical demand data Wastewater treatment plant pressure and flow SCADA data Pump manufacturer information

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-1


The system demands are simulated using 168 hourly demand factors multiplied by an average weekly demand value for each customer. Average customer demands were used to simulate an Existing Average Demand Scenario that was used for calibrating the model. Maximum customer demands were used to simulate an Existing Maximum Demand Scenario that was used to evaluate for system deficiencies. The pumps and tank levels are modified within the model based on treatment and storage capacity, valve settings, tank levels, and pressure settings. 4.2

SYSTEM PERFORMANCE CRITERIA

The performance criteria that were used to evaluate the Existing Maximum Demand Scenario for system deficiencies are summarized below in Table 4.1.

Table 4.1: Model Performance Criteria Description

Criteria

Maximum Supply to storage from the CWRPF

2.0 mgd

Maximum Pressure from Storage to Distribution

62 psi

Minimum Storage Tank Level

1 ft

Maximum Storage Tank Level

20 ft

Minimum acceptable pressure at LCRRF

45 psi

Maximum acceptable Headloss between CRWPF and LCRRF Maximum acceptable Pipeline Headloss per pipeline.

4.2.1

29.23 ft 3 ft/1000ft

CAWWTP and CRWPF Capacity Limitations

The existing Central AWWTP can treat up to 11 mgd AADF. The existing model includes effluent flow from the Central AWWTP that varies hourly as per the average hourly flow pattern at the plant, and averaged to 7.0 mgd of effluent flow. The CRWPF can treat up to 2 mgd of water for reclaimed storage and distribution. The reclaimed water production process is currently limited by the filter capacity. The model flow into the storage tank is limited to a maximum flow of 2 mgd. The tank will not fill if it is already at its maximum level. The remaining CAWWTP effluent is discharged to the river. City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-2


4.2.2

Distribution Pump Capacity

The reclaimed distribution system is pressurized by two 2 mgd pumps that are operated by variable frequency drives to maintain a pressure of 62 psi leaving the Central RWPF. Therefore the maximum flow from the CRWPF is limited to 4 mgd.

4.2.3

System Storage

One 1 mgd tank provides storage for reclaimed distribution. The tank is modeled as a cylindrical tank with a 90 ft diameter that is 20 ft tall.

4.2.4

Distribution System Pressure Requirements

Reclaimed distribution systems should be modeled to provide water to customers at a minimum pressure of 20 psi. The City’s interlocal agreement with the County requires that pressure at the LCRRF be maintained at 45 psi. Since the LCRRF is the largest and second farthest user in the reclaimed distribution system, the minimum pressure requirement in the distribution system will be 45 psi.

4.2.5

Distribution System Head Loss Requirements

The maximum acceptable headloss per 1000 ft should remain below 3 ft per 1000 ft, to keep from having significant pressure loss across the pipe. The model will evaluate each pipe within the existing distribution system for this criterion. Reclaimed water must flow through approximately 32,000 ft of piping to reach the LCRRF. The LCRRF is approximately 10 ft higher in elevation than the CRWPF. The maximum head loss that can occur between the CRWPF and LCRRF can be calculated by the subtracting the minimum pressure at the LCRRF from the pressure leaving the CRWPF, converting the pressure loss to head loss, and subtracting the head loss due to the elevation change. The maximum head loss that can occur between the CRWPF and LCRRF is:

((62 psi – 45 psi)*2.31 ft/psi ) – 10 ft = 29.23 ft

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-3


Dividing the maximum head loss by the distance between the two facilities allows for the maximum head loss per 1000 ft to be calculated. This head loss per 1000 ft equals:

29.23 ft / 32,000 ft = 0.91 ft / 1,000 ft

The weighted average of the head loss per 1,000 ft must not exceed this value to maintain a pressure of 45 psi at the LCRRF. Some pipelines may have higher headloss values along the pipeline route, however, as long as the weighted average remains less than 0.91 ft / 1000 ft, the distribution system pressure can be maintained.

4.3

DEMAND ALLOCATION

The existing model includes seven customers. The customer demands used for the two existing modeling scenarios are shown in Table 4.2. Table 4.2: Existing Reclaimed Water Distribution System Customer Model Scenario Demands Model Node Number

User Name

Customer Demands (mgd) Average Scenario

Maximum Scenario

Red Sox Minor League Facility

274

0.050

0.148

J. B. Schutz City Nursery

272

0.040

0.106

City of Fort Myers, WTP

276

0.010

0.028

Lee County Resource Recovery Facility

154

0.700

1.014

Buckingham Community Park Medians on Dr. Martin Luther King Jr. Blvd. Housing Authority

258

0.035

0.075

252

0.018

0.087

202

0.020

0.026

0.873

1.484

TOTAL =

The average scenario demands are within the range of the average and maximum demands in Table 3.4, and sum to the average recorded flow from Central RWPF between 9/1/03 and 11/24/03.

The Maximum Scenario demands are the maximum

historical monthly demands recorded in the billing data for each customer.

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

The

Malcolm Pirnie, Inc. 4-4


customers, as described in Section 3.3, use reclaimed water only during certain times of the week. The hourly demand factors for each user are shown in Figure 4.1. The hourly demand factors are multiplied by the average demands listed above to achieve the hourly demand from the distribution system at each reclaimed user. The combined demands for all users are shown in Figure 4.2. The “Hour of the Week� shown in the Figures begins with Monday morning at 12:00 AM.

Figure 4.1: Existing Reclaimed User Demand Factors 12 Nursery MLK Medians 10

Buckingham Park Red Sox LCRRF

Demand Factor

8

WTP Housing Authority

6

4

2

0 0

4.3.1

24

48

72 96 Hour of the Week

120

144

168

Existing Distribution System Model

The Existing Model pipes and nodes are shown in Figure 4.3.

The model

includes all pipes that currently transmit reclaimed water to customers, for a total of approximately 8.5 miles of existing piping. These pipes have been installed within the Dr. Martin Luther King and East Service Areas, as defined in Section 1.3. The pipe diameters, lengths, and Model Pipe numbers are listed for each service area in Table 4.3.

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-5


Figure 4.2: Existing Average and Maximum Scenario Model Demands

2,500 Exsting Average Demand Scenario Existing Maximum Demand Scenario

Flow (gpm)

2,000

1,500

1,000

500

0

24

48

72

96

120

144

168

Hour of the Week Table 4.3: Existing Reclaimed Water Model Pipes Street Martin Luther King Service Area Raleigh Street Michigan Avenue Veronica S. Shoemaker Blvd. Dr. Martin Luther King Jr. Blvd Michigan Link Avenue Tampa Street Miami Avenue Jacksonville Street

Diameter (in)

Approximate Length (ft)

Model Pipe Number(s)

24 20 20 8 20 20 12 12 12 8

1000 5600 2600 800 7500 3900 1000 1400 1600 2200

247 193, 223 227 225 197, 199, 201 195, 579 229 231 233 565

20 16 16 12 12

3900 5600 3600 3400 500

113, 771 105, 123, 577 107, 109, 111 203, 327 255

East Service Area State Road 82 Buckingham Road LCRRF

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-6


Existing Model

Reclaimed Water Distribution Model Pipe Diameters and Node Elevations

Prepared By: Malcolm Pirnie, Inc.

City of Fort Myers Reclaimed Water Master Plan

Figure 4.3


4.3.2

Model Calibration

The existing average scenario was used to complete the calibration of the model. Calibration of the distribution model was completed by modifying flow patterns or pipe roughness coefficients to match available distribution flow and pressure data to the model output. The City provided hourly reclaimed water data for flows distributed from the CRWPF recorded from 9/1/2003 – 11/23/2003. A comparison of the actual maximum, minimum, and average hourly flows leaving the Central RWPF and the sum of the hourly customer demands used in the existing average scenario are shown in Figure 4.4. The average demands and the overall recorded average flow from the CRWPF are both approximately 0.873 mgd (606 gpm.)

Figure 4.4: Comparison of Model and Actual Hourly Flows

1500

Flow (gpm)

1200

900

600

300 Average Hourly Flow Model Hourly Flow

Minimum Hourly Flow Maximum Hourly Flows

0 0

24

48

72

96

120

144

168

Hours of the Week

None of the existing users had historical pressure data at their delivery locations; however pressure measurements can be taken at the LCRRF. The pressures at the LCRRF were maintained between 55 and 57 psi for the duration of the Average Demand City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-7


Scenario. A staff member from the LCRRF verified that the resulting pressures from the existing Model were consistent with the pressures they receive at their facility. Since most of the piping was installed within the last 10 years, the roughness coefficient of the ductile iron and PVC piping has most likely not changed much for the duration of their installation. Therefore, the model results are assumed to be fairly accurate and not affected by to corrosion, calcification, or biological growth.

4.4

IDENTIFICATION OF EXISTING SYSTEM DEFICIENCIES

The existing system maximum demand scenario was used to evaluate the existing reclaimed water distribution system for any system deficiencies. A comparison of the model criteria to the model output is summarized in Table 4.4.

Table 4.4: Summary of Model Output vs. Performance Criteria Description Maximum Supply from the CRWPF to Storage Maximum Flow from storage to Distribution Minimum Storage Tank Level Maximum Storage Tank Level Minimum acceptable system pressure Minimum acceptable pressure at LCRRF Maximum Allowable Pipeline Headloss

Criteria 2.0 mgd 4.0 mgd 1 ft 20 ft 20 psi 45 psi 3 ft/1000ft

Model Output 2.0 mgd 3.0 mgd 16.33 ft 20 ft 49.48 psi 49.48 psi 2.35 ft/1000ft

The influent flow and the effluent flow into the 1 MG reclaimed storage tank for the maximum demand scenario are shown in Figure 4.5. The maximum flow into the storage tank is 2.0 mgd. The maximum flow leaving the Central RWPF is 3.0 mgd, (2100 gpm). The model output for the tank level of the 1 MG storage tank is shown in Figure 4.6. The tank level is maintained between the maximum level of 20 ft and a low value of 13.16 ft for the model duration.

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-8


Figure 4.5: Flow Into and Out of the CRWPF Storage 3.50 Flow into Storage

Flow out of Storage

3.00

Flow (mgd)

2.50

2.00

1.50

1.00

0.50

0.00 0

24

48

72 96 Simulation Hour

120

144

168

Figure 4.6: CRWPF Tank Levels

21

Tank Water Level (ft)

18 15 12 9 6 3 CRWTF Tank Level 0 0

24

48

72

96

120

144

168

Simulation Hour

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-9


The minimum, average, and maximum model output pressures at each of the reclaimed water users are summarized in Table 4.5. The pressure at the LCRRF was the lowest pressure location from the maximum demand scenario. The minimum pressure at the LCRRF was 48.3, and the simulated pressures for the scenario are shown in Figure 4.7.

Table 4.5: Pressures for Reclaimed Water Users for the Maximum Demand Scenario

User Name

Model Node Number

Distribution System Pressure (psi) Minimum Average Maximum Pressure Pressure Pressure

Red Sox Minor League Facility

274

52.8

56.2

57.1

J. B. Schutz City Nursery

272

53.2

56.3

57.1

City of Fort Myers, WTP

276

52.8

56.2

57.1

Lee County Resource Recovery Facility

154

48.3

52.8

54.0

Buckingham Community Park

258

48.5

53.1

54.4

Medians on Dr. Martin Luther King Jr. Blvd.

252

52.6

56.2

56.9

Housing Authority

202

54.8

57.7

58.4

The hydraulic grade line for the 32,000 ft of piping from the CRWPF to the LCRRF for the maximum head loss simulation hour is shown in Figure 4.8. The maximum head loss per thousand feet determined by the maximum demand scenario was 2.35 ft/1000 ft in the 12 inch pipeline along Buckingham Road. This is below the maximum model criteria of 3 ft/1000 ft. A snapshot of the model output for the peak hour demand of the maximum demand scenario is shown in Figure 4.9.

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-10


Existing Model

Maximum Demand Scenario Pressure and Headloss

Prepared By: Malcolm Pirnie, Inc.

City of Fort Myers Reclaimed Water Master Plan

Figure 4.7


Figure 4.8: Pressure at the LCRRF

60

50

Pressure (psi)

40

30

20 Maximum Demand Scenario 10

City-County Interlocal Agreement Requirement

0 0

24

48

72

96

120

144

168

Hour of the Week Figure 4.9 Hydraulic Grade Line from the CRWPF to the LCRRF

180 160 140

Head (ft)

120 100 80 60 40 20 0 0

4000

8000

12000

16000

20000

24000

28000

32000

Pipe Length from CRWPF (ft) Elevation Head

Pressure Head

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Total Head

Total Head Loss

Malcolm Pirnie, Inc. 4-11


4.5

CAWWTP AND CRWPF EFFLUENT FLOW ANALYSIS

One of the benefits of reclaimed water distribution in the City of Fort Myers area is the reduction of effluent flows from the CAWWTP to the Caloosahatchee River. A summary of the total effluent volumes from the CAWWTP and the CRWPF for the average demand and the maximum demand scenarios for the 1-week simulation is summarized in Table 4.6.

Table 4.6: Summary of Effluent Volumes from the CAWWTP and CRWPF for the Average and Maximum Demand Scenarios

Facility

Summary of 1-week Simulation Effluent Volumes Average Demand Scenario

Maximum Demand Scenario

From CAWWTP

49.00

49.00

To CRWPF

6.40

10.93

To River

42.60

38.07

City of Fort Myers Reclaimed Water Master Plan Section 4: Evaluation of Existing System

Malcolm Pirnie, Inc. 4-12


5.0 FUTURE RECLAIMED WATER SUPPLY AND DEMANDS This report section summarizes the future reclaimed water supply and usage potential and other effluent disposal options for the City’s wastewater treatment plants. Design for treatment upgrades is already underway to expand reclaimed water production at the Central and South AWWTP to 6.0 mgd and 9.0 mgd, respectively. A new East AWWTP is assumed to contribute an additional 8.0 mgd of reclaimed water treatment capacity by the end of 2009. The new user demands were calculated based on land area and usage type. The total demands are quantified for the future 5-year and 20-year scenarios.

Additional methods for reclaimed water storage and disposal are also

discussed in this section.

5.1

FUTURE RECLAIMED WATER SUPPLY The amount of reclaimed water that will be available in the future will be limited

to the amount of wastewater flowing to the wastewater treatment plants, and the amount of effluent that is treated to reclaimed water standards. The City and County areas served by the CAWWTP and SAWWTP will experience increases in flow due to population growth and expansion of their individual service areas. The City will also expand the reclaimed water production capacity at their existing plants and will most likely build a third plant that will utilize 100-percent reclaimed effluent disposal.

5.1.1

Treatment Capacity

The CAWWTP and SAWWTP wastewater treatment capacities will remain 11 mgd and 12 mgd, respectively, in the future as there is no room onsite for expansion of the wastewater treatment processes. The maximum reclaimed production capacity will be 6.0 mgd at the CAWWTP and 9.0 mgd at the SAWWTP. Previous sewer system master planning studies performed for the City indicated the necessity of a third wastewater treatment plant in the East Service Area. Malcolm Pirnie also confirmed this conclusion in the Wastewater Master Plan. We recommend that a new 8.0 mgd Maximum Three month Rolling Average Daily Flow capacity wastewater treatment plant

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-1


be operational by the end of 2009. We will assume that this new plant will have 100% reclaimed treatment capacity. The wastewater treatment and reclaimed water production capacity of the City’s treatment facilities in the future are summarized in Table 5.1.

Table 5.1: Future Wastewater Treatment and Reclaimed Water Production Capacities Location Central Facility South Facility East Facility Total

5.1.2

Wastewater Treatment MTMRADF Capacity (mgd) 2009 2024 11.0 11.0 12.0 12.0 8.0 23.0 31.0

Reclaimed Production Capacity (mgd) 2009 2024 6.0 6.0 9.0 9.0 8.0 15.0 23.0

Reclaimed Water Availability

The future availability of reclaimed water is limited to the projected wastewater flows. Table 5.2 summarizes the projected wastewater AADF available for treatment and reclaimed water supply.

Table 5.2 Projected Wastewater AADF and Maximum Possible Reclaimed Water Production Location Central Facility South Facility East Facility Total

5.2

Wastewater AADF (mgd) 2009 2024 8.35 8.06 9.51 9.25 5.79 17.86 23.00

Reclaimed Production (mgd) 2009 2024 6.0 6.0 8.7 9.0 5.79 14.7 20.79

IDENTIFICATION OF NEW POTENTIAL RECLAIMED WATER USERS The process used to identify potential future reclaimed water customers included

discussions with City government staff, review of previous studies to identify sites that could potentially use reclaimed water for existing and projected water demand, and also review of information received from the Lee County Planning and Parks Departments. Many of the proposed users are existing residential developments, parks, and golf

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-2


courses. Other proposed users are future residential developments, and parks and golf courses that have not yet been constructed.

5.2.1

Previous Studies Review

Two previous studies were reviewed to identify potential existing and future reclaimed water customers. The City of Fort Myers Effluent Resource Planning Report (Camp, Dresser, & McKee, 2001) and the Master Plan for the Regional Irrigation Distribution System (RIDS) For the Lower West Coast Region (SFWMD, 2002) both helped to identify potential reclaimed water customers within the planning area. The Effluent Resource Planning report assisted in estimating the number of future customers, as well as calculating the corresponding demands for each user.

The RIDS report

provided information on a potential means of effluent disposal to adjacent municipalities in the future.

5.2.2

Discussions with City Staff

A workshop was held with City staff to investigate potential new reclaimed water customers within the planning area. Information was gathered and reviewed with the help of a City planning area map and a City aerial, locating existing and planned golf courses and residential developments.

Most of the sites identified were existing

properties, requiring installation of a minimal amount of new transmission pipe, due to their proximity to existing reclaimed water distribution piping. However, some of the sites are existing residential developments that would require a significant amount of roadway construction and repair to install distribution piping. Directional drilling could also be used as an alternate construction method in those locations to minimize road damage, but this would increase construction costs. Many of the sites identified were future golf courses and residential developments not yet constructed. These sites may require a greater amount of new pipe to connect to the reclaimed water system, due to their distance from the existing system. However, the reclaimed water transmission piping for these sites could be installed at the time of site construction, avoiding any unnecessary roadway repairs.

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-3


5.2.3

Correspondence with City Departments and Developers

The City’s Planning and Zoning, and Parks and Recreation departments were contacted to identify planned developments or recreational facilities that could use reclaimed water. Many of the locations that were identified are existing sites constructed prior to the reclaimed water transmission pipelines. Also, the City Planning Department assisted in estimating the approximate timeframe and priority of each new user to begin operation. Several developers also shared their irrigation permits and attended Reclaimed Water Master Planning meetings to investigate the possibilities of receiving reclaimed water.

5.3

FUTURE USER DEMANDS Future reclaimed water use sites include a total of sixty-five new irrigation areas

and one new industrial use. The maximum demands of these future users will determine the sizing of the future distribution system transmission and distribution mains, and the treatment plant storage and pumping capacity.

5.3.1

Calculation of Future User Maximum Demands

Irrigable acreage was calculated for each irrigation user by estimating the amount of available onsite area capable of receiving reclaimed water. It was assumed that 30 percent of the total residential and commercial development area, 80 percent of the total park area, and 60 acres for every nine holes of the golf course would be irrigated. The maximum demand was calculated at a rate of one inch per week over the irrigated acreage.

The industrial usage at the LCRRF was determined from the interlocal

agreement between Lee County and the City. The land area, estimated demand, and future year they will be connected are listed in Table 5.3. The total maximum reclaimed demands for existing and future users are summarized in Table 5.4.

