SPLOST IV Capital Project Update - August 1, 2017

Page 1

HENRY COUNTY SPLOST PROJECT STATUS UPDATE Ron Burckhalter, SPLOST Capital Projects Director and Roque Romero, SPLOST Director of Transportation BOARD OF COMMISSIONERS MEETING August 1, 2017


SPLOST IV – COUNTY WIDE PROJECT UPDATE


SPLOST IV – COUNTY WIDE 911 RADIO REPLACEMENT Budget: $7,184,000.00 Status:

In Progress

Contract awarded to Harris Corporation 3/15/2016 Project 40% Complete All radios ordered and in process of shipping. Radio/Equipment installation in progress. Microwave system installed and tested.

Estimated Completion March 2018


SPLOST IV – COUNTY WIDE AIRPORT FBO

Budget: $1,000,000.00 Status: Preliminary Design In Progress Engineer: Croy Engineering


SPLOST IV – COUNTY WIDE

AMBULANCES (1-Remount/1-New) Budget: $326,529.00 Status:

COMPLETE

(1) Ambulance Remount Cost $100,214.00 Located at F.S. #13 (1) New Ambulance Cost $226,315.00 Located at F.S. #12


SPLOST IV – COUNTY WIDE

ANIMAL CONTROL RENOVATION Budget: $100,000.00 Status:

COMPLETE

Cost: $99,689.00 Renovations included: New digital security camera system. Epoxy wall coating in kennels, puppy room, and quarantine area. Additional fencing and new automatic gate. New interior doors.


SPLOST IV – COUNTY WIDE

FIRE STATIONS CAPITAL EQUIPMENT Budget: $2,153,471.00 Status:

COMPLETE

Cost: $2,134,000.00 Equipment for (3) New Fire Stations: Fire Station #14 (Luella) New Fire Truck & Ambulance Fire Station #15 (N. Mt. Carmel) New Fire Truck & Ambulance Fire Station #16 (Kelleytown) New Fire Truck & Ambulance


SPLOST IV – COUNTY WIDE

FIRE STATION #14 (Luella Area) Budget: $2,235,000.00 Status:

In Progress

Location: 1875 Hampton Locust Grove Road, Locust Grove, GA Architect:

The Howell Group of Marietta, GA

Contractor: Tommy Gibson Builders of Warner Robbins, GA Construction 80% Complete. Estimated Completion September 2017.



SPLOST IV – COUNTY WIDE

FIRE STATION #15 (N. Mt. Carmel Area) Budget: $2,440,000.00 Status:

COMPLETE

Location: 325 N. Mt. Carmel Road, Hampton, GA Architect:

The Howell Group

Contractor: Headley Construction



SPLOST IV – COUNTY WIDE

FIRE STATION #16 (Kelleytown Area) Budget: $2,600,000.00 Status:

In Progress

Location: 1575 Kelleytown Road, McDonough, GA Architect:

The Howell Group

Contractor: Tommy Gibson Builders Construction 25% Complete. Estimated Completion February 2018.


Fire Station #16 - Kelleytown


SPLOST IV – COUNTY WIDE

HCDOT CONSTRUCTION EQUIPMENT Budget:

$450,000.00

Status:

COMPLETE

Purchase of 2015 ROADTEC FB-100 Heavy Duty Front Mount Broom  Cost: $67,757.00 Purchase of (2) New 2017 International 7500 Dump Trucks Cost: $228,636.00 Purchase of (3) New 2016 Ford F250 Pick-Up Trucks Cost: $115,853.00


SPLOST IV – COUNTY WIDE JAIL RENOVATIONS Budget: $1,500,000.00 Status:

In Progress

Pod A & B Renovation - COMPLETE Pod A & B renovation items included new surveillance cameras, new access control system, plumbing renovation, plumbing fixture upgrade, and epoxy wall coating in shower/toilet area. Kitchen Renovation – In Progress. Kitchen renovation items include removing the existing floor and grout bed, replace existing sanitary sewer, replace all existing floor drains, add a new exterior door/frame, and apply epoxy floor and wall coating to entire kitchen area.


