Construction Planning Workbench (CPW) 2002-056-C

A U S T R A L I A

Objective To investigate the feasibility of automatically generating a draft construction schedule from a 3D building model stored in an IFC database. Building Information Model (3D View)

Draft Construction Schedule (4D View)

CPW

C A R S

CPW Functions Identify building COMPONENTS Associate construction ACTIVITIES Estimate required RESOURCES Derive logical SEQUENCE between construction activities

CPW: a rule-based system A is reinforced concrete beam B is a reinforced concrete slab A is connected to B A and B are constructed together If (X is a reinforced concrete beam) AND (Y is a reinforced concrete slab) AND (X is connected to Y) Then (X and Y are constructed together)

Project Leader: Robin Drogemuller (CSIRO) Email: Robin.Drogemuller@csiro.au

A possible construction sequence when reinforced concrete columns, beams and slabs are erected monolithically: • Place column reinforcement • Place column formwork • Erect scaffolding and formwork for beam and slab • Place beam and slab reinforcement • Pour concrete of column, beam and slab Column reinforcement Column formwork Beam and slab formwork Beam and slab reinforcement Column, beam and slab concrete

CSIRO Ms Fanny Boulaire Mr John Crawford Mr Robin Drogemuller Ms Cheryl McNamara Dr Gerardo Trinidad

University of Newcastle Dr Guillermo Aranda-Mena Dr Rod Gameson Mr Willy Sher Mr Peter Ward

Woods Bagot Mr David Marchant

John Holland Mr Nick Windmeyer

CRC Schedule Viewer

Based on the CRC IFC Viewer CRC for Construction Innovation, 9th Floor, L Block, QUT Gardens Point, 2 George St, Brisbane, Qld, 4000 Tel 61 7 3864 1393 / Fax 61 7 3864 9151 / Email: enquiries@construction-innovation.info