Proceedings Tuesday 12th April

Page 1

Proceedings for the 16th North Sea Offshore Cranes & Lifting Conference 12th ‐14th April 2011 Stavanger, Norway. Remember to check our web site www.liftingoffshore.com it will be continuously updated for next years conference in Aberdeen 24th – 26th April 2012


Table of Contents, Wednesday 13th April th Heavy Lifting in 2,500 m water depth, Henk de Boo van Uijen, Design, construction and commissioning of a heavy lift offshore crane, Arjo van Putten, Flexible load handling solutions for multi purpose vessels, Tønnes Seierstad

Wednesday 13 April

Page 3 Page 27 Page 76

New risk based bolt maintenance procedures – improved reliability/reduced life cost of offshore cranes, Rod Corbett Special engineered bolts for critical joints in the lifting industry, Ragnar Sandve Lifting and handling remote monitoring and diagnostic solutions, Aaron J. Spak W A RFID inspection system the new Crosby Quic ‐ Check, inspection and identification system , Frédéric Crynen Temporary lifting facilities for the BP Magnus crane replacement, Gordon Mccombie

Page 95 Page 120 Page 143 Page 169 Page 192

Mob‐boat handling with offshore cranes – combination of design parameter Tor Raknestangen Training & competence in crane transfer operations; the importance of being prepared, David Brittan Lifting persons with carriers suspended from offshore cranes application of European commission guidance document, Gunnar Matre

Page 227

Reception given by the municipality of Stavanger in the Stavanger Maritime Museum Local beer tasting program with small tapas

Page 324

Page 246 Page 297


Program Monday 11th April 12:00 Rigging of stands/booths at Stavanger Forum From 14:00 check‐in Rica Forum Stavanger hotel 15:30 Surprise tour with bus from Stavanger Forum 18:00 Meeting in the Organising Committee, meeting room “Feistein” 20:00 Get together at Rica Forum Restaurant 21st floor Remember to check our web site www.liftingoffshore.com it will be continuously updated with photos and program changes


Program Tuesday 12th April Morning session Chair: Svein Anders Eriksson ‐ 09:30 Welcome to Stavanger! Sissel Knutsen Hegdal, Stavanger city ‐ 09:40 Opening address Øyvind Tuntland, Petroleum Safety Authority Headline; Regulatory/Safety ‐ 10:00 OMHEC Update, Arnold V. de Groot ‐ 10:15 HSE focus, Iain Paterson ‐ 10:35 Coffee / CraneExpo


Todays program Tuesday 12th April Headline: Regulatory/Safety ‐ 11:05 Perspectives; What could we learn from an incident Arnold V. de Groot ‐ 11:25 PSA focus, Svein Anders Eriksson ‐ 12:00‐13: 00 Lunch / CraneExpo Remember to check our web site www.liftingoffshore.com it will be continuously updated with photos and program changes


Speaker

Sissel Knutsen Hegdal, Chair of Local Board for Culture and Sport, Stavanger Municipality


Speaker

Øyvind Tuntland, Director professional competence, Petroleum Safety Authority, NO


Opening address The 16th North Sea

Offshore Cranes and Lifting Conference 12h – 14th April 2011

Øyvind Tuntland Director professional competence PSA Norway

Oyvind.tuntland@ptil.no www.ptil.no

PTIL/PSA


Status NCS - spring 2011 All installations: Incidents in degree of seriousness “red" and “yellow"

200

35,0

“Red" incidents “Yellow" incidents Million working hours

30,0 25,0

150

20,0 15,0

100

Million work hours

250

No. of incidents

• From 2000 to 2005, a 75 % reduction in yellow and red lifting incidents was achieved by the industry • No fatalities for the last six years

10,0 50 5,0 0

0,0 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004

26.04.2011 PTIL/PSA 2


Overall trend – new developments (?) All installations: Incidents in degree of seriousness “red" and “yellow" 250

“Red" incidents “Yellow" incidents Million working hours

200

35,0 30,0 25,0

150

20,0

100

15,0

Million work hours

Since 2007 the number of lifting incidents with a high potential for serious injury to personnel and to property have increased

No. of incidents

Where does it end if the new trend is not stopped?

10,0 50 0

5,0 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004

0,0

?

? ?

According to some major operators, about 80 % of the lifting incidents are related to lifting operations in the drilling area 26/04/2011 PTIL/PSA 3


One (very) recent incident to illustrate the new trend • A slip joint was in the process of being lowered from vertical to horizontal position at the catwalk. • The bails were forced 45 degrees against the elevator link blocks which broke, hence the bails were forced further out of the lifting lugs of the elevator. • The slip joint (weighing 23 tonns) fell approx. 4 meters. • The slip joint first hit the load rest. The riser spider, before falling to the drill floor, fell against the drillers cabin before stopping. PTIL/PSA


Center latch elevator incident consequences • The load rest to the left of the slip joint was hit and jumping directly towards the signaller (flagman/lift leader) before it hit the tongue post, changed direction and stopped • Actual consequences were material damages only • Potential consequence could have been a fatality PTIL/PSA


What is common to the drilling lifting incidents? • Poor identification of operational hazards • Poor design, i.e. the special drilling lifting gear is not inherently safe and needs to be improved to meet modern safety standards • Difficult or impossible to verify correct locking • User information poor or not present • The lifting tools are not identified as lifting equipment and treated as such (planning, inspection, certification, maintenance) • Poor planning management and supervision • Some of the special drilling lifting gear have been designed and manufactured in accordance with API 8C, now EN ISO 13535

