Sheet Index Layout ID
Layout Name
A01
Site Plan
A02
Existing & Demolition Plan
A03
Proposed Plan
A04
Floor Finishes Plan
A05
HVAC Plan
A06
Roof Plan
A07
Electrical Plan
A08
Lighting Plan
A09
Interior Elevations
A10
Interior/Section Elevations
A11
Elevations
A12
Elevations
A13
Sections
A14
Details
Alterations To The Women's Rest Building At: 201 Russell Street South, Hastings
Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Ru ss el ll S tre et So ut h
e rn ou stb Ea st Ea et re St 2000mm high temporary site fencing is to be errected around the site to protect members of the public during demolition & construction work
on nd Ly ad Ro st Ea
N
Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3 1:500
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
333m² SITE PLAN
Sheet No:
A01
Scope of Work Roof 7.02.02
LEGEND Existing walls to remain
Replace all roof claddings & flashings etc. over new Thermakraft 215 roof underlay
VERANDA PLUNKET RECEPTION
PLUNKET OFFICE
Re-pitch flat roof over the Nursery with a new gable roof to match the rest of the building
To be demolished
Re-pitch flat roof over the Baby Change Room with a new membrane roof as per the plans & specifications 2.04.02
Decor
7.02.03
Re-paint the inside of the building Re-paint the veranda barrier stucco & capping etc.
STORE 4
03 D
Re-paint the exterior timberwork of the building repairing minor defects in the stucco as part of the contract Re-paint is to include the front & rear veranda's Glazing to be re-puttied
ENTRY
PLUNKET KITCHEN 2.04.01
7.01.02
THE KATE SHEPPARD ROOM D01
PLUNKET STORE ROOM
2.01.01
Flooring Carpet & vinyl to be replaced throughout the building Decking
2.03.01 STORE 2
Deck boards to be checked rotten and or damaged boards are to be replaced to match existing
2.05.01
HALL 2.05.01
STORE 3
Insulation D02
Install Autex R1.5 under floor polyester insulation Install Autex R3.2 polyester ceiling insulation
2.01.01
7.01.02
Kitchen Cabinetry Remove all cabinetry and sink from the Garden Room
OFFICE GARDEN ROOM
Remove all cabinetry and sink from the Kate Sheppard Room and replace with the cabinetry from the old Plunket kitchen plus additional pantry units as plan
7.01.01 PANIA ROOM
STORE 1
Install new cabinetry into the old Plunket kitchen which is to become the main kitchen for the building
7.01.02
COUNSELLING ROOM
All kitchen areas will require new electrical fittings any existing fittings are to be tested to ensure compliance with NZS
TOILETS 7.02.01
VERANDA
Glazing Re-glaze the top window glass in the Pania Room with clear float glass Reception The reception is to be re-located into the old Plunket Room and Store Room by removing the internal wall from between these two rooms
PERGOLA
Heating
PERGOLA
NURSERY
2.02.02
Remove the old gas heaters from within the building Install reclaimed HVAC system as per HVAC plan Electrical Replace with Switchboard / mains cable concealed entry into the building Lighting
BABY CHANGING
Keynote Legend 2.01.01
Remove door (to be re-used) frame up & gib opening
2.02.02
Remove roof cladding & furrings to leave rafters & ceiling in place
2.03.01
Form opening for re-used door - D03
2.04.01
Form opening for double doors (D01)
2.04.02
Remove wall (non load bearing)
2.05.01
Remove doors (to be re-used)
7.01.01
Remove kitchen units, cap pipework & waste at or below floor level
7.01.02
Remove gas heater, cap pipework
7.02.01
Remove hand dryer
7.02.02
Remove vanity unit, cap pipework & waste at or below floor level
7.02.03
Re-locate kitchen cabinetry to the Kate Sheppard room
Drawn:
Rob Collins
Any electrical cables found in walls being demolished are to be brought to the attention of the contract principal
N
Date:
BD1100
Light fittings are to be upgraded as per the lighting plan
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