SPLOST IV – COUNTY WIDE NEW INTERCHANGE ON I-75 Budget: $5,500,000.00 Status:

In Progress

Engineers:

Pond & Company

Feasibility Study - COMPLETE Interchange Justification Report In Progress


SPLOST IV – COUNTY WIDE

(30) POLICE PATROL VEHICLES Budget: $1,406,806.00 Status:

COMPLETE

Purchase of (30) Police Patrol Vehicles and Related Equipment  Cost: $1,383,187.00


SPLOST IV – COUNTY WIDE PROBATE COURT BUILDING IMPROVEMENTS Budget: $220,000.00 Status:

In Progress

Improvements Include: Courtroom Courtroom Furnishings & Equipment Security Equipment Customer Service Area Cubicles Flooring and Paint


SPLOST IV – COUNTY WIDE SEWER TO AIRPORT Budget: $2,000,000.00 Status: In Progress HCWA Design COMPLETE. Phase I Construction COMPLETE. Phase II Construction In Progress. Estimated Completion: December 2017.


SPLOST IV – COUNTY WIDE SEWER TO FAIRVIEW Budget: $2,000,000.00 Status: In Progress HCWA Design COMPLETE. Phase I Construction COMPLETE. Phase II Construction In Progress. Estimated Completion: November 2017


SPLOST IV – COUNTY WIDE

TECHNICAL COLLEGE BUILDING SPLOST Budget: $5,000,000.00 Status: In Progress Architect: Lord, Aeck and Sargent, Inc. Contractor: Parrish Construction Group Georgia State Financing & Investment Commission Project. Construction In Progress.


SPLOST IV – COUNTY WIDE PROJECT STATUS SUMMARY

16 of 17 County Wide Projects In Progress or COMPLETE


SPLOST IV - DISTRICT 1 PROJECT UPDATE Commissioner Johnny Wilson


SPLOST IV – DISTRICT 1

FIRE STATION #2 (Replacement) Budget: $2,361,600.00 Status:

COMPLETE

Cost: $2,308,534.00 Location: 35 Frances Ward Drive, Locust Grove, GA Architect:

The Howell Group

Contractor: J.R. Bowman Construction



SPLOST IV – DISTRICT 1

KITCHEN-LOCUST GROVE SENIOR/EVENT CENTER Budget: $550,000.00 Status:

In Progress

Location: 280 Mose Brown Drive, Locust Grove, GA Preliminary Design In Progress New Catered Kitchen New Full Service Kitchen


SPLOST IV – DISTRICT 1 TANGER BALL FIELDS Budget:

$550,000.00

Status:

COMPLETE

Cost: $482,507.00 Location: 2951 Tanger Blvd., Locust Grove, GA Joint project with the City of Locust Grove Concession Bldg., Sports Lighting, Storage/Meeting Bldg., Fencing, and Parking Lot Design.


SPLOST IV - DISTRICT 1

MAJOR TRANSPORTATION (2 of 3 In Progress) McDonough Parkway (Henry Connector) Budget: $5,000,000.00 Status: Right of Way Acquisition In Progress Engineer: Heath & Lineback Engineers

SR81 Widening (Lemon to Bethany) D1 Budget: $197,397.00 (50/50 Shared Cost w/District 3)  ARC Design Contribution up to $1.2M Status: Design In Progress Engineer: Moffatt & Nichol


SPLOST IV - DISTRICT 1

INTERSECTION IMPROVEMENTS (3 of 3 In Progress or COMPLETE)

Locust Road/Jackson Street @ SR42 Status:

COMPLETED by GDOT

South Bethany @ Old Jackson Budget: 1,000,000.00 Status: Right of Way Acquisition In Progress Engineer: AECOM

SR81 @ Mt. Bethel/Wynn (50/50 Shared Cost w/District 3) District 1 Cost: $505,804.00 Status: COMPLETE