PTIL/PSA


The industry challenge… • All elevators should be made inherently safe by design • Harmonized standards should be developed for all drilling lifting tools based on the principles of EN ISO 12100 1&2 o The work of CEN TC 147 WG 21 for updating of EN 13155 to include manual and mechanically operated elevators is very promising

• Remote controlled elevators (mechanical) should be used for lifting of all sizes of conductors

PTIL/PSA


The industry challenge … • All special lifting equipment (hoisting tools) in the drilling area must be identified • The operator and drilling contractor must establish a safe system of work and make sure the drilling hoisting tools satisfy regulatory requirements for lifting equipment • A systematic review and risk analysis should be carried out for all special drilling lifting equipment • The special lifting equipment should be modified or changed out according to the results from the analysis PTIL/PSA


Let the good safety initiatives grow!

I wish you a good conference! PTIL/PSA


Speaker

Arnold V. de Groot, Inspector Operations, State Supervision of Mines (SSM), NL & Chairman of OMHEC


Arnold de Groot Senior inspector SSM OMHEC Chairman

Stavanger 12-4 2011


Guidance! On:  Safety  Exchange of information  Harmonizing  Documents  NSOAF Members; UK, Norway, Denmark, the Netherlands. Regulators, industry and Classification societies.


OMHEC guidance documents    

OMHEC guidance on communications. OMHEC guidance for training standard. OMHEC maintenance guidance document. OMHEC standard for enterprise of competence.

Present OMHEC workgroups  Mapping of regulations on MOU’s.  Lifting of Personnel offshore.  Material handling in the drilling area.


Material handling in the drilling area


Why????? The battle for safe lifting?

Be aware and do not get caught by surprise!


Don’t get caught by routine!


Fort Eben Emael, Belgium 1939 Eben Emael was a giant fortress.

17 bunkers from various types. Total firepower: 2100 kg. a minute. An impressive piece of Belgium defense. Inside this fortress, 60 meter under the top, underground barracks for 1.200 soldiers. Military experts from various countries agreed that this fortress was one of the strongest in Europe.

To concur this fortress was impossible!


The fall Underpunkter

• Guess how much time the Germans needed to get control of the fortress? • Answer: 15 minutes and a crew of 71!


The fortress strength was its weakness! To convinced of their own strength (laid-back). Design based on WO I. No studies or analyzes on new threads. Artillerists not trained for man to man battle. The bottom line was that the fortress failed on organization, technology and human skills.

The fortress was NOT sound!


Know your weak spots! Integrity is not about your strength but about knowing your weak links! Be aware and do not get caught by routine!


Lifting operations are like good sex; It should never be a routine!


Guidance by www.OMHEC.org


Speaker

Iain Paterson, Health and Safety Executive HSE, UK


HSE regulatory perspective Iain Paterson Team Leader – Materials & Mechanical Engineering Offshore Division Health & Safety Executive iain.paterson@hse.gsi.gov.uk

16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and LiftingŠTalisman Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


Immediate enforcement action

Prohibition Notice Remove persons from the ‘danger area’ during lifting operations

16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


Enforcement action Prosecution of Talisman HSW S3 £225,000 fine Prosecution of Scaldis HSW S3 £18,750 fine 23 September 2010 16th North Sea Offshore Cranes and Lifting Conference


www.hse.gov.uk

16th North Sea Offshore Cranes and Lifting Conference


Load testing

16th North Sea Offshore Cranes and Lifting Conference


Load testing

16th North Sea Offshore Cranes and Lifting Conference


Final thought ‌.. The review of the broader issues surrounding the loss of RAF Nimrod MR2 aircraft XV230 in Afghanistan in 2006 by Charles Haddon-Cave QC

17.24 PowerPoint can, however, be dangerous, mesmerising, and lead to sloppy (or nil) thinking�

16th North Sea Offshore Cranes and Lifting Conference


Speaker

Arnold V. de Groot, Inspector Operations, State Supervision of Mines (SSM), NL & Chairman of OMHEC


What could we learn from an incident with a snubbing unit? A.V. de Groot Senior Inspector State Supervision of mines 12 -4 2011

16th North Sea Offshore Cranes and Lifting Conference


Safe lifting after Macondo

Why do we still need focus on lifting? 16th North Sea Offshore Cranes and Lifting Conference


Risk = probability x consequences Low risk estimate?

probability >

consequences > 16th North Sea Offshore Cranes and Lifting Conference


 A satellite platform (Dutch sector) / 9 May 2010  Connected with Seafox 4 > 100 personnel on board  well work over / hydraulic snubbing unit  miss operation / 50m tubing blows out life well  tubing penetrates two deck levels and snapped off a two inch nozzle on a gas riser  3000 Nm3 released in 90 minutes 16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


16th North Sea Offshore Cranes and Lifting Conference


Failed barriers: Design (was not fail safe), Equipment maintenance, Management of change, Procedures, Planning (and preparation for emergencies), Competence assurance , Supervision.

