Earned value management

Page 1

Earned value management (EVM)


Earned value management (EVM) calculation for a project:

Example:  The project has 1 task.  Total hours planned to do the project: 5 hours.  Number of hours spent: 6 hours.  Estimate to complete the project: 7 hours.  Hourly rate: USD 50 per hour.


Planned value (PV) = How much work should be done? PV = Total hours planned x hourly rate. PV = 5 hours x USD 50 = USD 250. Earned value (EV) = How much work was done? EV = Planned value × percent that project is completed. EV = USD 250 × 6/7 complete = USD 214. Actual cost (AC) = How much did the work cost? AC = Total hours spent x hourly rate. AC = 6 hours x USD 50 = USD 300.


Value 350 Planned value (PV)

Actual cost (AC)

300 250 200 Earned value (EV)

6

7

Hours


Schedule performance index (SPI) = Earned value (EV) ⁄ Planned value (PV) SPI = USD 214 / USD 250 = 0.86.

Schedule variance (SV): Earned value (EV) – Planned value (PV) SV = USD 214 – USD 250 = -USD 36. Cost performance index (CPI): Earned value (EV) / Actual cost (AC) CPI = USD 214 / USD 300 = 0.71. Cost variance (CV) = Earned value (EV) - Actual cost (AC) CV = USD 214 – USD 300 = -USD 86.


Sources of inspiration https://edward-designer.com/web/pmp-earned-value-questions-explanined/ https://www.pmi.org/learning/library/earned-value-management-systems-analysis-8026


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.