SPLOST IV - DISTRICT 1

DIRT ROADS (5 of 5 In Progress or COMPLETE) Harris Drive (Leguin Mill Road to South Bethany Road) Cost: $1,545,246.00 Status: COMPLETE

Lester Mill Road (Hampton L.G. to Indian Creek) Budget: $4,527,554.00 Status: Construction In Progress Contractor: Southeastern Site Development


Lester Mill Road


SPLOST IV - DISTRICT 1

DIRT ROADS (Continued) Peeksville Road (New Hope to Bridge) Budget: $1,200,000.00 Status: Right of Way Acquisition In Progress Engineer: Heath & Lineback

Peeksville Road (Bridge to Old Jackson) Design Only Budget: $126,375.00 Status: Design In Progress Engineer: Heath & Lineback

Weems Road (Hampton LG to End) Surface Treatment Cost: $76,849.00 Status: COMPLETE


SPLOST IV – DISTRICT 1

BRIDGE IMPROVEMENTS (5 of 5 COMPLETE) King Mill over Tussahaw Creek (Culvert Repair) Cost: $90,537.00 Status: COMPLETE

Locust Grove over Indian Creek (Bridge Repair) Cost: $43,433.00 Status: COMPLETE

Jackson Lake over Mackey Creek (Bridge Replacement) District 1 Cost: $381,770.00 (1/3 Cost – District 1)(2/3 Cost – District 3) Status: COMPLETE


SPLOST IV – DISTRICT 1

BRIDGE IMPROVEMENTS (Continued) Old Jackson over Tussahaw Creek (Bridge Repair) Cost: $20,959.00 Status: COMPLETE

South Ola over Tussahaw Creek (Bridge Repair) Cost: $38,030.00 Status: COMPLETE


SPLOST IV – DISTRICT 1

RESURFACING, WIDENING OR SURFACE TREATMENT 13 COMPLETE Amber Court

Makayla Drive

Davis Lake Road

McCart Road

Ellistown Road

Peeksville Road

Ingram’s Lane

Sandy Ridge Road

Leguin Lane

Trestle Road

Luella Road

(East of SR155)

Luella Road

(West of SR155)

Weems Road


SPLOST IV – DISTRICT 1

PROJECT STATUS SUMMARY 3 of 3 Capital Projects In Progress or COMPLETE 15 of 16 Transportation Projects In Progress or COMPLETE NOTE: Excludes (13) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST III – DISTRICT 1 DIRT ROADS Frog Road Budget: $2,885,726.00 Status: Construction In Progress Contractor: McCoy Grading, Inc.


SPLOST IV - DISTRICT 2 PROJECT UPDATE Commissioner Dee Clemmons


SPLOST IV – DISTRICT 2 AVALON PARK RESTROOM Budget: $50,000.00 Status: In Progress Design/Build Request for Proposals In Progress.


SPLOST IV – DISTRICT 2

SENIOR/RECREATION CENTER Budget: $4,000,000.00 Status:

COMPLETE

Location:

56 McDonough Street, Hampton, GA

Architect:

Flynn, Finderup Architects

Contractor: Meja Construction


Bear Creek Senior Activity Center and Recreation Center


SPLOST IV – DISTRICT 2

INTERSECTION IMPROVEMENTS (5 of 6 In Progress) Industrial Parkway @ SR20 (GDOT Project) Status:

GDOT Design In Progress

Jodeco Road @ Blackhall Road Budget: $803,105.00 (Joint Project with GDOT) Status: Construction Bid Opened 6/21/2017

Mill @ SR81 Budget: $1,250,000.00 Status: Right of Way Acquisition COMPLETE; Construction Bids Due 8/24/2017 Engineer: AECOM


SPLOST IV – DISTRICT 2 INTERSECTION IMPROVEMENTS (Continued) Mt. Carmel @ Chambers Budget: $1,000,000.00 Status: Construction In Progress Contractor: CMES