16th North Sea Offshore Cranes and Lifting Conference


Risk = probability x consequences

The snubbing risks were identified but: Low probability, severe consequence scenarios should have triggered more mitigation and controls (including Emergency Response). Snubbing operations on a live well were treated as routine operations. 16th North Sea Offshore Cranes and Lifting Conference


Lifting over life process


Lifting over life process


Personal safety versus process safety

Will your process be safe by wearing a hard hat? 16th North Sea Offshore Cranes and Lifting Conference


Maintenance

Competence

Focus on your primary process! 16th North Sea Offshore Cranes and Lifting Conference


LTI as indicator for safety on the installation? Ask for backlog on preventive maintenance and the amount of curative work orders! The best contribution to real safety is to perform your job perfect!

Your equipment in perfect condition, perfect level of competence an planning. Resulting in a perfect (Safe) execution. 16th North Sea Offshore Cranes and Lifting Conference


Questions?

www.sodm.nl 16th North Sea Offshore Cranes and Lifting Conference


Speaker

Svein Anders Eriksson, Discipline leader, Petroleum Safety Authority, NO


PSA focus The 15th North Sea

Offshore Cranes and Lifting Conference 27h – 29th April 2010

Svein Anders Eriksson Discipline leader Logistics and Emergency Preparedness, PSA Norway

svein.eriksson@ptil.no www.ptil.no

PTIL/PSA


PSA focus based on NSOAF lifting audit results

2. Manangement of lifting operations

4. Training and competence 3. Risk assessment 1. Planning, selection and control of equipment

5 Supervision

26.04.2011 PTIL/PSA 2


Industry and regulatory focus is still needed on ---

Drilling lifting equipment

26.04.2011 PTIL/PSA 3


Some drilling hoisting tools ‌

PTIL/PSA


What is common to the drilling lifting incidents? • Poor identification of operational hazards • Poor design where the drilling lifting gear were not inherently safe and needed to be improved to meet modern safety standards • Most of the drilling lifting gear have been designed and manufactured in accordance with API 8C, now EN ISO 13535

PTIL/PSA


Safe design of machinery EN ISO 12100 part 1&2 (safe design of machinery) Lack of general principles for safe design are root causes for accidents and incidents Lack of information to exposed persons

“Swiss cheese” model

Lack of inherently safe design measures Accidents and incidents

Lack of technical protective measures Other issues PTIL/PSA


One challenge – non-harmonized standard: EN ISO 13535 • As a result of the shortcomings of ISO 13535 (former API 8C) and the findings during our past and current investigation, PSA has launched an international market surveillance program on manually operated elevators made according to EN ISO 13535 • This program is supported by DEA in Denmark, HSE in the UK and SMM in the Netherlands

PTIL/PSA


DNV study for PSA • Det Norske Veritas AS (DNV) has been requested by PSA to perform an evaluation of the locking mechanism on some manually operated side door elevators. • DNV concluded that the locking mechanisms with “safety pin” did not give sufficient risk reduction effect compared to inherently safe design measures. Hence, the elevators do not fulfil the principles of safety integration given in Annex I part 1.1.2 in the Machinery Directive 98/37/EC.

PTIL/PSA


Workshop Brussels 22 March 2011

PTIL/PSA


The needs for standards from a regulatory authority’s point of view • • • •

To set the level of safety in standards To allow for a goal setting approach To cover developments in technology To provide predictability for enforcement from regulators and for industry • To encourage safety by compliance on a voluntary basis and to incorporate best practices

Workshop Brussels 22 March 2011

PTIL/PSA


CEN TC147 Crane safety TC147

WG22 Manipulating devices

WG21 Non fixed attachments

WG20 Hand operated cranes

WG19

WG18 Loader cranes

WG17 Winches and hoists

WG16 Floating cranes

WG15 Offshore cranes

WG14 Bridge and gantry

WG13 Slewing jib cranes

WG12 Tower cranes

WG11 Mobile cranes

WG1 Terminology and harmonisation WG2 Crane Safety – Design ‐ General WG3 Crane Safety – Design – Requirements for equipment WG4 Crane Safety – Requirements for health and safety WG5 Crane Safety – Requirements for inspection and safe use

26 April 2011 Workshop on

PTIL/PSA 11


The way forward sofare in CEN • The Machinery Working Group of the EU Commission has given CEN TC 147/WG 21 “Nonfixed load lifting attachments” a mandate to establish a harmonized standard for elevators • Such requirements could be incorporated into EN 13155:2003/A1:2005, Cranes - Non-fixed load lifting attachments, last cited in OJ C 336 (2005-12-31).

PTIL/PSA


Possible strategy to develop a Cstandard for elevators 1)

Start with EN ISO 13155 (Harmonised C‐standard for similar products)

2)

Use existing ANSI/API 8C/ISO 13535‐2002 for identification of basic global requirements for such products

3)

Identify requirements that possibly could had prevented recent incidents and accidents

4) 5)

Apply the MD ESHRs through EN ISO 12100‐1 and ‐2 (A standard on machine safety) and identify requirements for elevators by risk assessment Amend EN ISO 13155 to adress elevators with requirements from 2) , 3) and 4), including hazard list and verification methods PTIL/PSA


If harmonised standards like EN ISO 12100 part 1&2 are not followed, the risk of damage to personell, fatalities or major accidents and are higher

PTIL/PSA


Safer products = less risk The key to safe drilling hoisting tools

Presumption of comformity

Compliance with EHSRs

PTIL/PSA


PTIL/PSA


Program part two Tuesday 12th April Afternoon session Chair: Iain Paterson Headline; IMPROVEMENTS AND NEW TECHNOLOGYY

