SI T E
DIARY CONFETTI MEDIA HUB 6-10 COVENT STREET NOTTINGHAM, NG1 3LL
CHEUNG HOI LING ESTHER T0046268 2017-18 ARCHITECTURE YEAR 2
1
2
C
3 ONTENT 4
5
INTRODUCTION TO PROJECT 1 2 3 4
01-07
08-19
Brief Concept Project team Construction programme
P R E PA R AT I O N W O R K S 1 2 3 4 5
Stage 2 programme Specifying design Meeting the team Demolition Ground works
6 Archaeology 7 Piling, ground beams & lift pit foundation 8 Site possession, welfare, signage 9 Coping with context 10 Health & Safety: Equipment 11 Health & Safety: Fire Escape
VISIT 1
20-25
26-35
36-42
1 Stage 2 programme 2 Insitu frame concrete 3 Alteration to existing building & roof protection 4 Stair 2 & external envelopes
VISIT 2 1 2 3 4 5
Programme 6 Courtyard Superstructure: Insitu frame concrete 7 External envelope & Stair 1 Superstructure: Ramps Walls Stair 2
VISIT 3 1 2 3 4 5
Programme 6 Planning Superstructure: Insitu frame concrete Steel frame & external envelope Stair 3 Health & safety: Crane
VISIT 4
6
1 2 3 4 5
1 2 3 4 5
1 2 3 4
1 History 2 Concrete mixes: Cement 3 Concrete mixes: Aggregates 4 Colours 5 Wall finishes: Formwork Key Walls
Ea C
D
Eb
310
E
Ec
13
12
Detail A - 300
Stair 1 Drawing 310
5 6 7 8 9
3400
2750
Detail G - 300
X502 COMPUTER SUITE
X508 STAIR 1
X509 STAIR 1 LOBBY
15
13
18 17 15
Detail L - 300
Detail F - 300
14 13
3230
3230
2945
4
8
X401 COMPUTER SUITE
7
X402 COMPUTER SUITE
X408 STAIR 1
6 5
X409 STAIR 1 LOBBY
4 3
19
Existing Confetti Building
18
15 14 13
3230
3230
2945
23151
12 11 10 9
W 13
W 09
1
X301 COMPUTER SUITE
Detail J - 300
8 7
X302 COMPUTER SUITE
X308 STAIR 1
6 5 4
X309 STAIR 1 LOBBY
3 1 20 19 18 17 16 15 14 13
3234
W 05
12
3400
2949
11 10 9 8
X201 LRC
X208 STAIR 1
7 6 5
X209 STAIR 1 LOBBY
4 Second Floor HE Second Floor 42.320 42.230 42.200
X204 SEMINAR ROOM
W 06
3 2
Ground Floor 42.064
1
14
Second Floor CONFETTI 41.820
Ground Floor 41.964
20
Ground Floor 41.820
19
E
18 17
Detail D - 300
3300
REV. DATE
X108 STAIR 1
5
X109 STAIR 1 LOBBY
4
X104 SEMINAR ROOM
3 2
Ground Floor 38.764
1
Ground Floor 38.568
20 First Floor Confetti 38.360
19
Detail K - 300
15
16-20 Bath Street, Nottingham NG1 1DF
14
3300
3300
2700
3300
13
W 03
8
X101 RECEPTION
7 6
ED 02
5
X008 STAIR 1
X009 STAIR 1 LOBBY
4
X005 WC LOBBY
X007 WC CHANGING (FEMALE WC)
X013 CONTROL ROOM
3
Ground Floor Ground Floor HE 35.630 35.630
2
16
35.440
Ground Floor 35.464
1
T
0115 841 8418
E
design@allanjoycearchitects .co.uk
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group PROJECT
Ground Floor 35.048
Detail O - 301
Ground Floor Confetti 34.740
MLD
BY
Architects, Landscape & Interior Design
12 11 10 9
MLD MLD MLD
DESCRIPTION
Ground Floor 38.360
18 17 16
Detail H - 300
MLD
12/05/17 Amendments to drawings following the Topo Survey and SE info 23/01/17 Stair 1 amended 10/01/17 Spec Refs added 23/12/16 Amendments to drawings
C B A
3300
2890
9 8 7 6
Timber stage platform
First Floor HE 39.060
30/05/17 Drawing status updated to construction
D
16 15 14 13 12 11 10
X101 CAFE First Floor 38.930
KINGSPAN Quadcore Karrier Panel + Brick Tie System -102.5 Black Brick as spec ref F10.110 -50mm cavity -125mm Brick Ties spaced generaly every 3 bricks, and fixed back to the Quadcore Karrier Panel as spec ref F30.220 -100mm Benchmark Quadcore Karrier Panel as H43.121 -50 mm Infill Structural Rails fixed to the structure -200mm thick concrete wall to Structural Engineer's details -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value = 0.18W/m2K
4
X304 SEMINAR ROOM
2
15
1 General arrangement drawings 2 Detail drawings 3 Service drawings Proposed masonry to be built off existing gable - cut bricks to be removed to start new wall New step + cover Flashing to abutment to color match brick as H27 - 440
17 16
Detail C - 300
Third Floor 45.590
Ground Floor Construction Solid Concrete Ground Based Floors - Vinyl floor finish as floor finishes drawings 401-402 -75mm screed as spec ref M10.130 - Underfloor Heating Systems refer to M+E Engineer's details -0.5mm separation layer lapped (minimum 150mm) -50mm perimeter Insulation overlap min.150mm from bottom of wall insulation to top of insulation upstand -130mm Kingspan Kooltherm K103 Floor Board insulation under concrete slab as spec ref M10.290A -0.9mm damp proof membrane -275mm thick concrete slab to Structural Engineer's details -well compacted sub base to Structural Engineer's details U-Value = 0.11W/m2K
16
Timber stage platform
1
15
W 14
X404 SEMINAR ROOM
2
Fourth Floor 48.694
Third Floor 45.464
Confetti CQ Campus
Air Seal - Gun grade sealant at male joint
Air seal - Continuous bead of gun grade sealant
Ground Floor 34.770
DRAWING
GA Section AA
Lower Ground Floor 32.800
A
93-102
Floors Construction (1st, 3rd, 4th, 5th) -275mm concrete deck to Structural Engineer's details -10mm latex levelling screed - Vinyl floor finish as floor finishes drawings 401-402
15
12 11 10 9
Second Floor Construction (LRC) -275mm concrete deck to Structural Engineer's details -3mm vapour control layer -50 mm Kooltherm as spec ref M10.290B -75mm screed as spec ref M10.130 - Vinyl floor finish as floor finishes drawings 401-402
14
16
Detail B - 300
79-92
6 Precedent: Pillip Exeter Academy Library 7 Precedent: Aberdeen Lane 8 Finishes types 9 Sanding 10 Stains & Blemishes 11 Deterioration
Terrace Roof System construction -350mm to 6th floor and 275mm to 5th floorconcrete deck to Structural Engineer's details -50mm screed to falls as spec ref M10.110 -3mm vapour control layer -150 mmKingspan Thermaroof TR27 LPC/FM - 25 mm thick Kingspan Thermaroof TR27 LPC/FM upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -1.5mm fully adhered single-ply membrane as S42.110A -50mm Ballast (paving slabs on support) as Q37.140 U-Value <0.15W/m2K.
13
Detail I - 300
X504 FIFTH FLOOR TERRACE
Fifth Floor 51.924 19
65-78
MAIN DRAWINGS
W 02
W 16
X501 COMPUTER SUITE
Lift shaft External envelope Partitions Connection to existing buildings M&E
Semi−intensive Green Roof Covering System construction -350mm concrete deck to Structural Engineer's details -50mm screed to falls as spec ref M10.110 -3mm vapour control layer - 25 mm thick Kingspan Thermaroof TR27 LPC/FM upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -150 mm Kingspan Thermaroof TR27 LPC/FM -1.5mm fully-adhered single ply membrane as S45.110A -roof barrier/protection layer(s) -drainage layer, filtration layer, substrate to depth required -80mm semi-intensive green roof covering as Q37.120A U-Value <0.15W/m2K.
12
External Curtain Walls Various Systems - refer to windows schedule Drawings 322-324 U-Value = 0.15W/m2K G-value of glass = 0.35
3 Metal Stud and Plasterboard partitions as spec ref K10.115
51-64
GENERAL NOTES
KINGSPAN Quadcore Karrier Panel + Brick Tie System -102.5 Black Brick as spec ref F10.110 -50mm cavity -125mm Brick Ties spaced generaly every 3 bricks, and fixed back to the Quadcore Karrier Panel as spec ref F30.220 -100mm Benchmark Quadcore Karrier Panel as H43.121 -100 mm Infill Structural Rails fixed to the structure -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value = 0.18W/m2K
3 Detail E - 300
Roof-Terrace Floor 55.324
GENERAL NOTES
External Walls BENCHMARK Quadcore Karrier Panel + Corten Recess Fixed Cassette -35mm Benchmark Corten Recessed Fix Cassette as H43.125 -100mm Benchmark Quadcore Karrier Panel fixed with a minimum of 2 Nr fasteners per panel per rail as H43.121 Ee -100 mm Infill SFS fixed to the structure -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value = 0.18W/m2K
Ed
3457
B
3234
1
Roof terrace balustrade guarding as spec ref L30.560
A
10
Programme Policies to extreme weather Superstructure: Roof Superstructure: Concrete structure & staircases
SPECIAL INTEREST
9
Programme 6 Partitions Superstructure: Insitu frame concrete 7 M&E Superstructure: Stair 1 8 Raised courtyard Superstructure: Stair 2 External envelope
VISIT 6
8
43-50
Programme Superstructure: Insitu frame concrete External envelope Stairs Courtyard
VISIT 5
7
B
C
D
E
Ea
Eb
Ec
Ed
Ee
PROJECT NUMBER
SCALE
2588
1:50 @ A1
Jul-16
REVISION
STATUS
BY
E
Construction MLD
DRAWING NUMBER
220
DATE
This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
11
REFERENCES
103
1
I
NTRODUCTION TO PROJECT
1.1
B RIEF Confetti Institute of Creative Technologies is an institute offers opportunity to gain real practical experiences in music technology, gaming, film & television, radio and live event production. It is in partnership with Nottingham Trent University and they plan to run new degree courses in the near future together. According to this plan, there will be a growth of 700 students within 5 years and the space of the current building is not able to accommodate this amount of people.
ORIGINAL BUILDING
PROPOSED DESIGN
As the current building have very little space left vacant in, the project aim to allow 15% additional teaching spaces for flexibility. The required spaces are mainly traditional seminar spaces, computer suites and course specific spaces, such as TV & music recording studio.
2
1.2
CONCEPT
1 CLEAR & WELCOMING ENTRANCE Designed in 5 storey and with corten steel cladding, the building will stand out from the street and suggest a welcoming access.
2 SECURITY
The design aimed to link all the access point to the new main building. Reducing access points can ensure security more readily managed.
3 FUNCTIONALITY
Accommodate an addition of 700 students over a 5-year period. Having 17 teaching spaces at a sizes of 24+1 tutor , breakout spaces and facilities, such as reception and cafe.
3
CURRENT PROBLEM
ROOF TOP GARDEN
CONNECTING SURROUNDING BUILDINGS
ECOLOGY
4 ACCESSIBILITY
Ramps link the new designed building and the existing buildings, allowing equal access regardless to the physical ability of students and unlock more areas.
5 STUDENT EXPERIENCES
The design creates spaces for socializing and communicating, such as the cafe area. Visual connections to the city centre through openings also enhance the experiences of students.
6 SUSTAINABILITY
The design is registered with BREEAM and achieved an outstanding score of 86.43%. This confirm the building generates sustainable environment that can enhance the well-being of the people who works in. 4
1.3
P ROJECT
TEAM
CLIENT
PROJECT MANAGEMENT
ARCHITECT
CONTRACTOR
They provide the brief to the architect for design. They also spend money for the whole project. The building will be used by them eventually.
The project is managed by NTU as courses will be join hand with Confetti in the future. The project manager is stayed on site to keep the construction and project on track. It is also responsible in contacting parties related to certain issues.
The project is hand over to the architect in design stage. It is responsible to produce design that meet the brief of the client and propose possible programme and cost of the project.
They are responsible in constructing the building on site. They need to report their programme and physically build according to the architect design and drawings.
5
1.4
CONSTRUCTION
PROGRAMME
The programme mainly split into 3 phases:
1 DEMOLITION
2 MAIN CONTRACT
Clearing the existing building and prepare the ground for groundwork. Archaeology was discovered in this stage.
10 months duration to build the groundwork, superstructure,building envelope, M&E service and finishing.
Completed between Dec 2016 & Jan 2017 Archaeology : Jan 2017 to April 2017
Started date: 8 May 2017 End date: 11 June 2018
3 FIT OUT
Furniture, fittings , equipment and signages are put in to prepare for usage in the coming term. Test and final amendments are made if any problems occur. Complete in August 2018 Able to be used by students in the First week of September
CURRENT STAGE 6
A 1
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCCDCECFCG
Confetti
2 3 4
2017 2018
Month/year
March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
5 Task 6 Tender programme 7 Tender addendum information 8 Contract appointment 9 Technical Design stage 10 Planning conditions discharge Architectural, structural and civil to 11 stage 4 12 Subcontractor procurement Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling Stats connections, Frame, Cladding, 14 M&E Roof finishes, Lift installation, 15 Windows and external doors
OFF SITE
Internal partitions, Wall and ceiling 16 finishes
OFF SITE
17 Sanitery goods, Landscaping 18 Construction programme 19 Start on site 06-05-2017 Site possession, cabins and welfare, 20 Signage Top soil strip, reduce dig, Piling, 21 Ground beams, Lift pit foundation Insitu frame, PCC stairs between 22 floors up to roof deck 23 Steelwork lift shaft and roof Alterations to existing building, roof 24 protection Stair 2 : Ist fix M&E, dryline walls, mist 25 coat Stair 2 : 2nd fix M&E, decoration 26 staircase, suspended ceiling decoration Stair 2 : 3rd fix M&E, Balustrading and 27 handrails, 2nd fix joinery 28 External panels all levels 29 Facing brickwork all levels 30 Corten steel all levels 31 Curtain walling all levels Roof parapets, deck, insulation, 32 outlets, sedum roof 33 1st building air test
34 35
36 37
38 39
40 41
42 43
44 45
46 47
Ground floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Ground floor power on/ heat on First floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation First floor power on/ heat on Second floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Second floor power on/ heat on Third floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Third floor power on/ heat on Fourth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Fourth floor power on/ heat on Fifth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Fifth floor power on/ heat on Sixth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Sixth floor power on/ heat on
Stair 1 : M&E, Joinery, Decoration, 48 suspended ceiling, Balustrading
STAGE 2 PROGRAMME
The contractor set a programme of their work from January 2017 to June 2018. Works include before possessing the site, such as meeting the project team and sourcing building materials. The on site works starts from May 2018 when they possessed the site. The start date and end date of each task are stated in detail.
Final testing and commissioning, air 49 testing, final clean and snag
The whole construction programme should end in June 2018 for fit out programme.
External landscaping, snag and clean 50 externals 51 PRACTICAL COMPLETION 52
Month/year
March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
53
As the programme on the left is detailed for the contractors reference, it is quite complicated. This table above simplified and summarized the tasks and programme of it and will be used throughout the diary to indicate the progress of the programme.
7
2
P R E PA R AT I O N WORKS
S TA G E
2.1 A 1
2 PROGRAMME
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCCDCECFCGCHCICJ
Confetti
2 3 4
This chapter will focus on the preparation works that have done before construction.
2017 2018
Month/year
5 Task 6 Tender programme 7 Tender addendum information 8 Contract appointment 9 Technical Design stage
March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
The on site construction programme started in May 2017, but the preparation works have done before that in order to get ready for constructing the building and avoid mistakes or delay of works within the construction programme.
10 Planning conditions discharge Architectural, structural and civil to 11 stage 4 12 Subcontractor procurement Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling Stats connections, Frame, Cladding, 14 M&E Roof finishes, Lift installation, 15 Windows and external doors Internal partitions, Wall and ceiling 16 finishes 17 Sanitery goods, Landscaping 18 Construction programme 19 Start on site 06-05-2017
Tasks includes: • Finalizing and specifying design • Meeting tender & contractors • Sourcing materials and meeting subcontractors • Demolition of site • Groundwork and piling • Health and safety
Site possession, cabins and welfare, 20 Signage Top soil strip, reduce dig, Piling, 21 Ground beams, Lift pit foundation Insitu frame, PCC stairs between 22 floors up to roof deck 23 Steelwork lift shaft and roof Alterations to existing building, roof 24 protection Stair 2 : Ist fix M&E, dryline walls, mist 25 coat Stair 2 : 2nd fix M&E, decoration 26 staircase, suspended ceiling decoration Stair 2 : 3rd fix M&E, Balustrading and 27 handrails, 2nd fix joinery 28 External panels all levels 29 Facing brickwork all levels 30 Corten steel all levels 31 Curtain walling all levels Roof parapets, deck, insulation, 32 outlets, sedum roof 33 1st building air test
9
2.2
S PECIFYING
DESIGN The architect produces a document in the National Building Specification, NBS, to specify the construction details of the building. This is to allow the contractors to follow the standard building requirement of the nation that allows them to refer to certain documents and information. This also assures the client that the design is practical and every part of the building has achieved the general standard in terms of construction. The images on the left are extracted from the structural specification document that the architect provided.
10
MEETING
2.3
THE TEAM CONFETTI CQ CAMPUS Feasibility Report Revision (-) January 2016
NBS
FEASIBILITY STUDY REPORT
Documents are brought to discuss within the team of clients, architects and contractors to finalize and confirm the details of the construction before starting the construction programme. This is to allow every parties of the project knows the programme and details of the design. It also ensures they know which party is responsible to certain field so that they can contact one another when they need to deal with certain issues. Documents include:
National Building Specification document that specifies the detail of the building is in British standard.
Feasibility study report analyses the site and explained the brief, concept of the design and general schedule of the whole building
Construction programme explains how the
CONSTRUCTION PROGRAMME
COSTING
contractor complete tasks and meet the end date of the construction in detail.
Costing indicates the cost of the whole programme that the client is within their financial plan and avoids over budget in the construction period when design is needed to change.
11
2.4
DEMOLITION
1
3
2 3
Before demolishing
2
1
3 Existing buildings that were unfit for purpose were being removed
4
Put up barriers to protect pedestrian from demolition
5
Use loader to knock down the building
Clear away the ruins and empty the site to prepare for digging
12
2.5
GROUND
Stripping the soil is to ensure the sit is suitable for construction purpose. Further through reduce dig to remove any potential trouble-spots , such as bad ground, soft spots or other deleterious material at this stage to prevent having to reconstruct the whole project at the final stage when problems are found later in the programme.
Victorian & Georgian foundations
10 3 11 4 12 11 12 5 13 6 13 14 7 14 1 15 8 15 29 16 3 16 10 4 17 18 17 11 5 19 18 12 6 19 20 13 7 20 21 14 8 9 21 22 15 10 22 23 16 11 23 12 24 17 18 24 13 19 25
Planning conditions discharge Architectural, structural and civil to 2017 2018 stage 4 Architectural, structural and civil to Month/year March April May June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept Subcontractor procurement stage 4 Subcontractor Enabling Site set up, Service Task works,procurement disconnetions, Piling Enabling works,Groundworks, Site set up, Service Tender programme disconnetions, Groundworks, Piling Stats connections, Frame, Cladding, A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC M&E Stats connections, Cladding, Tender addendum Frame, information M&E Roof finishes, Lift installation, Windows andLift external doors Roof finishes, installation, Contract appointment Windows and external Technicalpartitions, Design stage Internal Walldoors and ceiling finishes partitions, Wall and ceiling Internal 2017 2018 finishes Planning conditions discharge Month/year March April May June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept Sanitery goods,structural Landscaping Architectural, and civil to Construction Sanitery Landscaping stage 4 goods,programme Task Start onprogramme site 06-05-2017 Construction programme Subcontractor procurement Tender Start on site 06-05-2017 Site possession, cabins Enabling works, Site setand up,welfare, Service Signage disconnetions, Groundworks, Piling Site possession, cabins and welfare, Tender addendum information Signage Top strip, reduce dig, Cladding, Piling, Statssoil connections, Frame, Ground Lift pitdig, foundation M&Esoil beams, Top strip, reduce Piling, Contract appointment Technical Design stage Ground beams, pit foundation Insitu frame, PCC stairs between Roof finishes, LiftLift installation, floors up to roof deck Windows and external Insitu frame, PCC stairsdoors between Planning conditions discharge floors up to roof deck Internal partitions, Wall and ceiling Steelwork and roof finishes lift shaft Architectural, structural and civil to stage 4 Steelwork lift and building, roof Alterations toshaft existing roof Subcontractor procurement protection Sanitery goods, Landscaping Alterations to existing building, roof Construction Enabling works, Site dryline set up, Service protection Stair 2 : Ist fix programme M&E, walls, mist disconnetions, Groundworks, Piling Start 2on: Ist sitefix06-05-2017 coat Stair M&E, dryline walls, mist
WORKS Confetti
Sometime, valuable artefacts and archaeologies are discovered under the ground that may provide new resources for historians to study about the local heritage. Stats connections, Frame, Site possession, cabins andCladding, welfare, coat M&E Signage Stair 2 : 2nd fix M&E, decoration staircase, suspended ceiling decoration Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Top soil strip, reduce dig, Piling, Windows and external doors staircase, suspended ceiling decoration Ground beams, Lift pit foundation Stair : partitions, 3rd fix M&E, Balustrading Internal Wall and ceilingand Insitu2frame, PCC stairs between handrails, 2nd fix joinery 27 16 Stair : 3rd fix M&E, Balustrading and floors2 up to roof deck 22 finishes 27 handrails, 2nd fix joinery External panels all levels 28 goods, Landscaping 17 Steelwork lift shaft and roof 23 Sanitery 18 External panels all levelsbuilding, roof 28 Construction Alterations toprogramme existing onbrickwork site 06-05-2017 19 Facing all levels 29 protection 24 Start 25 14 20 26 15 26 21
Medieval trenches
cabins and welfare, Facing all dryline levels 29 Site Stairpossession, 2 brickwork : Ist fix M&E, walls, mist 20 coat steel all levels 25 Signage Corten 30 soilsteel strip,allreduce Corten levels dig, Piling, 30 Top beams, Liftlevels pitdecoration foundation 21 Stair 2 : walling 2nd fix all M&E, Curtain 31 Ground staircase, suspended ceiling decoration 26 Insitu frame, PCC stairs between walling deck, all levels 31 Curtain Roof parapets, insulation, 22 floors up to roof deck outlets, sedum deck, roof insulation, 32 Roof parapets, Stairbuilding 2 : sedum 3rd air fix roof M&E, Balustrading and 1st test 33 outlets, 32 handrails, 2nd fix joinery 27 Steelwork lift shaft and roof 23 1st building air test 33 Ground floor : Internal finishes, M&E, Alterations to existing building, fire stopping, ceilings,roof Ground floor suspended : Internal finishes, M&E, 24 External panels all levels 28 protection Joinery 1st and 2nd fix, decoration fire stopping, suspended ceilings, and :1st Ist and fix installation M&E, dryline walls, mist tiling,2sanitary 34 Stair Joinery 2nd fix, decoration and 25 Facingsanitary brickwork all levels 29 coat Ground floor power on/ heat on 35 tiling, installation 34 First floor : Internal floor powerfinishes, on/ heatM&E, on fire 35 Ground 2 : steel 2nd fix decoration stopping, suspended ceilings, Joinery First floor : Internal finishes, M&E, fire Corten all M&E, levels 30 Stair suspended ceiling and decoration 26 staircase, 1st and 2nd fix, decoration tiling, stopping, suspended ceilings, Joinery sanitary installation 36 1st and 2nd fix, all decoration walling levels and tiling, 31 Curtain First 2floor power on/ Balustrading heat on 37 Stair sanitary installation 36 : 3rd fix M&E, and Roof parapets, deck, insulation, Second floor : fix Internal finishes, First floor power on/ heat on M&E, 37 handrails, 2nd joinery 27 outlets, sedum roof 32 fire stopping, ceilings,M&E, Second floor :suspended Internal finishes, 1st building air test 33 Joinery 1st and 2nd fix, decoration and fire stopping, suspended panels all levels ceilings, 28 External tiling, sanitary 38 Joinery Ground floor Internal finishes, M&E, 1st and:installation 2nd fix, decoration and Second floor power on/ heat on 39 tiling, fire stopping, suspended ceilings, sanitary installation 38 brickwork all fix, levels 29 Facing Third : Internal finishes, M&E, and Joineryfloor 1st and 2nd decoration floor power on/ heat on 39 Second fire stopping, suspended ceilings, tiling, sanitary installation 34 Third floor : Internal finishes, M&E, steel all levels 30 Joinery 1st and 2nd fix, Ground floor power on/decoration heat on and 35 Corten fire stopping, suspended ceilings, tiling, sanitary installation 40 Joinery First floor Internal finishes, M&E, fire 1st :and 2nd fix, decoration and Third floor power on/ heat on 41 Curtain stopping, suspended ceilings, Joinery tiling, sanitary installation 40 walling all levels 31 Fourth floor : Internal finishes, 1st andfloor 2ndpower fix, decoration tiling, on/insulation, heat and on M&E, 41 Third Roof parapets, deck, fire stopping, ceilings, sanitary installation 36 Fourth floor : suspended Internal sedum roof finishes, M&E, 32 outlets, 1stpower and 2nd decoration and Firststopping, floor on/fix,heat on 37 Joinery ceilings, 1st building airsuspended test 33 fire tiling, sanitary 42 Joinery Second floor : installation Internal M&E, 1st and 2nd fix, finishes, decoration and floorpower : Internal Fourth floor on/finishes, heat on M&E, 43 Ground fire stopping, suspended ceilings, tiling, sanitary installation 42 fire stopping, suspended ceilings, Fifth floor Internal finishes, Joinery 1st: and 2nd fix, decoration and floor power on/ heat M&E, on fire 43 Fourth 1stsuspended andinstallation 2nd fix, decoration and stopping, ceilings, Joinery tiling,floor sanitary 38 Joinery Fifth : Internal finishes, M&E, fire sanitary installation 34 1st and 2nd fix, decoration and Second floor power on/ heat ontiling, 39 tiling, stopping, suspended ceilings, Joinery floor power on/ heat M&E, on 35 sanitary installation 44 Ground Third :fix, Internal finishes, 1st andfloor 2nd decoration and tiling, First floor : Internal finishes, M&E, fire 45 sanitary Fifth floor power on/ heat on fire stopping, suspended ceilings, installation 44 stopping, suspended ceilings, Joinery Sixth floor : Internal finishes, M&E, fire Joinery 1st and 2nd fix, decoration and 45 Fifth floor power on/ heat on andsanitary 2nd fix,installation decoration tiling, stopping, ceilings,and Joinery tiling, 40 1st Sixth floorsuspended : Internal finishes, M&E, fire installation 36 1st andfloor 2nd fix, decoration tiling, Third power on/ heat and on 41 sanitary stopping, suspended ceilings, Joinery floor power on/ heat on M&E, 37 sanitary installation 46 First Fourth : Internal finishes, 1st and floor 2nd fix, decoration and tiling, Second floor : Internal finishes, M&E,
Cave
13
Pottery
2.6
A RC H A E O LO G Y Cave
Builders uncovered a network of caves under the ground of the site and it was claimed that it will completely changed Nottingham’s history from the medieval period right through to the 19th century.
Kiln
The enclosed ditches and square rock cut pits were filled with pottery, glass and roof tiles which lead the archaeologists to think that in Medieval times people were making pottery pretty close to the Confetti site. Confetti’s Director of Operations, Greg Marshall said “It seems quite appropriate that our new digital media hub could be built on a site where a creative industry was practiced hundreds of years ago.” Substantial quantities of medieval pots and tiles have been found and taken away for study and preservation. The findings were completed in April 2017.
14
2.7
P ILING,
10 3 11 4 12 11 12 5 13 6 13 14 7 14 1 15 8 15 29 16 3 16 10 4 17 18 17 11 5 19 18 12 6 19 20 13 7 20 21 14 8 9 21 22 15 10 22 23 16 11 23 12 24 17 18 24 13 19 25
Planning conditions discharge Architectural, structural and civil to 2017 2018 stage 4 Architectural, structural and civil to Month/year March April May June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept Subcontractor procurement stage 4 Subcontractor Enabling Site set up, Service Task works,procurement disconnetions, Piling Enabling works,Groundworks, Site set up, Service Tender programme disconnetions, Groundworks, Piling Stats connections, Frame, Cladding, A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC M&E Stats connections, Cladding, Tender addendum Frame, information M&E Roof finishes, Lift installation, Windows andLift external doors Roof finishes, installation, Contract appointment Windows and external Technicalpartitions, Design stage Internal Walldoors and ceiling finishes partitions, Wall and ceiling Internal 2017 2018 finishes Planning conditions discharge Month/year March April May June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept Sanitery goods,structural Landscaping Architectural, and civil to Construction Sanitery Landscaping stage 4 goods,programme Task Start onprogramme site 06-05-2017 Construction programme Subcontractor procurement Tender Start on site 06-05-2017 Site possession, cabins Enabling works, Site setand up,welfare, Service Signage disconnetions, Groundworks, Piling Site possession, cabins and welfare, Tender addendum information Signage Top strip, reduce dig, Cladding, Piling, Statssoil connections, Frame, Ground Lift pitdig, foundation M&Esoil beams, Top strip, reduce Piling, Contract appointment Technical Design stage Ground beams, pit foundation Insitu frame, PCC stairs between Roof finishes, LiftLift installation, floors up to roof deck Windows and external Insitu frame, PCC stairsdoors between Planning conditions discharge floors up to roof deck Internal partitions, Wall and ceiling Steelwork and roof finishes lift shaft Architectural, structural and civil to stage 4 Steelwork lift and building, roof Alterations toshaft existing roof Subcontractor procurement protection Sanitery goods, Landscaping Alterations to existing building, roof Construction Enabling works, Site dryline set up, Service protection Stair 2 : Ist fix programme M&E, walls, mist disconnetions, Groundworks, Piling Start 2on: Ist sitefix06-05-2017 coat Stair M&E, dryline walls, mist
GROUND B E A M S & L I F T P I T F O U N D AT I O N Confetti
Steel reinforcing mesh Concrete
Earth
Stats connections, Frame, Site possession, cabins andCladding, welfare, coat M&E Signage Stair 2 : 2nd fix M&E, decoration staircase, suspended ceiling decoration Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Top soil strip, reduce dig, Piling, Windows and external doors staircase, suspended ceiling decoration Ground beams, Lift pit foundation Stair : partitions, 3rd fix M&E, Balustrading Internal Wall and ceilingand Insitu2frame, PCC stairs between handrails, 2nd fix joinery 27 16 Stair : 3rd fix M&E, Balustrading and floors2 up to roof deck 22 finishes 27 handrails, 2nd fix joinery External panels all levels 28 goods, Landscaping 17 Steelwork lift shaft and roof 23 Sanitery 18 External panels all levelsbuilding, roof 28 Construction Alterations toprogramme existing onbrickwork site 06-05-2017 19 Facing all levels 29 protection 24 Start 25 14 20 26 15 26 21
Steel reinforcing bars
Concrete
The site was covered by soil with trenches to place steel reinforcements. Concrete was then pour into the pit and let dry to form a solid foundation as the base of the building.
cabins and welfare, Facing all dryline levels 29 Site Stairpossession, 2 brickwork : Ist fix M&E, walls, mist 20 coat steel all levels 25 Signage Corten 30 soilsteel strip,allreduce Corten levels dig, Piling, 30 Top beams, Liftlevels pitdecoration foundation 21 Stair 2 : walling 2nd fix all M&E, Curtain 31 Ground staircase, suspended ceiling decoration 26 Insitu frame, PCC stairs between walling deck, all levels 31 Curtain Roof parapets, insulation, 22 floors up to roof deck outlets, sedum deck, roof insulation, 32 Roof parapets, Stairbuilding 2 : sedum 3rd air fix roof M&E, Balustrading and 1st test 33 outlets, 32 handrails, 2nd fix joinery 27 Steelwork lift shaft and roof 23 1st building air test 33 Ground floor : Internal finishes, M&E, Alterations to existing building, fire stopping, ceilings,roof Ground floor suspended : Internal finishes, M&E, 24 External panels all levels 28 protection Joinery 1st and 2nd fix, decoration fire stopping, suspended ceilings, and :1st Ist and fix installation M&E, dryline walls, mist tiling,2sanitary 34 Stair Joinery 2nd fix, decoration and 25 Facingsanitary brickwork all levels 29 coat Ground floor power on/ heat on 35 tiling, installation 34 First floor : Internal floor powerfinishes, on/ heatM&E, on fire 35 Ground 2 : steel 2nd fix decoration stopping, suspended ceilings, Joinery First floor : Internal finishes, M&E, fire Corten all M&E, levels 30 Stair suspended ceiling and decoration 26 staircase, 1st and 2nd fix, decoration tiling, stopping, suspended ceilings, Joinery sanitary installation 36 1st and 2nd fix, all decoration walling levels and tiling, 31 Curtain First 2floor power on/ Balustrading heat on 37 Stair sanitary installation 36 : 3rd fix M&E, and Roof parapets, deck, insulation, Second floor : fix Internal finishes, First floor power on/ heat on M&E, 37 handrails, 2nd joinery 27 outlets, sedum roof 32 fire stopping, ceilings,M&E, Second floor :suspended Internal finishes, 1st building air test 33 Joinery 1st and 2nd fix, decoration and fire stopping, suspended panels all levels ceilings, 28 External tiling, sanitary 38 Joinery Ground floor Internal finishes, M&E, 1st and:installation 2nd fix, decoration and Second floor power on/ heat on 39 tiling, fire stopping, suspended ceilings, sanitary installation 38 brickwork all fix, levels 29 Facing Third : Internal finishes, M&E, and Joineryfloor 1st and 2nd decoration floor power on/ heat on 39 Second fire stopping, suspended ceilings, tiling, sanitary installation 34 Third floor : Internal finishes, M&E, steel all levels 30 Joinery 1st and 2nd fix, Ground floor power on/decoration heat on and 35 Corten fire stopping, suspended ceilings, tiling, sanitary installation 40 Joinery First floor Internal finishes, M&E, fire 1st :and 2nd fix, decoration and Third floor power on/ heat on 41 Curtain stopping, suspended ceilings, Joinery tiling, sanitary installation 40 walling all levels 31 Fourth floor : Internal finishes, 1st andfloor 2ndpower fix, decoration tiling, on/insulation, heat and on M&E, 41 Third Roof parapets, deck, fire stopping, ceilings, sanitary installation 36 Fourth floor : suspended Internal sedum roof finishes, M&E, 32 outlets, 1stpower and 2nd decoration and Firststopping, floor on/fix,heat on 37 Joinery ceilings, 1st building airsuspended test 33 fire tiling, sanitary 42 Joinery Second floor : installation Internal M&E, 1st and 2nd fix, finishes, decoration and floorpower : Internal Fourth floor on/finishes, heat on M&E, 43 Ground fire stopping, suspended ceilings, tiling, sanitary installation 42 fire stopping, suspended ceilings, Fifth floor Internal finishes, Joinery 1st: and 2nd fix, decoration and floor power on/ heat M&E, on fire 43 Fourth 1stsuspended andinstallation 2nd fix, decoration and stopping, ceilings, Joinery tiling,floor sanitary 38 Joinery Fifth : Internal finishes, M&E, fire sanitary installation 34 1st and 2nd fix, decoration and Second floor power on/ heat ontiling, 39 tiling, stopping, suspended ceilings, Joinery floor power on/ heat M&E, on 35 sanitary installation 44 Ground Third :fix, Internal finishes, 1st andfloor 2nd decoration and tiling, First floor : Internal finishes, M&E, fire 45 sanitary Fifth floor power on/ heat on fire stopping, suspended ceilings, installation 44 stopping, suspended ceilings, Joinery Sixth floor : Internal finishes, M&E, fire Joinery 1st and 2nd fix, decoration and 45 Fifth floor power on/ heat on andsanitary 2nd fix,installation decoration tiling, stopping, ceilings,and Joinery tiling, 40 1st Sixth floorsuspended : Internal finishes, M&E, fire installation 36 1st andfloor 2nd fix, decoration tiling, Third power on/ heat and on 41 sanitary stopping, suspended ceilings, Joinery floor power on/ heat on M&E, 37 sanitary installation 46 First Fourth : Internal finishes, 1st and floor 2nd fix, decoration and tiling, Second floor : Internal finishes, M&E,
15
S ITE
POS SES SION, WELFARE, SIGNAGE
Various signages are marked in the construction site and especially at the entrances. This can remind both workers and visitors to be cautious in and around the site.
measure. Access from Beck Street is mainly used by the contractors and workers. This is to control the number of people entering the site to ensure safety and minimize accidents happen in the site. Everyone who come or leave the site need to sign-in and out.
There are 2 access points in the site, from Covent street and Beck Street. As Covent street is relatively wide, its main purpose is for deliveries of materials and storing them as there are limited space for storage in the site. It is therefore closed and blocked to the public as a safety
753
753
758
1760
3011
3
1184
3311
Ground Floor 35.630
5729
ED 03
3
5
1135
2597.5
ID 017
3947.5(17 1/2 bricks) U/S 2.76
DP
215
17
eq.
5
4
3
2
U/S 2.78
CH 3.36
SH 0.19 HH 3.03
U/S 3.14
C
1492
D
7718
E
450
AVCL
503.5
522
522
2
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 Knauf Windliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns
SP 2.23
190 1in12 503.5
468.5
1
30mm Deep Corten Cassettes 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Insulation Wall Construction - Corten Outer / SFS Inner 12.5 Knauf Sheathing Board 30mm DeepWindliner Corten Cassettes 150mmAirSFS Zone, withRails RW45 Insulation 69mm Gap withFilled Vertical on HH Brackets 25mm Battens to form Service Void 150mm Rockwool DuoSlab Insulation 12.5mm Plywood and Sheathing 12.5mm GB Plasterboard and skim + exposed concrete columns 12.5 Knauf Windliner Board 150mm SFS Zone, Filled with RW45 Insulation 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns Wall Construction - Corten Outer / RC Wall Inner 30mm Deep Corten Cladding Panel 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish FFL 35.47
Key Walls
4
5
2
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish Existing Wall HE Centre 215mm Existing Solid brick wall 25mm cavity Existing Walldepth HE Centre Metal studs at 600mm centres 215mm Existing Solid brick wall- K10/165A 12.5mmcavity Plasterboard 25mm depth Metal studs at 600mm centres - K10/165A 12.5mm Plasterboard
24/08/17 18/08/17 30/05/17 17/08/17 30/05/17 12/05/17
Change to the slab edge following the SE info Amendments to drawings following the Cladding info Change to the 1st floor café/kitchen area Amendments to HEC stair 2 following the SE info Amendments to drawings following the Topo Survey and SE info
MLD MLD MLD MLD MLD MLD
F E D C B A
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
Change to doors and Stair 1 Lobby Spec Refs added Amendments to drawings Amendments to drawings Amendments to drawings Amendments to drawings
MLD MLD MLD MLD MLD MLD
DESCRIPTION
BY
REV. DATE
F
G
H
14 13 12 LivePanel, Living Green Wall 11 102.5 Black Brick 50mm cavity 10 100mm Benchmark Quadcore Karrier Pane 9 100mm 'Tarmac Hemelite' 100mm fairfaced medium density blockwork 8 Green Wall as spec ref Q37.125
Existing Wall Confetti Insulation to be agreed with Structural Engineer K 10/185 plasterboard + skim as dabs onto RC wall
Access from Beck Street 10
8
600
ID 001, etc W001, etc ED01, etc IS01, etc
MLD MLD MLD MLD
Architects, Landscape & Interior Design
PARTITION Wall Type - K10/115 2x12.5mm SoundBloc Metal Studs at 600mm centres 100 Rockwood RW360 insulation in the cavity 2x12.5mm SoundBloc
- Internal Door Codes (Refer to drawing 320) - Window Codes (Refer to drawings 322-323) Green Wall as specCodes ref Q37.125 - External Door (Refer to drawings 323) - Internal Screene Codes (Refer to drawings 321)
LivePanel, Living Green Wall 102.5 Black Brick 50mm cavity 100mm Benchmark Quadcore Karrier Pane 100mm 'Tarmac Hemelite' 100mm fairfaced medium density blockwork
T
0115 841 8418
E
design@allanjoycearchitects .co.uk
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group 32.78
UP Wall Construction CortenPLAN Outer / SFS Inner PROPOSED GROUND FLOOR - GA -1:50
K J II H G
Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1
16-20 Bath Street, Nottingham NG1 1DF
4959
6128
Wall Construction - Brickwork Outer / SFS Inner HH 2.05 102.5 Black Brick as F10/110 SH 0.87 50mm Air Gap with Brick Ties and Support Brackets DH 2.05 150mm Rockwool DuoSlab Insulation HH 2.05 12.5 Knauf Windliner Sheathing 0.87 SHBoard 150mm DH SFS 2.05 Zone, Filled with RW45 Insulation 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns
Ground Floor 35.440
Amendments to substation and meeting room layout Amendments to substation layout Amendments to substation layout
eq.
B
1646
X017 PLANT ROOM 30 m2
04/01/18 19/12/17 08/11/17 18/09/17
H003
G 223
3562 SCH 2.83
A
C 222
FFL 35.44
2279
Ground Floor 35.630
Col
lery H002 Gal CH 2.99
35.43
ID 018
ED 04 Ground Floor 35.048
1800
ID 019
CH 2.99
X010 STAIR 2
Lift
CH 2.76
35.47
point
X011 STAIR 2 LOBBY
1
SH 0.88 HH 2.97
6
Ee
O N M L
SH 0.88 HH 2.97
7
SH 0.88 HH 2.97
8
DH 2.04
9
SH 0.86 HH 2.03
10
U/S 2.27
FFL 35.63
Ground Floor 35.630
DH 2.05
THL 35.64
ED 14
Insertion
STN/142 35.51
314
AVCL
1184 2176
1736
3153
1736 794
X020 MTG 3 9 m2
2806
124
2810
U/S 2.37
3
224
3436
6467
2339
800 600 1135 1095 400 800
4720
3109
130
4642
5045
1696
1000 1200 400
10932
1110
925
640 800 600
3650
A
220
3554 2950
B
221
628
2707
837
Ground Floor 34.740
X014 SERVER 16Ground m2 Floor 35.048
32.86
420
1010
HH 2.57 SH 1.23
20
HH 2.98 SH 1.15
19
CH 2.57
18
34.63
17
e
16
ir Storag
15
ID 010
NEW IS 004
X004 MTG 2 8 m2
X018 NEW STORE (86m2)
221 B
14
Under Sta
13
CH 2.84
12
DH 2.03
11
DH 1.97
10
CH 3.68
9
X002 MTG 1 9 m2
36.60
8
1567
Ground Floor 35.048
ID 015
CH 3.39
7
X012 clnrs cpbd 3 m2
34.71
6
NEW ID 021
ID 012
34.48
5
2000
ID 009
1/2 bricks)
4
IS 003
124
NEW DOOR
Ground Floor 35.048
X018 Staff Corridoor
1in12
Blocked
7752.5(34
35.61
3
IS 002
2000
ID 007
X015 COMMS 13 m2
Ed
Ground Floor 35.630
Ground Floor 35.630
5000
Ground Floor 34.740
3930
191
Mechanical riser
ID 016
2
ID 011
1732
378
Ec
11891
2000
1094
422
1
Eb 1215
220 A
1235
Ea
300
Indicative location of reception desk by others
X003 OFFICE 34 m2
STN/128 36.04
3a
W 01
312
4
ID 013 1736
287
X019 Mtg cpbd
ID 014 1010
UP 884 1in12
1in12
1828 1010 ID 008
4212
Electrical riser
7340
34.66
1930
Secure line
34.50
Ground Floor 35.630
MMC cab
FFL 34.74
7358
1in15
1500
2552
1in12
741
IS 001
CH 2.37
2a
3624
363
1010
Ground Floor 35.048
5000
3391
ID 006
Ground Floor 35.464
2500
2
455
1010
224
1110
1000
1
3550
499
ID 003
ID 002
inet
FFL
Ground Floor 35.630
2
3
300
ID 005
505
867
U/S 3.14
34.68
4
ID 001
DH 2.05
Ground Floor 35.464
X005 WC LOBBY
1
DH 2.10
5
1977
X009 STAIR 1 LOBBY
3700
walls 500
17
Ground Floor 35.464
1010
1280 1500
611
17 m2
ID 004
34.74
6
X001 RECEPTION 130 m2
Ground Floor 35.464
15 m2
Ground Floor 35.048
6 1600 34.7
4742
7
34.69
8
X006 WC CHANGING (MALE WC)
1696
X008 STAIR 1
9
X007 WC CHANGING (FEMALE WC)
rk 140 Blockwo
34.69
10
34.61
W 01
3200
1a
310
3
X013 CONTROL ROOM 8 m2
5038
Ground Floor 35.464
13
12
10
1000
11
X016 SUBSTATION 20 m2
2001
3550
ED 02
W 02
4
W 03
4
ED 01
1
9215
Step +0.0
ED 12
300
1248
579 73
1000
1200
400
800
600
bric
0 to Fit
approx. 250
552
1810
2
50
10534 1000
1000
F
300 ks)
34.74
Ground Floor 35.600
2000
2951
E 15985(71
34.70
3160
34.82
35.20
Ground Floor 35.300
73
923
4452
4550
D 301
1000
Eb
34.90
G
223
Ee
6752
Ed
421
Ec
35.10
Ea
422
35.00
E
35.09
1492
35.20
35.46
35.60
35.70
35.71
C 222
D
1646
35.24
C
3562
35.32
B
2279
35.28
35.46
35.63
35.80 A
35.12
35.72
35.86
35.91
1
deliveries in Main entrancentfoStr reet Cove
3783
2.8
17
3
PROJECT
Confetti CQ Campus 60 minutes fire resistance Wall
Cabin
Plasterboard on dabs to achieve min 60 minutes fire rating Existing wall
DRAWING
Ground Floor GA Wall Types and Setting Out PROJECT NUMBER
SCALE
2588
1:50 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
DATE
BY
201
O
Construction MLD
This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
16
2.9
COPING 3
WITH CONTEXT
There are cabins and borrowed rooms from surrounding buildings for workers to rest and plan their daily and weekly programme. (Refer to the plan in the previous page for its location)
Altered accesses for existing buildings
As the construction is causing noise, dust and blocking some of the accesses, there is a need to corporate with the surrounding buildings to make sure they are still functional under the construction of the new building.
USERS
The surrounding buildings include High Education Centre and Confetti ICT, which are operated as schools in term time. Therefore, the construction programme need to cope with the timetable of the schools to minimize the effects of noise on the students.
ACCESSES
They need to make sure the accesses are not blocking the circulation of buildings as well as provides alternative access to the surroundings.
17
2.10
H E A LT H
& SAFETY: EQUIPMENTS EQUIPMENTS
HELMET
People who enters the site, no matter the workers or visitors, must wear Personal Protective Equipment (PPE): Helmet, Vast & boots As hot concrete is being poured in the construction to form slabs, extra protective equipments should be wore, such as gloves, mask & googles.
VAST
Not every workers on the site are permitted to operate a certain machine, such as the concrete pump and the crane. The contractors ask a worker who is specified to that machine to come to the site and operate it. They need to be skilful in handling that machinery as they know the danger and have the capability to operate it safely. For visitors that go into the site, they must have a site induction to know the potential dangers and ensure their safety.
GLOVES
18
2.11
H E A LT H
& SAFETY: FIRE ESCAPE
SIGNAGE
In case of a fire, a temporary fire escape plan is set to deal with the accident.
FIRE ALARM
The fire alarm is linked to the surrounding buildings in order to alert everyone for evacuating to the outdoor.
FIRE POINTS
There are multiple mobile fire points that have fire extinguishers and instructions on how to use them. The plan of escape route is also nearby to let people know where they can escape to. 60min compartment floors fire separated form the existing adjoining building by compartment walls and doors Each staircase has additional fire and smoke protection for an hour, ensuring both stairs can stay in play in the event of a fire. Building is classified as Class 5: Assembly and Recreation, therefore the maximum travel distances is 18m/ 45m
19
3
S ITE
VISIT 1
Date: 17 October 2017 Weather: Sunny with wind Temperature: 11 °C People on site: About 30
• Project manager
• Contractors
• Workers
• Students and tutors
3 4
2017 2018
Month/year
March
5 Task 6 Tender programme
April
May
June
July
August Sept
S TA G E
3.1
7 Tender addendum information 8 Contract appointment 9 Technical Design stage
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
2 PROGRAMME
10 Planning conditions discharge Architectural, structural and civil to 11 stage 4 12 Subcontractor procurement Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling Stats connections, A Frame, Cladding,
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCCDCECFCGCHCICJ
Confetti
14 M&E 1 Roof finishes, Lift installation, 15 2 Windows and external doors 3 Internal partitions, Wall and ceiling 16 finishes 4 Month/year Sanitery goods, Landscaping 17 5 Task Construction programme 18 6 Tender programme 19 Start on site 06-05-2017 Site possession, cabins and welfare, 7 Tender addendum information 20 Signage soil strip, reduce dig, Piling, Contract appointment 8 Top DesignLift stage 9 Technical Ground beams, pit foundation 21 Insitu frame, PCC stairs between Planning discharge 10 upconditions to roof deck 22 floors Architectural, structural and civil to stage 4 11 lift shaft and roof 23 Steelwork procurement 12 Subcontractor Alterations to existing building, roof works, Site set up, Service protection 24 Enabling Groundworks, Piling 13 disconnetions, Stair 2 : Ist fix M&E, dryline walls, mist coat connections, Frame, Cladding, 25 Stats 14 M&E Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windows suspended and external doors 15 ceiling decoration 26 staircase, Internal partitions, Wall and ceiling finishes 16 Stair 2 : 3rd fix M&E, Balustrading and 27 handrails, 2nd fix joinery 17 18 28 19
Sanitery goods, Landscaping Construction External panelsprogramme all levels Start on site 06-05-2017
possession, and welfare, Facing brickworkcabins all levels 29 Site 20 Signage soilsteel strip,allreduce Corten levels dig, Piling, 30 Top 21 Ground beams, Lift pit foundation frame, PCC Curtain walling all stairs levels between 31 Insitu 22 floors up to roof deck Roof parapets, deck, insulation, 32 outlets, sedum roof 23 1st buildinglift airshaft test and roof 33 Steelwork Alterations to existing building, roof Ground floor : Internal finishes, M&E, 24 protection fire stopping, suspended ceilings, Stair 2 :1st Ist and fix M&E, dryline walls, mist Joinery 2nd fix, decoration and 25 tiling, sanitary installation 34 coat 35 Ground floor power on/ heat on Stair 2 : 2nd fix M&E,finishes, decoration First floor : Internal M&E, fire suspended ceilings, ceiling decoration 26 staircase, stopping, suspended Joinery 1st and 2nd fix, decoration and tiling, sanitary installation 36 Stair 2 : 3rd fix M&E, Balustrading and 37 handrails, First floor 2nd power on/ heat on fix joinery 27 Second floor : Internal finishes, M&E, fire stopping, suspended panels all levels ceilings, 28 External Joinery 1st and 2nd fix, decoration and 38 tiling, sanitary installation 29 Facing brickwork all levels 39 Second floor power on/ heat on Third floor : Internal finishes, M&E, steel all levels ceilings, 30 Corten fire stopping, suspended Joinery 1st and 2nd fix, decoration and 40 Curtain tiling, sanitary wallinginstallation all levels 31 41 Third floor power on/insulation, heat on Roof parapets, deck, : Internal outlets,floor sedum roof finishes, M&E, 32 Fourth stopping,airsuspended ceilings, 1st building test 33 fire
2017 2018 March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
According to the programme of the contractors, the following tasks should be finished or in progress on 17 th October. Tasks are expected finished: • Site possession, cabins and welfare,Signage • Top soil strip, reduce dig, Piling,Ground beams, Lift pit foundation • Alterations to existing building, roof protection • Stair 2 : 1st fix M&E, dryline walls, mist coat • Stair 2 : 2nd fix M&E, decoration staircase, suspended ceiling decoration • Stair 2 : 3rd fix M&E, Balustrade and handrails, 2nd fix joinery Task are expected in progress: • Insitu frame, PCC stairs between floors up to roof deck • External panels all levels
21
3.2
I NSITU
13 Groundworks, 10 disconnetions, Planning conditions discharge Piling Stats connections, Frame, Cladding, Architectural, structural and civil to 14 stage 4 11 M&E 12 Roof Subcontractor procurement finishes, Lift installation, and external 15 Windows Enabling works, Site setdoors up, Service disconnetions, Groundworks, Piling 13 Internal partitions, Wall and ceiling 16 finishes Stats connections, A Frame, Cladding,
FRAME CONCRETE 14 1 17 18 15 2 19 3
Confetti
M&E
Sanitery goods, Landscaping Roof finishes, Lift installation, Construction Windows and programme external doors Start on partitions, site 06-05-2017 Internal Wall and ceiling
possession, cabins and welfare, finishes 16 Site 4 Month/year Signage 20
Steel frame
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC
2017 2018 March
April
May
June
July
August Sept
Top soil goods, strip, reduce dig, Piling, Sanitery Landscaping 17 5 Task Construction programme 18 Ground beams, Lift pit foundation 21 6 Tender programme site 06-05-2017 19 Start Insitu on frame, PCC stairs between upaddendum to roofcabins deck 22 Site possession, and welfare, 7 floors Tender information 20 Signage Steelwork lift shaft anddig, roof 23 soil strip, reduce Piling, 8 Top Contract appointment 9 Technical Design stage Ground beams, Lift pit building, foundation 21 Alterations to existing roof protection 24 Insitu frame, PCC stairs between 10 conditions discharge floors tofix roof deck 22 Planning Stair 2up : Ist M&E, dryline walls, mist structural and civil to coat 25 Architectural, 4 11 Steelwork lift shaft and roof 23 stage 12 Subcontractor procurement Stair 2 : 2ndtofixexisting M&E, decoration Alterations building, roof works, Site set up, decoration Service staircase, suspended ceiling 26 protection 24 Enabling disconnetions, Groundworks, Piling 13 Stair 2 : Ist fix M&E, dryline walls, mist Frame, Cladding,and Stair : 3rd fix M&E, Balustrading coat 2connections, 25 Stats 14 handrails, 2nd fix joinery 27 M&E Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windowspanels and external doors 15 suspended ceiling decoration 26 staircase, External all levels 28 Internal partitions, Wall and ceiling 16 Stair 2 brickwork : 3rd fix M&E, Balustrading and Facing all levels 29 finishes 27 handrails, 2nd fix joinery
PROCESS OF INSITU CONCRETE SLAB 1 Place steel reinforcement mesh on the steel decking.
17 30 18 28 19 31 29 20 32 30 33 21 31
Sanitery goods, Corten steel all Landscaping levels Construction External panelsprogramme all levels Start on site 06-05-2017 Curtain walling all levels Site possession, cabins and welfare, Facing brickwork all levels Roof parapets, deck, insulation, Signage outlets, sedum roof Top soilsteel strip, Corten levels dig, Piling, 1st building airallreduce test Ground beams, Lift pit foundation Ground floor : Internal finishes, M&E, Insitu frame, PCC Curtain walling all stairs levels between fire stopping, suspended ceilings, floors up to roof deck Joinery 1st and deck, 2nd fix, decoration and Roof parapets, insulation, tiling, sanitary outlets, seduminstallation roof Steelwork lift Ground floor power on/roof heat on 1st building airshaft test and Alterations to existing building, roof First floor : Internal finishes, M&E, fire Ground floor : Internal finishes, M&E, protection stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st and 2nd fix,M&E, decoration and tiling, Stair 2 :1st Ist and fix dryline walls, mist Joinery 2nd fix, decoration and sanitary installation coat tiling, sanitary installation First floor power on/ heat on Ground floor power on/ heat on Second : Internal finishes, M&E, Stair floor 2 : floor 2nd fix M&E,finishes, decoration First : Internal M&E, fire fire stopping, suspended ceilings, staircase, suspended ceiling stopping, suspended ceilings,decoration Joinery Joinery 1st and 2nd fix, decoration and 1st and 2nd fix, decoration and tiling, tiling, sanitary installation sanitary installation Stair 2 : 3rd fix M&E, Balustrading and Second floor power on/ heat on First floor 2nd power on/ heat on handrails, fix joinery Third floor : Internal finishes, M&E, Second floor : Internal finishes, M&E, fire stopping, suspended ceilings, fire stopping, suspended ceilings, External panels all levels Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary installation Facing brickwork levels Third floor powerallon/ heat on Second floor power on/ heat on Fourth floor : Internal finishes, M&E, Third floor : Internal finishes, M&E, fire stopping, suspended Corten steel all levels ceilings, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary Curtain wallinginstallation all levels Fourth floor power on/ heat on Third floor power on/insulation, heat on Roof parapets, deck, Fifth floor : Internal finishes, M&E, fire Fourth floor : Internal finishes, M&E, outlets, sedum roof stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st 1st building and 2nd air fix,test decoration and tiling, Joinery 1st and 2nd fix, decoration and Ground floor : Internal finishes, M&E, sanitary installation tiling, sanitary installation fire suspended ceilings, Fifthstopping, floor power on/ heat on Fourth floor power on/ heat on Joinery 1st :and 2nd fix, decoration and Sixth floor Internal finishes, M&E, fire Fifth floor : Internal finishes, M&E, fire tiling, sanitary installation stopping, suspended ceilings, Joinery stopping, suspended ceilings, Joinery Ground floorfix,power on/ heat 1st and 2nd decoration andontiling, 1st and 2nd fix, decoration and tiling, First floor : Internal finishes, M&E, fire sanitary installation sanitary installation stopping, Sixth floorsuspended power on/ceilings, heat onJoinery Fifth floor power on/ heat on 1st and 2nd fix, decoration and tiling, Stair 1floor : M&E, Joinery,finishes, Decoration, Sixth : Internal M&E, fire sanitary installation suspended ceiling, Balustrading stopping, suspended ceilings, Joinery First floor power on/ heat on Final testing anddecoration commissioning, air 1st and 2nd fix, and tiling, Second floor : Internal finishes, M&E,
22 on top and carefully smooth it when 2 Pour concrete 34 32 23 35 it is not fully dried. 33 24 36 25 34 37 35 26 38 36 39 37 27 28 40 38 29 41 39 30 42 40 31 43 41 32 33 44 42 45 43 34 35 46 44 47 45 36 48 37
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
Current stage: Completed ground and 1st floor , preparing for 2nd floor
The superstructure of the design is insitu concrete floor slabs and columns. Therefore, the process of laying steel structure and pouring concrete repeats on every level. Steel framework is done by crossing steel elements, columns and beams, with one another. They ensure a stable support for pouring concrete and prevent concrete break or crack when it dried out.
3 When the concrete is completely dried, its surface is polished with machinery.
22
remove the mould and use machine to sand the surface.
Plan showing the position of columns on ground level . They are placed according to the grid. 35.72
35.86
Columns
35.60
35.70
35.71
C 222
D
1646
1492
35.20
C
3562
35.24
B
2279
35.46
A
35.32
35.80
35.63
35.46 E
Ea
G
223
D 301
73
Ground Floor 35.600
10534 1000
1000
2000
1000
923
400
800
600
1200
1248
579 73
1000
1a W 01
ED 01 925
1
10 9
310
600
X001 RECEPTION 130 m2
1000
220
A
3650
800
640
4742
5045
8
Ground Floor 35.630
2a
Secure line 3a
W 01
800
3554
400
10932
1930
1200
2
600
Indicative location of reception desk by others
422 1095
35.61
3
1135
312
1
800
221
B
400
2950
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
1010
420
4
2707
837
ID 017 DP
9
8
7
6
5
4
3
2
X011
STAIR 2 *Concrete finishes will LOBBYbe discussed
35.47
point
1
Lift
X010
019 2 sectionIDof inSTAIR the Special Interest in
CH 3.36
Ground Floor 35.630
FFL 35.44
U/S 2.78
35.43 2279
C 222
3562
1646
U/S 3.14
83
SCH 2.
B
allery H002 G CH 2.99
ID 018
Chapter 9
A
U/S 2.27
FFL 35.63
Ground Floor 35.630 10
DH 2.05
THL 35.64
Insertion
2 STN/14 35.51
314
ED 14
SH 0.19 HH 3.03
ground floor slabs between floors and pour concrete inside.
2 Let the concrete fully dry and harden. Then,
35.91
1 Place the tube concrete column mould on the
C
23
1492
D
E Ground Floor 35.440
UP 190
771
Wall Construction - Brickwork 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and 150mm Rockwool DuoSlab Insulat HH 12.5 Knauf Windliner Sheathing SHBo 150mm DH SFS 2.05 Zone, Filled with RW4 25mm Battens to form Service Void
and external doors 15 10 Windows Planning conditions discharge Roof-Terrace Floor 55.324 Internal partitions, Wall Architectural, structural and and ceiling civil to 16 stage 4 11 finishes 12 Subcontractor procurement
Roof-Terrace Floor 55.324
onstruction TBC
3.3
Dimension TBC
A
17 18 13 19
Sanitery Enabling goods, works, Landscaping Site set up, Service Construction disconnetions,programme Groundworks, Piling A Start connections, on site 06-05-2017 Stats Frame, Cladding,
LT E R A T I O N T O E XConfetti ISTING BUILDING & ROOF PROTECTION
TBCAEAFAGAHAIAJAKALAMANAOAPAQARASATAUAVAWAXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBWBXBYBZCACBCCC B C D E F G H I J K L M N O P Q R S All T UConstruction V W X Y Z AAABACAD
Site possession, cabins and welfare, 14 M&E 1 20 Signage Roof finishes, Lift installation, soil strip, Piling, Windows and reduce externaldig, doors 15 2 Top Ground beams, LiftWall pit foundation 21 Fifth Floor Internal partitions, and ceiling 3 51.924 finishesframe, PCC stairs between 16 Insitu 4 Month/year floors up to roof deck 22
Fifth Floor 51.924
2017 2018 March
April
May
June
July
2655
Sanitery goods, Landscaping 17 5 Task Construction programme 18 Steelwork lift shaft and roof 23 6 Tender programme on siteto06-05-2017 19 Start Alterations existing building, roof 24 Site possession, cabins and welfare, 7 protection Tender addendum information 20 Signage Stair 2 : Ist fix M&E, dryline walls, mist
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
Current stage: Completed
coat 25 soil strip, reduce dig, Piling, 8 Top Contract appointment Fourth Floor 9 Technical DesignLift stage Ground beams, pit foundation 21 48.694 Details of lift shaft Stair 2 : 2nd fix M&E, decoration Insitu frame, PCC stairs between and new section of10 staircase, suspended ceiling decoration 26 discharge floors upconditions to roof deck 22 Planning
As one of the aim of the construction is to connect the existing buildings, there is a flat roof to be agreed Architectural, structural and civil to need of opening access through walls. Stair 24 : 3rdliftfixshaft M&E, Balustrading and 11 Steelwork and roof 23 stage
Fourth Floor 48.694
August Sept
joinery 12 Subcontractor procurement 27 handrails, Alterations2nd to fix existing building, roof works, Site set up, Service protection 24 Enabling disconnetions, Groundworks, Piling 13 External panels all levels 28 Stair 2 : Ist fix M&E, dryline walls, mist
Third Floor 45.590
Third Floor 45.464
42.670 Second Floor 42.230
Second Floor HE 42.320
Floor CONFETTI
Stats connections, Frame, Cladding, 25 coat Third Floor Third Floor 45.590 14 Facing 29 M&E 45.464 brickwork all levels Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windows andallexternal doors 15 staircase,steel suspended decoration 26 Corten levelsceiling 30
45.464
Internal partitions, Wall and ceiling 16 Stair 2 : walling 3rd fix M&E, Balustrading and43.975 Curtain all levels 31 finishes 27 handrails, 2nd fix joinery Roof parapets, deck, insulation, goods, roof Landscaping 17 outlets, sedum 32 Sanitery 18 External panels all levels 28 Construction 1st building airprogramme test 33 19 Start on site 06-05-2017 Second Floor: HE Ground floor Internal finishes, M&E, Second Floor 42.320 42.230 possession, cabins and welfare, 42.200 Facing brickwork all levels 29 Site fire stopping, suspended ceilings, Second Floor CONFETTI 20 Signage 41.820 Joinery 1st and 2nd fix, decoration and soil strip,allinstallation reduce Corten steel levels dig, Piling, 30 Top tiling, sanitary 34 Lift pit foundation 21 Ground beams, floor power on/ heat on 35 Ground
42.320
NB: frame, PCC between First floor : Internal finishes, M&E, fire All filled openings and areas Curtain walling all stairs levels 31 Insitu up to roof deck 22 floors stopping, suspended ceilings, Joinery where structures haveRoof been parapets, deck, insulation, 1st and 2nd fix, decoration and tiling, sedum roof 32 outlets, removed to be plastered to sanitary installation 36 Steelwork 23 airshaft test and roof 33 1st buildinglift match adjacent walls. First floor power on/ heat on roof 37 Alterations to existing building, Groundfloor floor : Internal finishes, M&E, Skim the whole area Second protection : Internal finishes, M&E, 24 prior fire fire stopping, stopping, suspended suspended ceilings, ceilings, to decoration Stair 2 : Ist fix M&E, dryline walls, mist
40.690
First Floor HE 39.060
or Confetti
Ground Floor 35.630
Ground Floor HE 35.440
Floor Confetti
Ground Floor
Lower Ground Floor 32.700
SECTION CC
First Floor 38.930
First Floor HE 39.060
First Floor Joinery 1st 1st andConfetti 2nd fix, decoration and Joinery 38.360and 2nd fix, decoration and coat sanitary installation 25 tiling, 34 38 tiling, sanitary installation 37.917 floorpower poweron/ on/heat heaton on 35 Ground Second floor 39 Stair 2 : 2nd fix M&E, decoration First floor : Internal finishes, M&E, fire Third floor : Internal finishes, M&E, suspended ceiling decoration 26 staircase, stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st and 2nd fix, decoration and tiling, Joinery 1st and 2nd fix, decoration and sanitary installation 36 Stair 2 : 3rd fix M&E, Balustrading and 40 tiling, sanitary installation First floor power on/ 37 Third handrails, fix joinery 27 floor2nd power on/heat heaton on 41 Ground Floorfloor Ground Floor HE Second : Internal finishes, M&E, Fourth floor 35.630 35.630 : Internal finishes, M&E, 35.440 fire stopping, stopping, suspended ceilings, fire suspended panels all levels ceilings, 28 External Joinery 1st Joinery 1st and and 2nd 2nd fix, fix, decoration decoration and and Ground Floor Confetti 34.740 tiling, sanitary installation 38 tiling, installation 42 brickwork all levels 29 Facingsanitary floor power power on/ on/ heat heat on on 39 Fourth floor 43 Second Thirdfloor floor: :Internal Internalfinishes, finishes,M&E, M&E,fire Fifth steel all levels ceilings, 30 Corten fire stopping, suspended stopping, suspended ceilings, Joinery Joinery fix, decoration and 1st and 1st 2ndand fix, 2nd decoration and tiling, tiling, sanitary installation 40 sanitary Curtain walling all levels 31 installation 44 Lower Ground Floor 32.800 floor power on/insulation, heaton on 41 45 Third Fifth floor power on/ heat Roof parapets, deck, Fourthfloor floor : Internal finishes,M&E, M&E,fire Sixth : Internal sedum roof finishes, 32 outlets, stopping, ceilings, stopping, suspended Joinery 1st building airsuspended test ceilings, 33 fire Joinery fix, decoration and 1st and 1st 2ndand fix, 2nd decoration and tiling, Ground floor : Internal finishes, M&E, sanitary installation 42 sanitary installation 46 tiling, fire stopping, suspended ceilings, Fourthfloor floorpower poweron/ on/heat heatonon 43 Sixth 47 Joinery 1st and 2nd fix, decoration and Fifth floor : Internal finishes, M&E, fire Stair 1 : M&E, Joinery, Decoration, 34 tiling, sanitary installation stopping, suspended ceilings, Joinery 48 Ground suspended ceiling, Balustrading floor power on/ heat on 35 1st and 2nd 30.000 fix, decoration and tiling, Final floor testing: Internal and commissioning, airfire First finishes, M&E, 44 sanitary installation testing, final clean andceilings, snag Joinery 49 stopping, suspended 45 Fifth floor power on/ heat on 1st and 2nd fix, decoration andclean tiling, External landscaping, snag and Sixth floor : Internal finishes, M&E, fire installation 36 externals 50 sanitary stopping, suspended ceilings, Joinery floor power on/ heat on 37 51 First PRACTICAL COMPLETION 1st and 2nd fix, decoration and tiling, Second floor : Internal finishes, M&E,
39.060
35.957 35.630
They will be infill with blockworks and areas where structures have been removed will be plastered to match adjacent walls. Parts that will be kept will be protected my plastic cover.