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-4


Table 5.3 Future Reclaimed Water Customers

User Name

8 11 17 19 21 26 38

Irrigated Acreage

Golf Course Irrigation Eastwood Golf Course 100 Eastwood Golf Course Expansion 60 Pelican Preserve Golf Course 120 Colonial Golf & Country Club Golf 120 Course 1 120 Arborwood Golf Course Heritage Palms Golf Course 240 Ft. Myers Country Club and Golf 120 Course

Subtotal Golf Course Irrigation 10 12 13 14 16 18 20 22 23 24 27 28 29 56 57 58 59 60 61 62 63 68 69 71 72

Maximum Future Reclaimed Demand (gpd) 2009

2024

354,000 233,000 466,000

354,000 233,000 466,000

466,000

466,000

466,000 931,000

466,000 931,000

466,000

466,000

3,382,000

3,382,000

New Community Residential Irrigation Heritage Lakes Estates 468.2 Forum Development 84.8 Orchard 49.1 Development South of 82, East of 111.3 Treeline Extension Sherwood 27.8 Pelican Preserve Colonial Golf & Country Club Arborwood Palomino Reflection Isles Paseo Heritage Palms Province Park Berkshire Zemel South Lee Boulevard Plaza Cypress Woods Colonial Plantation Proposed Residential Casa La Linda McGregor Oaks Townhomes Lennar Homes/Matera Watermen Development Winkler 39 Bernwood Olympia Point

Subtotal Community Residential Irrigation

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

1,817,000 330,000 191,000 432,000 109,000

54.9 125.3 378.3 47.0 120.0 199.2 71.2 140.9 20.3 11.2 12.9 24.1 5.6 23.4 0.9 2.9 7.4 9.8 10.9 41.7

213,000 487,000 1,468,000 183,000 466,000 773,000 277,000 547,000 79,000 44,000 50,000 94,000 22,000 91,000 4,000 12,000 29,000 39,000 43,000 162,000 0

7,962,000

Malcolm Pirnie, Inc. 5-5


User Name

Irrigated Acreage

Maximum Future Reclaimed Demand (gpd) 2009

39 47 55

West of McGregor East Downtown Dean Park

Individual Residential Irrigation 96.8 27.2 4.5

376,000 106,000 18,000

Subtotal Individual Residential Irrigation 31 32 33 34 35 36 37 40 41 42 43 44 45 48 49 50 51 52 53 54

500,000

Parks and Recreation Irrigation Dupree Park 0.6 Dunbar Park 2.8 5.7 Winkler Neighborhood2 Fleishman Little League Ball field 11.8 McGregor Boulevard 3.0 Seminole Park 1.6 Jefferson Park 1.5 Coronado Park 1.1 Lions Park 5.6 Red Sox Main Field 10.7 Yawkey Park 0.4 Five Points Park 1.0 Centennial Park 5.6 Clemente Park 3.0 Cook Lake Park 0.6 Riverside Park 2.0 Freemont Park 0.6 Shady Oaks Park 8.4 Terry Park 28.2 Police Athletic (Billy Bowlegs Park) 7.0

Subtotal Parks and Recreation Irrigation 15 30 25 46 64 65 66 67 70 73

Colonial Plaza Colonial Properties DRI Pratt Commercial Users Downtown International College Golden Corral Restaurant Walmart at Colonial Lowes Cypress Point Commercial Apex Publix

Subtotal Commercial Irrigation

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

2024

31.7 112.7 9.2 5.4 4.6 1.1 10.1 3.4 1.7 6.6

46,000 12,000

42,000 2,000 4,000 22,000

3,000 11,000 23,000 46,000 12,000 7,000 6,000 5,000 22,000 42,000 2,000 4,000 22,000 12,000 3,000 8,000 3,000 33,000 110,000 28,000

128,000

402,000

0 438,000 36,000 22,000 18,000 5,000 39,000 14,000 7,000 0

124,000 438,000 36,000 22,000 18,000 5,000 39,000 14,000 7,000 26,000

579,000

729,000

Malcolm Pirnie, Inc. 5-6


Industrial Use Lee County Resource Recovery Facility -Expansion

9

300,000

300,000

400,000

400,000

4,489,000

13,375,000

Subtotal Industrial Use Total New Identified Future Maximum Daily Demands (gpd) Notes:

1 2

There are not currently plans to include a Golf Course in the Arborwood Development Winkler Neighborhood includes Trailhead Park.

Table 5.4 Total Potential Reclaimed Water Demand Existing and Future Dates Existing Demands

5.3.2

Maximum Daily Reclaimed Water Demands (mgd) 1.77

2009 Demands

6.26

2024 Demands

15.15

Future Reclaimed Water Users by Service Areas

The approximate locations of the existing and future users identified in this report are shown in Figure 5.1. Table 5.5 lists all existing and new users by service area, as defined in Section 1.3, and summarizes the total demands in each service area. The map number in Table 5.5 corresponds to those numbers assigned to each user in Figure 5.1.

Table 5.5: Future Maximum Demands by Service Area Users 1 2 9 10 12 13 14

Buckingham Community Park Lee County Resource Recovery Facility Lee County Resource Recovery Facility Expansion Heritage Lakes Estates Forum Development Orchard Development South of 82, East of Treeline Extension

15

Colonial Plaza

16 57 72 73

Sherwood Lee Boulevard Plaza Olympia Point Apex Publix Subtotal East Service Area

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Maximum Demands (gpd) 2009 2024 75,000 75,000 1,300,000 1,300,000 400,000 400,000 0 1,817,000 0 330,000 0 191,000 0 432,000 0

124,000

0 0 0 0 1,775,000

109,000 44,000 162,000 26,000 5,010,000

Malcolm Pirnie, Inc. 5-7


Legend

Parcels

36 - Seminole Park

Reclaimed Users

38 - Ft. Myers Country Club

1 - Buckingham Community Park

2 - Lee County Resource Recovery Facility 3 - City Nursery

4 - Housing Authority 5 - Medians on MLK

50 51 53 49 52 47 45

39

39

41

42

4

38

33

37

63

60 34

0

5

59

8 - Eastwood Golf Course

3 6

13

7 8 64 6566 67 58

26 27

9

10

11

29 28

30

7 - City of Fort Myers, WTP

9 - Lee County Resource Recovery Facility Expansion

31

32

40

35

36 62

48

46

6 - Red Sox Minor League Facility

54 61 55

71 68 69 70 25

15 72

12

14

73 16 56

11 - Eastwood Golf Course Expansion

1

12 - Forum Development (Omni) 13 - Orchard

57

17

14 - Development S of 82, E of Treeline Extension 15 - Colonial Plaza 16 - Sherwood

17 - Pelican Preserve Golf Courses 18 - Pelican Preserve

19

19 - Colonial Golf & Country Club (Golf Course)

20 23

24

2

10 - Heritage Lakes

18

20 - Colonial Golf & Country Club (Residential) 21 - Arborwood Course

22 - Arborwood Residential

23 - Palomino Reflection Isles

21

24 - Paseo

25 - Pratt Commercial Users

26 - Heritage Palms Golf Course

22

27 - Heritage Palms 28 - Province Park 29 - Berkshire

30 - Colonial Properties DRI 31 - Dupree Park 32 - Dunbar Park

33 - Winkler Neighborhood

34 - Fleishman Little League Ball field 35 - McGregor Boulevard

City of Fort Myers Reclaimed Water Master Plan

Existing and Proposed Reclaimed Water Users

37 - Jefferson Park

39 - West of McGregor 40 - Coronado Park 41 - Lions Park

42 - Red Sox Main Field 43 - Yawkey Park

44 - Five Points Park 45 - Centennial Park 46 - Downtown

47 - East Downtown 48 - Clemente Park

49 - Cook Lake Park 50 - Riverside Park 51- Freemont Park

52 - Shady Oaks Park 53 - Terry Park

54 - Police Athletic(Billy Bowlegs Park) 55 - Dean Park

56 - Zemel South

57 - Lee Blvd Plaza

58 - Cypress Woods

59 - Colonial Plantation

60 - Proposed Residential 61 - Casa La Linda

62 - McGregor Oaks Townhomes 63 - Lennar Homes/Matera 64 - International College

65 - Golden Corral Restaurant 66 - Walmart at Colonial 67 - Lowes

68 - Watermen Development 69 - Winkler 39

70 - Cypress Point Commercial 71 - Bernwood

72 - Olympia Point 73 - Apex/Publix

Figure 5.1 October 2005


Table 5.5: Future Maximum Demands by Service Area (Continued) Users 17 18 19 20 21 22 23 24 56 67 68 25 26 27 58 59 60 65 66 69 70 71 8 28 29 30 33 64 3 4 5 6 7 11 31 32 41 42 48 55 61

Pelican Preserve Golf Course Pelican Preserve Colonial Golf & Country Club Golf Course Colonial Golf & Country Club Arborwood Golf Course Arborwood Palomino Reflection Isles Paseo Zemel South Lowes Watermen Development Subtotal Southeast Service Area Pratt Commercial Users Heritage Palms Golf Course Heritage Palms Cypress Woods Colonial Plantation Proposed Residential Golden Corral Restaurant Walmart at Colonial Winkler 39 Cypress Point Commercial Bernwood Subtotal South Service Area Eastwood Golf Course Province Park Berkshire Colonial Properties DRI Winkler Neighborhood International College Subtotal Carrel Service Area J. B. Schutz City Nursery Housing Authority Medians on Dr. Martin Luther King Jr. Blvd. Red Sox Minor League Facility City of Fort Myers, WTP Eastwood Golf Course Expansion Dupree Park Dunbar Park Lions Park Red Sox Main Field Clemente Park Dean Park Casa La Linda Subtotal Dr. Martin Luther King Jr. Service Area

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Maximum Demands (gpd) 2009 2024 466,000 466,000 0 213,000 466,000 466,000 0 487,000 466,000 466,000 0 1,468,000 0 183,000 0 466,000 0 79,000 14,000 14,000 0 29,000 1,412,000 4,337,000 36,000 36,000 931,000 931,000 0 773,000 0 50,000 0 94,000 0 22,000 5,000 5,000 39,000 39,000 0 39,000 7,000 7,000 0 43,000 1,018,000 2,039,000 354,000 354,000 0 277,000 0 547,000 438,000 438,000 0 23,000 18,000 18,000 810,000 1,657,000 106,000 106,000 26,000 26,000 87,000 87,000 148,000 148,000 28,000 28,000 233,000 233,000 0 3,000 0 11,000 0 22,000 42,000 42,000 0 12,000 0 18,000 0 91,000 670,000 827,000 Malcolm Pirnie, Inc. 5-8


Table 5.5: Future Maximum Demands by Service Area (Continued) Maximum Demands (gpd) 2009 2024 34 Fleishman Little League Ball field 46,000 46,000 35 McGregor Boulevard 12,000 12,000 36 Seminole Park 0 7,000 37 Jefferson Park 0 6,000 38 Ft. Myers Country Club and Golf Course 466,000 466,000 39 West of McGregor 0 376,000 40 Coronado Park 0 5,000 62 McGregor Oaks Townhomes 0 4,000 63 Lennar Homes/Matera 0 12,000 Subtotal McGregor Service Area 524,000 934,000 43 Yawkey Park 2,000 2,000 44 Five Points Park 4,000 4,000 45 Centennial Park 22,000 22,000 46 Downtown 22,000 22,000 47 East Downtown 0 106,000 Subtotal Downtown Service Area 50,000 156,000 49 Cook Lake Park 0 3,000 50 Riverside Park 0 8,000 51 Freemont Park 0 3,000 52 Shady Oaks Park 0 33,000 53 Terry Park 0 110,000 54 Police Athletic (Billy Bowlegs Park) 0 28,000 Subtotal Palm Beach Service Area 0 185,000 1 Notes: There are not currently plans to include a Golf Course in the Arborwood Development 2 Winkler Neighborhood includes Trailhead Park. Users

5.3.3

Demand Patterns

The demand patterns for the existing users will continue to be the same for the future Model scenarios. We have also made the assumption that all users with demands larger than 100,000 gpd will have their own onsite storage, and will have the same constant demand pattern that was used for the LCRRF. Future users with less than 100,000 gpd will have demand patterns equal to the existing user that their use will be most similar, as shown previously in Figure 4.1. Additional demand patterns were created for residential and commercial customers with a peak demand factor of 1.5 and a minimum demand factor of 0.5. A general pattern was also developed for parks, which is identical to the Water Treatment Plant pattern. The demand patterns for each new user are listed in Table 5.6

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-9


Table 5.6: New User Demands Patterns Future Users Apex Publix Arborwood (Residential) Arborwood Golf Course Berkshire Bernwood Buckingham Community Park Casa La Linda Centennial Park Clemente Park Colonial Golf & Country Club (Golf Course) Colonial Golf & Country Club (Residential) Colonial Plantation Colonial Plaza Colonial Properties DRI Cook Lake Park Coronado Park Cypress Point Commercial Cypress Woods Dean Park Development S of 82, E of Treeline Extension Downtown Dunbar Park Dupree Park East Downtown Eastwood Golf Course Eastwood Golf Course Expansion Five Points Park Fleishman Little League Ball field Forum Development Freemont Park Ft. Myers Country Club Golden Corral Restaurant Heritage Lakes Estates Heritage Palms Heritage Palms Golf Course International College Jefferson Park Lee Boulevard Plaza Lee County Resource Recovery Facility Expansion

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Demand Pattern Used Commercial LCRRF LCRRF LCRRF Residential Park Residential Park Park LCRRF LCRRF Residential Commercial Commercial Park Park Commercial Commercial Residential LCRRF Park Park Park Residential LCRRF LCRRF Park Red Sox LCRRF Park LCRRF Commercial LCRRF LCRRF LCRRF Commercial Park Residential LCRRF

Malcolm Pirnie, Inc. 5-10


Table 5.6: New User Demands Patterns (Continued) Future Users Lennar Homes/Matera Lions Park Lowes McGregor Boulevard McGregor Oaks Townhomes Olympia Point Orchard Palomino Reflection Isles Paseo Pelican Preserve Pelican Preserve Golf Courses Police Athletic(Billy Bowlegs Park) Pratt Commercial Users Proposed Residential Province Park Red Sox Main Field Riverside Park Seminole Park Shady Oaks Park Sherwood Terry Park Walmart at Colonial Watermen Development West of McGregor Winkler 39 Winkler Neighborhood Yawkey Park Zemel South

5.4

Demand Pattern Used Residential Park Commercial Park Residential LCRRF LCRRF LCRRF LCRRF LCRRF LCRRF Red Sox Commercial Residential LCRRF Residential Park Park Park LCRRF Red Sox Commercial Residential Residential Residential Park Park Residential

EXCESS WATER STORAGE AND DISPOSAL OPTIONS A significant quantity of wastewater effluent and reclaimed water will be

produced in excess of the future reclaimed water demand. This section will discuss the following options for storage and/or disposal of excess reclaimed water and wastewater effluent.

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-11


Discharge to the Caloosahatchee River

Rapid Infiltration Basins

Shallow Aquifer Recharge Injection Wells

Deep Injection Wells

Aquifer Storage and Recovery

Disposal through Regional Interconnections

5.4.1 Excess Treated Effluent and Reclaimed Water Produced The maximum future reclaimed water user demands identified will not equal or exceed the production capacity of the City’s reclaimed water production facilities, nor will the reclaimed water production quantity equal the amount of treated wastewater effluent. The future quantities of wastewater effluent and reclaimed water produced in excess of the future reclaimed water demand are summarized below in Table 5.7.

Table 5.7 Summary of Projected Excess Wastewater Effluent and Excess Reclaimed Water Supply

Existing and Future Dates

Wastewater Projected AADF (mgd)

Maximum Reclaimed Production Capacity (mgd)

Maximum Reclaimed Water Demands (mgd)

Excess Possible Non-Reclaimed Effluent (mgd)

Excess Possible Reclaimed Supply Range (mgd)

Existing

13.27

2.0

1.77

11.27 - 13.04

0.23 – 2.0

2009

17.86

15.0

6.26

2.86 - 9.12

8.74– 15.0

2024

23.1

23.0

15.15

0.10 - 15.24

7.86 – 23.0

5.4.2

Discharge to the Caloosahatchee River

Discharging to the Caloosahatchee River is the existing method used by the City to dispose of excess wastewater effluent and reclaimed water produced. The FDEP has several new laws and future objectives limiting the potential for future increases in surface water discharge of treated wastewater. The City will need to identify alternatives for disposal of wastewater effluent and reclaimed water as the Florida implementation of the Federal guidelines of the Total Maximum Daily Load (TMDL) program become more defined.

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-12


The TMDL, as defined in Section 303 (d) of the Clean Water Act, is the identified maximum amount of pollutant that a water body can receive and still meet its designated water quality standards. States are required to implement TMDLs and attain water quality standards as set by each facility’s discharge permit. The Caloosahatchee River is in Group 3 of the Basin rotation schedule. The FDEP has completed the first two phases (watershed evaluation, and the monitoring and assessment) and will complete the third phase of developing and implementing TMDL’s by the end of 2004. An action plan will be developed for the fourth phase in 2005 and implemented in 2006 as the fifth phase. Surface water dischargers will be evaluated for their specific pollutant contributions into these impaired waters. Surface water discharge, particularly any proposed expansions or increases in quantity, are heavily reviewed by the FDEP. The City should be able to continue use of this disposal option in a reduced capacity for the CAWWTP and SAWWTP. This option, however, will not be an option for the new East WWTP, because it is several miles from the Caloosahatchee River.

5.4.3

Rapid Infiltration Basins

Reclaimed water can be used to replenish groundwater through the use of rapid infiltration basins (RIBs). The infiltration basins are designed to accelerate percolation through the soil and unsaturated zone, removing total suspended solids in the process and allowing the filtered reclaimed water to reach the groundwater for future extraction. Although recharge of groundwater with reclaimed water has obvious advantages for water management, some disadvantages also exist. RIBs require a large amount of land surface area to allow for percolation. Also, there is the potential for contamination of the underground aquifer by the reclaimed water. Limitations on water quality, physical characteristics of basins, setbacks from potable water supply wells, and design and operation requirements are discussed in FAC 62-610. Limits are present on total organic carbon (TOC) and total organic halogen (TOX) in reclaimed water for groundwater recharge in order to reduce the risks related to non-conventional and toxic constituents. The concentration of nitrate in reclaimed water used in RIBs may not exceed 12 mg/L (as nitrogen) to protect groundwater from nitrate

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-13


contamination. This limit also ensures that the concentration in groundwater is less than 10 mg/L nitrate (as nitrogen), which is the state of Florida drinking water standard. Primarily because this option requires a significant amount of land area, it would not be applicable for the existing CAWWTP and SAWWTP. However, this may be a good disposal option for excess wastewater effluent and excess reclaimed water produced at the new East WWTP.

5.4.4

Shallow Aquifer Recharge Injection Wells

Reclaimed water can be disposed of by injection into a confined aquifer through shallow injection wells. The effluent must be treated to potable water quality standards, as required by FDEP, because this water is discharged directly into an aquifer without the benefit of any soil treatment. The distance between injection wells and groundwater extraction wells must be maximized to increase the detention time of the injected water underground and to allow mixing with natural groundwater. All injection projects shall comply with the technical and permitting requirements included in Chapter 62-528, F.A.C. The injection of reclaimed water into underground aquifers is a rarely used alternative. Direct injection of reclaimed water exhibits a high risk for contamination of the drinking water aquifer.

In addition, the cost associated with this alternative is

substantial due to the additional treatment needed to treat the water to potable water quality standards. Also, due to the high risk involved for contamination of the aquifer, the permitting process tends to be a lengthy and costly procedure. The implementation of injection wells, particularly any proposed expansions or new wells are heavily discouraged by the FDEP and face increased regulatory consideration.

5.4.5

Deep Injection Wells

Deep well injection is a common disposal method that is feasible from both a regulatory and technical standpoint as long as certain subsurface conditions exist. A highly permeable injection zone must be present so that large quantities of effluent can be disposed of at reasonable injection pressures. The injection zone must also contain saltwater with a total dissolved solids content in excess of 10,000 mg/L, which is City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-14


classified as the upper limit for an underground drinking water source. Finally, the injection zone must be underneath confining beds having low vertical permeability to avoid migration of the injected fluids upward into drinking water aquifers. These injection wells are utilized for wastewater disposal into deep saline aquifers during wet weather periods, when the reclaimed water demand for irrigation is low. Permitting a deep injection well requires an extensive investigation into the regional and local geology and hydrogeology, and the development of a well design and testing program.