Simpson Mill @ Hampton-L.G. Budget: $620,000.00 Status: Preliminary Design In Progress Engineer: AECOM


Mt. Carmel @ Chambers


SPLOST IV – DISTRICT 2

DIRT ROADS (10 of 10 In Progress or COMPLETE) Amah Lee (Old SR3 to End of Pavement) Budget: $390,000.00 Status: Right of Way Acquisition In Progress Engineer: Wolverton & Associates

Farmer Drive (Surface Treatment) Cost: $24,988.00 Status: COMPLETE

Fields Drive (Surface Treatment) Cost: $20,686.00 Status: COMPLETE


SPLOST IV – DISTRICT 2

DIRT ROADS (Continued) Floyd Road (Surface Treatment) Cost: $9,085.00 Status: COMPLETE

Jones Road (Surface Treatment) Cost: $44,776.00 Status: COMPLETE

Mt. Olive Road (Jonesboro to End of Pavement) Cost: $55,472.00 Status: COMPLETE


SPLOST IV – DISTRICT 2

DIRT ROADS (Continued) Selfridge Road (Speedway Blvd. to Airport Entrance) Budget: $850,000.00 Status: Preliminary Design In Progress Engineer: Wolverton & Associates

South Cleveland Church (New Morn to Stone Road) Budget: $862,000.00 Status: Preliminary Design In Progress Engineer: Wolverton & Associates

South Mt. Carmel (Surface Treatment) Cost: $17,529.00


SPLOST IV – DISTRICT 2

DIRT ROADS (Continued) Thoroughbred Drive (Greenwood Road to End of Pavement) Budget: $507,000.00 Status: Right of Way Acquisition In Progress Engineer: Wolverton & Associates


SPLOST IV – DISTRICT 2

BRIDGE IMPROVEMENTS (5 of 5 In Progress or COMPLETE) Blackhall over Rum Creek (Bridge Replacement) Budget: $300,000.00 (Joint Project with GDOT) Status: Right of Way Acquisition In Progress

Hampton over Indian Creek (Culvert Repair) Cost: $296,786.00 Status: COMPLETE

Hampton over Towaliga River (Bridge Repair) Cost: $52,081.00 Status: COMPLETE


SPLOST IV – DISTRICT 2

BRIDGE IMPROVEMENTS (Continued) Jonesboro over Walnut Creek (Bridge Repair) Cost: $42,830.00 Status: COMPLETE

Old SR3 over Norfolk Southern RR (Bridge Repair) Budget: $80,000.00 Status: COMPLETE Contractor: Baldwin Paving


SPLOST IV – DISTRICT 2

RESURFACING, WIDENING OR SURFACE TREATMENT 24 COMPLETE Arnold Road

Lake Talmadge Dam

Chambers Road

Lower Woolsey Road

David Road

Manley Drive

Dillion Drive

Meadow Trail

Gold Leaf Drive

Norfolk Drive

Falls Court

North Drive


SPLOST IV – DISTRICT 2

(Continued)

RESURFACING, WIDENING OR SURFACE TREATMENT

Oakridge Court

Portsmouth Avenue

Oak Trail

Shoreline Way

Pates Lake Court

Simpson Mill Road

Pates Lake Cove

South Drive

Pates Lake Drive

Tidewater Avenue

Pates Lake Way

Water Oaks Court


SPLOST IV – DISTRICT 2

PROJECT STATUS SUMMARY 2 of 2 Capital Projects In Progress or COMPLETE 20 of 23 Transportation Projects In Progress or COMPLETE NOTE: Excludes (24) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST III – DISTRICT 2

INTERSECTION IMPROVEMENTS Old Highway 3 @ SR81 Budget: $5,629,075.00 Status: Construction In Progress Contractor: CMES, Inc.


