“memorial mews” bowen project update

Dec 2012

Development Funding Approved. 20 of the 22 town houses sold, with more recent sales at higher prices. Bloomer Construction appointed as the builder of the development. Site set-up and demolition works scheduled to commence soon. Expected completion date for the project is October 2013.

Overview

AT A GLANCE

The project can be summarised as

Overview:

22 townhouse development

the development of 3 main buildings,

Location:

6 Brisbane Street, Bowen,QLD

Project Size:

$9.4m

Forecast Settlement Date:

October 2013

Construction Timeframe:

9 months

Fund Objective:

The development and construction of a townhouse project to provide wholesale prices for investors.

containing a total of 22 town houses, each of which are 3 bedroom, 2 bathroom and single garage units with rear courtyards. Project size is approx $9.4m. The development is located at 6 Brisbane Street, Bowen, QLD. With the funding now approved, the early works and demolition are expected to commence soon, with an expected project

Current Status:

completion by October 2013. The timing for this development could not be better with the announcement of the

Market Update:

Abbott Point Port project expected to have a very positive impact on the property market, with increased demand for both rental and sales anticipated. The market generally is rebounding with a positive outlook into 2013. The increase in construction activity in the area is a key indicator to the market improvement, with the announcement of Stages 2 – 5 of Abbott Point to bring an additional multi billion of construction activity to the region. This is expected to have a very positive effect to the residential property market and anticipated completion is forecast to be timed well in this regard.

Abbott Point update:

• Funding approval in place. • Building contract in place. • Builder commencing on site within weeks. • • • •

Local market rebounding. Activity levels increasing. Low vacancy rate. Comparable sales above presale values.

• • • •

Port stages 2 to 5 approved. Mine to port rail approved. Environmental approvals in place. Forecast commencement in 2013.


“memorial mews� bowen project update Forecast project timeframe Completion of Design/Constructions Drawings

Development Permits Early Works and Demolition

Main Construction Works

Strata Titling

Settlement of Sales

Nov

Dec

Jan

Feb

Mar

Apr

May

June

Jul

Aug

Sept

Development Location

existing building

Construction plan view

computer generated image ( CGi ) Of future development

Oct

Nov

Important note This Investor Update document contains general information relating to the Lynter Group Bowen Residential Development Trust (Trust) and does not contain personal advice or financial product advice. This information has been prepared without taking account of your objectives, financial situation or needs. Before acting on this information and making financial decisions, you should consider whether this information is appropriate for you and are recommended to seek independent financial, investment, tax and/or legal advice having regard to your own objectives, financial situation and needs. Any forward looking statements and estimates are provided as a general guide only and should not be relied upon as an indication or guarantee of future performance. The Trust is subject to various risks, including property industry risks and development and construction risks which may affect the performance of the Trust and investor returns. Accordingly, there is no guarantee that the Trust will complete the development within the timeframe forecast (or at all), and there is no guarantee that forecast or targeted investor returns, and/or returns of capital invested, will be achieved.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.