EXISTING & DEMOLITION PLAN
333m² Sheet No:
A02
1 A11
Keynote Legend
VERANDA
OFFICE 2
OFFICE 1
5.03.01
New half height walls
DW
New Walls
90
WALL LEGEND Existing walls to remain
5.02.04 D05
5.02.03 5.02.02 KITCHEN
5.02.06 S3 A10
3885
RECEPTION 1 D01
COUNSELLING ROOM 3
5.02.05
ENTRY
S3 A10
THE KATE SHEPPARD ROOM
R G
D02
F
D03
RECEPTION 2
New 25° gable roof over the nursery to match the cladding type of the main building
3.03.02
Re-pitch existing membrane roof with new framing and 17mm CD ply then clad with 1.5mm EPDM
3.03.03
New gable wall clad with cedar shingles to match the existing gable walls
3.03.04
Existing rainwater heads & downpipes
4.01.02
Change glazing panels at top of windows to clear float glass
5.01.01
Use H3 battens @ 450 max ctrs (over dpc) sized accordingly to cover pipework & line with 10mm gib aqualine
5.02.02
New cupboard unit (lockers)
5.02.03
New kitchen units
5.02.04
New tall units to match re-located units as closey as posible - See interior elevations
5.02.05
Kitchen units re-located from kitchen
5.02.06
New reception counter
5.02.07
Pantry cupboards
5.03.01
Re-hang door to opposite hand
7.01.01
Upgrade switchboard
3285
5.02.07 90 HALL
STORE
3.03.01
7.01.01
5.01.01 OFFICE 3 GARDEN ROOM 4.01.02
PANIA ROOM
2 A12
COUNSELLING ROOM 2
COUNSELLING ROOM 1
2 A11
TOILETS 4.01.02
VERANDA
PERGOLA
Supply and install Insulation to ceilings and underfloor Autex R1.5 under floor polyester under floor insulation Autex R3.2 polyester ceiling insulation
PERGOLA
S1 A14
6410 NURSERY
4100
S1 A14
3.03.01
3.03.03 BABY CHANGING
3.03.04 3.03.02
N S2 A13
1 A12 Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
PROPOSED PLAN
333m² Sheet No:
A03
Office 2 A: 21.59 m2 Carpet tiles
Office 1 A: 17.14 m2 Carpet tiles
Counselling Room 3 A: 7.72 m2 Carpet tiles
Reception A: 12.76 m2 Vinyl
Kitchen A: 14.72 m2 Vinyl
A: 33.37 m2 Carpet tiles
Store
A: 20.27 m2 Vinyl
A: 9.13 m2 Carpet tiles
Toilet
Hall 2 A: 10.88 m2 Vinyl
Garden Room
A: 1.94 m2 Vinyl
The Kate Sheppard Room
Hall 1
Reception 2 16 A: 12.08 m2 Carpet tiles
Entry A: 8.50 m2 Vinyl
Counselling Room 1
A: 19.39 m2 Carpet tiles
Office 3 A: 14.48 m2 Carpet tiles
Pania Room A: 32.77 m2 Carpet tiles
A: 15.90 m2 Carpet tiles
Counselling Room 2
Toilets
A: 9.09 m2 Carpet tiles
A: 14.03 m2 Vinyl
Nursery A: 23.62 m2 Carpet tiles
Baby Changing A: 5.95 m2 Carpet tiles
N
Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
FINISHES PLAN
333m² Sheet No:
A04
AC2-ODU
AC2-floor console
EX
EX Hi wall
TS FH
Ø200 flexi
AC2
Mitsubishi electric floor console split MFZ-KA35 3.5KW New
AC3
Mitsubishi electric hi wall split MSZ-GE25 2.5KW New
EX
Existing split systems - Retained
FH
PDL thermostat fan heater 2KW surface wall mounted model 3304 WH with surface mount kit
TS
PDL digital timer switch model 646E7
Grilles & Diffusers A Ø200 flexi
A
Ø200 flexi
Ø200 flexi
TST
Supply diffuser Holyoake 100 l/s ECO-SA-ZOO
B
Return grille Holyoake 175 l/s EC125 RC 300x300
C
Outdoor air inlet Holyoake 75 l/s RLW-L-RC 250x200 (white)
Dampers in duct branches
B Ø250
TS FH
EX Hi wall
A
A
Ø250 solid
Ø250 solid B
EX
Daikin ducted split FDYQ100KAV1 10KW Client supplied
Heaters
A
Oven rangehood by others
AC1
TS FH
AC1 Ø300 flexi
Flexi ducting Ceiling diffuser
B Ø300 flexi
A
Ø200 flexi TS FH
Ø200 flexi TS FH
Outdoor air inlet
Ø150 flexi
Ø300 flexi
A
C
Ducted unit mounted in roof space, access to install in conjunction with construction of new roof over nursery
AC1-ODU
AC3-ODU
Hi wall AC3 Outdoor units mounted in garden on concrete pad with galvanised pipe & mesh security enclosure
Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
HVAC PLAN
333m² Sheet No:
A05
15o
15o
25o
25o
o
15
4 A14
4 A14
Dektite flashing in the diamond formation over cooker hood extract
15o
S3 A10