SECTION AA
Plastic covered are placed to the nearby existing HE buildings in order to protect the wall and roof. They prevent the surface and structure of them during the construction process of Confetti building, as the space of the site is limited. 9020
First Floor 38.930
24
16 10 finishes Planning conditions discharge
2 & E X T E R N A L E N V E LO P E Alterations to existing building, roof Sanitery goods, Landscaping Task
2017 2018 March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
protection Construction programme Tender programme Start 2on: Ist sitefix06-05-2017 Stair M&E, dryline walls, mist coat Site possession, cabins and welfare, Tender addendum information
20 Signage Stair soil 2 : 2nd fixreduce M&E, decoration Top strip, dig, Piling, 8 Contract appointment suspended ceiling decoration 26 9 staircase, Technical DesignLift stage Ground beams, pit foundation 21
E
Ea
35.09
1492
35.20
D
1646
Current stage: Not in process 35.24
G 4550
Ground Floor 35.300
D 301
3160
73
Ground Floor 35.600
10534 1000
1000
2000
1000
923
Eb
223
35.20
35.60
C 222
35.28
35.46
C
3562
35.32
B
2279
35.46
A
1200
400
800
600
4
1248
579 73
1000
ED 02
W 02 11
Ground Floor 35.464
13
12
1a W 01
3109
Internal partitions, Wall and ceiling Roof parapets, deck, insulation, 16 Stair 2 : sedum 3rd fix roof M&E, Balustrading and outlets, 32 finishes handrails, 2nd joinery 27 building airfix test 33 1st goods, Landscaping 17 Sanitery Ground floor : Internal finishes, M&E, programme 18 External panels all levels ceilings, 28 Construction fire stopping, suspended on site 06-05-2017 19 Start Joinery 1st and 2nd fix, decoration and
ED 01 925
10
640
4742
5045
8 7
1696
X008 STAIR 1
9
310
4642
1
6
611
1000
4
Ground Floor 35.630
1200
1
IS 001
2552
1in15
Ground Floor 35.630
1930
Secure line
400
10932
ID 001
2500
2a
2
3a 2339 1235
753
1135
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
X00 MTG 9 m2
20
1010
420
ID 015
794
4
X012 clnrs cpbd 3 m2
3153
1736
1095 400 800
221
4
3
ID 011
Mechanical riser ID 016
2
2000
1094
422
1
Eb 1215
753
Ea
1736
600
Indicative location of reception desk by others
628
2707
837
758
800
W 01
312 3
2
3
1500
EXTERNAL PANELS
Ground Floor 35.464
1696
X001 RECEPTION 130 m2
600
220
A
3650
800
5
35.61
ID 017 U/S 2.37
DP
7
6
5
4
3
2
int
X011 STAIR 2 LOBBY
1
X010 STAIR 2
llery H002 Ga CH 2.99
CH 3.36
U/S 2.78
G
Ground Floor 35.630
FFL 35.44
SH 0.19 HH 3.03
35.43 2279
223 3562
1646 SCH 2.8
A
B
C
1492
D
7718
E
3
U/S 3.14
Wall Construction - Brickwork Outer / SFS Inner HH 2.05 102.5 Black Brick as F10/110 SH 0.87 50mm Air Gap with Brick Ties and Support Brackets DH 2.05 150mm Rockwool DuoSlab Insulation HH 2.05 12.5 Knauf Windliner Sheathing 0.87 SHBoard 150mm DH SFS 2.05 Zone, Filled with RW45 Insulation 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns
Ground Floor 35.440
UP
May
June
July
August Sept
450
April
2
503.5
468.5 AVCL
1in12
FFL 35.47
1
30mm Deep Corten Cassettes 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Insulation Wall Construction - Corten Outer / SFS Inner 12.5 Knauf Sheathing Board 30mm DeepWindliner Corten Cassettes 150mmAirSFS Zone, withRails RW45 Insulation 69mm Gap withFilled Vertical on HH Brackets 25mm Battens to form Service Void 150mm Rockwool DuoSlab Insulation 12.5mm Plywood and Sheathing 12.5mm GB Plasterboard and skim + exposed concrete columns 12.5 Knauf Windliner Board 150mm SFS Zone, Filled with RW45 Insulation 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns Wall Construction - Corten Outer / RC Wall Inner 30mm Deep Corten Cladding Panel 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Rainscreen Insulation
Oct
Nov
Dec
Jan
SP 2.23
190
Wall Construction CortenPLAN Outer / SFS Inner PROPOSED GROUND FLOOR - GA -1:50
Key Walls
CH 2.76
ID 019 ID 018
C 222
Lift
4
Feb
March 5
April
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish
MayExisting WallJune HE Centre
July
215mm Existing Solid brick wall 25mm cavity Existing Walldepth HE Centre Metal studs at 600mm centres 215mm Existing Solid brick wall- K10/165A
F
DH 2.04
8
SH 0.86 HH 2.03
9
U/S 2.27
Ground Floor 35.630 10
DH 2.05
FFL 35.63
ED 14
35.47
314
THL 35.64
STN/142 35.51
STAIR 2
po Insertion
Site possession, cabins and welfare, sanitary installation 34 Facing brickwork all levels 29 tiling, 20 Ground floor power on/ heat on 35 Signage First soil floor : Internal finishes, M&E, fire Top strip, dig, Piling, steel allreduce levels 30 Corten stopping,beams, suspended ceilings, Joinery Lift pit foundation 21 Ground 1st andframe, 2nd fix, decoration and tiling, Insitu PCC stairs between 31 Curtain walling all levels 36 floors upinstallation to roof deck 22 sanitary parapets, deck, First floor power on/insulation, heat on 37 Roof outlets, floor sedum: Internal roof finishes, M&E, 32 Second Steelwork lift shaft and roof 23 test 33 1st fire building stopping,airsuspended ceilings, Alterations to existing building, roof Joinery and: Internal 2nd fix, decoration and Ground1st floor finishes, M&E, 24 protection sanitarysuspended installationceilings, 38 tiling, fire stopping, 2 :1st Ist and fixpower M&E, dryline Second floor on/decoration heatwalls, on mist 39 Stair Joinery 2nd fix, and 25 Third floor : Internal finishes, M&E, tiling, sanitary installation 34 coat stopping, Ground floor suspended power on/ ceilings, heat on 35 fire Stair 2 :1st 2nd fix 2nd M&E,fix, decoration Joinery decoration and First floor : and Internal finishes, M&E, fire suspended ceiling decoration 26 tiling, sanitary installation 40 staircase, stopping, suspended ceilings, Joinery on/ heat and on tiling, 41 Third 1st andfloor 2nd power fix, decoration Fourth : Internal finishes, M&E, sanitary installation 36 Stair 2 :floor 3rd fix M&E, Balustrading and suspended ceilings, Firststopping, floor 2nd power on/ heat on 37 fire handrails, fix joinery 27 Joinery and 2nd fix, finishes, decoration and Second 1st floor : Internal M&E, sanitary installation 42 fire stopping, suspended External panels all levels ceilings, 28 tiling, 43 Fourth power on/ decoration heat on and Joinery floor 1st and 2nd fix, : Internal finishes, M&E, fire tiling,floor sanitary installation 38 Fifth 29 Facing brickwork all levels suspended ceilings, Second floor power on/ heat Joinery on 39 stopping, 1st andfloor 2nd :fix, decoration and tiling, Third Internal finishes, M&E, steel all levels ceilings, 30 sanitary installation 44 Corten fire stopping, suspended 45 Fifth floor on/fix,heat on Joinery 1stpower and 2nd decoration and : Internal finishes, M&E, fire tiling, floor sanitary installation 40 Sixth Curtain walling all levels 31 suspended ceilings, Joinery Third floor power on/ heat on 41 stopping, Roof parapets, deck, insulation, and floor 2nd fix, decoration andM&E, tiling, Fourth : Internal finishes, outlets, sedum roof 32 1st 46 sanitary installation fire stopping, suspended ceilings, 33 1st building air test 47 Sixth floor on Joinery 1st power and 2ndon/ fix,heat decoration and Ground floor : Internal finishes, M&E, sanitary installation 42 tiling, Stair 1 : M&E, Joinery, Decoration, fire stopping, suspended ceilings, Fourth floorceiling, powerBalustrading on/ heat on 43 suspended 48 Joinery 1st and 2nd fix, decoration and Fifth floor : Internal finishes, M&E, Final testing and commissioning, airfire 34 tiling, sanitary installation stopping, suspended ceilings, Joinery 49 Ground testing, final andon/ snag floorclean power heat on 35 1st and 2nd fix, decoration and tiling, External snag andM&E, cleanfire First floorlandscaping, : Internal finishes, 44 sanitary installation 50 stopping, externals suspended ceilings, Joinery 45 Fifth floor power on/ heat on 51 1st PRACTICAL COMPLETION and 2nd fix, decoration and tiling, Sixth floor : Internal finishes, M&E, fire 36 sanitary installation 52 Month/year stopping, suspended ceilings, Joinery March 37 First floor power on/ heat on 1st and 2nd fix, decoration and tiling, Second floor : Internal finishes, M&E,
35.63
Enabling works, Site set up, Service 24 protection Groundworks, Piling 13 Facing all dryline levels walls, 29 disconnetions, Stair 2 brickwork : Ist fix M&E, mist coat connections, Frame, Cladding, 25 Stats 14 Corten steel all levels 30 M&E Roof 2finishes, installation, Stair : 2nd fixLift M&E, decoration Windows and external doors 15 staircase,walling suspended ceiling decoration 26 Curtain all levels 31
35.72
Insitu frame, PCC stairs between Stair 2up : 3rd M&E, Balustrading and 10 Planning conditions discharge to fix roof deck 22 floors 2nd structural fix joinery and civil to 27 handrails, Architectural, 4 11 Steelwork lift shaft and roof 23 stage External panels all levelsbuilding, roof 28 Subcontractor 12 procurement Alterations to existing
35.86
As the frame allowing external panels to go on top has not yet started, the work of inserting external panels need to be delayed.
17 5 24 18 6 19 25 7
finishes Month/year Steelwork lift shaft and roof
35.70
This is due to the delay of the whole programme. As there are surprising archaeological findings under the ground, it delayed the programme as it was unexpected and required extra time to dig and cover up the historical site. The current construction progress is 4 weeks behind the programme.
Insitu frame, stairsdoors between Windows andPCC external floors to roof deck Internaluppartitions, Wall and ceiling
35.80
According to the programme, Stair 2 should be in progress at that time. However, it is certain that the task has not started yet.
15 2 22 3 16 4 23
35.71
EXTERNAL PANELS
Confetti
35.91
According to the programme, Stair 2 should be completed at that time. However, it is cleared that it has not placed in the site. Issues regarding to Stair 2 will be discussed in more detail in the section of Visit 2, Chapter 4.
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC
3554
STAIR 2
Site possession,Groundworks, cabins and welfare, Piling 13 disconnetions, 20 Signage Stats connections, A Frame, Cladding, M&Esoil strip, reduce dig, Piling, 14 Top 1 beams, pit foundation 21 Ground Roof finishes, LiftLift installation,
2950
S TA I R
Architectural, structural and civil to Sanitery stage 4 goods, Landscaping Construction Subcontractorprogramme procurement Start on site 06-05-2017 Enabling works, Site set up, Service
B
3.4
17 11 18 12 19
25
August Sept
1
4
S ITE
VISIT 2
Date: 13 November 2017 Weather: Overcast Temperature: 5 °C People on site: 30 to 40
• Project manager
• Contractors
• Workers
• Students and tutors
3 4
2017 2018
Month/year
March
5 Task 6 Tender programme
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
P ROGRAMME
4.1
7 Tender addendum information 8 Contract appointment 9 Technical Design stage
10 Planning conditions discharge Architectural, structural and civil to 11 stage 4 12 Subcontractor procurement Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling Stats connections, A Frame, Cladding,
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCCDCECFCGCHCICJ
Confetti
14 M&E 1 Roof finishes, Lift installation, 15 2 Windows and external doors 3 Internal partitions, Wall and ceiling 16 finishes 4 Month/year
2017 2018 March
April
May
June
July
August Sept
Sanitery goods, Landscaping 17 5 Task Construction programme 18 6 Tender programme 19 Start on site 06-05-2017 Site possession, cabins and welfare, 7 Tender addendum information 20 Signage soil strip, reduce dig, Piling, Contract appointment 8 Top DesignLift stage 9 Technical Ground beams, pit foundation 21 Insitu frame, PCC stairs between Planning discharge 10 upconditions to roof deck 22 floors Architectural, structural and civil to stage 4 11 lift shaft and roof 23 Steelwork procurement 12 Subcontractor Alterations to existing building, roof works, Site set up, Service protection 24 Enabling Groundworks, Piling 13 disconnetions, Stair 2 : Ist fix M&E, dryline walls, mist coat connections, Frame, Cladding, 25 Stats 14 M&E Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windows suspended and external doors 15 ceiling decoration 26 staircase, Internal partitions, Wall and ceiling finishes 16 Stair 2 : 3rd fix M&E, Balustrading and 27 handrails, 2nd fix joinery 17 18 28 19
Sanitery goods, Landscaping Construction External panelsprogramme all levels Start on site 06-05-2017
possession, and welfare, Facing brickworkcabins all levels 29 Site 20 Signage soilsteel strip,allreduce Corten levels dig, Piling, 30 Top 21 Ground beams, Lift pit foundation frame, PCC Curtain walling all stairs levels between 31 Insitu 22 floors up to roof deck Roof parapets, deck, insulation, 32 outlets, sedum roof 23 1st buildinglift airshaft test and roof 33 Steelwork Alterations to existing building, roof Ground floor : Internal finishes, M&E, 24 protection fire stopping, suspended ceilings, Stair 2 :1st Ist and fix M&E, dryline walls, mist Joinery 2nd fix, decoration and 25 tiling, sanitary installation 34 coat 35 Ground floor power on/ heat on Stair 2 : 2nd fix M&E,finishes, decoration First floor : Internal M&E, fire suspended ceilings, ceiling decoration 26 staircase, stopping, suspended Joinery 1st and 2nd fix, decoration and tiling, sanitary installation 36 Stair 2 : 3rd fix M&E, Balustrading and 37 handrails, First floor 2nd power on/ heat on fix joinery 27 Second floor : Internal finishes, M&E, fire stopping, suspended panels all levels ceilings, 28 External Joinery 1st and 2nd fix, decoration and 38 tiling, sanitary installation 29 Facing brickwork all levels 39 Second floor power on/ heat on Third floor : Internal finishes, M&E, steel all levels ceilings, 30 Corten fire stopping, suspended Joinery 1st and 2nd fix, decoration and 40 Curtain tiling, sanitary wallinginstallation all levels 31 41 Third floor power on/insulation, heat on Roof parapets, deck, : Internal outlets,floor sedum roof finishes, M&E, 32 Fourth stopping,airsuspended ceilings, 1st building test 33 fire
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
According to the programme of the contractors, the following tasks should be finished or in progress on 14th November. However, the real programme (Red dotted line) on site is 4 weeks behind scheduled programme(Blue dotted line) Tasks are expected finished: • Stair 2 : Ist fix M&E, dryline walls, mist coat • Stair 2 : 2nd fix M&E, decoration staircase, suspended ceiling decoration • Stair 2 : 3rd fix M&E, Balustrade and handrails, 2nd fix joinery • External panels all levels Task are EXPECTED in progress: • Insitu frame, PCC stairs between floors up to roof deck • Facing brickwork all levels • Corten steel all levels • Roof parapets, deck insulation, outlets and sedum roof Tasks are in ACTUAL progress : • Insitu frame, PCC stairs between floors up to roof deck • External panels all levels
Scheduled programme in visit date Real on site programme
27
2017 2018 March
April
May
June
July
Stair 2connections, : 3rd fix M&E, Balustrading Stats Frame, Cladding,and 25 coat 2nd fix joinery 27 handrails, M&E 14
Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windowspanels and external doors 15 all levels 28 staircase, suspended ceiling decoration 26 External Third
Internal partitions, Wall and ceiling 16 Stair 2 brickwork : 3rd fix M&E, Balustrading and Facing all levels 29 finishes 27 handrails, 2nd fix joinery 17 30 18 28 19 31 29 20 32 30 33 21
24 36 25 34 37 35 26 38
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
Current stage: 3/F & 4/F construction
The superstructure is now constructing in the third and forth floor. Originally, they are constructing floor by floor, but they have ran out of time, so they decided to construct 2 floors at the same time. The photos and drawings show some of the members of the superstructure, forming mainly by concrete in reinforced steel and settle by shuttering. The programme of roof parapets and sedum roof are also postponed as the construction is currently in the third and forth level, has not reached the fifth and top level.
4th
Steel36392737shuttering
30 42 40 31 43 41 32 33 44 42 45 43 34 35 46 44 47 45 36 48 37
3rd
28
C
40 38 29 41 39
o m
28
m
e
n t
Column 2C
Sanitery goods, Corten steel all Landscaping levels Construction External panelsprogramme all levels Start on site 06-05-2017 Curtain walling all levels Site possession, cabins and welfare, Facing brickwork all levels Roof parapets, deck, insulation, Signage outlets, sedum roof Top soilsteel strip, Corten levels dig, Piling, 1st building airallreduce test Ground beams, Lift pit foundation Ground floor : Internal finishes, M&E, Insitu frame, PCC Curtain walling all stairs levels between fire stopping, suspended ceilings, floors up to roof deck Joinery 1st and deck, 2nd fix, decoration and Roof parapets, insulation, tiling, sanitary outlets, seduminstallation roof Steelwork lift Ground floor power on/roof heat on 1st building airshaft test and Alterations to existing building, roof First floor : Internal finishes, M&E, fire Ground floor : Internal finishes, M&E, protection stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st and 2nd fix,M&E, decoration and tiling, Stair 2 :1st Ist and fix dryline walls, mist Joinery 2nd fix, decoration and sanitary installation coat tiling, sanitary installation First floor power on/ heat on Ground floor power on/ heat on Second : Internal finishes, M&E, Stair floor 2 : floor 2nd fix M&E,finishes, decoration First : Internal M&E, fire fire stopping, suspended ceilings, staircase, suspended ceiling stopping, suspended ceilings,decoration Joinery Joinery 1st and 2nd fix, decoration and 1st and 2nd fix, decoration and tiling, tiling, sanitary installation sanitary installation Stair 2 : 3rd fix M&E, Balustrading and Second floor power on/ heat on First floor 2nd power on/ heat on handrails, fix joinery Third floor : Internal finishes, M&E, Second floor : Internal finishes, M&E, fire stopping, suspended ceilings, fire stopping, suspended ceilings, External panels all levels Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary installation Facing brickwork levels Third floor powerallon/ heat on Second floor power on/ heat on Fourth floor : Internal finishes, M&E, Third floor : Internal finishes, M&E, fire stopping, suspended Corten steel all levels ceilings, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary Curtain wallinginstallation all levels Fourth floor power on/ heat on Third floor power on/insulation, heat on Roof parapets, deck, Fifth floor : Internal finishes, M&E, fire Fourth floor : Internal finishes, M&E, outlets, sedum roof stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st 1st building and 2nd air fix,test decoration and tiling, Joinery 1st and 2nd fix, decoration and sanitary installation Ground floor : Internal finishes, M&E, tiling, sanitary installation Fifthstopping, floor power on/ heat on fire suspended ceilings, Fourth floor power on/ heat on Sixth floor Internal finishes, M&E, fire Joinery 1st :and 2nd fix, decoration and Fifth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery tiling, sanitary installation stopping, suspended ceilings, Joinery 1st and 2nd decoration andontiling, Ground floorfix,power on/ heat 1st and 2nd fix, decoration and tiling, sanitary installation First floor : Internal finishes, M&E, fire sanitary installation Sixth floorsuspended power on/ceilings, heat onJoinery stopping, Fifth floor power on/ heat on 1st and 2nd fix,Joinery, decoration and tiling, Stair 1 : M&E, Decoration, Sixth floor : Internal finishes, M&E, fire sanitary installation suspended ceiling, Balustrading stopping, suspended ceilings, Joinery First floor power on/ heat on air Finaland testing anddecoration commissioning, 1st 2nd fix, and tiling, Second floor : Internal finishes, M&E,
31 Reinforcement 22 mesh34322335 33
Oct
Top soil goods, strip, reduce dig, Piling, Sanitery Landscaping Task
Ground beams, Lift pit foundation Construction programme Tender programme Start on site 06-05-2017 Insitu frame, PCC stairs between floors upaddendum to roofcabins deck Site possession, and welfare, Tender information Signage Steelwork lift shaft anddig, roof Top soil strip, reduce Piling, Contract appointment Technical Design stage Ground beams, Lift pit building, foundation Alterations to existing roof 24 protection Insitu frame, PCC stairs between 10 Planning conditions discharge floors tofix roof deck 22 Stair 2up : Ist M&E, dryline walls, mist 25 coat Architectural, structural and civil to 4 11 Steelwork lift shaft and roof 23 stage 12 Subcontractor procurement Stair 2 : 2ndtofixexisting M&E, decoration Alterations building, roof staircase,works, suspended ceiling 26 protection Enabling Site set up, decoration Service 24 disconnetions, Groundworks, Piling 13 Stair 2 : Ist fix M&E, dryline walls, mist
Fo r t h
August Sept
m
17 5 21 18 6 19 22 7 20 23 8 9 21
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC
e
S
U P E R S T R U C T UConfetti RE: INSITU FRAME CONCRETE
n t
4.2
Groundworks, 13 10 disconnetions, Planning conditions discharge Piling Stats connections, Frame, Cladding, Architectural, structural and civil to M&E 4 14 stage 11 12 Roof Subcontractor procurement finishes, Lift installation, and external 15 Windows Enabling works, Site setdoors up, Service disconnetions, Groundworks, Piling 13 Internal partitions, Wall and ceiling 16 finishes Stats connections, A Frame, Cladding, 14 M&E 1 Sanitery goods, Landscaping 17 Roof finishes, Lift installation, 18 Windows and programme external doors 15 2 Construction Start on partitions, site 06-05-2017 19 Internal Wall and ceiling 3 possession, cabins and welfare, finishes 16 Site 4 Month/year Signage 20
4.3
2655
S
X405 COMPUTER SUITE
X303 COMPUTER SUITE
X305 COMPUTER SUITE
17 5 21 18 6 19 22 7 20 23 8 9 21
Top soil goods, strip, reduce dig, Piling, Sanitery Landscaping Task
X203 LRC
Second Floor Construction (LRC) -275mm concrete deck to Structural Engineer's details B C vapour D E control F G layer H I J K L MN O P Q -3mm -50 mm Kooltherm as spec ref M10.290B -75mm screed as spec ref M10.130 - Vinyl floor finish as floor finishes drawings 401-402
X205 COMPUTER SUITE
Ground Floor 41.964
3111
X102 KITCHEN
Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windowspanels and external doors 15 all levels 28 staircase, suspended ceiling decoration 26 External
X105 COMPUTER SUITE
17 30 18 28 19 31 29 20 32 30 33 21
3235
Same as ground Floor (Type 12) but on Precast concrete Plank to Structural Engineer's details X004 MTG 2
X014 SERVER
Ground Floor 35.048
31 22 34 32 23 35 33
Detail S - 301
24 F
G
MLD MLD MLD MLD BY
Pink dotted lines show the ramp
Architects, Landscape & Interior Design Internal partitions, Wall and ceiling 16-20 Bath Street, Nottingham NG1 1DF finishes 16 Stair 2 brickwork : 3rd fix M&E, Balustrading and all levels 29 Facing Ground Floor E design@allanjoycearchitects .co.uk fix joinery T 0115 841 8418 27 handrails, 2nd38.360
Ground Floor 38.568
X003 OFFICE
2017 2018
Ground Floor Construction Solid Concrete Ground Based March April May June July Floors - Vinyl floor finish as floor finishes drawings 401-402 -75mm screed as spec ref M10.130 - Underfloor Heating Systems refer to M+E Engineer's details -0.5mm separation layer lapped (minimum 150mm) -50mm perimeter Insulation overlap min.150mm from bottom of wall insulation to top of insulation upstand -130mm Kingspan Kooltherm K103 Floor Board insulation under concrete slab as spec ref M10.290A -0.9mm damp proof membrane -275mm thick concrete slab to Structural Engineer's details -well compacted sub base to Structural Engineer's details U-Value = 0.11W/m2K
Stair 2connections, : 3rd fix M&E, Balustrading Stats Frame, Cladding,and 25 coat 2nd fix joinery 27 handrails, M&E 14
X103 QUIET CAFE
R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC
Floors Construction (1st, 3rd, 4th, 5th) -275mm concrete deck to Structural Engineer's details -10mm latex levelling screed - Vinyl floor finish as floor finishes drawings 401-402
Ground beams, Lift pit foundation Construction programme Tender programme Start on site 06-05-2017 Insitu frame, PCC stairs between floors upaddendum to roofcabins deck Site possession, and welfare, Tender information Signage Steelwork lift shaft anddig, roof Top soil strip, reduce Piling, Contract appointment Technical Design stage Ground beams, Lift pit building, foundation Alterations to existing roof 24 protection Insitu frame, PCC stairs between 10 Planning conditions discharge floors tofix roof deck 22 Stair 2up : Ist M&E, dryline walls, mist 25 coat Architectural, structural and to Drawing status updated to construction D civil 30/05/17 C 12/05/17 Amendments to drawings following the Topo 4 11 Steelwork lift shaft and roof 23 stage Survey and SE info 12 Subcontractor procurement B 10/01/17 Stair 2 : 2ndtofixexisting M&E, decoration Alterations building, roof Spec Refs added A 23/12/16 Amendments to drawings staircase,works, suspended ceiling 26 protection Enabling Site set up, decoration Service 24 REV. DATE DESCRIPTION disconnetions, Groundworks, Piling 13 Stair 2 : Ist fix M&E, dryline walls, mist
3215 Mechanical Riser
- 25 mm thick Kingspan Thermaroof TR27 LPC/FM upstand to be used around the perimeter of the roof on the internal faรงade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -1.5mm fully adhered single-ply membrane as S42.110A -50mm Ballast (paving slabs on support) as Q37.140 U-Value <0.15W/m2K.
U P E R S T R U C T UConfetti RE: RAMPS 2945
X403 COMPUTER SUITE
Groundworks, 13 10 disconnetions, Planning conditions discharge Piling Stats connections, Frame, Cladding, Architectural, structural and civil to M&E 4 14 stage 11 12 Roof Subcontractor procurement finishes, Lift installation, and external 15 Windows Enabling works, Site setdoors up, Service disconnetions, Groundworks, Piling 13 Internal partitions, Wall and ceiling 14 finishes 16 Stats connections, A Frame, Cladding, 14 M&E 1 Sanitery goods, Landscaping 17 Roof finishes, Lift installation, 18 Windows and programme external15doors 15 2 Construction Start on partitions, site 06-05-2017 19 Internal Wall and ceiling 3 possession, cabins and welfare, finishes 16 Site 4 Month/year Signage 20 16
H
36 25 34 37 35 26 38 36 39 37 27 28 40 38 29 41 39 30 42 40 31 43 41 32 33 44 42 45 43 34 35 46 44 47 45 36 48 37
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
Sanitery goods, Corten steel all Landscaping levels CLIENT Construction External panelsprogramme all levels Detail V - 301 Confetti Media Group Start on site 06-05-2017 Curtain walling all levels Site possession, cabins and welfare, Facingparapets, brickwork all levels Roof deck, insulation, PROJECT Signage outlets, sedum roof Confetti CQ Campus Top soilsteel strip, Corten levels dig, Piling, 1st building airallreduce test Ground beams, Lift pit foundation Ground floor : Internal finishes, M&E, DRAWING Insitu frame, PCC Curtain walling all stairs levels between fire stopping, suspended ceilings, GA Section BB floors up to roof deck Ground Floor 34.770 Joinery 1st and 2nd fix, decoration and Roof parapets, deck, insulation, tiling, sanitary outlets, seduminstallation roof PROJECT NUMBER DATE SCALE Steelwork lift Ground floor power on/roof heat on 1st building airshaft test and Detail Z - 301 2588 1:50 @ A1 Jul-16 Alterations to existing building, roof First floor : Internal finishes, M&E, fire Ground floor : Internal finishes, M&E, STATUS NUMBER REVISION BY protection stopping, suspended ceilings,DRAWING Joinery fire stopping, suspended ceilings, 221tiling, D Construction MLD I and 1st 2nd fix,M&E, decoration and Stair 2 : Ist fix dryline walls, mist Joinery 1st and 2nd fix, decoration and sanitary installation coat sanitary tiling, installation This drawing is copyright and remains the property of Allan Joyce Architects Ltd First floor power on/ heat on Generally do not scale drawings. All dimensions to be checked on site. Ground floor power on/ heat on Second : Internal finishes, M&E, Stair floor 2 : floor 2nd fix M&E,finishes, decoration First : Internal M&E, fire fire stopping, suspended ceilings, staircase, suspended ceiling decoration stopping, suspended ceilings, Joinery Joinery 1st and 2nd fix, decoration and 1st and 2nd fix, decoration and tiling, tiling, sanitary installation sanitary installation Stair 2 : 3rd fix M&E, Balustrading and Second floor power on/ heat on First floor 2nd power on/ heat on handrails, fix joinery Third floor : Internal finishes, M&E, Second floor : Internal finishes, M&E, fire stopping, suspended ceilings, fire stopping, suspended ceilings, External panels all levels Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary installation Shuttering Facing brickwork levels Third floor powerallon/ heat on Second floor power on/ heat on Fourth floor : Internal finishes, M&E, Third floor : Internal finishes, M&E, fire stopping, suspended Corten steel all levels ceilings, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary Curtain wallinginstallation all levels Fourth floor power on/ heat on Third floor power on/insulation, heat on Roof parapets, deck, Fifth floor : Internal finishes, M&E, fire Fourth floor : Internal finishes, M&E, outlets, sedum roof stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st 1st building and 2nd air fix,test decoration and tiling, Joinery 1st and 2nd fix, decoration and sanitary installation Ground floor : Internal finishes, M&E, tiling, sanitary installation Fifthstopping, floor power on/ heat on fire suspended ceilings, Fourth floor power on/ heat on Sixth floor Internal finishes, M&E, fire Joinery 1st :and 2nd fix, decoration and Fifth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery tiling, sanitary installation stopping, suspended ceilings, Joinery 1st and 2nd decoration andontiling, Ground floorfix,power on/ heat 1st and 2nd fix, decoration and tiling, sanitary installation First floor : Internal finishes, M&E, fire sanitary installation Sixth floorsuspended power on/ceilings, heat onJoinery stopping, Fifth floor power on/ heat on 1st and 2nd fix,Joinery, decoration and tiling, Stair 1 : M&E, Decoration, Sixth floor : Internal finishes, M&E, fire sanitary installation suspended ceiling, Balustrading stopping, suspended ceilings, Joinery First floor power on/ heat on air Finaland testing anddecoration commissioning, 1st 2nd fix, and tiling, Second floor : Internal finishes, M&E,
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
Current stage: 3/F & 4/F construction
The programme has slightly delayed causing by changing the method of pouring concrete slabs. As the design follows the Equality Act , it should includes access for disabled for them to fully access the building. Therefore, the design incorporates ramps on levels. Therefore, they need to pour the concrete with level changes. The original plan of pouring is from the front to the back. However, due to the uncertainty of the structure antiquity of existing building and the courtyard area, the pouring method need to change to pouring from the back to front. This way requires putting more shuttering in and makes the process of finishing this task longer, leading to a delay of their work. They are now aiming to get the programme back on time in Christmas period as the students have vacation and they can fully do their work without affecting the operation of schools.
29
C
A
190 1in12
A
A A
FIRST FLOOR LEVEL STRUCTURAL PLAN
Confetti New building
FIRST FLOOR LEVEL FINISHES PLAN
Confetti New building
PROJECT NUMBER
SCALE
DAT
2588
1:25 @ A1
Ju
DRAWING NUMBER
REVISION
STATUS
BY
318
A
Preliminary
M
The ramp is designed to connect the existing HE building and the new Confetti building as they have difference in the height of levels.
This drawing is copyright and remains the property of Allan Joyce Architects Lt Generally do not scale drawings. All dimensions to be checked on site.
ID 112
Shuttering
UP
The design knocks through all the floors , except 1st floor and the ramp unlocks extra 160 square metres to the new building and forming 2400 square metre in total.
First Floor 38.930
130
130
1in12
1in12
A
Moved 2F & 3F details to dwg no. 320. Added Stud details. Added section CC.
DESCRIPTION
RW
BY
Architects, Landscape & Interior Design
First Floor 39.060
TA 2.27
TA 2.27
First Floor 39.060
31-08-17
REV. DATE
SP 1.45
SP 1.45
To link the existing with the new, the construction just required cutting holes on existing walls for entrances. This reduces the cost of the project in making use of the usable materials on site.
UP 1560
First Floor 38.930
1200
SH 0.95 HH 2.17
ID 112
SH 0.95 HH 2.17
16-20 Bath Street, Nottingham NG1 1DF T
0115 841 8418
E
design@allanjoycearchitects .co.uk
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
SP 1.37
SP 1.37
Existing HEC building A
Confetti Media Group
F Open entrance from existing walls
SP 1.45
SP 1.45
F
PROJECT
Confetti CQ Campus
General Notes
DRAWING
to be confirmed on site prior to commencing any fabrication. GF- All&dimensions 1F Ramps Details
Existing HEC building A
- Top of all handrails to be 1000mm min. above pitch line of ramps and above finished landing level. - All handrails to be nominal 40mm satin stainless steel. PROJECT DATE SCALE - Wall NUMBER handrails to be supported on stand off wall brackets; continuous around half landings; extend 300mm past top and bottom of ramps and be returned to wall.
2588 FIRST FLOOR LEVEL STRUCTURAL PLAN
FIRST FLOOR LEVEL FINISHES PLAN
Confetti New building
Existing HEC building
1560 1000
uilding N
UP
1in12
First Floor 38.930
8
1:25 @ A1
Jun-17
DRAWING NUMBER
REVISION
STATUS
BY
318
A
Preliminary
MLD
PARTITION Wall Type - K10/115 2x12.5mm SoundBloc Metal Studs at 600mm centres This drawing is copyright and remains the property of Allan Joyce Architects Ltd in the cavity 100 Rockwood RW360 insulation 2x12.5mm SoundBloc Generally do not scale drawings. All dimensions to be checked on site.
First Floor 39.060
Rigid sheet flooring over ramp landing structure supported on Timber Frame at 450cc 2no.Timber Floor Joists At Edge
18
600
SECTION AA FIRST FLOOR LEVEL
Solid Wall Balustrade 12.5mm Plywood Green Wall as specand ref 12.5mm Q37.125plasterboard and skim Timber studs to suit balustrade width at 600mm c/cs 12.5mm and 12.5mm plasterboard and skim LivePanel,Plywood Living Green Wall 102.5 Black Brick 50mm cavity 100mm Benchmark Quadcore Karrier Pane 100mm 'Tarmac Hemelite' 100mm fairfaced medium density blockwork
Ramps and Floor structure to be coordinated with SE
30
4.4
WALLS
GABLE END WALL
As not all of the building is linked to the existing building of Confetti or the HE building internally, there are walls separating them and there is a need to construct a gable ended wall to seal the gap between the existing and the new in order to avoid water slipping though the voids. Concrete is filled with reinforcement bars and shuttering is used to consolidate the form until it is completely dry.
Reinforcement mesh
Pouring concrete
Allow the concrete to dry
Internal shuttering bracing
31
4
450
3047.5
6
5
4
3
2
1
Apex CH 3.85
MLD MLD
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
MLD MLD MLD MLD MLD MLD
REV. DATEX210 DESCRIPTION
STAIR 2
U/S 2.19
314
Change to doors and Stair 1 Lobby Spec Refs added Amendments to drawings ID 212 to drawings Amendments Amendments to drawings Second Floor Amendments to drawings 42.320 U/S 2.15
7
F E D C B A
30/05/17 Amendments to HEC stair 2 following the SE info 12/05/17 Amendments to drawings following 1847 the Topo Survey and SE info 41.22
41.25
Ee
CH 2.43
HH 2.88 SH 0.77
CH 3.05
CH 3.05
Apex CH 3.81
41.37
3947.5(17 1/2 bricks)
420
450
H CH 2.50 G
Wheelchair Refuge
3
X211 STAIR 2 LOBBY
2707
Lift
BY
U/S 2.81 Col 12
13
14
15
16
17
18
19
41.30
11
20
41.36
U/S 2.98
G
A
H
B
Green Wall as spec ref Q37.125 U/S 2.81 Col
3
LivePanel, Living Green Wall 102.5 Black Brick 50mm cavity 100mm Benchmark Quadcore Karrier Pane 100mm 'Tarmac Hemelite' 100mm fairfaced medium density blockwork
As the building is not constructing in traditional stud work system, it allows the internal of the building starts early in order to keep the programme on track. The partitions are now in the process of filling insulations.
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation 12.5 Knauf Windliner Sheathing Board 150mm SFS Zone, Filled with Rockwool RW45 Batts 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm Sound Board and skim + exposed concrete columns
SHEAR WALLS
AVCL
The shear walls are constructed in concrete and it is used to resist lateral loads that mostly caused by wind. It will be clad with corten steel externally to form a uniformed external visual.
W
www.allanjoycearchitects .co.uk
D
77
E
CLIENT U/S 2.81 Confetti Media Group
PROJECT
Confetti CQ Campus DRAWING
4
Second Floor GA Wall Types and Setting Out SHEAR PROJECTWALLS NUMBER
2588
5
HH 2.36 SH 1.16
PARTITIONS
- Internal Door Codes (Refer to drawing 320) - Window Codes (Refer to drawings 322-323) Green Wall as specCodes ref Q37.125 - External Door (Refer to drawings 323) - Internal Screene Codes (Refer to drawings 321)
2
design@allanjoycearchitects .co.uk
TA 2.92
ID 001, etc W001, etc ED01, etc IS01, etc
PARTITION Wall Type - K10/115 2x12.5mm SoundBloc Metal Studs at 600mm centres 100 Rockwood RW360 insulation in the cavity 2x12.5mm SoundBloc
40mm Deep Corten Cassettes 35mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Rainscreen Wall Construction - Corten Outer Insulation / SFS Inner 12.5 Knauf Sheathing Board 40mm DeepWindliner Corten Cassettes 150mmAirSFS Zone, withRails Rockwool Batts 35mm Gap withFilled Vertical on HHRW45 Brackets 25mm Battens to form Service Void 150mm Rockwool DuoSlab Rainscreen Insulation 12.5mm Plywood and Sheathing 12.5mm Sound 12.5 Knauf Windliner Board Board and skim + exposed concrete columns 150mm SFS Zone, Filled with Rockwool RW45 Batts 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm Sound Board and skim + exposed concrete columns Wall Construction - Corten Outer / RC Wall Inner 40mm Deep Corten Cassettes 35mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish
E
SP 2.49
1
0115 950 7161
1492
CH 2.98
Plant Room External Wall 100mm fairfaced medium density blockwork - F10/225 10mm clear residual cavity Existing Wall Confetti 100mm Kingspan Kooltherm K106 Cavity Board Insulation to be agreed with Structural Engineer 100mm medium density blockwork - F10/225 K 10/185fairfaced plasterboard + skim as dabs onto RC wall
0115 841 8418
C
HH 2.99 SH 0.84
Key Walls
HH 2.88 SH 0.77
600
F
PROPOSED SECOND PLAN -1:50 Wall FLOOR Construction GA - Corten Outer / SFS Inner
AVCL
8
201
1646
U/S 2.81
LivePanel, Living Green Wall 102.5 Black Brick 50mm cavity 100mm Benchmark Quadcore Karrier Pane 100mm 'Tarmac Hemelite' 100mm fairfaced medium density blockwork FFL 42.16
CH 3.05
10
T
3562
16-20 Bath Street, Nottingham NG1 1DF
HH 2.99 SH 0.84
2304
CH 2.45
CH 2.98
4959
Architects, Landscape & Interior Design
41.32
HH 2.99 SH 0.84
HH 2.88 SH 0.77
CH 3.05
CH 3.05
6128
C 222
ID 211
Wall Construction - Brickwork 102.5 Black Brick as F10/110, 50 50mm Air Gap with Brick Ties and 150mm Rockwool DuoSlab Rainsc Exposed concrete finish Existing Wall HE Centre
SCALE
1:50 @ A1
PARTITIONS DATEExisting Solid brick wall 215mm
25mm cavity Existing Walldepth HE Centre Metal studs at 600mm centres 215mm Existing Solid brick wall- K 12.5mm Plasterboard 25mm cavity depth
Jul-16
DRAWING NUMBER
REVISION
STATUS
203
K
Construction MLD
Metal BY studs at 600mm centres - K 12.5mm Plasterboard Terrace External Wall 102.5 Black Brick as F10/110 6 50mm Terracecavity External Wall 100mm Benchmark This drawing is copyright and remains the property of Allan Joyce Architects 102.5LtdBlack Brick asQuadcore F10/110 Ka 6 100mmcavity fairfaced medium density 50mm Generally do not scale drawings. All dimensions to be checked on site. 100mm Benchmark Quadcore Ka
100mm fairfaced medium density
Plant Room External Wall 100mm fairfaced medium density 10mm clear residual cavity 100mm Kingspan Kooltherm K10 100mm fairfaced medium density
32
3040
13
14
15
16
17
18
19
CH 3 .07
CH 2 .49
CH 3 .03
E
SH 0.81 HH 2 .93
F
G
U/S 2.78
1in12
Second Floor 42.320
SH 0.82 HH 2.95 CH 3.03
5
4
3
2
1
3040
6
18/09/17 Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1
K J II H G
24/08/17 18/08/17 30/05/17 17/08/17 30/05/17 12/05/17
Change to the slab edge following the SE info Amendments to drawings following the Cladding info Change to the 1st floor cafĂŠ/kitchen area Amendments to HEC stair 2 following the SE info Amendments to drawings following the Topo Survey and SE info
F E D C B A
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
Change to doors and Stair 1 Lobby Spec Refs added Amendments to drawings Amendments to drawings Amendments to drawings Amendments to drawings
REV. DATE
X
DESCRIPTION
3783
Current stage: In process Real process Architects, Landscape & Interior Design
SH 0.88 HH 2.97
CH 2.85
126
16-20 Bath Street, Nottingham NG1 1DF
4959
G
H
14 13 12 LivePanel, Living Green Wall 11 102.5 Black Brick 50mm cavity 10 100mm Benchmark Quadcore Karrier Pane 9 100mm 'Tarmac Hemelite' 100mm fairfaced medium density blockwork 8 Green Wall as spec ref Q37.125
T
0115 841 8418
E
design@allanjoycearchitects .co
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group
SH 0.88 HH 2.97
Existing Wall Confetti Insulation to be agreed with Structural Engineer K 10/185 plasterboard + skim as dabs onto RC wall
Top soil strip, dig, Piling, floor : Internal finishes, M&E, fire Corten steel allreduce levels 30 First Handrail and guarding to extend 300mm beyond first Lift pit foundation 21 Ground stopping,beams, suspended ceilings, Joinery riser X PARTITION Wall Type - K10/115 X 1st andframe, 2nd fix, decoration and tiling, Insitu PCC stairs between 31 Curtain walling all levels 8 2x12.5mm SoundBloc 600 ID 111 Handrail landing.centres sanitary 36 Metalcontinuous Studs ataround 600mm floors upinstallation to roof deck 22 Wheelchair 1400 100 Rockwood RW360 insulation in the cavity Roof parapets, deck, insulation, Refuge 37 First floor power on/ heat on 2x12.5mm SoundBloc contrasting nosings as spec sedum: Internal roof finishes, M&E, 32 outlets, L30.250B to treads and risers Second floor lift shaft and roof ID 114 ID 001, etc 23 shown shaded - Internal Door Codes (Refer to drawing 320) 1st building air test 33 Steelwork fire stopping, suspended ceilings, - Window Codes (Refer to drawings 322-323) Alterations to existing building, roof W001, etc ID 113 Green Wall as specCodes ref Q37.125 ED01, etc - External Door (Refer to drawings 323) Ground1st floor finishes, M&E, Joinery and: Internal 2nd fix, decoration and 1272 2678 IS01, etc - Internal Screene Codes (Refer to drawings 321) protection 24 LivePanel, Living Green Wall fire stopping, suspended ceilings, sanitary installation First Floor38 Plan tiling, C 102.5 Black Brick 2 :1st Ist and fixpower M&E, dryline 50mm cavity Joinery 2nd fix, and Second floor on/decoration heatwalls, on mist 39 Stair 100mm Benchmark Quadcore Karrier Pane 25 tiling, sanitary installation 34 coat Third floor : Internal finishes, M&E, 100mm 'Tarmac Hemelite' 100mm fairfaced medium density blockwork ID 017 E 23/06/17 Balustrade system added, step positions MLD Extend handrail 300mm min from first Ground floor suspended power on/1400 heat on step 35 fire stopping, ceilings, amended to align balustrade D 15/06/17 LGF plan added & dimensions amended MLD Stair 2 :1st 2nd fix 2nd M&E,fix, decoration X X C 30/05/17 Amendments to drawings following the SE info MLD First floor : and Internal finishes, M&E, fire Joinery decoration and B 12/05/17 Amendments to drawings following the Topo MLD ED 14 staircase, suspended ceiling decoration 26 Survey and SE info stopping, suspended ceilings, Joinery sanitary installation 40 tiling, A 10/5/17 Floor levels amended MLD 1st and 2nd fix, decoration and tiling, heat on300 41 Third floor power on/ REV. DATE DESCRIPTION BY 300 sanitary installation 36 Stair 2 :floor 3rd fix M&E, Balustrading Fourth : Internal finishes, M&E, IDand 019 Firststopping, floor 2nd power on/ heat on 37 handrails, fix joinery 27 fire suspended ceilings, Second 1st floor : Internal M&E, Joinery and 2nd fix, finishes, decoration and ID 018 1272 2678 Architects, Landscape & Interior Design fire stopping, suspended Ground Floor tiling, sanitary installation 42C PlanExternal panels all levels ceilings, 28 16-20 Bath Street, Nottingham NG1 1DF Joinery floor 1st and 2nd fix, 43 Fourth power on/ decoration heat on and T 0115 841 8418 E design@allanjoycearchitects .co.uk F 0115 950 7161 W www.allanjoycearchitects .co.uk tiling,floor sanitary installation 38 Fifth : Internal finishes, M&E, fire 29 Facing brickwork all levels CLIENT Second floor power on/ heat Joinery on 39 stopping, suspended ceilings, Confetti Media Group Third Internal finishes, M&E, 1st andfloor 2nd :fix, decoration and tiling, X X steel all levels ceilings, 30 fire stopping, suspended PROJECT sanitary installation 44 Corten Confetti CQ Campus Joinery 1stpower and 2nd decoration and 45 Fifth floor on/fix,heat on 460 tiling, floor sanitary installation 40 Curtain walling all levels 31 Sixth : Internal finishes, M&E, fire DRAWING Stair 2 - HEC Third floor power on/ heat on 41 stopping, suspended ceilings, Joinery Roof parapets, deck, insulation, Footing as SE information Fourth : Internal finishes, 1st and floor 2nd fix, decoration andM&E, tiling, sedum roof 32 outlets, PROJECT NUMBER DATE SCALE 1272 sanitary 2678 2588 1:25/1:50 @ A1 Jan-17 fire stopping, ceilings,4654 46 installation 1st building airsuspended test 33 DRAWING NUMBER REVISION STATUS BY Joinery 1st power and 2ndon/ fix,heat decoration and 47 Floor Sixth on Lower Ground Plan floor 314 E Construction MLD Ground floor : Internal finishes, M&E, sanitary installation 42 tiling, Stair 1 : M&E,suspended Joinery, Decoration, This drawing is copyright and remains the property of Allan Joyce Architects Ltd fire stopping, ceilings, Fourth floorceiling, power on/ heat on 43 suspended Generally do not scale drawings. All dimensions to be checked on site. 48 Joinery 1st and 2ndBalustrading fix, decoration and Fifth floor : Internal finishes, M&E, fire Final testing and commissioning, air 34 tiling, sanitary installation stopping, suspended ceilings, Joinery 49 Ground testing, final andon/ snag floorclean power heat on 35 1st and 2nd fix, decoration and tiling, First floorlandscaping, : Internal finishes, External snag andM&E, cleanfire 44 sanitary installation 50 stopping, externals suspended ceilings, Joinery 45 Fifth floor power on/ heat on and 2nd fix, decoration and tiling, 51 1st PRACTICAL COMPLETION Sixth floor : Internal finishes, M&E, fire 36 sanitary installation stopping, suspended ceilings, Joinery March April 52 Month/year May June July August Sept 37 First floor power on/ heat on 1st and 2nd fix, decoration and tiling, Second floor : Internal finishes, M&E, 7
1184
H
U/S 2.71
U/S 2.71
Refer to detail on drawing 319
ID 211
8
2176
U/S 2.71
U/S 2.58
1in12
D
CH 3 .01
126
CH 2 .85
UP
C
SH 0.81 HH 2 .93
Wheelchair Refuge
Wheelchair Refuge 19
SH 0.71
18
U/S 2.58
SH 0.82 HH 2 .95
CH 3 .03
ID 319 17
SH 0.81 HH 2 .93
16
SH 0.95 HH 2 .17
15
Generally, concrete stairs and associated guarding / handrails / noising all as spec ref : L30.250B
20
2678
3011 1184
SH 0.88 HH 2.97
14
U/S 2.93
13
SH 0.82 HH 2 .95
Third Floor 45.464
1512
SH 0.86 HH 2.03
3040
SP 2.23
12
6467
224
A 220 B 221
SH 0.82 HH 2 .95
CH 3 .03
12
B
GENERAL NOTES
Wheelchair Refuge
U/S 2.27
DH 2.05
11
C 222
A
L
eq.
11
X017 PLANT ROOM 30 m2
Ground Floor 35.048
Ee
32.78
PROJECT
Confetti CQ Campus 60 minutes fire resistance Wall
17
Plasterboard on dabs to achieve min 60 minutes fire rating Existing wall
CH 3.03
Balustrades went wrong 3 weeks before delivery, and it is not able to get other supply or manufacture on site on time (now just M&E). 15
DRAWING
Ground Floor GA Wall Types and Setting Out PROJECT NUMBER
SCALE
D
2588
1:50 @ A1
J
17
18
19
20
21
DRAWING NUMBER
REVISION
STATUS
B
201
O
Construction M
Generally do not scale drawings. All dimensions to be checked on site.
9
8
7
6
5
4
3
Ground Floor 35.630
2
163
1400
point
1
DH 2.05
FFL 35.63
THL 35.64
10
U/S 2.27
SH 0.82 HH 2.95
This drawing is copyright and remains the property of Allan Joyce Architects
DP
20 steps (163.5mm)
16
U/S 2.58
503.5
W 10
W 11
1800
X ID 314
ID 313
ID 314 1
FFL 39 .01
20 steps (165.5mm)
1
2
H103 .61 SCH 2
165.5
2
3
SP 1 .37
CH 3.36
3
4
Col
U/S 2.78
4
5
SP 1 .37
SH 0.19 HH 3.03
eq.
5
6
B
6
7
221
7
8
STN/146 39 .07
39.060
Exposed fasteners shall be of same materials, color and finish as material to which applied. Exposed surfaces throughout project shall have same inherent texture and color for similar locations.
inner face strings
37.917
21 steps (163.3mm)
U/S 2.78
not Extents ed survey
*
Work in every weekends before Christmas work to get the staircase done before linking of the old and new building. CH 2.52
*
50
Ground Floor 35.630
FFL
SH 0.19 HH 3.03
Attempts
1400
CH 3.36
468.5
SH 0.88 TA 2 .95
8
9
FFL 39 .06
450
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
Win/A SH 2.04
9
ID 318
10
CH 2 .99
522
C105 CH 3 .02
Ceil 40 .88
SH 0.87 TA 2 .94
FFL 38 .23
ID 312
ID 311
10
CH 2 .99
522
38 .26
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
STN/108 38 .36
FFL
SH 0.90 HH 2 .53
38 .36
DH 2 .00 Win/A SH 2.05 HH 2 .53
DH 2 .02
SH 0.86 TA 2 .94
STN/109 38 .27
38 .27
FFL 38 .23
ID 310
ID 315
W 01
4
FFL 39.08
503.5
TA 2 .89 SH 0.81
HH 2 .99 SH 0.79
DH 2 .02
FFL 38 .28 SH 0.91 HH 1 .96
DH 1 .96
Floor Slope 38 .31
220 A
DH 1 .95
CH 3 .26
38 .24
U/S 41 .09
Ea
ID 316 W 12
3
DH 2 .06
1
STN/110 38 .23
ID 313
Ee
ED 04
Ed
TA 2 .23 FFL 45 .54
2
U/S level 41 .06
ID 307
Ec
Col
3
FFL
ID 308 IS 303
Eb
Col
4
STN/129 39 .72
IS 302 ID 309
SP 1 .66
5
U/S 2.94
ID 306
1
6128
Roof parapets, F deck, insulation, ID 212 finishes Stair 2 : sedum 3rd fix roof M&E, Balustrading and outlets, handrails, 2nd joinery 1st building airfix test
40 .30
2
SP 1 .37
16 32 27 33
U/S 2.01
40 .89 Ceil
ID 305 ID 302 3
IS 301
04/01/18 Amendments to substation and meeting room layout
to substation layout May 3 NJune19/12/17JulyAmendments August Sept M 08/11/17 Amendments to substation layout
17
ID 301
4
UP
April
First Floor 39.060
Insertion
*
19
2678
Problem
Existing Wall HE Centre 215mm Existing Solid brick wall 25mm cavity Existing Walldepth HE Centre Metal studs at 600mm centres 215mm Existing Solid brick wall- K10/165A 12.5mmcavity Plasterboard 25mm depth
STN/142 35.51
03 319
5
FFL 39.04
*
*
20
6
STN/143 39.04
50
18
Second Floor Plan Wall Construction - Brickwork Outer / RC Wall Inner C 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish
New columns as Structural Engineers specification shown dotted
*
01
17
C
1272
01
319
16
7718
319
40.690
15
Third Floor Plan
Metal studs at 600mm centres - K10/165A 12.5mm Plasterboard
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 Knauf Windliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 1400 25mm Battens to form Service Void inner face strings and 12.5mm GB Plasterboard and skim + exposed concrete columns 12.5mm Plywood
19
7
SP 1 .45
1272
14
March
CH 3.03
AVCL
*
ID 303
18
8
3a
CH 3 .06
CONFETTI
ID 304
16 17
9
HH 2.99 SH 0.84
All exposed steel to be painted as spec M60.150B
5
42.320
15
10
ID 317
IS 304
Sanitery goods, Landscapingvoid supported by Current1718stage is programme Ground floor :just Internal a finishes, M&E, External panels all levels ceilings, 28 Construction fire stopping, suspended on site 06-05-2017 19 Startsteel temporary Joinery 1st and columns 2nd fix, decorationas and the staircase has not Site possession, cabins and welfare, Facingsanitary brickwork all levels 29 tiling, installation 34 arrived.2035 Signage 10 on Ground floor power on/ heat
New beams as Structural Engineers specification
02
1a
1
2a
CH 2.98
4
319
13
O
Feb
215
IS 305A
Third Floor 45.464
HH 2.99 SH 0.84
FFL 35.47
AVCL
inner face strings 30mm Deep Corten Cassettes 69mm Air Gap with Vertical Rails on HH Brackets 43.975 150mm Rockwool DuoSlab Insulation Wall Construction - Corten Outer / SFS Inner 12.5 Knauf Sheathing Board 30mm DeepWindliner Corten Cassettes * 150mmAirSFS Zone, withRails RW45 Insulation 69mm Gap withFilled Vertical on HH Brackets 25mm Battens to form Service Void 150mm Rockwool DuoSlab Insulation 12.5mm Plywood and Sheathing 12.5mm GB Plasterboard and skim + exposed concrete columns 12.5 Knauf Windliner Board 150mm SFS Zone, Filled with RW45 Insulation 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns Wall Construction - Corten Outer / RC Wall Inner 30mm Deep Corten Cladding Panel 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish
12
Jan
W 02 11
TA 2 .27
1400
Key Walls
W 14
W 09
FFL
11
X Wall Construction - Brickwork Outer / SFS Inner HH 2.05 102.5 Black Brick as F10/110 SH 0.87 7 6 Ground Floor 50mm Air Gap with Brick Ties and Support Brackets 1400 35.440 DH 2.05 150mm Rockwool DuoSlab Insulation HH 2.05 0.87 SHBoard Vinyl finish as drawingsUP 401 to 406 to surface of treads12.5 Knauf Windliner Sheathing with min 55mm wide contrasting nosings as spec 150mm DH SFS 2.05 Zone, Filled with RW45 Insulation L30.250B 190 25mm Battens to form Service Void 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns 1in12
Wall Construction CortenPLAN Outer / SFS Inner PROPOSED GROUND FLOOR - GA -1:50
1
D 301
SP 1 .45
E
2
300
H101
D
83
U/S 3.14
Old
3
Dec
W 13
.62 SCH 2
C
1492
4
C 222
F 300
E
E
FFL 39 .04
*
B
164645.464
5
FFL
3562 SCH 2.
A
FFL 35.44
C 222
2279
Ground Floor 35.630
6
D
As the stairs is linked to the old and new building, it is * the main escape Therefore, it needs to connections,for Frame,fire. Cladding, coat route 25 Stats 14 Corten steel all levels 30 M&E be wide and bigRoof to allow the capacity that they G installation, Stairenough 2finishes, : 2nd fixLift M&E, decoration 223 and external doors 15 staircase,walling suspended ceiling decoration 26 Windows Curtain all levels 31 expect to growInternal to in 2021,2022 to evacuate safely. partitions, Wall and ceiling HH 2.19 SH 0.46
Infilling opening
7
CH 4.46
Handrail and guarding to extend 300mm beyond first step
8
C
Ea
Col
ID 018
9
U/S 1.39
B
2
stage 4 11 lift shaft and roof 23 Steelwork 1400 Subcontractor 12 procurement External panels all levelsbuilding, roof 28 Alterations to existing Enabling works, Site set up, Service 24 protection ID 319 disconnetions, Groundworks, Piling 13 Facing all dryline levels walls, 29 Stair 2 brickwork : Ist fix M&E, mist 10
allery H002 G CH 2.99
50 *
Lift
Ee
Ed Ec Eb
A
39 .08
ID 019
U/S 2.76
H003
X010 STAIR 2
3947.5(17 1/2 bricks)
STN/143 39 .04
X011 STAIR 2 Steel stairs to Structural Engineer's details LOBBY
1135
2597.5
CH 3 .03
Beams stairs to Structural Engineer's details
Nov
ED 03
3
CH 2.99
* *
2678
1
1
CH 2.76
35.47
point
1272
2
2
Oct
3311
.90 SCH 4
3
3
2017 2018
Ground Floor 35.630
2806
38 .23
4
4
August X020 Sept MTG 3 9 m2
HH 2 .87 SH 0.80
5
5
X014 SERVER 16Ground m2 Floor 35.048
.33 SCH 4
6
6
July
38 .21
7
7
June
Ceil 41 .10
8
AprilX004May MTG 2 8 m2
Wall 1 .29h
9
8
ID 010
NEW IS 004
38 .22
FFL 35.63
10
Existing half truss removed to Structural Engineer's details
9
NEW ID 021
ID 012
HH 2 .87 SH 0.80
DP
THL 35.64
Insertion
2 STN/14 35.51
314
ED 14
10
1567
5729
Insitu frame, PCC stairs between ID 318 Stair : 3rd M&E, Balustrading and 10 Planning conditions discharge floors2up to fix roof deck 22 handrails, 2nd structural fix joinery and 1010 27 Architectural, civil to
Ground Floor 35.630
2000
32.86
ID 017
124
Ground Floor 35.048
2810
25 Site possession, cabins and welfare, 7 coat Tender addendum information 20 Signage 5 Stair soil 2 : 2nd fixreduce M&E, decoration Top strip, dig, Piling, 8 Contract appointment Balustrade returned to wall along top landing. U/S 2.37 suspended ceiling decoration 26 9 staircase, Technical DesignLift stage Ground beams, pit foundation 21
628
2707
837
Wheelchair Refuge
1010
753
3153
1736
20
U/S 3.49
19
1987
18
100
17
U/S 4.30
16
98
15
1010
14
X018 NEW (86m2
Ground Floor 35.048
Ed
1874
13
157
12
1400
11
250
10
1400 inner face strings
9
1400inner face strings
8
1400inner face strings
7
758
6
DH 2.04
5
1400inner face strings
4
794
3
2000
IS 003
1736
753
600 800
2
420
B
400
New 1
X015 COMMS 13 m2
221 B
221
ID 016
35.630
1732
ID 011 doors IS 002 Insitu frame, stairs between andPCC external 15 2 Windows floors up to roof deck 22 Mechanic al Internal partitions, Wall and ceiling 3 riser 16 finishes 4 Month/year March Steelwork lift shaft andX002 roof 23 X012 ID 015 MTG 1 clnrs Alterations to existing roof Sanitery goods, Landscaping 17 5 Task 9building, m2 cpbd Construction programme 18 protection 24 62 Tender programme 3m Start 2on: Ist sitefix06-05-2017 19 Stair M&E, dryline walls, mist 124
422 1095
35.61
1135
Confetti
1094
191
3436
Site possession,Groundworks, cabins and Piling 13 disconnetions, Eb welfare, 20 Signage Stats connections, A Frame, Cladding, 1235 2000Piling, strip, reduce dig, M&Esoil1215 14 Top 1 beams, Lift pit foundation 21 Ground Roof finishes, Lift installation,
Ea
ID 014 1010
378
ID 009 X018 X003 Ec Staff OFFICE Corridoor 34 m2 Ground Floor Ground Floor 34.740 B C D E11891 F G H I J K L M N O P Q R S T U V35.630 W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC Ground Floor
Wheelchair Refuge
2
ID 013 1736
287
2339
1200 400 800
3a
Indicative location of reception desk by others
312
Architectural, structural and civil to Sanitery stage 4 goods, Landscaping Construction Subcontractorprogramme procurement Start on site 06-05-2017 Enabling works, Site set up, Service
17 11 18 12 19
al
riser
7340
s) 4 1/2 brick
4.5
16 10 finishes Planning conditions discharge
7752 .5(3
10932
1930
S TA I R
W 01
00
630
Secure line
Handrail and guarding to extend 300mm beyond first step
974
2278
U/S 1.93
1400
Section XX All dimensions and levels subject to check site measurement
163.3
First tread and quarter landing to be formed in timber
+0.05
35.957 35.630
CH 2.49
CH 2.46
inner face strings
33 Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
41.964
C O U RT YA R D
4.6
This makes use of the design of the building in Role in the building design Timber Structure to be confirmed following • The only external space and smoking area X102 KITCHEN
X105 • Outdoor seating for cafe area COMPUTER SUITE
construction process to make construction more convenient. It shows that the design itself can incorporate with the construction process for temporary purposes. 3111
details from SE
First Floor 38.930
Caterliver deck on first floor
X004 MTG 2
Same as ground Floor (Type 12) but on Precast concrete Plank to Structural Engineer's details
X014
• Allow space to insert cantileverSERVER deck to shift and lift things Detail S - 301
Ground Floor 38.568
• Allow workers to move materials easily upwards, saving more time and become more efficient
Lift up
Role in the construction process
Detail V - 301
3235
SSL 38.558
Ground Floor 35.048
Ground Floor 34.770
Temporary space for gathering materials Detail Z - 301
G
H
I
34
4.7
E XTERNAL
lift shaft and roof 23 10 Steelwork Planning conditions discharge Alterations to existing building, Architectural, structural and civilroof to protection 24 stage 4 11 12 Stair Subcontractor procurement 2 : Ist fix M&E, dryline walls, mist 25 coat Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC Stair 2connections, : 2nd fix M&E, decoration Stats Frame, Cladding, staircase, suspended ceiling decoration 26 14 M&E 1 Roof finishes, Lift installation, 2 : 3rd fixexternal M&E, Balustrading and Windows and doors 15 2 Stair 2nd fix joinery 27 handrails, Internal partitions, Wall and ceiling 3 2017 2018 16 finishes 4 Month/year March April May June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept 28 External panels all levels
E N V E LO P E & S TA I R 1 Confetti
Sanitery goods, Landscaping 17 5 Task Construction programme 18 Facing brickwork all levels 29 6 Tender programme 19 Start on site 06-05-2017 Site possession, cabins and welfare, 7 Corten Tender addendum information steel all levels 30 20 Signage Top soil walling strip, reduce dig, Piling, 8 Curtain Contract appointment all levels 31 9 Technical DesignLift stage Ground beams, pit foundation 21 Roof parapets, deck, insulation, Insitu frame, PCC sedum roofstairs between 32 outlets, 10 discharge floors upconditions to air roof deck 22 1st building test 33 Planning 11 23 12 24 34 13 35 25 14 36 15 26 37 16 27 17 38 18 28 39 19 29 20 40 30 21 41 31 22 32 42 23 33 43 24 25 34 44 35 45 26
Architectural, and civilM&E, to Ground floor :structural Internal finishes, stage 4 Steelwork lift shaft and roof fire stopping, suspended ceilings, Subcontractor procurement Alterations to existing roofand Joinery 1st and 2nd fix,building, decoration Enabling works, Site set up, Service protection tiling, sanitary installation disconnetions, Groundworks, Piling Ground floor on/ heat on Stair 2 : Ist fix power M&E, dryline walls, mist Stats connections, Cladding, First : InternalFrame, finishes, M&E, fire coat floor M&E stopping, suspended ceilings, Joinery 1st and decoration and tiling, Roof installation, Stair 2finishes, : 2nd 2nd fix, fixLift M&E, decoration sanitary Windows and external doors staircase,installation suspended ceiling decoration First floor power on/ heat Internal partitions, Wall andonceiling Second floor : Internal finishes, M&E, finishes Stair 2 : 3rd fix M&E, Balustrading and fire stopping, suspended ceilings, handrails, 2nd fix joinery Joinery 1st and 2nd fix, decoration and Sanitery goods, Landscaping tiling, sanitary installation Construction programme External panels all levels Second floor power on/ heat on Start on site 06-05-2017 Third floor : Internal finishes, M&E, Site possession, cabins and welfare, Facing brickwork all levels fire stopping, suspended ceilings, Signage Joinery 1st and 2nd fix, decoration and Top strip,allinstallation reduce tiling,soil sanitary Corten steel levels dig, Piling, Ground beams, Lifton/ pit heat foundation Third floor power on Fourthframe, floor :PCC Internal finishes, M&E, Insitu stairs between Curtain walling all levels fire stopping, suspended floors up to roof deck ceilings, Roof parapets, insulation, Joinery 1st and deck, 2nd fix, decoration and outlets, sedum roof tiling, sanitary installation Steelwork lift shaft and 1st building test on/ roof Fourth floorair power heat on Alterations to existing building, roof Ground floor : Internal finishes, M&E, Fifth floor : Internal finishes, M&E, fire protection fire stopping, suspended ceilings, stopping, suspended ceilings, Joinery Stair 2 :1st Ist and fix dryline walls, mist Joinery 2nd fix, decoration and 1st and 2nd fix,M&E, decoration and tiling, coat tiling, sanitary installation sanitary installation Ground floor power Fifth floor power on/ on/ heatheat on on Stair 2floor : 2nd fix M&E,finishes, decoration First floor :: Internal M&E, Sixth Internal finishes, M&E, fire fire staircase, suspended ceilings, ceiling decoration stopping, suspended Joinery 1st and 2nd fix, decoration and tiling, Stair 2 : 3rd fix M&E, Balustrading and sanitary installation First floor power on/ handrails, fix joinery Sixth floor2nd power on/ heat heat on on Second Internal Decoration, finishes, M&E, Stair 1 : floor M&E,: Joinery, fire stopping, suspended suspended ceiling, External panels all Balustrading levels ceilings, Joinery 1st and 2nd fix, decoration and Final testing and commissioning, air tiling, sanitary installation testing,brickwork final clean all andlevels snag Facing Second floor power on/ heat on External landscaping, snag and clean Third floor : Internal finishes, M&E, externals Corten steel all levels ceilings, fire stopping, suspended PRACTICAL COMPLETION Joinery 1st and 2nd fix, decoration and tiling, sanitary Curtain wallinginstallation all levels Month/year March Third floor power on/insulation, heat on Roof parapets, deck, Fourth floor : Internal outlets, sedum roof finishes, M&E, fire stopping,airsuspended ceilings, 1st building test Joinery 1st and 2nd fix, decoration and Ground floor : Internal finishes, M&E, tiling, sanitary installation fire stopping, suspended ceilings, Fourth floor power on/ heat on Joinery 1st and 2nd fix, decoration and Fifth floor : Internal finishes, M&E, fire tiling, sanitary installation stopping, suspended ceilings, Joinery Ground floor power on/ heat on 1st and 2nd fix, decoration and tiling, First floor : Internal finishes, M&E, fire sanitary installation stopping, suspended ceilings, Joinery Fifth floor power on/ heat on 1st and 2nd fix, decoration and tiling, Sixth floor : Internal finishes, M&E, fire sanitary installation stopping, suspended ceilings, Joinery First floor power on/ heat on 1st and 2nd fix, decoration and tiling, Second floor : Internal finishes, M&E,
The programme of external envelope, including: brickwork and corten steel has delayed. This is due to the delay of the steel frame system programme as the steel frame hold the external claddings. If the frame work has not completed, the claddings are not able to apply on top. Therefore, more details of claddings will be discussed in Chapter 7: Visit 5 & Chapter 8: Visit 6. Stair 1 is a pre-cast concrete staircase that is manufacture by subcontractor and the work on site will only be attaching the staircase on walls and further furnishing. However, the manufacturer has not produced the staircase and delayed the schedule of the installation of stair 1 on site. Therefore, only steel frame are supporting and forming the void for the Stair 1 to fit in. More details will be included in Chapter 7: Visit 5.
