INDUSTRY INSIGHT AfriSam is supplying readymix concrete from its Umlaas Road operation, with its Pietermaritzburg facilities as a backup

AFRISAM SUPPLIES RAUBEX

in N3 upgrade

As part of extensive upgrades to one of South Africa’s most vital highways, JSE-listed contractor Raubex Construction is being supplied with construction material by AfriSam, including cement, readymix, aggregate and other quarry material.

R

aubex has been working on a 4 km stretch of the N3 highway, between Dardanelles and Lynnfield Park since January 2021, which will expand the current two-lane road to four lanes in each direction. The N3 between the port city of Durban and the country’s powerhouse of Johannesburg carries heavy traffic volumes that have only increased in recent decades. This project is part of government’s key Strategic Integrated Project focusing on the Durban-Free StateGauteng logistics and industrial corridor. It will improve access to Durban’s export and import facilities, and raise efficiency along this route. According to Abri Lubbe, contracts manager, Raubex, the road contract includes the widening

of four existing bridges and the construction of an entirely new road-over-road bridge structure at the Umlaas Road junction. This new twin-spine bridge over the R603 will allow easier access for both north- and south-bound N3 traffic heading for Richmond.

Bridges

“Work on widening the bridges at the Umlaas and Sunnyvale underpasses has been completed, as has the agricultural underpass,” says Lubbe. “This involved the construction of abutments, the application of precast beams, in situ decks, balustrades and end-blocks.” There is also one road-over-rail bridge that will be extended once the contraflow stage is reached, where traffic is diverted on to one side of the highway to give contractors full access to the other side. Piling for the twinspine bridge The project includes the widening of four existing bridges and the has been construction of an entirely new road-over-road bridge structure

6

IMIESA May 2022

completed, allowing the foundations to progress on this lengthy aspect of the project; work began on this three-span structure in October 2021 and is due for completion by the end of 2023. Thys Greeff, construction manager, Raubex, explains that the contraflow will allow roadwork on the south-bound lanes to begin in earnest, which will include the complete revamp of the existing lanes.

Road construction “We are excavating the existing road by between 1 000 mm and 600 mm, and will fill this with blasted material from AfriSam,” says Greeff. “Depending on conditions, the next level may then comprise a 150 mm capping layer and a 300 mm G6 selected layer. This is followed by a 350 mm stabilised sub-base layer of crushed material.” AfriSam is providing its specialised roadstabilising cement, Roadstab Cement, which is being supplied in 50 kg bags to the Raubex subcontractor who spreads the cement on to the sub-base layer. By the end of the contract, around 180 000 bags will have been supplied, making up some 9 000 t of cement. The road layer will be completed with a 200 mm asphalt layer, comprising a 120 mm EME base, a 40 mm AP-1 interlayer, and a 40 mm bitumen-rubber gap-graded wearing course, says Greeff.


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

Walk-behind roller upgrade sets new standard

3min
page 53

Measuring in a cloud of dust

4min
pages 50-52

Flooring refurbishment at the SAAO

2min
page 49

Perfecting the art of dam wall rehabilitation

4min
pages 47-48

Precast manholes offer value and durability

1min
page 43

extreme weather conditions

1min
page 46

The new and definitive Terraforce Design Guide Consider low-volume concrete roads for

5min
pages 44-45

Home of the Brick

3min
page 42

Resource management key for future growth

2min
page 41

The vital role of retaining wall structures

6min
pages 38-40

Solutions to bring water to our people

3min
page 31

Construction in the cloud

2min
page 26

A study: water security and climate change risks for municipalities

8min
pages 28-30

Linnhoff plant overcomes logistical challenges on Tema road project

4min
pages 36-37

Working towards EPC compliance

3min
page 24

Digital twin solution for AEC practitioners

1min
page 27

Correct cabling specification key for PV installations

3min
page 25

Municipal microgrids promote clean energy and autonomy

5min
pages 22-23

Optimising energy supply and demand

5min
pages 20-21

Infrastructure news from around the continent

4min
pages 10-11

How to reduce future flood damage

5min
pages 18-19

President’s comment

3min
page 7

How the disaster declaration supports local municipalities

6min
pages 16-17

Providing clean water for future generations

8min
pages 12-15

Editor’s comment

4min
pages 5-6

AfriSam supplies Raubex in N3 upgrade

6min
pages 8-9
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.