5.4.6

Aquifer Storage and Recovery (ASR)

Groundwater aquifers can provide a means of storage and recovery for reclaimed water. ASR of reclaimed water involves injection into a subsurface formation for storage and recovery at a later date. ASR is especially useful, because large quantities can be stored during low irrigation demand periods, and recovered during seasonal high demand irrigation periods, eliminating the need for large surface storage facilities. The amount of reclaimed water that can be stored and withdrawn from each ASR well is limited by aquifer characteristics. Several wells may be necessary to achieve the desired storage capacity. The water recovered from the aquifer storage and recovery system must meet the CBOD5, TSS, and fecal coliform limits established for reuse as per Chapter 62-610, FAC. If the limits are not achieved, the FDEP will require that additional treatment or disinfection facilities be provided to ensure compliance with these limits. The City has experienced problems with meeting these standards at their Potable Water ASR well at the Winkler Pump Station. Extensive water quality monitoring programs must be implemented to assure the recharged reclaimed water does not affect the quality of adjacent groundwater. Chapter 62-610, FAC provides details on implementation and monitoring programs for ASR sites in Florida. The potential also exists for incomplete recovery of the injected water. Although very few reclaimed ASR facilities have been permitted in Florida, the study of ASR for reclaimed storage in Florida is increasing.

Hillsborough County

implemented the state’s first reclaimed water ASR system at their Northwest facility in City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-15


July 2001. This system is not currently operational due to problems with THM’s and arsenic. Several other reclaimed water ASR projects are being developed and are completing the DEP’s permitting process. These include projects in Sarasota County, Manatee County, St. Petersburg, Collier County, and the Englewood Water District. In 2002, the Englewood Water District became the second utility to initiate cycle testing of a reclaimed water ASR system. Limited ASR storage could be implemented at the CAWWTP and SAWWTP, however implementing reclaimed water ASR wells in populated areas has been especially difficult. This could also be used at an offsite location that has less perceived potential for contamination of drinking water wells. Additional discussion of other possible ASR locations is discussed in Section 5.4.6.

5.4.6

Discharge through Regional Interconnections

The City could dispose of excess reclaimed water through interconnections with Lehigh Acres, Gateway, and the City of Cape Coral. The SFWMD has developed a plan identified as the Regional Interconnection and Distribution System (RIDS) for the Lower West Coast Region (Lee and Collier Counties) with the objective to meet the projected irrigation demand associated with future growth.

The City is required by their

Consumptive Use Permit to participate in the SFWMD RIDS program. The SFWMD recommends use of the RIDS, stating that it would: • • • • •

Optimize existing reclaimed water supplies Maximize seasonally available surface waters Diversify supply sources, potentially reduce water shortage declarations Offset potable water usage for irrigation purposes reduce wastewater disposal volumes Offset future potential groundwater withdrawals

This SFWMD study assumed that all future wastewater flows would be available for use as reclaimed water. The goal of the RIDS is to have 100 percent utilization of the effluent water in order to offset the irrigation demand during the dry season. The RIDS plans to utilize reclaimed water interconnects, allowing water to be shared between utilities. Also, ASR systems, recharged with reclaimed water during the wet season, could provide a source of irrigation water supply during the dry season.

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-16


A potential reclaimed water ASR site was identified within the City that would serve Fort Myers, Gateway, and Lehigh Acres. The site consists of 12 wells and a pumping station and would allow for 9 mgd of reclaimed water to be stored for use during the dry season. Figure 5.2 shows the proposed reclaimed water ASR site. The RIDS also suggests possible interconnect locations that would allow water to be shared between the Central and South plants, and the towns of Fort Myers South, Lehigh Acres, and Gateway. A second interconnect was proposed to serve Fort Myers South, Fiesta Village, and the Gulf Environmental Services system.

These

interconnection locations are also shown on Figure 5.2. If the City chooses, excess reclaimed water not used within the City’s service area can be discharged into the regional system through these interconnects. The City can implement recommendations made in the RIDS report to assist with storage and disposal of excess reclaimed water. The following benefits were published in the RIDS report: • • • • •

Meet increasing demands Allow reclaimed water to be shared between utilities for beneficial reuse Reduce reliance on surface water discharge Allow expansion of reclaimed water systems and infrastructure Utilize and/or store close to 100 percent of the reclaimed water in the region on an annual basis

City of Fort Myers Reclaimed Water Master Plan Section 5: Future Reclaimed Water Supply and Demand

Malcolm Pirnie, Inc. 5-17


FIGURE 5.2


6.0 MODEL EVALUATION OF FUTURE DISTRIBUTION SYSTEM The future distribution system was modeled for 5-year and 20-year future scenarios. The model analysis was similar to the model analysis of existing system presented in Section 4. The model was completed for a one week duration using the future supply and maximum user demands listed in Section 5. The future model was constructed to supply all of the identified future reclaimed water users at their peak demands. Piping was also included to connect the reclaimed water production facilities at the CAWWTP and the SAWWTP, for the 5-year model, and the East WWTP, for the 20-year model. All existing pressurized pipes that are transmitting water to the City’s seven existing reclaimed customers were included in the model. These evaluations include a comparison of peak flow showing the following for the future 2009 and 2024 scenarios: • • • • • • •

6.1

Snapshots of system pressure and pipeline head loss at peak demand time. Tables listing existing piping that is not currently being used for reclaimed distribution, but will be utilized in the future. Tables listing new piping that will be needed. Tables showing minimum pressures at each user. Graphs of pressures at the LCRRF. Total flow amounts discharged through interconnections with other municipalities. Comparisons of wastewater effluent flow, treatment capacity, and the amount of treated wastewater that is discharged to the Caloosahatchee River.

MODEL PERFORMANCE CRITERIA The City has already determined that the future production capacities will be 6.0

mgd at the CRWPF and 9.0 mgd at the SRWPF. The future models will include 9 MG of reclaimed storage at the SRWPF, while the CRWPF will be limited to 1 MG due to space constraints. An additional 8.0 mgd reclaimed production facility was added for the 2024 Model at a location just south of the LCRRF. Table 6.1 summarizes the model criteria used to build and evaluate the future 2009 and 2024 Models.

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Malcolm Pirnie, Inc. 6-1


Table 6.1: Model Performance Criteria Central Reclaimed Water Production Facility Maximum Reclaimed Water Production Capacity Maximum Pressure Storage to Distribution Average Wastewater Flow 2009 Average Wastewater Flow 2024 Reclaimed Water Distribution Storage Volume Minimum Storage Tank Level Maximum Storage Tank Level South Reclaimed Water Production Facility Maximum Reclaimed Water Production Capacity Maximum Pressure Storage to Distribution Average Wastewater Flow 2009 Average Wastewater Flow 2024 Reclaimed Water Distribution Storage Volume Minimum Storage Tank Level Maximum Storage Tank Level East Reclaimed Water Production Facility Maximum Reclaimed Water Production Capacity Maximum Pressure Storage to Distribution Reclaimed Water Distribution Storage Volume Average Wastewater Flow 2024 Minimum Storage Tank Level Maximum Storage Tank Level Interconnections Gateway Pressure Sustaining Valve Setting Cape Coral Pressure Sustaining Valve Setting Distribution System Minimum acceptable pressure at LCRRF Minimum acceptable pressure at all other Reclaimed Users Maximum acceptable Pipeline Head loss

6.2

6.0 mgd 62 psi 7.84 mgd 8.06 mgd 1.0 MG 5 ft 20 ft 9.0 mgd 65 psi 8.94 mgd 9.25 mgd 9.0 MG 5 ft 30 ft 8.0 mgd 48 psi 8.0 MG 5.79 mgd 5 ft 30 ft 40 psi 40 psi 45 psi 30 psi 3 ft/1000ft

2009 MODEL The 5-year future scenario model includes the identified users and the maximum

demands of 6.26 mgd projected for 2009. The total wastewater flows are projected to be 15.15 mgd. The future reclaimed water production capacity and user demand projections were discussed in Section 5 of this report and in the Wastewater Master Plan. Reclaimed water was also allowed to be discharged to the Gateway area through an interconnection located to the northeast of the proposed Arborwood Development. City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Malcolm Pirnie, Inc. 6-2


6.2.1

Piping Required for the 2009 Model

Many existing and new pipelines will be needed to connect the SAWWTP and CAWWTP and to supply reclaimed water to each of the existing and future customers. The City has several existing reclaimed pipelines that are not currently being used. Figure 6.1 shows the 2009 Model piping, and differentiates between the piping has already been installed and the new piping that will be needed by 2009. Table 6.2 lists the pipes that have already been installed that were not use in the Existing Model, (because they are not currently in used for reclaimed water distribution) but will be used for the 2009 Model. Table 6.2: Existing Piping Used in the 2009 Model Street

Diameter (in)

Length (ft)

Model Pipe Number(s)

1300 3800 2600 2600 1100

12 8 16 8 10

217 57, 59, 61, 167 215 53, 55 47

Carrell Service Area Eastwood Golf Course Executive Circle Ortiz Avenue Schoolhouse Road Veronica Shoemaker Boulevard Downtown Service Area 1st Street McGregor Boulevard McGregor Service Area Ft. Myers Country Club Hill Avenue

4300 2500

8 8

17, 493 75, 257

700 1400

16 8

McGregor Boulevard

8700

8

165 163 15, 145, 147, 207, 343, 611, 681

Martin Luther King Service Area Dr. Martin Luther King Boulevard Orange Street East Service Area

6000 600

8 20

149, 401 45

1100

16

119

5100

20

211, 213, 603, 815

Colonial Boulevard Cypress Loop Road Forum Boulevard University Avenue South Service Area Bernwood Place Ben C. Pratt Parkway

4900

12

127

1100

20

131

6400

16

125, 133

2000

10

129

1000 1500

4 4

10200

16

23, 25 39, 305 41, 219, 221, 797, 799, 817

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Malcolm Pirnie, Inc. 6-3


2009 Model

Future Piping Phases

Prepared By: Malcolm Pirnie, Inc.

City of Fort Myers Reclaimed Water Master Plan

Figure 6.1


Table 6.3 lists the new piping that is included in the 2009 Model. These pipe locations are listed according to the Service Area they are located in, and by the streets that they are routed parallel to. The diameters, lengths, and model numbers for the pipes are also listed along with a brief explanation justifying the need for the piping. The diameters of the piping included in the 2009 Model are shown in Figure 6.2. Table 6.3: New Piping Needed for the 2009 Model

Street

Carrell Road

Veronica Shoemaker Boulevard

Length (ft)

18,500

Head loss Diameter Range Model Pipe (in) (ft/1000ft) Number(s) Carrell Service Area 301, 333, 24 0.32- 0.68 335, 375

5,300

16

0.57 - 0.64

779

1,100

10

0.79 - 0.79

303

Purpose of the New Piping Southeast connection of CRWPF and SRWPF Southeast connection of CRWPF and SRWPF Connection to the Winkler Shoemaker users

Downtown Service Area Central Avenue

500

10

0.07 - 0.58

269

Edison Avenue First Street

700 1,700

6 8

0 – 2.37 0 - 0.03

267 441

Jackson Street

1,100

4

0 - 0.01

505

Lafayette Street

2,100

8

0.07 - 0.58

271

McGregor Boulevard

800

4

0 - 0.03

355, 495

US 41

700

4

Carrell Road

1,600

24

0.32 - 0.42

DeLeon Street

8,300

24

0.42 - 0.66

Edison Avenue

1,400

6

0 – 0.61

381 383, 387, 641, 747 263, 265, 503

Euclid Avenue

500

6

0 – 0.61

261

1,300

24

0.42 - 0.6

337

1,900

12

0 - 0.69

289,379

1,200

24

0.32 - 0.42

745

800

6

0 - 0.61

259

FTM Golf to DeLeon

Ft. Myers Country Club Victoria Avenue

0 - 0.8 351 McGregor Service Area

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Northwest connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF Connection to Downtown Connection to Yawkey Park North connection of CRWPF and SRWPF Connection to the Five Points user Connection to Centennial park Southeast connection of CRWPF and SRWPF Southeast connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF North connection of CRWPF and SRWPF Southeast connection of CRWPF and SRWPF Connection to McGregor mains Southeast connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF

Malcolm Pirnie, Inc. 6-4


2009 Model

Future Piping Diameters

Prepared By: Malcolm Pirnie, Inc.

City of Fort Myers Reclaimed Water Master Plan

Figure 6.2


Table 6.3: New Piping Needed for the 2009 Model (Continued)

Street

Length (ft)

Head loss Diameter Range Model Pipe (in) (ft/1000ft) Number(s) Martin Luther King Service Area

2,200

8

0.07 - 0.58

273

800

6

0.34 - 0.94

275

Edison Avenue

2,600

16

0.3 - 0.49

567

High Street

1,400

6

0.34 - 0.94

281

Indian Street

2,000

6

0.34 - 0.94

279

Michigan Street

600

10

0 - 0.01

283

Palm Avenue

700

6

0.34 - 0.94

5,300

16

0.3 - 0.88

277 403, 561, 563

7,800

16

0.01 - 0.64

227,689,691

Cranford Avenue

Ford Street Veronica Shoemaker Boulevard

Colonial Boulevard

2,600

20

900

16

East Service Area 0.74 – 0.83 1.6 – 1.78

529 685

Purpose of the New Piping Northwest connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF Northwest connection of CRWPF and SRWPF Southeast connection of CRWPF and SRWPF Southeast connection of CRWPF and SRWPF Needed to provide service to the Southeast Service Area

Southeast Service Area Colonial Country Club Gateway Interconnection

Stubout

12

2.18-2.74

Pelican Preserve

5,700 Stubout

535, 593 717, 719, 721

12

0.36 - 0.88

533, 591

South Treeline Avenue

2,700 700

16 10

0.98-1.15 0.88 - 0.88

541, 715 589

3,500

20

0.74 - 0.83

531

5,700

16

Treeline Avenue

Ben C. Pratt Parkway

Stubout

16

0.09 - 0.88

0.98 - 1.15 South Service Area

537

Service to Colonial Country Club Needed for Gateway Interconnection Needed for service to Pelican Preserve Needed for Arborwood, and Gateway Interconnection Service to Arborwood Service SE service area to Colonial Country Club and Pelican Preserve Service to Southeast Service Area to Canal Service to Heritage Palms

16

0.32 - 0.32

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

313

Malcolm Pirnie, Inc. 6-5


6.2.2

2009 Model Pressures

The 2009 Model was constructed so that all of the user demands would be met, and all the pressures would meet the design criteria. Table 6.4 lists the minimum pressure output at each of the users for the 2009 Model. All of the pressures remained above 30 psi at all of the user locations. The minimum pressure at the LCRRF was 46.4 psi. The user with the lowest pressure was the Parker Daniels Development with a minimum pressure of 43.1 psi. Table 6.4: Minimum Distribution Pressures for the 2009 Model

Users Buckingham Community Park Arborwood Golf Course Centennial Park City Nursery City of Fort Myers, WTP Colonial Golf & Country Club (Golf Course) Colonial Properties DRI Cypress Point Commercial Downtown Eastwood Golf Course Eastwood Golf Course Expansion Five Points Park Fleishman Little League Ball field Ft. Myers Country Club Golden Corral Restaurant Heritage Palms Golf Course Housing Authority International College Lee County Resource Recovery Facility Lee County Resource Recovery Facility Expansion Lowes McGregor Boulevard Medians on MLK Pelican Preserve Golf Courses Pratt Commercial Users Red Sox Main Field Red Sox Minor League Facility Walmart at Colonial Yawkey Park City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

2009 Model Pressure (psi) 46.1 44.7 62.7 55.2 54.7 48.0 51.0 54.1 62.9 52.7 54.7 60.9 64.5 62.0 53.3 54.3 58.9 54.0 45.4 45.0 52.9 63.2 53.7 48.0 53.6 58.9 54.8 53.1 58.9

Model Node # 258 516 346 272 276 520 224 56 412 260 588 384 386 592 692 244 202 690 154 586 694 590 252 518 54 454 274 676 344 Malcolm Pirnie, Inc. 6-6


6.2.3

Potential 2009 Interconnection Location

For the purposes of the Model, an interconnection was included at the north end of the Gateway Development for the 2009 Model. A 12-inch diameter transmission main was routed to the interconnection location (City limit/Gateway border) from Treeline Avenue at the north end of the Arborwood Development. This interconnection location was discussed previously and identified by the SFWMD as a RIDS recommended interconnection site. The interconnection was modeled to discharge into a storage tank, while maintaining an upstream pressure of 40 psi. A total of 9.5 MG of reclaimed water for the 7-day model duration was able to discharge to Gateway. 6.2.5

Excess Wastewater Effluent and Reclaimed Water Produced

A summary of the total effluent volumes from the Central and South facilities for the 2009 Model scenarios for the 1-week simulation is summarized in Table 6.5. Table 6.5: Total 1-week Flow Volumes for the 2009 Model 2009 Model Flows Total Wastewater Flow Excess Effluent Reclaimed Water Produced Change in Storage Excess Reclaimed Water Discharged Reclaimed Water Distributed City Users Gateway Interconnection

6.3

1-week Simulation Volumes (MG) South Plant Central Plant 62.6 54.9 5.2 13.3 57.4 41.6 1.2 0.2 32.9 11.4 23.3 30.0 43.8 9.5

2024 MODEL The 20-year future modeling scenario includes the previously identified users and

the maximum demand of 15.15 mgd projected for 2024. The total wastewater flows are projected to be 23.1 mgd as discussed in previously in Section 5.

The Gateway

interconnection and an interconnection with the City of Cape Coral were included in the 2024 Model.

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Malcolm Pirnie, Inc. 6-7


6.3.1

Piping Required for the 2024 Model

Many existing and new pipelines will be needed to connect the SAWWTP and CAWWTP and to supply reclaimed water to each of the existing and future customers. Due to the City’s current priority to target large, bulk users of reclaimed water, some of the existing pipes are not currently being used to provide flow to customers. Figure 6.3 shows the 2024 Model piping and differentiates between the piping that is existing and the new piping that will be needed. Table 6.6 lists the pipes that have already been installed that were not used in the Existing Model or 2009 Model, but will be used for the 2024 Model. Table 6.7 lists the new piping that is included in the 2024 Model. These locations of the pipes are listed according to the Service Area they are located in, and by the streets that they are routed parallel to. The diameters, lengths, and model pipe numbers for the pipes are also listed, along with a brief explanation justifying the need for the piping. The diameters of the piping included in the 2024 Model are shown in Figure 6.4. Table 6.6: Existing Piping Used in the 2024 Model Street

Schoolhouse Road Veronica Shoemaker Boulevard Cranford Avenue Providence Street Rhode Island Avenue Burtwood Drive Ft. Myers Country Club Harold Avenue McGregor Boulevard Osceola Drive Vesper Drive Via Torcida West Riverside Drive Cranford Avenue

Diameter Length (in) (ft) Carrell Service Area 1500 10 2500 8 Downtown Service Area 500 8 800 6 800 6

Model Pipe Number(s)

49 169, 173 467 465 469

McGregor Service Area 400 8 161 700 16 683 800 6 157 6100 8 135, 137, 141, 209, 339, 341 600 12 139 1700 8 345 500 6 159 800 16 595 3300 6 151, 153, 155 Martin Luther King Service Area 400 8 473

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Malcolm Pirnie, Inc. 6-8


2024 Model

Future Piping Phases

Prepared By: Malcolm Pirnie, Inc.

City of Fort Myers Reclaimed Water Master Plan

Figure 6.3


2024 Model

Future Piping Diameters

Prepared By: Malcolm Pirnie, Inc.