Not yet fit in steel frame system for external walls, could not install external claddings 48 28 36 46 37 27 47
38 49 29 39 50 30 51
Supporting the superstructure 40 31 52 with steel frame April May 41 32 53 33 42 43 34 35 44 45 36 37
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
35
5
S ITE
VISIT 3
Date: 5 December 2017 Weather: Passing clouds Temperature: 8 °C People on site: 30 to 40
• Project manager
• Contractors
• Workers
• Students and tutors
3 4
2017 2018
Month/year
March
5 Task 6 Tender programme
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
P ROGRAMME
5.1
7 Tender addendum information 8 Contract appointment 9 Technical Design stage
10 Planning conditions discharge Architectural, structural and civil to 11 stage 4 12 Subcontractor procurement Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling Stats connections, A Frame, Cladding,
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCCDCECFCGCHCICJ
Confetti
14 M&E 1 Roof finishes, Lift installation, 15 2 Windows and external doors 3 Internal partitions, Wall and ceiling 16 finishes 4 Month/year Sanitery goods, Landscaping 17 5 Task Construction programme 18 6 Tender programme 19 Start on site 06-05-2017 Site possession, cabins and welfare, 7 Tender addendum information 20 Signage soil strip, reduce dig, Piling, Contract appointment 8 Top DesignLift stage 9 Technical Ground beams, pit foundation 21 Insitu frame, PCC stairs between Planning discharge 10 upconditions to roof deck 22 floors Architectural, structural and civil to stage 4 11 lift shaft and roof 23 Steelwork procurement 12 Subcontractor Alterations to existing building, roof works, Site set up, Service protection 24 Enabling Groundworks, Piling 13 disconnetions, Stair 2 : Ist fix M&E, dryline walls, mist coat connections, Frame, Cladding, 25 Stats 14 M&E Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windows suspended and external doors 15 ceiling decoration 26 staircase, Internal partitions, Wall and ceiling finishes 16 Stair 2 : 3rd fix M&E, Balustrading and 27 handrails, 2nd fix joinery 17 18 28 19
Sanitery goods, Landscaping Construction External panelsprogramme all levels Start on site 06-05-2017
possession, and welfare, Facing brickworkcabins all levels 29 Site 20 Signage soilsteel strip,allreduce Corten levels dig, Piling, 30 Top 21 Ground beams, Lift pit foundation frame, PCC Curtain walling all stairs levels between 31 Insitu 22 floors up to roof deck Roof parapets, deck, insulation, 32 outlets, sedum roof 23 1st buildinglift airshaft test and roof 33 Steelwork Alterations to existing building, roof Ground floor : Internal finishes, M&E, 24 protection fire stopping, suspended ceilings, Stair 2 :1st Ist and fix M&E, dryline walls, mist Joinery 2nd fix, decoration and 25 tiling, sanitary installation 34 coat 35 Ground floor power on/ heat on Stair 2 : 2nd fix M&E,finishes, decoration First floor : Internal M&E, fire suspended ceilings, ceiling decoration 26 staircase, stopping, suspended Joinery 1st and 2nd fix, decoration and tiling, 36 Stair sanitary installation 2 : 3rd fix M&E, Balustrading and 37 handrails, First floor 2nd power on/ heat on fix joinery 27 Second floor : Internal finishes, M&E, fire stopping, suspended panels all levels ceilings, 28 External Joinery 1st and 2nd fix, decoration and 38 tiling, sanitary installation 29 Facing brickwork all levels 39 Second floor power on/ heat on Third floor : Internal finishes, M&E, steel all levels ceilings, 30 Corten fire stopping, suspended Joinery 1st and 2nd fix, decoration and 40 Curtain tiling, sanitary wallinginstallation all levels 31 41 Third floor power on/insulation, heat on Roof parapets, deck, : Internal outlets,floor sedum roof finishes, M&E, 32 Fourth stopping,airsuspended ceilings, 1st building test 33 fire
2017 2018 March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
According to the programme of the contractors, the following tasks should be finished or in progress on 14 November. Tasks are expected finished: • Site possession, cabins and welfare,Signage • Top soil strip, reduce dig, Piling,Ground beams, Lift pit foundation • Steelwork lift shaft and roof • Alterations to existing building, roof protection • Stair 2 : 1st fix M&E, dryline walls, mist coat • Stair 2 : 2nd fix M&E, decoration staircase, suspended ceiling decoration • Stair 2 : 3rd fix M&E, Balustrade and handrails, 2nd fix joinery External panels all levels Task are expected in progress: • Insitu frame, PCC stairs between floors up to roof deck • Facing brickwork all levels • Corten steel all levels • Curtain walling all levels • Roof parapets, deck insulation, outlets and sedum roof Scheduled programme in visit date Real on site programme 37
3215 2017 2018 May
June
July
August Sept
Oct
Nov
Dec
3111
Room Server 3.01 SCH
38.26
FFL 37.76
9
3235
C105 CH 3.02
U/S 2.4
FFL 37.92
access
DH 2.00
1 STN/11 38.32
FFL 38.29
SCH 2.58
SCH 2.38
DH 2.01
HH 1.92 SH 1.09
HH 1.92 SH 1.09
HH 1.92 SH 1.09
HH 1.92 SH 1.09
HH 1.92 SH 1.09
DH 1.95
HH 1.92 SH 1.09
HH 1.92 SH 1.09
HH 1.92 SH 1.09
Step
FFL 38.12
SH 0.88 TA 2.95 DH 1.95
CH 2.37
5 STN/11 36.46
CH 3.01
SH 0.87 TA 2.94
FFL 38.23 Ceil 40.88
SH 0.86 TA 2.94
CH 2.37
DH 1.95 FFL 38.11
FFL 38.13
DH 1.96
38.12
SCH 2.44
FFL 38.06
DH 1.94
DH 1.94
2 STN/11 38.10
Step
4 STN/11 38.04
CH 2.88
SH 0.63 HH 3.05
FFL 38.13
SCH 2.41
beam downstand
CH 2.77
Win/A SH 2.04
X114 NEW RAISED COURTYARD
First Floor 38.568
X102 KITCHEN 24m2
X102 KITCHEN 12 m2
GRAB AND GO
ID 110
x 550 deep
Ground Floor 34.770
ID 108
First Floor 38.930
Mechanical riser
void
9 STN/10 38.27
AREA
300 wide
First Floor X103 38.930 CAFE SERVERY 38 m2
U/S 2.50
NEW COURTYARD
W 07 ADDITIONAL SEATING
First Floor 38.930
Eb Ea
GA Section
NEW DOORS OUT TO
First Floor 38.360
Electrical riser
Ed
First Floor 38.930
221 B
422
W 01
ACROSS
Ec
200 wide x 1000 high upstand
FFL 38.23
LOW WALL 1100MM HIGH
3a
312
DH 2.02
NEW STEPS
1100MM HIGH
3
U/S2.1
DRAWING
ED 16
ACCESS
ID 107 LOW WALL
ID 109
3
0
1in15
CH 3.26
1in15 First Floor 38.764
First Floor 38.930
SH 0.90 HH 2.53
2
FFL 38.36
Ground Floor 35.048
1in15
ED 15
First Floor 38.568
1
2
IS 101
ID 106
First Floor 38.360
DH 2.00 Win/A SH 2.05 HH 2.53
ID 105
ID 102 3
4
2a
570
DH 2.02
ID 101
First Floor 38.764
X101 CAFE 151 m2
U/S 2.01
40.89 Ceil
UP
8 STN/10 38.36
X109 STAIR 1 LOBBY
5
38.27
38.21
20
STN/11 38.23
First Floor 38.568
19
6
W 04
220 A
X104 SEMINAR ROOM 30 m2
ID 104 ID 103
FFL 38.28 SH 0.91 HH 1.96
18
7
DH 1.96
17
8
U/S 41.09
U/S level 41.06
X106 FEMALE WC
16
X108 STAIR 1
9
Floor Slope 38.31
X107 ACCESSIBLE WC 15
10
310
38.24
1a
U/S 2.94
Limited
Room Server CH 3.34
38.26
OH 2.04
W 02 11
1
FFL 37.76
TA 2.90 SH 0.82
TA 2.92 SH 0.85
TA 2.89 SH 0.81
HH 2.99 SH 0.79
FFL 40.30
beam
SCH 4.33
downstand
STN/12 39.72
x 550 deep
SCH 4.90
W 06 300 wide
38.23
300
D 301
First Floor 38.930
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
W 08
20
4 ID 112
1010
CH 3.03
19
20
U/S 2.58
7110
ID 113
125 354 1010
100
New ramp to be constructed by contractor
F
G
Col
SH 0.81 HH 2.93
U/S 2.93
18
Col
CH 2.99
DH 2.05
21 20
DRAWING NUMBE dumb waiter 1100x1100
cupbd
Store 1.54 sqm
Chang S
shaft
39.04
HH 2.83 SH 0.73
recess for drinking tap
Disabled WC + shower
wash
U/S 2.71
Col H104 SCH 2.56
Turning circle
Male WC
COURTYARD
7
STN/14 39.01
U/S 2.93
CH 3.01
HH 2.83 SH 0.73
221
FFL
SP 1.37
U/S 2.78
19
23 22
cook
U/S 2.71
CH 3.01
CH 2.49
CH 3.07
6
TA 2.23
CH 3.06
FFL 39.06
I
Lounge
26 25 24 16 17
up
SP 1.37
U/S 2.57
prep
29 28 27
C120 U/S 2.78
FFL 39.07
SH 0.79 HH 2.88
2588
To ConFetti
15 14
FFL 39.01
1010
H
U/S 2.71
SP 1.37
634
C101
Link to Confetti
DH 2.06
STN/14 39.07
CH 2.99
FFL 39.06
CH 2.99
TA 2.23
DH 2.04
H
C101/102 LIVE ROOM
up
E
SP 1.37
CH 3.03
D
SP 1.45
C
CH 3.06
B
3622
222 A
C110
PROJECT NUMBER
Ee
WINDOW
U/S 2.71
Detail Z - 301
First Floor 39.060
TA 2.27
SH 0.82 HH 2.95
21
100
18
First Floor 38.930
UP 130 1in12
H103 SCH 2.61
110
17
Lift
First Floor 39.060
Col
16
C
910 333 Wheelchair Refuge
X111 STAIR 2 LOBBY
SP 1.45
15
248
ID 114
OMIT FULL HEIGHT
ID 111
1031
X110 STAIR 2
SH 0.81 HH 2.93
1
U/S 2.58
2
CH 3.01
3
SH 0.81 HH 2.93
4
SH 0.81 HH 2.93
5
U/S 2.58
6
CH 3.01
7
SH 0.81 HH 2.93
8
314
X112 clnrs cpbd SH 0.95 HH 2.17
SH 0.82 HH 2.95 CH 3.03
2010
600
FFL 39.04
Lift U/S 2.71
Col
U/S 2.81
CH 3.01
CH 3.01
Existing door to be relocated
SH 0.81 HH 2.93
DH 2.05
This drawing is copy
HH 2.78 SH 0.68
S14
U/S 2.78
FFL 39.05
CH 3.16
U/S 2.26
U/S 2.96
FFL 39.04
DH 2.05
door blocked
CH 4.85
DH 1.98
No access
CH 3.01
CH 3.02
8
STN/14 39.03
CH 3.00
W he Re elcha fuge ir
Generally do not sca Stair 1
DH 2.05
45
46 47 48 49 28 29 30 31
H105 SCH 2.60
Col
32
Col
S15
33
FFL 39.03
36 48 37
F
E 300
Ea
W 05
U/S 2.56
HH 2.83 SH 0.73
STN/1 34.68
34 35 46 44 47 45
E
3
44 42 45 43
C 222
D
FFL 39.08
32 33
0115 950 71
Confetti C
Ed Ec U/S 1.39
C
H102 SCH 2.58
42 40 31 43 41
421
420 B
STN/14 39.04
30
F
PROJECT Ee
Eb
A
H101 SCH 2.62
40 38 29 41 39
X014 SERVER
CH 3.03
28
0115 841 84
Confetti M
Detail V - 301
Same as ground Floor (Type 12) but on Precast concrete Plank to Structural Engineer's details
Ceil 41.10
38 36 39 37 27
T
CLIENT
Wall 1.29h
26
Corten steel all levels Construction External panelsprogramme all levels Start on site 06-05-2017 Curtain walling all levels Site possession, cabins and welfare, Facing brickwork all levels Roof parapets, deck, insulation, Signage outlets, sedum roof Top soilsteel strip, Corten levels dig, Piling, 1st building airallreduce test Ground beams, Lift pit foundation Ground floor : Internal finishes, M&E, Insitu frame, PCC Curtain walling all stairs levels between fire stopping, suspended ceilings, floors up to roof deck Joinery 1st and deck, 2nd fix, decoration and Roof parapets, insulation, tiling, sanitary outlets, seduminstallation roof Steelwork lift Ground floor power on/roof heat on 1st building airshaft test and Alterations to existing building, roof First floor : Internal finishes, M&E, fire Ground floor : Internal finishes, M&E, protection stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st and 2nd fix,M&E, decoration and tiling, Stair 2 :1st Ist and fix dryline walls, mist Joinery 2nd fix, decoration and sanitary installation coat tiling, sanitary installation First floor power on/ heat on Ground floor power on/ heat on Second : Internal finishes, M&E, Stair floor 2 : floor 2nd fix M&E,finishes, decoration First : Internal M&E, fire fire stopping, suspended ceilings, staircase, suspended ceiling stopping, suspended ceilings,decoration Joinery Joinery 1st and 2nd fix, decoration and 1st and 2nd fix, decoration and tiling, tiling, sanitary installation sanitary installation Stair 2 : 3rd fix M&E, Balustrading and Second floorS power on/ heat on Detail -fix 301 First floor power on/ heat on handrails, 2nd joinery Third floor : Internal finishes, M&E, Second floor : Internal finishes, M&E, fire stopping, suspended ceilings, fire stopping, suspended ceilings, External panels all levels Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary installation Facing brickwork levels Third floor powerallon/ heat on Second floor power on/ heat on Fourth floor : Internal finishes, M&E, Third floor : Internal finishes, M&E, fire stopping, suspended Corten steel all levels ceilings, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and Joinery 1st and 2nd fix, decoration and tiling, sanitary installation tiling, sanitary Curtain wallinginstallation all levels Fourth floor power on/ heat on Third floor power on/insulation, heat on Roof parapets, deck, Fifth floor : Internal finishes, M&E, fire Fourth floor : Internal finishes, M&E, outlets, sedum roof stopping, suspended ceilings, Joinery fire stopping, suspended ceilings, 1st 1st building and 2nd air fix,test decoration and tiling, Joinery 1st and 2nd fix, decoration and sanitary installation Ground floor : Internal finishes, M&E, tiling, sanitary installation Fifthstopping, floor power on/ heat on fire suspended ceilings, Fourth floor power on/ heat on Sixth floor Internal finishes, M&E, fire Joinery 1st :and 2nd fix, decoration and Fifth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery tiling, sanitary installation stopping, suspended ceilings, Joinery 1st and 2nd decoration andontiling, Ground floorfix,power on/ heat 1st and 2nd fix, decoration and tiling, sanitary installation First floor : Internal finishes, M&E, fire sanitary installation Sixth floorsuspended power on/ceilings, heat onJoinery stopping, Fifth floor power on/ heat on 1st and 2nd fix,Joinery, decoration and tiling, Stair 1 : M&E, Decoration, Sixth floor : Internal finishes, M&E, fire sanitary installation suspended ceiling, Balustrading stopping, suspended ceilings, Joinery First floor power on/ heat on air Finaland testing anddecoration commissioning, 1st 2nd fix, and tiling, Second floor : Internal finishes, M&E,
D
16-20 Bath St Ground Floor 38.360
38.22
36 25 34 37 35
July
Architects
HH 2.87 SH 0.80
34 32 23 35 33 24
G
X105 COMPUTER SUITE
SH 0.82 HH 2.95
31 22
June
HH 2.87 SH 0.80
X004 MTG 2
May
The courtyard area was used as a storage space in the last visit , but now the courtyard is prepared Stair : 3rd fix M&E, Balustrading Frame, Cladding,and coat 2connections, 25 Stats to be constructed. the designed has a raised handrails, 2ndAs fix joinery 27 M&E 14 Ground Floor Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration 38.568are inserted in courtyard, 152826steel beams and columns Windows and external doors External panels all levels staircase, suspended ceiling decoration Internal partitions, Wall and ceiling the courtyard area and ready for putting pre-cast 16 Stair 2 brickwork : 3rd fix M&E, Balustrading and Facing all levels 29 finishes handrails, 2nd fix joinery concrete on2717 top as the floor slabs. Sanitery goods, Landscaping 30 18 28 19 31 29 20 32 30 33 21
X003 OFFICE
April
REV. DATE
SH 0.79 HH 2.95
The superstructure is still under construction and the current stage of the programme is pouring concrete on the 5th floor slabs and columns. They are getting ready to repeat the work on the 6th floor, which is the roof level.
March
Duct
Ground beams, Lift pit foundation Construction programme Tender programme Start on site 06-05-2017 Insitu frame, PCC stairs between floors upaddendum to roofcabins deck Site possession, and welfare, Tender information Signage Steelwork lift shaft anddig, roof Top soil strip, reduce Piling, Contract appointment Technical Design stage Ground beams, Lift pit building, foundation Alterations to existing roof 24 protection Insitu frame, PCC stairs between 10 Planning conditions discharge floors tofix roof deck 22 Stair 2up : Ist M&E, dryline walls, mist 25 coat Architectural, structural and civil to 4 11 Steelwork lift shaft and roof 23 stage 12 Subcontractor procurement Stair 2 : 2ndtofixexisting M&E, decoration Alterations building, roof staircase,works, suspended ceiling 26 protection Enabling Site set up, decoration Service 24 disconnetions, Groundworks, Piling 13 Stair 2 : Ist fix M&E, dryline walls, mist
U/S 2.59
X102 KITCHEN
Feb
Top soil goods, strip, reduce dig, Piling, Sanitery Landscaping Task
STEEL STRUCTURE
X103 QUIET CAFE
Jan
U/S 2.07
April
U/S 2.00
March
SH 0.79 HH 2.95
INSITU FRAME & CONCRETE
30/05/17 Dr 12/05/17 Am Su BAugust 10/01/17 Sp Sept A 23/12/16 Am
HH 2.41 SH 0.68
17 5 21 18 6 19 22 7 20 23 8 9 21
D C
Ground Floor 41.964
A 220
S
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC
B
5.2
U P E R S T R U C T UConfetti RE
X205 COMPUTER SUITE
221
X203 LRC
Groundworks, 13 10 disconnetions, Planning conditions discharge Piling Stats connections, Frame, Cladding, Architectural, structural and civil to M&E 4 14 stage 11 12 Roof Subcontractor procurement finishes, Lift installation, and external 15 Windows Enabling works, Site setdoors up, Service disconnetions, Groundworks, Piling 13 Internal partitions, Wall and ceiling 16 finishes Stats connections, A Frame, Cladding, 14 M&E 1 Sanitery goods, Landscaping 17 Roof finishes, Lift installation, 18 Windows and programme external doors 15 2 Construction Start on partitions, site 06-05-2017 19 Internal Wall and ceiling 3 possession, cabins and welfare, finishes 16 Site 4 Month/year Signage 20
PROPOSED FIRST FLOOR GA PLAN -1:100
HH 2.83 SH 0.73
CH 3.01
AV Store HH 2.83 SH 0.73
HH 2.83 SH 0.73
HH 2.83 SH 0.73
38
44
43 42 41 40 39 38 37 36 35 34
S TEEL
F RA M E & E X T E R N A L E N V E LO P E Confetti
Sanitery goods, Landscaping 17 5 Task Construction programme 18 Facing brickwork all levels 29 6 Tender programme 19 Start on site 06-05-2017
30
5.3
lift shaft and roof 23 10 Steelwork Planning conditions discharge Alterations to existing building, Architectural, structural and civilroof to protection 24 stage 4 11 12 Stair Subcontractor procurement 2 : Ist fix M&E, dryline walls, mist 25 coat Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCC Stair 2connections, : 2nd fix M&E, decoration Stats Frame, Cladding, staircase, suspended ceiling decoration 26 14 M&E 1 Roof finishes, Lift installation, 2 : 3rd fixexternal M&E, Balustrading and Windows and doors 15 2 Stair 2nd fix joinery 27 handrails, Internal partitions, Wall and ceiling 3 2017 2018 16 finishes 4 Month/year March April May June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept 28 External panels all levels
Site possession, cabins and welfare, 7 Corten Tender addendum information steel all levels 30 20 Signage
35mm Benchmark Metallic Recessed Fix Cassette or similar
100 mm Infill SFS fixed to the structure
FFL = 45.464
1428-4008
Architectural, and civilM&E, to Ground floor :structural Internal finishes, 4 11 Steelwork lift shaft and roof 23 stage fire stopping, suspended ceilings, 12 Subcontractor procurement Alterations to existing roofand Joinery 1st and 2nd fix,building, decoration Enabling works, Site set up, Service protection 24 34 tiling, sanitary installation Groundworks, Piling 13 Ground floor on/ heat on 35 disconnetions, Stair 2 : Ist fix power M&E, dryline walls, mist connections, Cladding, First : InternalFrame, finishes, M&E, fire coat floor 25 Stats Breather Membrane (to be confirmed) Bracket VB/180 with 14 Adaptor M&E stopping, suspended ceilings, Joinery FOR ZONES 200-235mm 1st and decoration and tiling, Roof installation, Stair 2finishes, : 2nd 2nd fix, fixLift M&E, decoration 36 Windows and external doors 15 staircase,installation suspended ceiling decoration 26 sanitary 12.5mm Thick CP Board: Knauf Windliner floor power on/ heat 37 First with taped joints Internal partitions, Wall andonceiling floor : Internal finishes, M&E, Corten Cladding Panel finishes 16 Second Stair 2 : 3rd fix M&E, Balustrading and Vapour Control Layer fire stopping, suspended ceilings, 27 handrails, 2nd fix joinery Internal Finishes:25mm Timber baton, Joinery 1st and 2nd fix, decoration and 12.5mm Plywood,12.5mm BG Plasterboard 17finishSanitery goods, Landscaping with skim 38 tiling, sanitary installation Construction programme 18 Horizontal Rail 60x40x2mm TBC panels all levels 28 Second floor power on/ heat on 39 External 19 Start on site 06-05-2017 Third floor : Internal finishes, M&E, possession, cabins and welfare, Facing brickwork all levels 29 Site fire stopping, suspended ceilings, 20 Signage Joinery 1st and 2nd fix, decoration and Top strip,allinstallation reduce tiling,soil sanitary 40 Corten steel levels dig, Piling, 30 beams, Lifton/ pit heat foundation 21 Third floor power on 41 Ground 150mm SFS with 150mm Fourthframe, floor :PCC Internal finishes, M&E, Insitu stairs between RWA45 Insulation in cavity 31 Curtain walling all levels 150mm Rainscreen Duo stopping, suspended floors up to roof deck ceilings, 22 fire Slab Roof parapets, insulation, Joinery 1st and deck, 2nd fix, decoration and outlets, sedum roof 32 tiling, sanitary installation 42 Steelwork lift shaft and 23 building test on/ roof 33 Fourth floorair power heat on 43 1st Alterations to existing building, roof Ground floor : Internal finishes, M&E, Fifth floor : Internal finishes, M&E, fire 24 protection fire stopping, suspended ceilings, stopping, suspended ceilings, Joinery Stair 2 :1st Ist and fix dryline walls, mist Joinery 2nd fix, decoration and 1st and 2nd fix,M&E, decoration and tiling, 25 tiling, sanitary installation 34 coat sanitary installation 44 Ground floor power 35 Fifth 45 floor power on/ on/ heatheat on on PVC Isolation tape between dissimilar metals Stair 2floor : 2nd fix M&E,finishes, decoration First floor :: Internal M&E, Sixth Internal finishes, M&E, fire fire REV. DATE DESCRIPTION BY Bracket Adaptors do not generally suspended ceilings, ceiling decoration 26 staircase, stopping, suspended Joinery penetrate insulation zone 1st and 2nd fix, decoration and tiling,Horizontal Rail 60x40x2mm TBC 36 Stair 2 : 3rd fix M&E, Balustrading and sanitary installation 46 First floor power on/ 37 handrails, fix joinery 27 47 Sixth floor2nd power on/ heat heat on on Architects, Landscape & Interior Design Second Internal Decoration, finishes, M&E, Stair 1 : floor M&E,: Joinery, 16-20 Bath Street, Nottingham NG1 1DF fire.co.ukstopping, suspended 48 External suspended ceiling, T 0115 841 8418 E design@allanjoycearchitects panels all Balustrading levels ceilings, 28 F 0115 950 7161 W www.allanjoycearchitects .co.uk Joinery 1st and 2nd fix, decoration and Final testing and commissioning, air CLIENT 38 tiling, sanitary installation testing,brickwork final clean all andlevels snag 49 Facing 29 Confetti Media Group 39 Second floor power on/ heat on External landscaping, snag and clean Third floor : Internal finishes, M&E, PROJECT 50 Corten steel all levels ceilings, 30 externals fire stopping, suspended Confetti CQ Campus 51 PRACTICAL COMPLETION Joinery 1st and 2nd fix, decoration and DRAWING tiling, sanitary 40 Month/year Curtain wallinginstallation all levels 31 52 March April May Facade Section Corten Cladding Detail floor power on/insulation, heat on 41 Third Roof parapets, deck, Fourth floor : Internal PROJECT NUMBER DATE SCALE sedum roof finishes, M&E, 32 53 outlets, 2588 1:20 @ A1 33 fire stopping,airsuspended ceilings, 1st Jul-16 building test DRAWING NUMBER REVISION STATUS BY Joinery 1st and 2nd fix, decoration and Ground floor : Internal finishes, M&E, 301 Preliminary MLD sanitary installation 42 tiling, fire stopping, suspended ceilings, This drawing is copyright and remains the property of Allan Joyce Architects Ltd 43 Fourth floor power on/ heat on Generally do not scale drawings. All dimensions to be checked on site. Joinery 1st and 2nd fix, decoration and Fifth floor : Internal finishes, M&E, fire 34 tiling, sanitary installation stopping, suspended ceilings, Joinery 35 Ground floor power on/ heat on 1st and 2nd fix, decoration and tiling, First floor : Internal finishes, M&E, fire 44 sanitary installation stopping, suspended ceilings, Joinery 45 Fifth floor power on/ heat on 1st and 2nd fix, decoration and tiling, Sixth floor : Internal finishes, M&E, fire 36 sanitary installation stopping, suspended ceilings, Joinery 37 First floor power on/ heat on 1st and 2nd fix, decoration and tiling, Second floor : Internal finishes, M&E,
Insulation by glazing contractor EPDM by glazing contractor Jamb angle by glazing contractor
IF IN DOUBT ASK DO NOT SCALE THIS DRAWING This drawing is the property of Verteks Associates Ltd and is issued on the condition it is not reproduced, retained or disclosed to any unauthorised person, either wholly or in part without the written consent of Verteks Associates Ltd . This drawing should be read in conjunction with all relevant design drawings, calculations and system manufacturers instructions. All dimensions are to be checked by the contractor and any errors or omissions reported prior to commencement of any fabrication and/or installation. Any discrepancies are to be notified immediately.
A01 6
cladding
Current stage: Fixing steel frame on primary structure
16
Drawing Number
6
Corten Steel
100mm Benchmark Quadcore Karrier Vertically laid or similar fixed with a minimum of 2 Nr fasteners per panel per rail U-Value = 0.18W/m2K
Top soil walling strip, reduce dig, Piling, 8 Curtain Contract appointment all levels 31 9 Technical DesignLift stage Ground beams, pit foundation 21 Roof parapets, deck, insulation, Insitu frame, PCC sedum roofstairs between 32 outlets, 10 discharge floors upconditions to air roof deck 22 1st building test 33 Planning
Denotes fixing reference. Read in conjunction with fixing schedule
Glazing by Acorn Position to be agreed
Notes :
1.5mm Corten closer
Associated Drawings :
Curtain Walling System Frameless Window insert to Curtain Walling System
Curtain walling
Mullion fixing to Curtain walling System
1650
180
Gridline A
600
Aluminium Fixing Plate
30
275mm concrete deck to Structural Engineer's details
500
180
C1
Construction issue comments inc
pw 05.10.17
P1
ISSUED FOR APPROVAL First Issue
pw 28.09.17
Description
Revision
Revised By
Date
30
180
Cavity barriers and smoke stop for Curtain Walling to suit site. Bracket Structural Fixing to Structural Engineers Details Acoustic Insulation
Perforated Cor-Ten Cassette Screen setback 25mm from adjacent Corten cladding panels
Curtain walling
Window pod PIR board and fire rated canister applied insulation Outer sill flashing with interface to recessed fix cassette
30
FFL = 38.930
Corten gutter system with interface to recessed fix cassette
Facade Section Detail 1 - 1
300
Waterproof membrane
FFL = 42.230
400
180
Although according to the programme, the corten steel cladding should be finished by the time of this visit, the whole programme has delayed and the task has not started yet.
HORBURY BUILDING SYSTEMS LTD SOUTH GROVE HOUSE ● SOUTH GROVE ● ROTHERHAM ● S60 2AF Tel: 01709 515 044 ● Fax: 01709 515 066
Project
Confetti Campus Nottingham
Package
Rainscreen Cladding Title
Plan Detail Interface with Glazing
The steel frame is now applying on the first and second floor as the superstructure of these 2 levels has completed. They planned to start the curtain wall glazing on Monday, 11 December 201, as the glazing is arriving to the site. Cad File Name
1428
Drawn By
Approved
PW
Date
Drawing Number
Checked
SR
Scale
28.09.17
1:5
1428-4008
Paper Size
A3 C1 Revision
They re-sequence the external envelope, instead of June July August Sept Oct Nov Dec Jan Feb March April May June July August Sept putting up the corten steel cladding, they choose to do The external envelop will be further discussed in the steel frame system and external glazing first. Chapter 7: Visit 5 & Chapter 8: Visit 6 when the work of the curtain wall or claddings start.
39
16 10 finishes Planning conditions discharge
S TA I R
5.4
Architectural, structural and civil to Sanitery stage 4 goods, Landscaping Construction Subcontractorprogramme procurement Start on site 06-05-2017 Enabling works, Site set up, Service
17 11 18 12 19
3
Site possession,Groundworks, cabins and welfare, Piling 13 disconnetions, 20 Signage Stats connections, A Frame, Cladding, M&Esoil strip, reduce dig, Piling, 14 Top 1 beams, pit foundation 21 Ground Roof finishes, LiftLift installation,
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBA
Confetti
Insitu frame, stairsdoors between andPCC external 15 2 Windows floors up to roof deck 22 Internal partitions, Wall and ceiling 3 16 finishes 4 Month/year Steelwork lift shaft and roof 23
2017 2018 March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
Alterations to existing building, roof Sanitery goods, Landscaping 17 5 Task Construction programme 18 protection 24 6 Tender programme Start 2on: Ist sitefix06-05-2017 19 Stair M&E, dryline walls, mist 25 Site possession, cabins and welfare, 7 coat Tender addendum information 20 Signage Stair soil 2 : 2nd fixreduce M&E, decoration Top strip, dig, Piling, 8 Contract appointment suspended ceiling decoration 26 9 staircase, Technical DesignLift stage Ground beams, pit foundation 21
Current stage: Only Stair 3 is fit in , Stair 1 & 2 are still installed
Insitu frame, PCC stairs between Stair 2up : 3rd M&E, Balustrading and 10 Planning conditions discharge to fix roof deck 22 floors 2nd structural fix joinery and civil to 27 handrails, Architectural, 4 11 Steelwork lift shaft and roof 23 stage 12 procurement External panels all levelsbuilding, roof 28 Subcontractor Alterations to existing Enabling works, Site set up, Service 24 protection disconnetions, Groundworks, Piling 13 Facing all dryline levels walls, 29 Stair 2 brickwork : Ist fix M&E, mist
Stair 3 is visible in the site from this visit. It is only in the form of a steel structure without balustrades and furnishing.
Stats connections, Frame, Cladding, 25 coat 14 Corten steel all levels 30 M&E Roof installation, Stair 2finishes, : 2nd fixLift M&E, decoration Windows and external doors 15 staircase,walling suspended ceiling decoration 26 Curtain all levels 31
Further construction of the staircase need to be done on site, such as fixing glazing, adding balustrades and Internal partitions, Wall and ceiling Roof parapets, deck, insulation, furnishing. finishes Stair 2 : sedum 3rd fix roof M&E, Balustrading and outlets, Ee
TA 2 .89 SH 0.81
Ed
U/S 1.39
FFL
40 .30
.33 SCH 4
STN/129 39 .72
16 32 2nd joinery 27 1st building airfix test 33 handrails, 17 Sanitery goods, Landscaping Ground floor : Internal finishes, M&E, programme 18 External panels all levels ceilings, 28 Construction fire stopping, suspended 19 Start on site 06-05-2017 Joinery 1st and 2nd fix, decoration and possession, cabins and welfare, Facing brickwork all levels 29 Site tiling, sanitary installation 34 20 Ground floor power on/ heat on 35 Signage Top strip, dig, Piling, First soil floor : Internal finishes, M&E, fire steel allreduce levels 30 Corten Lift pit foundation 21 Ground stopping,beams, suspended ceilings, Joinery 1st andframe, 2nd fix, decoration and tiling, Insitu PCC stairs between 31 Curtain walling all levels 36 sanitary floors upinstallation to roof deck 22 1ST1250FLOOR parapets, deck, First floor power on/insulation, heat on 37 Roof outlets, sedum roof 32 Second floor :shaft Internal finishes, M&E, GENERAL NOTES Steelwork lift and 23 testNOTES roof 33 1st Work of finishes have not done in building GENERAL fire stopping,air suspended ceilings, Alterations toGenerally, existing building, roof concrete stairs and associated guarding / Ground floor : Internal finishes, M&E, Joinery 1st and 2nd fix, and / this stageGenerally, yet handrails / noising all asdecoration spec ref : L30.250B concrete stairs and associated guarding 24 protection fire stopping, suspended ceilings, tiling, installation handrails / 38 noising allsanitary as spec ref : L30.250B First Floor 250 29 2 :1st Ist and fixpower M&E, dryline 38.930 Joinery 2nd fix, and Second floor on/decoration heatwalls, on mist 39 Stair 20 25 tiling, installation 34 coat Third floor : Internal finishes, M&E, Tread sanitary as structural 18 engineer's details Ground floor power on/ ceilings, heat on 35 fire stopping, suspended 18 Size of perspex & fixings as 250 29 Stair 2 :1st 2nd fix 2nd M&E,fix, decoration First floor : and Internal finishes, M&E, fire Joinery decoration and manufacturer's 17 recommendation suspended ceiling decoration 26 16 stopping, suspended ceilings, Joinery tiling, sanitary installation 40 staircase, Vinyl finish as drawings 401 toand 406floor to2nd surfacepower of treads fix, decoration Third on/ heat and on tiling, 41 1st with min 55mm wide contrasting nosingsfix asInternal spec sanitary installation 36 Stair 2 : 3rd M&E, Balustrading and Fourth floor : finishes, M&E, L30.250A Tread as structural Firststopping, floor 2nd power on/ heat on 37 handrails, fix joinery 27 fire suspended ceilings, Detail 1st 1 and Second floor : Internal M&E, Joinery 2nd fix, finishes, decoration and engineer's details fire stopping, suspended tiling, sanitary installation 42 External panels all levels ceilings, 28 Joinery floor 1st and 2nd fix, 43 Fourth power on/ decoration heat on and Satin stainless steel slotted handrails tiling,floor sanitary installation : Internal finishes, M&E, fire Stair Rise: 165mm formed from 8mm safety perspexSize of perspex & fixings as 38 Fifth 29 Facing brickwork all levels Second floor power on/ heat Joinery on 39 stopping, suspended ceilings, manufacturer's Third Internal finishes, M&E, 1st andfloor 2nd :fix, decoration and tiling, recommendation steel all levels ceilings, 30 fire stopping, suspended sanitary installation 44 Corten Joinery 1stpower and 2nd decoration and 45 Fifth floor on/fix,heat on Vinyl Ground Floorfinish as drawings 401 Stringer aswalling structural tiling, sanitary installation 40 Curtain all levels 31 Sixth floor : Internal finishes, M&E, fire engineer's details 35.630 to 406 to surface of treads 41 stopping, Third floor power on/ heat on suspended ceilings, Joinery Roof parapets, deck, insulation, Continuous clamping plate toand suit stringer Fourth floor : Internal finishes, 1st 2nd fix, decoration andM&E, tiling, sedum roof 32 outlets, with min 55mm wide Satin Stainless Steel fire stopping, ceilings, 46 sanitary installation Cloaking suspended to 1stDecorative building air test 33 clamp plate contrasting nosings as spec 47 Sixth Joinery 1st fixings and 2ndon/ fix,heat decoration and floor on Size of glass & power Ground floor : asInternal finishes, M&E, manufacturer's L30.250A sanitary installation 42 tiling, Stair 1 : M&E, Joinery, Decoration, recommendation fire stopping, suspended ceilings, Fourth floorceiling, power on/ heat on 43 suspended 48 Joinery 1st and 2ndBalustrading fix, decoration and Fifth floor finishes, M&E, fire Section YY Detail 2 : Internal Final testing and commissioning, air All dimensions and levels subject to check site measurement 34 tiling, sanitary installation stopping, suspended ceilings, Joinery 49 Ground testing, final andon/ snag floorclean power heat on 35 1st and 2nd fix, decoration and tiling, First floor :29/08/17 Internal External snag andM&E, cleanfire MLD Elandscaping, Balustradefinishes, system amended 44 sanitary installation D 17/08/17 Steel stringers beams and treads amended MLD 50 stopping, externalsC suspended 13/07/17 Balustradeceilings, system amended Joinery MLD 45 Fifth floor power on/ heat on B 19/01/17 Change to concrete wall MLD and 2nd fix, decoration and tiling, 51 1st PRACTICAL COMPLETION A Spec Refs added Sixth floor :10/01/17 Internal finishes, M&E, fire MLD REV. DATE DESCRIPTION BY 36 sanitary installation stopping, suspended ceilings, Joinery March April 52 Month/year 37 First floor power on/ heat on Vinyl finish as drawings 401 to 406 to surface of treads 1st and 2nd fix, decoration and tiling, with min 55mm wide contrasting nosings as spec Second floor : Internal finishes, M&E, C
D
222
301
C105 CH 3 .02
38 .22
300
Ea
.90 SCH 4
F 300
E
E
38 .23
D
HH 2 .87 SH 0.80
C
HH 2 .87 SH 0.80
B
38 .26
HH 2 .99 SH 0.79
Ec
Eb
A
W 06
W 02
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
SH 0.88 TA 2 .95
SH 0.87 TA 2 .94
FFL 38 .23
ED 15
A 220
ED 16
ID 102
2
3
SH 0.86 TA 2 .94
FFL 38 .23
ID 101
4
Ceil 40 .88
FFL
ID 106
SH 0.90 HH 2 .53
ID 105
38 .36
5
DH 2 .00 Win/A SH 2.05 HH 2 .53
DH 2 .02
STN/108 38 .36
6
U/S 2.94
DH 1 .95
U/S 2.01
40 .89 Ceil
STN/109 38 .27
20
38 .27
38 .21
19
7
DH 2 .02
FFL 38 .28 SH 0.91 HH 1 .96
DH 1 .96
Floor Slope 38 .31
ID 103
18
220 A
Ceil 41 .10
ID 104
16
17
9
8
CH 3 .26
38 .24
Wall 1 .29h
15
10
U/S 41 .09
11
1a
STN/110 38 .23
U/S level 41 .06
W 05
1
1
Stair 3 only connect the ground level and the first floor, linking the entrance area to the cafe area above. ID 107
2a
W 04
IS 101
2
W 07
ID 109
Ed
Ec
Eb
Win/A SH 2.04
3a
ID 108
Ea
3
ID 110
B
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
W 08
20
B 221
1
221
W 01
4
ID 111
8
7
6
5
4
3
2
15
16
17
18
19
20
21
1
Wheelchair Refuge
SH 0.81 HH 2 .93
SH 0.95 HH 2 .17
Ee
CH 3 .03
SH 0.82 HH 2 .95
ID 112
Ee
A 220 B 221
U/S 2.58
SH 0.81 HH 2 .93
CH 3 .01
SH 0.81 HH 2 .93
SH 0.81 HH 2 .93
SH 0.81 HH 2 .93
W 06
W 02 U/S level 41 .06
W 05 11
1a
FFL
SH 0.90 HH 2 .53
38 .36
9 STN/10 38 .27
40 .89 Ceil
ID 106
DH 2 .00 Win/A SH 2.05 HH 2 .53
ID 105
DH 2 .02
8 STN/10 38 .36
5
FFL 38 .23
20
6
38 .27
38 .21
19
7
DH 2 .02
U/S 2.01
9 8
U/S 2.94
220 A
ID 103
18
FFL 38 .28 SH 0.91 HH 1 .96
ID 104
16 17 10
DH 1 .96
15
1
Floor Slope 38 .31
Ceil 41 .10
ID 101
ID 102 4
3
2
1
ID 107
2a
W 04
165
IS 101
2
W 07 ID 109
Ed 3a
Win/A SH 2.04
Ec Eb ID 108
Ea 3
ID 110
B
W 01 1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
W 08
20
B 221 4
ID 111 5
4
3
2
1
Wheelchair Refuge
CH 3 .03
18
19
20
21
U/S 2.71
H103 .61 SCH 2
TA 2 .27
FFL 39 .04
U/S 2.58
ID 113 FFL 39 .08
STN/143 39 .04
SH 0.82 HH 2 .95
17
Col
16
C
SP 1 .45
15
CH 3 .03
ID 114
U/S 2.58
6
SH 0.81 HH 2 .93
7
CH 3 .01
8
SH 0.81 HH 2 .93
SH 0.95 HH 2 .17
Ee
CH 3 .03
SH 0.82 HH 2 .95
ID 112
222 F
G
Col
FFL 39 .01
CH 2 .99
CH 2 .49
DH 2 .06
STN/146 39 .07
FFL 39 .06
CH 2 .99
TA 2 .23 SP 1 .37
CH 3 .07
H
U/S 2.71
SH 0.81 HH 2 .93
E
U/S 2.93
D
SP 1 .37
CH 3 .03
C
SP 1 .45
B
CH 3 .06
A
SH 0.82 HH 2 .95
3300 20 steps (165mm)
300
38 .24
1650 10 steps (165mm)
F 300
E
E
9 STN/12 39 .72
D
Ea D 301
.90 SCH 4
C
C 222
38 .23
B
Wall 1 .29h
7
8
U/S
Eb A
HH 2 .87 SH 0.80
02
Ee
Ed Ec
A 220
165
U/S 2.93
CH 2 .49
CH 3 .07
U/S 2.58
CH 3 .03
U/S 2.58
SH 0.82 HH 2 .95 CH 3 .03
SH 0.82 HH 2 .95
CH 3 .01
SH 0.82 HH 2 .95
CH 3 .03
SH 0.95 HH 2 .17
CH 3 .07
CH 2 .49
CH 3 .03
1100
7
1650 10 steps (165mm)
1100
U/S 2.71
38 .22
1100
U/S 2.78
HH 2 .87 SH 0.80
1100
H
U/S 2.71
H101
Col
SP 1 .37
100
G
.62 SCH 2
1100
SH 0.81 HH 2 .93
CH 3 .03
U/S 2.58
SH 0.82 HH 2 .95
3300
SH 0.82 HH 2 .95
U/S 2.93
B
221
U/S 2.71
FFL 39 .01
SP 1 .37
1100
SH 0.88 TA 2 .95
F
Col
3300
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
Ee
ID 113
SP 1 .37
0 20 steps (165mm)
C105 CH 3 .02
Win/A SH 2.04
U/S 2.71
ID 112
ID 111
E
STN/146 39 .07
1100
38 .26
SH 0.87 TA 2 .94
FFL 38 .23 Ceil 40 .88
W 08
20
H103 .61 SCH 2
1650 10 steps (165mm)
TA 2 .89 SH 0.81
DH 1 .95
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
19
Col
Y
HH 1 .92 SH 1.09
18
FFL 39 .06
All dimensions and levels subject to check site measurement
U/S 41 .09
17
CH 2 .99
Section XX
HH 2 .99 SH 0.79
16
CH 2 .99
02
STN/108 38 .36
15
DH 2 .06
Ground Floor Confetti 34.740
FFL
14
D
TA 2 .23
Base plate connection as structural engineer's details
SH 0.90 HH 2 .53
13
Col
1
2
38 .36
12
SP 1 .37
Ground Floor 35.630
DH 2 .00 Win/A SH 2.05 HH 2 .53
11
C
SP 1 .45
GROUND LEVEL
Ground Floor HE 35.630
02
° 33.4
FFL = 35.630
4 3 29
DH 2 .02
10
1
TA 2 .27
Steel stringers beams to structural engineer's details
SH 0.86 TA 2 .94
9
2
21
SP 1 .45
6 5
STN/109 38 .27
8
3
20
H101
6mm folded Steel plate filled with concrete to form treads as structural engineer's details
38 .21
7
4
19
CH 3 .06
7
°
8
33.4
01
Handrail and guarding to extend 300mm beyond first step
38 .27
6
5
18
FFL 39 .08
37.280 10 9
FFL 38 .23
5
6
17
C
B
.62 SCH 2
FFL = 37.280
11
DH 2 .02
4
7
16
FFL 39 .04
12
FFL 38 .28 SH 0.91 HH 1 .96
3
8
15
STN/143 39 .04
13
1200
DH 1 .96
2
U/S 2.78
CH 3 .03
18
02
Ceil 41 .10
ID 110
W 01
4
Ed
ID 108
Col
SP 1 .37
20
15 14
Floor Slope 38 .31
Eb
Ea
3
SP 1 .37
Exposed fasteners shall be of same materials, color and finish as material to which applied. Exposed surfaces throughout project shall have same inherent texture and color for similar locations.
ED 15
ED 16
FFL 39 .01
DH 2 .06
STN/146 39 .07
CH 2 .99
FFL 39 .06
CH 2 .99
TA 2 .23
All exposed steel to be painted as spec M60.150B
H
W 07
Ec
Wheelchair Refuge
First Floor 38.930
U/S 2.01
40 .89 Ceil
ID 106
ID 102 U/S 2.71
1
ID 107
ID 114
Vinyl finish as drawings First 401 toFloor 406 to Confetti surface of treads 38.360 nosings as spec with min 55mm wide contrasting L30.250A
U/S 2.94
220 A
2
CH 3 .26
Col
SP 1 .37
3
IS 101
ID 109
1
FFL = 38.930
G
ID 105
ID 101
4
38 .24
Wall 1 .29h
5
STN/110 38 .23
6
U/S level 41 .06
20
7
3a
222
1100 Concrete low wall to structural engineer's details
HH 2 .87 SH 0.80
19
8
FFL
ID 103
18
9
2a
W 04
2
A
Delta Vitra Glazed Balustrades System: - Clamp plate bolted to steel stringers. - Slotted handrails continued - 1100mm hight laminated structural glass balustrade
W 06
ID 104
17
10
F
STN/129 39 .72
W 02
11
1a
1
SP 1 .45
1250
CH 3 .06
951
E
H101
1163
.62 SCH 2
1163
D
38 .22
H103 .61 SCH 2
TA 2 .27
FFL 39 .04
FFL 39 .08
W 05
16
C
The upper level will be connected through Stair 2 which still have not arrived to the site as well as Stair 1. It is delayed a lot as the original plan is finishing the installation of them in August. Therefore, it is cleared 8 contractor had rescheduled the programme. that the 300
15
B
F 300
E
E
.90 SCH 4
D
Ea
D
301
40 .30
C
C
222
38 .23
B
HH 2 .87 SH 0.80
A
.33 SCH 4
Eb
SP 1 .45
ID 113
222
A
Ed
Ec
U/S 1.39
STN/143 39 .04
C
U/S 2.71
Col
CH 3 .03
ID 114
U/S 2.78
U/S 2.71
GENERAL NOTES
Detail 1
Generally, concrete stairs and associated guarding40/ handrails / noising all as spec ref : L30.250B May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
5.5
H E A LT H
& SAFETY: CRANE
As currently the construction started on the upper levels, lifting is required to transport materials. Transporting by workers alone to upper floors is difficult . Therefore, the team uses crane for lifting. Lifting only occurs from Convent street as Covent street is closed for storage and transporting, meaning that it would not affect the street and the surrounding buildings.
The operation and position of the crane is approved by the Nottingham City Council and it follows the rule of using on site.
The position of the crane is located in the mechanical riser of the building design. It is considered according to the crane swing to be functional on site and not on the critical path of the construction. Main heat vacuum and ducts will be inserted to the void after the crane is removed from the site.
Lifting from Covent Street
Mechanical riser as the void for the crane
41
P LANNINGS As they are currently 6 weeks behind the schedule, they need to spend extra time working in order to complete the whole construction by 11 June.
During the Christmas break period, they aim at:
1. Completing the 5th floor & 6th floor (roof) 2. Fitting in Stair 1 & Stair 2 They decided to do more works and bring more workers 3. Starting the external envelope and internal fittings on site during Christmas break since the students are having holidays, they have less consideration on the The partitions are coming in on 8 January and the immediate negative effects on the surroundings, such plumper and electric mechanicians are coming in 15 as noise. January for M&E fitting.
13
14
15
16
17
18
19
837
1010
5
1135
3947.5(17 1/2 bricks)
U/S 2.76
DP
3
2
ID 019
U/S 2.78
CH 3.36
SH 0.19 HH 3.03
1in12
4
5
10
AVCL
AVCL
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish Existing Wall HE Centre 215mm Existing Solid brick wall 25mm cavity depth Metal studs at 600mm centres - K10/165A 12.5mm Plasterboard
Existing Wall Confetti Insulation to be agreed with Structural Engineer Exposed concrete finish
Change t Amendm Change t Amendm Amendm Survey a
F E D C B A
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
Change t Spec Ref Amendm Amendm Amendm Amendm
REV. DATE
Type 1
PARTITION Wall Type 1 2no.layer of 12.5mm Soundblock either side,16mm Resilient Bar fixed to one side, 92mm C studs with 50mm Isover between studs. Skim finish to both sides of partition.
Type 2
PARTITION Wall Type 2 1no. Layer of 15mm Soundbloc either side of 92mm C Studs with 50mm Isover APR between studs. (Use 15mm Soundbloc MR in WC Areas) Skim finish to both sides of partition.
Type 3
Type A
Change t & Windo
DESCRIP
01 1 5 841 841 8
F
01 1 5 950 71 61
1700
CLIENT
Confetti Medi PROJECT
60 minutes fire resistance Wall
17
42
Plasterboard on dabs to achieve min 60 minutes fire rating Existing wall
Movement joint
PARTITION Wall Type 3 1no. Layer of 15mm Soundbloc MR either side of 70mm C Studs with 50mm Isover APR between studs. Skim finish to both sides of partition. PARTITION Wall Type A 3no. Layers 15mm Soundbloc either side of BG 146mm C Stud at 300mm Centres within 148mm Head and base channels. 75mm Isover APR between studs with Skim finish to both side of partition.
T
H
14 13 12 11 10 9 8
503.5
497
DH 2.05
190
24/08/17 18/08/17 30/05/17 17/08/17 30/05/17 12/05/17
Architects, Land
4959
G
DH 2.05
HH 2.05 SH 0.87
UP
K J II H G
Amendm Amendm Amendm
1 6-20 Bath Street, N
6128
F HH 2.05 SH 0.87
Ground Floor 35.440
X017 PLANT ROOM 30 m2
32.78
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns Wall Construction - Blockwork Outer / SFS Inner 100mm fairfaced medium density blockwork - F10/225 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns
7718
E
SP 2.23
SCH 2.83
N
1492
D
04/01/18 19/12/17 08/11/17 18/09/17
eq.
1646
C
Ground Floor 35.048
29/01/18 Amendm 16/01/18 MJ, CFB, Amendm
O N M L
H003
3562
PROPOSED GROUND FLOOR GA PLAN -1:50 Key Walls
G 223
U/S 3.14
Col
lery H002 Gal CH 2.99
FFL 35.44
B
C 222
Ground Floor 35.630
CH 2.99
X010 STAIR 2
Lift
Ee
1800
X011 STAIR 2 LOBBY
14/02/18 Amendm
Q P
17
ED 04
3751
4
3491
5
SH 0.88 HH 2.97
6
R
SH 0.88 HH 2.97
7
CH 2.76
35.47
t
STAIR 2
DH 2.04
8
SH 0.86 HH 2.03
9
U/S 2.27
10
DH 2.05
FFL 35.63
Ground Floor 35.630
1
2279
AVCL
215
eq.
THL 35.64
poin Insertion
STN/142 35.51
ED 14
A
3a
1184 2176
ED 03
2597.5
MJ
ID 018
AVCL
224 1184
1110
1496
3471
35.048
X020 MTG 3 9 m2
2617
2806
1736
1736
NEW IS 004 3532
3
U/S 2.37
3
X014 SERVER 16Ground m2 Floor
Ground Floor 35.630
ID 017
314
3a ID 010
32.86
420
1010
Type 1*
Ground Floor 35.048
20
2740
1532
535
12
535
763 11
768
10
100
3070 4642
1696
1000 1200 400
10932
800 600 1135 1095 400 800
9
252
925
640 800
220
600
3650
A 3554 2950
221
8
DH 2.03
7
220 A
6
300
5
ID 021 148
X004 MTG 2 8 m2
CH 3.39
4
ID 012
Ground Floor 35.048
ID 009
Ground Floor 35.630
2000
Type 1*
X002 MTG 1 9 m2
STN/128 36.04
3
ID 015
2778
34.71
2
X012 clnrs cpbd 3 m2
IS 003 148
Type 2
Type 1*
X018 Staff Corridoor
148
.48
ID 016
Mechanical riser
2000
IS 002 2810
34.66
Type 1*
ID 011
1736
324
X015 COMMS 13 m2
140
3248
35.61
1092
338
3574
Ed
11857
2000
.50
1215
1010
Ec
Ground Floor 35.630
1225
CH 2.37
Eb
Ea
422
1
X003 OFFICE 26 m2
INTERNAL WALLS
Indicative location of reception desk by others
1500
ID 014
ID 013 1736
- 3steps
3306
314
3a
X019 Mtg cpbd
Electrical riser
Type 1*
1100MM HIGH
400
ID 007
1in12 3545
1184 ID 008
1343
Type 1*
- 3steps
1656 138
Ground Floor 35.048
450
1930
EXTERNAL ENVELOP
400
1178
400
5789 LOWWALL
U/S 3.14
inet MMC cab
34.910 34.910
1828
4596
1in12 1854
3390
3700
UP
1010
5000
Ground Floor 35.464
1in15
Ground Floor 35.630
DH 2.10
2552
496 400
1010
234
1408 ID 006
3546
ID 003 ID 002
1110
1202
FFL
1
Type 1*
- 3steps
17
Floor
35.464
100
ID 005 499
DH 2.05
IS 001
X005 WC LOBBY
Ground Floor 35.048
34.74
2
2500
2a
312
4
3
1010
X009 STAIR 1 LOBBY Type 1*
2 17 mGround
ID 004
34.910
rk walls 140 Blockwo 500
34.68
Ground Floor 35.630
2
3
ID 001
Ground Floor 35.464
311 4
Ground Floor 35.464
1979
410
5
X007 WC CHANGING (FEMALE WC)
15 m2
Type 1*
6
X001 RECEPTION 130 m2
X013 CONTROL ROOM 8 m2
Type 1*
6 1600 34.7
4742
7
34.69
8
X016 SUBSTATION 20 m2
10
3200
STAIR 1 X008 STAIR 1
9
4 Step +0.0
W 03
34.69
10
310
W 01
MJ
Type 3
X006 WC CHANGING (MALE WC)
34.61
Ground Floor 35.464
W 01
Secure line
9215
5038
ED 02 13
12
Fit
ED 12
1000
11
1a
0 to approx. 250
552
1810
3546
ED 01
1
300
bricks) 15740(71
4
W 02
bricks)
300
50
1200
400
800
600
1/2 6413(28
F
E
34.74
10534 1000
2951
123 1003 579 195
1000
34.70
35.71
3160
l A - 306 Plan Detai
1000
35.20
bricks) 9215(41 Ground Floor 35.300
34.82
4550
4452
Ee
6752
Ed
421
Ec
35.10
Ea
Eb
34.90
330
422
35.00
35.09
35.60
35.46
E
ting out Line Bricks Set
See drawing 2588-306 for recessed downpipe details
2000
1000
35.20
35.24
1492
D
D 301
Ground Floor 35.600
923
1646
C
3562
C 222
G 223
35.32
B
2279
.12
35.46
35.63
35.80 A
35.70
However, bringing more workers on site might increase the possibility of accidents as the space in site is limited and might increase communication problems. Thus, it might further delayed the work.
35.28
35.91
35.86
They also planned to work over the weekends and late at night to chase back the delayed schedule.
B
5.6
Bricks Setting out Line
ID 001, etc W001, etc ED01, etc IS01, etc
- Internal Door Codes (Refer to drawing 320) - Window Codes (Refer to drawings 322-323) - External Door Codes (Refer to drawings 323) - Internal Screene Codes (Refer to drawings 321)
Confetti CQ C DRAWING
Ground Floor Wall Types an PROJECT NUMBER
S
2588
1
DRAWING NUMBER
R
201
R
This drawing is copyright a
6
S ITE
VISIT 4
Date: 16 January 2018 (Tue) Weather: Passing clouds Temperature: 2 °C People on site: 40 to 50
• Project manager
• Contractors
• Workers
• Students and tutors
3 4
2017 2018
Month/year
March
5 Task 6 Tender programme
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
P ROGRAMME
6.1
7 Tender addendum information 8 Contract appointment 9 Technical Design stage
10 Planning conditions discharge Architectural, structural and civil to 11 stage 4 12 Subcontractor procurement
CONTRACT PROGRAMME
Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling A Stats connections, Frame, Cladding,
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCCDCECFCGCHCICJ
Confetti
14 M&E 1 Roof finishes, Lift installation, 15 2 Windows and external doors 3 Internal partitions, Wall and ceiling 16 finishes 4 Month/year 17 5 Sanitery Task goods, Landscaping programme 18 6 Construction Tender programme 19 Start on site 06-05-2017 possession, cabins and welfare, 7 Site Tender addendum information 20 Signage soil strip, reduce dig, Piling, Contract appointment 8 Top Technical Design 9 Ground beams, Liftstage pit foundation 21 Insitu frame, PCC stairs between Planning discharge 10 floors up conditions to roof deck 22 Architectural, structural and civil to stage 4 lift shaft and roof 11 Steelwork 23 Subcontractor procurement 12 Alterations to existing building, roof Enabling works, Site set up, Service 24 protection disconnetions, Groundworks, Piling 13 Stair 2 : Ist fix M&E, dryline walls, mist Stats connections, Frame, Cladding, 25 coat 14 M&E Roof2finishes, installation, Stair : 2nd fixLift M&E, decoration Windowssuspended and external doors 15 staircase, ceiling decoration 26 Internal partitions, Wall and ceiling finishes 16 Stair 2 : 3rd fix M&E, Balustrading and 27 handrails, 2nd fix joinery 17 18 28 19
Sanitery goods, Landscaping Construction External panelsprogramme all levels Start on site 06-05-2017
Site possession, and welfare, brickworkcabins all levels 29 Facing 20 Signage Top soilsteel strip,allreduce levels dig, Piling, 30 Corten 21 Ground beams, Lift pit foundation Insitu frame, PCC stairs between walling all levels 31 Curtain 22 floors up to roof deck Roof parapets, deck, insulation, 32 outlets, sedum roof Steelwork 23 1st buildinglift airshaft test and roof 33 Alterations to existing building, roof Ground floor : Internal finishes, M&E, 24 protection fire stopping, suspended ceilings, Stair 2 :1st Ist and fix M&E, dryline walls, mist Joinery 2nd fix, decoration and coat sanitary installation 25 tiling, 34 35 Ground floor power on/ heat on Stair floor 2 : 2nd fix M&E, decoration First : Internal finishes, M&E, fire staircase,suspended suspendedceilings, ceiling decoration 26 stopping, Joinery 1st and 2nd fix, decoration and tiling, 36 sanitary Stair 2 : installation 3rd fix M&E, Balustrading and 37 floor 2nd power heat on handrails, fix on/ joinery 27 First Second floor : Internal finishes, M&E, stopping, suspended External panels all levels ceilings, 28 fire Joinery 1st and 2nd fix, decoration and 38 tiling, sanitary installation 29 Facing brickwork all levels 39 Second floor power on/ heat on Third floor : Internal finishes, M&E, Corten steel suspended all levels ceilings, 30 fire stopping, Joinery 1st and 2nd fix, decoration and 40 sanitary Curtain wallinginstallation all levels 31 tiling, 41 Third floor power on/insulation, heat on Roof parapets, deck, : Internal outlets,floor sedum roof finishes, M&E, 32 Fourth suspended ceilings, 1st stopping, building air test 33 fire
2017 2018 March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
According to the programme of the contractors, the following tasks should be finished or in progress on 16 January 2018. However, the real programme (Blue dotted line) on site is 4 weeks behind scheduled programme (Red dotted line). Tasks are EXPECTED finished: • Insitu frame • Lift shaft • Stair 2 • External panels all levels • Facing brickwork all levels • Corten steel all levels
Task are EXPECTED in progress: • Curtain wall all levels • Roof parapets, deck insulation, outlets and sedum roof • Ground floor internal finishes and M&E • First floor internal finishes and M&E Tasks are in ACTUAL progress : • Insitu frame • Curtain wall all levels • Internal finishes and M&E Scheduled programme in visit date Real on site programme 44
six week(6 programme TARGET PROGRAMME WEEKS) 13/12/2017
Glenn Reeves
Line 1
Name
Duration
CONSTRUCT 6TH FLOOR / ROOF
Start
Finish
2017 December 18 25 1 1 2 3
3w 08 Jan 18 26 Jan 18
4
8
2018 January 15 22 5 6
7
29
1
EXTERNAL FACADE 2
SFS GRD - 1ST FLOOR
1w 18 Dec 17 22 Dec 17 2
3
SFS 1ST - 2ND FLOOR
1w 08 Jan 18 12 Jan 18
4
SFS 2ND - 3RD FLOOR
1w 15 Jan 18 19 Jan 18
5
SFS 3RD - 4TH FLOOR
1w 22 Jan 18 26 Jan 18
6
SFS 4TH - 5TH FLOOR
1w 29 Jan 18 02 Feb 18
3 4 5 6
8
Feb 5
9
As the programme is behind the schedule, and the contract programme will never change to indicates tasks and end date, a target programme is set per 6 weeks by the contractor to state the current process and target to chase back the schedule behind. From the table on the left , it is cleared that the tasks are break into smaller parts and stated the duration and dates of tasks in specific.