SPLOST IV - DISTRICT 3 PROJECT UPDATE Commissioner Gary Barham


SPLOST IV – DISTRICT 3

HERITAGE PARK IMPROVEMENTS Budget: $25,000.00 Status:

COMPLETE

Cost: $21,437.00 Improvements Included: Steps with handrails from upper parking lot to Military Museum and crosswalk. Sidewalk with handrails to Veteran’s Wall of Honor.


SPLOST IV – DISTRICT 3

JASON T. HARPER ARENA IMPROVEMENTS Budget: $1,500,000.00 Status:

Design COMPLETE

Architect:

Southern A&E

In process of phasing the construction.


SPLOST IV – DISTRICT 3 NORTH OLA PARK

Budget: $1,500,000.00 Status:

In Progress

Purchased property behind Ola Elementary, south of the park, for park expansion New 3-4 Year Old T-Ball Field COMPLETE. New 115 space parking lot addition COMPLETE. RFP for Design/Build for Additional Ball Fields In Progress.


SPLOST IV – DISTRICT 3

MAJOR TRANSPORTATION (2 of 2 In Progress) McDonough Parkway (SR42 to SR155) Budget: $2,827,000.00 Status: Final Design In Progress; Right of Way Acquisition Next Engineer: Kimley-Horn

SR81 Widening (Lemon to Bethany) D3 Budget: $774,009.00 (50/50 Shared Cost w/District 1)  ARC Design Contribution up to $1.2M Status: Concept Design In Progress Engineer: Moffatt & Nichol


McDonough Parkway (SR42 to SR155)


SPLOST IV – DISTRICT 3

INTERSECTION IMPROVEMENTS (7 of 9 In Progress OR COMPLETE)

Bethany Road @ SR81 Status: Completed by GDOT

Campground Road @ SR155 Budget: $600,000.00 Status: Right of Way Acquisition COMPLETE Engineer: AECOM

Dailey Mill @ Jodeco Road Cost: $251,260.00 Status: COMPLETE


SPLOST IV – DISTRICT 3

INTERSECTION IMPROVEMENTS (Continued) East Lake @ SR20 District 3 Cost: $1,124,489.00 (50%/50% Shared Cost w/District 4) Status: COMPLETE

Jodeco Road @ Oak Grove Road Cost: $285,249.00 Status: COMPLETE


East Lake @ SR20


SPLOST IV – DISTRICT 3

INTERSECTION IMPROVEMENTS (Continued) Lake Dow/Rodgers @ Rosser Cost: $954,010.00 Status: COMPLETE

SR81 @ Mt. Bethyl/Wynn (50/50 Shared Cost w/District 1) District 3 Cost: $449,354.00 Status: COMPLETE


Lake Dow Road @ Rodgers/Rosser


SPLOST IV – DISTRICT 3

DIRT ROADS (6 of 7 In Progress or COMPLETE) Butler’s Bridge Drive (Surface Treatment) Cost: $52,904.00 Status: COMPLETE

Candler Road (Surface Treatment) Cost: $31,176.00 Status: COMPLETE

East Knight Road (Surface Treatment) Cost: $30,348.00 Status: COMPLETE


SPLOST IV – DISTRICT 3

DIRT ROADS (Continued) Eskew Road (Surface Treatment) Cost: $37,419.00 Status: COMPLETE

Turner Church Road (East of Bridge to SR20) Budget: $1,802,000.00 Status: Construction Bid Award 8/1/2017 Engineer: Pond & Co.

Turner Circle (Surface Treatment) Cost: $26,832.00 Status: COMPLETE


SPLOST IV – DISTRICT 3

BRIDGE IMPROVEMENTS (4 of 4 In Progress) Dailey Mill over Walnut Creek (Bridge Repair) Cost: $235,103.00 Status: COMPLETE

Elliott over Walnut Creek Tributary (Bridge Repair) Budget: $300,000.00 (Joint Project with GDOT) Status: GDOT Design In Progress; Right of Way Acquisition In Progress


SPLOST IV – DISTRICT 3 BRIDGE IMPROVEMENTS (Continued) Jackson Lake over Mackey Creek (Bridge Replacement) District 3 Cost: $751,777.00 (2/3 Cost District 3)(1/3 Cost District 1) Status: COMPLETE