13:00 Case Study – Use of real time crane simulator for presimulation and training, Bård E. Bjørnsen 13:30 Design, construction and operation of offshore cranes for the wind turbine installation market, Michiel Mol 14:15 Coffee break / CraneExpo 14:45 Re‐evaluation of dnv simplified formulae for crane tip motions, Xiaoming Gu 15:30 Improved safety in bulk operations offshore, Jon Olav Kopperstad 16:10 End of day one with closing remarks, questions and reflections


Speaker

Bård E. Bjørnsen Ship Manoeuvring Simulator Centre AS


Case Study: Use of real time crane simulator for presimulation and training for Technip Ekofisk HPS Installation Authors: Bård E. Bjørnsen, Ship Manoeuvring Simulator Centre AS André Eilertsen, Technip NO Knut Johan Nedrelid, Technip NO

The 16th North Sea OFFSHORE CRANES & LIFTING CONFERENCE Stavanger 12th – 14th April 2011


Contents • • • • •

Introduction to the Project Challenges due to the HPS Footprint Description of the SMS Simulator Presimulation, Training and Offshore Installation Summing up

2


Introduction to the project Project background HPS weight and dimensions Installation vessel Skandi Arctic

3


Project background ► Project background

• • • •

Ekofisk 2/4VA SSWI Project – HPS & SPS Installation Part of the Greater Ekofisk Area Development Project Operator/Client: ConocoPhillips Waterdepth: 78m

Ekofisk

4


HPS weight and dimensions ► Host Protection Structure (HPS)

• Dry weight incl. rigging and water filled top frame = 210.0 [Te] • Submerged weight: 140.0 [Te] • LxBxH = 31.2x31.2x9.5 [m]

5


Installation vessel Skandi Arctic ► Skandi Arctic – main dimensions

• Length over all: • Length BP: • Breadth:

156.9 [m] 137.7 [m] 27.0 [m]

6


Challenges due to HPS footprint Crane capacity and lifting height Sea fastening arrangement Deck handling during overboarding

7


Crane capacity and lifting height ► Crane capacity

• Minimum required radius for overboarding: 24.0 [m] • Static weight of HPS close to the crane capacity

8


Crane capacity and lifting height ► Rigging design

• 10Te crane block must be landed on deck • Lifting height at R = 24.0m did not allow slings long enough to connect rigging besides HPS • Solution: remove minimum 2 off hatches and lower hook/slings through roof of HPS • Final decision to remove 4 off hatches for increasing weather criterion to Hs,ops = 2.0m • Dry weight of structure (water filled): 180.0 Te

9


Sea fastening arrangement Outriggers

HPS Structure

VLS

T1

T2

T3

SPS Structure

HPS roof hatches 10


Sea fastening arrangement ► Design of outriggers

• Outriggers extending 8.5m outside vessel port side • Designed to withstand impact with waves over entire length during transit • Lifting height further reduced due to height of outriggers/grillage

11


Deck handling during overboarding ► Use of crane tugger winches

• Primary tool for controlling the overboarding • Not possible to utilize from lift-off position due to: - HPS top frame located too close to crane pedestal - sheaves being fixed (no swivel)

12


Deck handling during overboarding ► Use of crane tugger winches

• Structure should be square to crane boom for crane tuggers to be effective • Safe distance between HPS top frame and crane pedestal • Plan for lifting the structure into this position in a controlled manner?

13


Deck handling during overboarding ► Use of crane tugger winches

• Solution: use of 4.0m high bumpers to rotate the structure around one leg • Lift HPS 3.0m off deck, rotate/boom out to R = 24.0m • Take up slack in crane tuggers before lifting HPS to 5.0m off deck and out of bumpers

14


Deck handling during overboarding ► Bumpers for rotation of HPS

• Height of bumpers: 4.0m • Marking applied at 3.0m as visual reference for crane driver during rotation/boom out • Bumpers located in the middle between overtrawlable fins/mudmat supports

15


Deck handling during overboarding ► Use of tagging towers

• 3 off tagging towers included as contingency for overboarding • T1 used to initiate rotation of structure, and as hold-back until crane tuggers tensioned • For the remaining part of the overboarding, T1-T3 used only to follow the load

16


Description of the SMS Simulator Ship simulator Crane simulator Relevant projects

17


3 full mission Ship Simulators

18


2 Crane simulators

19


Training courses • Plattform crane • Subsea crane • Joint crane and ship simulation training

20


Crane simulator control room; Instruction, Engineering and Communication

21


Deck Operator

22


Subsea lifting operation training course

23


Technip – Presimulating lift off ”tie-in spool piece”

24


Simulator model

25


Presimulation, Training and Offshore Installation

Simulator pictures Installation pictures Lesson learnt

26


Connection of rigging to crane block •

Crane block lowered through roof of the structure with 1 off crane tugger attached

• Crane block lowered through roof of the

structure with 1 off crane tugger attached

• Crane tugger reconnected to HPS top frame by use of man riding basket

27


Overboarding step 1 • Lift HPS to 3.0m above deck • T1: take up slack

28


Overboarding step 2 • Rotate HPS around aft STBD leg/boom out to R = 24.0m • T1: follow the load • Take up slack in crane tuggers

29


Overboarding step 3 • Lift HPS to 5.0m above deck and out of bumpers • Adjust orientation of HPS with crane tuggers

30


Overboarding step 4 • Slew the crane at constant radius • Start taking up slack with T2 once leg is clear of the crane pedestal

31


Overboarding step 5 • Slew the crane at constant radius • Follow the load with T1 and T2