BRICKWORK 7
BWK GRD - 1ST FLOOR
2w 15 Jan 18 26 Jan 18
8
BWK 1ST - 2ND FLOOR
2w 29 Jan 18 09 Feb 18
7 8
CURTAIN WALLING WINDOWS GRD - 1ST
1w 15 Jan 18 19 Jan 18
10 WINDOWS 1ST - 2ND
1w 22 Jan 18 26 Jan 18
9
9 10
INTERNAL Ground Floor 11 Partition 1st fix
1w 08 Jan 18 12 Jan 18
12 M&E
1w 15 Jan 18 19 Jan 18
1st fix
11 12
First Floor 13 Partition 1ST Fix
1w 08 Jan 18 12 Jan 18
14 M&E
1w 15 Jan 18 19 Jan 18
1ST Fix
13 14
Second Floor 15 Partition 1ST Fix
1w 22 Jan 18 26 Jan 18
16 M&E
1w 29 Jan 18 02 Feb 18
1ST Fix
17 Substation works GF
2w 18 Dec 17 12 Jan 18 17
18 Pre cast Stair instal no 1
1w 08 Jan 18 12 Jan 18
19 Pre cast Stair instal no 2
1w 15 Jan 18 19 Jan 18
The end date of the construction is critical as it affects the programme of furniture fitting or even the final end date of the project, 3 September. Therefore, the contractor has to understand and accept the consequences if they did not complete the task within the construction end date, 11 June. The site visit day should have several tasks happening on site at the same time, including roof construction, 2nd &3 rd floor steel frame system, ground and first floor brickwork, curtain wall and M&E. Therefore, these certain tasks are expected to see in this visit.
15 16
This chapter will be using this target programme to check whether the task is completed or in process.
18 19
Scheduled programme in visit date
Trades Contractor Default Drawn by: Planner - Chart Properties
Dwg No. 00001
Project Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp
Revision No. A
Notes: Comment - Chart Properties
Planned by Asta Powerproject
45
12 M&E
S
6.2
1w 15 Jan 18 19 Jan 18
1st fix
First Floor
six week programme
13 Partition 1ST Fix
1w 08 Jan 18 12 Jan 18
14 M&E
1w 15 Jan 18 19 Jan 18
13/12/2017Second Floor 16 M&E Line
5TH FLOOR
6TH FLOOR/ ROOF
1w 29 Jan 18 02 Feb 18 Finish Duration Start
1w 08 Jan 18 12 Jan 18 1w 15 Jan 18 19 Jan 18
GRD - 1ST FLOOR 2 SFSContractor Trades
1w 18 Dec 17 22 Dec 17
SFSDefault 1ST - 2ND FLOOR
1w 08 Jan 18 12 Jan 18
5
SFS 3RD - 4TH FLOOR
1w 22 Jan 18 26 Jan 18
8
BWK 1ST - 2ND FLOOR
2w 29 Jan 18 09 Feb 18
Key Walls
3234
CURTAIN WALLING Further information will be discussed 8: Visit GENERAL NOTESin Chapter 9 WINDOWS GRD - 1ST 6, as currently the construction ofWalls the roof still have not External 10 WINDOWS 1ST - 2ND BENCHMARK Quadcore Karrier Panel + Corten Recess Fixed 1 started completely. Cassette
Ec
Ed
Ec
Eb
2343
3562
B
1646
C
1492
D
E Ea
C 222
Key Walls
220
509
143
1642
15
16
17
18
19
20
11
10
9
8
7
6
5
4
Mechanical riser
Fifth Floor 55.324
7
1010
1682
W 21
13
3
2
1
514
148
221
ID 602
12
4
ED 08
Ea
2338
1604
910
14
X601 PLANT 32 m2
2502
2950
B
13
X508 STAIR 1
X509 STAIR 1 LOBBY
C
2343
Detail G - 300
W 02 X509 STAIR 1 LOBBY
A
17 16 15
Detail F - 300
14
B
1646
C
1492
D
Key Walls
BENCHMARK Quadcore Karrier Panel as H43/121+ Corten Recess Fixed Cassette as H43/125
1
2
3
F
KINGSPAN Quadcore Karrier Panel + Brick Tie System
100mm fairfaced medium density blockwork - F10/225 10mm clear residual cavity 100mm Kingspan Kooltherm K106 Cavity Board 100mm fairfaced medium density blockwork - F10/225
BENCHMARK Quadcore Karrier Panel as H43/121+ Corten Recess Fixed Cassette as H43/125
Existing Wall HE Centre
PARTITION Wall Type - K10/115
14
5 35mm Benchmark Corten Recessed Fix Cassette as H43/125 100mm Benchmark Quadcore Karrier Panel as H43/121 fixed with a minimum of 2 Nr fasteners per panel per rail 50 mm Oversail SFS fixed to the structure Exposed concrete finish
215mm Existing Solid brick wall 25mm cavity depth Metal studs at 600mm centres - K10/165A 12.5mm Plasterboard
KINGSPAN Quadcore Karrier Panel + Brick Tie System
Terrace External Wall
6 102.5 Black Brick as F10/110, 50mm cavity 125mm Brick Ties spaced generaly every 3 bricks, and fixed back to the Quadcore Karrier Panel with Fabloks as F30/220 100mm Benchmark Quadcore Karrier Panel as H43/121 fixed with a minimum of 2 Nr fasteners per panel per rail 100 mm Infill SFS fixed to the structure as H43/121 12.5mm Plasterboard + exposed concrete columns
102.5 Black Brick as F10/110 50mm cavity 100mm Benchmark Quadcore Karrier Pane - H43/121 100mm fairfaced medium density blockwork - F10/225
Detail L - 300
2x12.5mm SoundBloc Metal Studs at 600mm centres 100 Rockwood RW360 insulation in the cavity 2x12.5mm SoundBloc
ID 001, etc W001, etc ED01, etc IS01, etc
3230
4
X408 STAIR 1
16
X409 STAIR 1 LOBBY
4 3 2 1 19 18 17 16 15
X404 SEMINAR ROOM
16 Existing Confetti Building
Detail L -
TimberF - 300 Detail stage platform
Proposed masonry to be built off existing gable - cut bricks to be removed to start new wall
Ee
H G
30/05/17 Amendments to HEC stair 2 following the SE info 12/05/17 Amendments to drawings following the Topo Survey and SE info
MLD MLD
F E D C B A
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
Change to doors and Stair 1 Lobby Spec Refs added Amendments to drawings Amendments to drawings Amendments to drawings Amendments to drawings
MLD MLD MLD MLD MLD MLD
DESCRIPTION
BY
REV. DATE
3 4 Comment - Chart Properties Notes:
Ground Floor Construction Solid Concrete Ground Based Floors - Vinyl floor finish as floor finishes drawings 401-402 -75mm screed as spec ref M10.130 300 - Underfloor Heating Systems refer to M+E Engineer's details -0.5mm separation layer lapped (minimum 150mm) -50mm perimeter Insulation overlap min.150mm from bottom of wall insulation to top of insulation upstand -130mm Kingspan Kooltherm K103 Floor Board insulation
9
15
630mm
Architects, Landscape & Interior Design 1 6-20 Bath Street, Nottingham NG1 1 DF T
01 1 5 841 841 8
E
F
01 1 5 950 71 61
W
CLIENT
design@allanjoycearchitects .co.uk www.allanjoycearchitects .co.uk
Confetti Media Group
Dwg No. 00001 PROJECT
Confetti CQ Campus DRAWING
PROJECT NUMBER
SCALE
DRAWING NUMBER
REVISION
STATUS
DATE
Jul-16 BY
MLD
This drawing is copyright and remains the property ofAllan Joyce Architects Ltd Generally do not scale drawings . All dimensions to be checked on site.
13
W 14
- Internal Door Codes (Refer to drawing 320) - Window Codes (Refer to drawings 322-323) - External Door Codes (Refer to drawings 323) - Internal Screene Codes (Refer to drawings 321)
Floors Construction (1st, 3rd, 4th, 5th) -275mm concrete deck to Structural Engineer's details -10mm latex levelling screed - Vinyl floor finish as floor finishes drawings 401-402
11
17
19 2
Terrace Roof System construction 16 -350mm to 6th floor and 275mm to 5th floorconcrete deck to Structural Engineer's details -50mm 18 17screed to falls as spec ref M10.110 2w 18 Dec 17 12 Jan -3mm vapour control layer -150 mmKingspan Thermaroof TR27 LPC/FM 18 18mm thick Kingspan Thermaroof 1w 08 Jan 18 12 Jan - 25 TR27 LPC/FM upstand to be the roof on the internal 18 used around the perimeter of19 1w 15 Jan 18 19 Jan façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the roof insulation. Notes: Comment - Chart Properties Revisionhorizontal No. A -1.5mm fully adhered single-ply membrane as S42.110A -50mm Ballast (paving slabs on support) Planned as Q37.140 by Asta Powerproject U-Value <0.15W/m2K.
Second Floor Construction (LRC) Roof - Terrace Plan GA Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp -275mm concrete deck to Project Structural Engineer's details RoofTypes and Setting Out -3mm vapour control layer 8 2588 1:50 @ A1 -50 mm Kooltherm as spec ref M10.290B -75mm screed as spec ref M10.130 207 H Construction - Vinyl floor finish as floor finishes drawings 401-402
15
18
9
1
1w 29 Jan 18 02 Feb 18
Plant Room External Wall
102.5 Black Brick as F10/110, 50mm cavity 7 125mm Brick Ties spaced generaly every 3 bricks, and fixed back to the Quadcore Karrier Panel with Fabloks as F30/220 100mm Benchmark Quadcore Karrier Panel fixed with a minimum of 2 Nr fasteners per panel per rail 50 mm Oversail SFS fixed to the structure 12.5mm Plasterboard
12
15
E
4959
4 35mm Benchmark Corten Recessed Fix Cassette as H43/125 100mm Benchmark Quadcore Karrier Panel as H43/121 fixed with a minimum of 2 Nr fasteners per panel per rail 100 mm Infill SFS fixed to the structure as H43/121 12.5mm Plasterboard + exposed concrete columns
13
19
of the horizontal roof insulation. G H Default -1.5mm fully adhered single-ply membrane as S42.110A -50mm Ballast (paving slabs on support) as Q37.140 U-Value <0.15W/m2K. Drawn by: Planner - Chart Properties 6128
7718
PROPOSED TERRACE FLOOR GA PLAN -1:150
X504 FIFTH 13 FLOOR TERRACE
18
Detail 222 I - 300 3562
1w 15 Jan 18
13
6693
Detail I - 300
X504 FIFTH FLOOR TERRACE
19
8
Feb 5
Semi−intensive Green Roof Covering System 10 construction 26 Jan 18 -350mm concrete deck to Structural Engineer's details -50mm screed to falls as spec ref M10.110 -3mm vapour control layer - 25 mm thick Kingspan Thermaroof TR27 LPC/FM upstand to be used around the perimeter of the roof on the internal 11 12 Jan 18 façade of parapets 12 be maintained 19 Jan 18 A minimum distance of 300 mm should between the top of the insulation upstand and the bottom of the horizontal roof insulation. -150 mm Kingspan Thermaroof TR27 LPC/FM 12 Jan 18 fully-adhered single 13 -1.5mm ply membrane as S45.110A -roof barrier/protection layer(s) 14 19 Jan 18 -drainage layer, filtration layer, substrate to depth required -80mm semi-intensive green roof covering as Q37.120A U-Value <0.15W/m2K.
1w 22 Jan 18 26 Jan 18
9337.5(41 1/2 bricks)
External Curtain Walls Various Systems - refer to windows schedule Drawings 322-324 U-Value = 0.15W/m2K G-value of glass = 0.35
Detail G - 300
2
-350mm to 6th floor and 275mm to 5th floorconcrete deck to6 Structural Engineer's details
3416
Lift
3
1w 08 Jan 18
7078
External Curtain -50mmWalls screed to falls as spec ref M10.110 -3mm vapour control layer cast Stair instal no 1 18 Pre Various Systems refer to windows schedule Drawings -150 mmKingspan Thermaroof TR27 LPC/FM TR27 LPC/FM upstand 322-324 - 25 mm thick Kingspan Thermaroof Pre cast Stair instal no 2 19 to be used around the perimeter of the roof on the internal U-Value =façade 0.15W/m2K of parapets minimum distance of 300 mm should be maintained Trades Contractor G-value ofAbetween glass 0.35 the top=of the insulation upstand and the bottom
7069
3
1w 15 Jan 18 660mm
1135 ED 07
2362
ID 601
311
Green Roof as Q37 on singl e ply membrane as J42.110A
1w 08 Jan 18
221 B
Detail E - 300
KINGSPAN Quadcore Karrier Panel + Brick Tie System -102.5 Black Brick as spec ref F10.110 -50mm cavity -125mm Brick Ties spaced generaly every 3 bricks, and fixed back to the Quadcore Karrier Panel as spec ref F30.220 -100mm Benchmark Quadcore Karrier Panel as H43.121 -100 mm Infill Structural Rails fixed to the structure -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value =Terrace 0.18W/m2K 17 Substation works GF Roof System construction 6853
2475(11 bricks)
3234 3650 3554
3
First Floor
Semi−intensive Green Roof Covering System construction Partition 13 Engineer's -350mm concrete deck to Structural details1ST Fix -50mm screed to falls as spec ref M10.110 1ST Fix -3mm vapour control layer 14 M&E - 25 mm thick Kingspan Thermaroof TR27 LPC/FM upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained Second Floor between the top of the insulation upstand and the bottom Ed of the horizontal roof insulation. Ec 1ST Fix 15 -150 mm Kingspan Thermaroof TR27 Partition LPC/FM X605 Eb EXTERNAL PLANT -1.5mm fully-adhered single ply membrane as S45.110A 54 m -roof barrier/protection layer(s)16 M&E 1ST Fix -drainage layer, filtration layer, substrate to depth required -80mm semi-intensive green roof covering as Q37.120A U-Value <0.15W/m2K. bricks) 15065(67
9337.5(41 1/2 bricks)
ED 09 1585
t ts
7527.5(33 1/2 bricks)
KINGSPAN Quadcore Karrier Panel + Brick Tie System -102.5 Black Brick as spec ref F10.110 6 -50mm cavity -125mm Brick Ties spaced generaly every 3 bricks, and fixed X604 X602 LIFT LOBBY X603 back to the Quadcore Karrier Panel ref2 F30.220 STAIRas 2 specSTAIR LOBBY -100mm Benchmark Quadcore Karrier Panel as H43.121 -100 mm Infill Structural Rails fixed to the structure -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim 6 U-Value = 0.18W/m2K 5390
12
220 A
12
Paved Terrace as Q37 on sigl e ply membrane as J42.110A
3a
3
bricks)
m m m m o o C r C o ino N M 3
1w 22 Jan 18
n n e e
300
bricks)
A
1a
External Walls BENCHMARK Quadcore Karrier Panel + Corten Recess Fixed Cassette -35mm Benchmark Corten Recessed Fix Cassette as H43.125 -100mm Benchmark Quadcore Karrier Panel fixed with a minimum of 2 Nr fasteners per panel per rail as H43.121 Ee -100 mm Infill SFS fixed to the structure 2a -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value = 0.18W/m2K
2
Detail E - 300
9215(41
2951
F
E
300
1/2 6637.5(29
Ed
4452
4550
D 301
GENERAL NOTES
1
1
6752
Ed
A
310
7
29
GENERAL NOTES
1w 15 Jan 18 19 Jan 18
INTERNAL -35mm Benchmark Corten Recessed Fix Cassette as H43.125 -100mm Benchmark Quadcore Karrier Panel fixed with a Ground Floor minimum of 2 Nr fasteners per panel per rail as H43.121 Ee Partition 1st fix -100 mm Infill SFS fixed to the11structure fix ref 12 M&E as1st -12.5mm 'Gyproc Wallboard' plasterboard spec K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value =GENERAL 0.18W/m2K NOTES Ee
310
16
18
1w 15 Jan 18 19 Jan 18 Revision No. A
SFS Drawn4by: Planner - Chart2ND Properties - 3RD FLOOR Dwg No. 00001
4
8
2018 January 15 22 5 6
5 After adding the staircase and finishing the , the Discussed on the soft and hard landscapingProjecton 15 Jan Powerproject\Projects\Confetti.pp Ref. C:\Users\glenn.reeves\Documents\Asta Plannedroof by Asta Powerproject 6 6 SFS 4TH - 5TH FLOOR 1w 29 Jan 18 02 Feb 18 superstructure will be completed, it is expected to be 2018. Confirmed that the slab, insulation layers and BRICKWORK finished by the end of January, according to the 6 weeks green roof covering will be in a total of over 600mm 7 7 BWK GRD - 1ST FLOOR 2w 15 Jan 18 26 Jan 18 programme. deep. This is for draining the green roof sufficiently. 8 8 BWK 1ST - 2ND FLOOR 2w 29 Jan 18 09 Feb 18
The 5th floor has completed during the Christmas break. Columns and floor slabs were all done and the contractors are now forming steel works on top of the columns for the final level.
Ec
Glenn Reeves 15
2017 December 18 25 1 2 3 2w 18 Dec 17 12 Jan 18 171 3w 08 Jan 18 26 Jan 18
1ST Fix Name
19 EXTERNAL Pre cast StairFACADE instal no 2 3
14
1w 22 Jan 18 26 Jan 18
17 Substation works GF CONSTRUCT 6TH FLOOR / 1 ROOF 18 Pre cast Stair instal no 1
Eb
13
UPER STRUCTURE: INSITU FRAME CONCRETE 1ST Fix
15 Partition 1ST Fix
Eb
12
14
15
Second Floor Construction (LRC) -275mm concrete deck to Structural Engineer's details -3mm vapour control layer -50 mm Kooltherm as spec ref M10.290B -75mm screed as spec ref M10.130 - Vinyl floor finish as floor finishes drawings 401-402 Floors Construction (1st, 3rd, 4th, 5th) -275mm concrete deck to Structural Engineer's details
46
six week programme EXTERNAL FACADE
6.3
E
1w 18 Dec 17 22 Dec 17 2
2 SFS GRD - 1ST FLOOR 13/12/2017
X T E R N A L E N V E LO P E
3
2017 six week programme December
1w 15 Jan 18 19 Jan 18 Duration Start Finish 1w 22 Jan 18 26 Jan 18
4 SFS 2ND - 3RD FLOOR Line Name 5 SFS 3RD - 4TH FLOOR ROOF
BRICKWORK Line FACADE BWK GRD Name - 1ST FLOOR 7 EXTERNAL 2 8
30
1w 29 Jan 18 02 Feb 18 3w 08 Jan 18 26 Jan 18
6 SFS 4TH - 5TH FLOOR 13/12/2017 CONSTRUCT 6TH FLOOR / 1
3 1
SFS BWKGRD 1ST -- 1ST 2NDFLOOR FLOOR CONSTRUCT 6TH FLOOR / SFS 1ST - 2ND FLOOR ROOF SFS 2ND WALLING - 3RD FLOOR CURTAIN
4
SFS 1ST - 2ND FLOOR BRICKWORK INTERNAL SFS 2ND - 3RD FLOOR
1w 08 Jan 18 12 Jan 18
29 Jan 18 02 Feb 1w 22 Dec 26 Dec Jan 18 17 2 1w 18 17 22 19 Jan 18 26 26 Jan Jan 18 18 09 Feb 12 Feb Jan 18 02 18
BWK3RD GRD 1STFLOOR FLOOR Ground Floor SFS - -4TH 8 BWK 1ST 2ND FLOOR fix FLOOR 11 SFS 4TH1st - 5TH 6 Partition
1w 15 Jan 18 Jan 18 2w 1w 15 22 Jan 18 29 Jan 2w 1w 08 29 Jan 18 18
12 M&E
1w 15 Jan 18 19 Jan 18
1st fix
CURTAIN WALLING BRICKWORK WINDOWS - 1ST First BWK Floor GRD -GRD 1ST FLOOR
1w 2w 1w 2w
WINDOWS 2ND Partition 1ST Fix - FLOOR BWK 1ST - 1ST 2ND 1ST Fix
15 15 Jan Jan 18 18 22 08 Jan 18 29
19 26 Jan Jan 18 18 26 12 Jan 18 09 Feb
Mullion fixing to Curtain walling System
8
Feb 5
5 8 6
11 12
9 7 10
13
8
14
9 11
13 11 1ST 14 Pre instal no 1 18 M&Ecast Stair 1st fixFix 12 M&E
1w 08 12 19 Jan Jan 18 18 15 Jan Jan 18 18 19 1w 15
18
19 Pre cast Stair instal no 2
1w 15 Jan 18 19 Jan 18
15 10 12
16 The installation of curtain wall is on schedule according INTERNAL weeks programme as the glazing arrive on time First Floor Substation works GFto the 6 2w 18 Dec 17 12 Jan 18 17 Ground Floor 13 Partition 08 11 12 Jan Jan 18 18 Partition 1ST 1st fixFix 08 Jan Jan 18 18 12 1wmanufacturer. from the1w 14 12
19
The curtain walling is now inserting on the ground and 15 13 12 Jan Jan 18 18 08 Jan Jan 18 18 26 1w 22 the first 1w floor. As they do not require steel framing, 16 18 1w Notes: Comment - Chart Properties Dwg No. 00001 Revision No. A 14 19 Feb Jan 18 15 Jan Jan 18 18 02 1w 29 this enable the task to start earlier then the external Project Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp Planned by Asta Powerproject works GFcladding2w 17 Substation Dec 17 12 Jan 18 17 Second Floor of18corten steel. 1ST 15 Default Partition 1ST Fix Fix 13 Partition M&E 1ST Fix 16 Drawn - Chart Properties M&E 1ST Fix 14by: Planner
30
Acoustic Insulation
REV. DATE
Perforated Cor-Ten Cassette Screen setback 25mm from adjacent Corten cladding panels
DESCRIPTION
BY
Architects, Landscape & Interior Design 16-20 Bath Street, Nottingham NG1 1DF T
0115 841 8418
E
design@allanjoycearchitects .co.uk
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group
Window pod PIR board and fire rated canister applied insulation
Confetti CQ Campus 30
FFL = 38.930
Corten gutter system with interface to recessed fix cassette
Facade Section Detail 1 - 1
1w 22 Jan 18 1w 29 Jan Jan 18 18 1w 08 1w 15 Jan 18
26 Jan 18 12 Feb Jan 18 02 18 19 Jan 18
15 18
16
19 The manufacturer has specified the glazing and the Jan 18 17 works GFaluminium 17 Substation Dec 17 12according Trades Contractor 2w 18frame to the requirement of the Default contractors and is clearly stated in 18a document for the Notes: Comment - Chart Properties Revision No. A Drawn Properties Pre- Chart cast Stair instal no 1 Dwg No. 00001 1w 08 Jan 18 12 Jan 18 18by: Planner contractor toJanrefer. 19 Pre cast Stair instal no 2 18 19 Jan 18 1w 15 Project19 Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp Planned by Asta Powerproject
Default
DRAWING
Facade Section Corten Cladding Detail PROJECT NUMBER
SCALE
DATE
2588
1:20 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
Preliminary
MLD
301
15 Partition 1ST Fix StairFix instal no 1 18 M&Ecast 1ST 16 Pre 19 Pre cast Stair instal no 2
Trades Contractor
PROJECT
Outer sill flashing with interface to recessed fix cassette
9
6
Second Floor First Floor Trades Contractor
Waterproof membrane
FFL = 42.230
Cavity barriers and smoke stop for Curtain Walling to suit site. Bracket Structural Fixing to Structural Engineers Details
29
4 7
1w 22 Jan 26 Jan Jan 18 18 Jan 18 18 12 1w 08 15 Jan 18 02 19 Feb Jan 18 1w 29
17
9
3
CURTAIN WALLING 1w 15 Jan 18 19 Jan 18
Frameless Window insert to Curtain Walling System
87
8
Glenn Reeves
5 10
1w 15 Jan 18 19 Jan 18
9 1st fixFix - 2ND 11 1ST1ST 15 WINDOWS 10 Partition 1st fix 12 M&E 1ST Fix 16
6
Feb 5
3 1
INTERNAL CURTAIN WALLING Ground Floor Second WINDOWS GRD - 1ST
Curtain Walling System
8
2018 January 7 15 22 5 6
9
14 M&E
30
Aluminium Fixing Plate
1w 26 Jan 18 3w 08 Jan 18 12
7
29
1
4
9 7 10 13 8
275mm concrete deck to Structural Engineer's details
2017 December 18 25 1 17 21 1w 17 22 2 3 09 Dec Feb 18 29 Dec Jan 18 2w 18
4
8
22 Jan 18 19 26 Jan 18 1w 15
4 7 5
FFL = 45.464
3
1
2018 4 January 15 5 22 5 6
1w 15 Jan 18 19 Jan 18
3
100 mm Infill SFS fixed to the structure
2
25
Duration Jan 18 Jan 18 26Finish 2w 15Start
5 9
35mm Benchmark Metallic Recessed Fix Cassette or similar
18 1
3
SFS 3RD - 4TH FLOOR WINDOWS GRD - 1ST EXTERNAL FACADE 6 SFS 10 1ST -FLOOR 2ND SFS 4TH GRD--5TH 1STFLOOR 2 WINDOWS
4
100mm Benchmark Quadcore Karrier Vertically laid or similar fixed with a minimum of 2 Nr fasteners per panel per rail U-Value = 0.18W/m2K
Glenn Reeves
1w 08 Jan 18 12 Jan 18
SFS 1ST - 2ND FLOOR
Drawn by: Planner - Chart Properties
Dwg No. 00001
Project Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp
Revision No. A
Notes: Comment - Chart Properties
Planned by Asta Powerproject
This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
47
13/12/2017CONSTRUCT 6TH FLOOR / 1
ROOF
Line EXTERNALName FACADE 2 3 1 4 5 6 2 3 4 7 5 8 6
9 7 10 8
SFS GRD - 1ST FLOOR CONSTRUCT 6TH FLOOR / SFS 1ST - 2ND FLOOR ROOF SFS 2ND - 3RD FLOOR
3w 08 Jan 18 26 Jan 18
2017 December Duration Start Finish 18 25 1 1w 18 Dec 17 22 Dec 17 21 2 3 1w 26 Jan 18 3w 08 Jan 18 12
4
1w 22 Jan 18 26 Jan 18
SFS 1ST - 2ND FLOOR BRICKWORK SFS 2ND - 3RD FLOOR
1w 08 Jan 18 12 Jan 18
8
2018 January 15 22 5 6
CURTAIN WALLING BRICKWORK WINDOWS - 1ST BWK GRD -GRD 1ST FLOOR
1w 15 Jan 18 2w 1w 15 22 Jan Jan 18 18 29 2w Jan 18 18 1w 29 Jan
19 Jan 18 26 26 Jan Jan 18 18 09 Feb 02 Feb 18 18
15 15 Jan Jan 18 18 22 Jan 29 Jan 18 18
19 26 Jan Jan 18 18 26 Jan 18 09 Feb 18
1w 2w 1w 2w
WINDOWS 2ND BWK 1ST - 1ST 2ND- FLOOR INTERNAL CURTAIN WALLING Ground Floor WINDOWS GRD - 1ST
1w 15 Jan 18 19 Jan 18 Jan 18 1w 26 Jan Jan 18 18 22 Jan 18 12 1w 08 1w 15 Jan 18 19 Jan 18
9 Partition 1st 1ST fix - 2ND 11 WINDOWS 10 12 M&E 1st fix
8
Feb 5
9
4 5
29 Dec Jan 18 02 Dec Feb 18 1w 17 2 1w 18 17 22
BWK GRD- -4TH 1STFLOOR FLOOR SFS 3RD BWK 1ST 2ND FLOOR SFS 4TH - 5TH FLOOR
7
29
3 1
1w 15 Jan 18 19 Jan 18
SFS 3RD - 4TH FLOOR EXTERNAL FACADE SFS SFS 4TH GRD--5TH 1STFLOOR FLOOR
Glenn Reeves
1
6 3 4 7
5 8 6
9 7 10
8
9 11
10 12
INTERNAL First Floor Ground Floor 13 Partition 1ST 1st fixFix 11 Partition 14 1ST M&E 1st fixFix 12 M&E
1w 12 Jan Jan 18 18 08 Jan Jan 18 18 12 1w 08 18 19 1w 19 Jan Jan 18 18 15 Jan Jan 18 1w 15
Second Floor First Floor 15 Partition 1ST 1ST Fix Fix 13 Partition 16 M&E 1ST Fix 1ST Fix 14 M&E
22 Jan 1w 12 Jan Jan 18 18 Jan 18 18 26 1w 08 29 Jan 18 02 Feb 18 1w 1w 15 Jan 18 19 Jan 18
17 Substation works GF Second Floor
2w 18 Dec 17 12 Jan 18 17
13 11 14 12
15
13
22 Jan 18 26 Jan 18 STEEL1w FRAME SYSTEM (SFS)& 12 Feb Jan 18 1w 18 29 Jan Jan 18 18 02 1w 08 CLADDINGS 1w 15 Jan 18 19 Jan 18
15 Partition 1ST Fix 18 StairFix instal no 1 M&Ecast 1ST 16 Pre 19 Pre cast Stair instal no 2
18
15 16
19
works GF 17 Substation Trades Contractor
The red indicates the aluminium frame of the glazing which includes transoms and mullions, while the blue shows the double glazing of the curtain wall.
16
14
2w 18 Dec 17 12 Jan 18 17
Default
Originally the frame is fixing floor by floor, but to work Notes: Comment - Chart Properties Revision No. A 18 1w 08 Jan 18 12 Jan 18 faster, the contractors 19frame on 2 nd Pre cast Stair instal no 2 Jan 18 19 Jan 18 is now fixing the 1w 15 Project19 Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp Planned by Asta Powerproject Trades Contractor floor at the same time. Drawn Properties Pre- Chart cast Stair instal no 1 Dwg No. 00001 18by: Planner
Default
The wall is fixed through the back restraint bracket to the concrete floor slab and the frame is still covered in order to avoid scratches and damages during the construction.
Drawn by: Planner - Chart Properties
Dwg No. 00001
Revision No. A
Notes: Comment - Chart Properties
After finish fixing the frame, the programme of putting Project Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp Planned by Asta Powerproject claddings and internal partitions may start. The contractors are optimistic that the work can start in the week after, from 22 January. Further information will be included in Chapter 7: Visit 5, as it should be in process in the next visit , 13 February.
48
First Floor
6.4
S TA I R S
13 Partition 1ST Fix
1w 08 Jan 18 12 Jan 18
14 M&E
1w 15 Jan 18 19 Jan 18
1ST Fix
14
six week programme
Second Floor 15 Partition 1ST Fix
1w 22 Jan 18 26 Jan 18
16 M&E
1w 29 Jan 18 02 Feb 18
13/12/2017
13
1ST Fix
15
Glenn Reeves
16
2017 2018 January Dec 17 12Finish Jan 18 17 December 2w 18 Start Duration 18 25 1 8 15 22 1 2 3 4 5 6 CONSTRUCT 6TH FLOOR / 18 18 1w 26 Jan Jan 18 18 1 Pre cast Stair instal no 1 3w 08 08 Jan Jan 18 18 12 1 ROOF 19 19 Pre cast Stair instal no 2 1w 15 Jan 18 19 Jan 18
17 Substation works Line Name GF
7
29
8
Feb 5
Trades Contractor EXTERNAL FACADE 2
SFSDefault GRD - 1ST FLOOR
Drawn by: Planner - Chart Properties
3
SFS 1ST - 2ND FLOOR
1w 18 Dec 17 22 Dec 17 2 Dwg No. 00001
Revision No. A 1w 08 Jan 18 12 Jan 18
SFS 2ND - 3RDPowerproject\Projects\Confetti.pp FLOOR Project4Ref. C:\Users\glenn.reeves\Documents\Asta
1w 15 Jan 18 19 Jan 18
5
SFS 3RD - 4TH FLOOR
1w 22 Jan 18 26 Jan 18
6
SFS 4TH - 5TH FLOOR
1w 29 Jan 18 02 Feb 18
3
Notes: Comment - Chart Properties 4
Planned by Asta Powerproject 5 6
BRICKWORK 7
BWK GRD - 1ST FLOOR
2w 15 Jan 18 26 Jan 18
8
BWK 1ST - 2ND FLOOR
2w 29 Jan 18 09 Feb 18
7 8
CURTAIN WALLING WINDOWS GRD - 1ST
1w 15 Jan 18 19 Jan 18
10 WINDOWS 1ST - 2ND
1w 22 Jan 18 26 Jan 18
9
9 10
INTERNAL Ground Floor 11 Partition 1st fix
1w 08 Jan 18 12 Jan 18
12 M&E
1w 15 Jan 18 19 Jan 18
1st fix
11 12
First Floor
STAIR 1 Although Stair 1 is scheduled to be fixed between 8th and 12th January, it is still not visible on site on the 16th January. This is due to the delay of the manufacturer that they did not finish the concrete staircase on time. Workers are fixing steel supports on walls for inserting the stair-core later in this week as Stair 1 should be arriving the week after ,22 January.
STAIR 2 Stair 2 is still not visible on site.
13 Partition 1ST Fix
1w 08 Jan 18 12 Jan 18
14 M&E
1w 15 Jan 18 19 Jan 18
1ST Fix
Second Floor 15 Partition 1ST Fix 16 M&E
STAIR 3
1ST Fix
1w 22 Jan 18 26 Jan 18 1w 29 Jan 18 02 Feb 18
13 14
15 16
Temporary balustrades are placed to ensure safety 2w 18 Dec 17 12 Jan 18 17 in the site so that they can assist the workers and the Although it is scheduled as constructing after18Stair in instal novisitors walking and 18 12 Jan 18 down the stairs. Pre cast1Stair 1 1w 08 Jan 18 up 19 19 Jan 18 Pre cast Stair instal no 2 19 15 Jan 18 1w the 6 weeks programme, it is said to be arriving on the Trades Contractor next day of this visit, 17 January, and will be insert to the However, no further construction was added on since Default structure immediately. theDwg last focusing on Notes: Comment - Chart Properties No. 00001 visit, it is because Revision No. A the workers are Drawn by: Planner - Chart Properties other tasks that they need to get the programme Project Ref. C:\Users\glenn.reeves\Documents\Asta Powerproject\Projects\Confetti.pp Planned by Asta Powerprojectback Therefore, it will be further discussed in the Chapter to schedule so Stair 3 is not in the 6 week programme 7&8 as it will be installed completely by that time. that they set . 17 Substation works GF
49
9
3111
C O U RT YA R D X105 COMPUTER SUITE
Insitu concrete
Pre-cast concrete
Ground Floor 38.568
Ground Floor 38.360
Detail V - 301 CH 3.24
SH 0.81 HH 2.93
3235
Duct
U/S 2.07
U/S 2.00
HH 2.41 SH 0.68
Female WC
FFL Col
HH 2.83 SH 0.73
U/S 2.58
H104 SCH 2.56
CH 3.01
CH 3.01
39.04
SP 1.37
Turning circle
STN/147 39.01
COURTYARD Lift Col
SH 0.81 HH 2.93
DH 2.05 CH 3
CH 3.01
21 20
S13
Disabled WC + shower
S12
U/S 2.93
18 17
15 16 Changing Room Shower
wash
U/S 2.71
34.770
12 13 14
Store 1.54 sqm
shaft recess for drinking tap
U/S 2.71
19
33 34
SH 0.81 HH 2.93
dumb waiter 1100x1100
Ambulant Disabled
U/S 2.78
22
30
31 32
SH 0.81 HH 2.93
35 36 11
cupbd
20
cook
CH 3.01
29 28 27 26
U/S 2.58
CH 3.01
SH 0.81 HH 2.93
up
23 22 21
SH 0.81 HH 2.93
CH 2.49
CH 3.07
U/S 2.93
Col
U/S 2.57
25
U/S 2.71
DH 2.05
CH 2.99
TA 2.23
HH 2.83 SH 0.73
FFL 39.06
SH 0.79 HH 2.88
26 24 17 18
Stair 2
25 24 23
SH 0.95 HH 2.17
2010 1010 100 3622 1010
Lounge
29
up
SP 1.37
634
SH 1.51 HH 2.31 TA 2.39
SH 1.54 HH 2.35 TA 2.40
SH 0.82 HH 2.95 CH 3.03
Duct
SCH 2.58
SCH 2.58
CH 3.03
DH 1.96
DH 1.96
SCH 2.58
U/S 2.58
DP
Hatch
Lounge
28 27
19
Further construction of placing insulation and floor furnishing are required in the future programme. Ground Floor Wheelchair Refuge
prep
15 14
16
U/S 2.78
FFL 39.07
U/S 2.59
on
110
tructi under cons CH 2.78
SH 0.82 HH 2.95
Toilets
To ConFetti
FFL 39.01
CH 3.03
DH 1.96
Hatch
Ground Floor 35.048
H
U/S 2.71
Col
SH 0.82 HH 2.95
Circular SH 0.94 HH 1.73
FFL 37.69
G
SP 1.37
CH 3.06
SH 0.79 HH 2.95
Step
SH 0.64 HH 2.95 U/S 3.07
Link to Confetti
DH 2.06
STN/146 39.07
CH 2.99
TA 2.23
FFL 39.06
CH 2.99
DH 2.04
H102 SCH 2.58
SH 0.79 HH 2.95
Ceil 40.54
A 220
DH 1.96
DH 1.96
Circular SH 1.61 HH 2.41 FFL 37.89
B
Hatch
CH 2.83
Circular SH 0.94 HH 1.73
U/S 1.99
DH 1.96
C101
C120
U/S 2.81
Existing door to be
SH 0.74 TA 3.21
F
SP 1.37
H101 SCH 2.62
Detail S - 301
SH 0.64 HH 2.95 U/S 3.07
E
Kitchen CH 3.14
D
SP 1.45
C
CH 3.06
B
CH 3.17
COURTYARD
C101/102 LIVE ROOM
222 A
C110
Ee
WINDOW
U/S 2.71
H103 SCH 2.61
First Floor 39.060
TA 2.27
FFL 39.04
FFL 39.08
STN/143 39.04
100
Canteen
New ramp to be constructed by contractor
1in12 ID 113
FFL 37.90
UP 130
125 354 1010
FFL 37.74
21
7110
FFL 37.73
20
U/S 1.99
19
Step
18
Lift
First Floor 39.060
Col
17
C
910 333 Wheelchair Refuge
X111 STAIR 2 LOBBY
First Floor 38.930
SP 1.45
16
ID 114
FLAT ROOF
OMIT FULL HEIGHT
CH 3.03
15
248
1031
X110 STAIR 2
SH 0.74 TA 3.21
1
Column
2
Ceiling Decorative CH 2.83
3
Column
4
CH 3.17
5
Column
6
CH 3.32
7
SH 0.63 HH 3.05
8
314
SCH 3.02
ID 112
X112 clnrs cpbd ID 111
STN/113 37.90
4
600
Circular SH 1.61 HH 2.41
W 08
20
SH 0.74 TA 3.21
19
It is a pre-cast concrete slab, instead of using the same method of pouring concrete on insitu frame as the other part of the building. This is due to avoid uncontrollable pouring in limited space of the courtyard. SH 0.63 HH 3.05
18
Circular SH 1.61 HH 2.41
17
DH 1.96
16
38.12
15
Step
14
FFL 37.92
13
U/S 2.90
U/S 2.89
STN/112 38.10
12
FFL 38.13
11
Step
FFL 37.76
FFL 38.11
FFL 38.06
10
DH 1.94
9
Step
FFL 38.12
SCH 2.44
8
STN/111 38.32
CH 2.37
7
DH 1.95
FFL 38.13
SCH 2.41
CH 2.77
6
DH 1.95
CH 2.37
DH 1.94
5
SCH 2.38
FFL 38.29
CH 3.01
Step
STN/114 38.04
CH 2.88
4
DH 2.00
SCH 2.58
STN/115 36.46
221 B
3
access
DH 2.01
HH 1.92 SH 1.09
SH 0.88 TA 2.95
beam
First Floor 38.930
First Floor 38.930
2
Limited
Room Server CH 3.34
38.26
HH 1.92 SH 1.09
HH 1.92 SH 1.09
HH 1.92 SH 1.09
HH 1.92 SH 1.09
SH 0.87 TA 2.94
FFL 38.23 Ceil 40.88
downstand
422 1
U/S 2.91
line Assumed external wall
X102 KITCHEN 24m2
X102 KITCHEN 12 m2
FFL 37.76
C105 CH 3.02
HH 1.92 SH 1.09
HH 1.92 SH 1.09
DH 1.95
Win/A SH 2.04
X114 NEW RAISED COURTYARD
First Floor 38.568
GRAB AND GO
ID 110
U/S 2.50
NEW COURTYARD
x 550 deep
ID 108
Mechanical riser
W 01
HH 1.92 SH 1.09
AREA
First Floor 38.930
void
NEW DOORS OUT TO
W 07 ADDITIONAL SEATING
First Floor 38.930
ID 109
300 wide
First Floor X103 38.930 CAFE SERVERY 38 m2
SH 0.86 TA 2.94
ACROSS
Eb
3
ED 15 ED 16
First Floor 38.360
Ec
Ea
STN/110 38.23
NEW STEPS
Electrical riser
1100MM HIGH
200 wide x 1000 high upstand
U/S2 .13
ACCESS
ID 107 LOW WALL 1100MM HIGH
LOW WALL
Ed
312
STN/109 38.27
1in15
First Floor 38.764
3a
FFL 38.23
First Floor 38.930
DH 2.02
1in15
220 A
1
2
IS 101
CH 3.26
3
4
2a
W 04
ID 106
First Floor 38.360
1in15
The steel structure of the raised courtyard was visible in the last visit. This visit, the concrete slab has added to the construction and is placed on the top of the steel structure. U/S 2.44
OH 2.04
First Floor 38.568
ID 102
2
UP 570
SH 0.90 HH 2.53
ID 105
DH 2.00 Win/A SH 2.05 HH 2.53
X109 STAIR 1 LOBBY
FFL 38.36
X101 CAFE 151 m2
X014 SERVER ID 101
First Floor 38.764
DH 2.02
5
U/S 2.01
40.89 Ceil STN/108 38.36
6
First Floor 38.568
38.27
20
7
ID 104 ID 103
U/S 2.94
DH 1.96
19
FFL 38.28 SH 0.91 HH 1.96
18
Floor Slope 38.31
8
38.21
X108 STAIR 1
9
38.24
17
10
310
X104 SEMINAR ROOM 30 m2
Ceil 41.10
X106 FEMALE WC
16
1
Wall 1.29h
X107 ACCESSIBLE WC 15
U/S 41.09
U/S level 41.06
11
1a
U/S 3.06
CH 3.32
U/S 2.44
W 02 W 05
SH 0.74 TA 3.21
Room Server 3.01 SCH
SCH 4.33
x 550 deep
FFL 40.30
W 06 300 wide
STN/129 39.72
D 301
beam downstand
SCH 4.90
F 300
38.23
E 300
Ea
HH 2.87 SH 0.80
E
38.22
C 222
D
HH 2.87 SH 0.80
C
TA 2.92 SH 0.85
U/S 1.39
B
38.26
HH 2.99 SH 0.79
Ec
Eb
A
TA 2.89 SH 0.81
Ed
TA 2.90 SH 0.82
Ee
421
420
SH 0.76 TA 3.20
Same as ground Floor (Type 12) but on Precast concrete Plank to Structural Engineer's details
221
6.5
Male WC
Ambulant Disabled
D C B
21/08/17 Change to HE reception wall GF and door position FF 10/08/17 Additional dimensions added to HE Centre 12/05/17 Amendments to drawings following the Topo Survey and SE info
A
23/01/17 Amendments to drawings REV. DATE
DESCRIPTION
MLD TE MLD MLD BY
50
7
S ITE
VISIT 5
Date: 13 February 2018 (Tue) Weather: cloudy with rain occasionally Temperature: 3 °C People on site: 40 to 50
• Project manager
• Contractors
• Workers
• Mechanicians
• Students and tutors
P ROGRAMME
7.1 A 1
B C D E F G H I J K L M N O P Q R S T U V W X Y Z AAABACADAEAFAGAHAIAJAKALAM ANAOAPAQARASATAUAVAW AXAYAZBABBBCBDBEBFBGBHBIBJBKBLBMBNBOBPBQBRBSBTBUBVBW BXBYBZCACBCCCDCECFCGCHCICJ
Confetti
2 3 4
2017 2018
Month/year
Line
March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
5 Task 6 Tender programme
Key Subcontractor Procurement Construction Programme
5 6 7 8
Architectural, structural and civil to 11 stage 4 12 Subcontractor procurement
Site Preperation
Superstructure
5w 25 Sep 17 A
27 Oct 17 A
5w
02 Oct 17 A
03 Nov 17 A
20
5w
09 Oct 17 A
10 Nov 17 A
Construct Third Floor Slab
4w
23 Oct 17 A
17 Nov 17 A
Construct Columns and Walls Third to Fourth
4w 10 Nov 17 A 07 Dec 17 A
23 24
Construct Columns and Walls Second to Third
22
Construct Fourth Floor Slab
4w 20 Nov 17 A 15 Dec 17 A
Construct Columns and Walls Fourth to Fifth
4w 04 Dec 17 A
12 Jan 18 A
25
Construct Fifth Floor Slab
3w 19 Dec 17 A
22 Jan 18 A
26
Construct Columns and Walls Fifth to Terrace
2w 20 Dec 17 A
16 Jan 18
27
Stair 1 PCC Deliver and Install
1w
08 Jan 18 A
12 Jan 18 A
28
Stair 2 PCC Deliver and install
1w
15 Jan 18 A
19 Jan 18 A
29
Construct Terrace Slab
2w
15 Jan 18 A
26 Jan 18 A
30
Strip and Site Clear
2w
29 Jan 18 A
09 Feb 18 A
44 45
46 47
22 23 24 25
30
35 36 37
40 41
HE Steelwork Frame and Stair / Floors
2w 07 Aug 17 A 18 Aug 17 A
Floor Joists and Landings installed
1w 21 Aug 17 A 25 Aug 17 A
42 43
Lift Shaft Frame
2w 04 Sep 17 A
15 Sep 17
Roof Protect
1w 29 Aug 17 A
04 Sep 17
44 45
31 32 33
38 39 40 41 42 43
Partition Walls
1w 21 Aug 17 A 25 Aug 17 A
44
1st fix M&E
1w 21 Aug 17 A 25 Aug 17 A
45
46
1st fix Joinery + Door instal
3d 29 Aug 17 A
47
Partial Stair 2 and Client Handover, Out of hours finishes External Envelope External Wall External SFS and Carrier Panel
External SFS and carrier pannels grnd - 1st
52
External SFS and carrier pannels 1st - 2nd
53
External SFS and carrier pannels 2nd - 3rd
54
External SFS and carrier pannels 3rd - 4th
55
External SFS and carrier panels 4th to 5th External SFS and carrier panels 5th to 6th Roof Curtain Walling / Windows and Doors
31 Aug 17
18 Dec 17 A
04 May 18
48
18 Dec 17 A
04 May 18
49
16 Mar 18
50
11w
18 Dec 17 A
1w 18 Dec 17 A 22 Dec 17 A 1w
08 Jan 18 A
1w 06 Feb 18 A 1w
12 Mar 18
16 Mar 18
15 Jan 18 A
22 Mar 18
57 58
1w
15 Jan 18 A
19 Jan 18 A
22 Jan 18 A
07 Feb 18 A
60
Curtain walling and windows 2nd - 3rd
2w 1d 09 Feb 18 A
19 Feb 18 A
61
Curtain walling and windows 3rd - 4th
2d
27 Feb 18
28 Feb 18
62
Curtain Walling / Windows 4th to 5th
1w
01 Mar 18
07 Mar 18
Facing Brick Gnd to 1st
1w
07 Mar 18
1w 3d
13 Mar 18
9w 3d
26 Feb 18 A
1w 26 Feb 18 A
24 Apr 18
23 Apr 18
04 May 18
67 68 69 70 71
17 Apr 18
72
Corten Fixed Cassette Gnd to 1st
1w
27 Feb 18
05 Mar 18
73
Corten Fixed Cassette 1st to 2nd
1w
05 Mar 18
09 Mar 18
75
Corten Fixed Cassette 2nd to 3rd
1w
12 Mar 18
16 Mar 18
76
Corten Fixed Cassette 3rd to 4th
1w
20 Mar 18
26 Mar 18
77
Corten Fixed Cassette 4th to 5th
1w
26 Mar 18
03 Apr 18
78
Corten Fixed Cassette 5th to 6th
2w
04 Apr 18
17 Apr 18
74
80
Roof Works
87 88 89 90 91 92
27 Feb 18
79 80 81
03 Apr 18
12 Mar 18
24 Apr 18
12 Mar 18
23 Mar 18
1w
20 Mar 18
26 Mar 18
Deck/ insulation / Single Ply
2w
26 Mar 18
10 Apr 18
Rainwater Goods
1w
12 Apr 18
18 Apr 18
87 88 89
04 Apr 18
10 Apr 18
2w
11 Apr 18
24 Apr 18
1w
11 Apr 18
17 Apr 18
5w
05 Mar 18
10 Apr 18
93 94
2w
05 Mar 18
16 Mar 18
1w
12 Mar 18
16 Mar 18
2w
install roof plant Upper roof Deck/ insulation / Single Ply Membrane
1w 1w
Rainwater Goods
99
86
1w
Upper Roof Parapets / Gutters
98
84
Mesh Fenceline
Plant Bases and upstands
97
83
85
Terrace Floor Finish
95 96
82
Green Sedum Roof 6th Floor Upper Roof
94
102
78
24 Apr 18
28 Mar 18
26 Mar 18
6w
2w
77
03 Apr 18
16 Mar 18
15 Mar 18
1w
Roof Parapets / Outlets
76
05 Mar 18
05 Mar 18
2w
Plant Bases and upstands
75
27 Feb 18
2w
Rainwater Goods 6th Floor Lower Roof
74
27 Feb 18
1w
Lower roof Deck Lower Roof Membrane and Insulation
85
86
4w 4d
Lower Roof Parapets / Outlets
84
93
7w 4d
5th Floor Roof
27 Feb 18
64
66
10 Apr 18
11 Apr 18
26 Mar 18 19 Mar 18 03 Apr 18 26 Mar 18
Building Watertight Ground Floor Internal Finishes Internal Finishes
1st fix Partitions
17w 3d
08 Jan 18 A
90 91 92
95
10 Apr 18
96
23 Mar 18
97
09 Apr 18
98
26 Mar 18
99
14 May 18
100
17w 3d
08 Jan 18 A
14 May 18
101
4w 3d
08 Jan 18 A
07 Feb 18 A
102
103
M&E Installation
3w 3d
15 Jan 18 A
28 Feb 18
104
Close Up Dry Lining / Partitions
1w 4d
29 Jan 18 A
19 Feb 18 A
104
2w
29 Jan 18 A
16 Feb 18 A
105
1w
27 Feb 18
05 Mar 18
105
Fire Stopping
106
Joinery
107
under floor heating
108
screeding
109
Plastering
110
2d
05 Mar 18
06 Mar 18
1w
08 Mar 18
14 Mar 18
1w 4d 27 Feb 18 A
103
106 107 108
09 Mar 18
109
Mist Coat Walls
2d
111
2nd Fix M&E
2w
07 Mar 18
20 Mar 18
112
Decoration Works inc. Tiling
1w
19 Mar 18
23 Mar 18
113
Suspended Ceiling Finishes
1w
26 Mar 18
03 Apr 18
114
Internal Glass Screens
1w
03 Apr 18
09 Apr 18
114
115
Floor Finishes
2w
115
116
3rd Fix M&E
05 Mar 18
06 Mar 18
03 Apr 18
16 Apr 18
1w
19 Apr 18
25 Apr 18
117
Power On / Heat On
16 Apr 18
16 Apr 18
118
Joinery - 2nd Fix (doors)
2w
09 Apr 18
20 Apr 18
119
IPS installation
1w
12 Apr 18
18 Apr 18
120
Sanitary Installation
1w
23 Apr 18
27 Apr 18
121
Final Fix FF&E
2w
30 Apr 18
14 May 18
122
Cleaning and Snagging
123
First Floor Internal Finishes
124
Internal Finishes
1w 18w 3d 18w 3d
08 May 18 08 Jan 18 A 08 Jan 18 A
110 111 112 113
116 117 118 119 120 121
14 May 18
122
21 May 18
123
21 May 18
126
M&E Installation
March April May 20 27 3 10 17 24 1 8 15 22 3w 4d 15 Jan 18 A 01 Mar 18 A -8 -7 -6 -5 -4 -3 -2 -1 1 2 3
127
Close Up Dry Lining / Partitions
1w 4d 14 Feb 18 A
26 Feb 18 A
128 Line 129
Fire Stopping Name Suspended MF Ceilings
2w 12 Feb 18 A Duration Start 2w 1d 20 Feb 18
23 Feb 18 A Finish 06 Mar 18
130
Joinery
1w
26 Feb 18
02 Mar 18
131
1st Fix FF&E
2w
26 Feb 18
09 Mar 18
132
Plastering
133
Line 125
Name
1st fix Partitions
Duration 4w 3d
Start 08 Jan 18 A
Finish 14 Feb 18 A
-8
-7 -6 -5 -4 -3 -2 -1 1 2 3 20 27 3 10 17 24 1 8 15 22 March April May
29 4 4 29
5
5
5 5
June 12 19 6 7 6 7 12 19 June
26 8
3
8 26
9 3
9
2017 2018 124 July August September October November December January February March April May June July August September 125 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 126 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 127 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 128 12 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 July August September October November December January February March April May June July August September 129 2017 2018 130 131
12 Mar 18
13 Mar 18
2w
14 Mar 18
27 Mar 18
2nd Fix M&E
1w
26 Mar 18
03 Apr 18
135
Decoration Works inc. Tiling
1w
04 Apr 18
10 Apr 18
136
Suspended Ceiling Finishes
1w
10 Apr 18
16 Apr 18
136
137
Internal Glass Screens
2w
10 Apr 18
23 Apr 18
137
138
Floor Finishes
1w
26 Apr 18
02 May 18
139
Power On / Heat On
23 Apr 18
23 Apr 18
140
Joinery - 2nd Fix (doors)
2w
16 Apr 18
27 Apr 18
IPS installation
1w
19 Apr 18
25 Apr 18
142
Sanitary Installation
1w
30 Apr 18
04 May 18
143
Final Fix FF&E
2w
08 May 18
21 May 18
144
Cleaning and Snagging
1w
15 May 18
21 May 18
145
Second Floor Internal Finishes
7d
138 139
As the revised target programme is more updated and more related to real construction process, it is used from this Chapter accompany with the 6-weeks programme that show the actual progress in the site.
140 141 142 143 144
04 May 18
145
04 May 18
146
3w 1d
22 Jan 18 A
12 Feb 18 A
147
2w
29 Jan 18 A
23 Feb 18 A
Close Up Dry Lining / Partitions
4d
27 Feb 18
02 Mar 18
149
Fire Stopping
4d
27 Feb 18
02 Mar 18
150
151
Joinery
4d
05 Mar 18
08 Mar 18
151
152
22 Jan 18 A
-6d 135
1st fix Partitions
14w 3d
22 Jan 18 A
134
M&E Installation
Internal Finishes
14w 3d
133
150
148
3d
132
149
147
148
1st Fix FF&E 152
Plastering
153
Mist Coat Walls
154 155
1w
05 Mar 18
09 Mar 18
1w 2d
12 Mar 18
20 Mar 18
19 Mar 18
23 Mar 18
26 Mar 18
03 Apr 18
2nd Fix M&E
1w
Decoration Works inc. Tiling
156 157
1w
Suspended Ceiling Finishes
1w
29 Mar 18
06 Apr 18
Internal Glass Screens
1w
03 Apr 18
09 Apr 18
158
Floor Finishes
2w
10 Apr 18
23 Apr 18
159
3rd Fix M&E
1w
16 Apr 18
20 Apr 18
160
Power On / Heat On
23 Apr 18
23 Apr 18
161
Joinery - 2nd Fix
1w
16 Apr 18
20 Apr 18
162
IPS installation
1w
10 Apr 18
16 Apr 18
Sanitary Installation
1w
16 Apr 18
20 Apr 18
163
153 154 155 156 157 158 159 160 161 162 163
Final Fix FF&E 164 165 166
167
Cleaning and Snagging Third Floor Internal Finishes Internal Finishes
1st fix Partitions
168 169
1w
30 Apr 18
04 May 18
11w 2d
20 Feb 18 A
14 May 18
165
11w 2d
20 Feb 18 A
14 May 18
166
1w 27 Feb 18 A
05 Mar 18 A
M&E Installation
2w 20 Feb 18 A
05 Mar 18 A
Close Up Dry Lining / Partitions
1w
170
Fire Stopping
1w
07 Mar 18
13 Mar 18
171
Joinery
1w
13 Mar 18
19 Mar 18
172
20 Mar 18
28 Feb 18
164
167 168
06 Mar 18
169 170 171
1st Fix FF&E Plastering
1w
173 174
Mist Coat Walls
1w
03 Apr 18
2nd Fix M&E
1w
10 Apr 18
175
Decoration Works inc. Tiling
1w
16 Apr 18
176
Suspended Ceiling Finishes
1w
23 Apr 18
26 Mar 18
172
09 Apr 18
173
16 Apr 18
174
20 Apr 18
175
27 Apr 18
177
Internal Glass Screens
3d
23 Apr 18
25 Apr 18
178
Floor Finishes
1w
30 Apr 18
04 May 18
179
3rd Fix M&E
1w
30 Apr 18
04 May 18
180
Power On / Heat On
09 Apr 18
09 Apr 18
181
Joinery - 2nd Fix
1w
30 Apr 18
04 May 18
182
IPS installation
1w
23 Apr 18
27 Apr 18
183
Sanitary Installation
1w
30 Apr 18
04 May 18
184
Cleaning and Snagging
1w
08 May 18
14 May 18
185
Fourth Floor Internal Finishes
The contractor is still positive that they can meet the end date in 11 June and they revise the programme to prove to the project team. Target and progress programme are set to revise the whole programme, stating the tasks that are completed and the duration of tasks that they are going to complete in the future.
-4d
2d
Mist Coat Walls
134
141
As the programme is quite behind the schedule that the contractor set in the beginning of the project even though they worked longer in the Christmas holidays. The project team and the contractor had a meeting regarding to whether the construction can be completed on time.