Oak Grove over Walnut Creek (Bridge Repair) Cost: $79,611.00 Status: COMPLETE


Jackson Lake over Mackey Creek


SPLOST IV – DISTRICT 3

RESURFACING, WIDENING OR SURFACE TREATMENT 29 COMPLETE Airline Road

East Lake Road (50/50 Shared w/D4)

Brookdale Court

Fir Drive

Chardonnay Oaks Drive

Foster Drive

Charming Court

Jodeco Road (50/50 Shared w/D4)

Clearview Circle

Juniper Drive

Compton Court

Lakehaven Parkway

Country Meadows

Millbrook Way Millstone Court


SPLOST IV – DISTRICT 3 (Continued)

RESURFACING, WIDENING OR SURFACE TREATMENT Overlook Drive

Sherwood Loop

Pinecone Court

Silver Tip Court

Post Oak Ridge

Spruce Drive

Rosser Road

Whispering Pines Lane

Rowan Drive

Wood Valley Drive

Saxony Court

Wynnfield Blvd.

Sherwood Court

Wynnfield Way


SPLOST IV – DISTRICT 3

PROJECT STATUS SUMMARY 3 of 3 Capital Projects In Progress or COMPLETE 19 of 22 Transportation Projects In Progress or COMPLETE NOTE: Excludes (29) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST IV - DISTRICT 4 PROJECT UPDATE Commissioner Blake Prince


SPLOST IV – DISTRICT 4 BUD KELLEY PARK

Budget: $2,750,000.00 Status:

COMPLETE

Location: 1605 Kelleytown Road, McDonough, GA Design/Build Firm: Sports Turf 124 Acre Passive Park 2+ Miles of Walking Trails (1) 30’x60’ Pavilion with Serving Window & Tables (2) 20’x40’ Pavilions with Picnic Tables Large Playground with Rubber Surface at ADA Areas 20’x40’ Shade Structure with (6) Fitness Elements


Bud Kelley Park


SPLOST IV – DISTRICT 4 MAJOR TRANSPORTATION (1 of 2 In Progress) Rock Quarry Road Widening Budget: $418,820.00  ARC Design Contribution up to $1.2M Status: Concept Design In Progress; Waiting for GDOT Approval Engineer: Croy Engineering


SPLOST IV – DISTRICT 4

INTERSECTION IMPROVEMENTS (4 of 4 In Progress or COMPLETE)

Banks Road @ Rock Quarry Road Cost: $542,133.00 Status: COMPLETE

East Lake Road @ SR20 Cost: $1,124,618.00 (50%/50% Shared Cost w/District 3) Status: COMPLETE


SPLOST IV – DISTRICT 4

INTERSECTION IMPROVEMENTS (Continued) Hemphill Road @ SR138 Budget: $1,942,000.00 Status: Construction In Progress

Moseley Road @ SR138 Status:

COMPLETED by GDOT


SR138 @ Hemphill Road


SPLOST IV – DISTRICT 4

DIRT ROADS (1 OF 2 IN PROGRESS) Elliott Road (East Lake Road to Crumbley Road) Budget: $2,272,000.00 Status: Right of Way Acquisition COMPLETE; Construction Bid Next Engineer: Wolverton & Associates


SPLOST IV – DISTRICT 4 BRIDGE IMPROVEMENTS (3 of 3 In Progress) Hemphill over James Creek (Bridge Repair) Cost: $42,954.00 Status: COMPLETE

Old Conyers over Big Cotton Indian Creek (Bridge Repair) Cost: $40,509.00 (50/50 Shared Cost w/District 5) Status: COMPLETE

Selfridge over Little Cotton Indian Creek (Bridge Replacement) Budget: $1,221,899.00 Status: Preliminary Design In Progress Engineer: AECOM