• Slacken off T1 before wire interferring with the crane pedestal • Follow the load with T2 and T3

32


Overboarding step 6 • Structure 90° to vessel side in position for lowering through the splash zone

33


Lowering through splash zone • Crane tuggers kept tensioned until structure in the water

• Crane tuggers slackened off

34


Lessons learned from simulator exercises • Familiarising crane driver/deck foreman with the project -> feedback • Optimize position for winches and tagging towers on deck • Visualisation useful for detection of clash/snag points • Video presentation for information and briefing purposes

35


In addition: Test lift during mobilisation ► Test lift with all wires connected

• Familiarisation of crane driver and deck crew • Final check to ensure no clash/snag points • Good to use video for discussion and briefing/familiarisation of crew

36


Summing up

37


Summary ► Training and familiarisation

• • • • •

Simulation is real time and reasonable realistic, Simulation is valuable tool for understanding and planning the job Simulator training is a first approach for familiarisation On board Test lift is important for familiarisation of deck crew Simulator Visualization/video is of great value for briefing personnel onboard

38


Thank you!

39


Speaker

Michiel Mol, Expert Engineers, GustoMSC, NL Background: Technical University Delft, Faculty of Mechanical Engineering, Specialization in Transport Technology, Graduated (Masters) May 1998. Present occupation GUSTOMSC, Schiedam, Product Development Department, expert engineer. Involved in Wind Turbine Installation Cranes, Pipe Laying Systems, Heavy Lifting Equipment, J‐lay systems, Offshore removal transport. Presentation: Design, Construction and operation of offshore cranes for the wind turbine installation market


GustoMSC Design, Construction and operation of offshore cranes for the Wind Turbine Installation market

Michiel Mol The 16th North Sea Offshore Cranes & Lifting Conference Stavanger, 12th April 2011


Equipment for offshore Wind Turbine Installation

Goal of Presentation Introduction to Offshore Wind Equipment for offshore WTI Integrated design Developments Please ask

page 2


Equipment for offshore Wind Turbine Installation Contents of presentation     

GustoMSC Offshore WTI Crane & vessel design Developments Conclusion

page 3


SBM Offshore Group

SBM Offshore NV GustoMSC (501)

Schiedam SBM Malaysia (280)

Monaco Houston SBM- Atlantia (736)

SBM Group Operations Office / WW (2141)

Kuala Lumpur

Total number of employees: over 5100 representing 38 nationalities

page 4


GustoMSC cranes                       

SSCV Hermod, Heerema (5,000 + 4,000 t) * HLV Oleg Strashnov, Seaway Heavy Lifting (5,000 t) - 2011 DCV Balder, Heerema (4,000 + 3,000 t) *, incl. fly-jib DPV 7500, COOEC (4,000 t) - 2010 SSCV DB 101, McDermott (ex-Narwhal, 3,500 t) * DB 52, McDermott (ex-Thor, 2,000/3,000 t) * Titan 1, 2*, 3 and 4 (600/800 t) Stanislav Yudin, Seaway Heavy Lifting (2,500 t) * Ispolin (1,200 t) Kuroshio (2,500 t) * Daiichi Yutakago, Moricho (1,500 t) Svanen, Ballast Nedam (8,200 t) * Swing Thompson (1,200 t) Pacific Horizon (1,000 t) * MPI Adventure (1,000 t) - 2011 MPI Discovery (1,000 t) - 2011 Wind Lift 1, BARD (500 t) - 2009 ARB-3, Saudi Aramco (550 t) - 2010 Brave Tern, Fred. Olsen Windcarrier (800 t) - 2012 Bold Tern, Fred. Olsen Windcarrier (800 t) - 2012 Seajacks Zaratan, SEAJACKS (800 t) - 2012 NG-9000C-HPE, Drydocks World (800 t) - 2012 Sea installer, A2SEA (800 t) - 2012

Tomorrow presentation!

page 5


GustoMSC Construction units Wind Turbine Installation Exploration

Construction

Production Jack-up

Semisubmersible

Vessel

page 6


Equipment for offshore Wind Turbine Installation Contents of presentation     

GustoMSC Offshore WTI Crane & vessel design Developments Conclusion

page 7


Present installation methods Getting started; „Just do it‟ with the tools available.

SEA-1250 “Buzzard (1982), Photo courtesy Deme / GeoSea : GustoMSC designed jack-up Buzzard

page 8


Present installation methods

And it works! Speed & project risk

SEA-1250 “Buzzard (1982) and SEA-900 “Vagant” (1995),

Photo courtesy Deme / GeoSea : GustoMSC designed jack-up Buzzard

page 9


Present installation methods Offshore Wind Turbine Foundation:  mono pile, tri-pod, jacket etc  transition piece Topside:  tower  Turbine: nacelle, hub, rotor blades

Installation with a jack-up

page 10


Present installation methods Mono pile & transition piece

Photos courtesy Mammoet

page 11


Present installation methods Steel tower

Guides & bumpers?