City of Fort Myers Reclaimed Water Master Plan

Figure 6.4


Table 6.7: New Piping Needed for the 2024 Model Street

Broadway Solomon Schoolhouse Road Colonial Boulevard from Veronica Veronica Shoemaker Boulevard

Head loss Range (ft/1000ft) Carrell Service Area

Model Pipe Number(s)

Length (ft)

Diameter (in)

3000

4

0 - 0.87

377

700

10

0.38 – 0.57

51

2200

4

0.02 – 0.57

803

900

6

0.04 – 1.16

801

Purpose of the New Piping Serves the Winkler Neighborhood Park Connects Existing Piping across Winkler Connects to Proposed Residential Connects to Colonial Plantation

Downtown Service Area 1st Street

3100

8

0 - 0.48

449, 515

Palm Beach Boulevard

1300

8

0 – 1.03

477, 479

Arthur Avenue Barkley and Royal Palm Square

700

McGregor Service Area 4 0 - 0.1

373

5100

20

0.02-3.23

329, 807

Coronado Road

1900

4

0 - 0.05

361

Cortez Boulevard

2200

4

0 - 0.05

291, 293, 363

Jefferson Avenue

400

8

0.66 - 1.65

391

La Palma Lane

800

12

0.27 - 0.68

365

McGregor Boulevard

900

16

0.02 – 3.21

299

Matera Connection

1200

4

0.01 – 0.19

809

Princeton Avenue

900

10

0.66 – 1.7

393

Shadow Lane

1800

6

0.04 - 1.16

295

Winkler Avenue

600

10

0.66 - 1.7

385

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Connects Downtown and Palm Beach Service Areas Serves the Palm Beach Service Area Serves Seminole Park Connects to the Cape Coral Interconnect Connects to Coronado Park Connects to Coronado Park Connects to Jefferson Park and Ft. Myers Golf Course Connects to Jefferson Park and Fort Myers Golf Course Connects to the Cape Coral Interconnect Connects to the Matera Development Connects to Jefferson Park and Fort Myers Golf Course Connection for residential users west of McGregor Connects to Jefferson Park and Ft. Myers Golf Course

Malcolm Pirnie, Inc. 6-9


Table 6.7: New Piping Needed for the 2024 Model (Continued) Street

Dupree Street

Head loss Model Pipe Range Number(s) (ft/1000ft) Martin Luther King Service Area 900 4 0 - 0.02 571 1800 4 0 - 0.22 559

Length (ft)

Diamet er (in)

Edison Avenue 4100

10

0.45 – 1.17

569, 687

Marsh Avenue

3100

4

0 - 0.55

581

Michigan Street

2800

8

0.18 - 2.49

475, 489

Veronica Shoemaker Boulevard

2000

10

0 - 1.84

405

Purpose of the New Piping Connects to Dupree Park Connects to Dunbar Park Connects Dupree Park, Water Treatment Plant and the Red Sox Minor League Field Connects Dean Park Transmission Main for Downtown and Palm Beach Service Areas Transmission main for the Palm Beach Service Area

East Service Area Colonial Boulevard

5400

20

0.65 - 1.22

551

Lee Boulevard

2100

20

0.65 - 1.22

553, 693

Lee Boulevard to Buckingham Road

2300

20

0.25 - 0.79

555

North Treeline Avenue

2400

8

2.28 - 2.28

575

Transmission piping for the new East WWTP Transmission piping for the new East WWTP Transmission piping for the new East WWTP Serves developments along North Treeline Avenue

Southeast Service Area Arborwood to Reflection Isles

5,100

10

1.63 – 1.63

549

Reflection Isles

3,000

10

1.63 – 1.63

547

Reflection Isles to Paseo

3,800

10 0.88 - 0.88 Palm Beach Service Area

545

4700

8

0.01 - 0.85

587, 601

1000

6

0.04 - 1.1

805

1300

4

0 - 0.73

417, 597

700

8

0.01 - 2.34

407

2400

4

0.01 - 1.46

409, 423

1100

4

0.02 - 0.59

3000

6

0.02 – 1.03

Royalston Avenue

2500

4

0 – 1.31

421 419, 481, 609 413, 415

Terry Avenue

600

4

0 – 1.31

411

Veronica Shoemaker Boulevard

900 1400

10 8

0 - 1.84 0.01 – 0.85

773 585

Bell Street East Riverside Drive Marion Avenue

Palm Beach Boulevard

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

Needed for service to Palomino and Parker Needed for service to Palomino and Parker Needed for service to Parker Daniels Connects Police Athletic League Connects Police Athletic League to Casa La Linda Connects Riverside Park Connects Terry Park and Shady Oaks Park Connects Terry Park and Shady Oaks Park Serves the Palm Beach Service Area Connects Riverside Park Connects Terry Park and Shady Oaks Park Connects Police Athletic League Malcolm Pirnie, Inc. 6-10


6.3.2

2024 Model Pressures

The 2024 Model was constructed so that all of the user flow and pressure demands would be met. Table 6.8 lists the minimum pressure output at each of the users for the 2024 Model. All of the pressures remained above 30 psi at all of the users. The minimum pressure at the LCRRF is 45.0 psi. The user with the lowest pressure was the Paseo (Parker Daniels) Development with a minimum pressure of 33.3 psi. Table 6.8 Minimum Distribution Pressures for the 2024 Model Users Apex Publix Arborwood (Residential) Arborwood Golf Course Berkshire Bernwood Buckingham Community Park Casa La Linda Centennial Park City Nursery City of Fort Myers, WTP Clemente Park Colonial Golf & Country Club (Golf Course) Colonial Golf & Country Club (Residential) Colonial Plantation Colonial Plaza Colonial Properties DRI Cook Lake Park Coronado Park Cypress Point Commercial Cypress Woods Dean Park Development S of 82, E of Treeline Extension Downtown Dunbar Park Dupree Park East Downtown Eastwood Golf Course Eastwood Golf Course Expansion Five Points Park Fleishman Little League Ball field Forum Development Freemont Park Ft. Myers Country Club

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

2024 Model Pressure (psi) 46.3 42.5 39.7 50.4 45.8 46.2 54.0 59.6 51.6 51.8 55.9 42.4 40.0 47.3 46.3 49.5 58.6 57.1 47.6 47.1 56.6 44.0 59.8 55.1 52.4 57.2 47.1 49.1 57.8 63.9 46.3 57.9 59.4

Model Node #(s) 698 478 516 352 34 258 684 346 272 276 340 520 484 680 256 224 366 342 56 678 510 504 412 338 500 442 260 588 384 386 178 362 592

Malcolm Pirnie, Inc. 6-11


Table 6.8 Minimum Distribution Pressures for the 2024 Model (Continued) Users Golden Corral Restaurant Heritage Lakes Estates Heritage Palms Heritage Palms Golf Course Housing Authority International College Jefferson Park Lee Boulevard Plaza Lee County Resource Recovery Facility Lee County Resource Recovery Facility Expansion Lennar Homes/Matera Lions Park Lowes McGregor Boulevard McGregor Oaks Townhomes Medians on MLK Olympia Point Orchard Palomino Reflection Isles Paseo Pelican Preserve Pelican Preserve Golf Courses Police Athletic(Billy Bowlegs Park) Pratt Commercial Users Proposed Residential Province Park Red Sox Main Field Red Sox Minor League Facility Riverside Park Seminole Park Shady Oaks Park Sherwood Terry Park Walmart at Colonial Watermen Development West of McGregor Winkler 39 Winkler Neighborhood Yawkey Park Zemel South

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

2024 Model Pressure (psi) 47.8 46.7 48.0 47.5 53.9 48.7 59.9 46.2 45.4 45.0 57.3 55.6 47.5 60.3 55.5 49.3 46.4 46.5 34.7 33.3 42.7 42.6 54.4 46.7 47.1 49.0 55.7 51.5 59.0 56.2 57.2 46.5 56.9 47.4 46.6 53.3 47.7 55.5 55.7 46.2

Model Node #(s) 692 158 38 244 202 690 400 674 154 586 688 308 694 590 188 252 700 506 490 492 480 518 512 54 682 350 454 274 364 378 356 474 354 676 32 194, 198, 206, 212 696 348 344 472

Malcolm Pirnie, Inc. 6-12


6.3.3

Potential 2024 Interconnection Locations

The 2024 Model included an interconnection with the City of Cape Coral. For the purposes of the Model, the Cape Coral interconnection location is just south of the Midpoint Bridge, along McGregor Boulevard. A 20-inch diameter main was routed from the SRWPF to the interconnection location at Colonial Boulevard and McGregor Boulevard. The interconnection was modeled so that reclaimed water could discharge to a storage tank, while maintaining an upstream pressure of 40 psi. A total of 3.3 MG of reclaimed water for the 7-day model duration was able to discharge through the Gateway Interconnection, and 11.0 MG to the Cape Coral Interconnection and 7.0 MG to the Lehigh Interconnection.

6.3.4

Excess Wastewater Effluent and Reclaimed Water Produced

A summary of the total effluent volumes from the Central, South, and East facilities for the 2024 Model scenarios for the 1-week simulation is summarized in Table 6.9.

Table 6.9: Total 1-week Flow Volumes for the 2024 Model 2024 Model Flows Total Wastewater Flow Excess Effluent Discharged Reclaimed Water Produced Change in Storage Excess Reclaimed Water Discharged Reclaimed Water Distributed City Users Gateway Interconnection Cape Coral Interconnection Lehigh Interconnection

1-week Simulation Volumes (MG) South Plant Central Plant East Plant 64.8 6.6 58.2 2.1 11.3 44.8

City of Fort Myers Reclaimed Water Master Plan Section 6: Model Evaluation of Future Distribution System

56.4 14.7 41.8 0.09 0.01 41.7 106.2 3.3 11.0 7.0

40.5 -40.5 -0.5 -41.0

Malcolm Pirnie, Inc. 6-13


7.0 COST ESTIMATE FOR FUTURE IMPROVEMENTS This section discusses the costs associated with the future reclaimed water production and distribution infrastructure improvements. The costs are summarized for the 5-year and 20-year future dates by the following categories: • • •

Production Improvements Interconnections Distribution Piping

Additional discussion is included on the potential revenue from the sale of the reclaimed water to customers and to adjacent municipalities through interconnections. Information is also included on the methods that the City can utilize to fund the recommended improvements. 7.1

BASIS OF COSTS The costs provided in this Master Plan are calculated in 2004 dollars. As this

Master Plan was being prepared, CDM was completing the planning and design for the expansion of the reclaimed water production improvements at the CAWWTP and the SAWWTP. The treatment plant upgrade costs calculated by CDM were incorporated into this Master Plan. The costs for the reclaimed water production portion of the new East Wastewater Treatment Plant are assumed to be similar to the upgrades at the CRWPF and SRWPF. The interconnection costs are calculated based on required length of pipe necessary to connect to the City’s system, and installation of a control valve and flow meter. Costs include a 10 percent engineering design fee and 20 percent contingency. The distribution system piping costs are prepared by using $4.00 per inch diameter per foot length, with an additional $1.00 per inch diameter per foot for valves, hydrants, and bends and include a 10 percent engineering design fee and 20 percent contingency. All values are rounded up to the nearest $1,000. Reclaimed water costs to users are calculated assuming the average annual demand will be half of the maximum projected demand. The assumed amount the City will charge for reclaimed water is $0.5748 per 1,000 gallons. This amount will be City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-1


compared to the amount the City charges for potable water, which is $3.03 per 1,000 gallons to determine the cost savings for reclaimed users.

7.2

5-YEAR IMPROVEMENTS The short-term recommended infrastructure improvements over the next 5 years

are estimated to be approximately $17.0 million for production improvements, $0.73 million for interconnection improvements, and $10.5 million for piping improvements, totaling approximately $28.23 million dollars.

The costs estimated for these

improvements are described below.

7.2.1

Production Improvements

The improvements at the CRWPF will include additional filter and chlorine contact capacity to produce 6.0 mgd of reclaimed water. Existing equipment can handle a maximum production of 2.0 mgd reclaimed water. Onsite storage will be limited to the existing 1.0 MG storage tank. Most of the pumps, piping, instrumentation and controls, and operations staffing at the CRWPF are already in place. Therefore the cost for upgrading the CRWPF will be approximately $5,000,000. The construction of the SRWPF will include filtration and chlorine contact capacity, yard piping, control valves, instrumentation, 9 MG of storage capacity, and a minimum of 18 mgd high service distribution pumping capacity with variable frequency drives. The approximate cost for the SRWPF will be approximately $12,000,000.

7.2.2

Interconnections

The Gateway interconnection is included as a way for the City to share reclaimed water with the Gateway areas. The location was suggested by the SFWMD as part of their Regional Irrigation Distribution System Project. The total estimated cost for the Gateway interconnection is $1,454,600. The interconnection at Gateway will include a 12-inch transmission main from Treeline Avenue, a control valve, and a flow meter. The estimated costs for the Gateway interconnection and pump station are summarized in Table 7.1.

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-2


Table 7.1 Cost Estimate for the Gateway Interconnection Cost per Unit

Item 12-inch Diameter Pipeline

Quantity

Estimated Costs

Units

$60

5,700

ft

$342,000

Control Valve

$10,000

1

valve cost

$10,000

Flow Meter

$20,000

1

meter cost

$20,000 Subtotal

Engineering Design Fee

10%

$3,592,000

pump station cost

$372,000 $359,200

Contingency

20%

$3,592,000

pump station cost

$718,400

$5,000

1

Operations and Maintenance

years

$5,000

Total Cost Estimate for the Gateway Interconnection

$1,454,600

Operation and maintenance costs were estimated for one year assuming interconnection completion by 2008.

The costs for construction, operation, and

maintenance of this interconnection could be completed as a joint venture with Lee County and assuming that the County contributes 50 percent of the cost, the cost to the City will be approximately $728,000.

7.2.3

Distribution Piping

The costs for piping modifications to be completed by 2009 total $10,453,000. These piping modifications are summarized below by service area in Table 7.2. The costs for the new pipelines in the Carrell Service Area are the highest. This area contains the majority of the 24-inch diameter main that will connect the CRWPF and SRWPF, and route reclaimed water to the South and Southeast Service Areas. Table 7.2 Costs for New Piping Needed by 2009 Length (ft)

Street Location

Diameter (in)

Total Approximate Cost

Carrell Service Area Carrell Road Veronica Shoemaker Boulevard

18,500

24

$

2,931,000

5,300

16

$

560,000

1,100

10

$

73,000

$

3,564,000

Subtotal Carrell Service Area Piping Cost

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-3


Table 7.2 Costs for New Piping Needed by 2009 (Continued) Length (ft)

Street Location

Diameter (in)

Total Approximate Cost

Downtown Service Area Central Avenue

500

10

$

33,000

Edison Avenue

700

6

$

28,000

First Street

1,700

8

$

90,000

Jackson Street

1,100

4

$

30,000

Lafayette Street

2,100

8

$

111,000

McGregor Boulevard

800

4

$

22,000

US 41

700

4

$

19,000

$

333,000

Subtotal Downtown Service Area Piping Cost McGregor Service Area Carrell Road

1,600

24

$

254,000

DeLeon Street

8,300

24

$

1,315,000

Edison Avenue

1,400

6

$

56,000

Euclid Avenue

500

6

$

20,000

1,300

24

$

206,000

1,900

12

$

151,000

1,200

24

$

191,000

800

6

$

32,000

$

2,225,000

FTM Golf to DeLeon Ft. Myers Country Club Victoria Avenue

Subtotal McGregor Service Area Piping Cost Dr. Martin Luther King Service Area 2,200

8

$

117,000

800

6

$

32,000

Edison Avenue

2,600

16

$

275,000

High Street

1,400

6

$

56,000

Indian Street

2,000

6

$

80,000

Michigan Street

600

10

$

40,000

Palm Avenue

700

6

$

28,000

5,300

16

$

560,000

$

824,000

$

2,012,000

Cranford Avenue

Ford Street

Veronica Shoemaker Boulevard 7,800 16 Subtotal Dr. Martin Luther King Service Area Piping Cost

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-4


Table 7.2 Costs for New Piping Needed by 2009 (Continued) Length (ft)

Street Location

Diameter (in)

Total Approximate Cost

East Service Area Colonial Boulevard

2,600

20

$

344,000

900

16

$

96,000

$

440,000

Subtotal East Service Area Piping Cost Southeast Service Area Colonial Country Club Gateway Interconnection Pelican Preserve South Treeline Avenue Treeline Avenue

100

16

$

11,000

5,700

12

$

452,000

100

12

$

8,000

2,700

16

$

286,000

700

10

$

47,000

3,500

20

$

462,000

5,700

16

$

602,000

$

1,868,000

$

11,000

$

11,000

$

10,453,000

Subtotal East Service Area Piping Cost South Service Area Ben C. Pratt Parkway

100

16

Subtotal East Service Area Piping Cost Total 2009 System New Piping Costs

7.3

20-YEAR IMPROVEMENTS The long-term recommended infrastructure improvements for 2010 through 2024

are estimated to be $13.0 million for production improvements, $1.8 million for interconnection improvements, and $5.3 million for piping improvements, totaling $20.1 million. The costs estimated for these improvements are described below.

7.3.1

Production Improvements

The wastewater projections show that the City will need to build an East AWWTP with 8.0 mgd of by 2009. For the purpose of this report, we will assume that the costs for the reclaimed portion of the East AWWTP will be $13,000,000. A more detailed cost estimate for the new East AWWTP will be included in the Wastewater Master Plan.

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-5


7.3.2

Interconnections

The City could complete additional interconnections with the City of Cape Coral and Lehigh Acres. The total costs of the interconnections with Cape Coral and Lehigh Acres are estimated to be $3,400,000 and $128,500, respectively. Additional operational and maintenance costs for the Gateway interconnection will total $75,000.

The

calculated costs for the Cape Coral, Lehigh Acres, and Gateway interconnections for 2010 through 2024 are summarized in Table 7.3.

Table 7.3: Interconnection Costs for 2010 through 2024 Item 16-inch pipeline from the SRWPF 16-inch pipeline across the Caloosahatchee River Control Valve Flow Meter

Cost per unit Quantity Cape Coral Interconnection

Units

Estimated Costs

$80

6,100

ft

$488,000

$200

10,000

ft

$2,000,000

$15,000 $30,000

1 1

valve cost meter cost Subtotal pump station Engineering Design Fee 10% $2,533,000 cost pump station Contingency 20% $2,533,000 cost Operations and Maintenance $10,000 10 years Total Cost Estimate for the Cape Coral Interconnection Lehigh Acres Interconnection Control Valve $15,000 1 valve cost Flow Meter $30,000 1 meter cost Subtotal pump station Engineering Design Fee 10% $45,000 cost pump station Contingency 20% $45,000 cost Operations and Maintenance $5,000 14 years Total Cost Estimate for the Lehigh Acres Interconnection Gateway Interconnection Operations and Maintenance $5,000 15 years Total Cost Estimate for the Gateway Interconnection Total Interconnection Costs from 2010 through 2024

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

$15,000 $30,000 $2,533,000 $253,300 $506,600 $100,000 $3,392,900 $15,000 $30,000 $45,000 $4,500 $9,000 $70,000 $128,500 $75,000 $75,000 $3,596,400

Malcolm Pirnie, Inc. 7-6


The costs for the Cape Coral interconnection will include a 16-inch diameter pipeline from the SRWPF and a 16-inch diameter pipeline across the river to Cape Coral. The cost for directional drilling and for hanging the pipe from the Midpoint Bridge is estimated at $200 per foot. The Florida Department of Transportation would also have to approve the bridge installation.

Similar costs were estimated for a potable water

interconnection with the City of Cape Coral.