SPLOST IV – DISTRICT 4 RESURFACING, WIDENING OR SURFACE TREATMENT 20 COMPLETE Banks Road

Holloway Road

Old Conyers Road

Crumbley Road

Jodeco Road (Shared w/D3)

Pleasant Grove Circle

Earlygold Street

Kelleytown Woods Drive

Roseberry Road

East Lake Road (Shared w/D3)

Kelleytown Woods Parkway

Sunhigh Street

Kelley Way

Tie Street

Elberta Street

Maygold Street

Woods Court

Flat Rock Road

North Grove Court

Woods Lane


SPLOST IV – DISTRICT 4

PROJECT STATUS SUMMARY 1 of 2 Capital Projects COMPLETE 10 of 11 Transportation Projects In Progress or COMPLETE NOTE: Excludes (20) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST III – DISTRICT 3 and DISTRICT 4 MAJOR TRANSPORTATION Campground Road Ext. Budget: $12,922,095.00 Status: Construction In Progress Contractor: McCoy Grading, Inc.


Campground Road Extension



SPLOST IV - DISTRICT 5 PROJECT UPDATE Commissioner Bruce Holmes


SPLOST IV – DISTRICT 5

VILLAGE PARK at NORTH HENRY Budget: $6,850,000.00

Community Building

Status: COMPLETE

(2) Multi-Use Sport Fields

Location: 750 Fairview Road

Ellenwood, GA Architect: Breedlove Landplanning Contractor: Sunbelt Builders 34+ Acre Community Park Event Lawn Interactive Fountain

Concession/Meeting/Restroom/ Scoring Tower Building (1) 40’x60’ Pavilion w/Serving Window and Tables (2) 20’x40’ Pavilions w/Tables Walking Trails Fitness Circuit Playground


Village Park at North Henry


SPLOST IV – DISTRICT 5 COCHRAN PARK IMPROVEMENTS Budget: $600,000.00 Status: COMPLETE Cost: $517,801.00 Location: 305 East Atlanta Road, Stockbridge, GA Improvements Include: New Sports Field Lighting. New Scoreboards.


SPLOST IV – DISTRICT 5

MAJOR TRANSPORTATION (2 of 3 In Progress) Anvil Block Road Widening Budget: $7,141,000.00 Status: Construction In Progress Engineer: AECOM

West Village Parkway (Previously Known as West Panola) Budget: $4,238,639.00 Status: Final Design In Progress Engineer: McGee Partners


Anvil Block Road Widening


West Village Parkway (Previously West Panola)


SPLOST IV – DISTRICT 5

INTERSECTION IMPROVEMENTS (1 of 3 In Progress) East Atlanta @ Thurman & Flatrock Budget: $361,000.00 Status: Preliminary Design In Progress Engineer: Wolverton & Associates


SPLOST IV – DISTRICT 5

BRIDGE IMPROVEMENTS (2 of 2 COMPLETE) Old Conyers over Big Cotton Indian Creek (Bridge Repair) Cost: $40,509.00 (50/50 Shared Cost w/District 4) Status: COMPLETE

Stagecoach over Big Cotton Indian Creek (Bridge Repair) Cost: $23,533.00 Status: COMPLETE


SPLOST IV – DISTRICT 5

RESURFACING, WIDENING OR SURFACE TREATMENT 6 COMPLETE Awendaw Circle Fairview Road Orchard Road Panola Road Rex Road Waverly Blvd.


SPLOST IV – DISTRICT 5

PROJECT STATUS SUMMARY 2 of 2 Capital Projects COMPLETE 5 of 9 Transportation Projects In Progress or COMPLETE NOTE: Excludes (6) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST IV PROJECT STATUS SUMMARY CAPITAL

TRANSPORTATION

PROJECTS

PROJECTS

Total Projects:

28

Total Projects:

82

Projects COMPLETE:

13

Projects COMPLETE:

38

Projects In Progress:

13

Projects In Progress:

31

• NOTE: These numbers do not include any Resurfacing/Surface Treatment/Widening projects.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.