Photo courtesy Mammoet

page 12


Present installation methods Nacelle installation Vagant

page 13


Present installation methods Nacelle

page 14


Present installation methods Hub and blades

Photoâ€&#x;s courtesy A2Sea, MPI page 15


Present installation methods

Buzzard and Vagant

MPI Resolution

Svanen Thialf

JB-114 Stanislav Yudin

page 16


Offshore wind Projected Development

2020

Annual wind power installations EU (2000-2030) 2010

Data collected in February 2010 Source: EWEA, European Wind Energy Association, Pure Power, p.47 page 17


Equipment for offshore Wind Turbine Installation „Existing‟ and „new‟ WTI Equipment

Crane capacity increase Many (dedicated) units entering the market GustoMSC significant position as integrated developer

page 18


Equipment for offshore Wind Turbine Installation Contents of presentation     

GustoMSC Offshore WTI Crane & vessel design Developments Conclusion

page 19


Crane and vessel design WTI CRANE REQUIREMENTS Lifting    

Dedicated WTI cranes Lift capacity Load variation Lifting height Lifting speed

Operational conditions  Wind load  Floating capabilities  Transit & survival

Accuracy  No guides and bumpers Load spectrum  WTI frequent usage

page 20


Crane and vessel design VESSEL REQUIREMENTS Vessel loading capacity, jacking height  Loading capacity & area  Water depth  Number of legs  Crane position Environmental conditions  Sailing  Jacking  Survival Sailing speed  Cycle time  Vessel design Load spectrum  Frequent use of jacking system page 21


Crane and vessel design Integrated design of vessel, jacking system and crane

Global Hull FEA

page 22


Photo slides


Photo slides


Crane and vessel design Improved deck efficiency:  Long crane boom  Limited deck space Minimum radius  Crane obstructed by jack-up leg

Solution:  „CRANE AROUND LEG‟

Consequence:  Crane load in jack house  Crane and jack house integration  Interface is very important  Minimize risk; one responsible party

 Cost page 25


Crane and vessel design Jacking system loads during crane operation Can be governingďƒ to be checked

Survival Wave

Operational Wave + Crane

page 26


Crane and vessel design

page 27


Crane and vessel design

What‟s new?

1968 two GustoMSC Cranes Around Leg on board “Cowrie One” (SHELL)

page 28


Crane and vessel design 500 t crane for Bard

800 t Leg crane

1000 t crane for MPI

page 29


Equipment for offshore Wind Turbine Installation Contents of presentation     

GustoMSC Offshore WTI Crane & vessel design Developments Conclusion

page 30


WTI development

Courtesy: NREL

page 31


WTI development UK plans for 2020 (Round 3)

300 nautical miles

page 32


WTI development Jacket foundation development? Feeder concepts? Foundation Installers? Water depth?

Beatrice 2 x 5 MW @ Âą 42 m water depth Photos courtesy RePower

page 33


WTI development Water depth 60 - 70 m Lift capacity 1200 ton 12 m chord leg GLC-1200X-ED Lift-off functionality

page 34


WTI development Lift-off functionality

page 35


WTI development Lift-off functionality hoist speed

A lift-off case study  Crane stiffness  Supply vessel particulars  Hoist speed  Heading  Hs/Tp  Hook-on  DAF  Reaction time  Automation level

page 36


WTI development Joint Industry Development Project (SBM involved) Onboard Wave and Motion Estimation (OWME) Motion prediction 60 seconds ahead Improve Lift-off performance

page 37


WTI development Floating wind Floating wind farms in water depths of 60 m and deeper

page 38


WTI development WTI Maintenance Limited load Full height Limited deck space required Reversed Installation & component exchange Cost effective solutions required

page 39


WTI development Turbine Installation in one piece GustoMSC proposal, 2002 Based on XY cantilever system

•Single use vessel •Supply chain management (investments) •Complexness/proven concept •Cost effectiveness

page 40


Equipment for offshore Wind Turbine Installation Contents of presentation     

GustoMSC Offshore WTI Crane & vessel design Developments Conclusion

page 41


Presentation conclusion

WTI is becoming a mature market.

WTI units have converged Majority is self-propelled jack-up, 6 -10 turbines, 800 - 1000 t crane.

It is essential to properly balance vessel, jacking unit and crane.

Crane Around The Leg concept improves deck efficiency and crane operations

Separation foundation and turbine installation

Development directions not easy to predict

Cost effectiveness is crucial.

page 42


Equipment for offshore Wind Turbine Installation

Questions?

page 43


Thank you for your attention

www.GustoMSC.com


Speaker

Xiaoming Gu IKM Ocean Design AS Background: He has 12 years of academic and industry experience in Civil/Structure engineering. He obtained his first degree in Civil Engineering from Southeast University, Nanjing, China in 1998 and PhD in Structure Engineering from Nanyang Technological University, Singapore in 2005. Before started in IKM Ocean Design AS, Stavanger in 2007, he had been working in China and Singapore as an engineer in industry and a researcher in the university. He is currently a Senior Structure Engineer and mainly working on subsea structure design and analysis. Presentation: Re‐evaluation of DNV simplified formulae for crane tip motions


IKM OCEAN DESIGN

OPTIMAL

SOLUTIONS

Zero injuries – an overall objective!

1


Re-evaluation of DNV Simplified Formulae for Crane Tip Motions By: Xiaoming Gu, Helge Nesse, Per R. Nystrøm

Zero injuries – an overall objective!


Table of contents 1.

Why simplified formulae for crane tip motions are needed?

2.

DNV simplified formulae

3.

A comparison study

4.

Proposed change on the formulae

5.

Conclusions and limitations


1. Why simplified formulae for crane tip motions are needed?

Offshore lifting operation • Highly weather dependent Wind, wave, current...

• Vessel dependent Size, shape, COG, crane configuration...

• Lifting object dependent Size, shape, weight, position...