63
65
23 Mar 18
26 Mar 18
2w 2w
62
04 May 18
13 Mar 18
12 Mar 18
2w
73
3d
61
13 Mar 18
01 Mar 18
2w
Facing Brick 4th to 5th
6w 4d
56
60
22 Mar 18
1w 4d
Facing Brick 3rd to 4th
70
Facing Brick 5th to 6th
55
59
02 Mar 18 A
Facing Brick 1st to 2nd Facing Brick 2nd to 3rd
69
Corten Fixed Cassette installation
54
1w 9w 4d
2w 3d
Curtain Walling / Windows 5th to 6th Roof
53
28 Feb 18 08 Mar 18
Curtain Walling / Windows grnd - 1st
External Doors and Louvres
52
12 Feb 18
Curtiain walling and windows 1st - 2nd
Facing Brickwork
51
12 Jan 18 A
02 Mar 18
59
68
47
17w 3d 17w 3d
58
67
-2d 46
01 Sep 17 A 01 Sep 17 A
2w 4d 09 Feb 18 A
14d
29
15 Sep 17
28 Jul 17 A
-10d
28
04 Aug 17 A 04 Aug 17 A
26
27
24 Jul 17 A
24 Jul 17 A
79
176 177 178 179 180 181 182 183
Final Fix FF&E
186
Internal Finishes
184
11w
28 Feb 18
18 May 18
185
11w
28 Feb 18
18 May 18
186 187
187
1st fix Partitions
1w
28 Feb 18
06 Mar 18
188
M&E Installation
1w
08 Mar 18
14 Mar 18
189
Close Up Dry Lining / Partitions
1w
16 Mar 18
22 Mar 18
189
190
Fire Stopping
1w
16 Mar 18
22 Mar 18
190
191
Joinery
1w
192
Plastering
193
188
23 Mar 18
29 Mar 18
191
1w
23 Mar 18
29 Mar 18
192
Mist Coat Walls
1w
03 Apr 18
09 Apr 18
194 195
1st Fix FF&E
2nd Fix M&E
1w
06 Apr 18
12 Apr 18
Decoration Works inc. Tiling
1w
12 Apr 18
18 Apr 18
196
Suspended Ceiling Finishes
1w
16 Apr 18
20 Apr 18
197
Internal Glass Screens
3d
17 Apr 18
19 Apr 18
198
Floor Finishes
2w
18 Apr 18
01 May 18
199
3rd Fix M&E
1w
200
Power On / Heat On
23 Apr 18
27 Apr 18
04 May 18
04 May 18
193 194 195 196 197 198 199 200
201
Joinery - 2nd Fix
1w
04 May 18
11 May 18
202
IPS installation
1w
27 Apr 18
03 May 18
Sanitary Installation
1w
04 May 18
11 May 18
14 May 18
18 May 18
03 Apr 18
21 Jun 18
205
203
201 202 203
Final Fix FF&E 204
Cleaning and Snagging
1w
205
Fifth Floor Internal Finishes
11w 1d
206
207
Internal Finishes
1st fix Partitions
204
11w 1d
03 Apr 18
21 Jun 18
206
4w 3d
03 Apr 18
21 Jun 18
207
208
1st fix M&E Installation
1w
10 Apr 18
16 Apr 18
208
209
Close Up Dry Lining / Partitions
1w
10 Apr 18
16 Apr 18
209
210
Fire Stopping
1w
10 Apr 18
16 Apr 18
210
211
Joinery
1w
16 Apr 18
20 Apr 18
211
212
20 Apr 18
212
1st Fix FF&E Plastering
1w
213
Mist Coat Walls
1w
214
2nd Fix M&E
215
16 Apr 18 23 Apr 18
27 Apr 18
1w
27 Apr 18
03 May 18
Decoration Works inc. Tiling
1w
04 May 18
11 May 18
216
Suspended Ceiling Finishes
1w
10 May 18
16 May 18
217
Internal Glass Screens
1w
04 May 18
11 May 18
218
Floor Finishes
219
3rd Fix M&E
220
Power On / Heat On
221
Joinery - 2nd Fix
1w 3d
14 May 18
23 May 18
1w
15 May 18
21 May 18
27 Apr 18
27 Apr 18
1w
21 May 18
25 May 18
213 214 215 216 217 218 219 220 221
222
IPS installation
3d
16 May 18
18 May 18
223
Sanitary Installation
1w
18 May 18
24 May 18
224
Cleaning and Snagging
1w
25 May 18
01 Jun 18
27 Feb 18
23 May 18
225
222 223
Final Fix FF&E 224
Stair 1 Internal Finishes 225
Lift shaft
11w 4d
226
227
11w 4d
27 Feb 18
23 May 18
226
1w 2d
27 Feb 18
07 Mar 18
227
Form Entrances
3w
05 Mar 18
23 Mar 18
228
229
Board out Internal skin
2w
05 Mar 18
16 Mar 18
229
26 Mar 18
23 May 18
231
232 233 234 235
External landscaping, snag and clean 50 externals 51 PRACTICAL COMPLETION
SFS TO FRAME
228 230
Final testing and commissioning, air 49 testing, final clean and snag
Month/year
21
24 Jul 17 A 31 Jul 17 A
83
Stair 1 : M&E, Joinery, Decoration, 48 suspended ceiling, Balustrading
52
20
Grey Term Vacation
34
2d 03 Aug 17 A 04 Aug 17 A
146
42 43
19
15 Sep 17
1w
82
Ground floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Ground floor power on/ heat on First floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation First floor power on/ heat on Second floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Second floor power on/ heat on Third floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Third floor power on/ heat on Fourth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Fourth floor power on/ heat on Fifth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Fifth floor power on/ heat on Sixth floor : Internal finishes, M&E, fire stopping, suspended ceilings, Joinery 1st and 2nd fix, decoration and tiling, sanitary installation Sixth floor power on/ heat on
18
08 Mar 18
7w 4d
EXAM PERIOD
EXAM PERIOD
17
26 Feb 18
1w
81
Roof parapets, deck, insulation, 32 outlets, sedum roof 33 1st building air test
16
24 Jul 17 A
Temporary Weatherproofing to access studio
72
31 Curtain walling all levels
15
7w 4d
Temporary Works / Propping
71
30 Corten steel all levels
+ 14
1w 4d
Adjacent Gnd Flr Live room wall demo
65
29 Facing brickwork all levels
+
08 Mar 18
39
66
28 External panels all levels
+ 13
EXAM PERIOD
26 Jan 18 A
38
64
Stair 2 : 3rd fix M&E, Balustrading and 27 handrails, 2nd fix joinery
+
15 Jan 18 A
37
101
40 41
Internal Finishes
12
Red EXAM PERIOD
15 Jan 18 A
2w
100
38 39
Steelwork to Upper Roof 6th floor
63
Stair 2 : 2nd fix M&E, decoration 26 staircase, suspended ceiling decoration
7w 4d
2w
Stair 2 Construction
56
Stair 2 : Ist fix M&E, dryline walls, mist 25 coat
36 37
Steelwork Frame
Stair 2 Roof / Staircase Existing Walls and Stair removed
57
34 35
Main Build Steelwork Frame
10 11
08 Mar 18 09 Feb 18
Construct Columns and Walls First to Second
50
Alterations to existing building, roof 24 protection
08 May 17
05 Jul 17 A
Construct Second Floor Slab
21
+
9
08 May 17
20 Oct 17 A
2017 2018 July August September October November December January February March April May June July August September 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72
4
23 Aug 17 A
01 Sep 17 A
19
51
23 Steelwork lift shaft and roof
10 Jul 17 A 10 Jul 17 A
18
49
Insitu frame, PCC stairs between 22 floors up to roof deck
27 Jun 17 A
5w 18 Sep 17 A
48
Top soil strip, reduce dig, Piling, 21 Ground beams, Lift pit foundation
30 May 17 A
10 Jul 17 A
5w
35
Site possession, cabins and welfare, 20 Signage
08 May 17 5w 1d
Construct Columns and Walls Grd-First
3 9
5
21/06/2018
Construct First Floor Slab
36
17 Sanitery goods, Landscaping 18 Construction programme 19 Start on site 06-05-2017
19 May 17
08 May 17
8
8w 2d
26 8
+
7
28w 4d
June 12 19 6 7
5
3
6
32w 3d
Insitu Concrete Frame
5
2
+
1w 08 May 17 A 12 May 17 A 08 May 17
Substructure Works
14
29 4
1
+
2w 08 May 17 A 19 May 17 A
Working Platform / Hardstanding done by Client Demolition and Work Alterations
13
March April May 20 27 3 10 17 24 1 8 15 22 -7 -6 -5 -4 -3 -2 -1 1 2 3
1w 08 May 17 A 12 May 17 A
55w 3d 08/05/2017 A
12
34
Internal partitions, Wall and ceiling 16 finishes
08 May 17 A
08 May 17
Signage
10
33
Roof finishes, Lift installation, 15 Windows and external doors
2w
Hoarding and Fencing Cabins and Welfare
17
31
Stats connections, Frame, Cladding, 14 M&E
Finish
08 Jun 17 04 Sep 17 21 Jun 18
16
32
Enabling works, Site set up, Service 13 disconnetions, Groundworks, Piling
Start
07 Apr 17
20w 1d 07 Apr 17 55w 3d 08 May 17 A
Site Possession
Main Build Works
15
10 Planning conditions discharge
8w
Site Set Up
9
11
8 Contract appointment 9 Technical Design stage
Duration
-8 Technical Design Stage
2 3 4
7 Tender addendum information
Name
1
8w
Install lift Final Testing and Commisioning
8w 3d
230
16 Apr 18
15 Jun 18
231
6w
16 Apr 18
29 May 18
232
Air Testing
2d
14 May 18
15 May 18
Final Cleaning and Snagging
2w
04 Jun 18
15 Jun 18
3w
14 May 18
04 Jun 18
235 236
Final Testing and Commissioning
External Works
233 234
236
External Hardlandscaping Footpath
2w
14 May 18
25 May 18
237
External Hardlandscaped Paved areas
2w
21 May 18
04 Jun 18
237
Snagging and Cleaning externals
2w
238
238
239
Practical Completion
21 May 18
04 Jun 18
11 Jun 18
11 Jun 18
Start
Finish
239
-8 Line
March
April
May
June
July
August Sept
Oct
Nov
Dec
Jan
Feb
March
April
May
June
July
August Sept
Name
Duration
-7 -6 -5 -4 -3 -2 -1 1 2 3 20 27 3 10 17 24 1 8 15 22 March April May
4 29
5
5
6 7 12 19 June
8 26
9 3
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 July August September October November December January February March April May June July August September 2017 2018
Floor Level 2nd
3rd
4th
53
52
-XQH
-XO\
$XJXVW G
6HSWHPEHU
*UH\ 7HUP 9DFDWLRQ
-XQH
-XO\
$XJXVW
6HSWHPEHU
-XQH
-XO\
$XJXVW 6HSWHPEHU
G
-XQH
-XO\
-XQH
-XO\
-XQH
-XO\
-XQH
-XO\
6HSWHPEHU
-XQH
-XO\
6HSWHPEHU
-XQH
-XQH
-XO\
-XO\
$XJXVW
6HSWHPEHU
6HSWHPEHU
6HSWHPEHU
$XJXVW
$XJXVW
$XJXVW
$XJXVW
$XJXVW
$XJXVW
6HSWHPEHU
6HSWHPEHU
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
0DUFK -DQXDU\ $SULO 0D\ -XQH )HEUXDU\ -XO\ $XJXVW 6HSWHPEHU 0DUFK 2FWREHU 1RYHPEHU $SULO 'HFHPEHU -DQXDU\ )HEUXDU\ 0D\ 0DUFK $SULO -XQH 0D\ -XQH G
G
*UH\ 7HUP 9DFDWLRQ
G
G
0DUFK -DQXDU\ $SULO 0D\ -XQH )HEUXDU\ -XO\ $XJXVW 6HSWHPEHU 0DUFK 2FWREHU 1RYHPEHU $SULO 'HFHPEHU -DQXDU\ )HEUXDU\ 0D\ 0DUFK $SULO -XQH 0D\ -XQH
(;$0 3(5,2'
(;$0 3(5,2'
(;$0 3(5,2'
G
(;$0 3(5,2'
G
G
G
G
5HG (;$0 3(5,2'
G
G
G
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
0DU &RUWHQ )L[HG &DVVHWWH WK WR WK Z )HE -DQ -DQ 0 ( ,QVWDOODWLRQ Z )HE 0DU 0LVW &RDW :DOOV $SU $SU -RLQHU\ QG )L[ )HE 6XVSHQGHG 0) &HLOLQJV Z 0DU 0 ( ,QVWDOODWLRQ Z -DQ )HE $SU $SU ,36 LQVWDOODWLRQ Z 0DU &RUWHQ )L[HG &DVVHWWH WK WR WK Z -DQ -DQ &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z 0DU 0DU QG )L[ 0 ( $SU $SU ,36 LQVWDOODWLRQ )HE )HE -RLQHU\ &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z )HE )HE 5RRI :RUNV Z -DQ 0DU $SU $SU 6DQLWDU\ ,QVWDOODWLRQ -DQ )HE 0DU 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ $SU $SU 6DQLWDU\ ,QVWDOODWLRQ )HE )HE VW )L[ )) ( )HE )HE )LUH 6WRSSLQJ Z WK )ORRU 5RRI Z -DQ 0DU 0D\ -XQ )LQDO )L[ )) ( Z 0DU 0DU 6XVSHQGHG &HLOLQJ )LQLVKHV 0D\ )LQDO )L[ )) ( Z 0D\ )HE 0DU 3ODVWHULQJ )HE )HE 6XVSHQGHG 0) &HLOLQJV Z -XQ -XQ &OHDQLQJ DQG 6QDJJLQJ /RZHU 5RRI 3DUDSHWV 2XWOHWV Z -DQ -DQ 0DU 0DU ,QWHUQDO *ODVV 6FUHHQV $SU $SU &OHDQLQJ DQG 6QDJJLQJ 0DU 0LVW &RDW :DOOV Z 6HFRQG )ORRU ,QWHUQDO )LQLVKHV -DQ 0D\ )HE )HE -RLQHU\ G Z G 0DU -DQ )HE /RZHU URRI 'HFN Z 7KLUG )ORRU ,QWHUQDO )LQLVKHV Z G -DQ $SU $SU $SU )ORRU )LQLVKHV Z 0DU 0DU QG )L[ 0 ( Z Z G -DQ 0D\ )HE VW )L[ )) ( ,QWHUQDO )LQLVKHV )HE /RZHU 5RRI 0HPEUDQH DQG ,QVXODWLRQ Z )HE )HE 1DPH 'XUDWLRQ 6WDUW )LQLVK ,QWHUQDO )LQLVKHV Z G -DQ $SU $SU $SU UG )L[ 0 ( -XO\ 0D\ 0DU 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ Z )HE )HE 3ODVWHULQJ 2FWREHU 1RYHPEHU 0DUFK -DQXDU\ $SULO 0D\ -XQH )HEUXDU\ $XJXVW 6HSWHPEHU 0DUFK 2FWREHU 1RYHPEHU $SULO 'HFHPEHU -DQXDU\ )HEUXDU\ 0DUFK $SULO -XQH 0D\ -XQH VW IL[ 3DUWLWLRQV -DQ -DQ )HE 0DU 5DLQZDWHU *RRGV Z 'HFHPEHU $SU $SU 3RZHU 2Q +HDW 2Q VW IL[ 3DUWLWLRQV -DQ -DQ 0DU $SU 6XVSHQGHG &HLOLQJ )LQLVKHV Z )HE 0DU 0LVW &RDW :DOOV WK )ORRU /RZHU 5RRI Z )HE 0DU 0 ( ,QVWDOODWLRQ Z -DQ )HE $SU $SU -RLQHU\ QG )L[ -DQ )HE 0 ( ,QVWDOODWLRQ 0DU 0DU ,QWHUQDO *ODVV 6FUHHQV G 0DU 0DU QG )L[ 0 ( Z )HE )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV 5RRI 3DUDSHWV 2XWOHWV Z )HE )HE $SU $SU ,36 LQVWDOODWLRQ -DQ )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z G 0DU $SU )ORRU )LQLVKHV 0DU 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ Z )HE )HE )LUH 6WRSSLQJ )HE 3ODQW %DVHV DQG XSVWDQGV Z )HE $SU $SU 6DQLWDU\ ,QVWDOODWLRQ -DQ )HE )LUH 6WRSSLQJ $SU $SU UG )L[ 0 ( 0DU 6XVSHQGHG &HLOLQJ )LQLVKHV Z )HE )HE 6XVSHQGHG 0) &HLOLQJV )HE 0DU 'HFN LQVXODWLRQ 6LQJOH 3O\ Z 0DU 0D\ )LQDO )L[ )) ( Z )HE )HE 6XVSHQGHG 0) &HLOLQJV $SU $SU 3RZHU 2Q +HDW 2Q 0DU 0DU ,QWHUQDO *ODVV 6FUHHQV Z )HE )HE -RLQHU\ G 0D\ 0DU 0DU 5DLQZDWHU *RRGV Z $SU $SU &OHDQLQJ DQG 6QDJJLQJ )HE )HE -RLQHU\ $SU $SU -RLQHU\ QG )L[ Z 0DU $SU $SU )ORRU )LQLVKHV Z )HE )HE VW )L[ )) ( 0DU 7HUUDFH )ORRU )LQLVK Z 7KLUG )ORRU ,QWHUQDO )LQLVKHV Z G -DQ $SU )HE )HE VW )L[ )) ( 0DU $SU ,36 LQVWDOODWLRQ Z $SU $SU UG )L[ 0 ( )HE )HE 3ODVWHULQJ 0DU *UHHQ 6HGXP 5RRI Z 0DU ,QWHUQDO )LQLVKHV Z G -DQ $SU )HE 0DU 3ODVWHULQJ $SU $SU 6DQLWDU\ ,QVWDOODWLRQ Z $SU $SU 3RZHU 2Q +HDW 2Q )HE 0DU 0LVW &RDW :DOOV 0DU 0HVK )HQFHOLQH Z 0DU VW IL[ 3DUWLWLRQV -DQ -DQ 0DU 0DU 0LVW &RDW :DOOV $SU )LQDO )L[ )) ( Z $SU $SU -RLQHU\ QG )L[ Z WK )ORRU 8SSHU 5RRI Z )HE 0DU 0DU 0DU QG )L[ 0 ( -DQ )HE 0 ( ,QVWDOODWLRQ 0DU 0DU QG )L[ 0 ( $SU $SU &OHDQLQJ DQG 6QDJJLQJ $SU $SU ,36 LQVWDOODWLRQ Z 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ 8SSHU 5RRI 3DUDSHWV *XWWHUV Z 0DU )HE )HE )RXUWK )ORRU ,QWHUQDO )LQLVKHV Z G -DQ 0D\ -DQ )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z G 0DU 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ $SU $SU 6DQLWDU\ ,QVWDOODWLRQ Z 0DU 6XVSHQGHG &HLOLQJ )LQLVKHV )HE )HE 3ODQW %DVHV DQG XSVWDQGV Z 0DU ,QWHUQDO )LQLVKHV Z G -DQ 0D\ -DQ )HE )LUH 6WRSSLQJ 0DU $SU 6XVSHQGHG &HLOLQJ )LQLVKHV Z 0D\ 0D\ )LQDO )L[ )) ( Z 0DU 0DU ,QWHUQDO *ODVV 6FUHHQV Z 0DU 0DU LQVWDOO URRI SODQW Z )HE )HE 6XVSHQGHG 0) &HLOLQJV 0DU 0DU ,QWHUQDO *ODVV 6FUHHQV G VW IL[ 3DUWLWLRQV -DQ )HE $SU $SU &OHDQLQJ DQG 6QDJJLQJ Z $SU $SU )ORRU )LQLVKHV Z )HE )HE 8SSHU URRI 'HFN LQVXODWLRQ 6LQJOH 3O\ 0HPEUDQH Z )HE )HE -RLQHU\ 7KLUG )ORRU ,QWHUQDO )LQLVKHV Z G -DQ $SU 0DU $SU )ORRU )LQLVKHV )HE )HE 0 ( ,QVWDOODWLRQ Z 0DU $SU $SU UG )L[ 0 ( 0DU 5DLQZDWHU *RRGV Z )HE )HE VW )L[ )) ( ,QWHUQDO )LQLVKHV Z G -DQ $SU $SU $SU UG )L[ 0 ( )HE )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z 0DU $SU $SU 3RZHU 2Q +HDW 2Q 0DU %XLOGLQJ :DWHUWLJKW )HE 0DU 3ODVWHULQJ $SU $SU 3RZHU 2Q +HDW 2Q )HE )LUH 6WRSSLQJ VW IL[ 3DUWLWLRQV Z )HE -DQ -DQ *URXQG )ORRU ,QWHUQDO )LQLVKHV Z -DQ -XQ $SU $SU -RLQHU\ QG )L[ 0DU 0LVW &RDW :DOOV $SU $SU -RLQHU\ QG )L[ )HE )HE 6XVSHQGHG 0) &HLOLQJV -DQ )HE 0 ( ,QVWDOODWLRQ Z 0DU ,QWHUQDO )LQLVKHV Z -DQ -XQ $SU $SU ,36 LQVWDOODWLRQ 0DU 0DU QG )L[ 0 ( 0DU $SU ,36 LQVWDOODWLRQ )HE )HE -RLQHU\ Z )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z G $SU $SU 6DQLWDU\ ,QVWDOODWLRQ VW IL[ 3DUWLWLRQV Z -DQ -DQ -DQ 0DU 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ $SU $SU 6DQLWDU\ ,QVWDOODWLRQ )HE 0DU VW )L[ )) ( Z 0D\ -DQ )HE )LUH 6WRSSLQJ 0D\ )LQDO )L[ )) ( -DQ -DQ 0 ( ,QVWDOODWLRQ Z $SU 6XVSHQGHG &HLOLQJ )LQLVKHV $SU $SU )LQDO )L[ )) ( Z 0DU )HE 0DU 3ODVWHULQJ )HE )HE 6XVSHQGHG 0) &HLOLQJV Z $SU $SU &OHDQLQJ DQG 6QDJJLQJ -DQ )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z 0DU 0DU ,QWHUQDO *ODVV 6FUHHQV G 0DU $SU $SU &OHDQLQJ DQG 6QDJJLQJ 0DU 0LVW &RDW :DOOV Z 7KLUG )ORRU ,QWHUQDO )LQLVKHV Z G -DQ $SU )HE )HE -RLQHU\ -DQ )HE )LUH 6WRSSLQJ Z )RXUWK )ORRU ,QWHUQDO )LQLVKHV Z G -DQ 0D\ 0DU $SU )ORRU )LQLVKHV 0DU 0DU QG )L[ 0 ( ,QWHUQDO )LQLVKHV Z G -DQ $SU )HE )HE VW )L[ )) ( Z )HE -RLQHU\ Z )HE ,QWHUQDO )LQLVKHV Z G -DQ 0D\ $SU $SU UG )L[ 0 ( 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ Z )HE 0DU 3ODVWHULQJ VW IL[ 3DUWLWLRQV -DQ -DQ )HE )HE VW )L[ )) ( Z 0DU $SU $SU 3RZHU 2Q +HDW 2Q VW IL[ 3DUWLWLRQV -DQ )HE 0DU 0DU 6XVSHQGHG &HLOLQJ )LQLVKHV Z 0DU 0LVW &RDW :DOOV -DQ )HE 0 ( ,QVWDOODWLRQ Z 0DU )HE 0DU 3ODVWHULQJ Z $SU $SU -RLQHU\ QG )L[ )HE )HE 0 ( ,QVWDOODWLRQ $SU $SU ,QWHUQDO *ODVV 6FUHHQV G 0DU 0DU QG )L[ 0 ( Z -DQ )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV Z G 0DU 0DU 0LVW &RDW :DOOV G 0DU $SU ,36 LQVWDOODWLRQ )HE )HE &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV $SU $SU Z 0DU )ORRU )LQLVKHV 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ Z -DQ )HE )LUH 6WRSSLQJ 0DU 0DU Z QG )L[ 0 ( $SU 6DQLWDU\ ,QVWDOODWLRQ )HE )HE )LUH 6WRSSLQJ $SU UG )L[ 0 ( 0DU $SU 6XVSHQGHG &HLOLQJ )LQLVKHV Z )HE )HE 6XVSHQGHG 0) &HLOLQJV $SU 'HFRUDWLRQ :RUNV LQF 7LOLQJ Z $SU $SU $SU )LQDO )L[ )) ( Z )HE )HE 6XVSHQGHG 0) &HLOLQJV Z $SU $SU 3RZHU 2Q +HDW 2Q 0DU ,QWHUQDO *ODVV 6FUHHQV G 0DU )HE )HE -RLQHU\ $SU $SU 6XVSHQGHG &HLOLQJ )LQLVKHV Z $SU $SU &OHDQLQJ DQG 6QDJJLQJ )HE )HE -RLQHU\ $SU $SU -RLQHU\ QG )L[ Z 0DU $SU )ORRU )LQLVKHV )HE )HE VW )L[ )) ( $SU $SU ,QWHUQDO *ODVV 6FUHHQV Z )RXUWK )ORRU ,QWHUQDO )LQLVKHV Z G -DQ 0D\ )HE 0DU VW )L[ )) ( $SU $SU ,36 LQVWDOODWLRQ $SU $SU UG )L[ 0 ( Z )HE 0DU 3ODVWHULQJ 0D\ )ORRU )LQLVKHV Z 0D\ ,QWHUQDO )LQLVKHV Z G -DQ 0D\ )HE 0DU 3ODVWHULQJ $SU $SU 6DQLWDU\ ,QVWDOODWLRQ Z 0DU $SU $SU 3RZHU 2Q +HDW 2Q 0DU 0LVW &RDW :DOOV $SU 0D\ UG )L[ 0 ( Z VW IL[ 3DUWLWLRQV -DQ )HE 0DU 0DU 0LVW &RDW :DOOV $SU 0D\ )LQDO )L[ )) ( Z $SU $SU -RLQHU\ QG )L[ Z 0DU 0DU QG )L[ 0 ( $SU $SU 3RZHU 2Q +HDW 2Q )HE )HE 0 ( ,QVWDOODWLRQ 0DU 0DU QG )L[ 0 ( 0D\ 0D\ &OHDQLQJ DQG 6QDJJLQJ Z $SU ,36 LQVWDOODWLRQ 0DU 0DU 'HFRUDWLRQ :RUNV LQF 7LOLQJ Z 0DU $SU $SU -RLQHU\ QG )L[ GRRUV
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
2FWREHU
1RYHPEHU
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
'HFHPEHU
$SU $SU )HE )HE $SU $SU Z 0DU )HE )HE Z 0DU $SU )HE )HE $SU $SU Z G 0DU Z 0DU )HE )HE $SU $SU )HE )HE $SU $SU 0DU Z 0DU )HE )HE $SU 0D\ Z 0DU Z $SU $SU $SU $SU G )HE )HE )HE Z 0D\ )HE 0DU $SU $SU Z $SU Z 0D\ )HE 0DU Z G -DQ 0D\ 0DU $SU $SU G 0DU $SU $SU Z )HE 0DU Z G -DQ 0D\ 0DU Z 0DU $SU $SU $SU $SU 0DU 0DU Z -DQ )HE 0DU Z $SU 0D\ Z $SU $SU 0DU 0DU Z 0DU )HE )HE 0DU 0DU 0D\ Z 0D\ $SU $SU 0DU 0DU )HE )HE $SU $SU Z $SU $SU 0DU Z 0DU Z )HE $SU )HE )HE $SU $SU Z $SU 0D\ Z $SU $SU G Z )HE $SU )HE 0DU $SU $SU Z 0D\ 0D\ $SU $SU Z )HE 0DU Z )HE Z G -DQ 0D\ $SU $SU Z G Z )HE $SU $SU Z 0DU Z 0DU Z G -DQ 0D\ $SU $SU )HE 0DU Z $SU $SU 0DU 0DU Z $SU $SU )HE 0DU Z -DQ )HE $SU Z $SU 0DU 0DU $SU $SU Z $SU Z )HE )HE $SU $SU Z 0DU 0DU $SU $SU G 0DU )HE )HE Z $SU $SU Z G $SU -XQ $SU $SU $SU $SU )HE Z $SU 0D\ Z )HE $SU $SU Z $SU 0D\ Z Z $SU 0D\ )HE 0DU 0D\ Z 0D\ $SU $SU 0D\ 0D\ Z 0D\ 0D\ G )HE 0DU Z G -DQ 0D\ $SU $SU Z G -XQ -XQ Z 0DU Z G -DQ 0D\ 0DU Z Z )HE $SU Z 0D\ -XQ $SU $SU 0DU 0DU Z -DQ )HE Z )HE $SU $SU $SU Z 0D\ 0D\ 0DU 0DU Z )HE )HE $SU $SU Z )HE )HE Z -XQ 0DU 0DU )HE )HE Z 0D\ $SU $SU G )HE 0DU Z Z 0D\ -XQ $SU $SU Z )HE )HE $SU $SU )HE 0DU Z -XQ -XQ $SU $SU Z )HE 0DU $SU 0D\ Z $SU Z $SU $SU Z 0DU )HE 0DU 0D\ Z 0D\ $SU $SU Z G 0DU 0DU Z $SU -XQ Z G 0DU $SU $SU 0DU Z Z )HE $SU Z $SU 0D\ 0DU $SU Z 0DU 'XUDWLRQ 6WDUW )LQLVK Z 'HFHPEHU )HE $SU 0D\ 0D\ G $SU $SU 0DU 0DU Z Z )HE -XQ -XQ $SU $SU G )HE $SU $SU Z Z 0D\ -XQ )HE 0DU Z $SU $SU $SU $SU Z
0DUFK
-DQXDU\ $SULO 0D\
-XQH )HEUXDU\ -XO\
$XJXVW
6HSWHPEHU 0DUFK 2FWREHU 1RYHPEHU $SULO 'HFHPEHU
53
0D\ 0DUFK -DQXDU\ $SULO 0D\ -XQH )HEUXDU\ -XO\ $XJXVW 6HSWHPEHU 0DUFK 1RYHPEHU $SULO 'HFHPEHU -DQXDU\ )HEUXDU\ 0D\ 0DUFK $SULO -XQH -XQH 2FWREHU
Task are in ACTUAL progress: â&#x20AC;¢ Steel frame system â&#x20AC;¢ Internal partitions â&#x20AC;¢ 1st fix M&E â&#x20AC;¢ Insitu frame concrete on roof level â&#x20AC;¢ Lift shaft
-XQH
Task are EXPECTED in progress: â&#x20AC;¢ External envelope (Curtain wall, Corten cladding) â&#x20AC;¢ Lower roof membrane and insulation on 5th floor â&#x20AC;¢ Roof parapets â&#x20AC;¢ 1st fix FF&E â&#x20AC;¢ Joinery â&#x20AC;¢ Plastering â&#x20AC;¢Partitions â&#x20AC;¢Lift shaft
-XQH 0D\
Task are EXPECTED finished: â&#x20AC;¢ Superstructure: Insitu frame concrete â&#x20AC;¢Stair 1 & 2
$SULO
)HEUXDU\ 0D\ 0DUFK
-DQXDU\
The table is an extract from the whole revised programme and according to the programme, the following tasks should be completed or in progress on 13 January 2018.
S UPERSTRUCTURE:
7.2
Final setting out of Roof-Terrace to be confirmed :
of Coping 922
A
B
3562
C
1646
D
1492
310
Ea
E
Eb
4550
1
5- Balustrade System to be confirmed by client 2951 Ec Ed
4452
3599
2279
443.5
2- Terrace Roof System build-up + Thermal performance, Roof Falls, Drainage to be confirmed following details from Roof subcontractor
Roof terrace balustrade guarding as spec ref L30.560
INSITU FRAME CONCRETE 497
INCOMPLETED ROOF SLABS
Detail A - 300 Top of Coping 55.775
3 Detail E - 300
of-Terrace Floor 324
13
SSL 55.024
JT3 .5x35 35 JT3 .5x35 35
Top of Coping Top of Masonry 55.547 55.462
12
GENERAL NOTES
GENERAL NOTES
External Walls Wall Construction - Corten Outer / SFS Inner 30mm Deep Corten Cassettes 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm 6752 SFS Zone, Filled with RW45 Insulation Ee 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns U-Value = 0.18W/m2K
Semi−intensive Green Roof Covering System construction -350mm concrete deck to Structural Engineer's details -3mm vapour control layer - 50 mm thick upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -1.60 tapered insulation zone to form the fall -1.5mm fully-adhered single ply membrane as S45.110A -roof barrier/protection layer(s) -drainage layer, filtration layer, substrate to depth required -80mm semi-intensive green roof covering as Q37.120A U-Value <0.15W/m2K.
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns U-Value = 0.18W/m2K
12
The programme of superstructure should be ended according to the revised programme. However, the work of insitu frame concrete structure is still going on as the roof level has not fully completed. The concrete has been poured on the roof level , but it s not fully dried. Therefore, the steel supporting frame cannot be removed in order to hold the concrete slabs.
Terrace Roof System construction -350mm to 6th floor and 275mm to 5th floorconcrete deck to Structural Engineer's details -3mm vapour control layer -tapered zone for pedestal to allow falls from one side to the other of 1.60 tapered insulation zone to form the fall ( within the pedestal zone) - 50 mm thick upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -1.5mm fully adhered single-ply membrane as S42.110A -50mm Ballast (paving slabs on support) as Q37.140 U-Value <0.15W/m2K.
13
MJ (1 9.200) 54.647
External Curtain Walls Various Systems - refer to windows schedule Drawings CFB 322-324 U-Value = 0.15W/m2K G-value of glass = 0.35
Stair 1 Drawing 310
Top of Coping Top of Masonry 53.447 53.362
X501 COMPUTER SUITE
Detail B - 300
X502 COMPUTER SUITE
Detail I - 300
X508 STAIR 1
X509 STAIR 1 LOBBY
X504 FIFTH FLOOR TERRACE
Second Floor Construction (LRC) -275mm concrete deck to Structural Engineer's details -3mm vapour control layer -50 mm Kooltherm as spec ref M10.290B -75mm screed as spec ref M10.130 - Vinyl floor finish as floor finishes drawings 401-402
14
51 .924 19
15
SSL 51 .624
MJ (1 6.200) 51 .647
13
18 17 16 51 .074
15
Type 2
14
CFB
Type 2 Detail F - 300
13
2945
10 9 8
Type 1
4
X402 COMPUTER SUITE
X408 STAIR 1
6 5
49.374 4
Detail C - 300
X409 STAIR 1 LOBBY
3
X404 SEMINAR ROOM
15
MJ (1 3.275) 48.722
48.694 19 18
Proposed masonryCFB to be built off existing gable - cut bricks to be removed to start new wall New step + cover Flashing to abutment to color match brick as H27 - 440
17 16 47.844
15
Type 2
Type 2
Type 1
13
Type A
12 11
3230
47.1 64
2945
10 9 8 6
X302 COMPUTER SUITE
5
X308 STAIR 1
46.1 44 4
X309 STAIR 1 LOBBY
3 Third Floor 45.590
1
Detail J - 300
X304 SEMINAR ROOM Timber stage platform
2 45.464
15
20
MJ (9.750) 45.1 97
19 18 17 16 44.444
Wall Construction - Brickwork Outer / RC Wall Inner -102.5 Black Brick as F10/110, 50mm cavity -50mm Air Gap with Brick Ties and Support Brackets -150mm Rockwool DuoSlab Rainscreen Insulation -100mm SFS Zone, Filled with RW45 Insulation -200mm thick concrete wall to Structural Engineer's details Exposed concrete finish U-Value = 0.18W/m2K
4
7
X301 COMPUTER SUITE
19200(256 bricks)
3230
23293
14
1
The contractor is aiming to finish the work of superstructure by the end of this week, 17 February. Therefore, the roof structure should be visible in the next visit in March, as the workers and contractor should aim at chasing back the schedule left behind.
Existing Confetti Building
2 1
Ground Floor Construction Solid Concrete Ground Based Floors - Vinyl floor finish as floor finishes drawings 401-402 -75mm screed as spec ref M10.130 - Underfloor Heating Systems refer to M+E Engineer's details -0.5mm separation layer lapped (minimum 150mm) -50mm perimeter Insulation overlap min.150mm from bottom of wall insulation to top of insulation upstand -130mm Kingspan Kooltherm K103 Floor Board insulation under concrete slab as spec ref M10.290A -0.9mm damp proof membrane -275mm thick concrete slab to Structural Engineer's details -well compacted sub base to Structural Engineer's details U-Value = 0.11W/m2K
16
7
X401 COMPUTER SUITE
Floors Construction (1st, 3rd, 4th, 5th) -275mm concrete deck to Structural Engineer's details -10mm latex levelling screed - Vinyl floor finish as floor finishes drawings 401-402
11
3230
3230
50.394
15
Detail L - 300
12
Type A
rth Floor 694
Type 2
15
Type 2
CFB
Type 1
14
Type 1 Type A
16200(216 bricks)
11
3400
43.764
2949
3234
12 10 9 8
X208 STAIR 1
6 5
42.744
X209 STAIR 1 LOBBY
4
X204 SEMINAR ROOM 13275(177 bricks)
7
X201 LRC Detail D - 300
3 2 1
14
Second Floor CONFETTI 41 .820
42.064
42.064
MJ (6.525 41 .972
41 .964
20 19 18
41 .074
Ground Floor 41 .820
Type 2
15
Type 2
9750(130 bricks)
7
Detail H - 300
Detail K - 300
X108 STAIR 1
6
Timber stage platform
5
39.424
X109 STAIR 1 LOBBY
4
X104 SEMINAR ROOM
12/05/17 Amendments to drawings following the Topo Survey and SE info 23/01/17 Stair 1 amended 10/01/17 Spec Refs added 23/12/16 Amendments to drawings
REV. DATE
MLD MLD MLD MLD MLD
DESCRIPTION
BY
3 2 1
38.764
38.764 20
38.568
19
First Floor Confetti 38.360
MJ (2.997) 38.297
18 17 16 37.774
Type 2
15
14
Type 2
6525(87 bricks)
X101 CAFE First Floor HE 39.060
11
3300
2897
3300
40.41 4 9 8
MLD MLD MLD MLD
C B A
13
10
28/02/18 Change to RoofTerrace Structure, internal partitions, external wall build-up 22/01/18 MJ, CFB, Bricks setting out and downpipe position added 10/11/17 Change to RoofTerrace external wall and roof build-up 25/10/17 Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1 30/05/17 Drawing status updated to construction
D
Type 1
14 12
I H G F E
CFB
17 16
Refer to GA Floor Plan drawings (2588 201-207)
Type 2
13
Second Floor HE ond Floor 42.320 230 42.200
Ground Floor 38.360
Architects, Landscape & Interior Design
Type 2
1 6-20 Bath Street, Nottingham NG1 1 DF
13 11
3300
37.1 1 4 10
2700
2850(38 bricks)
12
3300
3300
t Floor 930
3
Detail G - 300
h Floor 924
rd Floor 464
Type 2
Type A
2750
3400
Type 2
9 8 7
X101 RECEPTION
Detail O - 301
X008 STAIR 1
6 5
36.1 24
X009 STAIR 1 LOBBY
4
X005 WC LOBBY
X007 WC CHANGING (FEMALE WC)
X013 CONTROL ROOM
T
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
F
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group
3
ound Floor Ground Floor HE 630 35.630
2
16
35.440
1
Ground Floor 35.464
35.464
Level (0.00) 35.447
PROJECT
Confetti CQ Campus
Ground Floor 35.048
SSL 34.985
Ground Floor 34.770
Ground Floor Confetti 34.740
DRAWING
GA Section AA
Lower Ground Floor 32.800
2279
A
3562
B
1646
C
1492
D
4550
E
Ea
4452
Eb
2951
Ec
6752
Ed
Ed
PROJECT NUMBER
SCALE
DATE
2588
1:50 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
220
I
Construction MLD
This drawing is copyright and remains the property ofAllan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
54
S UPERSTRUCTURE:
7.3
Key Walls
Ea
Eb
310
E
Ec
External Walls BENCHMARK Quadcore Karrier Panel + Corten Recess Fixed Cassette -35mm Benchmark Corten Recessed Fix Cassette as H43.125 -100mm Benchmark Quadcore Karrier Panel fixed with a minimum of 2 Nr fasteners per panel per rail as H43.121 Ee -100 mm Infill SFS fixed to the structure -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value = 0.18W/m2K
3234
1
Roof terrace balustrade guarding as spec ref L30.560
Ed
KINGSPAN Quadcore Karrier Panel + Brick Tie System -102.5 Black Brick as spec ref F10.110 -50mm cavity -125mm Brick Ties spaced generaly every 3 bricks, and fixed back to the Quadcore Karrier Panel as spec ref F30.220 -100mm Benchmark Quadcore Karrier Panel as H43.121 -100 mm Infill Structural Rails fixed to the structure -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value = 0.18W/m2K
3 Detail E - 300
13
12
Stair 1 Drawing 310
Detail G - 300
W 02 X508 STAIR 1
15
GENERAL NOTES
Semi−intensive Green Roof Covering System construction -350mm concrete deck to Structural Engineer's details -50mm screed to falls as spec ref M10.110 -3mm vapour control layer - 25 mm thick Kingspan Thermaroof TR27 LPC/FM upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -150 mm Kingspan Thermaroof TR27 LPC/FM -1.5mm fully-adhered single ply membrane as S45.110A -roof barrier/protection layer(s) -drainage layer, filtration layer, substrate to depth required -80mm semi-intensive green roof covering as Q37.120A U-Value <0.15W/m2K.
12
Terrace Roof System construction -350mm to 6th floor and 275mm to 5th floorconcrete deck to Structural Engineer's details -50mm screed to falls as spec ref M10.110 -3mm vapour control layer -150 mmKingspan Thermaroof TR27 LPC/FM - 25 mm thick Kingspan Thermaroof TR27 LPC/FM upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -1.5mm fully adhered single-ply membrane as S42.110A -50mm Ballast (paving slabs on support) as Q37.140 U-Value <0.15W/m2K.
13
Stair 1 acts as the main staircase that students can access from Covent Street. It runs through all the levels,except to the roof. External Curtain Walls Various Systems - refer to windows schedule Drawings 322-324 U-Value = 0.15W/m2K G-value of glass = 0.35
3
X502 COMPUTER SUITE
S TA I R 1
GENERAL NOTES
X509 STAIR 1 LOBBY
Detail I - 300
X504 FIFTH FLOOR TERRACE
19 17 16 15
Detail F - 300
14 13
Second Floor Construction (LRC) -275mm concrete deck to Structural Engineer's details -3mm vapour control layer -50 mm Kooltherm as spec ref M10.290B -75mm screed as spec ref M10.130 - Vinyl floor finish as floor finishes drawings 401-402
14
According to the contractor, the concrete stair 1 was installed in 23 January and it is now visible on site. 13
18
Detail L - 300
Floors Construction (1st, 3rd, 4th, 5th) -275mm concrete deck to Structural Engineer's details -10mm latex levelling screed - Vinyl floor finish as floor finishes drawings 401-402
15
12
3230
11 10 9
Components of the staircase are delivered on site and lifted by the crane to assemble the whole staircase in the void of the structure.
4
8 7
X402 COMPUTER SUITE
X408 STAIR 1
6 5
X409 STAIR 1 LOBBY
4 3
Timber stage platform
2 1
15
19 18 16 15 14 13 12
3230
11 10 9 8
X302 COMPUTER SUITE
6
X308 STAIR 1
4
X309 STAIR 1 LOBBY
3 1 20 19 18 17 16 15 14 13 12
3400
11 10 9
KINGSPAN Quadcore Karrier Panel + Brick Tie System -102.5 Black Brick as spec ref F10.110 -50mm cavity -125mm Brick Ties spaced generaly every 3 bricks, and fixed back to the Quadcore Karrier Panel as spec ref F30.220 -100mm Benchmark Quadcore Karrier Panel as H43.121 -50 mm Infill Structural Rails fixed to the structure -200mm thick concrete wall to Structural Engineer's details -12.5mm 'Gyproc Wallboard' plasterboard as spec ref K10.165A with 2.5mm 'Thistle Multifinish' plaster skim U-Value = 0.18W/m2K
4
X304 SEMINAR ROOM
2
15
Staircase 1 was originally scheduled to complete by November, but it is only installed by January. This is not only due to the domino effects of the delay of other tasks in the construction programme, but also because of the concrete manufacturer postponing the production of the stair as well as the delivery. This shows the manufacturer of building elements affects the progress the whole construction progress. Detail J - 300
7 5
Ground Floor Construction Solid Concrete Ground Based Floors - Vinyl floor finish as floor finishes drawings 401-402 -75mm screed as spec ref M10.130 - Underfloor Heating Systems refer to M+E Engineer's details -0.5mm separation layer lapped (minimum 150mm) -50mm perimeter Insulation overlap min.150mm from bottom of wall insulation to top of insulation upstand -130mm Kingspan Kooltherm K103 Floor Board insulation under concrete slab as spec ref M10.290A -0.9mm damp proof membrane -275mm thick concrete slab to Structural Engineer's details -well compacted sub base to Structural Engineer's details U-Value = 0.11W/m2K
16
Existing Confetti Building
Proposed masonry to be built off existing gable - cut bricks to be removed to start new wall New step + cover Flashing to abutment to color match brick as H27 - 440
17
W 09
W 14
X404 SEMINAR ROOM
8
X208 STAIR 1
7 6 5
X209 STAIR 1 LOBBY
4
X204 SEMINAR ROOM
W 06
3 2
Ground Floor 42.064
1
14
Ground Floor 41.964
20
Ground Floor 41.820
19 18 17 16
E
30/05/17 Drawing status updated to construction
MLD
D
12/05/17 Amendments to drawings following the Topo Survey and SE info 23/01/17 Stair 1 amended 10/01/17 Spec Refs added 23/12/16 Amendments to drawings
MLD
15 14
C B A
13 12
3300
11 10 9
REV. DATE
8 7
X108 STAIR 1
6 5
X109 STAIR 1 LOBBY
4
MLD MLD MLD
DESCRIPTION
BY
X104 SEMINAR ROOM
3 2
Ground Floor 38.764
1
Ground Floor 38.568
20 19
Ground Floor 38.360
18
Architects, Landscape & Interior Design
17 16 15
16-20 Bath Street, Nottingham NG1 1DF
14 13 12
3300
11 10 9
W 03
8 7 6
ED 02
5
X008 STAIR 1
X009 STAIR 1 LOBBY
4
X005 WC LOBBY
X007 WC CHANGING (FEMALE WC)
16
E
design@allanjoycearchitects .co.uk
0115 950 7161
W
www.allanjoycearchitects .co.uk
Confetti Media Group INSITU FRAME STRUCTURE PROJECT
Ground Floor 35.464
1
0115 841 8418
F
CLIENT
X013 CONTROL ROOM
3 2
T
Ground Floor 35.048
Confetti CQ Campus
Air Seal - Gun grade sealant at male joint
Air seal - Continuous bead of gun grade sealant
Ground Floor 34.770
DRAWING
GA Section AA
E
Ea
Eb
Ec
Ed
Ee
PROJECT NUMBER
SCALE
2588
1:50 @ A1
DATE
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
220
E
Construction MLD
This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
55
The project team has an argument with the pre -cast concrete supplier in terms of the quality of the finishes. As the supplier offers 2 types of finishes in the August 2017, the fair-faced finish and the raw finished. The project team wanted to have the fair-faced finish to matches the visual appearance of the wall and floors. However, due to the budget the supplier only offered them the raw finish as the fair-faced finish cost additional fare. Given that the manufacturer has abundant of time, the quality of the concrete staircase should be acceptable. However, the quality of the raw finishes is not up to the expectation of the project team, as the quality of the insitu concrete finishes on site looks even better then the pre-cast staircase concrete.
FAIR-FACED FINISHING
In additional with the interior lighting on walls added on later in the programme, the imperfection of the concrete will be shown clearly in comparison with the fair-faced wall. Therefore, they need to bring in a specialist concrete finisher to solve the aesthetic issue. Further information about concrete finishes will be discussed in Chapter 9.
RAW FINISHING ON INSITU CONCRETE
RAW FINISHING ON PRE-CAST CONCRETE
56
S UPERSTRUCTURE:
7.4
S TA I R 2
Dimension TBC
Dimension TBC Ee
C105 CH 3 .02
beam
STN/129 39 .72
downstand
FFL 40 .30
deep wide x 550
.90 SCH 4
W 06 300
38 .22
300
38 .23
F 300
E
E
HH 2 .87 SH 0.80
D
Ea
D 301
.33 SCH 4
C
C 222
HH 2 .87 SH 0.80
B
38 .26
HH 2 .99 SH 0.79
U/S 1.39
Eb
A
Fifth Floor 51.924
TA 2 .89 SH 0.81
Ed Ec
W 02
Electrical riser
W 07
Ed
void
Mechanical riser
7
8
9
10
11
12
13
14
15
16
17
18
19
W 08
20
B 221
6
221 B
X102 KITCHEN 12 m2
ID 110
W 01 5
beam
B C
3
X105 COMPUTER SUITE 51 m2
ID 108
X114 NEW RAISED COURTYARD
downstand
X103 CAFE SERVERY 38 m2
Win/A SH 2.04
x 550 deep 300 wide
ID 109
Ec Eb
4
U/S 2.58
SH 0.81 HH 2 .93
CH 3 .01
220
A
B 221
SH 0.81 HH 2 .93 U/S 2.58
CH 3 .01
SH 0.81 HH 2 .93 SH 0.81 HH 2 .93
U/S 2.93
CH 2 .49
CH 3 .07
SH 0.81 HH 2 .93
CH 3 .01 U/S 2.58
CH 3 .01
SH 0.81 HH 2 .93
U/S 2.93
CH 3 .01
SH 0.81 HH 2 .93
U/S 2.57
U/S 2.96
SH 0.81 HH 2 .93
U/S 2.93
CH 2 .49
SH 0.81 HH 2 .93
CH 3 .01 U/S 2.58
CH 3 .01
SH 0.79 HH 2 .88
SH 0.81 HH 2 .93
U/S 2.93
CH 3 .01
CH 3 .01
HH 2 .83 SH 0.73
STN/1 34 .68
DH 2 .05
First Floor HE 39.060
FFL 39 .05
CH 3 .16
U/S 2.26
FFL 39 .04
DH 2 .05
STN/148 39 .03
CH 3 .00
door blocked
CH 4 .85
DH 1 .98
No access
CH 3 .02
CH 3 .01
U/S 2.96
FFL
39 .03
Col
SH 0.81 HH 2 .93
CH 3 .07 U/S 2.57
SH 0.95 HH 2 .17
SH 0.82 HH 2 .95 CH 3 .03
SH 0.81 HH 2 .93
CH 3 .01
U/S 2.58
SH 0.79 HH 2 .88
SH 0.81 HH 2 .93
SH 0.95 HH 2 .17
U/S 2.58
SH 0.82 HH 2 .95 CH 3 .03
A
220
B 221
SH 0.82 HH 2 .95
CH 3 .03
CH 3 .03
U/S 2.58
SH 0.82 HH 2 .95 CH 3 .03 SH 0.82 HH 2 .95 SH 0.79 HH 2 .95
CH 3 .16
Col
STN/147 39 .01
HH 2 .83 SH 0.73
door blocked
CH 4 .85
Col
H105 .60 SCH 2
HH 2 .83 SH 0.73
HH 2 .83 SH 0.73
DH 1 .98
DH 2 .05
U/S 2.59
221 B
Ee
No access
FFL 39 .05
U/S 2.26
FFL 39 .04
DH 2 .05
STN/148 39 .03
CH 3 .00
CH 3 .01
CH 3 .02
SH 0.79 HH 2 .95
beam
CH 3 .03
SH 0.81 HH 2 .93
CH 3 .01
downstand
U/S 2.96
Win/A SH 2.04
x 550 deep 300 wide
SH 0.82 HH 2 .95
CH 2 .49
CH 3 .07
SH 0.81 HH 2 .93
U/S 2.93
U/S 2.57
CH 3 .01
CH 3 .03 CH 3 .03 SH 0.82 HH 2 .95
SH 0.79 HH 2 .88
SH 0.88 TA 2 .95
SH 0.79 HH 2 .95
HH 1 .92 SH 1.09
SH 0.87 TA 2 .94
FFL 38 .23
U/S 2.59
C105 CH 3 .02
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
SH 0.79 HH 2 .95
38 .26
SH 0.90 HH 2 .53
FFL 38 .36
DH 2 .00 Win/A SH 2.05 HH 2 .53
DH 2 .02
SH 0.86 TA 2 .94
STN/109 38 .27
38 .27
FFL 38 .23
CH 3 .01
H104
CH 3 .01
.56 SCH 2
CH 3 .01
Ceil 40 .88
DH 2 .05
Col
G
First Floor Confetti 38.360
DH 2 .05
First Floor Confetti 38.360
U/S 2.56
HH 2 .83 SH 0.73
DH 2 .02
Col
HH 2 .78 SH 0.68
HH 2 .83 SH 0.73
First Floor 38.930
FFL
STN/147 39 .01
HH 2 .83 SH 0.73
FFL 39 .06
First Floor HE 39.060
38 .28 SH 0.91 HH 1 .96
HH 2 .83 SH 0.73
39 .04
FFL
SP 1 .37
X HH 2 .78 SH 0.68
DH 1 .96
H104
.56 SCH 2
CH 3 .01
DH 2 .05
TA 2 .23
CH 2 .99
CH 3 .06
Demolish existing walls, roofs and floors to form lift shaft
U/S 2.71
U/S 2.71
U/S 2.78
Floor Slope 38 .31
Col
Col
SP 1 .37
H102
U/S 2.81
A
U/S 2.71
U/S 2.71
U/S 2.71
U/S 2.78
FFL 39 .01
CH 2 .99
SP 1 .37
FFL 39 .07
U/S 2.78
220
FFL 39 .01
Col
HH 2 .83 SH 0.73
B C
X114 NEW RAISED COURTYARD
H
U/S 2.71
X
DH 1 .95
H103
Col
U/S 2.78
U/S 2.78
U/S 2.81
H
DH 2 .06
STN/146 39 .07
FFL 39 .06
CH 2 .99
TA 2 .23
U/S 2.78
B C
Stripping out
G
U/S 2.71
U/S 2.71
Col
SP 1 .37
DH 2 .04
Remove infill section of brickwork to reinstate original opening size
First Floor HE 39.060
F
39 .04
Second Floor CONFETTI 41.820
G
E
FFL
F
.61 SCH 2
D
CH 2 .99
E
SP 1 .45
CH 3 .06
Demolition
.58 SCH 2
X
D
H101 .62 SCH 2
X
C
Col
C
DH 2 .05
H103
.61 SCH 2
TA 2 .27
FFL 39 .04
FFL 39 .08
STN/143 39 .04
X
B
1in12
ID 113
CH 2 .99
1in12
ID 113
B
222 A
Remove existing shelving
Form new openings through to new building
A
U/S 2.71
DH 2 .06
21
21
FFL 39 .06
20
20
SP 1 .37
19
19
FFL 39 .07
18
18
CH 3 .06
17
C
17
SP 1 .37
Form new openings through to new building
Second Floor HE Second Floor 42.320 42.230 42.200
U/S 2.71
Col
16
A
UP 130
16
C
TA 2 .23
Demolish existing stair Second Floor HE 42.320
Ee
SP 1 .45
15
X111 STAIR 2 LOBBY CH 3 .03
ID 114
15
UP 130
SP 1 .37
Wheelchair Refuge
X110 STAIR 2
W 08
Lift
ID 111 Wheelchair Refuge
STN/146 39 .07
1
X102 KITCHEN 12 m2
ID 112
X112 clnrs cpbd
FFL 39 .06
2
Mechanical riser
ID 110
20
CH 2 .99
3
19
X111 STAIR 2 LOBBY
TA 2 .23
4
18
SP 1 .37
5
17
SP 1 .45
6
16
CH 3 .06
X102 KITCHEN 12 m2 W 08
ID 111 7
15
TA 2 .27
X105 COMPUTER SUITE 51 m2
ID 108
ID 112
Lift
14
FFL 39 .08
Ec
X103 CAFE SERVERY 38 m2 Mechanical riser
ID 110
42.670
20
13
SP 1 .45
19
12
H102
18
11
1
X110 STAIR 2
.58 SCH 2
17
10
2
DH 2 .04
16
9
3
H101 .62 SCH 2
15
8
4
FFL 39 .04
14
7
5
STN/143 39 .04
13
6
6
CH 3 .03
12
221 B
11
5
7
CH 3 .26
SH 0.87 TA 2 .94
10
beam
9
downstand
8
4
222
X114 NEW RAISED COURTYARD
Win/A SH 2.04
STN/1 34 .68
7
3
8
A
x 550 deep 300 wide
Ed
6
2
ID 114
W 07
ID 109
Eb Ea
5
X112 clnrs cpbd 8
1
SH 0.88 TA 2 .95
Electrical riser
4
Second Floor CONFETTI 41.820
void W 01
ED 15
ED 16
X105 COMPUTER SUITE 51 m2
ID 108
4
A
1in15
STN/110 38 .23
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
SH 0.90 HH 2 .53
FFL 38 .36
DH 2 .00 Win/A SH 2.05 HH 2 .53
DH 2 .02
SH 0.86 TA 2 .94
STN/109 38 .27
38 .27
FFL 38 .23
FFL 38 .23 Ceil 40 .88
DH 2 .02
FFL
38 .28 SH 0.91 HH 1 .96
DH 1 .96
DH 1 .95
ID 107
B C
3
ED 16
X
1in15
3a
void W 01 4
U/S
Floor Slope 38 .31
A
IS 101
B C
3
3
220
STN/108 38 .36
FFL
39 .03
X
1
1in15
2
CH 3 .26
38 .24
38 .21
Col
2a
W 04
1
STN/110 38 .23
Ceil 41 .10
Col
H105 .60 SCH 2
1in15
Ed
ED 15
U/S 2.94
W 07
ID 109
ID 102 2
3
4
2
Remove infill section of brickwork to reinstate original opening size A
U/S 2.94
41 .09
U/S level 41 .06
Wall 1 .29h
DH 2 .05
ID 105
U/S 2.01
40 .89 Ceil
ID 106
U/S 2.01
40 .89 Ceil
ID 106
U/S
C105 CH 3 .02
FFL 39 .05
CH 3 .16
DH 2 .05
FFL 39 .04
ID 101
X101 CAFE 155 m2
UP 570
ID 107
Electrical riser
Ec Eb
X103 CAFE SERVERY 38 m2
UP
570
41 .09
38 .26
HH 2 .99 SH 0.79
STN/129 39 .72
FFL 40 .30
.90 SCH 4
38 .23
HH 2 .87 SH 0.80
.33 SCH 4
38 .22
HH 2 .87 SH 0.80
door blocked
CH 4 .85
DH 1 .98
No access
U/S 2.26
STN/148 39 .03
CH 3 .00
CH 3 .01
CH 3 .02
beam
U/S level 41 .06
TA 2 .89 SH 0.81
CH 3 .01
downstand
X109 STAIR 1 LOBBY
1in15
1in15
Ea
STN/129 39 .72
DH 2 .05
deep wide x 550
X104 SEMINAR ROOM 30 m2
ID 104 ID 103
19 20
5
1
IS 101
3a
.90 SCH 4
Col
HH 2 .83 SH 0.73
18
6
ID 102 2
3
4
2a
FFL 40 .30
STN/147 39 .01
17
8 7
ID 105
38 .23
HH 2 .83 SH 0.73
HH 2 .83 SH 0.73
X106 FEMALE WC
16
X108 STAIR 1
9
X101 CAFE 155 m2 W 04
2
HH 2 .87 SH 0.80
CH 3 .01
H104
.56 SCH 2
W 06 300
X107 ACCESSIBLE WC 15
10
X109 STAIR 1 LOBBY
STN/108 38 .36
Col
300
W 02 11
1a
ID 103
38 .21
HH 2 .83 SH 0.73
FFL 39 .06
HH 2 .83 SH 0.73
F 300
E
E
Strip out all existing remaining WC sanitaryware , cubicles, finishes, etc
Third Floor 45.590
Ceil 41 .10
SP 1 .37
39 .04
FFL
FFL 39 .07
U/S 1.39
D
Ea
D 301
Third Floor 45.464
38 .24
DH 2 .05
CH 2 .99
TA 2 .23
CH 3 .06
Ec
C
C 222
beam
19
ID 101
Form new openings through to new building
Third Floor 45.590
downstand
X104 SEMINAR ROOM 30 m2
ID 104
20
5
Eb
B
W 05
18
6
X A
X108 STAIR 1
8 7
Ee
U/S 2.56
CH 3 .01
17 10 9
Ed
1
X106 FEMALE WC
Wall 1 .29h
Col
SP 1 .37
U/S 2.71
deep wide x 550
38 .22
W 06 300
X107 ACCESSIBLE WC
1
HH 2 .78 SH 0.68
X
300
11
16
U/S 2.71
HH 2 .83 SH 0.73
F 300
E
E
W 02
X
U/S 2.78
Second Floor HE 42.320
D
15
Demolish existing wall, remove existing windows and concrete lintel and rebuild the top section of the arch HH 2 .83 SH 0.73
D 301
1a
B C Demolish existing wall
Strip out all existing remaining WC sanitaryware , cubicles, finishes, etc
C
C 222
W 05
U/S 2.71
HH 2 .87 SH 0.80
FFL 39 .01
SP 1 .37
H102
.58 SCH 2
U/S 2.78
HH 2 .99 SH 0.79
U/S 1.39
B
Demolish existing wall
Demolish existing wall and remove and retain existing door for re-use elsewhere
U/S 2.81
Third Floor 45.590
Stair 2 is designed to serve as a fire escape route to the building. As the new design of the building connected the existing HEC building, the staircase of the original HEC building cannot hold the increasing amount of users. Also, as the old staircase is made by timber and narrow, it does not meet the fire regulation. Ee
Ed Ec Eb
A
Ea
DH 2 .06
STN/146 39 .07
FFL 39 .06
CH 2 .99
CH 2 .99
TA 2 .23
U/S 2.78
Fourth Floor 48.694
H
.33 SCH 4
G
U/S 2.71
Col
SP 1 .37
DH 2 .04
X
H103
SP 1 .45
CH 3 .06
F
TA 2 .89 SH 0.81
.61 SCH 2
U/S 2.58
Col
Demolish existing flat roof
TA 2 .27
FFL 39 .08
E
H101 .62 SCH 2
m new openings ough to new ding
Remove existing ceiling structure
Ee
U/S 2.71
SP 1 .45
SH 0.82 HH 2 .95
UP 130 1in12
ID 113
FFL 39 .04
D
SH 0.79 HH 2 .95
Wheelchair Refuge
X111 STAIR 2 LOBBY
STN/143 39 .04
C
U/S 2.59
1
SH 0.81 HH 2 .93
2
U/S 2.58
3
21
CH 3 .01
4
20
SH 0.81 HH 2 .93
5
19
CH 3 .03
18
SH 0.81 HH 2 .93
SH 0.95 HH 2 .17
6
ID 114 17
U/S 2.93
7
X110 STAIR 2
16
B
A
Lift
ID 111 8
15
C 222
A
SH 0.79 HH 2 .95
X112 clnrs cpbd
CH 3 .03
SH 0.82 HH 2 .95
ID 112
A
Col
H105 .60 SCH 2 Col
223 FCB
FFL
39 .03
U/S 2.56
CH 3 .01
HH 2 .83 SH 0.73
HH 2 .83 SH 0.73
Infilling opening
X
The old staircase in the HEC building will be demolished and replaced by the new concrete staircase that the design proposed. Fire alarm, light fixings and fire resistance materials will be used to assist the function of Stair 2.
HH 2 .83 SH 0.73
STN/1 34 .68
Remove existing glass screen Demolish existing steps
HH 2 .83 SH 0.73
Ground Floor HE 35.440
Form new openings through to new building
Ground Floor HE 35.440
Demolition Ground Floor Ground Floor HE 35.630 35.630 35.440
A
Ground Floor Confetti 34.740
Ground Floor Confetti 34.740
Lower Ground Floor 32.800
Lower Ground Floor 32.800
Lower Ground Floor 32.700
B
1646
C
C 222
Infilling opening
D 301
6900
Stripping out
D
1492
SECTION AA
DEMOLISHING Infilling opening
E
12868
1768
4200
1a
Lobbies have been added to each floors to ensure additional fire and smoke protection. This also applies on Stair 1 and confirmed that both stairs can stay in play in the event of a fire.
Roof-Terrace Floor 55.324
A
2a
IS 405A
1
Third Floor 45.590
Third Floor 45.464
Third Floor 45.464
Third Floor 45.590
13/06/17 Construction Issue REV. DATE
45.464
MLD
DESCRIPTION
5600
BY
IS 404
PROJECT
T
0115 841 8418
Demolition and Proposed construction work F 0115 950 7161 in the HEC CLIENT
PROJECT NUMBER
SCALE
2588
1:100 @ A1
DRAWING NUMBER
REVISION
315
A
Ground Floor Confetti 34.740
STATUS
E
design@allanjoycearchitects .co.uk
W
www.allanjoycearchitects .co.uk
DATE
Confetti Media Group May-17
Ground Floor 35.630
PROJECT
9020
0115 841 8418
F
0115 950 7161
E
design@allanjoycearchitects .co.uk
W
www.allanjoycearchitects .co.uk
311
CLIENT
First Floor Confetti 38.360
11
12
13
14
15
16
17
18
7
Confetti CQ Campus
35.630
6
5
4
3
2
NEW DESIGN
Lower Ground Floor 32.800
Generally do not scale drawings. All dimensions to be checked on site. DRAWING
Demolition and Proposed construction work in the HEC DATE
SCALE
1:100 @ A1
May-17
DRAWING NUMBER
REVISION
STATUS
BY
315
A
Construction MLD
30.000
SECTION AA
Type 1
X413 STAIR 2 LOBBY
4 MJ
9216
MJ
DRAWING
105 370
Demolition and Proposed construction work in the HEC PROJECT NUMBER
SCALE
DATE
2588
1:100 @ A1
May-17
DRAWING NUMBER
REVISION
STATUS
BY
315
A
Construction MLD
1200
495
105
2065
Lift
This drawing is copyright and remains the property of Allan Joyce Architects Ltd
57 G
Generally do not scale drawings. All dimensions to be checked on site.
This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
Fourth Floor 48.694
1
Ground Floor Confetti 34.740
Lower Ground Floor 32.700
Type 1
X412 STAIR 2
W 01
Wheelchair Refuge
PROJECT4
35.440
660
19
Confetti Media Group
37.917
BY
PROJECT NUMBER SECTION CC 2588
T
39.060
Ground Floor Ground Floor HE 35.630 35.630
Ground Floor HE 35.440
This drawing is copyright and remains the property of Allan Joyce Architects Ltd
ON WORK IN THE HEC
First Floor HE 39.060
35.957
Construction MLD Confetti CQ Campus
Lower Ground Floor 32.800
Lower Ground Floor 32.700
First Floor 38.930
9020
Ground Floor 35.630
Ground Floor HE 35.440
First Floor HE 39.060
16-20 Bath Street, Nottingham NG1 1DF
First Floor Confetti 38.360
DRAWING
Architects, Landscape & Interior Design
ID 413
1800
First Floor 38.930
1200
16-20 Bath Street, Nottingham NG1 1DF
40.690
Ea
1868
105
First Floor 38.930
Architects, Landscape & Interior Design
B
Confetti CQ Campus First Floor HE 39.060
3
42.320
Second Floor CONFETTI 41.820
NB: All filled openings and areas where structures have been removed to be plastered to match adjacent walls. Skim the whole area prior to decoration
300
261
Second Floor HE Second Floor 42.320 42.230 42.200
Second Floor CONFETTI 41.820
2885 100
Second Floor HE 42.320
Second Floor 42.230
Confetti Media Group
ID 414
2455
W 12
1010
BY
42.670
X411 CORRIDOR
Type 1
1010
CLIENT
DESCRIPTION
43.975
1560
www.allanjoycearchitects .co.uk REV. DATE
1500
W
MLD
2388
0115 950 7161
13/06/17 Construction Issue
521
F
A
2100
design@allanjoycearchitects .co.uk
221
Second Floor 42.230
E
2950
Second Floor HE 42.320
0115 841 8418
269
3a
16-20 Bath Street, Nottingham NG1 1DF T
ID 415
1500
Type 1*
1555
Details of lift shaft and new section of flat roof to be agreed
Fourth Floor 48.694
A
Architects, Landscape & Interior Design
Third Floor 45.464
IS 401
3000
Fourth Floor 48.694
C 222
2279
A
B
X408 STAIR 1
Type A
2
BY
4350
6
1930
Fourth Floor 48.694
Third Floor 45.590
X401 COMPUTER SUITE 51 m2
3554
DESCRIPTION
W 02 11
5
MLD 2655
13/06/17 Construction Issue REV. DATE
7
1361
2655
A
Fifth Floor 51.924
9900 220
Fifth Floor 51.924
8
X402 COMPUTER SUITE 49 m2
3650
All Construction TBC
Dimension TBC
Fifth Floor 51.924
9
4742
Roof-Terrace Floor 55.324
All Construction TBC
Dimension TBC
3160
10
310
W 15
All Construction TBC
4550
W 16
30.000
1
Roof-Terrace Floor 55.324
e ng out Lin Bricks Setti
330
890
SECTION CC
C
3562
Ea
Stripping out
Demolition Lower Ground Floor 32.700
2279
105
HH 2 .83 SH 0.73
4642
A
SH 0.88 TA 2 .95
SH 0.87 TA 2 .94
FFL 38 .23 Ceil 40 .88
220
HH 1 .92 SH 1.09
DH 1 .95
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
U/S
SH 0.90 HH 2 .53
FFL 38 .36
DH 2 .00 Win/A SH 2.05 HH 2 .53
DH 2 .02
SH 0.86 TA 2 .94
STN/109 38 .27
New lift shaft shown dotted
ID 107
1in15
4
ED 15 ED 16
1in15
New lift shaft shown dotted
Ea
3
38 .27
1
IS 101
3a
2
Remove existing roof to allow new brickwork to sit on existing
ID 102 2
3
4
2a
W 04
2
1
U/S 2.01
40 .89 Ceil
ID 106
FFL 38 .23
UP 570 1in15
DH 2 .02
ID 105
FFL
38 .28 SH 0.91 HH 1 .96
ID 101
STN/108 38 .36
X109 STAIR 1 LOBBY
5
DH 1 .96
Floor Slope 38 .31
A
ID 103
19 20
6
220
18
38 .21
8 7
CH 3 .26
X108 STAIR 1
9
38 .24
17 10
X101 CAFE 155 m2
STN/110 38 .23
1
U/S 2.94
41 .09
X104 SEMINAR ROOM 30 m2
ID 104
Ceil 41 .10
X106 FEMALE WC
16
Wall 1 .29h
X107 ACCESSIBLE WC 15
HH 1 .92 SH 1.09
11
1a
p out all existing maining WC itaryware , cubicles, shes, etc
U/S level 41 .06
W 05
223 3562
1646
C
1492
D
7718
E
4
3
2
ED 09 Ee
TA 2 .89 SH 0.81
Ed
U/S 1.39
C105 CH 3 .02
143
FFL
40 .30
W 14
.33 SCH 4
38 .22
HH 2 .87 SH 0.80
300
W 09
STN/129 39 .72
F 300
E
E
.90 SCH 4
D
Ea D 301
38 .23
C
C 222
HH 2 .87 SH 0.80
B
38 .26
HH 2 .99 SH 0.79
Ec Eb A
W 02
W 13 HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
DH 1 .95
HH 1 .92 SH 1.09
HH 1 .92 SH 1.09
U/S 2.94
U/S 41 .09
SH 0.88 TA 2 .95
SH 0.87 TA 2 .94
FFL 38 .23 Ceil 40 .88
U/S 2.01
STN/108 38 .36
FFL
SH 0.90 HH 2 .53
38 .36
DH 2 .00 Win/A SH 2.05 HH 2 .53
DH 2 .02
40 .89 Ceil
SH 0.86 TA 2 .94
5
STN/109 38 .27
38 .21
6
38 .27
20
7
FFL 38 .23
19
8
DH 2 .02
ID 303
18
9
FFL 38 .28 SH 0.91 HH 1 .96
17 10
DH 1 .96
Ceil 41 .10
Floor Slope 38 .31
1
220 A
ID 304
16
CH 3 .26
38 .24
Wall 1 .29h
15
HH 1 .92 SH 1.09
11
1a
STN/110 38 .23
U/S level 41 .06
4958
ID 301
A 220
ID 305 ID 306
ID 302 4
3
2
1
IS 302 ID 309
2a
IS 301
2
ID 308 ID 307
IS 303 IS 305A
Ed ID 317
3a
Ec Eb
IS 304
Ea
ID 316
ID 310
W 12
3
Stair 2 came to the site on the on 17 January and it is installed till the 5th floor.
910
W 10
ID 315
ID 312
ID 311
B
5
4
3
2
1
W 11
ID 313
CH 3 .03
Ee
ID 314
9
8
7
6
5
4
3
11
12
13
14
15
16
2
SH 0.95 HH 2 .17
SH 0.82 HH 2 .95
ID 318
1
SH 0.81 HH 2 .93
6
CH 2 .85
U/S 2.58
SH 0.81 HH 2 .93
U/S 2.93
CH 2 .49
CH 3 .07
200 1200
1682
3457
SH 0.71
U/S 2.58
SH 0.82 HH 2 .95 CH 3 .03
SH 0.82 HH 2 .95
SP 1 .37
Col
9
8
7
6
5
4
3
2
*
Refer to detail on drawing 319
The installation is not fully completed as the superstructure of the roof has just begin. Therefore, the staircase cannot be installed from the 5th floor to the roof level yet.
1
40
10
127
17
13 9 11
11
12
13
Completed till 5th floor
14
*
9
W 01
8
17
18
19
Handrail to span across window with brackets fixed to steel either side
1616
X
1200
*
16
250
X
7
15
200
Exposed fasteners shall be of same materials, color and finish as material to which applied. Exposed surfaces throughout project shall have same inherent texture and color for similar locations.