Assuming that construction will be

completed by 2014, costs for operation and maintenance will be included for ten years of use. A control valve and flow meter could be provided for the Lehigh Acres interconnection at the Gateway location or on the property of the East AWWTP. Operation and maintenance for the Lehigh Acres interconnection is included for 14 years, assuming that connection would begin in 2011 when the East AWWTP is operational. The Florida Governmental Utility Authority (FGUA) currently operates the Lehigh Acres wastewater system, however plans to turn over the Lehigh system to Lee County in the future. The exchange will most likely occur prior to the completion of the 20-year infrastructure improvements. The costs for construction of the Lehigh Acres and Cape Coral interconnections, and the operation and maintenance of the Cape Coral, Lehigh Acres, and Gateway interconnections may be completed as a joint venture with the City of Cape Coral and the County. Assuming that each involved party contributes 50 percent of the respective interconnection cost, the cost to the City will be approximately $1,798,000.

7.3.3

Distribution Piping

The costs estimate for the long-term piping modifications to be completed from 2010 through 2024 is estimated to total $5,273,000. A summary of the costs calculated by service area are listed below in Table 7.4. The service area that will require the highest expenditure for reclaimed piping from 2010 through 2024 will be the East Service Area, while the South and Southeast service areas will not require additional reclaimed piping.

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-7


Table 7.4: Piping Costs for 2010 through 2024

Street Location

Length (ft)

Diameter (in)

Carrell Service Area Broadway Solomon 3000 Schoolhouse Road 700 Colonial Boulevard from Veronica 2200 Veronica Shoemaker Boulevard 900

4 10 4 6

Subtotal Carrell Service Area Downtown Service Area 1st Street 3100 8 Palm Beach Boulevard 1300 8 Subtotal Downtown Service Area McGregor Service Area Arthur Avenue 700 4 Barkley and Royal Palm Square 5100 20 Coronado Road 1900 4 Cortez Boulevard 2200 4 Jefferson Avenue 400 8 La Palma Lane 800 12 McGregor Boulevard 900 16 Matera 1200 4 Princeton Avenue 900 10 Shadow Lane 1800 6 Winkler Avenue 600 10 Subtotal McGregor Service Area Dr. Martin Luther King Service Area Dupree Street 900 4 1800 4 Edison Avenue 4100 10 Marsh Avenue 3100 4 Michigan Street 2800 8 Veronica Shoemaker Boulevard 2000 10 Subtotal Dr. Martin Luther King Service Area East Service Area Colonial Boulevard 5400 20 Lee Boulevard 2100 20 Lee Boulevard to Buckingham Road 2300 20 North Treeline Avenue 2400 8 Subtotal East Service Area

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Approximate Cost $ $ $ $

80,000 47,000 59,000 36,000

$

222,000

$ $ $

164,000 69,000 233,000

$ $ $ $ $ $ $ $ $ $ $ $

19,000 674,000 51,000 59,000 22,000 64,000 96,000 32,000 60,000 72,000 40,000 1,189,000

$ $ $ $ $ $ $

24,000 48,000 271,000 82,000 148,000 132,000 705,000

$ $ $ $ $

713,000 278,000 304,000 127,000 1,422,000

Malcolm Pirnie, Inc. 7-8


Table 7.4: New Piping Costs for 2010 through 2024 (Continued) Street Location

Length (ft)

Diameter (in)

Approximate Cost

Southeast Service Area Arborwood to Reflection Isles

5,100

10

$

337,000

Reflection Isles

3,000

10

$

198,000

Reflection Isles to Paseo

3,800

10

$

251,000

$

786,000

Subtotal Southeast Service Area Palm Beach Service Area 4700

8

$

249,000

Bell Street

1000

6

$

40,000

East Riverside Drive

1300

4

$

35,000

700

8

$

37,000

2400

4

$

64,000

1100

4

$

30,000

Palm Beach Boulevard

3000

6

$

119,000

Royalston Avenue

2500

4

$

66,000

Terry Avenue

600

4

$

16,000

Veronica Shoemaker Boulevard

900

10

$

60,000

$

716,000

$

5,273,000

Marion Avenue

Subtotal South Service Area Total 2024 System New Piping Costs

7.4

RECLAIMED REVENUE PROJECTION The City will recover some of the costs for implementing a reclaimed distribution

system by charging their customers for reclaimed water, and by sending water to adjacent municipalities through interconnections. The current reclaimed water billing rate is currently $0.5748 per 1,000 gallons. The revenue received from reclaimed users is calculated in Table 7.5, assuming the average annual reclaimed usage is equal to 50 percent of the maximum reclaimed usage.

Table 7.5 Existing and Projected Revenue from Reclaimed Water Billing Existing and Future Dates

Average Reclaimed Demands (mgd)

Existing 2009 2024

0.89 3.13 7.58

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Annual Revenue ($/year) $ 186,724 $ 656,680 $ 1,590,299

Malcolm Pirnie, Inc. 7-9


Assuming linear increases in revenue from reclaimed users between 2004 and 2009, the City should collect approximately $2.53 million in revenue for the sale of reclaimed water to City customers, and an additional $17.3 million will be collected between 2010 and 2024. The projections of reclaimed production and customer demand show that there will be a large surplus of reclaimed water produced. The potential residential users identified as part of this report were limited to residential customers that are in new developments and in locations that already had some irrigation piping installed. These limitations were proposed to limit the capital cost and disruption of installing the piping to connect all potential users within the City. If other individual users were allowed to connect to the reclaimed distribution system, additional reclaimed water could be distributed and more revenue could be obtained. The City could also derive revenue from use of the interconnections with the reclaimed systems of adjacent municipalities. Interconnections were included in the model, Gateway planned for 2009 and the Cape Coral and Lehigh Acres planned for 2024. The City should also consider providing interconnections to the County Areas which are served by the City’s Wastewater Treatment Plants. Table 7.6 below lists the potential additional revenue assuming maximum production availability.

Table 7.6 Projected Revenue Potential from Interconnections

Future Dates

Average Reclaimed Production Availability (mgd)

Average Reclaimed Water Demands (mgd)

Average Demand Available for Additional Customers and Interconnections (mgd)

2009

14.47

3.13

11.34

$

2,380,000

2024

20.79

7.58

13.21

$

2,772,000

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Maximum Additional Revenue Potential ($/year)

Malcolm Pirnie, Inc. 7-10


It is unlikely that the available flows will actually be utilized by the adjacent municipalities through the interconnections. The amount of reclaimed water that can be distributed through these interconnections will be limited by hydraulic restrictions and by the actual reclaimed water demands in Cape Coral, and Gateway.

7.5

COST SAVINGS ATTRIBUTED TO THE USE OF RECLAIMED WATER The implementation of a reclaimed distribution system will save reclaimed

customers approximately 81 percent as compared to the cost of irrigation using potable water. The total savings estimated for reclaimed customers, using reclaimed water rather than potable water, is estimated to be approximately $2.8 million per year in 2009 and $6.8 million per year in 2024. The City will achieve an annual savings of approximately $700,000 per year by the year 2024 by implementing reclaimed water at their parks, golf courses, and roadway beautification projects.

7.6

FUNDING SOURCES The estimated $19.8 million of revenue from reclaimed water customers collected

over the next 20 years will not recover the $48.3 million in costs of the infrastructure improvements recommended in this report. The city will need to raise reclaimed rates to cover the cost of the improvements, or will need to investigate other methods of funding. The City has historically used several alternate funding methods to pay for the infrastructure required to construct the existing reclaimed system, including State Revolving Funds, grants, and inter-local agreements for joint funding with Lee County. This assumes that Lehigh Acres, Lee County and The City of Cape Coral would also help with the costs to construct interconnection pump stations. The City could have residential developers complete the installation of some reclaimed transmission mains in return for reduced taxes until the cost of the mains are reimbursed.

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-11


7.6.1 FDEP State Revolving Fund Loan Program The Water Pollution Control State Revolving Fund (SRF) Program provides lowinterest loans for planning, designing, and constructing water pollution control facilities. The SRF Priority List schedules projects to be financed with loans from the SRF. It is developed annually and adopted by the Department under the provisions of Chapter 62503 of the Florida Administrative Code.

Projects eligible for SRF loans include

wastewater management facilities, reclaimed wastewater reuse facilities, storm water management facilities, and various other widely accepted pollution control activities. SRF funds are made available for preconstruction loans and construction loans. The SRF loan provides a 40-percent discount off of the 20-year bond rates at a lowinterest rate (currently equals 3.0 percent). The SRF also includes authorization of additional funds to projects already on the list and adding new projects to the list. Utilization of SRF funds represents the lowest-cost opportunity available to finance City improvements. Repayment of the loan can be done so using the net operating revenues of the Water and Wastewater Utilities. The City of Fort Myers is currently listed on the SRF Priority List to receive funding for the 2005 Fiscal Year (FY) for Phase IV and Segment 2 in the Downtown area of the City’s sewer rehabilitation and replacement program. Treatment and reuse facility improvements at the Central and South AWWTPs, as well as Phase IV and Segment 1 of the Downtown sewer rehabilitation and replacement program were awarded funding from the SRF for FY 2004.

7.6.2

SFWMD Alternative Water Supply (AWS) Grant Program

Section 373.1961(2) of the Florida Statutes encourages governing boards of the water management districts to include funding for the development of alternative water supply systems in their annual budgets. To be eligible for the SFWMD AWS Funding Program, projects must propose the development of capital facilities for effective and appropriate alternative water supplies. In FY 2004, the SFWMD received 42 requests for funding in response to the AWS Funding Program application process. The City was approved as one of 34 proposals that received funding. Funding for expansion of the CRWPF from 2 mgd to 6 mgd was received in the amount of $200,000. City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-12


7.6.3

Funding Strategy

The City currently is, and previously has, received financial assistance from both the FDEP State Revolving Fund and the SFWMD Alternate Water Supply Program for water and wastewater improvements. Based on the City’s familiarity and track record with the FDEP and SFWMD finding sources, it is recommended that these two sources be used for funding of the future reclaimed water infrastructure improvements if possible. The alternative would be to raise the rates for reclaimed water. The costs for the interconnection pump stations should be split with the municipalities that will be sharing the reclaimed water. Lehigh Acres and Gateway (Lee County) should be able to contribute to the cost of the Gateway interconnection and pump station. Lee County may also be sending wastewater flow to the East WWTP and, therefore, be sharing the expense for the funding of the new plant. The City of Cape Coral has a widespread reuse system, and is already running out of water to serve their customer demands. They may be eager to explore the possibility of an interconnection to supplement their existing supply. SFWMD is requiring the City to participate in the interconnections as per conditions in their water use permit, and therefore should be willing to provide grant funding in addition.

Additional funding can be secured from State and Federal grant

funds, such as the Governor’s Program (formerly the WAP Grant Program) and the EPA State and Tribal Assistance Grants, respectively. These grants will provide funding, generally in lower quantities, but will assist to negate the use of borrowed funds if possible. Many of the large new residential developments that are being planned and constructed are eager to have reclaimed water connected for their irrigation use. The City is currently negotiating with the developers to pay for all or part of the transmission main costs. The developers would then be reimbursed by having lower taxes until the cost of the transmission mains are reimbursed.

City of Fort Myers Reclaimed Water Master Plan Section 7: Cost Estimate for Future Improvements

Malcolm Pirnie, Inc. 7-13


8.0 SUMMARY OF CONCLUSIONS AND RECOMMENDATIONS This section summarizes the conclusions and recommendations for this Reclaimed Water Master Plan.

The projected flows and future planned production upgrades at the

CRWPF, future SRWPF, and new East RWPF are discussed. Recommendations for major distribution system piping and installation are summarized.

The findings,

conclusions, and final recommendations of this Reclaimed Master Plan are presented below.

8.1

FINDINGS AND CONCLUSIONS The findings and conclusions of this Reclaimed Water Master plan have been

determined from studying all of the available data from the City on the reclaimed water production and distribution system. This report has been reviewed in depth by City staff for accuracy and correctness of all dates, times, and projection assumptions.

8.1.1 Existing Reclaimed Water System The City’s existing reclaimed water system currently serves seven customers. Among the current users, the most common use for reclaimed water is for irrigation of public parks and landscaping. However, the largest user of reclaimed water is Lee County’s Resource Recovery Facility. Each of the existing users receives reclaimed water on an individual demand basis, with an annual average demand totaling approximately 0.79 mgd in 2003. The LCRRF receives a continuous flow of reclaimed water each day of the year at much larger quantities than the other users. The City’s interlocal agreement with the County requires that reclaimed water be delivered to the LCRRF at a minimum pressure of 45 psi. This pressure requirement was assigned in the model as the minimum pressure for all areas of the distribution system.

The City achieves successful delivery of

reclaimed water to all customers as the demand exists.

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-1


Currently, reclaimed water production and distribution is limited by the amount of distribution system storage capacity. The CRWPF maintains a 1 MG ground storage reservoir for onsite storage, which satisfies the City’s current reclaimed water demand.

8.1.2

Regulatory Summary

The Central AWWTP reuse permit, developed and monitored by the FDEP, specifies the quantity and quality of effluent that can be used for reuse and land application. Plant staff must continuously monitor parameters such as CBOD5, TSS, pH, turbidity, and residual chlorine levels present in the effluent following disinfection to determine whether the effluent is of reclaimed water quality. A single sample maximum CBOD5 and suspended solids concentration of 60 mg/L and 5 mg/L, respectively, a total residual chlorine concentration of at least 1 mg/L, and a pH value within the range of 6.5 to 8.5 constitutes effluent in compliance with reclaimed water standards. Monthly Discharge Monitoring Reports and annual Effluent Analysis Reports are submitted to the FDEP to verify that the wastewater facilities are meeting reclaimed water and surface water discharge limitations and are not impacting ground water or surface water quality. The CAWWTP, SAWWTP, and the CRWPF historically have been in compliance with all applicable regulations and the reclaimed water provided to the City’s existing users is sufficient for the intended uses.

Growth of the City’s

reclaimed water distribution system will allow the City to decrease their dependence on effluent discharge to the Caloosahatchee River, which will soon be required as a result of recent TMDL legislation passed in Florida. The City is currently permitted to provide reclaimed water to customers for irrigation of landscaped areas and for use in industrial applications. As discussed in this Master Plan, many of the future planned users will be residential developments. Upon expansion of the system and the addition of new users, it will be necessary for the City to modify their existing FDEP permit to allow for irrigation of residential areas (by the individual homeowner). The permit may include special conditions for those residential developments to be newly constructed. The City may chose to provide only a set volume of reclaimed water, requiring the customer to provide storage and repumping capabilities as necessary to meet the desired pressure needs. City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-2


As the City begins to implement a more regional-type reclaimed water distribution system, the City’s Code of Ordinances must be revised to address numerous regulated design conditions and public health concerns. Additional standards must be included for the presence of double check valves or reduced pressure backflow prevention devices at locations with the high risk for cross connections with the potable water system. A routine schedule for inspection of these reclaimed water services should be maintained to assure that cross connections are avoided. Enhanced inspection efforts will be required in order for residential or small commercial reclaimed water users to become part of the City’s service, as per the FDEP requirements in FAC 62-610.470 and 62-555.360. Public awareness and education efforts must also be implemented to increase public understanding of reclaimed water. Through public awareness programs, the City can promote water conservation through the use of reclaimed water, attracting additional communities and industries to connect to the reclaimed water system. Advantages such as a reduced demand on drinking water sources, a cost-efficient supply of water, and the reliability of a continuous supply of water for irrigation of lawns, parks, and golf courses will provide the public with a positive view of reclaimed water.

Identification of

reclaimed water distribution system piping and equipment, through the use of colored pipe and appropriate signage, is required in order to raise awareness and assure that the public understands the water is not for human consumption.

8.1.3

Historic and Projected Reclaimed Water Demands

The historic reclaimed water demand, from the existing seven users, is approximately 0.717 mgd, with a maximum demand of 1.155 mgd observed during the maximum month of reclaimed water usage. Research into both existing sites and future developments that could potentially use reclaimed water, for the purpose of quantifying existing and projected water demand, resulted in identification of 66 additional future reclaimed water customers. The majority of the future users consist of golf courses, existing and new residential developments, and City parks, with only one industrial and ten commercial irrigation customers. The total potential reclaimed water demand from

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-3


the 73 identified future users is estimated to be 6.26 mgd and 15.15 mgd for 2009 and 2024, respectively. The City has already made the commitment to complete expansion of 6.0 mgd and 9.0 mgd reclaimed water production capacity, respectively, at their Central and South AWWTPs. The minimum three-month average wastewater flow should remain less than these values to remain in compliance with their future water use and wastewater treatment permits. The three-month rolling average flow was calculated for each day based on the flows recorded for the previous 90-day period.

The minimum three-month rolling

average for the calendar year was determined as the day during that year with the minimum calculated rolling average. The historical and projected minimum three-month rolling average flows for each plant are listed in Table 8.1. Historical minimum threemonth average daily flows have been as high as 83% of average annual flow at the CAWWTP and 90% at the SAWWTP.

Table 8.1 Historical and Projected Minimum Three-Month Rolling Average Wastewater Flows

Time Period

AADF (mgd) CAWWTP

1998 1999 2000 2001 2002

7.79 6.94 5.72 6.36 6.21

2009 2024

7.84 8.94

Minimum 3-Month Rolling Average Influent Flow (mgd)

SAWWTP

Minimum 3-Month Rolling Average/ AADF

CAWWTP SAWWTP CAWWTP Historical Flows 6.96 5.99 5.32 77% 6.92 5.28 5.78 76% 6.52 4.76 5.90 83% 6.79 4.67 5.22 73% 7.07 4.81 5.34 77% Projected Flows (based on highest minimum/average ratio) 8.06 6.51 7.25 83% 9.25 7.42 8.33 83%

SAWWTP 76% 84% 90% 77% 76% 90% 90%

A second method was used to determine the Central and South AWWTPs ability to meet future treatment capacity needs. Table 8.2 shows the historical and projected “lowest� three month average flows, calculated by averaging the three months during the calendar year when the monthly average flow is the lowest. This calculation method differs from that shown in Table 8.1 in that the lowest three months are not required to be City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-4


consecutive. Historical values for the average of the lowest three months of flow have been as high as 82% of average annual flow at the CAWWTP and 88% at the SAWWTP.

Table 8.2 Historical and Projected “Lowest” Three Month Average Wastewater Flows AADF (mgd)

Time Period

CAWWTP

SAWWTP

Average of the Lowest 3 Months of Influent Flow (mgd) CAWWTP

Lowest 3 Month Average/ AADF ratio

SAWWTP

CAWWTP

SAWWTP

5.47 5.81 5.72 5.25 5.40

78% 77% 82% 75% 78%

79% 84% 88% 77% 76%

Historical Flows 1998 1999 2000 2001 2002

7.79 6.94 5.72 6.36 6.21

6.96 6.92 6.52 6.79 7.07

6.09 5.35 4.70 4.74 4.84

Projected Flows (based on highest lowest 3 month/average ratio) 2009 2024

8.0 9.0

8.66 10.0

6.43 7.33

7.09 8.14

82% 82%

88% 88%

Both methods of calculating the three-month average flows (Table 8.1 and Table 8.2) for the CAWWTP and SAWWTP provided comparable results. In both analyses, the projected minimum three-month average flows for the CAWWTP are higher than the 6.0 mgd reclaimed water capacity that is planned at the CAWWTP for 2009 and 2024. The future flows will depend on where the wastewater flows in the eastern collection area are conveyed. These projections assume that 1.07 mgd 1.43 mgd are conveyed to the County’s Gateway WWTP in the years 2009 and 2024, respectively. The remaining flows from the east are split 50% to CAWWTP and 50% to SAWWTP for 2009, and 100% to the new East WWTP in 2024).

8.1.4

Operational Control

The current operational protocol automatically rejects reclaimed water before it is pumped to storage if the pH is not between 6.5 and 8.5, the chlorine residual is less than 1.0 mg/l, or if the turbidity is greater than 5 mg/L. The pumps are equipped with variable frequency drives that vary flow but maintain a constant pressure of 62 psi for flow from the CRWPF.