• Expensive Nok 300.000/day ex. fuel, equipments and project personnel for a typical installation vessel in North Sea.

Zero injuries – an overall objective!


1. Why simplified formulae for crane tip motions are needed?

Hydrodynamic analysis • To define an acceptable weather window for the selected installation vessel • To widen the range of suitable installation vessel for the selected operation season • To provide load information for the lifting object design

Zero injuries – an overall objective!


1. Why simplified formulae for crane tip motions are needed?

By refined numerical analysis • Pro (technically)  Time domain  Coupling of multibody system

• Con (economically)  Overkilled for tendering stage or light lifting  Complicated and time consuming

Source: http://www.sintef.no

Zero injuries – an overall objective!


1. Why simplified formulae for crane tip motions are needed?

Need for a simplified method • Tendering stage • Light lift for small size objects

Zero injuries – an overall objective!


1. Why simplified formulae for crane tip motions are needed?

Relevant DNV standards • DNV Rules for Planning and Execution of Marine Operations, 1996  Part 2 Chapter 5- Lifting  Part 2 Chapter 6- Sub Sea Operations

• DNV RP-H103, Modeling and Analysis of Marine Operations, 2010  Chapter 4- Lifting Through Wave Zone-Simplified Method

Zero injuries – an overall objective!


1. Why simplified formulae for crane tip motions are needed?

Input required for the simplified method • Sea state  Wave height  Wave period

• Geometry of lifting objects  Shape  Project area on horizontal plane  Perforation ratio  Etc.

Information available

• Position of lifting objects  Well above sea level  Within splash zone  Below surface

• Crane tip motions  Vessel hydrodynamic characterisitcs (RAO)  Vessel heading  Crane boom configuration  Stiffness of hoisting system

Zero injuries – an overall objective!

To be calculated


1. Why simplified formulae for crane tip motions are needed?

What to do with the crane tip motions? • By refined numerical analysis? or • By simplified formulae?

My answer: Why go back to the numerical analysis if you have choosed to use a simplified method?

Zero injuries – an overall objective!


2. DNV simplified formulae

DNV formulae • Part 2 Chapter 6 Section 2- Design Loads, DNV Rules for Planning and Execution of Marine Operations, 1996 • Chapter 4- Lifting Through Wave Zone-Simplified Method, DNV RP-H103, Modeling and Analysis of Marine Operations, 2010 • Chapter 9 Lifting Operations, Section 9.2- Light Lifts DNV RP-H103, 2010 Eq. 1

Eq. 2

Eq. 3

How about the formulae’s performance? Zero injuries – an overall objective!


3. A comparison study

A comparison study Comparison between results from • Refined numerical analysisOrcaflex

and • Simplified formulaePart 2 Chapter 6- Sub Sea Operations, DNV Rules for Planning and Execution of Marine Operations, 1996

Zero injuries – an overall objective!


3. A comparison study

Vessel data Edda Flora

Courtesy of Østensjø Rederi AS

Zero injuries – an overall objective!


3. A comparison study

Vessel RAO Surge

Sway

Heave

Courtesy of Østensjø Rederi AS

Zero injuries – an overall objective!


3. A comparison study

Assumptions • The duration of lowering through the wave zone is assumed 30 mins. • Vessel heading 45 deg 0 degrees are waves from ahead while 90 degrees are waves from port • Vessel speed 0 km/h

Courtesy of Østensjø Rederi AS

Zero injuries – an overall objective!


3. A comparison study

Results Crane tip displacement

The crane tip displacement ď ¨ct is underestimated by 10~35% using Eq. 1

Zero injuries – an overall objective!


3. A comparison study

Results Crane tip velocity

The crane tip velocity vct is overestimated with a safety margin of 20~60% using Eq. 2 (the conservatism varies from 20% to 40% while Tz falls in a range between 6.5 s and 10.5 s, 60% is only for Tz=12.5 s)

Zero injuries – an overall objective!


3. A comparison study

Results Crane tip acceleration

The crane tip acceleration act is overestimated with a safety margin by 40~200% using Eq. 3

Zero injuries – an overall objective!


3. A comparison study

A re-look at the formulae  ct   H2  b sin  R 2  l sin  P 2  vct  2  H  TH

a ct  4

2

  b sin  R    l sin  P          T T R P     

H  2  TH

Zero injuries – an overall objective!

2

2

Eq. 1 2

  b sin  R    l sin  P          2 2   TR   TP  2

2

Eq. 2 2

Eq. 3


4. Proposed changes

Proposed changes  ct   H2

P Tz TH

 vct  2  H  TH

a ct  4 2

 b sin  R 

2

P Tz TR

 l sin  P 

  b sin  R    l sin  P            TR   TP 

 H   PT2  H

Zero injuries – an overall objective!

2

2

2

2

2

Eq. 4

TP

2

  b sin  R    l sin  P          PT2   PT2  R P     

P Tz

Eq. 5

2

Eq. 6


4. Proposed changes

Results from modified formulae Crane tip displacement

25~55% safety margin- Eq. 4

Zero injuries – an overall objective!


4. Proposed changes

Results from modified formulae Crane tip velocity

20~60% safety margin- Eq. 2/5

Zero injuries – an overall objective!


4. Proposed changes

Results from modified formulae Crane tip acceleration

25~65% safety margin- Eq. 6

Zero injuries – an overall objective!