10
1200
10
6
contrasting nosings as spec L30.250B to treads and risers shown shaded
1750
5 8
4
7
6
5
4
3
2
1
12
11
10
9
8
7
6
5
4
3
2
1 40
3 34°
2
FFL = 51.924
ID 511
2600
12
1010
1200
15 14
Fifth Floor 53.964
3400
SP 1 .37
U/S 2.71
16
1200
20 steps (170mm)
FFL 39 .01
STN/146 39 .07
11
18
1
Fifth Floor 51.924
19 18
Fifth Floor Plan
17
*
6190
15 Handrails as spec L30.250B with offset radius bracket fixings to wall to be set at 1000mm above pitchline
ID 413
12
Handrail and guarding to extend 300mm beyond first riser
11
1000
10
11
1200
9
* *
8
12
13
14
15
W 01
7 6
18
3 2
1454
7
6
5
4
3
2
X
Wheelchair Refuge
B
13/07/17 Balustrade system amended
MLD
A
10/01/17 Spec Refs added
MLD
REV. DATE
18 Architects, Landscape & Interior Design
17 16 14 6179
13
Extend handrail 300mm min from first step
Stair 2
1200
Third Floor 45.464
10
9
8
7
6
5
4
3
2
1 40
1
DRAWING
250
X
3 34°
W 01
Wheelchair Refuge
4 2
All dimensions and levels subject to check site measurement
www.allanjoycearchitects .co.uk
PROJECT
2600
Handrail and guarding to extend 300mm beyond first step
5
design@allanjoycearchitects .co.uk
W
Confetti CQ Campus
7 6
E
0115 950 7161
ID 315
*
8
0115 841 8418
F
Confetti Media Group
11 10 9
T
CLIENT
X
Wheelchair Refuge
3230
Precast concrete stairs to Structural Engineer's details
12
Fifth Floor 47.164
19 steps (170mm)
16-20 Bath Street, Nottingham NG1 1DF
Fourth Floor Plan
15 1200
Section XX
BY
1
19
*
FFL = 45.464
DESCRIPTION
40
Fourth Floor 48.694
1
19
1200
Vinyl finish as drawings 401 to 406 to surface of treads with min 55mm wide contrasting nosings as spec L30.250B
4
34°
17
250
X
5
FFL = 48.694
16
2600
Fifth Floor 50.054
200
1300
1500
3230
Extend handrail 300mm min from top step and return to wall
1010
13
1200
127
16 14
19 steps (170mm)
Col
X
Roof-Terrace Floor Plan
19
FFL 39 .06
20
CH 2 .99
Part of stair 2 that is not yet constructed
Roof-Terrace Floor 55.324
*
U/S 2.78
Generally, concrete stairs and associated guarding / handrails / noising all as spec ref : L30.250B
X
12
FFL = 55.324
H
GENERAL NOTES
W 21
*
CH 2 .99
*
G
U/S 2.71
DH 2 .06
20
TA 2 .23 FFL 45 .54
19
1in12
SP 1 .66
18
UP
126
F
SP 1 .37
17
E
SP 1 .45
16
D
H101
15
.62 SCH 2
14
C
CH 3 .06
B
H103 .61 SCH 2
TA 2 .27
FFL 39 .04
FFL 39 .08
STN/143 39 .04
C
222
A
U/S 2.71
Col
19
SP 1 .45
18
CH 3 .03
CH 3 .03
ID 319
17
SH 0.81 HH 2 .93
7
CH 3 .01
8
Wheelchair Refuge
9
Wheelchair Refuge
B 221
10
4
221
W 01
10
13
Win/A SH 2.04
1200
ID 601
PROJECT NUMBER
SCALE
2588
1:25 @ A1
DATE
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
311
B
Construction MLD
This drawing is copyright and remains the property of Allan Joyce Architects Ltd
Third Floor Plan
ID 318
Generally do not scale drawings. All dimensions to be checked on site.
58
)HE
-DQ $ -DQ
-DQ )HE
6WDLU &RQVWUXFWLRQ
,QWHUQDO )LQLVKHV
Z G
-XO $
6HS
Z G
-XO $
6HS
-XO $ -XO $ -XO $ $XJ $ $XJ $ $XJ $ 6HS $ $XJ $ $XJ $ $XJ $ $XJ $ 6HS $
$XJ $ -XO $ $XJ $ $XJ $ $XJ $ $XJ $ 6HS 6HS $XJ $ $XJ $ $XJ 6HS $
Z G
'HF $
$SU
Z G
'HF $
$SU
Z
'HF $
)HE
'HF $ -DQ $ -DQ $ -DQ 6WDUW -DQ
'HF -DQ -DQ -DQ )LQLVK )HE
3
%ULFN *QG WR VW VKHV %ULFN VW WR QG DUWLWLRQV %ULFN QG WR UG VWDOODWLRQ %ULFN UG WR WK S 'U\ /LQLQJ 3DUWLWLRQV %ULFN WK WR WK SSLQJ %ULFN WK WR WK GHG 0) &HLOLQJV
HG &DVVHWWH LQVWDOODWLRQ
)L[HG &DVVHWWH *QG WR VW )L[HG &DVVHWWH VW WR QG 1DPH )L[HG &DVVHWWH QG WR UG )L[HG &DVVHWWH UG WR WK )L[HG &DVVHWWH WK WR WK )L[HG &DVVHWWH WK WR WK
5RRI
5RRI 3DUDSHWV 2XWOHWV URRI 'HFN 5RRI 0HPEUDQH DQG ,QVXODWLRQ DWHU *RRGV
/RZHU 5RRI
-DQ -DQ -DQ -DQ )HE -DQ )HE -DQ 0DU -DQ 0DU )HE
-DQ -XQ )HE -DQ )HE -DQ 0DU -DQ 0DU )HE $SU )HE
Z Z 'XUDWLRQ Z Z Z Z
-DQ )HE 6WDUW )HE )HE )HE 0DU
)HE )HE )LQLVK )HE )HE 0DU 0DU
Z
-DQ
0DU
Z
-DQ
0DU
-DQ -DQ )HE )HE
-DQ )HE )HE 0DU
)HE
0DU
)HE )HE )HE 0DU 0DU 0DU 0DU
)HE )HE 0DU 0DU 0DU 0DU 0DU
Z
2
Z
Z Z Z Z Z
DUDSHWV 2XWOHWV %DVHV DQG XSVWDQGV QVXODWLRQ 6LQJOH 3O\ DWHU *RRGV H )ORRU )LQLVK 6HGXP 5RRI )HQFHOLQH
8SSHU 5RRI
Z Z Z Z Z Z Z Z
5RRI 3DUDSHWV *XWWHUV %DVHV DQG XSVWDQGV URRI SODQW URRI 'HFN LQVXODWLRQ 6LQJOH 3O\ 0HPEUDQH DWHU *RRGV J :DWHUWLJKW
Z Z Z Z Z
-DQ -DQ
-DQ
0DU
)HE
0DU
)HE )HE 0DU )HE 0DU 0DU
)HE )HE 0DU )HE 0DU 0DU
Z
-DQ
-XQ
Z
-DQ
-XQ
-DQ -DQ -DQ -DQ )HE )HE )HE 0DU 0DU $SU $SU $SU 0D\ $SU $SU $SU $SU $SU 0D\ -XQ
-DQ -DQ )HE )HE )HE )HE 0DU 0DU 0DU $SU $SU $SU 0D\ 0D\ $SU $SU $SU 0D\ -XQ -XQ
)) ( QJ DW :DOOV 0 ( RQ :RUNV LQF 7LOLQJ GHG &HLOLQJ )LQLVKHV *ODVV 6FUHHQV QLVKHV 0 ( 2Q +HDW 2Q QG )L[ GRRUV
DOODWLRQ ,QVWDOODWLRQ [ )) ( J DQG 6QDJJLQJ
Z Z Z Z Z
HUQDO )LQLVKHV
Z
-DQ
-XQ
VKHV
Z
-DQ
-XQ
-DQ -DQ -DQ -DQ )HE
-DQ -DQ -DQ )HE )HE
DUWLWLRQV VWDOODWLRQ S 'U\ /LQLQJ 3DUWLWLRQV SSLQJ GHG 0) &HLOLQJV
Z Z Z Z Z 'XUDWLRQ
6WDUW
3599
SSL 55.024
)LQLVK
-XO\
$XJXVW
6HSWHPEHU
Roof-Terrace Floor 55.324
13
12
CFB
(;$0 3(5,2'
1
Metal Stud and Plasterboard partitions as spec ref K10.115
X501 COMPUTER SUITE *UH\ 7HUP 9DFDWLRQ
SSL 51.624
CFB
1
X401 COMPUTER SUITE
G
Fourth Floor 48.694
CFB
Third Floor Third Floor 45.590 45.464
MJ (9.750) 0DUFK $SULO 45.197
0D\
-XQH
-XO\
$XJXVW
6HSWHPEHU
CFB
/LQH
X201 LRC
Second Floor CONFETTI 41.820
CFB
First Floor Confetti 38.360
MJ (2.997) 38.297
0DUFK
Level (0.00) 35.447
$SULO
Ground Floor Ground Floor HE 35.630 35.630 35.440
Ground Floor Confetti
0D\
o -XQH
'HF $
$SU
Z
'HF $
)HE
-DQ
0DU
5- Balustrade System to be confirmed by client
Z G
0DUFK -DQXDU\ $SULO 0D\ -XQH )HEUXDU\ -XO\ $XJXVW 6HSWHPEHU 0DUFK 2FWREHU 1RYHPEHU $S '
Z G
Z Z Z Z G Z Z G Z Z G Z
X512 STAIR 2
Z Z
$
-DQ 0D\ -DQ 0D\ )HE 0D\ $ )HE -XQ $ 0DU -XO $ 0DU -XO $ -DQ
0D\ 0D\ )HE )HE 0D\ $ 0D\ $ )HE )HE 0D\ $ 0D\ $ )HE 0DU 0D\ $ 0D\ $ -DQ
G
G
$SU
-DQ 0D\ )HE 0D\ )HE -XO $ 0DU $XJ $ 0DU )HE $SU
-DQ 0DU
(;$0 3(5,2'
(;$0 3(5,
SFS SYSTEM
G
*UH\ 7HUP 9DFDWLRQ
Existing HEC Building
X412 STAIR 2
Proposed masonry to be built off existing gable - cut bricks to be removed to start new wall New step + cover Flashing to abutment to color match brick as H27 - 440
G
220
m o
inner face strings
1400
inner face strings
1400
m
CURTAIN WALLING CONCRETE
G
inner face strings
X312 STAIR 2
)DFLQJ %ULFNZRUN )LUVW )ORRU ,QWHUQDO )LQLVKHV
)DFLQJ %ULFN *QG WR VW )DFLQJ %ULFN VW WR QG VW IL[ 3DUWLWLRQV )DFLQJ %ULFN QG WR UG 0 ( ,QVWDOODWLRQ )DFLQJ %ULFN UG WR WK &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV )DFLQJ %ULFN WK WR WK )LUH 6WRSSLQJ )DFLQJ %ULFN WK WR WK 6XVSHQGHG 0) &HLOLQJV &RUWHQ )L[HG &DVVHWWH LQVWDOODWLRQ Third Floor &RUWHQ )L[HG &DVVHWWH *QG WR VW 45.464 &RUWHQ )L[HG &DVVHWWH VW WR QG 1DPH 2FWREHU 1RYHPEHU &RUWHQ )L[HG &DVVHWWH QG WR UG &RUWHQ )L[HG &DVVHWWH UG WR WK &RUWHQ )L[HG &DVVHWWH WK WR WK &RUWHQ )L[HG &DVVHWWH WK WR WK ,QWHUQDO )LQLVKHV
Z G Z
Z Z Z Z Z Z Z Z Z Z Z
Z
Z
-DQ -DQ
-DQ -DQ -DQ -DQ )HE -DQ )HE -DQ 0DU -DQ 0DU )HE -DQ
$SU -XQ
-DQ -XQ )HE -DQ )HE -DQ 0DU -DQ 0DU )HE $SU )HE
G
G
0DU
Third Floor 45.590
Floor Third Z -DQ )HE 45.464 )HE Z )HE 'XUDWLRQ 6WDUW )LQLVK 0DUFK $SULO 0D\ -XQH -XO\ $XJXVW 6HSWHPEHU 1RYHPEHU $S ' 'HFHPEHU -DQXDU\ )HEUXDU\ 0DUFK 2FWREHU )HE Z )HE )HE Z )HE
5RRI :RUNV
WK )ORRU 5RRI
/RZHU 5RRI 3DUDSHWV 2XWOHWV /RZHU URRI 'HFN /RZHU 5RRI 0HPEUDQH DQG ,QVXODWLRQ 5DLQZDWHU *RRGV
WK )ORRU /RZHU 5RRI
5RRI 3DUDSHWV 2XWOHWV 3ODQW %DVHV DQG XSVWDQGV 'HFN LQVXODWLRQ 6LQJOH 3O\ 5DLQZDWHU *RRGV 7HUUDFH )ORRU )LQLVK *UHHQ 6HGXP 5RRI 0HVK )HQFHOLQH
Z Z
)HE 0DU
0DU 0DU
Z
-DQ
0DU
Z
-DQ
0DU
Z Z Z Z
-DQ -DQ )HE )HE
-DQ )HE )HE 0DU
Z
)HE
0DU
Z Z Z Z Z Z Z
)HE )HE )HE 0DU 0DU 0DU 0DU
)HE )HE 0DU 0DU 0DU 0DU 0DU
43.975 43.975
-XO\
X001 RECEPTION
WK )ORRU 8SSHU 5RRI
8SSHU 5RRI 3DUDSHWV *XWWHUV Second Floor 3ODQW %DVHV DQG XSVWDQGV 42.230 LQVWDOO URRI SODQW 8SSHU URRI 'HFN LQVXODWLRQ 6LQJOH 3O\ 0HPEUDQH 5DLQZDWHU *RRGV %XLOGLQJ :DWHUWLJKW
*URXQG )ORRU ,QWHUQDO )LQLVKHV ,QWHUQDO )LQLVKHV
VW IL[ 3DUWLWLRQV 0 ( ,QVWDOODWLRQ &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV )LUH 6WRSSLQJ -RLQHU\ VW )L[ )) ( 3ODVWHULQJ 0LVW &RDW :DOOV QG )L[ 0 ( 'HFRUDWLRQ :RUNV LQF 7LOLQJ Stair 3 6XVSHQGHG &HLOLQJ )LQLVKHV Drawing 312 ,QWHUQDO *ODVV 6FUHHQV )ORRU )LQLVKHV UG )L[ 0 ( 3RZHU 2Q +HDW 2Q -RLQHU\ QG )L[ GRRUV
First Floor 38.930 ,36 LQVWDOODWLRQ 6DQLWDU\ ,QVWDOODWLRQ )LQDO )L[ )) ( &OHDQLQJ DQG 6QDJJLQJ
Z
)HE
0DU
Z Z Z Z Z
)HE )HE 0DU )HE 0DU 0DU
)HE )HE 0DU )HE 0DU 0DU
Z
-DQ
-XQ
Z
-DQ
-XQ
Z Z Z Z Z Z Z G Z Z Z Z Z Z
-DQ -DQ -DQ -DQ )HE )HE )HE 0DU 0DU $SU $SU $SU 0D\ $SU $SU $SU $SU $SU 0D\ -XQ
-DQ -DQ )HE )HE )HE )HE 0DU 0DU 0DU $SU $SU $SU 0D\ 0D\ $SU $SU $SU 0D\ -XQ -XQ
$XJXVW
6HSWHPEHU
/LQH
Z Z Z Z Z
)LUVW )ORRU ,QWHUQDO )LQLVKHV
Z
,QWHUQDO )LQLVKHV
VW IL[ 3DUWLWLRQV 0 ( ,QVWDOODWLRQ &ORVH 8S 'U\ /LQLQJ 3DUWLWLRQV )LUH 6WRSSLQJ 6XVSHQGHG 0) &HLOLQJV
2FWREHU
1DPH 1RYHPEHU
-DQ
Second Floor HE 42.320
40.690 40.690
-XQ
-DQ
-XQ
Z Z Z Z Z
-DQ -DQ -DQ -DQ )HE
-DQ -DQ -DQ )HE )HE
First Floor HE 39.060
37.917 37.917
0DUFK -DQXDU\ $SULO 0D\ -XQH )HEUXDU\ -XO\ $XJXVW 6HSWHPEHU 0DUFK 2FWREHU 1RYHPEHU $S '
59
35.957 Ground Floor 35.630
First Floor HE 39.060
Z
'XUDWLRQ 6WDUW )LQLVK 'HFHPEHU
Second Floor HE 42.320
There are 4 type of external envelope in total: 1. Corten Steel cladding on Steel Frame System 2.Corten Steel cladding on brickworks 3. Curtain wall 4. Corten Steel cladding on concrete
X101 CAFE
Z G
2- Terrace Roof System build-up + Thermal performance, Roof Falls, Drainage to be confirmed following details from Roof subcontractor
They are delayed due to the general suspension of the whole programme.
First Floor HE 39.060
$SU
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ifth Floor -DQ 6WDLU 3&& 'HOLYHU DQG LQVWDOO Z -DQ WK )ORRU /RZHU 5RRI Z )HE 0DU -DQ &RQVWUXFW 7HUUDFH 6ODE51.924 Z -DQ 5RRI 3DUDSHWV 2XWOHWV Z )HE )HE -DQ 6WULS DQG 6LWH &OHDU Z -DQ )HE 3ODQW %DVHV DQG XSVWDQGV Z )HE 0DLQ %XLOG 6WHHOZRUN )UDPH Z G -DQ $ )HE 0DU 'HFN LQVXODWLRQ 6LQJOH 3O\ Z )HE 6WHHOZRUN )UDPH Z -DQ $ -DQ 0DU 5DLQZDWHU *RRGV Z 0DU )HE 6WHHOZRUN WR 8SSHU 5RRI WK IORRU Z G -DQ 0DU 7HUUDFH )ORRU )LQLVK Z 0DU 6WDLU &RQVWUXFWLRQ Z G -XO $ 6HS 0DU *UHHQ 6HGXP 5RRI Z 0DU ,QWHUQDO )LQLVKHV Z G -XO $ 6HS 0DU 0HVK )HQFHOLQH Z 0DU 6WDLU 5RRI 6WDLUFDVH ([LVWLQJ :DOOV DQG 6WDLU UHPRYHG Z -XO $ $XJ $ WK )ORRU 8SSHU 5RRI Z )HE 0DU 7HPSRUDU\ :RUNV 3URSSLQJ Z -XO $ -XO $ 8SSHU 5RRI 3DUDSHWV *XWWHUV Z )HE )HE $GMDFHQW *QG )OU /LYH URRP ZDOO GHPR Z -XO $ $XJ $ )HE 3ODQW %DVHV DQG XSVWDQGV Z )HE 7HPSRUDU\ :HDWKHUSURRILQJ WR DFFHVV VWXGLR G $XJ $ $XJ $ 0DU LQVWDOO URRI SODQW Z 0DU Z $XJ $ $XJ $ +( 6WHHOZRUN )UDPH DQG 6WDLU )ORRUV )HE 8SSHU URRI 'HFN LQVXODWLRQ 6LQJOH 3O\ 0HPEUDQH Z )HE FourthFloor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ourth Floor )HE VW )L[ )) ( Z )HE 48.694 ([WHUQDO 6)6 DQG FDUULHU SDQQHOV JUQG VW Z 'HF $ 'HF 0DU 3ODVWHULQJ Z )HE 2 HEC -DQ ([WHUQDO 6)6 DQG FDUULHU SDQQHOV VW QG Z -DQ $ Stair 0DU 0LVW &RDW :DOOV G 0DU 314 -DQ ([WHUQDO 6)6 DQG FDUULHU SDQQHOV QG UG Z -DQ $ Drawing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
Z $SU Third Floor )HE &XUWDLQ ZDOOLQJ DQG ZLQGRZV UG WK Z )HE $SU ,36 LQVWDOODWLRQ Z $SU 47.164 )HE &XUWDLQ :DOOLQJ :LQGRZV WK WR WK Z )HE 0D\ 6DQLWDU\ ,QVWDOODWLRQ Z $SU )HE &XUWDLQ :DOOLQJ :LQGRZV WK WR WK 5RRI Z )HE -XQ )LQDO )L[ )) ( Z 0D\ 0DU ([WHUQDO 'RRUV DQG /RXYUHV Z G )HE -XQ &OHDQLQJ DQG 6QDJJLQJ Z -XQ
C
2 Second Floor HE Second Floor 42.320 42.230 42.200
First Floor 38.930
'HF $
Final setting out of Roof-Terrace to be confirmed :
The frame of the curtain wall system is now visible in the facade of the 1st & 2nd floor. However, glazing has not fixed on to the frame.
MJ (6.525 41.972
Z G
Although the programme stated that the Steel Frame System (SFS) should be completed in the current stage, the SFS system is only fixed until the 3rd floor.
X301 COMPUTER SUITE
$XJ $ -XO $ $XJ $ $XJ $ $XJ $ $XJ $ 6HS 6HS $XJ $ $XJ $ $XJ 6HS $
4
4
3
-XO $ -XO $ -XO $ $XJ $ $XJ $ $XJ $ 6HS $ $XJ $ $XJ $ $XJ $ $XJ $ 6HS $
Z Z Z Z Z G Z
)DFLQJ %ULFN *QG WR VW )DFLQJ %ULFN VW WR QG :RUNLQJ 3ODWIRUP +DUGVWDQGLQJ GRQH E\ &OLHQW )DFLQJ %ULFN QG WR UG 'HPROLWLRQ DQG :RUN $OWHUDWLRQV )DFLQJ %ULFN UG WR WK 6XEVWUXFWXUH :RUNV )DFLQJ %ULFN WK WR WK 6XSHUVWUXFWXUH Third Floor )DFLQJ %ULFN WK WR WK 53.964 ,QVLWX &RQFUHWH )UDPH
6HS
Z G
6LWH 3UHSHUDWLRQ
&RUWHQ )L[HG &DVVHWWH LQVWDOODWLRQ
6HS
-XO $
Z $SU -XQ Z -DQ -DQ Z G $SU 6HS -DQ Z -DQ Z G 0D\ $ -XQ Top of Coping -DQ )HE Z Top of Masonry 55.547 0D\ Z 0D\ $ Z )HE )HE 55.462
0DLQ %XLOG :RUNV
2
MJ (13.275) 48.722
&XUWDLQ :DOOLQJ :LQGRZV DQG 'RRUV
1
Fifth Floor 51.924 MJ (16.200) 51.647
21 W Stair 2 ([WHUQDO 6)6 DQG FDUULHU SDQHOV WK WR WK 5RRI Drawing 311
-XO $
Z 'HF $ 'HF -DQ Z -DQ $ -DQ Z -DQ $ -DQ -DQ Z 'HFHPEHU 'XUDWLRQ 6WDUW )LQLVK -DQ )HE Z )HE Z )HE
)DFLQJ %ULFNZRUN
([WHUQDO 6)6 DQG FDUULHU SDQQHOV JUQG VW ([WHUQDO 6)6 DQG FDUULHU SDQQHOV VW QG ([WHUQDO 6)6 DQG FDUULHU SDQQHOV QG UG ([WHUQDO 6)6 DQG FDUULHU SDQQHOV UG WK 2FWREHU 1RYHPEHU 1DPH ([WHUQDO 6)6 DQG FDUULHU SDQHOV WK WR WK
7HFKQLFDO 'HVLJQ 6WDJH
5HG (;$0 3(5,2'
([WHUQDO 6)6 DQG &DUULHU 3DQHO
-DQ )HE
Z Z Z G Z Z Z Z Z Z G
([WHUQDO :DOO
)HE
Z G
([WHUQDO (QYHORSH
/LQH
-DQ -DQ
-DQ $
Z G
2950
&XUWDLQ :DOOLQJ :LQGRZV JUQG VW .H\ 6XEFRQWUDFWRU 3URFXUHPHQW &XUWLDLQ ZDOOLQJ DQG ZLQGRZV VW QG &RQVWUXFWLRQ 3URJUDPPH &XUWDLQ ZDOOLQJ DQG ZLQGRZV QG UG 6LWH 6HW 8S &XUWDLQ ZDOOLQJ DQG ZLQGRZV UG WK 6LWH 3RVVHVVLRQ &XUWDLQ :DOOLQJ :LQGRZV WK WR WK +RDUGLQJ DQG )HQFLQJ &XUWDLQ :DOOLQJ :LQGRZV WK WR WK 5RRI &DELQV DQG :HOIDUH ([WHUQDO 'RRUV DQG /RXYUHV 6LJQDJH
MJ (19.200) 54.647
1DPH
VKHV
Z Z Z Z Z Z Z G Z Z Z Z Z Z
G
$SU -XQ
,QWHUQDO )LQLVKHV
DUWLWLRQV VWDOODWLRQ S 'U\ /LQLQJ 3DUWLWLRQV SSLQJ
Roof-Terrace Floor 55.324
2750
Z Z Z Z Z Z Z Z Z Z Z
Z G Z
-DQ -DQ
20 steps (165.5mm)
FNZRUN HUQDO )LQLVKHV
1
6HS $ )HE 2FW $ )HE 2FW $ )HE 1RY $ )HE 1RY $ 0DU 1RY $ 0DU 'HF $ 0DU 'HF $ 0DU -DQ $ -DQ -DQ )HE -DQ )HE -DQ 0DU -DQ 0DU -DQ )HE -DQ )HE )HE 0DU -DQ 0DU )HE 0DU 6HS 0DU 6HS 0DU $XJ $ 0DU -XO $ )HE $XJ $ )HE $XJ $ 0DU $XJ $ )HE $XJ $ 0DU 6HS 0DU 6HS -XQ $XJ $ -XQ $XJ $ -DQ $XJ -DQ 6HS $ )HE $SU )HE $SU )HE )HE )HE 'HF 0DU -DQ 0DU -DQ 0DU -DQ $SU )HE $SU )HE $SU 0DU 0D\ -DQ 0D\ -DQ $SU )HE $SU )HE $SU )HE 0D\ )HE -XQ 0DU -XQ
Z Z Z G
Z -DQ $ Z G -DQ
6WDLU 5RRI 6WDLUFDVH ([LVWLQJ :DOOV DQG 6WDLU UHPRYHG 7HPSRUDU\ :RUNV 3URSSLQJ $GMDFHQW *QG )OU /LYH URRP ZDOO GHPR 7HPSRUDU\ :HDWKHUSURRILQJ WR DFFHVV VWXGLR +( 6WHHOZRUN )UDPH DQG 6WDLU )ORRUV )ORRU -RLVWV DQG /DQGLQJV LQVWDOOHG /LIW 6KDIW )UDPH 5RRI 3URWHFW 3DUWLWLRQ :DOOV VW IL[ 0 ( VW IL[ -RLQHU\ 'RRU LQVWDO 3DUWLDO 6WDLU DQG &OLHQW +DQGRYHU 2XW RI KRXUV ILQLVKHV
-DQ 0DU
-XO $ -DQ 6HS $ )HE 6HS $ )HE 2FW $ )HE 2FW $ )HE 2FW $ 0DU 1RY $ -DQ 1RY $ -DQ 'HF $ -DQ 'HF $ -DQ 'HF $ )HE -DQ )HE -DQ )HE -DQ )HE -DQ )HE -DQ $ )HE -DQ $ 0DU -DQ 0DU -XO $ 0DU -XO $ 0DU -XO $ )HE -XO $ )HE -XO $ )HE $XJ $ 0DU $XJ $ )HE $XJ $ 0DU 6HS $ 0DU $XJ $ -DQ $XJ $ -DQ $XJ $ -DQ $XJ $ -DQ 6HS $ -DQ 'HF $ -DQ 'HF $ )HE 'HF $ )HE 'HF $ )HE -DQ $ 0DU -DQ $ 0DU -DQ $SU -DQ $SU )HE $SU -DQ 0D\ -DQ $SU -DQ $SU -DQ $SU )HE $SU )HE $SU )HE 0D\ )HE -XQ
2396
)) ( DO 6)6 DQG FDUULHU SDQQHOV JUQG VW QJ DO 6)6 DQG FDUULHU SDQQHOV VW QG DW :DOOV DO 6)6 DQG FDUULHU SDQQHOV QG UG 0 ( DO 6)6 DQG FDUULHU SDQQHOV UG WK RQ :RUNV LQF 7LOLQJ DO 6)6 DQG FDUULHU SDQHOV WK WR WK GHG &HLOLQJ )LQLVKHV DO 6)6 DQG FDUULHU SDQHOV WK WR WK 5RRI *ODVV 6FUHHQV DOOLQJ :LQGRZV DQG 'RRUV QLVKHV Q :DOOLQJ :LQGRZV JUQG VW 0 ( Q ZDOOLQJ DQG ZLQGRZV VW QG 2Q +HDW 2Q Q ZDOOLQJ DQG ZLQGRZV QG UG QG )L[ GRRUV
Q ZDOOLQJ DQG ZLQGRZV UG WK DOODWLRQ Q :DOOLQJ :LQGRZV WK WR WK ,QVWDOODWLRQ Q :DOOLQJ :LQGRZV WK WR WK 5RRI [ )) ( DO 'RRUV DQG /RXYUHV J DQG 6QDJJLQJ
Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z Z G Z Z Z Z G Z Z G Z Z G Z Z Z Z Z Z Z G Z Z Z Z Z Z Z Z Z Z Z Z G Z Z Z G Z Z G Z Z Z Z Z Z G Z Z Z Z Z Z Z Z Z G Z Z Z Z Z Z Z Z Z Z Z Z Z G Z
-XO $ -DQ
2945
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
Z Z
$SU
-DQ 0D\ )HE 0D\ )HE -XO $ 0DU $XJ $ 0DU )HE $SU
2945
UHWH )UDPH HG &DVVHWWH LQVWDOODWLRQ
-DQ 0D\ -DQ 0D\ )HE 0D\ $ )HE -XQ $ 0DU -XO $ 0DU
2949
Z Z Z Z G Z Z G Z Z G Z
-XQH
Top of Coping 55.775
2897
%ULFN *QG WR VW RQ %ULFN VW WR QG 3ODWIRUP +DUGVWDQGLQJ GRQH E\ &OLHQW %ULFN QG WR UG G :RUN $OWHUDWLRQV %ULFN UG WR WK :RUNV %ULFN WK WR WK H %ULFN WK WR WK
$
-DQ
3400
Z G
)HE 0D\ )HE 0D\ )HE 0D\ $ )HE 0D\ $ 0DU 0D\ $
3230
RUNV
0DU
-DQ 0D\ $ )HE 0D\ )HE 0D\ $ )HE 0D\ $ )HE 0D\ $
23293
Z G
)HE
-XQ -DQ 6HS -DQ -XQ
3230
Z Z Z Z Z Z Z Z G Z
FNZRUN
OO
-DQ
3234
Q ZDOOLQJ DQG ZLQGRZV QG UG Q ZDOOLQJ DQG ZLQGRZV UG WK VVLRQ Q :DOOLQJ :LQGRZV WK WR WK DQG )HQFLQJ Q :DOOLQJ :LQGRZV WK WR WK 5RRI G :HOIDUH DO 'RRUV DQG /RXYUHV
)6 DQG &DUULHU 3DQHO
)HE
0D\
3300
Z G
Z $SU Z -DQ Z G $SU -DQ Z Z G 0D\ $
$SULO
3300
DOOLQJ :LQGRZV DQG 'RRUV
(87 bricks) 6525
DO 6)6 DQG FDUULHU SDQHOV WK WR WK 5RRI
0DUFK
(38 bricks) 2850
Z Z Z Z 'XUDWLRQ Z Z
'HVLJQ 6WDJH Q :DOOLQJ :LQGRZV JUQG VW QWUDFWRU 3URFXUHPHQW Q ZDOOLQJ DQG ZLQGRZV VW QG RQ 3URJUDPPH
3
Top of Coping Top of Masonry 58.922 58.837
Top of Coping Top of Masonry 58.622 58.537
(177 bricks) 13275
DO 6)6 DQG FDUULHU SDQQHOV JUQG VW DO 6)6 DQG FDUULHU SDQQHOV VW QG DO 6)6 DQG FDUULHU SDQQHOV QG UG DO 6)6 DQG FDUULHU SDQQHOV UG WK 1DPH DO 6)6 DQG FDUULHU SDQHOV WK WR WK
3554
X T E R N A L E N V E LO P E
(256 bricks) 19200
OO
)6 DQG &DUULHU 3DQHO
E
2
Top of Coping 58.922
(216 bricks) 16200
7.5
ORSH
Z Z Z G Z Z Z Z Z Z G
(130 bricks) 9750
5RRI 6WDLUFDVH ([LVWLQJ :DOOV DQG 6WDLU UHPRYHG DU\ :RUNV 3URSSLQJ W *QG )OU /LYH URRP ZDOO GHPR DU\ :HDWKHUSURRILQJ WR DFFHVV VWXGLR HOZRUN )UDPH DQG 6WDLU )ORRUV LVWV DQG /DQGLQJV LQVWDOOHG W )UDPH RWHFW :DOOV ( RLQHU\ 'RRU LQVWDO 6WDLU DQG &OLHQW +DQGRYHU 2XW RI KRXUV ILQLVKHV
1
3649
6WHHOZRUN )UDPH 6WHHOZRUN WR 8SSHU 5RRI WK IORRU
XFWLRQ
VKHV
&RQVWUXFW 7HUUDFH 6ODE 6WULS DQG 6LWH &OHDU 0DLQ %XLOG 6WHHOZRUN )UDPH
20 steps (163.5mm)
Z Z G
-DQ -DQ
-DQ $
21 steps (163.3mm)
UN )UDPH UN WR 8SSHU 5RRI WK IORRU
-DQ -DQ
JT3 .5x35 35 JT3 .5x35 35
Z Z Z G
1100
FW 7HUUDFH 6ODE G 6LWH &OHDU
6WHHOZRUN )UDPH
Ground Floor HE 35.630 35.440
2
3
4
5
6
7
9
8
B
221
1
SH 0.82 HH 2.95 CH 3.03
420
4
8
7
6
5
4
3
2
15
16
17
18
19
20
21
2 SCH 2.6
H1 01
U/S 2.58
SH 0.82 HH 2.95
110
CH 3.03
314
C 222
2279
B
CH 3.03
A
3562
443.5
Key Walls
1 450
AVCL
STEEL FRAME SYSTEM (SFS)
The glazing is expected to be fixed in the following week, 16 February, together working with the SFS system on the upper floors at the same time.
As the curtain wall is double glazed panels,it performs good under thermal comfort and keep the internal space warm even though there are no insulation on it.
497
Similar to the last visit, the SFS system still have not completely on all floors and the glazings are not fixed on the frame as well. However, some window frames are installed on the first and second floor, with handles and mechanism for opening and closing.
2
AVCL
SH 0.82 HH 2.95
PROPOSED FIRST FLOOR GA PLAN -1:50
Wall Construction - Corten Outer / SFS Inner 30mm Deep Corten Cassettes 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone Filled with RW45 Insulation , 12.5mm GB Plasterboard and skim + exposed co 12.5mm Plywood and Wall Construction - Corten Outer / RC Wall Inner 30mm Deep Corten Cladding Panel 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish Wall Construction - Brickwork Outer / SFS Inner
Black Brick as F10/110 CORTEN STEEL ON 102.5 CONCRETE 50mm Air Gap with Brick Ties and Support Brackets
3
AVCL
150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone Filled with RW45 Insulation , 12.5mm GB Plasterboard and skim + exposed c 12.5mm Plywood and
The insulation layer is now applying on the concrete wall to build up the layers for corten steel claddings. The reason why the claddings are designed to fixed on the concrete instead of letting the concrete expose externally is to match the aesthetic of the cladding on SFS system and to provide sufficient thermal comfort through adding more layers on wall.
60
1010
1700 1184
X014 SERVER 16Ground m2 Floor
Ground Floor 34.740
35.048
2176
2806
1736
3a ID 010
Ground Floor 35.048
2617
535
763 1736
1184
3471
400
10932
800 600
1135
X018 NEW STORE (86m2)
Type 1*
224
1496
1110
252
4642
1696
1000 1200
100
3070
925
640 800
220
600
3650
A
1095
Ground Floor 35.048
ID 009
NEW IS 004 3532
X020 MTG 3 9 m2
HH 2.98 SH 1.1 5
e
3554
34.63
ir Storag Under Sta
DH 2.03
DH 1.97
CH 3.68
148
1532
CH 2.84
36.60
ID 021
X004 MTG 2 8 m2
34.71 220 A
Type 1*
Type 1*
X002 MTG 1 9 m2
CH 3.39
2778
ID 012
.48
148
Type 2
300
2810
Mechanical riser
CH 2.37
IS 003
2000
Bl
R
14/02/18 Amendments to internal partitions
Q P
29/01/18 Amendments to internal doors ID008 MLD 16/01/18 MJ, CFB, Bricks setting out and downpipe position added MLD Amendments to internal wall partitions,dimensions updated
MLD
O N M L
04/01/18 19/12/17 08/11/17 18/09/17
K J II H G
24/08/17 18/08/17 30/05/17 17/08/17 30/05/17 12/05/17
Change to the slab edge following the SE info Amendments to drawings following the Cladding info Change to the 1st floor café/kitchen area Amendments to HEC stair 2 following the SE info Amendments to drawings following the Topo Survey and SE info
MLD MLD MLD MLD MLD MLD
F E D C B A
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
Change to doors and Stair 1 Lobby Spec Refs added Amendments to drawings Amendments to drawings Amendments to drawings Amendments to drawings
MLD MLD MLD MLD MLD MLD
DESCRIPTION
BY
Amendments to substation and meeting room layout Amendments to substation layout Amendments to substation layout
MLD MLD MLD MLD
The brick work mainly located on the North facade of the building. However, it has not yet started in the -350mm concrete deck to Structural Engineer's details construction site as the task is prioritized after the -3mm vapour control layer thick upstand between to be used around perimeter of 12 There are 2 layers- 50ofmminsulation thetheSFS studs task of superstructure and SFS fixing, there are no the roof on the internal façade of parapets and some of the Awalls ondistance the ground installed spare workers to work on brickworks. Therefore, they minimum of 300 mm level should behave maintained between the top of the insulation upstand and the bottom the insulation internally, leaving only plasterboard and scheduled the delivery of the bricks and their work later. of the horizontal roof insulation. -1.60steel taperedto insulation the external corten fix. zone to form the fall -1.5mm fully-adhered single ply membrane as S45.110A However, some of the blockwork started in the space of -roof barrier/protection layer(s) layer, filtration layer, substrate to depth required As the delivery of-drainage the corten steel cladding is the substation. -80mm semi-intensive green roof covering as Q37.120A rescheduled, theU-Value work <0.15W/m2K. of external cladding is postponed. 400
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Ground Floor 35.630
20
420
1010
768
800
221
3
2740
837
535
2950
B
2
ED 03
3
5
1135
2597.5
MJ
ID 017
3947.5(17 1/2 bricks)
U/S 2.76
U/S 2.37
DP
2 1
3a
AVCL
DH 2.05
190
4
5
10
AVCL
AVCL
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish Existing Wall HE Centre 215mm Existing Solid brick wall 25mm cavity depth Metal studs at 600mm centres - K10/165A 12.5mm Plasterboard
Existing Wall Confetti Insulation to be agreed with Structural Engineer Exposed concrete finish
Type 1
PARTITION Wall Type 1 2no.layer of 12.5mm Soundblock either side,16mm Resilient Bar fixed to one side, 92mm C studs with 50mm Isover between studs. Skim finish to both sides of partition.
Type 2
PARTITION Wall Type 2 1no. Layer of 15mm Soundbloc either side of 92mm C Studs with 50mm Isover APR between studs. (Use 15mm Soundbloc MR in WC Areas) Skim finish to both sides of partition.
Type 3
Type A
Type 1*
13
Terrace Roof System construction -350mm to 6th floor and 275mm to 5th floorconcrete deck to Structural Engineer's details -3mm vapour control layer -tapered zone for pedestal to allow falls from one side to
PARTITION Wall Type 1 - without16mm Resilient Bar
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
F
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group PROJECT
Confetti CQ Campus
60 minutes fire resistance Wall
17
Plasterboard on dabs to achieve min 60 minutes fire rating Existing wall
Movement joint
PARTITION Wall Type 3 1no. Layer of 15mm Soundbloc MR either side of 70mm C Studs with 50mm Isover APR between studs. Skim finish to both sides of partition.
PARTITION Wall Type A 3no. Layers 15mm Soundbloc either side of BG 146mm C Stud at 300mm Centres within 148mm Head and base channels. 75mm Isover APR between studs with Skim finish to both side of partition.
T
H
14 13 12 11 10 9 8
503.5
1in12
Architects, Landscape & Interior Design
4959
G
DH 2.05
HH 2.05 SH 0.87
UP
REV. DATE
1 6-20 Bath Street, Nottingham NG1 1 DF
6128
F
HH 2.05 SH 0.87
SP 2.23
U/S 2.78
CH 3.36
SH 0.19 HH 3.03
497
AVCL
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns Wall Construction - Blockwork Outer / SFS Inner 100mm fairfaced medium density blockwork - F10/225 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns
7718
E
Ground Floor 35.440
X017 PLANT ROOM 30 m2
32.78
N
U/S 3.14
1492
D
Ee
ED 04
eq.
1646
C
Ground Floor 35.048
H003
3562
Col
llery H002 Ga CH 2.99
223
3 SCH 2.8
B
G
Ground Floor 35.630
FFL 35.44
2279
A
C 222
CH 2.76
ID 019
CH 2.99
X010 STAIR 2
Lift
1800
nt
X011 STAIR 2 LOBBY
3751
3
3491
4
SH 0.88 HH 2.97
5
SH 0.88 HH 2.97
6
DH 2.04
7
SH 0.86 HH 2.03
8
U/S 2.27
9
DH 2.05
FFL 35.63
Ground Floor 35.630
10
ID 018
3
17
eq.
THL 35.64
ED 14
35.47
314
215
Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1
221 B
1
ID 015
32.86
4
poi Insertion
Insulation to be agreed with Structural Engineer
BRICKWORK 148
STN/128 36.04
Type 1*
X012 clnrs cpbd 3 m2
IS 002
34.66
422
ID 011
.50
1092
2000
1in10 ID 022
Ground Floor 35.630
1736
- 3steps
324
X015 COMMS 13 m2
140
X018 Staff Corridoor
11857
2000
1500
Ec
ID 007
34.828
- 3steps
3248
35.61
10
1215
GENERAL NOTES The insulation layer is installing between the frame in the ground level Semi−intensive currently. Green Roof Covering System construction STN/142 35.51
Existing Wall
1225
1010
338
Type 1*
UP 82
3574
Ed
Ground Floor 35.630
Ea
DH 2.1 0
Eb
ID 013 1736
1500
34.910
3306
Indicative location of reception desk by others
X019 Mtg cpbd ID 014
In Abeyance
1in12 3545
1184 ID 008
1343
400
450
W 01
X003 OFFICE 26 m2
34.910
Ground Floor 35.048
Electrical riser
Type 1*
1100MM HIGH
3a
ID 016
Key Walls
4
400
1178
400
5789 LOWWALL
inet MMC cab
1656 138
1828
4596
1in12 1854
3390
U/S 3.14
820
UP
1010
5000
Ground Floor 35.464
1in15
Ground Floor 35.630
496 400
314
PROPOSED GROUND FLOOR GA PLAN -1:50
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish U-Value = 0.18W/m2K
2552
1930
Secure line
312
1
1202
FFL
IS 001
STEEL FRAME SYSTEM (SFS) External Walls Wall Construction - Corten Outer / SFS Inner 30mm Deep Corten Cassettes 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns U-Value = 0.18W/m2K
1
Type 1* 1010
234
1110
1408 ID 006
3546
ID 003 ID 002
2500
2a
2
GENERAL NOTES
2
ID 005 499
3700
34.68
Ground Floor 35.630
3
X005 WC LOBBY
DH 2.05
311 4
3
ID 001
Ground Floor 35.464
X009 STAIR 1 LOBBY Type 1*
- 3steps
17
Floor
35.464
100
34.74
X001 RECEPTION 130 m2
1010
1979
410
5
2 17 mGround
ID 004
Ground Floor 35.048
76 1600 34.
6
34.69
4742
7
34.61
8
Ground Floor 35.464
15 m2
Type 1*
34.910
rk walls 140 Blockwo 500
34.69
X008 STAIR 1
Type 1* X007 WC CHANGING (FEMALE WC)
X006 WC CHANGING (MALE WC)
10 9
X013 CONTROL ROOM 8 m2
3200
Type 3
1000
Ground Floor 35.464
X016 SUBSTATION 20 m2
10
5038
ED 02 13
12
W 01
EXTERNAL
W 03
50
11
1a
310
INTERNAL
MJ
04 Step +0.
ED 12
3546
ED 01
1
9215
0 to Fit approx. 250
552
1810
4
W 02
bricks)
F 300
123 1003 579 195
1000
1200
400
800
600
15740(71
1/2 6413(28
34.74
10534 1000
2951
E 300 bricks)
34.70
3160
il A - 306 Plan Deta
1000
35.20
bricks) 9215(41 Ground Floor 35.300
34.82
4550
4452
6752
Ed
421
Ec
35.10
Ea
Eb
34.90
e ting out Lin Bricks Set
330
422
35.00
35.09
E
See drawing 2588-306 for recessed downpipe details
2000
1000
35.20
35.24
35.71
35.70
35.60
35.46
35.32
1492
D
D 301
Ground Floor 35.600
923
1646
C
3562
C 222
.12
35.46
35.63
35.80 B
2279
35.28
35.86
35.91 A
G 223
Ee
Bricks Setting out Line
ID 001, etc W001, etc ED01, etc IS01, etc
- Internal Door Codes (Refer to drawing 320) - Window Codes (Refer to drawings 322-323) - External Door Codes (Refer to drawings 323) - Internal Screene Codes (Refer to drawings 321)
DRAWING
Ground Floor GA Wall Types and Setting Out PROJECT NUMBER
SCALE
DATE
2588
1:50 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
201
R
Construction MLD
This drawing is copyright and remains the property ofAllan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
61
1492
SH 0.88 HH 2.97
SH 0.86 HH 2.03
AVCL
14 13 12 11 10 9 8
DH 2.05
HH 2.05 SH 0.87
UP DH 2.05
190 503.5
1in12
Construction - Brickwork Wall Inner There are 4 different types ofWall partitions inOuter the/ RCdesign, 102.5 Black Brick as F10/110, 50mm cavity 4 Air Gap with Brick Ties and Support Brackets differentiate mainly in sound50mm insulation andInsulation the size of 150mm Rockwool DuoSlab Rainscreen Exposed concrete finish 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns studs. Wall Construction - Blockwork Outer / SFS Inner Existing Wall HE Centre 100mm fairfaced medium density blockwork - F10/225 215mm Existing Solid brick wall The architect revised the drawing and 50mm Air Gap with Brick Ties andspecified Support Brackets 3a 5 25mm cavity depth 150mm Rockwool DuoSlab Insulation Metal studs at 600mm centres - K10/165A Knaufthe Windlinerdesign Sheathing Board as some of the different type of partitions12.5 in Currently, the sound insulation 12.5mmlayer Plasterboard has not applied 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns rooms require certain performance, for example some to the structure yet, only resilient bars and boards Existing Wall Confetti 10 for setting up toInsulation to be the agreed with Structural Engineer computer suits are functioned as recording musics or are installed hold insulations and Exposed concrete finish radio, they need better sound insulation. Thus, the perform as acoustic barriers. partitions have 3 insulation layers. AVCL
G
HH 2.05 SH 0.87
DH 2.04
U/S 2.78
CH 3.36
SH 0.19 HH 3.03
497
- Brickwork Outer / SFS Inner The partitions are settingWall inConstruction the and it is 102.5 Black Brick building as F10/110 50mm Air Gap with Brick Ties and Support Brackets 3 150mm Rockwool DuoSlab Insulation currently building till the 3rd floor. 12.5 KnaufWindliner Sheathing Board
6128
F Ground Floor 35.440
PROPOSED GROUND FLOOR GA PLAN -1:50 Key Walls
7718
E
SP 2.23
N
U/S 3.14
223
D
H003
1646
C
H 2.99
3562
3 SCH 2.8
B
Col
P ARTITIONS
2279
A
G
Ground Floor 35.630
FFL 35.44
7.6
C 222
H 2.76
allery H002 G CH 2.99
ID 018
AVCL
Type 1
PARTITION Wall Type 1 2no.layer of 12.5mm Soundblock either side,16mm Resilient Bar fixed to one side, 92mm C studs with 50mm Isover between studs. Skim finish to both sides of partition.
Type 2
PARTITION Wall Type 2 1no. Layer of 15mm Soundbloc either side of 92mm C Studs with 50mm Isover APR between studs. (Use 15mm Soundbloc MR in WC Areas) Skim finish to both sides of partition.
Type 3
PARTITION Wall Type 3 1no. Layer of 15mm Soundbloc MR either side of 70mm C Studs with 50mm Isover APR between studs. Skim finish to both sides of partition.
AVCL
PARTITION Wall Type A 3no. Layers 15mm Soundbloc either side of BG 146mm C Stud at 300mm Centres within 148mm Head and base channels. 75mm Isover APR between studs with Skim finish to both side of partition.
Type A
Type 1*
PARTITION Wall Type 1 - without16mm Resilient Bar
d cted tructe obstru obs Window assumed) s ns ion ensio (dimens
3rd Floor
Ee
Existing WC to be removed
G
421
223 FCB
1492
D
330
E
e ting out Lin Bricks Set
Ea
D 301
12868
4452
9 1/2 15627.5(6
2
1500min.
890
W 09
2502
W 02
15 16
X208 STAIR 1
9
7
Type 3
6
910 251
2
3
1
Type 2
2105
X209 STAIR 1 LOBBY
Type 2
1302
ID 202 1010
2500 IS 201
6900
1506
00 400
7366
LOWWALL LOWWALL
5789
122
400
1178
3554
3a
Ec
Eb
Ea
535 35
3
X203 LRC 50 m2
Type 2 T Ty
2950
1736
Mechanical riser
535
105
1200
Lift
105
14
15
16
17
18
19
20
ID 21 1
Second Floor 42.230
3047.5
450
3947.5(17 1/2 bricks)
Apex CH
U/S 2.81
41.36
1in12
6128
F
4959
G
U/S 2.81
U/S 2.81
U/S 2.81
H
62
41.32
HH 2.88 SH 0.77
CH 3.05
CH 3.05
CH 3.02
CH 3.02
HH 2.33 SH 1.23
7718
E U/S U/ S 2.81 2.81
U/S 2.81
UP 30 DH 2.04
223
FFL 42. 19
1492
D
G
HH 2.33 SH 1.23
1646
C U/S 2.81
Second Floor 42.200
HH 2.99 SH 0.84
20113562
B
1810
327.5
U/S 2.19
13
C 2.98 CH
9 99 HH 2.9 SH 0.84
C 222
2279
A
12
450 MJ
910
Col
11
W11
3
360
1800 180
air Wheelchair Refuge
105 5
W 10
41.25
495
2065
Second Floor 41 .964
Apex CH 3.81
X211 STAIR 2 LOBBY
1200
X205 COMPUTER SUITE 48 m2
Type A
CH 2.43
X X210 STAIR 2 314
105 370 1 0
Ed
41.37
1
3
236 359
1736 173
HH 2.88 SH 0.77
2
CH 3.05
3
CH 3.02
4
FFL 42.20
5
HH 2.92 SH 0.79
Second Floor 42.320
6
Type 1
ID 207
ID 209
CH 3.05
ID 21 2
7
ID 206
410
1in15
1in15 5276
HH 2.27 SH 1.37
C ID 21 0
1010
8 224UP
Second Floor 41 .820
0 50 215 21
Second Floor 42.230
U/S 2.98
420
4
Second Floor 42.230
Ground Floor
221
B
W 01
0 223 400
Electrical El riser ID 208
m o Type yp 2
1100MM 1100M HIGH
1
m 1in15 1854
400
Second Floor 42.064 4
1in15
3179
Second Floor 41 .964 4
4934
450
1930
Second Floor 42.230
1500
2
2552
ID 205 05 1010
4 174 317 1500
3487
2a
233
Type ypp 1
Type 1
MJ
3650
ID 201
Second Floor 42.064
n e Type Typ T ype 1 yp
ID21 3
20
4
10
Second Floorr 41 .964
19
5
A
ID 203
18
X204 SEMINAR ROOM
Type 3 29 m2
FFL 41.88
4742
4641
8
296
310
17
416
ID 204
X206 MALE WC
FFL 41.85
1696
10
X207 ACCESSIBLE Type 2 WC 1010 100
2 82 1.8 41. 4
1
Type 3
3109
3000
1a
4350
6 SH 1.2 6 HH 1.7 4 CH 2.1
11
W 05
9900 220
W 06
4
3160
X201 LRC 168 m2
392 7.5 2485
MJ
5165
2400
3900
F 300
E 300 ks) bric
bricks) 9215(41
6 2.66 H 2.6 SC SCH
C 222
6000
Eb
4550
2200min.
1646
C
1/2 bricks) 6413(28
810min.
3562
B
2951
1710
2279
Ec
1457
A
6752
Ed
420
Col
SP
THIS IS A CAD DRAWING - DO NOT HAND MODIFY - DO NOT SCALE - PHOTOCOPYING MAY DISTORT. COPYRIGHT IN THIS DRAWING IS THE PROPERTY OF MIES BUILDING SERVICES. IT MUST NOT BE REPRODUCED, AMENDED OR USED FOR THE EXECUTION OF ANY WORKS WHETHER IN CONNECTION WITH THE PROPOSED WORKS FOR WHICH IT HAS BEEN PREPARED OR OTHERWISE WITHOUT THE EXPRESS CONSENT IN WRITING OF MIES BUILDING SERVICES.
CORRIDOR SECTION AA 1:10 SCALE
2a
3a
ELECTRICAL CROSSOVER ZONE
250Ø SUPPLY DUCTWORK
475
375
100
100
100
The design concept is to give an industrial aesthetic to the building. Therefore, the M&E will be fully exposed to the interior of the building. As there are no covering between the services and the interior space, the work of installation must be sophisticated to be aesthetically pleasing.
500
ELECTRICAL CONTAINMENT ZONE
1050
28Ø CONDENSATE DRAINAGE FROM FCU'S 15x15Ø LTHW F&R
LIGHT FITTING
ER SER D WAT CHILLE
RICAL CONTAINMENT ZONE
150
First fixed of the M&E has been installed on the ground level and 1st floor. The mechanicians are going to work on the 2nd and 3rd floor.
DATA CONTAINMENT
2nd fix of the M&E will be started in early March together with the remaining 1st fix on the upper levels in order to complete the tasks quicker.
SERVICES LEGEND CHW PIPEWORK LPHW PIPEWORK MCWS/BCWS PIPEWORK AGD PIPEWORK SUPPLY DUCTWORK EXTRACT DUCTWORK WC EXTRACT DUCTWORK LIGHT FITTING
38.26
9 HH 2.9 SH 0.79
900
150
FIRE CONTAINMENT
RE H
1050
SSU
475
900
PIPEWORK CROSSOVER ZONE
SUPPLY DUCT WORK
HW)
PRE 3a
22x22Ø CHW F&R
275
2515
VICE (C
LOW
:10 SCALE
TER WA OT
LV/FIRE CONTAINMENT DATA/ELV CONTAINMENT SUB MAIN CONTAINMENT
ABBREVIATIONS 11
17
10
X108 STAIR 1
9 8 7
18 19
20
W)
EXIT
5
EXIT
6
X101 CAFE 150 m2
X104 SEMINAR ROOM 30 m 2
HH 1.92 SH 1.09
X106 FEMALE WC
16
HH 1.92 SH 1.09
X107 ACCESSIBLE WC 15
HH 1.92 SH 1.09
DENOTES LOW LEVEL DENOTES HIGH LEVEL DENOTES CHILLED WATER SERVICE DENOTES ABOVE GROUND DRAINAGE DENOTES LOW PRESSURE HOT WATER DENOTES BOOSTED COLD WATER SERVICE DENOTES MAINS COLD WATER SERVICE DENOTES LOW VOLTAGE DENOTES EXTRA LOW VOLTAGE
HH 1.92 SH 1.09
LL HL CHW AGD LPHW BCWS MCWS LV ELV
H (LP
X109 STAIR 1 LOBBY
EXIT 4
3
2
1
ADDITIONAL SEATING AREA
X114 NEW RAISED COURTYARD
X103 CAFE SERVERY 80 m 2 X102 KITCHEN 19m 2
void
1
2
3
4
5
6
7
8
GRAB AND GO
9
10
11
12
13
14
38.26
9 HH 2.9 SH 0.79
16
17
18
19
20
Col
HH 2.93 SH 0.81
CH 3.01
1
U/S 2.58
H103
EXIT Resource House,
SCH 2.6
Date
6
16/02/18
Description
CH 3.0
Updated as per client comments
TA 2.27
FFL 39.08
HH 2.95 SH 0.82
U/S 2.58
A
U/S 2.71
SP 1.45
CH 3.03
X111 STAIR 2 LOBBY
A0 Rev
HH 2.93 SH 0.81
HH 2.17 SH 0.95
CH 3.03 HH 2.95 SH 0.82
HH 1.92 SH 1.09
HH 1.92 SH 1.09
HH 1.92 SH 1.09
X104 SEMINAR ROOM 30 m 2
15
X112 clnrs cpbd X110 STAIR 2
HH 1.92 SH 1.09
IBLE
M& E
7.7
63
R AISED
7.8
C O U RT YA R D
3111
3215
W 10
m W 07
e
t n
Step-Down Pedestal application -Fascia Board flush with top of pavers -Ledger board
Design TBC
Replace existing door with a new window in altered opening. Design TBC 1st floor Terrace Roof System construction (all TBC by subcontractor)
38.230
38.568
38.230
38.230
2775
/s central 406UB
r
round 833
/s central 533UB
be encased with FireCase system to achieve 60min protection to structure
Ground Floor 34.740
2512 to u/s central 533UB
2442 to u/s central 406UB
2775
3235
SSL (ToS) NB: All new steelwork to be encased with FireCase system to achieve 60min protection to structure 37.780
(ToS) 37.580
X205 COMPUTER SUITE In terms of thermal performance, a nondomestic
building should possess an u-value of 0.18 W/m2K . Replace existing windows with a new The composition of the floor of this raised courtyard .964 glazed doors in existing opening with successfully achieves an u-value of less than 0.15 W/m2K lowered cill. that reach the standard and give thermal comfort.
Guarding to be agreed
Ground Floor 38.568
More work had been done to the raised courtyard since the last visit. A layer of screed is coated on top of the pre-cast concrete so as to give a smooth surface to layer the water vapour barrier and insulation on top as the sharp edges of the pre-cast concrete might pierce the water vapour barrier and negatively affects vapour controlling.
-50mm zone for paving slab -175mm tapered zone for pedestal to allow falls from one side to the other of 1.80. 150mm tapered insulation zone to form the fall ( within the pedestal zone) -Fully adhered single-ply membrane as S42.110A on top of the tapered insulation -150 mm SSL Kingspan ThermaroofTR27 LPC/FM (ToS) 37.780 (ToS) Kingspan ThermaroofTR27 LPC/FM upstand to be used NB: 25 mm thick 37.580 around the perimeter of the roof on the internal faรงade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -Vapour control layer -75mm screed as spec ref M10.110 U-Value <0.15W/m2K.
1st floor Ground Floor Construction Solid Concrete Ground Based Floors - Vinyl floor finish as floor finishes drawings 401-402 -250mm thick concrete slab to Structural Engineer's details -Separation layer lapped (minimum 150mm)
X102 KITCHEN First Floor .930
X014 SERVER
64
8
S ITE
VISIT 6
Date: 13 February 2018 Weather: Cloudy, with strong wind Temperature: 5 °C People on site: 60 to 70
• Project manager
• Contractors
• Workers
• Mechanicians
• Students and tutors
P ROGRAMME
8.1
siw week Programme
28/02/2018
Stepnell ltd
Line
Name
Duration
Start
February 19 26 -2 -1
Finish
1
External Envelope
6w
2
SFS 4th - 5th
3
SFS 5th - 6th
4
BWK grnd - 1st
1w 19/02/2018 A 23/02/2018 A
5
BWK 1st - 2nd
2w 26/02/2018 A
09/03/2018
6
BWK 2nd -3rd
2w
12/03/2018
23/03/2018
7
BWK
2w
26/03/2018
10/04/2018
8
Curtain walling 3rd -4th
1w 20/02/2018 A 26/02/2018 A
9
Curtain walling 4th - 5th
1w 28/02/2018 A
06/03/2018
10
Curtain walling 5th - 6th
1w
08/03/2018
14/03/2018
11
Corten grnd - 1st
2w
26/02/2018
09/03/2018
12
Corten 1st - 2nd
2w
05/03/2018
16/03/2018
13
Corten 2nd - 3rd
2w
12/03/2018
23/03/2018
3rd - 4th
19/02/2018
Glenn Reeves
03/04/2018
1
1w 19/02/2018 A
23/02/2018
2
1w 26/02/2018 A
02/03/2018
1
5
2
2018 March 12 19 3
4
26
5
April 9
2
6
The contractor set a 6-week programme on the tasks they target to complete. It takes into account of the delayed tasks that they have not finished and tried to do more works at the same time to meet the end date eventually. According to the programme, the following tasks should be completed or in progress on 20 March 2018.
3
4 5 6 7
8 9 10
11 12 13
Ground Floor Internal Finishes 14
Under floor heating
1w
05/03/2018
09/03/2018
15
Screeding
1w
12/03/2018
16/03/2018
16
M&E 1st fix
2w 19/02/2018 A
02/03/2018
17
Plastering
1w
05/03/2018
09/03/2018
18
2nd fix M&E
2w
07/03/2018
20/03/2018
Task are EXPECTED finished: • Steel Frame System (SFS) • Curtain walling • Lift shaft
14 15 16 17 18
1ST FLOOR 19
M&E 1st fix
1w 19/02/2018 A 23/02/2018 A 19
20
Plastering
1w
26/02/2018
02/03/2018
21
2nd fix M&E
2w
12/03/2018
23/03/2018
Task are EXPECTED in progress: • Brickworks • Corten steel claddings • 1st & 2nd fix of M&E • Plastering • Roof works
20 21
2nd FLOOR 22
1st fix M&E
1w 26/02/2018 A
02/03/2018
23
Plastering
1w
12/03/2018
16/03/2018
24
Screeding
1w
05/03/2018
09/03/2018
24
25
22 23
3RD FLOOR 25
1st fix partitions
1w 05/03/2018 A
09/03/2018
26
1st fix M&E
2w
08/03/2018
21/03/2018
27
Plastering
1w
19/03/2018
23/03/2018
26 27
Task are in ACTUAL progress: • Brickwork on 2nd floor • Plastering • Screeding on ground & 2nd floor • Roof works • Partitions • M&E
4TH FLOOR 28
1st fix partitions
1w 12/03/2018 A
16/03/2018
29
M&E 1st fix
2w
19/03/2018
03/04/2018
2w
26/02/2018
09/03/2018
30
31
28 29
LIFT SHAFT 30
SFS ROOF WORKS
31
Plant room steel
1w 26/02/2018 A
02/03/2018
32
Parapet works
1w
05/03/2018
09/03/2018
33
Main coverings / Insulation
2w
12/03/2018
23/03/2018
32 33
Floor Level Ground
1st
Drawn by: Planner - Chart Properties Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
2nd
Dwg No. 00001
7
3rd
Revision No. A
4th
Plantroom
Roof
Notes: Comment - Chart Properties
Planned by Asta Powerproject
66
8.2
P OLICIES
T O E X T R E M E W E AT H E R
1 MARCH (THU) SNOW Due to the snow in 1 March 2018, the programme has delayed for a week and this affects the schedule afterward and may delay the contractor in finishing all the construction work on time. Therefore, they went on negotiating with the project team in the case of claiming an â&#x20AC;&#x2DC;abnormal weatherâ&#x20AC;&#x2122;. The contract defined the abnormal weather basing on a 3-5 years historical data and the stance of the project team is that the snow in 1 March is extreme but not abnormal. Also, as the workers only stop working for a day, instead of a whole week, it should not be a huge delay and should be able to complete on the end date, 11 June. The delay is mainly due to deliveries of brickworks, screeding works, and external claddings as they need to be resequenced accordingly. It did not affect the whole programme, just some elements in the programme. As there are no external claddings ,the building is fully exposed and the snow can go into the building. Workers may need extra time to clear the snow and ice when they came back.
67
S UPERSTRUCTURE:
8.3
G
Ed
223
Ec
Eb 2279
A
ROOF
Ee
3562
B
1646
C
1492
D
C 222
4452
Ea
2951
F
E
E
Final setting out of Roof-Terrace to be confirmed :
6752
300
300
4550
GENERAL NOTES
443.5
D 301
GENERAL NOTES
External Walls Semi−intensive Green Roof Covering System construction 2- Terrace Roof System build-up + Thermal rier etation bar vegetation barrier Wall Construction - Corten Outer / SFS Inner (Plant Room) 1 1 pebble veg performance, Roof Falls, pebble Drainage to be confirmed 11 30mm Deep Corten Cassettes -75 x 225mm C24 floor joists @ 400mm c/c's, as f following details from Roofsedsubcontractor um roof 1a sedum roo Gst to be 69mm Air Gap with Vertical Rails on HH Brackets Structural Engineers specification ing out of Roof-Terrace confirmed : GENERAL NOTES GENERAL NOTES Top of Coping 150mm Rockwool DuoSlab Insulation -Plywood decking as spec ref J42.110B 443.5 Detail U - 301 Top of Masonry 58.922 cies roof G H Ee 2 mixed spe 58.837 12.5 KnaufWindliner Sheathing Board -3mm vapour control layer Top of Coping 1 External Walls Semi−intensive Green Roof Covering System construction e Roof System build-up + Thermal Top of Masonry 58.622 150mm SFS Zone, Filled with RW45 Insulation setting out of Roof-Terrace to be confirmed : ToS - 50 mm thick upstand to be used around the perimeter of GENERAL NOTES GENERAL NOTES 58.537 1ance, Roof Falls, Drainage toFinal Wall Construction Corten Outer / SFS Inner (Plant Room) 1 443.5 58.378 be confirmed 11 12.5mm Plywood and 12.5mm GB Plasterboard and skim + the roof on the internal façade of parapets Tables & setting Tables & Benches 30mm Deep Corten Cassettes -75 x 225mm C24 f loor joists @ 400mm c/c's, as (flexible) (flixed) exposed A minimum distance 300 Covering mm to beSystem maintained between details from Roof subcontractor External concrete Walls columns Semi−intensive GreenofRoof construction 2- Terrace Roof System build-up + Thermal Terrace Wall Construction - BlockworkTables Outer / SFS Inner 69mm Air Gap with Vertical Rails on HH Brackets & Benches Structural Engineers specification U-Value = 0.18W/m2K the topRoom) of the insulation upstand and the bottom of the Corten planters Wall Construction - Corten Outer / SFS Inner (Plant 100mm fairf aced medium density blockwork(fixed) - F10/225 1 of Coping 150mm Rockwool DuoSlab Insulation perf ormance, Roof Falls, Drainage to be conf irmed -Plywood decking as spec ref J42.110B 11 & frames uplit from G H Ee horizontal roofC24 insulation. 3 50mm 22 30mm Deep Corten Cassettes -75 x 225mm floor joists @ 400mm c/c's, as either sideAir Gap with Brick Ties and Support Brackets 12.5 KnaufWindliner Sheathing497 Board -3mm vapour control layer 3no. uplights following details from Roof subcontractor Wall - Brickwork / SFS Inner of Coping -1.60 tapered insulation zone to form the fall 150mm Rockwool DuoSlab Insulation Top of Masonry Top Gst 69mmConstruction Air Gap with Vertical Rails onOuter HH Brackets Structural Engineers specif ication 58.622 150mm SFS Zone, Filled with RW45 Insulation 50 mm thick upstand to be used around the perimeter of 102.5 Black Brick as F10/110 58.537 Fst -1.5mm f ully-adhered single ply membrane as S45.110A Gst Cst Est 12.5 Knauf Windliner Sheathing Board of Coping: 150mm Rockwool DuoSlab Insulation -Plywood decking as spec ref J42.110B ing out of Roof -Terrace to ofbe confTop irmed 12.5mm Plywood and 12.5mm GB Plasterboard and skim + Detail U - 301 Top the roof on the internal f açade of parapets Masonry G H Ee 2a 58.922 GENERAL NOTES3 GENERAL NOTES 50mm Air Gap with Brick Ties and Support Brackets -root layer(s) as J42.110B 150mm SFS Zone, Filled with RW45 Insulation 58.837 443.5 12.5 Knauf Windliner Sheathing Board -3mmbarrier/protection vapour control layer
The superstructure of the roof has completed and currently, the workers are constructing the structure of the plant room on the roof terrace, then the green roofing.