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-5


The capacity at the CRWPF will increase to 6 mgd, but the storage will still be limited to 1MG. To effectively operate with this limited storage volume, the production facility should continuously vary the flow being treated based on the water level in the ground storage reservoir. This requires the filtration and chlorine contact equipment to be sufficiently sized to meet the peak demands of the reclaimed water customers, rather than being limited to a maximum flow rate of 6.0 mgd. The SRWPF will have enough space to install one days worth of reclaimed water storage for the design capacity of 9.0 mgd. This will provide a more reliable source of reclaimed water supply. Therefore, when the SRWPF is online, it should assume the role of pressurizing the distribution system, allowing the pumps at the CRWPF to reduce flows when the level in the 1 MG ground storage reservoir is low. The majority of the effluent of the East WWTP will need to be disposed of via distribution to reclaimed water customers and through interconnections with adjacent utilities. When the East RWPF is online, the distribution system pressurization from the SRWPF may need to be reduced to maximize the use of reclaimed water from the East RWPF.

8.1.5

Reliability of Reclaimed Water Supply

The City’s two existing wastewater treatment plants will soon have the capability to produce a combined 15 mgd of reclaimed water available for distribution. This will be sufficient to handle the estimated maximum 6.26 mgd (weekly average) demand for 2009. With the addition of a third new East WWTP, an additional 8 mgd of treatment capacity will be available to meet the estimated maximum 15.15 mgd (weekly average)reclaimed demand for 2024. The presence of three reclaimed water production facilities will provide a reliable and redundant source of reclaimed water and ensure a sufficient supply to all customers. This reliability will be enhanced by the construction of bi-directional flow capability at the proposed interconnection locations with the City of Cape Coral, Lehigh Acres and Gateway.

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-6


8.1.6

Costs and Revenues associated with Future Reclaimed Water Improvements

The short-term recommended infrastructure improvements over the next 5 years are estimated to be approximately $17.0 million for production improvements, $0.73 million for interconnection improvements, and $10.5 million for piping improvements, totaling approximately $28.23 million dollars. The long-term recommended infrastructure improvements for 2010 through 2024 are estimated to be $13.0 million for production improvements, $5.3 million for interconnection improvements, and $1.8 million for piping improvements, totaling $20.1 million. The estimated revenue from reclaimed water customers collected over the next 20 years is $19.8 million. Additional revenue could also be obtained from selling reclaimed water to adjacent municipalities through the proposed interconnections. To make up the difference in the costs for the infrastructure and the revenues collected, the City could raise the rate for reclaimed water use, or could utilize other funding methods.

These methods include State Revolving Funds, grants, and joint

funding with Lee County, Cape Coral and Lehigh Acres. The City has historically used State Revolving Funds, grants and assistance from Lee County to pay for the infrastructure required to construct the existing reclaimed system. The City could also have residential developers complete the installation of some reclaimed transmission mains in return for reduced taxes until the cost of the mains are reimbursed.

8.2

RECOMMENDATIONS 8.2.1 Future Planning Initiatives Future expansion of the reclaimed water system, production, and distribution will

require construction of additional offsite storage facilities to accommodate peak demands on the system.

Malcolm Pirnie recommends that the City pursue the following

initiatives. 他

Encourage reclaimed water for new developments The City should implement the use of reclaimed water for irrigation of newly constructed residential communities. This allows for reclaimed water pipelines to be laid at the time of building construction, eliminating the burden

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-7


of potentially costly infrastructure repair that would be required for connection of existing developments to the reclaimed water system. Connection of new residential developments to the City’s system would provide a reclaimed water demand of approximately 8.0 mgd by 2024 for the City. Conveyance of the reclaimed water to each individual development can be contracted so that the City must only provide a given volume of reclaimed water, requiring the developer to provide storage and pumping capabilities as necessary to meet the desired pressure needs. ¾

Implement reclaimed water irrigation at select City parks Irrigation of City parks using reclaimed water should be implemented. A total of 20 City parks were originally identified as future reclaimed water users. Further evaluation of the 20 parks with respect to ease of connection to the City’s system, and individual reclaimed water demand (based on irrigable acreage) resulted in 14 parks where irrigation with reclaimed water would be economical to the City. These select City parks are shown in Table 8.2. Irrigation of these areas using reclaimed water would be feasible for the City to implement and would offer a substantial savings to the City over potable water usage. Table 8.3 Recommended City Parks for Reclaimed Water Irrigation User Name Winkler Neighborhood Fleishman Little League Ball field McGregor Boulevard Seminole Park Jefferson Park Lions Park Red Sox Main Field Yawkey Park Five Points Park Centennial Park Clemente Park Shady Oaks Park Terry Park Police Athletic (Billy Bowlegs Park)

¾

Irrigated Acreage 5.7 11.8 3.0 1.6 1.5 5.6 10.7 0.4 1.0 5.6 3.0 8.4 28.2 7.0

Require storage at user locations to reduce peak demands In order to dampen the peak demands on the system, the City should require each individual user with demands greater than 100,000 gpd to maintain onsite storage. This will also lessen the burden on the City to meet the desired pressure needs within the distribution system.

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-8


¾

As the reuse system in implemented, seek to reduce discharge of effluent to the Caloosahatchee River from the CAWWTP and SAWWTP The CAWWTP and SAWWTP should be able to continue to dispose of their effluent through surface water discharge to the Caloosahatchee River; however, the potential exists for a future reduction in discharge capacity. The FDEP is currently in the process of developing and implementing TMDLs for the Caloosahatchee River. By 2006, guidelines will be published and water quality standards will be established within each facility’s discharge permit. In addition to the FDEP guidelines, the City’s Consumptive Use Permit will soon require the City to utilize 100-percent of the reclaimed water produced. This will allow the City to reduce their dependence on River discharge. However, the use of the River discharge will serve as adequate disposal capacity for wet weather disposal of excess reclaimed water.

¾

Expedite Reclaimed Storage and Pumping facilities at the East AWWTP Location. The City may chose to expedite the construction of the reclaimed water storage and pumping capacity that will need to be constructed for the East AWWTP. Since the storage capacity at the CRWPF is limited, this would provide an offsite location for reclaimed water storage. A pumping facility at this location will also help to maintain the pressure requirement of 45 psi at the LCRRF. This storage and pumping facility could be designed along with the upgrades of the CRWPF and the new SRWPF, and could be online by 2009. However, the updated wastewater flow projections show that the entire new East AWWTP will need to be online by 2009.

¾

Install RIBs or deepwell injection at East AWWTP for disposal of excess Production of reclaimed water at the East WWTP, during certain months of the year, may exceed the reclaimed water user demand at that time. Also, the reclaimed water production quantity may not equal the amount of treated wastewater effluent available. Therefore, storage and disposal of excess wastewater effluent and excess reclaimed water at the East WWTP may be necessary. The use of rapid infiltration basins or deep injection wells, as discussed in Section 5.4, is a viable option that will provide the City with a means to dispose of their effluent at the East AWWTP. A large amount of land area is necessary for implementation of the infiltration basins and therefore the City could investigate available land in the East Service Area. If adequate land is not available, the City may consider deep well injection.

¾

Explore the opportunity to construct Interconnections Interconnections between the City’s reclaimed water distribution system, the Gateway Development, and City of Cape Coral are recommended as part of

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-9


this Master Plan. The interconnections can be used to provide regional sharing of reclaimed water, and to provide the City with storage and pumping capacity. These interconnection locations can provide the City with additional reclaimed water if needed, and will provide revenue for excess reclaimed water that is not needed by City residents. 8.2.5

Future Infrastructure Requirements

Production Capacity The 9.0 mgd SRWPF at the 12.0 mgd AADF SAWWTP should provide adequate treatment capacity to meet the requirement that the City provide treatment for the lowest three month rolling average flow. However the projected flows show that the 6.0 mgd CRWPF will not provide the capacity to meet the lowest three month rolling average flows at the CAWWTP. This facility may need to be increased in size to 7.5 mgd, or more of the flows could be diverted to the new East WWTP in the future. The production at the Central and South reclaimed water facilities will be limited by the amount of demand present in the system, therefore expansion of the production facility to a capacity higher than 6.0 mgd may not be necessary, other than for regulatory requirements, if there is not sufficient demand to support the capacity. Several residential developments are already requesting reclaimed water. The approval of additional users will need to be rationed until additional capacity is available, in order to maintain the flows for the contract with the LCRRF.

Reclaimed Water System Storage The City should ideally have one days worth of storage onsite at the Reclaimed Water Production Facilities to handle the demand fluctuations that will occur during the day without having the tanks run dry. This will be possible at the SRWPF and East RWPF, but not the CRWPF. If all of the storage is installed as recommended in this report, a total of 18 MG will be available if there is 1 MG at the CRWPF, 9MG at the SRWPF, and 8 MG at the East RWPF. The majority of the City’s future users will require water for irrigation purposes during various hours of the day/week. The City should recommend that all users with demands greater than 100,000 gpd should have one days worth of storage onsite. The users could use tanks or ponds for storage of reclaimed water. City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-10


Piping Requirements All of the piping listed in Section 6 is recommended to serve future users. The pipe routes were chosen based on the path of least resistance.

The routing of the

pipelines can be changed as long as the users are still receiving reclaimed water. City staff will be trained to modify the piping in the model to evaluate many possible routing scenarios. The pipeline projects should be completed in conjunction with the remaining Water Main Replacement Project phases, if possible. The mains that are listed as 6-inch and 4-inch diameter mains should be increased in size if individual residential users may be served in the future. The addition of reclaimed water service to existing single connection residential users was avoided by request of City staff. The installation of service connections to individual users would cause disruption to neighborhoods and existing roadways, and would require backflow prevention devices to be installed on all of the potable connections to the users. The existing individual users in Heritage Palms, Dean Park, and West McGregor were included as possible future users because they already have some irrigation lines installed and could be served with reclaimed water with minimal piping connection modifications.

City of Fort Myers Reclaimed Water Master Plan Section 8: Summary of Conclusions and Recommendations

Malcolm Pirnie, Inc. 8-11


Table A.1 1992 Reclaimed Water Master Plan Report Recommendations South Water Reclamation Facility Service Area Phase I Implementation Options Plant Transmission Improvement System s

Distribution System

Legal, Admin Engineering, Land and Easements

Estimated Total Estimated Residential Connections Cost Served

Option

Service Area

A

North to Fort Myers Country Club Area

$3,366,000

$1,516,000

$2,205,000

$1,347,000

$8,434,000

1780

B

North to Fort Myers High Edison Home Area

$3,366,000

$1,997,000

$3,440,000

$1,673,000

$10,476,000

2780

C

North to Centennial Park

$3,366,000

$2,299,000

$3,557,000

$1,752,000

$10,974,000

2890

D

East to New Red Sox Complex

$3,366,000

$2,491,000

$4,282,000

$1,926,000

$12,065,000

3560

E

Service with Loop through Downtown Area

$3,366,000

$3,150,000

$4,399,000

$2,074,000

$12,989,000

3660

Central Water Reclamation Facility Service Area Phase I Implementation Options

Option

Plant Improvements

Transmission System

1

$2,298,000

$2,313,000

Distribution System $1,441,000

Legal, Admin Total Engineering, Estimated Cost Land and Easements $1,150,000

$7,202,000

Estimated Residential Connections Served 1440

Interconnection of South and Central Service Areas Option

Plant Improvements

Transmission System

Distribution System

I

$0

$5,322,000

$0

Appendix A

Legal, Admin Total Engineering, Estimated Cost Land and $1,011,000 $6,333,000

City of Fort Myers Reclaimed Water Master Plan

Estimated Residential Connections 0

Page 1


Table A.2 Effluent Resource Planning Report, March 2001

Number of New Customers = 18

2005

New Customer Demand (mgd) 3.14

Current Customer Demand (mgd) 0.69

Total Reuse Demand (mgd) 3.83

Total Reuse Supply (mgd) 13

Reuse Excess 9.17

2010

7.41

0.69

8.1

15

6.9

Year

Excess Reclaimed Water Disposal Options: Effluent Wastewater Reclaimed Water (1.5 mgd) Reclaimed Water (5.0 mgd) Reclaimed Water Transmission System WTP RO Concentrate Wastewater and RO Concentrate

Appendix A

Method Deepwell Injection ASR ASR Deepwell Injection Deepwell Injection

City of Fort Myers Reclaimed Water Master Plan

Total Estimated Cost $15,990,000 $961,000 $2,573,000 $15,167,000 $7,670,000 $21,775,000

Page 2


Reclaimed Water or Effluent Analysis Report Part I - Instructions (1) All applicable items must be completed in full. Note that if parts of this application do not apply, those parts of the form need not be executed. (2) All information is to be typed or printed in ink. (3) This form shall be submitted to the appropriate District Office in accordance with the schedule in the permit. (4) Analyses shall be performed using appropriate methods and shall be capable of achieving minimum detection limits less than or equal to the maximum contaminant levels shown. (5) The following instructions apply to Parts III through VIII of this form. (6) Column (a) - List the parameters that are to be analyzed. (7) Column (b) - List the STORET Code for these parameters. (8) Column (c) - Record the results of the analysis. If the result was below the minimum detection limit, indicate by showing a less than sign preceding the detection limit for the analytical method used (i.e. < 0.01). (9) Column (d) - List the primary or secondary drinking water standard from Chapter 17-550, F.A.C. (10) Column (e) - Indicate the analytical method used. Record the number from Figure 1 in Chapter 17-601, F.A.C., or from other sources. (11) Column (f) - Enter the date on which the analysis was run (MM/DD/YR). (12) Column (g) - If the result shown in Column (c) is greater than the standard shown in Column (d) - enter an asterisk (*) in Column (g).

Part II - General Information (1) Facility Name:

City of Fort Myers, Central AWWT and Reclaimed Water Production Facility

Address:

P.O. Box 2217

City:

Fort Myers, Florida

Telephone Number:

Zip:

33902

(941) 332-6871

(2) Owner or Authorized Representative Name: Title: Address: City:

Mario Curiel Central Plant Supervisor P.O. Box 2217 Fort Myers

Telephone Number: (3) Method of Discharge: (4) Report Period:

State: (941)332-6871 Public access and land application system 1/1/01 (Begin Date)

To:

12/31/01 (End Date)

Page 1 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991

Florida

Zip:

33902


(5) Name of Laboratory conducting the analysis: Address: City:

Sanders Laboratories

1050 Endeavor Ct. Nokomis

Telephone Number:

State:

Florida

Zip:

34275

(941) 488-8103

(6) The facilities DER identification number (also known as the GMS identification number) (7) DER test site identification number (for the sampling location)

5236MO1014

Reclaimed Distribution Line

(8) Description of the monitoring point (9) Date on which the sample was taken (MM/DD/YR)

1/16/01

Time of day at which the sample was taken: 12:30

a.m.

p.m.

(10) Date of extraction for the organic chemical analysis performed in Part VI (MM/DD/YR)

1/26/01

Part III - Inorganic Analysis (b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Arsenic

900208

<0.0028

0.05

EPA 200.7

1/17/01

No

Barium

900209

<0.0001

1.0

EPA 200.7

1/17/01

No

Cadmium

900210

<0.0002

0.010

EPA 200.7

1/17/01

No

Chromium

900211

<0.001

0.05

0.001

1/17/01

No

Fluoride

000951

0.6

4.0

EPA 340.2

1/17/01

No

Lead

900212

<0.001

0.05

EPA 200.7

1/17/01

No

Mercury

900213

<0.001

0.002

EPA 245.1

1/17/01

No

Nitrate (as N)

071850

0.09

10

EPA 353.2

1/17/01

No

Selenium

900214

0.0017

0.01

EPA 200.7

1/17/01

No

Silver

900215

<0.001

0.05

EPA 200.7

1/17/01

No

Sodium

000929

166

160

EPA 200.7

1/17/01

Yes

(a) Parameter Name

Part IV- Volatile Organic Analysis (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

900222

<0.01

0.02

EPA 504.1

1/18/01

No

---

0.83

75

EPA 524.2

1/17/01

No

Vinyl chloride

039175

<0.29

1

EPA 524.2

1/17/01

No

1,1-dichloroethane

034496

<0.1

7

EPA 524.2

1/17/01

No

1,2-dichloroethane

034531

<0.02

3

EPA 524.2

1/17/01

No

(a) Parameter Name Ethylene dibromide Para-dichlorobenzene

Page 2 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


Part IV- Volatile Organic Analysis (continued) (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

1,1,1-trichloroethane

034506

<0.21

200

EPA 524.2

1/17/01

No

Carbon tetrachloride

032102

<0.29

3

EPA 524.2

1/17/01

No

Trichloroethene

--

<0.02

3

EPA 524.2

1/17/01

No

Tetrachloroethene

--

<0.21

3

EPA 524.2

1/17/01

No

034030

<0.00005

1

EPA 524.2

1/17/01

No

(a) Parameter Name

Benzene

Part V- Trihalomethane Analysis (a) Parameter Name Total THM

(b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

082080

130

100

EPA 524.2

1/17/01

No

Part VI- Organic Chemical Analysis (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Endrin

039390

<0.01

0.02

EPA 508

1/26/01

No

Lindane

039782

<0.024

4

EPA 508

1/26/01

No

Methoxychlor

039480

<0.25

100

EPA 508

1/26/01

No

Toxaphene

039400

<0.5

5

EPA 508

1/26/01

No

2.4-D

039730

<0.362

100

EPA

1/25/01

No

2.4.5-TP (Silvex)

039760

<0.025

10

EPA 515.1

1/25/01

No

(a) Parameter Name

Part VII- Radiological Analysis (a) Parameter Name Gross alpha excl.

(b) STORET Code

(c) Analysis Result (pCi/L)

(d) Standard (pCi/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

001519

<1.8

15

EPA 900.0

1/24/01

No

011503

0.2

5

EPA 903.1

1/29/01

No

radon and uranium Radium-226 and Radium-228 combined

<1.0

Brooks&Blanc

Part VIII- Secondary Chemical Analysis (b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Chloride

000940

220

250

SM4500C1-B

1/22/01

No

Copper

900218

<0.0012

1

EPA 200.7

1/17/01

No

Iron

900219

<0.030

0.3

EPA 200.7

1/17/01

No

Manganese

900220

0.0165

0.05

EPA 200.7

1/17/01

No

(a) Parameter Name

Part VIII- Secondary Chemical Analysis (continued) Page 3 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


(b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Sulfate

000945

108

250

EPA 375.4

1/26/01

No

Zinc

900221

0.072

5

EPA 150.1

1/16/01

No

pH (units)

000403

6.55

6.5 - 8.5

EPA 160.1

1/16/01

No

TDS

070300

740

500

EPA 160.1

1/18/01

Yes

Foaming Agents

900217

0.8

0.5

SM 5540C

1/17/01

Yes

(a) Parameter Name

Part IX - Certification

I certify under penalty of law that I have personally examined and am familiar with the information submitted in this document and all attachments and that, based on my inquiry of those individuals immediately responsible for obtaining the information, I believe that the information is true, accurate, and complete. I am aware that these are significant penalties for submitting false information, including the possibility of fine and imprisonment.

Date:

4/18/01

Phone:

(941) 332-6871

Signature of Lead Operator Mario Curiel A-7178

Name (please type) and Certification Number

Address: P.O. Box 2217 Fort Myers, Florida

Page 4 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


Reclaimed Water or Effluent Analysis Report Part I - Instructions (1) All applicable items must be completed in full. Note that if parts of this application do not apply, those parts of the form need not be executed. (2) All information is to be typed or printed in ink. (3) This form shall be submitted to the appropriate District Office in accordance with the schedule in the permit. (4) Analyses shall be performed using appropriate methods and shall be capable of achieving minimum detection limits less than or equal to the maximum contaminant levels shown. (5) The following instructions apply to Parts III through VIII of this form. (6) Column (a) - List the parameters that are to be analyzed. (7) Column (b) - List the STORET Code for these parameters. (8) Column (c) - Record the results of the analysis. If the result was below the minimum detection limit, indicate by showing a less than sign preceding the detection limit for the analytical method used (i.e. < 0.01). (9) Column (d) - List the primary or secondary drinking water standard from Chapter 17-550, F.A.C. (10) Column (e) - Indicate the analytical method used. Record the number from Figure 1 in Chapter 17-601, F.A.C., or from other sources. (11) Column (f) - Enter the date on which the analysis was run (MM/DD/YR). (12) Column (g) - If the result shown in Column (c) is greater than the standard shown in Column (d) - enter an asterisk (*) in Column (g).