Re-roof existing building with selected 0.55 bmt coloursteel corrugated roof cladding Roof cladding fixing pattern is: Hit 1, miss 1, hit 1, miss 2……. Thermakraft 215 self supporting roof underlay 0.55bmt coloursteel corrugated longrun roof cladding 0.55bmt flashings to valleys and ridge/hip
25o
10o
S3 A10
10o 25o
25o
25o
25o
25o
25o
25o
S1 A14
S1 o
o
25
3o
25
New 25° gable roof over the nursery to match the A14 cladding type of the main building 25x1mm tensioned roof strap bracing Roof trusses @ 900mm max ctrs over existing rafters & ceiling 70x45 H1.2 purlins - end spans 600mm max then intermediate spans 900mm max Thermakraft 215 self supporting roof underlay 0.55bmt coloursteel corrugated longrun roof cladding 0.55bmt flashings to valleys and ridge/hip New spouting & downpipes connected to existing Use existing rainwater heads & downpies from flat roof Re-pitch existing membrane roof with H3.1 framing over existing and 17mm CD ply & 1.5mm EPDM membrane
N
S2 A13 Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
ROOF PLAN
333m² Sheet No:
A06
2 0.4
2 0.4
2 0.4
2 0.4
VERANDA
OFFICE 2
OFFICE 1
0.4 2
2 0.4
0.4 2
RECEPTION 1
0.4 2
COUNSELLING ROOM 3
ENTRY
2 1.2
0.4 2
KITCHEN 2 1.
THE KATE SHEPPARD ROOM 2 1.
RECEPTION 2
HALL
STORE
2 0.4
2 0.4
OFFICE 3 Upgrade switchboard
GARDEN ROOM
PANIA ROOM COUNSELLING ROOM 2
COUNSELLING ROOM 1
TOILETS VERANDA
Data & telephone cabling is to be carried out by HDC nominated contractor who is to be informed whenever any data or telephone cabling is required to be installed, removed or altered
PERGOLA
PERGOLA
NURSERY
BABY CHANGING
N
Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
ELECTRICAL PLAN
333m² Sheet No:
A07
B
B B
C
C
1.2
B
1.2
C
1.21.2
1.2
B B
B
B
B
B
B
1.2
B
B 2 1.
B B
A
A
A 1.2
1.2
1.2
B
C
A
1.2
1.2
1.2
B
1.2
C
B
C
B B
B
B
1.2
C
1.2
B Data & telephone cabling is to be carried out by HDC nominated contractor who is to be informed whenever any data or telephone cabling is required to be installd, removed or altered
Symbol
Description
B
PIR15A
B C
Description
B
C
1.2
B
B
1.2
1.2
B
1.2
B
B
B B
C
Symbol
B
B
B 1.2
Circuit wiring. Motion sensor.
PIR15A
B
Switch 2-way. Switch.
Fluorescent light T5
B
Twin 1500mm T5 luminaire
Weatherproof bulkhead
C
28w 2D 4000k
Recessed LED downlight
A
11w 3000k
Drawn:
Rob Collins
N
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
LIGHTING PLAN
333m² Sheet No:
A08
DW
3
4
Fridge
Cooker & hood
1
2
G
R F D03
1:50
Interior Elevations - Kitchen
Lockable
1:20
1
1:20
2
Lockable
Dishwasher
Lockable
1:20
3
1:20
Drawn:
Rob Collins
Lockable
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
4
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
INTERIOR ELEVATIONS
333m² Sheet No:
A09
1120 1800
1:20
Section S3
1
A03
New tall units to match re-located units as closely as possible
Re-located cabinets, benchtop & sink from kitchen
1:20 Drawn:
Rob Collins
1:50
1 Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
Interior Elevations - The Kate Sheppard Room
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
INTERIOR ELEVATIONS & SECTION
333m² Sheet No:
A10
Existing ramp access
1:100
North Elevation A03
New 3° membrane (1.5mm EPDM) roof over Baby changing room New 25° gable roof over Nursery
1:100
East Elevation A03
Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
333m²
PROPOSED ELEVATIONSSheet No:
A11
New 25° gable roof over Nursery New 3° membrane (1.5mm EPDM) roof over Baby changing room
1:100
South Elevation A03
New 3° membrane (1.5mm EPDM) roof over Baby changing room New 25° gable roof over Nursery
1:100
West Elevation A03
Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
333m²
PROPOSED ELEVATIONSSheet No:
A12
0.55bmt Coloursteel corrugated roof cladding Thermakraft 215 self supporting roof underlay 0.55bmt corrugated coloursteel roof cladding Thermakraft 215 self supporting roof underlay
H3.1 molding to match existing 180x30 H3.1 barge board