8400
JT3 .5x35 35 JT3 .5x35 35
220 A
1/2 bricks) 5738(25
6000
300
2400
1800
4554
bricks) 6740(305873
4800
2400
MJ
1800
1/2 bricks)
7078
bricks) 15065(67 1135 ED 07
MJ
2588(11
MJ
440(2 bricks)
pebble vegetation barrier
2400
1800
2100
220
300
3650
1800
2400
1800
300
A
2100
4742
3900
Green Roof as Q37 on single ply membrane as J42.110A
exposed concrete columns A minimum distance of 300 mm to be maintained between Top of Coping 150mm -drainage layer, upstand filtration to layer, substrate to depth required of Top of Masonry 58.622 150mm Rockwool SFS Zone, DuoSlab Filled withInsulation RW45 Insulation the top of the insulation upstand and the bottom - 50 mm thick be used around the perimeter U-Value = 0.18W/m2K ofsemi-intensive the 58.537 External Walls Semi−intensive Green Roof Covering System construction 12.5 Knauf Windliner Sheathing Board -80mm roof 12.5mm Plywood and 12.5mm GB Plasterboard and skim + roof insulation. the roof on the internalgreen façade ofcovering parapetsas Q37.120A horizontal Wall Construction - Corten Outer / SFS Inner GENERAL NOTES GENERAL<0.15W/m2K. NOTES Zone,columns Filled11 with RW45 Insulation (Plant Room) U-Value Ed SFS 443.5Outer 150mm 6a exposed concrete A minimum distance of 300 mm to be maintained between Wall - Brickwork / SFS Inner -1.60 tapered insulation the fall 30mmConstruction Deep Corten Cassettes -75skim x 225mm C24 floor zone joists to @form 400mm c/c's, as 12.5mm and 12.5mm GB Plasterboard and + Ec U-ValuePlywood = 0.18W/m2K the top of the insulation upstand and the bottom of the 102.5 Black Brick as F10/110 -1.5mm f ully-adhered single ply membrane as S45.110A 69mm Air Gap with Vertical Rails onX605 HH Brackets External concrete Walls columns Semi−intensive Green Roof Covering System construction Structural Engineers specification exposed horizontal roof insulation. Eb EXTERNAL PLANT 50mm Gap with1DuoSlab Brick Ties and 49 Support Brackets -root barrier/protection layer(s) as J42.110BSemi−intensive 150mmAirRockwool Insulation ED 08 Wall Construction - Corten Outer / SFS Inner (Plant Room) Green Roof Covering System construction -Plywood decking11 as spec ref J42.110B U-Value = 0.18W/m2K m2 497 Ee Wall Construction - Brickwork Outer / SFS Inner -1.60 required tapered insulation zone to form the fall 150mm Rockwool DuoSlab Insulation -drainage layer,control filtration layer, substrate to depth 30mm Deep Corten Cassettes 12.5 Knauf Windliner Sheathing Board -3mm vapour layer -75 x 225mm C24deck floortojoists @ 400mm c/c's, details as -350mm concrete Engineer's 102.5 Black Brick as F10/110 -1.5mm fully-adhered singleStructural ply membrane as S45.110A 12.5 Knauf Windliner Sheathing BoardInsulation Q37.120A 69mm AirCurtain Gap with Vertical Rails on HH Brackets -80mm 150mm SFS Zone, Filled with RW45 - 50 mmsemi-intensive thick upstandgreen to beroof usedcovering around as the perimeter of Structural Engineers ication Detail R -3301 GENERAL NOTES GENERAL NOTES External Walls -3mm vapour controlspecif layer 50mm Air Gap with Brick Ties and Support Brackets -root barrier/protection layer(s) as J42.110B M<0.15W/m2K. 14/02/18 12 Amendments to internal partitions and door position MLD 150mm SFS Zone, Filled with RW45 Insulation U-Value 150mm Rockwool DuoSlab Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim +- ref the roof on the internal façade of parapets --Plywood as spec ref ED09 Various Systems er to windows 50 mm decking thick be J42.110B used around the perimeter H Eeschedule Drawings 150mm Insulation -drainage layer, upstand filtration to layer, substrate to depth required of L 12/01/18 MJ, CFB, Bricks setting out and downpipe position added MLD 12.5mm Plywood columns and 12.5mm GB Plasterboard andRockwool skim + DuoSlab 12.5 Knauf Windliner Sheathing Board exposed -3mm vapour layer A minimum distance ofto300 mm to beSystem maintained between External concrete Walls Semi−intensive Green Covering construction 322-324 the roof on thecontrol internal façade ofcovering parapetsas Q37.120A AmendmentsRoof roof layout following the FFI inf o Top of Coping 12.5 KnaufWindliner Sheathing Board -80mm semi-intensive green roof exposed concrete columns Top of Masonry 13/12/17 Amendments to upstand wall construction and Steel the bottom MLD 58.622 150mm Filled 7with RW45 Insulation the U-Value = 0.18W/m2K - 50 mm thick upstand to bemm usedshould around perimeter of topRoom) ofK the insulation and of the Wall Construction - Corten Outer / SFS InnerSFS Zone, U-Value 0.15W/m2K A minimum distance of 300 bethe maintained Column positions following the SE info 58.537 150mm SFS=Zone, Filled11 with RW45 Insulation (Plant U-Value <0.15W/m2K. U-Value = Corten 0.18W/m2K Semi−intensive Green Roof Covering 07/11/17 Amendments to wall construction Steel System MLD 12.5mm Plywood and 12.5mm GB Plasterboard and skim +J roof theconstruction roof façade ofupstand parapetsand the bottom horizontal insulation. 30mm Deep Cassettes -75 x 225mm C24 floor joists @and400mm c/c's, as on G-value of glass 0.35 GB MJ (1 9.200) between thethe topinternal of the insulation Column positions 12.5mm Plywood and=12.5mm Plasterboard and skim +concrete 54.647 -350mm deck to Structural Engineer's details exposed concrete columns Wall - Brickwork / SFS Inner A minimum distance 300 mm to be maintained between -1.60 tapered insulation zone to theform all 69mmConstruction Air Gap with Vertical Rails onOuter HH Brackets I Engineers 18/09/17 Change specif to the slab edge following Cladding the f MLD Structural ication of the horizontal roofof insulation. & Windows info. Amendments to Stair 1 exposed concrete columns Type 1 External Curtain Walls -3mm vapour control layer U-Value = 0.18W/m2K 102.5 Brick as F10/110 the toptapered of the insulation upstand the of the -1.5mm fHdecking ully-adhered single ply membrane as S45.110A 150mmBlack Rockwool DuoSlab Insulation -Plywood as spec ref J42.110B 30/05/17 Amendments to HEC stair 2 following the SE info MLD -1.60 insulation zoneCovering to fand orm System the bottom fall construction 12 EescheduleU-Value = 0.18W/m2K Semi−intensive Green Roof Gthick 12/05/17 Amendments toto drawings following the Topo MLD Various Systems ref er to windows Drawings bricks) 50 mm upstand be used around the perimeter of 1/2 6 er to 4387(19 GA Floor Plan drawings (2588 201-207) -root 50mm Air Gap with Brick Ties and SupportRef Brackets horizontal roof insulation. as J42.110B-1.5mm 12.5 Knauf Windliner Sheathing -3mmbarrier/protection vapour control Survey andlayer SElayer(s) info ply membrane as S45.110A 3938(17 1/2 bricks) Board CFB 9337.5(41 1/2 bricks) MJ -350mmfully-adhered concrete decksingle to Structural Engineer's details Type 2 497 F 19/01/17 Change to doors and Stair 1 Lobby MLD 322-324 MJ the roof on the internal f açade of parapets 6693 150mm Rockwool DuoSlab Wall Construction - Brickwork Outer / SFS Inner -1.60 tapered of insulationlayer(s) zone to form the fall -drainage layer, filtration layer, substrate to depth required SFSDetail Zone, Filled withInsulation RW45 Insulation - 50 mm Ethick upstand to be used around the perimeter -roof barrier/protection 10/01/17 Spec Refs added MLD R - 301 6967 58.537 External Curtain Walls -3mm vapour control layer U-Value = 0.15W/m2K D 23/12/16 Amendments to300 drawings mm should beMLD A distance ofgreen maintained 12.5 Knauf Windliner 102.5and Black Brick as F10/110 -1.5mm fully-adhered single ply membrane as S45.110A -80mm roof Q37.120A 12 12.5mm Plywood and Sheathing 12.5mm Plasterboard skim +- ref theminimum roofsemi-intensive on the internal façade ofcovering parapetsas 12.5 KnaufWindliner Sheathing Board layer, substrate to depth required of -drainage layer, upstand filtration C 09/12/16 Amendments to drawings MLD Type GB ABoard Various Systems er to windows schedule Drawings Ee - 50the mmbottom thick to be used around the perimeter G-value of glass = 0.35 MJ (1 9.200) between the top of the insulation upstand and 3 B 30/11/16 Amendments to drawings MLD 150mm Zone,columns Filled with RW45 Insulation 50mm Air Gap with Brick Ties andTop Support -root barrier/protection layer(s) ascovering J42.110B U-Value <0.15W/m2K. exposed SFS concrete 150mm SFS Zone, Filled with RW45 Insulation of CopingBrackets A minimum distance of 300 mm to be maintained between -80mm semi-intensive green roof as Q37.120A 54.647 A 25/11/16 Amendments to drawings MLD 322-324 Top of Masonry 53.447 the roof on the internal f açade of parapets Terrace Wall Construction - Blockwork Outer / SFS Inner Detail I 300 of the horizontal roof insulation. 13 12.5mm Plywood and 12.5mm GBLifPlasterboard and skim + Steel columns 12.5mm 150mm and 12.5mm andRockwool skim + DuoSlab -drainage layer, filtration layer, substrate to depth required U-ValuePlywood = 0.18W/m2K the top of the insulation upstand and the bottom of the 53.362 Insulation Type GB 1*Plasterboard U-Value <0.15W/m2K. t X605Gst Type 1 U-Value = 0.15W/m2K 100mm fairfaced medium density blockwork - F10/225 A minimum distance of 300 mm should be maintained -1.60 tapered 12.5 KnaufWindliner Sheathing Board exposed concrete columns -80mm semi-intensive green roof covering as Q37.120A horizontal roofinsulation insulation.zone to form the fall EXTERNAL 50mm Air Gap with Brick Ties and Support Brackets G-value of glass = 0.35 MJ (1 9.200) between the top of the insulation upstand and the bottom Ref er to GA Floor Plan drawings (2588 201-207) 497 -1.5mm f ully-adhered single ply membrane as S45.110A CFB 150mm SFS Zone, Filled with RW45 Insulation U-Value = 0.18W/m2K Semi−intensive Green Roof Covering System construction U-Value <0.15W/m2K. Wall Construction Brickwork Outer / SFS Final setting out of Roof-Terrace to be conf irmed : Inner 54.647 -1.60 tapered insulation zone to f orm the f all Type 2 T errace Roof System GENERAL NOTES GENERAL NOTES PLANT ROOM 2146 1416 150mm Rockwool DuoSlab Insulation X503 443.5 of the horizontal roofconstruction insulation. -roof barrier/protection layer(s) 12.5mm Plywood and 12.5mm GB Plasterboard and skim +concrete decksingle -350mm to Structural Engineer's details 102.5 Black Brick as2- TF10/110 1build-up + Thermal -1.5mm ply membrane as S45.110A -350mm to Green 6thinsulation floor 275mm to 5th deck External Walls fully-adhered Semi−intensive Roof Coveringand System construction 12.5 KnaufWindliner Sheathing Board errace Type Roof System X605 COMPUTER SUITE -1.60 tapered zone to form the ffloorconcrete all W all Construction Corten Outer / SFS Inner (Plant Room) 1 -drainage layer, f iltration layer, substrate to depth required perf ormance, Roof Falls, Drainage to be conf irmed 11 Detail R -3301 4800 External Walls Type A 5873 4554 exposed concrete columns -3mm vapour control layer 50mm AirCurtain Gap with Brick Ties and Support Brackets -root barrier/protection layer(s) as J42.110B 150mm SFS Zone, Filled with RW45 Insulation 30mm Deep Corten Cassettes -75 x 225mm C24Engineer's floor joists @ 400mmdetails c/c's, as to Structural EXTERNAL Ref er to GA Floor Plan drawings (2588 201-207) following details from Roof subcontractor 12 Architects, & Interior Design -1.5mm f ully-adhered single ply membrane as S45.110A 4554 Detail Q - 301 Cst Est Est FstFst Gst 69mm Air Gapsemi-intensive with CFB Vertical Rails13 onLandscape HH Brackets Top of Coping Structural Engineers specif ication Gst Cst -80mm green roof covering as Q37.120A Type 2 53.447 Various - ref er Top to of windows schedule Drawings = 0.18W/m2K H U-Value Semi−intensive Green Roof Covering System construction - 50 thick to be used around the perimeter of 12.5mm Plywood and 12.5mm GB1646 Plasterboard and skim + Steel columns 150mmSystems Rockwool DuoSlab Insulation -drainage layer, filtration layer, substrate to depth required Masonry 150mmmm Rockwool DuoSlab upstand Insulation -Plywood decking as spec ref J42.110B -3mm vapour control layer 2279 3562 1492 G ROOM A B C PLANT D E G Ee Detail I - 300 -roof barrier/protection layer(s) 12.5 KnaufWindliner Sheathing Board -3mm vapour control layer C 53.362 Type 1* F U-Value 322-324 223 311 -350mm concrete deck Structural Engineer's the roof on<0.15W/m2K. the façade ofcovering parapetsas 12.5 KnaufWindliner ToS Sheathing Board -80mm semi-intensive green roof Q37.120A 150mm SFS Zone, Filled withinternal RW45 Insulation - 50 mm thick upstandfor to be pedestal used aroundto the perimeter of -tapered zone to allow falls from onedetails side to 13 11 222 6128 4959 -drainage layer, iltration 2279 3562 1646 1492 7718 58.378 Type A 12.5mm Plywood and 12.5mm GB Plasterboard and skim + the roof on the internal ff açade of parapetslayer, substrate to depth required Detail R - 301 U-Value 0.15W/m2K External Curtain Walls -3mm vapour control layer A minimum distance of 300 mm should be maintained 150mm SFS= Zone, Filled with RW45 Insulation exposed concrete<0.15W/m2K. columns U-Value Aother minimum distance of 300 mm to be maintained between the of 1.60 tapered insulation zone to form the fall ( A B C D E F G Terrace Wall Construction - Blockwork Outer / SFSHInner Top of Coping -80mm semi-intensive green covering as Q37.120A U-Value = 0.18W/m2K 12 the top of the insulation upstand and the bottom ofroof the 100mm f airf aced medium density blockwork F10/225 T errace Roof System construction Top of Masonry G-value of glass 0.35 GB Plasterboard (1 6.200)between the top of the insulation upstand and Various Systems refer to windows53.447 schedule MJ (1 9.200) -within 50the mm thick upstand bottom 12.5mm Plywood and=12.5mm and skim +-Brackets horizontal roof insulation. Detail IMJ - Drawings 300 the pedestal zone)to be used around the perimeter of 50mm Air Gap with Brick Ties and Support X605 497 53.362 Type 1* 13 U-Value 51 .647 Wall Construction - Brickwork Outer /Group SFS Inner 54.647 -1.60 tapered<0.15W/m2K. insulation zone to form the fall Conf etti Media 150mm Rockwool DuoSlab Insulation -350mm to 6th f loor and 275mm to 5th f loorconcrete deck Gst 322-324 Type 1* Type 1* Type 1* the roof on thesingle internal of parapets of102.5 theBlackhorizontal Brick as F10/110 roof insulation. -1.5mm fully-adhered ply membranef as S45.110A exposed concrete columns 12.5 KnaufWindliner Sheathing Board - 50-root mm thick upstand toaçade be used around the perimeter of 13 EXTERNAL 3 50mm Air Gap with Brick Ties and Support Brackets barrier/protection layer(s) as J42.110B 150mm SFS Zone, Filled with RW45 Insulation Type 1 to Structural Engineer's details U-Value 0.15W/m2K 12.5mm Plywood and 12.5mm= GB Plasterboard and skim + 13 Steel columns 150mm Rockwool DuoSlab Insulation A minimum distance ofto300 mm be maintained -1.60 tapered insulation zoneCovering to form System the fall -drainage layer, filtration layer, substrate required U-Value = 0.18W/m2K Timber Structure to be confirmed following Semi−intensive Green Roof construction X602 PROPOSED TERRACE FLOOR GA PLAN -1:150 the roofRoof on the internal fasdepth açade ofshould parapets 12.5 KnaufWindliner Sheathing Board -80mm semi-intensive green roof covering Q37.120A T errace System construction STAIR 2 details from SE X503 PLANT ROOM Refer to GA Floor Plan drawings (2588 201-207) -3mm vapour control layer G-value of glass = 0.35 150mm SFS Zone, Filled with Insulation MJ (1 9.200)-350mm U-Value <0.15W/m2K. CFB between thedistance top of the insulation upstandbeand the bottom -1.5mm fully-adhered single ply membrane asminimum S45.110A CFB concrete deck to Structural Engineer's details Conf ettiRW45 CQ Campus A of 300 mm should maintained Type 2 12.5mm Plywood and 12.5mm GB Plasterboard and skim + -350mm to 6th f loor and 275mm to 5th floorconcrete deck 54.647 X603 X604 X601 X605 COMPUTER SUITE -tapered zone f or pedestal to allow f alls f rom one side to exposedbarrier/protection concrete columns control layer Indicative line of blockwork to form Detail R stairs - 301PLANT ROOM PARTITION Wall Type 1 Curtain Walls -roof layer(s) of the horizontal roof External -3mm vapour STAIR 2 LIFT LOBBY EXTERNAL between the top of theinsulation. insulation upstand and the bottom Type 1 Movement joint U-Value = 0.18W/m2K 2no.layer of 12.5mm Soundblock either side,16mm Resilient Bar fType ixed to one side, 92mm CROOM studs Semi−intensive Green Roof Covering System construction (drainage chute position to be agreed) to Structural Engineer's details 1 LOBBY PLANT 12 6 Detail L 300 the other of 1.60 tapered insulation zone to f orm the f all ( 13 with 50mm Isover between studs. Skim finish to both partition. -350mm concrete deck to Structural Engineer's detailsto form the fall layer, f iltration layer, substrate to depth required Various Systems refsides erofto windows schedule Drawings -1.60 tapered insulation zone --drainage 50 mm thick upstand to be used around the perimeter of Type A of the horizontal roof insulation. External Curtain Walls -3mm vapour vapour control control layer Roof - Terrace Plan GA -3mm layer MJ (1 6.200) 12 Slab edge PARTITION Wall Type 2 Ref er to GA Floor Plan drawings (2588 201-207) within the pedestal zone) Various Systems - ref er to windows schedule Drawings roof covering as Top of Coping - 50 mm thick upstand to be used around the perimeter 322-324 -80mm semi-intensive Q37.120A fully-adhered single ply ofmembrane as S45.110A CFB the roof on theTypes internal façade Detail Q - 301 Type 2 13 51 .647 -1.5mm ully adhered single-ply membrane S42.110A 1no. Layer of 15mm Soundbloc either side of 92mm C StudsTop with of 50mm Isover APR Areas of pedestal to Masonry Roof and green Setting Outof parapets -1.5mm 322-324 Type 2 between the roof onf the internal façadepedestal of parapets 13 15 13 Detail I - 300 -tapered zone for to allow falls fromasone side to 15mm Soundbloc MR in WC Areas) Skim finish to both sides of partition. 53.447 support container planting -A 50 mm thick upstand to bemm usedshould around perimeter U-Value = 0.15W/m2K A minimum distance of of 300 mm should layer(s) be maintained 53.362 Type 1* studs. (UseU-Value = 0.15W/m2K -roof barrier/protection U-Value <0.15W/m2K. minimum distance of 300 bethe maintained -50mm Ballast (paving slabs on support) as Q37.140 G-value of glass = 0.35 6a between the top of the insulation upstand and insulation the bottom PARTITION Wall Type 3 the other of 1.60 tapered zone to f orm the fall ( the roof on the internal f açade of parapets of the horizontal roof insulation. Type 3 2588 1:50 @ A1 Jul-16 1no. Layer of 15mm Soundbloc MR side of 70mm= C Studs with 50mm Isover APR between G-value ofeitherglass 0.35 layer, substrate to depth required -drainage layer, f iltration MJ (1 9.200) between the top of the insulation upstand and the bottom Type 1 Type A U-Value <0.15W/m2K. MJ (1 6.200) -1.60 tapered insulation zone to f orm the f all studs. Skim finish to both sides of partition. the pedestal zone)as S45.110A 54.647 CFB Ref er to GA Floor Plan distance (2588 201-207) A minimum of 300 mmCFBshould be within maintained -1.5mm fsemi-intensive ully-adhered single ply membrane 13 .647 Top of Coping51 Type 2 -80mm green roof covering as Q37.120A Terrace Roofdrawings System construction of the horizontal roof insulation. -roof barrier/protection layer(s) Top of Masonry PARTITION Wall Type A 53.447 ID 001, etc - Internal Door Codes (Refer to drawing - 50the mmlayer, thick upstand to be used around the perimeter of Type 1* Type 1 Detail I Type -320) 300 Type 1 M Construction X403 7 Type A Type A 3no. Layers 15mm Soundbloc either side of BG 146mm CX405 Stud at 300mm Centres within 148mm -drainagebottom filtration layer, substrate to depth required between the top insulation upstand and A 53.362 W001, etc - Window Codes (Refer to drawings 322-323) Type 1* U-Value <0.15W/m2K. -350mm to207 6th fof loorthe and 275mm to 5th ffloorconcrete deck -1.60 tapered insulation zone to form theMLD all Second Floor Construction (LRC)of parapets Head and base channels. 75mm Isover APR between studs with Skim finish to both side of green roof covering as Q37.120A Detail L - 300 Gst ED01, etc - External Door Codes (Refer to drawings 323) the -80mm roofsemi-intensive on the internal façade partition. COMPUTER SUITE SUITE Type321) 1* of the horizontal roof insulation. U-Value <0.15W/m2K. IS01, etc - Internal Screene Codes (Refer to drawings Refer to GA Floor drawings (2588 201-207) Cst Est Fst Gst Plan COMPUTER to Structural Engineer's details -1.5mm f ully-adhered single ply membrane as S45.110A CFB -275mm concrete deck to Structural Engineer's details 13 CFB Type 2Wall Type 1 - without16mm Resilient Bar Type 2Type 1* PARTITION Aasminimum distance Terrace Roof System construction of 300 mm should be maintained -1.5mm f ully adhered single-ply membrane S42.110A X512 X513 X511 X503 Terrace Roof -3mmbarrier/protection vapour control -roof layer(s) -3mm vapour control -350mm to 6th floorSystem and 275mm toconstruction 5th floorconcrete deck X503 STAIR 2 STAIR 2 CORRIDOR COMPUTER SUITE 14 layer between the top of thelayer insulation upstand and the bottom to Structural Engineer's LOBBY (paving slabs support) asdepth Q37.140 13falls to -350mm to floorasand to 5th floorconcrete deck -taperedBallast zone pedestal toon allow from one side to6thlayerdetails Detail L - 300-50mm layer, substrate required -drainage layer,for filtration -50 mm Kooltherm spec275mm ref M10.290B -3mm vapour control COMPUTER SUITE Type A of the horizontal roof insulation. -tapered zone for pedestal to allow falls from one side to U-Value <0.15W/m2K. Top of Coping toform Structural Engineer's details the othersemi-intensive of 1.6013 tapered insulation zone to the fall (asinsulation -80mm green roof covering as Q37.120A the other of 1.60 tapered zoneref to formM10.130 the fall ( -75mm screed spec MJ (1 3.275) Top of Masonry 53.447 -1.5mm ully adhered single-ply membrane as S42.110A Detail IMJ - 300 within the f pedestal zone) 15 (1 6.200) 13 48.722 53.362 control layer within the <0.15W/m2K. pedestal zone) Type 1* U-Value - 50 mm thick upstand to beas usedf around thefinishes perimeter of drawings 401-402 --3mm Vinyl fvapour loor finish loor 13 X405 Type A 51 .647 -50mm Ballast slabs on support) as Q37.140 the roof on the internal f(paving açade of parapets (LRC) -Second 50 mmFloor thickConstruction upstand to be used perimeter CFB around the -tapered pedestal to allow falls from one side to A minimumzone distance of offor 300 mm should be maintained COMPUTER SUITE U-Value between the <0.15W/m2K. top of the insulation upstand and the bottom -275mm concrete deck Structural Engineer's details the roofRoof on the internal fto açade of parapets the ofother ofroof 1.60 tapered insulation theConstruction horizontal insulation. Terrace System construction Floors (1st, 3rd, 4th, 5th)zone to form the fall ( CFB -1.5mm fully adhered single-ply membrane as S42.110A MJ (1 6.200)A -3mm vapour control layer CFB 14 minimum distance 300 mm should maintained within the pedestal zone)astoQ37.140 -50mm Ballast (paving slabs ondeck support) X403 X405 Type A -350mm to 6th floor of and 275mm to 5thbefloorconcrete deck -275mm concrete Structural Engineer's details X412 13 51 .647 Second Construction (LRC) U-ValueFloor <0.15W/m2K. STAIR 2 -50 mm Kooltherm as spec ref M10.290B Type 1 Type 1 Type 2 - 50the mmbottom thicklevelling upstandscreed to be used around the perimeter of between the top of the insulation COMPUTER SUITE COMPUTER SUITE to Structural Engineer's details upstand and 15 -10mm latex X413 X411 X403 X405 13 Second Floorconcrete Construction (LRC) -275mm deck to Structural Engineer's details Detail L - 300 Type A STAIR 2 CORRIDOR COMPUTER SUITE COMPUTER SUITE-75mm screed as spec ref M10.130 -275mm concrete deck to Structural Engineer's details of parapets MJ (1 3.275) the roof on fthe internal façade of the horizontal roof layer insulation. -3mm vapour control --3mm Vinyl floor inish as floor LOBBY -3mm vapour vapour control control layer layerfinishes drawings 401-402 14 48.722 14 --1.5mm Vinyl f loor f inish as f loor f inishes drawings 401-402 CFB -50 mm Kooltherm as spec ref M10.290B Aasminimum of 300 mm should be maintained ully adhered single-ply membrane S42.110A -tapered fzone for pedestal to allow falls from side todistance -75mm screed as spec ref M10.130 -50one mm Kooltherm as spec ref M10.290B - Vinyl fthe loorthe finish astop floor drawings 401-402 between of the insulation upstandGround and theBased bottom -50mm (paving slabs on support) Q37.140 the otherBallast of 1.60 tapered insulation zone as toGround form fall (asfinishes Floor Construction Concrete 15 -75mm screed spec ref Solid M10.130 Detail - 300Floors Construction (1st, 3rd, 4th, 5th) MJ (1L3.275) MJ (1 6.200) Floorshorizontal Construction (1st, 3rd,roof 4th, 5th)insulation. CFB of the U-Value <0.15W/m2K. CFB within the pedestal zone) Floors 48.722 -275mm concrete deck to Structural Engineer's details 13 51 .647 - Vinyl floor finish as floor finishes drawings 401-402 -275mm concrete deck to Structural Engineer's details 15 -10mm latex levelling screed -1.5mm fullyasadhered single-ply as S42.110A - 50 mm thick upstand to be used around the perimeter of as drawings - Vinyl floor finishesmembrane drawings 401-402 - Vinylf floor loor finishfinish floor finishes 401-402 X405 Type A 15 -10mm latex levelling 16 screed Type A Second Construction (LRC)of parapets -50mm Ballast (paving slabs on support) as Q37.140 the roofFloor on the internal façade -75mm screed as spec ref M10.130 Ground Based Ground Floor Construction Solid Concrete X303 X305 Floors Construction (1st, 3rd, 4th, 5th) COMPUTER SUITE Vinyl f loor f inish as f loor f inishes drawings 401-402 Floors CFB CFB -275mm concrete deck to Structural Engineer's details U-Value <0.15W/m2K. A minimum distance of 300 mm should be -275mm -maintained Underf loor Systems - Vinyl floor finish asHeating floor finishes drawings 401-402 refer to M+E Engineer's COMPUTER SUITE COMPUTER SUITE concrete deck to Structural Engineer's details 16 Type A Type 2 Type 1 Type 1 -75mm screed as spec ref M10.130 X312 X313 X311 X303 X305 -3mm vapour control between the top of thelayer insulation upstand and the details 14 - Underfbottom loor Heating Systems refer to M+E Engineer's STAIR 2 STAIR 2 CORRIDORA COMPUTER SUITE COMPUTER SUITE 15 -10mm latex levelling screed X403 X405 Type Detail L - 300 detailsBased Ground Floor Construction Solid Concrete Ground LOBBY -50the mm Kooltherm asinsulation. spec ref M10.290B Second Floor Construction (LRC) (minimum 150mm) of horizontal roof -0.5mm separation layer lapped -0.5mm separation layer lapped (minimum 150mm) - Vinyl floor finish as floor finishes drawings 401-402 COMPUTER SUITE COMPUTER SUITE -50mm perimeter Insulation overlap min.150mm from Floors concrete toupstand Structural Engineer's details -75mm screed as specsingle-ply ref M10.130 -1.5mm fully adhered membrane -275mm as S42.110A -50mm Insulation overlap min.150mm from MJ (1 3.275) bottom ofperimeter wall insulation to topdeck of insulation -130mm Kingspan Kooltherm K103 Floor Board insulation --50mm ffinish as ffinishes drawings 48.722 -3mm layerto top of insulation upstand - Vinyl Vinyl ffloor loor inish(paving as ffloor loor inishes drawingsas401-402 401-402 Ballast slabs on support) Q37.140 15 under vapour concrete slab ascontrol spec ref M10.290A bottom of wall insulation 14 16 Type A Ground Floor Solid Concrete Ground Based -0.9mm damp proofConstruction membrane -75mm screed as spec ref M10.130 -50 -275mm mm thick Kooltherm as spec ref M10.290B X305 U-Value <0.15W/m2K. concrete slab to Structural Engineer's details -130mm Kingspan Kooltherm K103 Floor Board insulation CFB Floors -well compacted sub base to Structural Engineer's details MJ (9.750)-Floors Underf loor Heating(1st, Systems ref er to M+Eunder Engineer's Construction 3rd, 4th, 5th) -75mm screed as spec ref M10.130 COMPUTER SUITE U-Value = 0.11W/m2K spec ref M10.290A MJ45.1 (1 3.275) CFB 97 - Vinyl fconcrete loor finishslab as as floor finishes drawings 401-402 X405 Type A details 48.722 MLD drawings 401-402 28/02/18 Change Roof Terrace Structure, partitions , -275mm concrete Structural IEngineer's details - Vinyl ftoloor finish asinternal floor finishes Second Floor Construction -0.9mm damp proof membrane 16deck to (LRC) Type A external wallscreed build-up -75mm as spec ref M10.130 COMPUTER SUITE X303 X305 -0.5mm separation layer (minimum 150mm) 15 -10mm levelling screed -275mmlatex concrete deck tolapped Structural Engineer's details H 22/01/18 MJ, CFB, Bricksthick setting outconcrete and downpipe position added MLD -275mm slab to Structural Engineer's details Type 2 - Underf loor Heating Systems ref er to M+E Engineer's Type A COMPUTER SUITE COMPUTER SUITE -50mm perimeter overlap min.150mm from CFB MLD 5th) G 21/12/17 Amendments to Window W01sub(1st, --3mm Vinyl fvapour loor finish asInsulation floor drawings 401-402 Floors Construction control layerfinishes -well compacted base3rd, to 4th, Structural Engineer's details CFB 14 details F 08/11/17 Change to RoofTerrace external wall and roof build-up MLD X201 Mechanical X203 X205 bottom of wall insulation to top of insulation upstand -275mm to& Structural Engineer's details LRC Riser LRC COMPUTER SUITE-50 mm Kooltherm as spec ref M10.290B MLD E 25/10/17 Change to the concrete slab= edge0.11W/m2K followingdeck the Cladding U-Value -0.5mm separation layer lapped (minimum 150mm) Windows info. Amendments to 1st Floor Courtyard -130mm Kingspan Kooltherm K103 Floor Board insulation -10mm latex Ground Construction Concrete Ground -75mm Floor screed as15 spec ref Solid M10.130 D 30/05/17 Drawing Based status updatedlevelling to construction screed MLD MJMJ(1(9.750) 3.275) -50mm perimeter Insulation overlap min.150mm C 12/05/17 Amendments to drawings f ollowing the T opo MLD under concrete slab as spec ref M10.290A 48.722 14 I finishes 28/02/18 Change tofloor Roof Terrace Structure, partitions , from MLD 45.1 97 - Vinyl finish as floor finishesinternal drawings 401-402 Floors - Vinyl floor finish as floor drawings 401-402 Survey and SE info bottom of wall insulation to topMLDof insulation upstand B 10/01/17 Spec Ref s added damp proof membrane external wall build-up --0.9mm Vinyl floor finish as floor finishesCFBdrawings 401-402 A 23/12/16 Amendments to drawings MLD -130mm Kingspan Kooltherm K103 Floor Board insulation 312 16 Type A -275mm thick concrete slab to Structural Engineer's details Ground BasedMLD M10.130 Floor Construction Concrete screed as spec Floors Construction (1st, 3rd, 4th, 5th) REV. DATE MJ (9.750)-75mm DESCRIPTION BY X305 CFB Href 22/01/18 MJ,Ground CFB, Bricks andSolid downpipe position added under concrete slab out as spec ref M10.290A 45.1 97 -well compacted sub base to Structural Engineer's detailssetting - Underfloor Heating Systems refer toEngineer's M+EFloors Engineer's -275mm concrete deck to Structural details COMPUTER SUITE Type A -0.9mm damp proof membrane Timber Structure to be confirmed fU-Value ollowing = 0.11W/m2K - Vinyl floor to finish as floor finishes drawings 401-402 MLD details latex levelling screed G 21/12/17 Amendments Window W01 15 details from SE -10mm Type 2 -275mm thick concrete slab to Structural Engineer's details Type 1* Type A -75mm screedTerrace as spec ref M10.130 separation (minimum 150mm) --0.5mm Vinyl floor finish16 as layer floor finishes drawings 401-402 X101 X103 X102 CFB X303 X305 F lapped 08/11/17 Change to external wall and roof build-up X203 X205 -well compacted sub base to Structural Engineer's detailsMLD I 28/02/18 Change to Roof Terrace Structure, internal partitions , RoofMLD CAFE QUIET CAFE KITCHEN - Underf loor Heating Systems refer to M+E Engineer's MLD -50mm perimeter Insulation overlap min.150mm from COMPUTER SUITE COMPUTER SUITE LRC 25/10/17 Change to the&= slab edge following the Cladding & U-Value 0.11W/m2K external wall build-up E Architects, Landscape Interior Design details bottom of wallConstruction insulation toSolid top of insulation upstand Ground Floor Concrete Ground Based Windows info. Amendments to 1st Floor Courtyard 1 6-20 Bath Street, Nottingham NG1 1 DF -130mm Kingspan K103 Floor Board insulation -0.5mm separation layer lappedinternal (minimum 150mm) H 22/01/18 MJ,Floors CFB, Bricks settingKooltherm outI and downpipe position added MLD MLD 28/02/18 to Roof Tdesign@allanjoycearchitects errace Structure, partitions , D 30/05/17T Change Drawing status to construction MLD MJ (9.750) 01 1 5 841 841 8 E updated .co.uk 3
19
20
10
9
8
7
6
5
4
3
1627
2
1
3273(14 1/2bricks)
MJ
2320
514
11
100
221
12
Fifth Floor 55.324
MJ
18
1505
17
1010
16
2388
2902
15
3375(15 bricks)
910 100
50 795
2321
mixed species roof
JT3 .5x35 35 JT3 .5x35 35
2950
B
14
1
221 B
13
2
REV. DATE
2750
1
2750
N 2750
980
E
design@allanjoycearchitects .co.uk
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
2750
2817
3
19
Detail R - 301
PROJECT NUMBER
18
17
DATE
SCALE MJ (1 9.200) 54.647
Detail Q - 301
13
11
10
9
8
7
6
DRAWING NUMBER
REVISION
STATUS
BY
Top of Coping Top of Masonry 53.447 Detail I - 300
53.362 This drawing is copyright and remains the property ofAllan Joyce Architects Ltd
2750
3400
01 1 5 841 841 8
F
16
2750
3230
Fifth Floor
53.964 Plant Room External Wall 12 102.5 Black Brick as F10/110 200mm clear residual cavity 100mm fairfaced medium density blockwork - F10/225
T
Generally do not scale drawings. All dimensions to be checked on site.
4
3
3
T.O.S. 52.075
2
Fifth Floor 51 .924
19
SSL 51 .624
18
16
15
14
13
2750
3230
17
12
2655
3230
9
8
2945
3230
3230
11
10
Fifth Floor 50.054
MJ (1 6.200) 51 .647
A topping out ceremony was held on 9 March that the contractor, the clients and the architect celebrated the last piece of steel placing on the building by signing on top of it.
Detail L - 300
2655
1
2655
3230
5
Fifth Floor 51 .924
The roof aim at pushing the whole design of the building to a sustainable solution to the campus and the city. The design successfully achieves a rating of outstanding from the BREEAM, a certificate of green and sustainable design.
DRAWING
Roof-Terrace Floor 55.324
3400
JT3 .5x35 35
450
Terrace Wall Construction - Blockwork Outer / SFS Inner 100mm fairfaced medium density blockwork - F10/225 50mm Air Gap with Brick Ties and Support Brackets Detail PInsulation - 301 150mm Rockwool DuoSlab 12.5 KnaufWindliner Sheathing Board 15 150mm SFS Zone, Filled with RW45 Insulation 14 12.5mm Plywood and 12.5mm GB Plasterboard and skim + Steel columns
SSL 55.024
AVCL
1 6-20 Bath Street, Nottingham NG1 1 DF
Top of Coping Top of Masonry 58.622 58.537
20
2750
497 522
3599
50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board Top of SFS 150mm SFS Zone, Filled with RW45 Insulation 55.474 12.5mm Plywood and 12.5mm GB Plasterboard and skim + Steel columns
Top of Coping 55.547
BY
PROJECT
StairTerrace 2 External Wall Drawing 311 102.5 Black Brick as F10/110
Detail L - 301
AVCL
Top of Coping Top of Masonry 58.922 58.837
DESCRIPTION
CLIENT
Detail T - 301
Roof-Terrace Floor 55.324
Detail U - 301
2655
JT3 .5x35 35 JT3 .5x35 35 JT3 .5x35 35
Top of SFS 58.848
T.O.S. 58.378
JT3 .5x35 35 JT3 .5x35 35
Top of Coping 58.922
The architect has revised and confirmed the construction of the green roof. The roof possess about 700mm in depth. This is to ensure thermal performance internally as well as drain away water on the roof level, especially where there are greens.
7527.5(33 1/2 bricks)
3554
1930
600
JT3 .5x35 35 JT3 .5x35 35
685 12.5mm Plywood Paved Terrace Outer as Q37 on Terrace / SFS Inner and 12.5mm GB Plasterboard and skim + Steel columns ToS Wall Construction - Blockwork sigle ply membrane as 1e Roof System build-up + Thermal 6 J42.110A 100mm f airf aced medium density blockwork F10/225 58.378 Final setting out of Roof-Terrace to be confirmed : Air Gap with Brick Ties and Support Brackets 1 ance, Roof Falls, Drainage to50mm be conf irmed 497 3ast 150mm Rockwool DuoSlab Insulation Terrace Wall Construction3a- Blockwork Outer X601/ SFS Inner details from Roof subcontractor X605 opy PLANT 12.5 KnaufWindliner Sheathingbuild-up Board 100mmcanfairf aced medium density blockwork - F10/225 2Terrace Roof System + Thermal EXTERNAL 31 m2 3 9460(42 bricks) 150mm SFS Zone, Filled with RW45 Insulation 50mm Air Gap with Brick Ties and Support Brackets of Coping ormance, Roof Falls, GB Drainage be conf irmed DuoSlab Insulation 1200 G perf H ROOMto150mm 22 ( 42 bricks) 12.5mm Plywood and 12.5mmPLANT Plasterboard and9450 skim + Steel columns Rockwool MJ Ea 5737 2137 ED 09 1585 of CopingMechanical f ollowing details f rom Roof subcontractor 12.5 Knauf Windliner Sheathing BoardTop of Masonry Top ing out of Roof-Terrace to be conf irmed : Gst 58.622 6 riser 3 58.537 3st 443.5 150mm SFS Zone, Filled with RW45 Insulation Top of Coping 2339 Detail U - 301 Top of Masonry 58.922 G 12.5mm Plywood X604 and 12.5mm GB Plasterboard and skim + Steel columns ID 601 single ply membrane X602 LIFT LOBBY e Roof SystemX605 build-up +58.837 Thermal X603 as J42.110A 13 Terrace Wall Construction - Blockwork Outer STAIR/ 2SFS Inner STAIR 2 LOBBY 1200 313 1 Drainage to100mm beToS conf irmed 1ance, Roof Falls,EXTERNAL fairf aced medium density blockwork - F10/225 501 674 Type 1* Type 1* 58.378 PLANT ROOM 31150mm W 21 Air Gap with Brick Ties and Support Brackets details from Roof subcontractor 497 X605 Type 1* 150mm Rockwool DuoSlab Insulation ID 602 Terrace Wall Construction - Blockwork DetailOuter R - 301 / SFS Inner EXTERNAL of Coping 12.5 Knauf Windliner Sheathing Board G H blockwork - F10/225 22 4 PLANTInsulation ROOM 100mm fairfaced medium density 3 150mm SFS 4st Zone, Filled with RW45 Detail Q - 301 6 Gap with Brick Ties and Support Brackets 50mm Air Top of Coping Top of Masonry 12.5mm Plywood and 12.5mm GB Plasterboard150mm and skimRockwool + Steel columns 58.622 MJ 13 MJ DuoSlab Insulation 3305
440(2 bricks)
2
7
6
5
4
3
2
48.844
Fourth Floor 48.694
MJ (1 3.275) 48.722
Fourth Floor 48.694
1
19
18
8
2955
9
3230
3230
23293
11
10
7
6
5
4
Detail N - 301
3
Third Floor 45.590
2
2655 2945
2945
3019
13275(177 bricks)
2949
3234
MJ (9.750) 45.1 97
3215
Third Floor 45.464
3400
1
3230
Third Floor 45.464
3234
3230 3230
2945
16
15
14
13
12
Fifth Floor 47.1 64
2655 2945
2655
17
3230
3230 3230
3230
Detail M - 301 T.O.S.
18
9750(130 bricks)
First Floor 38.930
5
T.O.S. 38.420
SSL 38.558
cks)
First Floor 38.930
18
First Floor Confetti
Detail V - 301 MJ (2.997)
(87 bricks)
3111
2945 3215
3015
2945
3300
2890
3300
3019
32303400
First Floor HE 39.060
20
9
0 400
Stair 3 Drawing 312
First Floor 38.930
MJ (6.525 41 .972
41 .964
Second Floor CONFETTI 41 .820
3300
3230
Second Floor HE Second Floor 42.320 42.230 42.200
Ground Floor 38.568
68
SUPERSTRUCTURE:
8.4
C O N C R E T E S T R U C T U R E & S TA I R C A S E S 70 8
70 x 8mm PPC MS Flat Bar neatly welded at joints
General Notes
- All dimensions to be confirmed on site prior to commencing any fabrication. - Top of all handrails to be 1100mm min. above pitch line of stairs and above finished landing level. - All handrails to be nominal 40mm satin stainless steel. - Wall handrails to be supported on stand off wall brackets; continuos around half landings; extend 300mm past top and bottom of flight and be returned to wall. -Exposed fasteners shall be of same materials, color and finish as material to which applied. -Exposed surfaces throughout project shall have same inherent texture and color for similar locations.
40mm diameter satin finish SS circular handrail mechanically fixed from below to PPC MS Angle support
*
1000
6mm Treads fixed with countersunk fixings to stringer
Vinyl flooring to treads with contrasting nosings as spec L30.250B to treads and risers
70x8mm PPC MS balusters welded to top and bottom rails with 150, 100 or 50mm spacings in random arrangement. Layout shown to provide design intent.
01
Treads and landings from 6mm folded plate to SE details
8
8
250 x 10mm stringer to SE details
Balustrade system fixed through PPC MS flat welded between balusters and fixed with countersunk fixings to stringer and with spacers behind to provide offset gap of 5mm. Spacing to align with handrail fixings above.
Detail Section 01 ( 1.10 )
01
70
8
70 x 8mm PPC MS Flat Bar neatly welded at joints
1000
T
PROJECT
250 x 10mm stringer to SE details
Confetti CQ Campus Balustrade details (Stair 2 HEC)
Balustrade system fixed through PPC MS flat welded between balusters PROJECT SCALE and fixed NUMBER with countersunk fixings to stringer and with spacers behind to provide offset gap of 5mm. Spacing DRAWING to align withNUMBER handrail REVISION fixings above.
Detail Section 01 ( 1.10 )
01 DATE
1:10@ A2
Jun-17
1.10 ) STATUS Detail Section 02 ( BY
Preliminary
MLD
*
s) 6 1/2 brick 3712 .5(1 /2 bricks) 1912 (8 1
MJ
MJ
44092 bricks)
MJ 3D View
MJ
Ed (29 1/2 bricks)
X505 FIFTH FLOOR TERRACE
ricks 1575(7 b
7527.5(33 1/2 b
MJ
Ec
3D View
STAIR 1 bricks) 7415(33
ricks) 1575(7 b
389
s) 3 1/2 brick bricks) 9777.5(4 3590(16 MJ
ricks) 1575(7 b
MJ
MJ
MJ
890
ricks) 1575(7 b
MJ
389
70 x 6mm SS Flat Bar notched and welded at join with newels DRAWING
3D View
220 A
s) 6 1/2 brick 3712 .5(1
1575(7 bricks)
pe 1
01
Generally do not scale drawings. All dimensions to be checked on site.
499
Electrical riser ID 505 1736
www.allanjoycearchitects .co.uk
This drawing is copyright and remains the property of Allan Joyce Architects Ltd
W 20
600
design@allanjoycearchitects .co.uk
Confetti Media Group
319
MJ
1247
2812 .5
E
W
Treads and landings from 6mm folded plate to SE details
8
4897
4896
1575(7 bricks)
150
D 05 MJ
0115 841 8418
2588
ED 06
2035
*
6mm Treads fixed with countersunk fixings to Nottingham NG1 1DF 16-20 Bath Street, stringer
8
70x8mm PPC MS balusters welded to top and bottom rails with 150, 100 or 50mm spacings in random arrangement. Layout shown to provide design intent.
Detail Section 03 ( 1.20 )
MJ
1/2 bricks) 5738(25 ks) 5 1/2 bric 5737.5 (2
BY
Architects, Landscape & Interior Design
Vinyl flooring to treads with F 0115 950 7161as spec contrasting nosings L30.250B to treads and risers CLIENT
3D View
l e c
8 x 8mm PPC MS Angle Support factory welded to vertical balusters minimum one either end and then equally spaced between at max 1.2m centres
1300
*
G
40mm diameter satin finish SS circular handrail mechanically fixed from below to PPC MS Angle DESCRIPTION REV. DATE support
Detail Section 02 ( 1.10 )
40
Detail Section 03 ( 1.20 )
70 x 6mm SS Flat Bar notched and welded at join with newels
MJ
1/2 bricks) 6198(27 s) 9 1/2 brick 6637.5(2
X504 FIFTH FLOOR TERRACE
Maintain consistent gap between each section of the balustrade system. 50mm Refer to drawing 314 for location
Both the concrete stair core of Stair 1 & 2 are now fully installed, meaning a completion of 2 more superstructure tasks . The contractors are planning to complete the wall finishes of the stair well and the floor finishes during the Easter and the balustrades will be installed afterward.
1575(7 bricks)
cks) 440(2 bri
The only part that have not fully completed with insitu concrete is the cantilever that goes over the Confetti building on the 5th floor. Ee Although 5th floor has completed its concrete slab, the 2 cornerEof slab,which is about 8675square metre, remain d incomplete as that area allows scaffolding for workers 2951 bricks) 6525(29 to access different levels. They are planning to finish 0 bricks) 3600(16by then, all the superstructure that slab next week and 0 s) MJ 6525 .5 5(13 brick be done. 292will Sanding of all concrete structure isMrequired as they J MJ MJ have sharp edges andrickmight hurt or pierce through s) 1575(7 b MJ s) ck bri 1575(7 if there is no proper treatments. cks) rimaterials 1575(7 b
40
STAIRCASES
1300
INSITU FRAME CONCRETE STRUCTURE
8 x 8mm PPC MS Angle Support factory welded to vertical balusters minimum one either end and then equally spaced between at max 1.2m centres
STAIR 2
69
R
19
M&E 1st fix
1w 19/02/2018 A 23/02/2018 A 19
20
Plastering
1w
26/02/2018
02/03/2018
21
2nd fix M&E
2w
12/03/2018
23/03/2018
20 21
2nd FLOOR
L
8.5
IFTSHAFT
22
1st fix M&E
1w 26/02/2018 A
02/03/2018
23
Plastering
1w
12/03/2018
16/03/2018
24
Screeding
1w
05/03/2018
09/03/2018
22 23 24
siw week Programme
3RD FLOOR 25
1st fix partitions
1w 05/03/2018 A
09/03/2018
26
1st fix M&E
2w
08/03/2018
21/03/2018
27
Plastering
1w
19/03/2018
23/03/2018
1w 12/03/2018 A Duration Start
16/03/2018 Finish
28/02/2018
25 26 27
Stepnell ltd
Glenn Reeves
4TH FLOOR 28 1st fix partitions Line Name
G 223 FCB
4
18
5
4
3
2
1
364
Type 1
150 160
1800
105
MJ
RSA Fixed to rear for forming maintenance deck
1800
105 370
First Floor 39.060
1492
D
09/03/2018
2w
20/03/2018
810min.
07/03/2018
18
s) 6 1/2 brick 3712 .5(1 s) 6 1/2 brick 3712 .5(1
1800
1913 .5
MJ
Screeding
X410 CORRIDOR 3RD FLOOR
1w Blockwork laid flat. Compressive strength to be 1w determined by SE
1st fix partitions 1st fix M&E Plastering
12/03/2018
1349
21
16/03/2018
05/03/2018
09/03/2018
Type A
1w 05/03/2018 A 2w
Type 1
1w
23
09/03/2018
Electrical 08/03/2018 21/03/2018 riser 19/03/2018
23/03/2018
ID 407
16/03/2018
2w
19/03/2018
03/04/2018
SFS
2w
26/02/2018
09/03/2018
30
X403 COMPUTER SUITE 2 Plant steel 49 mroom
1w 26/02/2018 A 1w
05/03/2018
02/03/2018 Type A
31
Parapet works
Main coverings / Insulation
2w
12/03/2018
M&E 1st fix
Ec
25 26 27
Ed
1w 12/03/2018 A
1st fix partitions
24
271
1736
271
Type 1
22
IS 402
300
1954
W 18
2065
12/03/2018
300
100
ID 408
IS 403
20
23/03/2018
1585 1010 1w 26/02/2018 A 02/03/2018 ID 406
100
1st fix M&E
26
30
160 150
17
26/02/2018 Type 1 02/03/2018 Type A
2w
RSA Fixed to rear for ID forming 405 maintenance deck
25 27
15
16
28
SH 0.86 HH 2.03
296
1w
1500
33
X405 29 COMPUTER SUITE 54 m2
UPPER GROUND AND FIRST FLOOR LEVEL
MJ
Lift
1200
495
32
23/03/2018
Ground
1st
Drawn by: Planner - Chart Properties
2nd
33
3rd
Dwg No. 00001
3305
Plantroom
Roof
Notes: Comment - Chart Properties
to suit Kone requirements
Planned by Asta Powerproject
1716 W 19
15mm fireline Plasterboard to form protected lift shaft
3
Vapour Control Layer Infill SFS fixed to the structure
160
6695
12.5mm Thick CP Board: Knauf Windliner with taped joints Breather Membrane (to be confirmed)
160
1248
3047.5
450 MJ
150mm RWA45 Insulation within SFS zone
FCB
4th
2735
Revision No. A
SE to confirm 15mm firecase encasement to achieve 60min rating
MJ 9337.5(41 1/2 bricks)
Lift
5840
4950(22 bricks)
4387(19 1/2 bricks)
105 150mm Rainscreen Duo Slab in cavity
2065
2065
09/03/2018
Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp 152 UC
2065
UP
Lift
Brickwork outer leaf as F10.110 RSA Fixed to rear for forming maintenance deck
1in12
105
E
SECOND FLOOR LEVEL
PROPOSED FOURTH FLOOR GA PLAN -1:50
1w 2 05/03/2018
ID 411
Ancon Masonry support angle spec by SE
G 223 7718
TA 2.27
1646
C
24
14
12/03/2018 16/03/2018 150 160 2w 19/02/2018 A 02/03/2018
Type 1 LOBBY
2nd FLOOR
SP 1.45
3562
B
2
2nd fix M&E
130
FFL 39.08
2279
A
FFL 39.04
C 222
22
W 17
09/03/2018
1w 19/02/2018 A 23/02/2018 A 19
ID 402 23 Plastering 233 1010
32
15mm fireline Plasterboard Timber trimmers or steel beam to support cut floor above to SE details
Plastering Type
21
160 150
1700 clear
521
Wheelchair Refuge
20
31
ID 112
ID 111
9216
05/03/2018
Floor Level
15mm fireline Plasterboard to form protected lift shaft
4
M&E 1st fix
160
1555 92
X413 STAIR 2 LOBBY
Type 2
19
364
221
B
X112 Refuge clnrs cpbd 1560
2388
2950
4
6
Type 1 152 UC SE to confirm 15mm firecase encasement to achieveWheelchair 60min rating
Type 2 Eb
Fourth Floor 48.694
to suit Kone requirements
X412 STAIR 2
13
1w
0
M&E 1st10 fix 10 15 416 15mm fireline Plasterboard Plastering to form protected lift shaft ID 404 2nd fix M&E
LIFT SHAFT
1736
660
19
W 01
1w
1800
17
Ground Floor Internal Finishes 152 UC SE to confirm X407 Under floor heating 15mm firecase encasement ACCESSIBLE Screeding to achieve 60min rating
1700 clear
16
12
160 92
15
23/03/2018
29
SH 0.95 HH 2.17
14
12/03/2018
28
1736
13
2w
4TH FLOOR
ID 410 Mechanical riser
261
100 12
Ea
1868
1010
ID 413 11
Corten 2nd - 3rd
ROOF WORKS
1010
1500 1200
7
2105
251
TA 2.37
3000 2100
3
13
2000
4642
1800
1700 clear
2470 215
A
9900 220
3650 3554
300
2735
Roof
MJ
2885
11
16/03/2018
allery H002 G CH 2.99
ID 414
2455
W 12
X411 CORRIDOR
Type 1
09/03/2018
05/03/2018
3364 760
BASEMENT / LOWER GROUND FLOOR LEVEL
IS 404
26/02/2018
2w
Plantroom
Notes: Comment - Chart Properties
10
2w
1576
4th
9
Revision No. A
1500
Type 1
3a
W 14
7
1500min.
X409 STAIR 1 LOBBY
1353
269
14/03/2018
8
33
Corten 1st - 2nd
ID 409
Type 1*
08/03/2018
499
ID 415
1500
1361
1
CH 2.53
1930
+0.05 IS 405A
311
ID 401
1
2
1w Dwg No. 00001
5 66 6
32
2935
150
IS 401
2
3
31 5
6128
F
1627
Type 3
4
23/03/2018 10/04/2018
12/03/2018 26/03/2018
4
12
18
19
Fourth Floor 48.694
2w
ID 4031ST FLOOR
2065
5
09/03/2018 09/03/2018 23/03/2018
1w 20/02/2018 A 26/02/2018 A 2nd 3rd 1w 28/02/2018 A 06/03/2018
Corten grnd - 1st Project11 Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
17
18
6
7
1912 .5
4742
Lift
7
2a
5600
Main coverings BWK 3rd - 4th / Insulation
2w 26/02/2018 A 1w 05/03/2018 2w 12/03/2018
1900 clear
150 160
8
X402 COMPUTER SUITE RSA Fixed to rear for forming 49 m2 maintenance deck
Type A
33 7
16
17
X408 STAIR 1
9
6
4897
9
EeApril
2
3
2485
310
W 15
1696
10
5
6752
4896
15
Blockwork laid flat. Compressive strength to be determined by SE
BWK grnd - 1st Plant room steel BWK 1st - 2nd Parapet works BWK 2nd -3rd
15
160 150 16
X401 COMPUTER SUITE 51 m2
4 31 5 32 6
14
150 160
26
4
It is layered with 2 layer of insulations, same as the Type 2 WC Type 3 normal externalX404 envelope. The exterior of the lift shaft SEMINAR ROOM Type 3 28 m X406 is brick. This is to match the style and aesthetic of the MALE WC 4 X011 Lift whole East facade, creating unity. STAIR 2
4350
15mm fireline Plasterboard to form protected lift shaft
30
2
2951 1w 19/02/2018 A 23/02/2018 bricks) A 6525(29 1w 26/02/2018 A 02/03/2018
DP
11
2
2018 March 19 29 3
The structure of the lift shaft has completed, mainly F E 0 30 focusing on the fire resistance materials applying 300 on it, such as fire resistance plasterboard and fire encasement. Planned by Asta Powerproject
2502
W 02
1
02/03/2018
Ed
Ec
12
1
160
3160
W 16
1a
1w 26/02/2018 A
421
10by: Planner Curtain walling 5th - 6th Drawn - Chart Properties
2735 890
152 UC SE to confirm 15mm firecase encasement to achieve 60min rating
SFS 5th - 6th ROOF WORKS
ibks) Floor Level 0(70 brwalling 8 15Curtain 3rd -4th 74 MJ Ground 1st 9 Curtain 4th - 5th 90 80walling
1768
4200
301
6900
03/04/2018 09/03/2018 23/02/2018
1
28
5
150
222
6w 19/02/2018 2w 26/02/2018 1w 19/02/2018 A
2200min.
D
LIFT SHAFT External Envelope SFS 4th - 5th SFS
February 19 26 -2 -1
1565
C
12868
bricks) 9215(41
4550
1 30 2
U/S 2.27
Ea
03/04/2018
DH 2.05
E
19/03/2018
1710
1492
D
2w
1457
1646
C
4452
910
3562
B
Eb
3109
2279
A
330
M&E 1st fix
3
420
ing out Line Bricks Sett
29
4959
G
H
TYPICAL LAYOUT ABOVE HEC
70
28/02/2018
E
8.6 1
SFS SYSTEM
2
CURTAIN WALLING
Stepnell ltd
Line
X T E R N A L E N V E LO P E
Name
CONCRETE
4
BRICKWORKS
February 19 26 -2 -1
Finish
External Envelope
6w
2
SFS 4th - 5th
3
SFS 5th - 6th
4
BWK grnd - 1st
1w 19/02/2018 A 23/02/2018 A
5
BWK 1st - 2nd
2w 26/02/2018 A
09/03/2018
6
BWK 2nd -3rd
2w
12/03/2018
23/03/2018
7
BWK
2w
26/03/2018
10/04/2018
8
Curtain walling 3rd -4th
1w 20/02/2018 A 26/02/2018 A
9
Curtain walling 4th - 5th
1w 28/02/2018 A
11 1 12 2 13 3 4 5
19/02/2018
03/04/2018
1
1w 19/02/2018 A
23/02/2018
2
1w 26/02/2018 A
02/03/2018
1
5
2
12
2018 March 19 3
4
26
5
April 9
2
6
3
3rd - 4th
1w Duration
4
5
6 7
Stepnell ltd
06/03/2018
08/03/2018 Start
9
14/03/2018 Finish
-2
Corten grnd - 1st External Envelope Corten 1st - 2nd SFS 4th - 5th Corten 2nd - 3rd SFS 5th - 6th
2w 19/02/2018 26/02/2018 6w 2w 05/03/2018 1w 19/02/2018 A 2w 12/03/2018 1w 26/02/2018 A
Ground Floor Internal BWK grnd - 1st Finishes
09/03/2018 03/04/2018 16/03/2018 23/02/2018 23/03/2018 02/03/2018
1w 19/02/2018 A 23/02/2018 A
February 19 26 -1
10
1
5
2
2w 26/02/2018 A
09/03/2018
2w 1w
12/03/2018 05/03/2018
23/03/2018 09/03/2018
7 15
BWK 3rd - 4th Screeding
2w 1w
26/03/2018 12/03/2018
10/04/2018 16/03/2018
16
M&E 1st fix
2w 19/02/2018 A
02/03/2018
8 17
Curtain walling 3rd -4th Plastering
1w 20/02/2018 A 26/02/2018 05/03/2018 09/03/2018A
9 18
Curtain walling 4th - 5th 2nd fix M&E
1w A 2w 28/02/2018 07/03/2018
06/03/2018 20/03/2018
10
Curtain walling 5th - 6th
1w
08/03/2018
14/03/2018
26/02/2018
09/03/2018
26
5
April 9
2
6
13
3
BWK -3rd Under2nd floor heating
4
12
2
BWK 1st - 2nd
2018 March 12 19 3
11
1
6 14
Glenn Reeves
8
4 5
CORTEN STEEL ON CONCRETE 6
14
7
15
16
8
17 9
18 10
A sample of the conten steel cladding is located in the site to allow the contractor and the project team to know how the final look of the building is going to be. 1ST FLOOR
11
Corten grnd - 1st
2w
12 19
Corten 1st M&E 1st fix- 2nd
2w 05/03/2018 16/03/2018A 19 1w 19/02/2018 A 23/02/2018
13 20
Corten 2nd - 3rd Plastering
2w 1w
12/03/2018 26/02/2018
23/03/2018 02/03/2018
21
2nd fix M&E Ground Floor Internal Finishes 2nd FLOOR
2w
12/03/2018
23/03/2018
14 22 15 23 16 24 17
Under floor heating 1st fix M&E Screeding Plastering M&E 1st fix Screeding Plastering
1w 05/03/2018 1w 26/02/2018 A 1w 12/03/2018 1w 12/03/2018 2w 19/02/2018 A 1w 05/03/2018 1w 05/03/2018
09/03/2018 02/03/2018 16/03/2018 16/03/2018 02/03/2018 09/03/2018 09/03/2018
18
2nd fix M&E 3RD FLOOR
2w
07/03/2018
20/03/2018
09/03/2018
12
13
20
21
14
22
15 23
16 24 17
18
25
1ST FLOOR 1st fix partitions
1w 05/03/2018 A
26 19 27 20
1st fix M&E M&E 1st fix Plastering Plastering
2w 08/03/2018 21/03/2018 1w 19/02/2018 A 23/02/2018 A 19 1w 19/03/2018 23/03/2018 1w 26/02/2018 02/03/2018
21
2nd fix M&E 4TH FLOOR
2w
28
29 22 23 30 24
2nd FLOOR 1st fix partitions M&E 1st fix 1st fix M&E LIFT SHAFT Plastering SFS Screeding
12/03/2018
23/03/2018
1w 12/03/2018 A
16/03/2018
2w 19/03/2018 1w 26/02/2018 A
03/04/2018 02/03/2018
1w 2w 1w
12/03/2018 26/02/2018 05/03/2018
16/03/2018 09/03/2018 09/03/2018
1w 26/02/2018 A 1w 05/03/2018 A 1w 05/03/2018 2w 08/03/2018 2w 12/03/2018 1w 19/03/2018
02/03/2018 09/03/2018 09/03/2018 21/03/2018 23/03/2018 23/03/2018
25
26
27
20
21
28
29
22
23
30
24
ROOF WORKS 3RD FLOOR
Drawing Numb
er
1428-4006
31 25 32 26 33 27
Plant room steel 1st fix partitions Parapet works 1st fix M&E Main coverings / Insulation Plastering
31
MasonGround ry 5mm raked join ts
1st
28by: Planner 1st -fix Drawn Chartpartitions Properties 29
M&E 1st fix
LIFT SHAFT Project week Programme.pp DoRef. wnC:\Users\glenn.reeves\Desktop\Six pip
Nominal 5mm join t foam tape Compriband-N Black or similar approved
30
26 33
e position to be
SFS
confirmed
2nd
3rd
1w Dwg No. 00001
12/03/2018 A
16/03/2018
27
2w
19/03/2018
03/04/2018
2w
26/02/2018
09/03/2018
31
Plant room steel
1w 26/02/2018 A
02/03/2018
32
Parapet works
1w
05/03/2018
09/03/2018
33
Main coverings / Insulation
2w
12/03/2018
23/03/2018
IF4th IN DOUBT ASK
28 Revision No. A DO NOT SCALE THI S
DRAWING
A01
32Denotes fixing reference . Read in conjunct ion with fixing sche
dule
33
180
300
Notes :
Ground
1st
Drawn by: Planner - Chart Properties
2nd
3rd
Dwg No. 00001
4th
Plantroom
Roof
Notes: Comment - Chart Properties
Revision No. A Associated Dra
wings :
Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp Shear wall to lift
Roof
31
Floor Level
Bracket VB/180 with Adaptor FOR ZONES 200 -235mm
Plantroom
Notes: Comment - Chart Properties
This drawing is the property of Verte 29 ks Associates issued on the cond Ltd and is ition it is not repro disclosed to any unauthorised perso duced, retained or n, either wholly without the writte or in part n consent of Verte ks Associates Ltd . 30 This drawing shoul d be read in conju nction with all relev design drawings, ant calculations and system manufactu instructions. All rers dimensions are to be checked and any errors by the contractor or omissions repor ted prior to comm any fabrication encement of and/or installation . Any discrepanc ies are to be notified immediate ly.