5. Conclusions and limitations

Conclusions • A simplified method of hydrodynamic calculation is in need. • The conservatism achieved by the DNV formulae for crane tip motion are not consistent • The results obtained from the proposed formulae are conservative with a consistent safety margin

Limitations of this study Only one vessel was investigated

Zero injuries – an overall objective!


Thanks! Contact: xiaoming.gu@IKM.no

25


Speaker

Jon Olav Kopperstad, Evotec AS , NO Background: High school of technical college.Chief Mechanic, seismic research vessel, Geco Prakla, Mecanical Support Engineer, Geco Prakla Project Engineer (VDCG‐ vessel design & conversion group) Sales Manager Odim As, Sales & Marketing Manager Hydrakraft, Business Unit Manager, Odim Offshore Supply, SVP Marine Equipment, Evotec AS Presentation: Bulk Hose Securing Unit (BHSU)


Offshore Cranes & Lifting Conference Stavanger, 12th. – 14th. April 2011

Presentation by Jon Olav Kopperstad


BHSU Bulk Hose Securing Unit


Content • BULK HOSE SECURING UNIT (BHSU) • • • •

26.04.2011

Introduction / background Project participants System description Conclusion

3


Norsk Hydro’s Kick-Off meeting in Stavanger October 2003

Agenda: Safe Cargo Handling


Logistics on NCS in Statoil: 

Annual outbound deck tonnage : approx. 600.000

Annual outbound bulk tonnage : approx. 1.050.000

Numbers taken from Statoil presentation May 2010

26.04.2011

5


North Sea Offshore rigs / plattforms (NCS) 

MODU’s: 

Approx. 40 units

Production units 

Approx. 58 units

Total no. of Offshore Units(NCS): approx. 100 units 26.04.2011

6


Assumption: 

Every offshore units have one hose conection in average every day 

100 connections every day

700 connections every week

2.800 connections every month

33.600 connections every year

An intensive and repeatedly handling operation.

Most of the major oil companies have expressed their intension to increase the safety level for this type of operation.

26.04.2011

7


Guide-lines and procedures  Norsok Standard R‐002‐B1 “Bulk hose transfer stations on offshore installations shall be designed with hoses on power driven hose reels or similar, preferably with an automatic connection system on the supply vessel”  Norsok Standard R‐003 ‐ 6.1.8 Loading and un‐loading of Bulk  Rutiner for håndtering av bulkslanger mellom innretninger og forsyningsfartøy i Statoil

26.04.2011

8


26.04.2011

9


Murphy's laws If something can go wrong it probably will.

It’s only a matter of time

So, why not be pro‐active.

26.04.2011

10


BULK HOSE SECURING UNIT “Statoil contributes to improve safety in bulk operations offshore “  Statoil and Evotec formed in November 2009 a partnership through Statoil`s LOOP program. Statoil contributed financially in the development of Evomec` safety concept, "Bulk Hose Securing Unit" (BHSU).  The prototype is now installed and tested on the Eidesvik vessel "Viking Queen", and has been used in bulk operations since 1 December 2010.  Feedback from the personnel involved is positive. Use of BHSU both simplifies and improves the working conditions for crane operators and deck personnel in the handling of bulk hoses. “Evomec`s BHSU‐system improves the safety during bulk operations offshore.”

26.04.2011

11


BHSU - Project main purpose ďƒ˜ Develop a system which remove personnel from exposed areas during critical Bulk Hose Handling operations.

26.04.2011

12


BHSU - Project main design criteria  BHSU - An automated Bulk Hose Securing System • • • •

26.04.2011

To remove personnel from exposed area during Bulk Hose Handling. Easy to retrofit on existing fleet No adaption are required on rig side or existing bulk hoses. Handle various types and dimensions of Bulk hoses.

13


BULK HOSE SECURING UNIT

26.04.2011

14


26.04.2011

15


BULK HOSE SECURING UNIT

26.04.2011

16


26.04.2011

17


The successfull prototype test-periode officially ended March 01-2011

The BHSU is still in operation onboard Viking Queen.

Already used in more then 100 hose connections.

26.04.2011

18


Statoil celebrated the occasion with marzipan cakeparty onboard Viking Queen together with ship-crew and representatives from Evotec.

26.04.2011

19


BHSU – Advantages discovered based on experience • • • • • •

26.04.2011

Vessel can keep longer distance from rig. Easier to receive/secure Bulk Hoses with short hoses and/or small cranes. Make Hose Handling less sensitive for various weather conditions. Easier for the Crane Operators to deliver the hoses. Easier to adjust to required length of hose onboard vessel. Simplify multi Bulk Hose handling.

20


Conclution

BHSU - Project main achievements ďƒ˜ Removed personnel from exposed areas during bulk hose handling.

26.04.2011

21


Conclution

BHSU - Project main achievements ďƒ˜ To a safe position with a good overview of the Bulk Hose Handling Operation.

26.04.2011

22


Thank you for your attention !

26.04.2011

23


Social program Tuesday 12th April

16:45 Bus transport from Stavanger Forum to the harbor. 1,5 – 2 hour boat trip with an aperitif, small tapas and some great surprises aboard in the fjords. Conference dinner with a spectacular Norwegian cultural program in the Hall of Gloppe, with a Norwegian Nymph and Peter Mitchell!

23:00

Bus back to night cap in Stavanger

Remember to check our web site www.liftingoffshore.com

Remember to check our web site www liftingoffshore com it w


A social happening, the conference on tour















































































The End 03:47


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.