Canadian Consulting Engineer September October 2023

Page 34

Transportation Award of Excellence

Waaban Crossing Hatch and Systra IBT project development, design and construction. • Project decisions must be unanimous between the parties and made in consideration of project outcomes. • The agreement precludes the parties from submitting claims against each other. • The consultant and contractor are paid all of their costs (excluding profit) by the owner. • Profit is put at risk and earned by meeting project goals; e.g. meeting a timeline, obtaining approvals and permits or achieving local purchasing targets.

North America’s first IPD bridge The most significant innovation for the project was the IPD approach, which was wholeheartedly adopted by the city, the engineers (Hatch and Systra), the contractor (Kiewit) and its trade partners (Bauer and Walters Group). While IPD had been used for building construction, this was the first time it would be used in North America for a bridge. In the IPD model, all parties—including owner, engineer and constructor—sign a joint contract that incentivizes them to set aside their individual interests and act as a team to make the decisions that are best for the project. The agreement achieves collaboration in several ways: • All parties are fully involved in

This approach let the team work together during the project validation period, from 2018 to 2019, to modify and refine the bridge design concept and construction methodology from those in an earlier environmental assessment (EA), with the goal of bringing the target cost within the budget of $180 million. Major cost-saving innovations were conceived during the validation period. The approach span substructure design was simplified from the V-piers proposed in the EA to modified conventional vertical piers and pier caps, with a less ‘heavy’ and more ‘open’ appearance. The steel approach spans were replaced by 48-m long precast concrete Nebraska University (NU) girders. These were the longest girders that could be manufactured

34

CANADIAN CONSULTING ENGINEER

“One of the first integrated project delivery (IPD) undertakings outside buildings, this will be huge for people in Kingston.” – Jury

(with minor modifications to the precast plant), delivered by road and lifted into place on-site. Indeed, they were the largest concrete girders ever produced in Ontario! Since providing a temporary trestle in the river from which to construct the new bridge would represent a significant cost, a hybrid approach was selected instead, using a combination of a causeway in the shallow areas, a trestle in the deeper areas and a temporary liftbridge over the navigation channel. The resulting concept included the 1.2-km bridge with onshore approach roads providing connections at John Counter Boulevard on the west side of the river and Gore Road on the east side. A bridge deck cross-section width of 15.6 m would accommodate a two-lane roadway and a multi-use trail on the south side, separated from the roadway by a traffic barrier and widening out into two observation lookouts above the main span piers. Local benefits The city’s vision was to provide an iconic structure that would give residents a sense of pride, attract tourism and respect the natural environment. The more specific September/October 2023

PHOTOS COU RT E SY H ATC H.

F

or many years, the City of Kingston, Ont., recognized a new, third crossing of the Cataraqui River was needed to connect communities on both sides and to accommodate regional growth. In 2018, with funding secured, the city implemented the project using an Integrated Project Delivery (IPD) model and signed a contract with Hatch, Systra IBT and Kiewit. Together, despite the pandemic, this team completed the 1.2-km long bridge on time and under budget. It is Kingston’s largest infrastructure project to date.


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Digital Acceleration Initiative

6min
pages 60-62

CHUSJ Phase 2 Redevelopment

3min
pages 58-59

Calgary Cancer Centre Phases 1 - 3

4min
pages 56-57

Espace Montmorency Energy Loop

4min
pages 52-55

Pellet Plant Biofuel

3min
pages 50-51

We care enough to do it right

0
pages 49-50

Caribou Falls Block Dam 2 Reconstruction

2min
pages 48-49

Comox Valley Water Treatment Plant

3min
pages 46-47

La Baie Landslide and Embankment Restoration

4min
pages 44-45

Woodworth Dam Optimization

3min
pages 42-43

Port Saint John Westside Modernization

4min
pages 40-41

Transportation Tank Hill Emergency Restoration

4min
pages 38-39

Waaban Crossing

4min
pages 34-37

Vendôme Station Entry and Pedestrian Link

4min
pages 30-31

Centerm Expansion

4min
pages 26-29

Nancy Pauw Bridge

4min
pages 24-25

Million Meals Campaign

4min
pages 22-23

REFAM Argan Predictive Model

4min
pages 20-21

Standing Column Wells for Clé-des-Champs School

3min
pages 18-19

LAC Preservation Storage Facility

4min
pages 16-17

WHY SPECIFY UPONOR?

2min
pages 15-16

K3 Expansion – South Shaft Headframe

5min
pages 12-14

Canadian Consulting Engineering Awards Jury

4min
pages 10-12

2023 CANADIAN CONSULTING ENGINEERING AWARDS / PRIX CANADIENS DU GÉNIE-CONSEIL

1min
page 9

RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER

5min
page 7

LEON BOTHAM HONOURED WITH BEAUBIEN AWARD FOR LIFETIME ACHIEVEMENT

3min
page 6

CELEBRATING EXCELLENCE IN THE CONSULTING ENGINEERING INDUSTRY

2min
page 5

Cause for celebration

3min
page 4

Digital Acceleration Initiative

6min
pages 60-62

CHUSJ Phase 2 Redevelopment

3min
pages 58-59

Calgary Cancer Centre Phases 1 - 3

4min
pages 56-57

Espace Montmorency Energy Loop

4min
pages 52-55

Pellet Plant Biofuel

3min
pages 50-51

Caribou Falls Block Dam 2 Reconstruction

3min
pages 48-50

Comox Valley Water Treatment Plant

3min
pages 46-47

La Baie Landslide and Embankment Restoration

4min
pages 44-45

Woodworth Dam Optimization

3min
pages 42-43

Port Saint John Westside Modernization

4min
pages 40-41

Transportation Tank Hill Emergency Restoration

4min
pages 38-39

Waaban Crossing

4min
pages 34-37

Vendôme Station Entry and Pedestrian Link

4min
pages 30-31

Centerm Expansion

4min
pages 26-29

Nancy Pauw Bridge

4min
pages 24-25

Million Meals Campaign

4min
pages 22-23

REFAM Argan Predictive Model

4min
pages 20-21

Standing Column Wells for Clé-des-Champs School

3min
pages 18-19

LAC Preservation Storage Facility

4min
pages 16-17

WHY SPECIFY UPONOR?

2min
pages 15-16

K3 Expansion – South Shaft Headframe

5min
pages 12-14

Canadian Consulting Engineering Awards Jury

4min
pages 10-12

2023 CANADIAN CONSULTING ENGINEERING AWARDS / PRIX CANADIENS DU GÉNIE-CONSEIL

1min
page 9

RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER RAHIM AHMAD IS THE 2024 ALLEN D. WILLIAMS SCHOLARSHIP AWARD WINNER

5min
page 7

LEON BOTHAM HONOURED WITH BEAUBIEN AWARD FOR LIFETIME ACHIEVEMENT

3min
page 6

CELEBRATING EXCELLENCE IN THE CONSULTING ENGINEERING INDUSTRY

2min
page 5

Cause for celebration

3min
page 4
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.