Part II - General Information (1) Facility Name:

City of Fort Myers, Central AWWT and Reclaimed Water Production Facility

Address:

P.O. Box 2217

City:

Fort Myers, Florida

Telephone Number:

Zip:

33902

(941) 332-6871

(2) Owner or Authorized Representative Name: Title: Address: City:

Mario Curiel Central Plant Supervisor P.O. Box 2217 Fort Myers

Telephone Number: (3) Method of Discharge: (4) Report Period:

State: (941)332-6871 Public access and land application system 1/1/02 (Begin Date)

To:

12/31/02 (End Date)

Page 1 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991

Florida

Zip:

33902


(5) Name of Laboratory conducting the analysis: Address: City:

Sanders Laboratories

1050 Endeavor Ct. Nokomis

Telephone Number:

State:

Florida

Zip:

34275

(941) 488-8103

(6) The facilities DER identification number (also known as the GMS identification number) (7) DER test site identification number (for the sampling location)

5236MO1014

Reclaimed Distribution Line

(8) Description of the monitoring point (9) Date on which the sample was taken (MM/DD/YR)

1/15/02

Time of day at which the sample was taken: 10:00

a.m.

p.m.

(10) Date of extraction for the organic chemical analysis performed in Part VI (MM/DD/YR)

1/21/02, 1/1802, 1/31/02

Part III - Inorganic Analysis (b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Arsenic

900208

<0.0028

0.05

EPA 200.7

1/28/02

No

Barium

900209

<0.0001

1.0

EPA 200.7

1/28/02

No

Cadmium

900210

<0.0002

0.010

EPA 200.7

1/28/02

No

Chromium

900211

<0.001

0.05

0.001

1/28/02

No

Fluoride

000951

0.6

4.0

EPA 340.2

1/28/02

No

Lead

900212

<0.001

0.05

EPA 200.7

1/28/02

No

Mercury

900213

<0.001

0.002

EPA 245.1

1/28/02

No

Nitrate (as N)

071850

0.09

10

EPA 353.2

1/28/02

No

Selenium

900214

0.0017

0.01

EPA 200.7

1/28/02

No

Silver

900215

<0.001

0.05

EPA 200.7

1/28/02

No

Sodium

000929

166

160

EPA 200.7

1/28/02

Yes

(a) Parameter Name

Part IV- Volatile Organic Analysis (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

900222

<0.01

0.02

EPA 504.1

1/28/02

No

---

0.83

75

EPA 524.2

1/17/02

No

Vinyl chloride

039175

<0.29

1

EPA 524.2

1/17/02

No

1,1-dichloroethane

034496

<0.1

7

EPA 524.2

1/17/02

No

1,2-dichloroethane

034531

<0.02

3

EPA 524.2

1/17/02

No

(a) Parameter Name Ethylene dibromide Para-dichlorobenzene

Page 2 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


Part IV- Volatile Organic Analysis (continued) (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

1,1,1-trichloroethane

034506

<0.21

200

EPA 524.2

1/17/02

No

Carbon tetrachloride

032102

<0.29

3

EPA 524.2

1/17/02

No

Trichloroethene

--

<0.02

3

EPA 524.2

1/17/02

No

Tetrachloroethene

--

<0.21

3

EPA 524.2

1/17/02

No

034030

<0.00005

1

EPA 524.2

1/17/02

No

(a) Parameter Name

Benzene

Part V- Trihalomethane Analysis (a) Parameter Name Total THM

(b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

082080

130

100

EPA 524.2

1/17/02

No

Part VI- Organic Chemical Analysis (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Endrin

039390

<0.01

0.02

EPA 508

1/22/02

No

Lindane

039782

<0.024

4

EPA 508

1/22/02

No

Methoxychlor

039480

<0.25

100

EPA 508

1/22/02

No

Toxaphene

039400

<0.5

5

EPA 508

1/22/02

No

2.4-D

039730

<0.362

100

EPA

2/5/02

No

2.4.5-TP (Silvex)

039760

<0.025

10

EPA 515.1

2/5/02

No

(a) Parameter Name

Part VII- Radiological Analysis (a) Parameter Name Gross alpha excl.

(b) STORET Code

(c) Analysis Result (pCi/L)

(d) Standard (pCi/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

001519

<1.8

15

EPA 900.0

1/24/02

No

011503

0.2

5

EPA 903.1

1/29/02

No

radon and uranium Radium-226 and Radium-228 combined

<1.0

Brooks&Blanc

Part VIII- Secondary Chemical Analysis (b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Chloride

000940

220

250

SM4500C1-B

1/22/02

No

Copper

900218

<0.0012

1

EPA 200.7

1/28/02

No

Iron

900219

<0.030

0.3

EPA 200.7

1/28/02

No

Manganese

900220

0.0165

0.05

EPA 200.7

1/28/02

No

(a) Parameter Name

Part VIII- Secondary Chemical Analysis (continued) Page 3 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


(b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Sulfate

000945

108

250

EPA 375.4

1/22/02

No

Zinc

900221

0.072

5

EPA 150.1

1/28/02

No

pH (units)

000403

6.55

6.5 - 8.5

EPA 160.1

1/15/02

No

TDS

070300

740

500

EPA 160.1

1/21/02

Yes

Foaming Agents

900217

0.8

0.5

SM 5540C

1/16/02

Yes

(a) Parameter Name

Part IX - Certification

I certify under penalty of law that I have personally examined and am familiar with the information submitted in this document and all attachments and that, based on my inquiry of those individuals immediately responsible for obtaining the information, I believe that the information is true, accurate, and complete. I am aware that these are significant penalties for submitting false information, including the possibility of fine and imprisonment.

Date:

4/18/02

Phone:

(941) 332-6871

Signature of Lead Operator Mario Curiel A-7178

Name (please type) and Certification Number

Address: P.O. Box 2217 Fort Myers, Florida

Page 4 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


Reclaimed Water or Effluent Analysis Report Part I - Instructions (1) All applicable items must be completed in full. Note that if parts of this application do not apply, those parts of the form need not be executed. (2) All information is to be typed or printed in ink. (3) This form shall be submitted to the appropriate District Office in accordance with the schedule in the permit. (4) Analyses shall be performed using appropriate methods and shall be capable of achieving minimum detection limits less than or equal to the maximum contaminant levels shown. (5) The following instructions apply to Parts III through VIII of this form. (6) Column (a) - List the parameters that are to be analyzed. (7) Column (b) - List the STORET Code for these parameters. (8) Column (c) - Record the results of the analysis. If the result was below the minimum detection limit, indicate by showing a less than sign preceding the detection limit for the analytical method used (i.e. < 0.01). (9) Column (d) - List the primary or secondary drinking water standard from Chapter 17-550, F.A.C. (10) Column (e) - Indicate the analytical method used. Record the number from Figure 1 in Chapter 17-601, F.A.C., or from other sources. (11) Column (f) - Enter the date on which the analysis was run (MM/DD/YR). (12) Column (g) - If the result shown in Column (c) is greater than the standard shown in Column (d) - enter an asterisk (*) in Column (g).

Part II - General Information (1) Facility Name:

City of Fort Myers, Central AWWT and Reclaimed Water Production Facility

Address:

P.O. Box 2217

City:

Fort Myers, Florida

Telephone Number:

Zip:

33902

(239) 332-6871

(2) Owner or Authorized Representative Name: Title: Address: City:

Mario Curiel Central Plant Supervisor P.O. Box 2217 Fort Myers

Telephone Number: (3) Method of Discharge: (4) Report Period:

State: (239)332-6871 Public access and land application system 1/1/02 (Begin Date)

To:

12/31/02 (End Date)

Page 1 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991

Florida

Zip:

33902


(5) Name of Laboratory conducting the analysis: Address: City:

Sanders Laboratories

1050 Endeavor Ct. Nokomis

Telephone Number:

State:

Florida

Zip:

34275

(941) 488-8103

(6) The facilities DER identification number (also known as the GMS identification number) (7) DER test site identification number (for the sampling location)

5236MO1014

Reclaimed Distribution Line

(8) Description of the monitoring point (9) Date on which the sample was taken (MM/DD/YR)

1/15/02 (resample for 515.1 taken 1/23/02 at 8:00 am)

Time of day at which the sample was taken: 10:00

a.m.

p.m.

(10) Date of extraction for the organic chemical analysis performed in Part VI (MM/DD/YR)

1/21/02, 1/1802, 1/31/02

Part III - Inorganic Analysis (b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Arsenic

900208

<0.0028

0.05

EPA 200.7

1/28/02

No

Barium

900209

<0.0001

1.0

EPA 200.7

1/28/02

No

Cadmium

900210

<0.0002

0.010

EPA 200.7

1/28/02

No

Chromium

900211

<0.001

0.05

EPA 200.7

1/28/02

No

Fluoride

000951

0.461

4.0

EPA 300.0A

1/29/02

No

Lead

900212

<0.001

0.05

EPA 200.7

1/28/02

No

Mercury

900213

<0.001

0.002

EPA 245.1

1/23/02

No

Nitrate (as N)

071850

0.15

10

EPA 353.2

1/28/02

No

Selenium

900214

<0.0016

0.01

EPA 200.7

1/28/02

No

Silver

900215

<0.001

0.05

EPA 200.7

1/28/02

No

Sodium

000929

142

160

EPA 200.7

1/28/02

No

(a) Parameter Name

Part IV- Volatile Organic Analysis (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

900222

<0.01

0.02

EPA 504.1

1/18/02

No

---

<0.02

75

EPA 524.2

1/17/02

No

Vinyl chloride

039175

<0.29

1

EPA 524.2

1/17/02

No

1,1-dichloroethane

034496

<0.1

7

EPA 524.2

1/17/02

No

1,2-dichloroethane

034531

<0.02

3

EPA 524.2

1/17/02

No

(a) Parameter Name Ethylene dibromide Para-dichlorobenzene

Page 2 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


Part IV- Volatile Organic Analysis (continued) (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

1,1,1-trichloroethane

034506

<0.21

200

EPA 524.2

1/17/02

No

Carbon tetrachloride

032102

<0.29

3

EPA 524.2

1/17/02

No

Trichloroethene

--

<0.02

3

EPA 524.2

1/17/02

No

Tetrachloroethene

--

<0.21

3

EPA 524.2

1/17/02

No

034030

<0.05

1

EPA 524.2

1/17/02

No

(a) Parameter Name

Benzene

Part V- Trihalomethane Analysis (a) Parameter Name Total THM

(b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

082080

214

100

EPA 524.2

1/17/02

Yes

Part VI- Organic Chemical Analysis (b) STORET Code

(c) Analysis Result (ug/L)

(d) Standard (ug/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Endrin

039390

<0.01

0.02

EPA 508

1/22/02

No

Lindane

039782

<0.05

4

EPA 508

1/22/02

No

Methoxychlor

039480

<0.25

100

EPA 508

1/22/02

No

Toxaphene

039400

<0.5

5

EPA 508

1/22/02

No

2.4-D

039730

<0.100

100

EPA 515.1

2/5/02

No

2.4.5-TP (Silvex)

039760

<0.200

10

EPA 515.1

2/5/02

No

(a) Parameter Name

Part VII- Radiological Analysis (a) Parameter Name Gross alpha excl.

(b) STORET Code

(c) Analysis Result (pCi/L)

(d) Standard (pCi/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

001519

<2.4

15

EPA 900.0

1/24/02

No

011503

0.6

5

EPA 903.1

1/29/02

No

radon and uranium Radium-226 and Radium-228 combined

Brooks&Blanc

Part VIII- Secondary Chemical Analysis (b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Chloride

000940

177

250

SM4500C1-B

1/22/02

No

Copper

900218

<0.0012

1

EPA 200.7

1/28/02

No

Iron

900219

<0.030

0.3

EPA 200.7

1/28/02

No

Manganese

900220

0.0134

0.05

EPA 200.7

1/28/02

No

(a) Parameter Name

Part VIII- Secondary Chemical Analysis (continued) Page 3 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


(b) STORET Code

(c) Analysis Result (mg/L)

(d) Standard (mg/L)

(e) Analytical Method

(f) Analysis Date

(g) Above Standard

Sulfate

000945

86

250

EPA 375.4

1/22/02

No

Zinc

900221

0.022

5

EPA 150.1

1/28/02

No

pH (units)

000403

7.10

6.5 - 8.5

EPA 160.1

1/15/02

No

TDS

070300

564

500

EPA 160.1

1/21/02

Yes

Foaming Agents

900217

0.046

0.5

SM 5540C

1/16/02

No

(a) Parameter Name

Part IX - Certification

I certify under penalty of law that I have personally examined and am familiar with the information submitted in this document and all attachments and that, based on my inquiry of those individuals immediately responsible for obtaining the information, I believe that the information is true, accurate, and complete. I am aware that these are significant penalties for submitting false information, including the possibility of fine and imprisonment.

Date:

4/18/02

Phone:

(239) 332-6871

Signature of Lead Operator Mario Curiel A-7178

Name (please type) and Certification Number

Address: P.O. Box 2217 Fort Myers, Florida

Page 4 of 4 17-601.900(4), Reclaimed Water or Effluent Analysis Report Effective July 1, 1991


RECLAIMED WATER OR EFFLUENT ANALYSIS REPORT Part I - Instructions (1) All applicable items must be completed in full. Note that if parts of this application do not apply, those parts of the form need not be executed. (2) All information is to be typed or printed in ink. (3) This form shall be submitted to the appropriate District Office in accordance with the schedule in the permit. (4) Analyses shall be performed using appropriate methods and shall be capable of achieving minimum detection limits less than or equal to the maximum contaminant levels shown. (5) The following instructions apply to Parts III through VIII of this form. (6) Column (a) - List the parameters that are to be analyzed. (7) Column (b) List the STORET Code for these parameters. (8) Column (c) - Record the results of the analysis If the result was below the minimum detection limit, indicate by showing a less than sign preceding the detection limit for the analytical method used (i.e. <0.01). (9) Column (d) - List the primary or secondary drinking water standard from Chapter 62-550, F.A.C. (10) Column (e) - Indicate the analytical method used. Record the number from Figure 1 in Chapter 62-601, F.A.C., or from other sources. (11) Column (f) - Enter the date on which the analysis was run (MM/DD/YR). (12) Column (g) - If the result shown in Column (c) is greater than the standard shown in Column (d) - enter an asterisk (*) in Column (g).

Part II - General Information (1)

Facility Name:

City of Fort Myers, Central AWWT and Reclaimed Water Production Facility

Address:

P.O. Box 2217

City:

Fort Myers

Telephone Number (including area code) :

State: (239) 332-6871

1 DEP Form 62-620.910(15) Effective July 1, 1991

Florida

Zip:

33902-0000


(2)

Owner or Authorized Representative Name:

Mario Curiel

Title:

Central Plant Supervisor

Address:

P.O. Box 2217

City:

Fort Myers

State:

Florida

Zip:

Telephone including area code:

(239) 332-6871

(3)

Method of Discharge:

Public Access and land application System

(4)

Report Period

01/01/03

To

33902-2217

12/31/03

(Beginning Date) (5)

Name of Laboratory conducting the analysis: Address:

1050 Endeavor Ct.

City:

Nokomis

Telephone including area code:

(End Date)

Sanders Laboratories, Inc.

State:

Florida

Zip:

34275-0000

(941) 488-8103

(6)

The facility DEP identification number (WAFR or GMS ID #):

5236MO1014

(7)

DEP test site identification number (for the sampling location)

Reclaimed distribution line

(8)

Description of the monitoring point:

(9)

Date on which the sample was taken (MM/DD/YR)

01/22/03

Time of day at which the sample was taken

11:40

(10) Date of extraction for the organic chemical analysis performed in Part VI

2 DEP Form 62-620.910(15) Effective July 1, 1991

01/29/03

AM

PM

(MM/DD/YR)


Part III - Inorganic Analysis (a) Parameter Name Arsenic

(b) STORET Code 900208

(c) Analysis Result (mg/L) 0.005

Barium

900209

0.007

Cadmium

900210

Chromium

(d) Standard (mg/L) 0.05

(e) Analytical Method 200.7

(f) Analysis Date 02/06/03

(g) Above Standard no

1.0

200.7

02/06/03

no

0.003

0.010

200.7

02/06/03

no

900211

0.004

0.05

200.7

02/06/03

no

Fluoride

000951

0.44

4.0

EPA 300.0

01/25/03

no

Lead

900212

0.002

0.05

200.7

02/06/03

no

Mercury

900213

<0.001

0.002

EPA 245.1

01/27/03

no

Nitrate (as N)

071850

0.86

200.7

02/06/03

no

Selenium

900214

0.003

0.01

200.7

02/06/03

no

Silver

900215

<0.001

0.05

200.7

02/06/03

no

Sodium

000929

200.7

02/06/03

no

131

10

160

Part IV - Volatile Organic Analysis (a) Parameter Name Ethylene dibromide Para-dichlorobenzene

(b) STORET Code 900222

(c) Analysis Result (µg/L) <0.005

(d) Standard (µg/L) 0.02

(e) Analytical Method EPA 504.1

(f) Analysis Date 02/01/03

no

(g) Above Standard

--

<0.5

75

EPA 502.2

01/30/03

no

Vinyl Chloride

039175

<0.5

1

EPA 502.2

01/30/03

no

1,1-dichloroethane

034496

<0.3

7

EPA 502.2

01/30/03

no

1,2-dichloroethane

034531

<0.2

3

EPA 502.2

01/30/03

no

1,1,1-trichloroethane

034506

<0.3

200

EPA 502.2

01/30/03

no

Carbon tetrachloride

032102

<0.3

3

EPA 502.2

01/30/03

no

Trichloroethene

--

<0.2

3

EPA 502.2

01/30/03

no

Tetrachloroethene

--

<0.2

3

EPA 502.2

01/30/03

no

034030

<0.5

1

EPA 502.2

01/30/03

no

(f) Analysis Date 01/30/03

(g) Above Standard yes

Benzene

Part V - Trihalomethane Analysis (a) Parameter Name Total THM

(b) STORET Code 082080

(c) Analysis Result (µg/L) 260

(d) Standard (µg/L) 100 3

DEP Form 62-620.910(15) Effective July 1, 1991

(e) Analytical Method EPA 502.2


Part VI - Organic Chemical Analysis (a) Parameter Name Endrin

(b) STORET Code 039390

Lindane

039782

<0.06

4

EPA 508

01/31/03

no

Methoxychlor

039480

<0.05

100

EPA 508

01/31/03

no

Toxaphene

039400

<0.5

5

EPA 508

01/31/03

no

2,4-D

039730

<0.5

100

EPA 515.1

01/29/03

no

2,4,5-TP (Silvex)

039760

<0.05

10

EPA 515.1

01/29/03

no

(e) Analytical Method EPA 900.0

(f) Analysis Date 02/12/03

(g) Above Standard no

903.1/Brks/Blnk.