H1.2 roof trusses @ 900 max ctrs by registered truss manufacturer
H3.1 tongue & groove "V" joint match boarding Louvered vent made to match the louvers on the existing gables
5 Existing roof
Block in between rafters if not done
Cedar shingles
A14
H3.1 tongue & groove "V" joint match boarding to match existing Cornice molding on top of louver to match existing
EPDM membrane
New H3.1 17mm ply fascia board
Existing rafters & ceiling with new Autex R3.2 polyester ceiling insulation Louvered vent made to match the louvers on the existing gables 100x45 H3.1 framing on edge well fixed to gable truss to give the overhang to match existing Gable truss Autex R1.5 under floor polyester insulation
Cedar shingles sized to match the existing gables fixed to the H3.1 battens with 50mm stainless steel flat head nails
20x45 H3.1 battens
1:50
Cut curved shaped pieces of 45mm H3.1 framing to match the curvature of the existing gables
Section S2 A03
NOTE:
H3.2 furring pieces @ 400 max ctrs fixed to existing substrate to form the 3° pitch New 1.5mm EPDM membrane New 17mm H3 CD ply Existing gutter formation to be stripped back to substrate & re-lined with EPDM
H3.2 furring pieces @ 400 max ctrs fixed to existing substrate to form the 3° pitch New 1.5mm EPDM membrane New 17mm H3 CD ply
Existing substrate to be checked by HDC engineer representative once existing membrane has been removed
New fascia board
Existing rafters & ceiling with new Autex R3.2 polyester ceiling insulation Existing soffit Existing stucco Existing timber window
1:10 Drawn:
Rob Collins
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
Section
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
Plan Name:
333m² Sheet No:
A13
Upper roof underlay lapped over flashing
mm 250
0.55bmt change of pitch flashing
m 130m
0.55bmt corrugated coloursteel roof cladding Thermakraft 215 self supporting roof underlay
m 10m
Soft lead edge pressed into troughs
25°
450
Hem along top edge of flashing
H3.1 tongue & groove "V" joint match boarding Reduced purlin to fit over match boarding
Quarter round continuous spouting to match existing
Roof structure
15°
1:10
H1.2 roof truss 70x45 H1.2 purlins @ 600 max ctrs to end spans then 900 ctrs to intermediate spans Solid blocking between trusses
Change of Pitch
4 Exposed 120x45 H3.2 rafter extensions lapped 450-500mm nailed with pairs of 100x3.75 galvanised hand driven nails @ 100mm ctrs to roof trusses
Existing rafters & ceiling with new Autex R3.2 polyester ceiling insulation
Thermakraft 215 self supporting roof underlay continuous over ridge Ridge flashing Soft lead edge pressed into troughs 150
450
1:10
Eaves
2 A14 0.55bmt corrugated coloursteel roof cladding
450
1:10
Thermakraft 215 self supporting roof underlay
Ridge/Hip
H1.2 roof trusses @ 900 max ctrs by registered truss manufacturer
70x45 H1.2 purlins @ 600 max ctrs to end spans then 900 ctrs to intermediate spans 0.55bmt corrugated coloursteel roof cladding H3.1 tongue & groove "V" joint match boarding
Overall valley gutter width 250mm min
Quarter round continuous spouting to match existing Exposed 120x45 H3.2 rafter extensions lapped 450-500mm nailed with pairs of 100x3.75 galvanised hand driven nails @ 100mm ctrs to roof trusses
Clearance between roofing 50mm min 80m mm in
Existing rafters & ceiling with new Autex R3.2 polyester ceiling insulation
Existing stucco
20mm min 50mm min
Existing wall framing Autex R1.5 under floor polyester insulation
Solid support for valley gutter Roof underlay continuous under gutter if copper treatments are used
1:10
Valley
5
1:50 Drawn:
Rob Collins
1 A14
in mm 80m
Date:
BD1100
25-07-2014
Scale:
1:100 @ A3
Job No:
Job Name:
Section S1
WOMENS REST BUILDING 201 RUSSELL STREET SOUTH, HASTINGS
A03
Plan Name:
SECTION & DETAILS
333m² Sheet No:
A14