02/18/03

no

(e) Analytical Method SM4500C1-B

(f) Analysis Date 01/28/03

(g) Above Standard no

(c) Analysis Result (µg/L) <0.1

(d) Standard (µg/L) 0.02

(e) Analytical Method EPA 508

(f) Analysis Date 01/31/03

(g) Above Standard no

Part VII - Radiological Analysis (a) Parameter Name Gross alpha excl. radon and uranium Radium-226 and Radium-228 combined

(b) STORET Code 001519 011503

(c) Analysis Result (pCi/L) <3.5

(d) Standard (pCi/L) 15

2.3

5

Part VIII - Secondary Chemical Analysis (a) Parameter Name Chloride

(b) STORET Code 000940

(c) Analysis Result (mg/L) 170

(d) Standard (mg/L) 250

Copper

900218

0.006

1

200.7

02/06/03

no

iron

900219

0.175

0.3

200.7

02/06/03

no

Manganese

900220

0.023

0.05

200.7

02/06/03

no

Sulfate

000945

EPA 375.4

01/28/03

no

Zinc

900221

0.025

200.7

02/06/03

no

pH (units)

000403

7.12

EPA 150.1

01/23/03

no

TDS

070300

EPA 160.1

01/23/03

yes

Foaming Agents

900217

SM5540C

01/24/03

no

75

250 5 6.5 - 8.5

536

500

<0.05

0.5

4 DEP Form 62-620.910(15) Effective July 1, 1991


Part IX - Certification I certify under penalty of law that I have personally examined and am familiar with the information submitted in this document and all attachments and that, based on my inquiry of those individuals immediately responsible for obtaining the information, I believe that the information is true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment.

Date: Phone:

Signature of Lead Operator Mario Curiel A-7178 Name (please type) and Certification Number

(239) 332-6871

Address P.O. Box 2217 Fort Myers, Fl., 33902

5 DEP Form 62-620.910(15) Effective July 1, 1991


Chapter 26 PUBLIC FACILITIES* *Cross references: Procedure for conveyance of city property, § 2-29; code enforcement procedures, § 2-156 et seq.

ARTICLE V. RECLAIMED WATER PROGRAM* *Cross references: Extension of the reclaimed water use service, § 18-100 et seq.; utilities, Ch. 18.

Sec. 26-201. Purposes. The purposes of this article are: (1) (2) (3) (4) (5)

To establish that the public works department shall prepare a master plan for reclaimed water service and keep it current. To establish procedures and policy for obtaining reclaimed water service within and adjacent to the city. To provide for fees and charges. To establish requirements for construction of reclaimed water systems. To establish procedures for commitments for service.

(Code 1963, § 39-52; GMC § .010(E)(1))

Sec. 26-202. Administration. This article shall be administered by the city public works administrator through the public works department. The administrator is responsible for the development and promulgation of rules and regulations that will be needed to assist the public to work within these policies. (Code 1963, § 39-53; GMC § .010(E)(2))

Sec. 26-203. Jurisdiction. Unless otherwise provided herein, this article shall apply to the areas of the city which are within formally established service areas. (Code 1963, § 39-54; GMC § .010(E)(3))

Sec. 26-204. Source of reclaimed water. (a)

(b) (c)

To reduce demands on the city's potable water supply facilities, the city plans to supply reclaimed water to customers through a separate reclaimed water distribution system to satisfy water demands that do not require the use of potable water. This reclaimed water will consist of treated, filtered and chlorinated effluent from wastewater treatment plants. When alternative sources are available to the reclaimed water supply system, the reclaimed water supply shall be given first priority. Sources of reclaimed water shall comply with the following state department of environmental regulations as they may apply and as they may be revised from time to time.

TABLE INSET:

Florida City of Fort Myers Reclaimed Water Master Plan

Subject

1

Appendix C Code of Ordinances, Chapter 25, Article V


Administrative Code Chapter 17-4.620

General permits for wastewater collection.

Chapter 17-6.060

Effluent limitation.

Chapter 17-6.070

Treatment plants.

Chapter 17-6.080

Effluent disposal (land application).

Chapter 17-6.110

Treatment plans and effluent disposal systems.

Chapter 17-6.140

Permits required.

Chapter 17-6.180

Enforcement.

(d)

Sources of reclaimed water shall comply with state and local health department regulations and shall receive their approvals prior to utilization.

(Code 1963, ยง 39-56; GMC ยง .010(E)(4))

Sec. 26-205. Use and distribution of reclaimed water. (a)

The city shall develop and maintain a reclaimed water master plan. Such plan shall receive city council approval and shall include: (1) Designated areas of the city within which construction and use of a reclaimed water system shall be encouraged. (2) The suggested general location of a pipeline transmission system as a basis of supply for a local reclaimed water distribution system.

(b)

Use of reclaimed water is intended to limit potable water requirements within a residential development to that used in swimming pools, household laundries, kitchens, bathroom tubs, showers and lavatories. Use of water-saving devices on fixtures and a public attitude to avoid waste will result in a significant reduction in the use and consumption of potable water. Use of reclaimed water may include any and/or all of the following: (1) Lawn, garden and landscaping irrigation. (2) Irrigation of golf courses and other recreation areas. (3) Industrial.

(c)

(d) (e) (f)

(g)

The use of reclaimed water may be separately metered for each connection, as is the case for potable water, and appropriate rates will be established by the city council for the use of reclaimed water. The city plans to initially develop sources and supply reclaimed water to local distribution systems within the developments for irrigating lawns, gardens, trees, shrubbery, golf courses and open space in and adjacent to the city. Commercial and industrial customers presently using potable water will be encouraged to use reclaimed water wherever such use is safe and practicable, not only for landscape irrigation but in processes not requiring the use of potable water. To assist commercial and industrial users in evaluating possible uses of reclaimed water, the city will provide appropriate reclaimed water quality analysis. Within individual new development areas, a separate reclaimed water distribution system shall be installed in accordance with city engineering and construction standards when, in the opinion of the city, such installation is required to satisfy current planning for the distribution and use of reclaimed water. Costs for the installation of a nonpotable water distribution system shall be borne by the owner/developer. Applications for all new development shall include provisions for the use of reclaimed water.

City of Fort Myers Reclaimed Water Master Plan

2

Appendix C Code of Ordinances, Chapter 25, Article V


(Code 1963, § 39-57; GMC § .010(E)(5))

Sec. 26-206. Applications for reclaimed water service. Applications for reclaimed water service shall be made to the city public works department. (1) (2) (3) (4)

(5) (6)

Applicants requesting reclaimed water service shall make application on forms provided by the public works administrator. Such application will be reviewed by the public works administrator to determine the adequacy of existing facilities and what, if any, new facilities may be required to provide adequate service. If found feasible to provide service, the administrator will notify the applicant of such determination. If not financially feasible, the administrator will so notify the applicant and advise what changes must be made to make it feasible. Applications, when accepted by the public works department, shall constitute a contract between the applicant and the city, which shall bind the applicant to pay the public works department for the services rendered at its prescribed rates and charges and to comply with all the rules and regulations as prescribed and fixed hereunder or as hereafter adopted. If tracts of land, parcels or premises for which service is requested do not abut a dedicated public rightof-way, the owner shall provide the department with an appropriate utility easement before a commitment for service shall be granted. The applicant shall provide for and pay for all costs for the extension of the utilities from the stipulated points of connection to the applicant's property. Design and construction shall be in accordance with the appropriate policy, standards, and specifications of the city.

(Code 1963, § 39-59; GMC § .010(E)(6))

Sec. 26-207. Promulgation and enforcement of procedures and regulations. The public works administrator shall have the power to promulgate procedures and regulations with respect to the following matters: (1) (2) (3) (4) (5)

Application forms, procedures and requirements. Installation requirements including specification of acceptable materials, devices and regulations to help prevent backflow or cross-connections with other systems. Procedures for enforcement of the article and regulations pertaining to reclaimed water including procedures for inspection of the customer's system. Procedures for the orderly expansion of the reclaimed water system. Procedures and regulations for the efficient operation of the reclaimed water system.

(Code 1963, § 39-60; GMC § .010(E)(7))

Sec. 26-208. Unauthorized work on reclaimed water system. (a)

(b)

No person, unless expressly authorized by the public works administrator, shall tamper with, work on, or in any way alter or damage any city- reclaimed water facility. Tampering with or working on shall include, but not be limited to, opening or closing of valves, or causing of any reclaimed water to flow from the system. No unauthorized person shall cut into or make any connection with the system. The offending person shall be liable for the cost of all charges attributable to the correction of such tampering, including legal expenses, but payment of or correcting such damage shall not relieve the offending person from civil or criminal penalties the city or a court of law may impose for a violation of city ordinance. The service valve located between the customer's reclaimed water system and the city's distribution system may be operated by the customer when his private cut-off valve, required on the customer's premises, requires repair.

City of Fort Myers Reclaimed Water Master Plan

3

Appendix C Code of Ordinances, Chapter 25, Article V


(Code 1963, § 39-61; GMC § .010(E)(8))

Sec. 26-209. Inspection. (a)

(b) (c)

To ensure that the provisions of city ordinances, regulations and procedures are being observed, the city reserves the right and privilege of inspecting, removing, and/or securing any or all devices installed by the customer which connect to or control the reclaimed water. (1) Inspections without cause to believe that an ordinance or regulation is being violated shall be at reasonable times and shall not exceed a reasonable frequency. (2) Inspections where there is reasonable cause to believe that an ordinance or regulation is being violated shall be at such times and shall occur with such frequency as is necessary to establish that an ordinance or regulation is or is not being violated. Each customer of reclaimed water shall, by application, give prior written consent to entry upon his premises, and thereby waives any other written notice for such inspection. Failure of the city to obtain such a written waiver shall not affect the right of the city to proceed pursuant to this article. Refusing to permit an authorized city agent or employee to enter onto the premises for the purpose of inspecting the customer's reclaimed water system pursuant to this section shall constitute a violation of this section and shall be grounds for immediate discontinuance of reclaimed water service by the city to the subject premises.

(Code 1963, § 39-62; GMC § .010(E)(9))

Sec. 26-210. Ownership All constructed reclaimed water facilities and appurtenances, other than the plumbing, shall be accepted by the city, and shall become and remain the property of the city. No person shall by payment of any charges provided herein, or by causing any construction of the facilities accepted by the city, acquire any interest or right in any of these facilities, or any portion thereof, other than the privilege of having their property connected thereto for reclaimed water services in accordance with this article. (Code 1963, § 39-63; GMC § .010(E)(10))

Sec. 26-211. Identification. The reclaimed water distribution system shall include special considerations to avoid cross-connections with the potable water system. The following features shall be included in reclaimed water systems to protect the public health. (1) (2) (3) (4) (5)

Reclaimed water distribution systems shall be constructed with brown PVC pipe or purple with yellow block letters color-taped ductile iron pipe. Square valve box covers painted brown to distinguish from round potable water system valve boxes. Brown strip on street curb to identify reclaimed water customer. Backflow preventers installed on potable water service connection Reclaimed water meters color coded with tape to distinguish from potable water meters (where applicable). Meters, covers and meter box covers should be cast to indicate reclaimed water.

(Code 1963, § 39-64; GMC § .010 (E)(11); Ord. No. 2600, § 2, 8-19-91)

Sec. 26-212. Fees and charges. The city shall, by resolution, establish appropriate fees and charges for connection to and use of reclaimed water.

City of Fort Myers Reclaimed Water Master Plan

4

Appendix C Code of Ordinances, Chapter 25, Article V


Code 1963, ยง 39-65; GMC ยง .010(E)(12)

Sec. 26-213. Penalty. Pursuant to F.S. ยง 125.69, a person who violates any provision of this article shall be subject to prosecution in the name of state in the same manner as misdemeanors are prosecuted; and, upon conviction, such person shall be punished by a fine not to exceed five hundred dollars ($500.00) or by imprisonment in the county jail not to exceed sixty (60) days or by both such fine or imprisonment. (Code 1963, ยง 39-66; GMC ยง .010(E)(13))

Secs. 26-214--26-235. Reserved.

City of Fort Myers Reclaimed Water Master Plan

5

Appendix C Code of Ordinances, Chapter 25, Article V


ARTICLE X. CROSS-CONNECTION CONTROL STANDARDS Sec. 26-326. Purpose and intent. It is necessary for the protection and promotion of the health, safety and welfare of the people, served by the city water system, to adopt cross-connection control standards which provide for protection of the city potable water supply; protect the potable water system at the service connection by isolating within the consumer's premises actual or potential pollution or contamination which may result from backflow or through cross-connection; segregate domestic and industrial uses into separate systems to prevent possible pollution or contamination of the private potable water system and provide a continuous program of crossconnection control which will systematically and effectively prevent the contamination of the city potable water system. Such standards supplement, but do not supersede or modify the Standard Plumbing Code as adopted for the City of Fort Myers, Florida. (Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-327. Responsibilities. The consumer shall have the prime responsibility of preventing contaminants and pollutants from entering the city's water supply system from their water supply system. The consumer shall protect their water supply system against actual or potential cross-connection, backflow or back-siphonage, as required by the Standard Plumbing Code and this article and other applicable regulations. They shall assure that all internal protective devices are tested and maintained in the working condition required. They shall assure the necessary plumbing permits are obtained for new water supply system installations, and for alterations or repair to existing systems in accordance with the locally adopted Standard Plumbing Code including Appendix D. (Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-328. Operational criteria. When a hazard or potential hazard to the city water system is found on the consumer's premises, the consumer is required to install an approved backflow prevention device at each city water service connection to the premises in accordance with the requirements of this article. The type of device shall depend on the degree of hazard involved and shall be installed in accordance with "Backflow Prevention Devices (Illustrated)" and "Typical Installations (Illustrated)" attached hereto and made a part of this article. (Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-329. Protective devices. The type of protective device required shall depend upon the degree of hazard as described in AWWA Manual M-14 or as described below. Where more than one type of protection is possible, the actual method utilized shall be at the discretion of the city subsequent to physical inspection of the hazard. (1)

In the case of any premises where there is an auxiliary water supply, there shall be no physical connection between such auxiliary water supply and the consumer's water system which is served by the city water supply system. Where such connections are found, disconnections shall be accomplished and the city water system shall be protected against the possibility of future reconnection by an approved reduced pressure principle backflow prevention device at the service connection.

City of Fort Myers Reclaimed Water Master Plan

1

Appendix D Code of Ordinances Chapter 26, Article X


(2)

In the case of any premises where there is water or a substance that would be objectionable but not hazardous to health, if introduced into the city water system, the city water system shall be protected by an approved double check valve assembly.

(3)

In the case of any premises where there is any material dangerous to health which is handled in such a fashion as to create an actual or potential hazard to the city water system, the city water system shall be protected by an approved reduced pressure principle backflow prevention device.

(4)

In the case of any premises where it is physically impossible or impractical to make a complete in-plant cross-connection survey, the city water system shall be protected by the installation of an approved reduced pressure principle backflow prevention device at the service connection.

(Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-330. Facilities requiring backflow protection. (a)

The following is a partial list of facilities which will require reduced pressure principle backflow preventers at the service connection. Requirements are based upon the degree of hazard afforded the city potable water system. (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20) (21) (22) (23) (24) (25) (26) (27) (28) (29) (30) (31) (32)

Schools with laboratories of any kind. Automatic car washes. Automotive plants. Auxiliary water systems (except single-family and duplex). Beverage bottling plants. Canneries, packing houses and reduction plants. Chemical plants. Cooling towers. Dairies and cold storage plants. Exterminating companies. Facilities with commercial boilers or chilled water systems. Fertilizer manufacturing plants. Fiberglass molding, processing or storage. Film laboratories. Heating or cooling coils submerged in contaminants. Hospitals, medical buildings, sanitariums, morgues, mortuaries, autopsy facilities, nursing and convalescent homes and clinics, doctor or dentists offices with surgical facilities. Laboratories (industrial, commercial, medical and school). Laundries, dye works and cleaners. Metal manufacturing, cleaning, plating, processing or fabricating plants. Motion picture studios. Nuclear and radioactive materials facilities. Oil and gas production; storage or transmission properties. Paper and paper products plants. Plating plants. Power plants. Radiator shops. Radioactive materials or substances; plants or facilities handling. Restricted, classified or other closed facilities. Rubber plants. Sand and gravel plants. Travel trailer and mobile home parks. Wastewater treatment plants, pump stations and stormwater pumping facilities.

City of Fort Myers Reclaimed Water Master Plan

2

Appendix D Code of Ordinances Chapter 26, Article X


(33) (34) (35) (36) (37) (b)

Water treatment plants. Ice plants, junkyards and recycling plants. Beauty parlors and barbershops. Greenhouses and nurseries. Other buildings as found with suspected high hazards.

The following is a partial list of facilities which will require double check valve assemblies: (1)

(c)

Apartments. Three (3) or more units or boarding houses with more than three (3) rooms not having any auxiliary water system. (2) Buildings (over four (4) stores) not having an auxiliary water system. (3) Doctor and dental offices, without operating or surgical facilities. (4) Hotels and motels. (5) Irrigation systems connected to the potable water supply. (6) Office buildings. Commercial and industrial buildings not requiring reduced pressure principal backflow preventers. (7) Fire systems. As specified by AWWA Manual M-14. (8) Restaurants and food handlers. (9) Service stations. (10) Swimming pools other than single-family. (11) All other buildings as found with suspected low hazards except duplexes and singlefamily homes. A dual check valve or equivalent approved by the city shall be required on all new single-family homes or duplexes at time of construction.

(Ord. No. 2769, ยง 6, 12-4-95; Ord. No. 2886, ยง 1, 12-21-98)

Sec. 26-331. Approval of backflow prevention devices. Any backflow prevention device required herein shall be of a type approved by the city, the state department of environmental protection and the department of health and rehabilitative services. The size of the backflow prevention device shall be the same size as the customer's service line. (Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-332. Noncompliance; service to be discontinued; notice; consent to entry. (a)

In emergency situations when the city potable water supply is being contaminated or is in immediate danger of contamination, water service may be discontinued by the city.

(b)

No water service connection shall be installed on the premises of any consumer unless the city potable water system is protected as required by this article.

(c)

Delivery of water to the premises of any consumer may be discontinued by the city if any protective device required by this article has not been installed, or is defective or has been removed or bypassed. Discontinued water service shall not be resumed until conditions at the consumer's premises have been abated or connected to the satisfaction of the city.

(d)

Violation of any provision of this article shall be subject to the provisions set forth in section 114 of the City Code or as prescribed in the Standard Plumbing Code. Each day a violation continues shall be a separate offense.

(e)

For the purpose of making any inspections or discharging the duties imposed by this article, the city, the health department, and the building official, or their designees shall have the right to enter upon the premises of any consumer. Each consumer, as a condition of the continued

City of Fort Myers Reclaimed Water Master Plan

3

Appendix D Code of Ordinances Chapter 26, Article X


delivery to his premises of water from the city water supply, shall be considered as having stated his consent to the entry upon his premises of the city, the health department, and the building official or their designees for the purpose state herein. (Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-333. Ownership. The customer shall purchase, own and maintain all backflow prevention devices installed at the point of delivery to the consumer's water system. (Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-334. Testing of backflow preventers. (a)

(b)

The customer shall provide for routine testing of backflow prevention devices, maintain accurate records of tests and repairs made to the devices, and provide the city's utility department with copies of such records upon request. The records shall be on forms provided by the city's utility department. All costs incurred for device purchases, installations, maintenance, testing and repairs are to be paid by the customer. (b) Customers who cannot shut down operation for testing and repair of a backflow prevention device will install parallel devices to allow testing and repairs to take place. The customer shall not have a bypass around any backflow prevention device unless there is a backflow prevention device of the same type on the bypass. The customer is responsible for insuring the proper device size and in determining the need for parallel devices.

(Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-335. Areas embraced. All territory within or served by the city water system shall be embraced by the provisions of this article. (Ord. No. 2769, ยง 6, 12-4-95)

Sec. 26-336. Existing customers. The following shall apply to existing customers: (1)

Existing customers, using potable water for only domestic single-family and duplex purposes, will not be required to retrofit their service.

(2)

Existing customers will be required to retrofit when the degree of hazard has increased due to a change in occupancy, additional fixtures are added or other causes. See section 26-330, facilities requiring backflow protection.

(3)

Existing customers required to install a reduced pressure principle backflow prevention device shall comply within eighteen (18) months of passage of this article.

(Ord. No. 2769, ยง 6, 12-4-95)

City of Fort Myers Reclaimed Water Master Plan

4

Appendix D Code of Ordinances Chapter 26, Article X


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.