ROOF WORKS
1.5mm Corten Trim Installation to clo se Corten to Masonry.
Corten Cladding
25 32
Steel tracks are then fixed to the concrete and the corten steel cladding goes on top of the tracks and Planned by Asta Powerproject complete a consistence facade externally. Floor4TH Level FLOOR
Planned by Asta Powerproject
core
Panel
150mm Rainscree
n Duo Slab
Horizontal Rail 60x
40x2mm TBC
Internal Finishes:25 mm Timber baton, 12.5mm Plywood,12.5m m BG Plasterboard with skim finish
Vapour Contro
l Layer
600
150mm SFS with 150mm RWA45 Insulation in cavity
180
There are 4 different types of external envelop in the design. As shown in the photos above, there are curtain walling, corten claddings on concrete and the SFS system. The remaining type of external envelope is brickworks, which mainly locates on the West facade that joins the existing Confetti ICT building. It will be demonstrated later in this section.
11
Although the concrete is able to store heat, an insulation layer is still applying on the external side of the concrete wall, which further assists the thermal resistance of concrete wall and helps storing more heat to the internal space, providing sufficient thermal comfort.
INTERNAL
7
siw week Programme
10 Curtain walling 5th - 6th Line Name
EXTERNAL
Start
1
28/02/2018
3
Duration
Glenn Reeves
P2
12.5mm Thick CP Board: Knauf Win dliner with taped join ts 180
° 95
Breather Memb rane (to be confirmed) 150mm Rainscree n Duo Slab
P1 Revision
Issued for Approva comments inc l ISSUED FOR APP ROVAL First Issue Description
pw 05.10.17 pw 28.09.17 Date
Revised By
71
7
Module
instructions. All dimensions are to be checked by the contractor and any errors or omissions reported prior to commencement of any fabrication and/or installation. Any discrepancies are to be notified immediately.
20
Notes : Module
28/02/2018 28/02/2018
Horizontal Rail 60x40x2mm TBC
180
Bracket VB/180 with Adaptor FOR ZONES 200-235mm Breather Membrane (to be confirmed) 12.5mm Thick CP Board: Knauf Windliner with taped joints Corten Cladding Panel Vapour Control Layer
60
25
3
12.5
12.5
Internal Finishes:25mm Timber baton, 12.5mm Plywood,12.5mm BG Plasterboard with skim finish
30
220
218.5
218.5
1 150
Vertical Section
C1
Construction issue no comments
pw 05.10.17
P3
ISSUED FOR APPROVAL Horizontal Rail
pw 28.09.17
P2
ISSUED FOR APPROVAL insulation note corrected
pw 20.09.17
P1
ISSUED FOR APPROVAL First Issue
pw 29.08.17
1:5
Description
12.5
Revision
600
300
1200
900
900
300
600
600
900
300
G.1075
A.1075
C.1075
K3.1075
K3.1075
D.1075
A.1075
B.1075
B.1075
B.1075
A.1075
B.1075
C.1075
C.1075
D.1075
A.1075
B.1075
A.1075
K2.1075
300 300
600
600
600
300
600
620
305
300
600
300
1200
900
900
600
300
600
600
600
300
1200
300
905
600
600
900
300
300 300
600
600
300
600
305
530
600
600
900
300
500
600
300
300
2750
2750
A.2730 300
Confetti Campus Nottingham 500
10 11
Curtain walling 5th - 6th Corten grnd - 1st
1w 2w
08/03/2018 26/02/2018
14/03/2018 09/03/2018
12 11 13 12
Corten Corten Corten Corten
1st - 2nd grnd - 1st 2nd 3rd 1st --2nd
2w 2w 2w 2w
05/03/2018 26/02/2018 12/03/2018 05/03/2018
16/03/2018 09/03/2018 23/03/2018 16/03/2018
13
2w
12/03/2018
23/03/2018
14
Corten 2nd - 3rd Ground Floor Internal Finishes Ground Floor Internal Finishes Under floor heating
1w
05/03/2018
09/03/2018
15 14 16 15
Screeding Under floor heating M&E 1st fix Screeding
1w 12/03/2018 1w 05/03/2018 2w A 1w 19/02/2018 12/03/2018 1w 19/02/2018 05/03/2018 2w A
16/03/2018 09/03/2018 02/03/2018 16/03/2018
2nd fix M&E 1ST FLOOR
3230
3230
180
B.3210
A.3210
300 300
500
600
300
Drawn By
1428
07/03/2018
20/03/2018
7
10
11
12 13
12
13
14 15
14 16
15 17
16
17
18 18
20 21
20
23/03/2018
02/03/2018
1w 12/03/2018 1w 26/02/2018 A 1w 05/03/2018 1w 12/03/2018
16/03/2018 02/03/2018 09/03/2018 16/03/2018
1w
09/03/2018
05/03/2018
10
9
11
2w
Plastering
9
8
2nd fix M&E 2nd FLOOR
1w 26/02/2018 A
7
6
8
21
2nd FLOOR 1st fix M&E
2
6
5
1w 19/02/2018 26/02/2018 02/03/2018A 19 1w A 23/02/2018 2w 12/03/2018 23/03/2018 1w 26/02/2018 02/03/2018 12/03/2018
5
April 9 6April 9 6
5
4
1w 19/02/2018 A 23/02/2018 A 19
1w 05/03/2018 A
09/03/2018
2w 08/03/2018 1w 05/03/2018 A 1w 19/03/2018 2w 08/03/2018
21/03/2018 09/03/2018 23/03/2018 21/03/2018
Plastering 4TH FLOOR
1w
23/03/2018
Denotes fixing reference. Read conjunction with fixing schedule 4THinFLOOR
21
22 23
22 24
23
24
19/03/2018
25 25
26
27
26
27
1st fix partitions
1w 12/03/2018 A
16/03/2018
28
29
M&E 1st fix
03/04/2018 16/03/2018
28
29 30
LIFT M&E SHAFT 1st fix SFS SHAFT onLIFT panels are
2w 19/03/2018 1w 12/03/2018 A 2w 2w
19/03/2018 26/02/2018
03/04/2018 09/03/2018
30
2w
26/02/2018
09/03/2018
30
to
29 29
3520
Paper Size
A3 C1
180
1w 26/02/2018 A
02/03/2018
31
Parapet works Plant room steel
1w 26/02/2018 05/03/2018 1w A
09/03/2018 02/03/2018
31
33 32
Main coverings Parapet works / Insulation
2w 1w
12/03/2018 05/03/2018
23/03/2018 09/03/2018
33
Main coverings / Insulation
2w
12/03/2018
23/03/2018
1st 1st
Associated Drawings : Drawn by:- Planner - Chart Properties 4000 system detail
Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
Dwg No. 00001 Dwg No. 00001
32 32
33 33
2nd
3rd
4th
2nd
3rdRevision No. A
4th
Revision No. A
Plantroom
Plantroom Notes: Comment - Chart Properties
Roof Roof
Notes: Comment - Chart Properties
Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
Revision
1428-4000
ROOF WORKS Plant room steel
32 31
Floor Level
SR 1:5
31
Workers are working on installing insulations on the levels that has already installed its SFS system. There are 2 insulation layers in total, with 150mm each. They Planned by Asta Powerproject promised thermal comfort of 0.18W/m2K, which meet Planned by Asta Powerproject the 0.22W/m2K, u-value of a wall required. Ground Drawn by: Planner - Chart Properties
Checked
Scale
Drawing Number
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
Approved
PW
29.08.17
3520
2w
26
2
3
Plastering M&E 1st fix 2nd fix M&E Plastering
Ground
4th SSL 48 684
180
Date
3520
09/03/2018 02/03/2018 20/03/2018 09/03/2018
4
5
4
20 19 21 20
Floor Level
180
3520
07/03/2018 05/03/2018
2
26
3
2
19
ROOF WORKS
System Details Corten Cladding Typical Detail
G.3210
900
2w 1w
5
4
2 1
1ST FLOOR M&E 1st fix
28 1st fix partitions Notes :
44mm MAX
3520
1w 06/03/2018A 1w 28/02/2018 20/02/2018 A A 26/02/2018 1w 08/03/2018 14/03/2018 1w 28/02/2018 A 06/03/2018
180
Cad File Name
3520
Curtain 5th Curtain walling walling 4th 3rd --4th Curtain walling 4th 5th -- 5th 6th Curtain walling
1
2
2018 March 12 201819 March 3 12 19 3
44mm MAX
3230
3230
600
A.3210
A.3210
530
650 A.630
3520
W13
3520
3520
300 305
C.3210
600
B.3210
B.3210
600
A.3210
B.3210
300
K2.3210
A.3210
600
K2.3210
B.3210
300
A.3210
A.3210
900
650 C.630
300
C.3210
600
650 B.630
B.3210
300
A.3210
A.3210
600
Angle Adaptor in Fixed point 600 900 300 configuration ( 1No this type per horizontal rail) 3520
3520
3520
3520
3520
3520
3520
B.3210
600
3520
600
650 A.630
650 A.630 650 C.630
650 A.630 650 B.630
W09
3520
3520
3520
1:5
B.3210
600
B.3210
600
Angle Adaptor in Sliding point configuration 300 600 300 900 300
3520
590
300
B.3210
600
Module
B.3210
K1.3210
K1.3210
4th SSL 48 684
B.3210
FFL Fourth 48 694
9 8 10 9
Dims 30 SFS modules.
5th SSL 51 914
180
Title
Module
2w 26/03/2018 10/04/2018 1w 20/02/2018 A 26/02/2018 A
28
180
Tel: 01709 515 044 ● Fax: 01709 515 066 G.2730
2750
600
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
3230
Horizontal Rail 60x40x2mm TBC
BWK 3rd - 4th Curtain walling 3rd -4th
A01
Rainscreen Cladding
PVC Isolation tape between dissimilar metals
7 8
27
SOUTH GROVE HOUSE ● SOUTH GROVE ● ROTHERHAM ● S60 2AF
Package
20
2w 26/02/2018 A 23/02/2018 09/03/2018A 1w 19/02/2018 A 2w 12/03/2018 23/03/2018 2w 26/02/2018 A 09/03/2018 2w 26/03/2018 23/03/2018 10/04/2018 2w 12/03/2018
Plastering M&E 1st fix 2nd fix M&E Plastering
23/02/2018 03/04/2018 02/03/2018 23/02/2018
1
5
Glenn Reeves Glenn Reeves
The workers has almost finished installing the SFS system, only the 6th floor remain incomplete as the construction of the roof level has just started due to a delay of the completion of the superstructure.
HORBURY BUILDING SYSTEMS LTD W12
W12
Note : Frame width of corner glazing is subject to reveal Project depth tbc by glazing contractor
A.2730
2750 B.2730
2750 B.2730
300
B.2730
2750
2750
2750
2750 B.2730
A.2730
W15
Bracket Adaptors do not generally penetrate insulation zone K2.2730
2750 B.2730
K2.2730
2750
2750
600
A.2730
2750 B.2730
B.2730
B.2730
2750
2750
2750 A.2730
2750
600
A.2730
B.2730
A.2730
2750
2750
2750
69 B.2730
B.2730
300
C.2730
2750
2750
300
7 6
BWK 1st - 2nd BWK grnd - 1st BWK 2nd--3rd BWK 1st 2nd BWK 2nd 3rd-3rd - 4th BWK
3RD FLOOR
3520
600
2750
250 600
A.2730
2750 B.2730
A.2730
2750
2750
2750 290
600
30
300
B.2730
K1.2730
2750
2750 K1.2730
5th SSL 51 914
A.2730
FFL Fifth 51 924
5 4 6 5
18
180
W16
1w 26/02/2018 A 02/03/2018 1w 19/02/2018 A 23/02/2018 A
This drawing should be read in conjunction with all relevant 1stcalculations fix partitions design25 drawings, and system manufacturers instructions. All dimensions are to be checked by the contractor 26 25 1st 1st fix fix M&E partitions and any errors or omissions reported prior to commencement of 27 Plastering 26 and/or 1st fix M&E any fabrication installation. Any discrepancies are to be notified immediately.
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
600
SFS 5th - 6th BWK grnd - 1st
SFS SYSTEM
44mm MAX
1200
Finish 03/04/2018
3 4
23
K2.1075
B.1075
A.1075
B.1075
B.1075
468.5
B.1075
A.1075
A.1075
B.1075
A.1075
1095
1095
1095
150
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095 600
180
180
290
Start 19/02/2018
This drawing is the property of Verteks Associates Ltd and is issued 24 on theScreeding condition it is not reproduced, retained or disclosed to any unauthorised person, either wholly or in part 3RD FLOOR without the written consent of Verteks Associates Ltd .
180
300
Duration 6w
February 19 26 -2 February -1 19 26 1 -2 -1
1w 19/02/2018 6w 19/02/2018A 1w 26/02/2018 A 1w 19/02/2018 A
22
180
600
Finish
IF IN DOUBT ASK 23 22 Plastering 1st fix M&E DO 24 NOTScreeding SCALE THIS DRAWING
Note : Top of parapet to be advised when roof build up has been determined
1 C.1075
B.1075
B.1075
A.1075
C.1075
C.1075
D.1075
D.1075
A.1075
B.1075
B.1075
K1.1075
K1.1075
B.1075
FFL Roof 55 390
Start
SFS 4th - Envelope 5th External SFS 4th 5th -- 5th 6th SFS
Revised By
Date
Duration
2 1 3 2
17 16 18 17
468.5
01 4000
Name
Line Name 1 External Envelope
180
01 4005
Stepnell ltd Stepnell ltd
Line
Associated Drawings :
Drawing Number top of windpost 57 190
siw week Programme siw week Programme
Denotes fixing reference. Read in conjunction with fixing schedule
A01
180
1200
600
905
600
G.3500
A.3500
290
B.270
300
K3.270
600
290
600
K3.270
600
290
300
D.270
A.3500
600
290
B.3500
900
B.3500
600
B.3500
390
300
3rd SSL 45 454
500
180
44mm MAX
Note : Frame width of corner glazing is subject to reveal depth tbc by glazing contractor
900
600
305
3110
600
P4
800
J.3090
3110
3110
B.3090
600
3110
3110
600
K3.3090
300
K3.3090
900
B.3090
3110
3110
3110
300
B.3090
600
A.3090
900
C.3090
3110 A.3090
3110 B.3090
600
2nd SSL 42 065
180
pw 28.09.17
P2
ISSUED FOR APPROVAL new modules 300 600 900
pw 14.09.17
P1
ISSUED FOR APPROVAL First Issue
pw 07.09.17
180
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
W04
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
W05
180
4002
600
900
600
300
300
900
390
900
525
375 300
600
600
300
C.3115
A.3115
B.3115
B.3115
A.3115
H.745
765
765 F.745 765 C.745
C.3115
A.3115
A.3115
B.3115
C.3115
B.3115
A.3115 300
900
G.3115
600
B.3115
600
B.3115
B.3115
A.3115 300
B.3115
600
K3.3115
300
K3.3115
600
B.3115
A.3115
900
B.3115
290
B.3115
600
C.3115
300
K1.3115
A.3115
1st SSL 38 920
K1.3115
Module
FFL First 38 930
600
305
300
600
600
500
1st SSL 38 920
180
900
600
300
305
600
600
Date
Revised By
180
500
180
114°
300
Description
FFL First 38 930
540 G.520
600
540 B.520
900
540 B.520
375
K3.520 540
525
K3.520
900
540
390
540 B.520
900
540 A.520 540 C.520
300 300
540 B.520
1200
540 E.520 540 C.520
600
H.520
300
540
530
540 F.520 540 C.520
605
540 A.520 540 A.520 540 C.520
600
540 D.520
600
540 A.520 540 B.520
600
540 K2.520
300
540
900
K2.520
600
540 B.520
600
540 B.520
300
540 A.520 540 B.520
900
540 C.520
300
B.520
600
540
900
B.520
600
540 A.520 540
300
540 A.520 540 C.520
600
540 B.520
600
540 C.520
300
B.520
600
540 A.520 540
300
540 B.520
600
540 A.520 540 B.520
900
540
290
B.520 540 A.520 540 B.520
600
540 K1.520 540 C.520
300
K1.520
540 A.520 540
Module 38 930
Module 38 390
pw 03.10.17
P3
44mm MAX
525
ISSUED FOR APPROVAL Comments incorporated
ISSUED FOR APPROVAL Hidden Elevations added
Revision
02 W05
Corten steel claddings have not applied on the facade at this stage as the layers of the SFS system has not completed and the delivery of corten steel still has not arrive due to the rearrangement after the delayed programme and the snow. It is expected to arrive the site in the afternoon of the site visit day, 20 March. Installation can start after the cladding material arrive.
Issued for approval P5 further omments incorporated pw 05.10.17 180
H.535
390
C.3090
3110
3110 B.3090
300
555
3110
3110 600
A.3090
390
555 F.535 555 C.535
600
B.3090
03 4002
3110
3110
180
F.3090
01 4002
300
C.3500
600
B.3500
600
A.3500
900
B.3500
300
B.3500
530
B.3500
305
C.3500
600
A.3500
300
K2.3500
600
K2.3500
B.3500
300
B.3090
600
900
A.3500
1065 B.1045 600
B.3500
B.3500 600
1065 A.1045
A.3500 300
1065
B.3500 600
C.1045
A.3500
C.3500
300
3110
B.3500
600
900
A.3090
300 300
B.3090
3110
B.3500 B.3090
900
A.3090
A.3090
600
3110
600
3110
B.3500
600
3110
B.3500
600
3110
600
B.3090
300 300
300
C.3090
3110
3110 900
A.3090
1065
600
1065 A.1045
600
A.3500
C.3500
K1.3500 3110 590
C.1045
300
900
1065 B.1045
600
590
1065 B.1045
K1.3090
2nd SSL 42 065
B.3090
FFL Second 42 230
3110
300
3110
600
K1.3090
3rd SSL 45 454
B.3500
FFL Third 45 464
K1.3500
Module
114°
315
Module 38 390
320
Underside Soffit and Gutter 38 234
Return elevation to masonry
01 1000
Convent St Elevation - West
A
01 4004
1:100 01
4006
4007
Lower Parlament St Elevation - South
03 1000
1:100
6
16
6
01
02 1000
500
1650
180
180
HORBURY BUILDING SYSTEMS LTD SOUTH GROVE HOUSE ● SOUTH GROVE ● ROTHERHAM ● S60 2AF
typ 1:100 section
Return elevation to glazing
Project
Package
Tel: 01709 515 044 ● Fax: 01709 515 066
Confetti Campus Nottingham Rainscreen Cladding
72
7 7
siw week Programme
Name
Start
Finish
19/02/2018
February 19 26 -2 -1
Stepnell ltd
1
External Envelope
6w
03/04/2018
1
2
SFS 4th - 5th
1w 19/02/2018 A
23/02/2018
2
1w 26/02/2018 A Duration Start
02/03/2018 Finish
3 SFS 5th - 6th Line Name 4 1 5 2
BWK grndEnvelope - 1st External BWK4th 1st--5th 2nd SFS
4 8 5
BWK grnd - 1st Curtain walling BWK 1st - 2nd 3rd -4th
6 3 7
12
2
2018 March 19 3
4
2018 Breather Membrane (to be confirmed) February March 3 12.5mm Thick 19 26 5 CP Board: 12Knauf 19 Windliner with -2 -1 1 2 taped joints 3
1w 19/02/2018 A 23/02/2018 A 150mm Rockwool 1w 20/02/2018 A 2w 26/02/2018 A 26/02/2018 09/03/2018A Duoslab Insulation 1w 28/02/2018 A 23/03/2018 06/03/2018 2w 12/03/2018
Curtain walling BWK 2nd -3rd 4th - 5th Curtain3rd walling BWK - 4th5th - 6th
08/03/2018 26/03/2018
5
April 9 6
2
4
26
5
260
Glenn Reeves 7
April 9
2
6
7
7
4 8
5 9
14/03/2018 10/04/2018
6
10
7
102.5
201 522
1
1w 2w
26
High performance partial fill Insulation
4 1w 19/02/2018 150mm SFS with 150mm Rainscreen 6w 19/02/2018A 23/02/2018 03/04/2018A 1 RW A45 Insulation in cavity 5 2w 26/02/2018 A 09/03/2018 2 1w 19/02/2018 A 23/02/2018 Vapour Control Layer 6 2w 12/03/2018 23/03/2018 3 1w 26/02/2018 A 02/03/2018 Internal Finishes:25mm Timber baton, 12.5mm Plywood,12.5mm BG Plasterboard with skim finish 2w 26/03/2018 10/04/2018
BWK 2nd- -3rd SFS 5th 6th BWK 3rd - 4th
9 6 10 7
1
5
25
28/02/2018
Duration
Glenn Reeves
Brick Tie
12.5
Line
Brick Channel
3
Movement Joint
Movement Joint
Movement Joint
MJ
MJ
ltd siw weekStepnell Programme
28/02/2018
12.5
SECTION OF BRICK WALL
E
Movement Joint
F
E
Corten - 1st Curtain grnd walling 3rd -4th Corten 1st - 2nd4th - 5th Curtain walling Corten 2nd - 3rd Curtain walling 5th - 6th
2w 26/02/2018 09/03/2018A 1w 20/02/2018 A 26/02/2018 2w 05/03/2018 16/03/2018 1w 28/02/2018 A 06/03/2018 2w 12/03/2018 14/03/2018 23/03/2018 1w 08/03/2018
Ground Floor Internal Corten grnd - 1st Finishes
2w
26/02/2018
09/03/2018
Corten 1st - 2nd
2w
05/03/2018
16/03/2018
12
13 14
Corten 2nd heating - 3rd Under floor
2w 1w
12/03/2018 05/03/2018
23/03/2018 09/03/2018
14
15
1w
12/03/2018
16/03/2018
2w 19/02/2018 A
02/03/2018
17
Screeding Ground Floor Internal M&E 1st fix Finishes Plastering
1w
05/03/2018
09/03/2018
17
18 14
2nd fix floor M&Eheating Under
2w 1w
07/03/2018 05/03/2018
20/03/2018 09/03/2018
14 18
15
1w
12/03/2018
16/03/2018
16
Screeding 1ST FLOOR M&E 1st fix
2w 19/02/2018 A
02/03/2018
17 19 18
Plastering M&E 1st fix 2nd fix M&E Plastering
1w 05/03/2018 09/03/2018 1w A 23/02/2018 2w 19/02/2018 07/03/2018 20/03/2018A 19 1w 26/02/2018 02/03/2018
21
2nd fix M&E 1ST FLOOR
2w
19
2nd FLOOR M&E 1st fix
1w 19/02/2018 A 23/02/2018 A 19
20 22 21
Plastering 1st 2ndfix fixM&E M&E Plastering
1w 26/02/2018 02/03/2018 1w A 23/03/2018 02/03/2018 2w 26/02/2018 12/03/2018 Brick Tie, align with SFS 1w 12/03/2018 16/03/2018
24
Screeding 2nd FLOOR
1w
FFL = 45.464
Concrete deck to Structural Engineer's details
Concrete deck to Structural Engineer's details
Proprietary clear perpend weepholes to be spaced evenly at 665mm centres Continuous Cavity Fire Barrier on each floor
Proprietary clear perpend weepholes to be spaced evenly at 665mm centres Continuous Cavity Fire Barrier on each floor Full brick 102.5mm deep stretcher bond,10mm joints
FFL = 45.464
Brickwork support brackets to Structural Engineer's details
Brickwork support brackets to Structural Engineer's details
PPC Aluminium window reveals to form 'pod' as H11;
Mortar PPC Aluminium window reveals to form 'pod' as H11;
FFL = 45.464
Mortar
23
02
NB: Projecting Brickwork must follow exact pattern shown on elevations
NB: Projecting Brickwork must follow exact pattern shown on elevations
421
223 FCB
1768
W 16
3000
251 3
2
1560
364
1
Movement Joint
Movement Joint
MJ
9216
105 370
F
1200
495
3305
09/03/2018
1st fix M&E 1st fix partitions Plastering
21/03/2018 16/03/2018 23/03/2018
M&E 1st fix
2w 08/03/2018 1w A 1w 12/03/2018 19/03/2018 2w 19/03/2018
LIFT FLOOR SHAFT 4TH SFS
2w
1st fix partitions ROOF WORKS M&E 1st fix
28
26/02/2018
09/03/2018 16/03/2018
2w
19/03/2018
03/04/2018
32
Parapet works
1w 26/02/2018 A 2w 26/02/2018 1w 05/03/2018
02/03/2018 09/03/2018 09/03/2018
33
Main coverings ROOF WORKS/ Insulation
2w
23/03/2018
28 29
31 30 32 33
4th 32
3047.5
450 MJ
3rd
4th
Dwg No. 00001
Revision No. A
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
300
Roof
Notes: Comment - Chart Properties
Planned by Asta Powerproject
Plantroom
Roof
Notes: Comment - Chart Properties
CLIENT
Confetti Media Group
It was said that the current stage of the brickwork is on Confetti CQ Campus 2nd floor, however, it is not visible due to the blocking ofFFL the scaffolding situated Facade Section Brick Detail in front of some of the walls. 38.764 PROJECT
5840
R Q P O N
14/02/18 07/02/18 12/01/18 04/01/18 25/10/17
Amendments to internal partitions Amendments to Internal Partitions & Ext.walls build up MJ, CFB, Bricks setting out and downpipe position added Amendments to drawings following FFE drawings Amendments to drawings following Cladding and SE info
M L
10/10/17 Slab set-out dims added for clarity 18/09/17 Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1
K J II H G
24/08/17 18/08/17 30/05/17 17/08/17 30/05/17 12/05/17
Change to the slab edge following the SE info DATE Amendments to drawings following the Cladding info Change to the 1st floor café/kitchen area Amendments to HEC stair 2 following the SE info Amendments to drawings following the Topo Survey and SE info
MLD MLD MLD MLD MLD TE MLD
MLD MLD MLD MLD MLD MLD
DRAWING
PROJECT NUMBER
SCALE
DATE
2588
1:20 @ A1
Jul-16
DRAWING NUMBER
REVISION
BY
The brickwork is applied on the external side of the SFS 300 A Construction MLD system and giving a u-value of 0.18W/m2K that meet Facade Section Detail EE the 0.22W/m2K maximum u-value of walls.
1:20 @ A1
MJ 1/2 bricks) NUMBER DRAWING 9337.5(41
Jul-16
REVISION
STATUS
A
Construction MLD
4950(22 bricks)
This drawing is copyright and remains the property
Facade Section Detail FF Section Detail EE Facade
2nd
F
MJ (2.997) SCALE
4387(19 1/2 bricks)
1st
Plantroom 33
BY
T
2588 38.297
6695
DESCRIPTION
www.allanjoycearchitects .co.uk
PROJECT NUMBER
1248
REV. DATE
design@allanjoycearchitects .co.uk
1716
W 19
522
30
E
Facade Section Brick Detail 3
FFL = 38.568
27 29
W
DRAWING
3
12.5 26
01 1 5 950 71 61
Confetti CQ Campus
FFL 38.764
218.5
152
25
03/04/2018
1w 12/03/2018 A
12/03/2018
27
Architects, Landscape & Interior Design
PROJECT
105
Lift
1w 05/03/2018 A
26 28 27
26
01 1 5 841 841 8
Confetti Media Group
Type A
FCB
2065
25
23 25 24
21/03/2018
BY
F 19/01/17 Change to doors and Stair 1 Lobby E 10/01/17 Spec Refs added D 23/12/16 Amendments to drawings C 09/12/16 Amendments to drawings Ee Amendments to drawings ofAllanB Joyce30/11/16 Architects Ltd A 25/11/16 Amendments to drawings
Generally do not scale drawings . All dimensions to be checked on site. REV. DATE
DESCRIPTION
MLD MLD MLD MLD MLD MLD
STATUS
This drawing is copyright and remains the property ofAllan Joyce Architects Ltd Generally do not scale drawings . All dimensions to be checked on site.
BY
105
BRICK WALL ON THE WEST
1800
E Facade Section Detail FF
MJ
105
4
23/03/2018
22
F
X405 COMPUTER SUITE 54 m2
MJ (2.997) 38.297
21 23 24
T
CLIENT
Ed
FFL 38.568
FFL = 38.568 364
4
FFL Type 1 38.568 FFL = 38.568
521
5
1736
261 1010
1010
100
221
6
X413 STAIR 2 LOBBY
20 22
1 6-20 Bath Street, Nottingham NG1 1 DF
MJ
Wheelchair Refuge
19/03/2018
Drawn by: Planner - Chart Properties
1 6-20 Bath Street, Nottingham NG1 1 DF
271
1736
X403 COMPUTER SUITE 49 m2
ID 411
21
Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
ID 407
External Aluminium window reveal Framing to form cill Type 1
X412 STAIR 2
W 01
Type 1
BRICKWORKS
The brick work mainly located on the East and North Planned by Asta Powerproject facade, and part of the West that near and connected to the existing Confetti ICT building.
IS 402
Brick pattern laid in stretcher bond 15mm deep, 10mm joints
Electrical riser
Fourth Floor 48.694
19
FFL = 38.568 B
660
1555
2100
1500 18
300
Ec
1868
1w
4TH FLOOR 1st fix partitions
Ground
ks) 450(2 bric
2388
17
1954
271
1736
9900 220
3650
A 3554
16
ID 408
Type 2 Eb
Plastering 3RD FLOOR
221 B
2950
15
300
100
1500
IS 403
27
Floor Level Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
bricks) 7415(33
14
X410 CORRIDOR
18
BRICKWORK
Architects, Landscape & Interior Design
7865
ID 413 13
ID 406
Type A
1/2 bricks) 9777.5(43
12
1585
1010
233
3364
1st fix M&E
BY
1349
MJ303
11
ID 405
ID 410 Mechanical riser
1800 DESCRIPTION
W 18
Type 1
Ea
1913.5
Type A
1500
External Aluminium window reveal Framing to form cill
Type 1
100
ID 402 1010
REV. DATE
150
1200
Type 2
Type 1
499
300
3
Type 2
X409 STAIR 1 LOBBY
1353
269
X411 CORRIDOR 2885
4
2105
17
20
3712.5(16
MJ
3a
Type 1
ID 414
2455
1
2
1361
1930
ID 415
IS 404
E
ID 401
2a ID 409 IS 401 Brick pattern laid in stretcher bond Solid bricks, 215mm x 102.5mm x 65mm, Type 1* deep, 10mmType 15mm joints1 perforate Flemish bond 760 Refer to Structural Engineer's drawing for fixing details of PCC MSISpost, flat and rods stainless steel 405A 1500
W 12
3
ID 403
A
15 16
31 1w 26/02/2018 A 02/03/2018 Ground 1st 2nd 3rd 32 Parapet 09/03/2018 works MLD A 16/01/181w Change05/03/2018 to perforated brickwork panels, MJ, brickwork MLD 16/01/18 Change to perf orated brickwork panels, MJ, brickwork ks) bric 1/2 support12/03/2018 brackets, cavity barriers following S/C details. 3712.5(16supportks)brackets, cavity barriers following S/C details. 33by: Planner 2w 23/03/2018 Main / Insulation Dwg No. 00001 Revision No. A Drawn - Chartcoverings Properties 1/2 bric
1627
6
Type A
5600
4
Type 3
4
X404 SEMINAR ROOM
Type 3 28 m2
ID 404
19
Fourth Floor 48.694
Solid bricks, 215mm x 102.5mm x 65mm, perforate Flemish bond Refer to Structural Engineer's drawing for fixing details of PCC MS post, flat and rods stainless steel
7
18
5
1
Architects, Landscape & Interior Design
C 222
2279
A
G
1 6-20 Bath Street, Nottingham NG1 1 DF
223 3562
B
1646
C
1492
D
6128
7718
E
F
4959
G
H
T
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
F
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group PROPOSED FOURTH TH FLOOR FLO GA PLAN -1:50
PROJECT
443.5
Key Walls
1
Wall Construction - Corten Outer / SFS Inner 30mm Deep Corten C Cassettes V Vertic 69mm Air Gap with Vertical Rails on HH Brackets kwool DuoSlab Insulation 150mm Rockwool
Confetti CQ Campus
503.5
Facade Elevation
7
X406 MALE WC
17
X407 ACCESSIBLE Type 2 WC 1010 150 416
16
Floor Level 31 Plant room steel
1912.5
4742
X401 COMPUTER SUITE 51 m2
311
4642
8
X402 COMPUTER SUITE 49 m2
FFL = 38.568
16
1696
X408 STAIR 1
9
W 17
bricks) 1912(8 1/2
W 15
2
15
10
Type 3
MJ (6.525 41 .972
220 A
Aluminium look-a-like spandrel panel 310
1500min.
4350
Bracket Structural Fixing to Structural Engineers Details
Aluminium look-a-like spandrel panel
1
11
16/03/2018 09/03/2018 09/03/2018
Plastering 1st fix partitions Screeding
FFLLIFT SHAFT 31 Plant room steel 30 SFS 42.064
4897
1a
Bracket Structural Fixing to Structural Engineers Details
2502
W 02
2485
Cavity barriers and smoke stop for Curtain Walling to suit site.
1576
4896
Cavity barriers and smoke stop for Curtain Walling to suit site.
FFL 42.064 FFL = 41 .964
FFL 41 .964
MJ (6.525 41 .972
4
3160
FFL = 41 .964
W 14
Movement Joint
FFL 41 .964 FFL = 41 .964890
4200
FFL = 41 .964
02/03/2018
29
MJ
2200min.
6900
12868
bribks) 15740(70 8090
Movement Joint
D 301
300
bricks) 9215(41
Vertical Section
1:5 1w 12/03/2018 1w A 1w 05/03/2018 05/03/2018 2w 08/03/2018
28
2935
300
Plan Section
01 4001
13 15
09/03/2018
23 25 24
30 665
1565
C 222
4550
bricks)
6525(29
05/03/2018
11
23/03/2018
1w 26/02/2018 A
29
810min.
Ea
2951
F
E
1710
E
4452
1457
1492
Ec
Eb
3109
D
Curtain wall system with windows opening g out Line Settin cksthe inward; Glazed fBri rom inside directly 330 into the window frame.
296
1646
C
420
910
Curtain wall system with windows opening inward; Glazed from the inside directly 3562 2279 frame. B A into the window
6752
Ed
Movement Joint
G
Movement Joint
Transom
Transom
Ee
12/03/2018
3RD 22 4001 1st fixFLOOR M&E
26
Curtain Wall system with all four sides of visible external caps to area without perforated brickwork detail in front; Glazing fixed from the outside directly into the curtain wall frame.
Curtain Wall system with all four sides of visible external caps to area without perforated brickwork detail in front; Glazing fixed from the outside directly into the curtain wall frame.
FFL = 41 .964
20
Full brick 102.5mm deep stretcher bond,10mm joints
Inward Opening Lights within Curtain Walling System
Inward Opening Lights within Curtain Walling System
W 06
MJ (9.750) 45.1 97
Movement Joint
Movement Joint
MJ (9.750) 45.1 97
Movement Joint
FFL = 45.464
Movement Joint
FFL = 45.464
16
13
10 C-SECTIONS
303.5
Full brick 102.5mm deep stretcher bond,10mm joints (Recessed pointing)
Full brick 102.5mm deep stretcher bond,10mm joints (Recessed pointing)
12
1
12
9
150
11
8
50
13 10
11
102.5
11 8 12 9
4
AVCL
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity
Type 1
PARTITION Wall Type 1 2no.layer of 12.5mm Soundblock either side,16mm Resilient Bar fixed to one side, 92mm C studs
Movement joint
73
28/02/2018
1/ GLAZING FIXED TO CONCRETE SLAB
Stepnell ltd
Line
Name
Duration
Start
Glenn Reeves
Finish
1
External Envelope
6w
2
SFS 4th - 5th
3
SFS 5th - 6th
28/02/2018 4 BWK grnd - 1st
19/02/2018
03/04/2018
1
1w 19/02/2018 A
23/02/2018
2
1w 26/02/2018 A
02/03/2018
2w 26/02/2018 A
09/03/2018
BWK 2nd -3rd
2w
12/03/2018
23/03/2018
2w Duration
26/03/2018 Start
10/04/2018 Finish
11 4 12 5
CONCRETE SLAB
3rdName - 4th
Curtain walling 3rd -4th External Envelope Curtain SFS 4thwalling - 5th 4th - 5th Curtain SFS 5thwalling - 6th 5th - 6th
1
4
26
5
2
8
Curtain walling 4th - 5th Under floor heating Curtain walling 5th - 6th Screeding
1w A 1w 28/02/2018 05/03/2018 1w 08/03/2018 1w 12/03/2018
06/03/2018 09/03/2018 14/03/2018 16/03/2018
16 11 17
M&E 1st fix Corten grnd - 1st Plastering
02/03/2018 09/03/2018 09/03/2018
12 18 13
Corten 1st - 2nd 2nd fix M&E Corten 2nd - 3rd
2w 19/02/2018 A 2w 26/02/2018 1w 05/03/2018 2w 05/03/2018 2w 07/03/2018
19
1ST FLOOR Ground Floor Internal Finishes M&E 1st fix
1w 19/02/2018 A 23/02/2018 A 19
20 14 21 15
Plastering Under floor heating 2nd fix M&E Screeding
1w 1w 2w 1w
26/02/2018 05/03/2018 12/03/2018 12/03/2018
02/03/2018 09/03/2018 23/03/2018 16/03/2018
16
2w 19/02/2018 A
02/03/2018
17
M&E 1st fix 2nd FLOOR Plastering
1w
05/03/2018
09/03/2018
18 22
2nd fix M&E 1st fix M&E
2w 07/03/2018 1w 26/02/2018 A
20/03/2018 02/03/2018
23
Plastering 1ST FLOOR Screeding
1w
12/03/2018
16/03/2018
1w
05/03/2018
09/03/2018
12/03/2018
7
5
2
2018 March 12 19 3
7
4
26
5
2
April 9
6
7
9 10
11
4
12
5
13 6
10/04/2018
7
1w 20/02/2018 A 26/02/2018 A
2w
1
3
9 14 10 15
26/03/2018
April 9
6
8
2
2w
Corten 2nd - 3rd BWK 2nd -3rd
February 19 26 -1
8 9
14 10 15
16 11
16/03/2018 20/03/2018 23/03/2018
17 12 18 13
20
14 21 15
16 17
CURTAIN WALL SYSTEM
2/ CORNER
18
22
23 24
The glazing has now applied on the window frame that was not visible in the last visit. Most of the West and South facade are installed with glazing while there are remaining parts on the upper level, 3rd to 6th floor, that need to be glazed within March. 19
M&E 1st fix 3RD FLOOR Plastering
1w 19/02/2018 A 23/02/2018 A 19
20
26/02/2018
02/03/2018
21 25
2nd fix M&E 1st fix partitions
2w 12/03/2018 1w 05/03/2018 A
23/03/2018 09/03/2018
26
1st fix M&E 2nd FLOOR Plastering
2w
08/03/2018
21/03/2018
1w
19/03/2018
23/03/2018
1w 26/02/2018 A
02/03/2018
23
1st fix M&E 4TH FLOOR Plastering
1w
12/03/2018
16/03/2018
24 28
Screeding 1st fix partitions
1w 05/03/2018 1w 12/03/2018 A
09/03/2018 16/03/2018
29
M&E FLOOR 1st fix 3RD LIFT SHAFT
2w
19/03/2018
03/04/2018
30 25
SFS 1st fix partitions
2w 26/02/2018 1w 05/03/2018 A
09/03/2018 09/03/2018
26
1st fix M&E ROOF WORKS Plastering
2w
08/03/2018
21/03/2018
1w
19/03/2018
23/03/2018
PlantFLOOR room steel 4TH Parapet works
1w 26/02/2018 A
02/03/2018
32
1w
05/03/2018
09/03/2018
33 28
Main 1st fixcoverings partitions / Insulation
2w 12/03/2018 12/03/2018 1w A
23/03/2018 16/03/2018
29
M&E 1st fix
2w
19/03/2018
03/04/2018
2w
2nd 26/02/2018
3rd 09/03/2018
27
22
CONCRETE COLUMN
27 31
MULLION DOUBLE GLAZING
1w
20
21
25
26
27
22
23
24
28
29
30
25
26
27
31
The curtain wall system has connections to all the concrete slabs and walls, SFS system and meeting another glazing on the corners. Therefore detailed Planned by Asta Powerproject drawings are produced by the manufacturers to confirm the details of installation and they gives guidelines to the workers to install them accordingly to the building Planned by Asta Powerproject on site. 32
33 28
29
FloorLIFT Level SHAFT 30
Ground SFS
1st
Dwg No. 00001
Drawn by: Planner - Chart Properties
ROOF WORKS
Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
3
1w 20/02/2018 6w 19/02/2018A 26/02/2018 03/04/2018A 1w 28/02/2018 A 06/03/2018 1w 19/02/2018 A 23/02/2018 1w 08/03/2018 1w 26/02/2018 A 14/03/2018 02/03/2018
BWK 3rd - 4th Ground Floor Internal Finishes Curtain walling 3rd -4th
24
2018 March 19 3
Glenn Reeves 6
2w 19/02/2018 26/02/2018 09/03/2018A 1w A 23/02/2018 2w 05/03/2018 16/03/2018 2w 26/02/2018 A 09/03/2018 2w 12/03/2018 2w 12/03/2018 23/03/2018 23/03/2018
7
12
5
Corten grnd - 1st BWK grnd - 1st Corten 1st - 2nd BWK 1st - 2nd
13 6
2
3
-2
10 3
5
Stepnell ltd4
BWK 1st - 2nd
6
8 1 9 2
1
1w 19/02/2018 A 23/02/2018 A
5
7 BWK Line
February 19 26 -1
siw week Programme -2
30
4th
Plantroom
31
Plant room steel
1w 26/02/2018 A
02/03/2018
32
Parapet works
1w
05/03/2018
09/03/2018
33
Main coverings / Insulation
2w
12/03/2018
23/03/2018
Roof
Notes: Comment - Chart Properties
Revision No. A
31
32
33
Floor Level
2
Ground
1st
Drawn by: Planner - Chart Properties
2nd
Dwg No. 00001
3rd
Revision No. A
4th
Plantroom
Roof
Notes: Comment - Chart Properties
Project Ref. C:\Users\glenn.reeves\Desktop\Six week Programme.pp
3/ GLAZING TO SFS SYSTEM C-SECTIONS
The curtain wall system that the building is applied to has a u-value of 0.15W/m2K, which meets the recommended u-value of a non- domestic building wall in the UK, within 0.22W/m2K. This suggests that the building can perform well under thermal comfort.
1
74
25
Facad
Facad
Facad
W13
20
50
40
50
W13 - Type 6
Hole diameters of 20mm and 40mm at 50mm centres horizontally and vertically. A minimum margin of 15mm to be maintained from edge of panels
Facade Module
Round Perforation - Straight Line
Facade Module
Brise Soleil Bracket centres tobe agreed with Acorn
30
1
100mm Benchmark Quadcore Karrier Vertically laid or similar fixed with a minimum of 2 Nr fasteners per panel per rail U-Value = 0.18W/m2K
W 13
35mm Benchmark Metallic Recessed Fix Cassette or similar
100 mm Infill SFS fixed to the structure
FFL = 45.464
FFL = 45.464
Aluminium Fixing Plate
W 05
30
275mm concrete deck to Structural Engineer's details
Corten steel claddings also apply on the windows, covering the glazing. It is, however, does not look the same as the claddings on the SFS system and the concrete walls. It has holes on the surface in order to penetrates some daylight into the interior.
Curtain Walling System Frameless Window insert to Curtain Walling System
Mullion fixing to Curtain walling System
Waterproof membrane
FFL = 42.230
Cavity barriers and smoke stop for Curtain Walling to suit site. Bracket Structural Fixing to Structural Engineers Details
30
FFL = 42.930
CLAD ON WINDOWS
Acoustic Insulation
As the design of the windows are opening mechanically, users, like students, cannot open the window by themselves. They are designed as simply for ventilation and for the janitors to clean the windows and glazings. REV. DATE
Perforated Cor-Ten Cassette Screen setback 25mm from adjacent Corten cladding panels
DESCRIPTION
BY
Sample is provided to the contractor in early stage of the construction to confirm the quality and the Confetti Media Group aesthetic of the claddings. This also gives a sense of Confetti CQ Campus how the building will looks after applying the claddings. Architects, Landscape & Interior Design
16-20 Bath Street, Nottingham NG1 1DF
T
0115 841 8418
E
design@allanjoycearchitects .co.uk
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
Window pod PIR board and fire rated canister applied insulation
PROJECT
Outer sill flashing with interface to recessed fix cassette
FFL = 38.930 30
FFL = 38.930
Corten gutter system with interface to recessed fix cassette
Facade Elevation
1
Facade Section Detail 1 - 1
DRAWING
Facade Section Corten Cladding Detail
The 2588 work 1:20 @ A1has not Jul-16 started yet, as the claddings has not 301 Preliminary MLD but it will soon be installed along with arrive to the site, the general claddings installing on the SFS system. PROJECT NUMBER
SCALE
DRAWING NUMBER
REVISION
DATE
STATUS
BY
This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
75
U/S 2.76
U/S 2.37
3
2
X011 STAIR 2 LOBBY
1
Lift
1646
1492
7718
D
E
U/S 2.78
CH 3.36
SH 0.19 HH 3.03 Indicative location of reception desk by others
2000
11
12
13
14
15
16
17
18
19
535 ID 015
2778
100 ID 012
2000
ID 021 148
X002 MTG 1 9 m2
2740
837
1700
X014 SERVER 16Ground m2 Floor
1184
35.048
X020 MTG 3 9 m2
1135
2597.5
MJ
3947.5(17 1/2 bricks)
U/S 2.76
U/S 2.37 DP
215
D
7718
Ee
ED 04
3751
04/01/18 19/12/17 08/11/17 18/09/17
K J II H G
24/08/17 18/08/17 30/05/17 17/08/17 30/05/17 12/05/17
Change to the slab edge following the SE info Amendments to drawings following the Cladding info Change to the 1st floor café/kitchen area Amendments to HEC stair 2 following the SE info Amendments to drawings following the Topo Survey and SE info
MLD MLD MLD MLD MLD MLD
F E D C B A
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
Change to doors and Stair 1 Lobby Spec Refs added Amendments to drawings Amendments to drawings Amendments to drawings Amendments to drawings
MLD MLD MLD MLD MLD MLD
X017 PLANT ROOM 30 m2
DESCRIPTION
BY
REV. DATE
F HH 2.05 SH 0.87
DH 2.05
Amendments to substation and meeting room layout Amendments to substation layout Amendments to substation layout Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1
1 6-20 Bath Street, Nottingham NG1 1 DF
4959
G
14 13 12
MLD
AIR GUARD
MLD MLD MLD MLD
76 Architects, Landscape & Interior Design
6128
E Ground Floor 35.440
O N M L
eq.
3 SCH 2.8
C
1492
29/01/18 Amendments to internal doors ID008 MLD 16/01/18 MJ, CFB, Bricks setting out and downpipe position added MLD Amendments to internal wall partitions,dimensions updated
H003
223 1646
CH 2.99
G
Ground Floor 35.630
Col
llery H002 Ga CH 2.99
CH 2.76
ID 019 ID 018
3491
Lift
Ground Floor 35.048
1800
X011 STAIR 2 LOBBY
1
X010 STAIR 2
SH 0.88 HH 2.97
2
14/02/18 Amendments to internal partitions
Q P
SH 0.88 HH 2.97
3
SH 0.86 HH 2.03
4
U/S 2.27
5
DH 2.05
6
R
17
eq.
Ground Floor 35.630 7
Ground Floor 34.740
ED 03
32.86
5
ID 017
Bl
X018 NEW STORE (86m2)
Type 1*
Ground Floor 35.630
3
1in10
3a ID 010
Ground Floor 35.048
X004 MTG 2 8 m2
- 3steps
ID 009
NEW IS 004 3532
Type 1*
20
1010
1532
535
10
Type 2
768
9
X012 clnrs cpbd 3 m2
IS 003 148
148
1500 34.828
221 B
8
Mechanical riser
2000
IS 002 2810
2806
ID 016
1736
Type 1*
1736
422
ID 011
Ground Floor 35.048
3248
1092
1736
ID 007
UP 82
ID 022
Ground Floor 35.630
2617
1215
763
1225
Type 1*
X018 Staff Corridoor
PARTITION Wall Type 1 - without16mm Resilient Bar
324
X015 COMMS 13 m2
140
Ec
11857
PARTITION Wall Type A 3no. Layers 15mm Soundbloc either side of BG 146mm C Stud at 300mm Centres within 148mm Head and base channels. 75mm Isover APR between studs with Skim finish to both side of partition.
3574
Ed
Ground Floor 35.630
Ea
7
X003 OFFICE 26 m2
Eb
1010
338
3471
3a
ID 013 1736
Type 1*
34.910
- 3steps
224
1496
1110
252
1696
1010
3070 4642
314
1500
ID 014
HH 2.98 SH 1.1 5
Type 1*
1100MM HIGH
34.63
Electrical riser
Type A
3306
1178
X019 Mtg cpbd
450
1930
400
PARTITION Wall Type 3 1no. Layer of 15mm Soundbloc MR either side of 70mm C Studs with 50mm Isover APR between studs. Skim finish to both sides of partition.
e
5789 LOWWALL
1in15
Ground Floor 35.630
ir Storag Under Sta
2552
CH 2.84
IS 001
Type 3
1in12
1184 ID 008
1343
400
1854
400
PARTITION Wall Type 2 1no. Layer of 15mm Soundbloc either side of 92mm C Studs with 50mm Isover APR between studs. (Use 15mm Soundbloc MR in WC Areas) Skim finish to both sides of partition.
3545
Ground Floor 35.048
1in12
3390
Type 2
In Abeyance
1656 138
1828
4596
5000
Ground Floor 35.464
2500
2a
1010
234
1110
1202
DH 2.03
1
et MMC cabin
DH 1.97
2
496 400
34.910 UP
1010
PARTITION Wall Type 1 2no.layer of 12.5mm Soundblock either side,16mm Resilient Bar fixed to one side, 92mm C studs with 50mm Isover between studs. Skim finish to both sides of partition.
Type 1*
820
34.68
4
Ground Floor 35.630
3
Type 1*
1408 ID 006
3546
ID 003 ID 002
CH 3.68
311
35.464
100
ID 005 499
36.60
ID 001
Ground Floor 35.464
X009 STAIR 1 LOBBY Type 1*
220 A
X001 RECEPTION 130 m2
X005 WC LOBBY
1979
410
5
U/S 3.14
300
6
1010
walls 500
17
Floor
34.74
4742
7
15 m2
Type 1*
3700
- 3steps
CH 2.37
X008 STAIR 1
2 17 mGround
ID 004
FFL
8
Ground Floor 35.464
.76 1600 34
10
Ground Floor 35.048
34.69
X006 WC CHANGING (MALE WC)
01
9
X007 WC CHANGING (FEMALE WC)
DH 2.05
W 01
Type 1*
34.910
ork 140 Blockw
3200
1a
BOARDING 1000
Ground Floor 35.464
Type 3
310
X013 CONTROL ROOM 8 m2
5038
ED 02 13
12
X016 SUBSTATION 20 m2
10
34.71
3546
CH 3.39
W 03
50
11
04 Step +0.
ED 12
STN/128 36.04
MJ
34.66
9215
.50
300
bricks) 15740(71
0 to Fit approx. 250
552
1810
4
W 02
bricks)
300
03 5 123 10 579 19
1000
1200
E
34.74
1000
400
800
600
1/2 6413(28
F
Existing Wall Confetti Insulation to be agreed with Structural Engineer Exposed concrete finish
Type 1
DH 2.1 0
3160
2951
10
34.69
Ground Floor 35.300
il A - 306 Plan Deta
10534 1000
35.20
bricks) 9215(41
See drawing 2588-306 for recessed downpipe details
Floor
Ec 4452
Ee
6752
Ed
421
34.61
4550
34.82
Ea
Eb
34.90
g out Line Bricks Settin
35.10
E
35.00
35.20
1492
D
35.24
35.46
35.32
1646
C
35.09
223
422
34.70
.12
35.28
35.46
G
Existing Wall HE Centre 215mm Existing Solid brick wall 25mm cavity depth Metal studs at 600mm centres - K10/165A 12.5mm Plasterboard
AVCL
.48
AVCL
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish
AVCL
5
1184
3a
4
2176
AVCL
330
1in12
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns Wall Construction - Blockwork Outer / SFS Inner 100mm fairfaced medium density blockwork - F10/225 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns
3
DH 2.05
190 503.5
497
Key Walls
DH 2.05
HH 2.05 SH 0.87
UP
PROPOSED GROUND FLOOR GA PLAN -1:50
The works of partitions have not completed as and the currentF stage is up to the 6128 4th floor. Partitions are mainly 14 G 13 made of 2 layers of insulations, enhancing the blocking 12 of sound transmission. There are a boarding and air 11 10 guard between then to ensure ventilation between 9 8 spaces. HH 2.05 SH 0.87
Ground Floor 35.440
SP 2.23
3 SCH 2.8
U/S 3.14
C
H003
3562
Col
223
N
B
allery H002 G
2279
A
G
Ground Floor 35.630
FFL 35.44
C 222
CH 2.99
ID 018
CH 2.76
ID 019
CH 2.99
X010 STAIR 2
SH 0.88 HH 2.97
4
SH 0.88 HH 2.97
5
6
DH 2.04
7
SH 0.86 HH 2.03
8
U/S 2.27
9
DH 2.05
FFL 35.63
10
3491
DP
THL 35.64
P
35.47
t
314
Ground Floor 35.630
ARTITIONS
ED 14
n poin Insertio
STN/142 35.51
8.7
1
8
MJ
ID 017
T
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
F
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
H CLIENT
C ONNECTION
8.8
The photos below show the process of the demolition of a corner of the existing building, Confetti ICT. From just protecting the existing,421 to attempt to punch through,420 to removing brick t Line walls. Setting ou
TO EXISTING BUILDING Ee
students are not using the building and minimize the noise and negative effects to them.
The workers kept the bricks of the demolished wall on Assuming area ofto existing to be removed the Covert street seeboxing whether they? can reuse the bricks to the building.
6752
Ed
EcIt will be connected from the ground floor till the second 51 29
1/2 bricks) 6413 (28
U/S 1 .39
E - 306
225
2502
4642
810min.
444
400
1736
444
LOW WALL
Ed
249
Eb
77
X102
Type 1*HATCHED SECTION INDICATES AREA OF
R Q
4500
Type 2
ID 108
ID 108
360
535
Ea
1010
1318
First Floor X103 38.930 CAFE SERVERY 79 m2
AREA
bricks) 7660(34
4099
Win/A 4 SH 2.0
Ec
up 338
W 07
ADDITIONAL SEATING
1100MM HIGH
First Floor 38.230
bricks) 7415(33
1178
ID 109
Slab Level 38.568
First Floor 38.930
0 STN/11 38.23
5789
(FFL 38.590)
6 SH 0.8 TA 2.94
Type 1
6 CH 3.2
1100MM HIGH
3286
Electrical riser
LOW WALL
First Floor 38.568
2597.5
7366
up 340
up 2 2
324
FFL 38.23
First Floor 38.764
- 1in15 up 166
NEW STEPS
1100MM HIGH
450
First Floor 38.930
1500
2552
247
LOW WALL
1500
IS 101
400
9 STN/10 38.27
400
2500
6509
First Floor 38.568
- 1in15 up 196 1854
4154
- 1in15
e ing out Lin Bricks Sett
1506
l B - 306 Plan Detai
300
1303
233
up 2 0 8
1in15
.5
ID 102 1010
2114
2950
400
3120
0 DH 2.0 Win/A 5 SH 2.0 3 HH 2.5
3638
Type 2
1045
ID 106 1699First Floor 570 38.360
MJ562
1
ID 105 1010
UP
0 SH 0.9 3 HH 2.5
2
Type 1
Type 1
FFL 38.36
ID 101
251
3
1457
910
First Floor 38.764
Type 2
40.89 Ceil 8 STN/10 38.36
5
2105
X109 STAIR 1 LOBBY
1710
296
Type 3
6
2 DH 2.0
1526
1 U/S 2.0 38.27
19 20
4
Type 1
4
220 A
ID 103
U/S 2.9
6 DH 1 .9
18
First Floor 38.568
38.21
X108 STAIR 1
ID 104
FFL 38.28 1 SH 0.9 6 HH 1 .9
17
lope Floor S 38.31
X106 FEMALE WC
16
10
38.24
416
Ceil 41 .1 0
15
X104 SEMINAR ROOM Type 3 29 m2
Wall 1.29h
3109
X107 ACCESSIBLE Type 2 WC 00 1010 1
el U/S lev 41 .06
11
7
Existing Door-Screen to be maintained
MAR 2018
2200min.
W 02
. 1500min
JAN 2018
FFL 40.30
EXISTING CONFETTI ICT
4
OCT 2017
9 STN/12 39.72
225
38.22
0 SCH 4.9
38.23
HH 2.87 SH 0.80
D - 306
HH 2.87 SH 0.80
l Plan Detai
l C - 306 Plan Detai
l Plan Detai
3 SCH 4.3
floor. By using ramps, level difference of the 2 buildings Eb 4452 F is altered and making the building more accessible to E 3927.5 300 finishing the connection 9of1/230b0ricks)all. This also open up more spaces for the new confetti 550 contractor aim at 4The bricks) 2485 9215(41 15627.5(6 J M the new and the existing within the Easter break building. of Confetti. This is to make use of the time that the W 06 9215
14/02/18 Amendments to internal part 07/01/18 Amendments to Internal Part
M& E
THIS IS A CAD DRAWING - DO NOT HAND MODIFY - DO NOT SCALE - PHOTOCOPYING MAY DISTORT. COPYRIGHT IN THIS DRAWING IS THE PROPERTY OF MIES BUILDING SERVICES. IT MUST NOT BE REPRODUCED, AMENDED OR USED FOR THE EXECUTION OF ANY WORKS WHETHER IN CONNECTION WITH THE PROPOSED WORKS FOR WHICH IT HAS BEEN PREPARED OR OTHERWISE WITHOUT THE EXPRESS CONSENT IN WRITING OF MIES BUILDING SERVICES.
CORRIDOR SECTION AA 1:10 SCALE
2a
3a
ELECTRICAL CROSSOVER ZONE
2ND FIX
315Ø SUPPLY DUCTWORK
The work of M&E is continuing on the site with a completion of 1st fix from the ground level to the 3rd level. The workers are currently working the 1st fix of M&E on the 4th and 5th floor. 475
375
LIGHT FITTING
100
100
100
500 ELECTRICAL CONTAINMENT ZONE
1050 28Ø CONDENSATE DRAINAGE FROM FCU'S 15x15Ø LTHW F&R
28x28Ø CHW F&R
900
275
150
PIPEWORK CROSSOVER ZONE
2615
1ST FIX DUCT WORK
At the same time, 2nd fix of M&E, including light fitting is working on the 1st and 2nd floor, but not the ground level. This is due to the design of the space in these 2 levels consist more open spaces with minimal internal partitions that allows multiple tasks, such as cutting ducts and fitting lights happen at the same time. In such case, it speeds up the work within a floor.
Notes:
1. For corridor 2. All dimensio 3. All measure 4. Any errors o before work co
X207 ACCESSIBLE WC
X204 SEMINAR ROOM 30 m2
X206 MALE WC
X208 STAIR 1
EXIT
EXIT
8.9
X209 STAIR 1 LOBBY
EXIT X201 LRC 172 m2 THIS IS A CAD DRAWING - DO NOT HAND MODIFY - DO NOT SCALE - PHOTOCOPYING MAY DISTORT. Electrical riser
COPYRIGHT IN THIS DRAWING IS THE PROPERTY OF MIES BUILDING SERVICES. IT MUST NOT BE REPRODUCED, AMENDED OR USED FOR THE EXECUTION OF ANY WORKS WHETHER IN CONNECTION WITH THE PROPOSED WORKS FOR WHICH IT HAS BEEN PREPARED OR OTHERWISE WITHOUT THE EXPRESS CONSENT IN WRITING OF MIES BUILDING SERVICES.
CORRIDOR SECTION AA 1:10 SCALE
2a
3a
SERVICES LEGEND CHW PIPEWORK
ELECTRICAL CROSSOVER ZONE
315Ø SUPPLY DUCTWORK
475 375
100
100
100
500 ELECTRICAL CONTAINMENT ZONE
X203 LRC 50 m2
X205 COMPUTER SUITE 51 m2
LPHW PIPEWORK MCWS/BCWS PIPEWORK AGD PIPEWORK
1050 28Ø CONDENSATE DRAINAGE FROM FCU'S
SUPPLY DUCTWORK 15x15Ø LTHW F&R
28x28Ø CHW F&R
EXTRACT DUCTWORK
900
275
150 PIPEWORK CROSSOVER ZONE
WC EXTRACT DUCTWORK LIGHT FITTING LV/FIRE CONTAINMENT DATA/ELV CONTAINMENT SUB MAIN CONTAINMENT Lift
X210 STAIR 2
1ST FIX A0
ABBREVIATIONS
X211 STAIR 2 LOBBY
LL HL CHW AGD LPHW BCWS MCWS LV ELV
DENOTES LOW LEVEL DENOTES HIGH LEVEL DENOTES CHILLED WATER SERVICE DENOTES ABOVE GROUND DRAINAGE DENOTES LOW PRESSURE HOT WATER DENOTES BOOSTED COLD WATER SERVICE DENOTES MAINS COLD WATER SERVICE DENOTES LOW VOLTAGE DENOTES EXTRA LOW VOLTAGE
2615
DUCT WORK 78
9
S PECIAL
INTEREST CONCRETE FINISHES
9.1
HISTORY:
ROMAN EMPIRE (BC)
CONCRETE 19-20TH CENTURY Followed by the fall of the Roman Empire, the technique was forgotten until the 14th century. However, the construction method was not common until the 19th century. PORTLAND CEMENT A method for producing Portland cement was patented by Joseph Aspdin in 1824, which made the foundation of the important component in concrete mixes nowadays. REINFORCED-CONCRETE SYSTEM The French engineer, François Hennebique, patented his pioneering reinforced-concrete construction system in 1892. He built the Weaver building using this system and it was Europe’s first multi-storey reinforced concrete building.
Concrete was first and commonly used as construction material in the Roman time. Architecture are still standing after 2000 years, indicating the long durability of concrete. Pantheon was one of the example that it is still the largest unreinforced concrete dome and the smooth surface finish allowed artists to draw fresco on top.
CLIMAX OF CONCRETE CONSTRICTION The technique was further developed not only on civil construction, but the way of building in more sculptural forms was also developed and architects such as Nervi, Saarinen and Niemeyer build their architecture in a more expressive form, making the technology reached its climax in the 1950’s-70’s. This also form the foundation of current concrete construction.
(TWAFlight Centre, Eero Saarinen)
80
CONCRETE
CONFETTI STRUCTURAL SPECIFICATION 25400 Confetti CQ
• • •
• • • •
•
125 • • •
BRITISH STANDARD (BS)
E10 Mixing/casting/curing in situ concrete
DESIGNATED CONCRETE For use for visually exposed elements including specified floor slabs, columns, and walls. Refer to drawings for clarification. Designation: RC40. Fibres: None. Aggregates: - Size (maximum): 20 mm. - Coarse recycled aggregates: Permitted at a mass fraction not exceeding 15% of coarse aggregate. Details to be submitted to CA for approval. - Additional aggregate requirements: No more than 20% to pass through a 10mm sieve. Aggregate types to be consistant for the entirity of the contract. Special requirements for cement/ combinations: minimum 325kg/m3 cememnt content . Consistence class: S3. Chloride class: Cl 0.40. Admixtures: Details of proposed admixtures to be given to the CA allowing two weeks for comment by the CA before their use in the concrete. Additional mix requirements: Mix should achieve a consistent light grey colour free from blemishes or discolouration. Refer to other clauses related to visual concrete. When materials have been determined no changes can be made to the mix proportions or the water/cement ratio. A single readymix source is to be used for the entirity of the contract. SUBSTITUTION OF STANDARDIZED PRESCRIBED CONCRETE FOR DESIGNATED CONCRETE General: Conform to BS 8500-2, clause 9. Substitution: In accordance with BS 8500-1, Table A.14. - Proposals: Submit for each substitution, stating reasons. Site mixing: If standardized prescribed concretes are made on site conform to BS 80002.1, subsections 2,3 and 4..
182N CONCRETE FOR SUNDRY TYPES OF IN SITU WORK • Specified in other sections of this specification as follows: - E60 Precast/Composite concrete floors/roof decks - F30 Accessories/Sundry items for brick/block/stone walling - F31 Precast concrete sills/lintels/copings/features - Q10 Kerbs/edgings/channels - Q40 Fencing - Q50 Site/street furniture/equipment - R12 Drainage below ground - R13 Land drainage • Concretes specified in this section which are equivalent to or better than the above may be used in lieu, subject to approval.
The above is the structural specification that the structural and civil engineering consultancy, Price & Myers specify the finishes of Insitu concrete according to the British Stardard. 5 Dec 2016
Ver. 1
BRITISH STANDARD (BS)
Concrete - Part 2: Specification for constituent materials and concrete
E10 / 2
BS 8500-2:2015+A1:2016
Concrete – Part 1: Method of specifying and guidance for the specifier
BRITISH STANDARD
BRITISH STANDARD Table A.6
Table 6 Concrete designation
Licensed copy:Nottingham Trent University, 18/03/2018, Uncontrolled Copy, © BSI
107
MIXES: CEMENT
Requirements for designated concretes for general applications Min. strength class
Slump class A)
GEN0 GEN1 GEN2 GEN3 RC20/25 RC25/30 RC28/35 RC30/37 RC32/40 RC35/45 RC40/50 RC40/50XF PAV1 PAV2
C6/8 C8/10 C12/15 C16/20 C20/25 C25/30 C28/35 C30/37 C32/40 C35/45 C40/50 C40/50 C28/35 E) C32/40 E)
S3 S3 S3 S3 S3 S3 S3 S3 S3 S3 S3 S3 S2 S3
FND2
C25/30
S3
FND2Z
C25/30
S3
FND3
C25/30
S3
FND3Z
C25/30
S3
FND4
C25/30
S3
FND4Z FND4M
C25/30 C25/30
S3 S3
Max. w/c ratio
— — — — 0.70 0.65 0.60 0.55 0.55 0.50 0.45 0.45 C) 0.55 C) 0.45 C) 0.55 0.50
Min. cement or combination content (kg/m3) for max. aggregate size (mm) ≥40 20 14 10 120 120 120 120 180 180 180 180 200 200 200 200 220 220 220 220 240 240 260 280 240 260 280 300 260 280 300 320 280 300 320 340 280 300 320 340 300 320 340 360 320 340 360 360 320 340 360 360 280 300 320 340 320 340 360 380 300 320 340 360 320 340 360 380
0.45 0.40 0.55 0.50 0.45 0.40
340 360 300 320 340 360
360 380 320 340 360 380
380 380 340 360 380 380
380 380 360 380 380 380
0.50 0.45 0.40 0.35
320 340 360 380
340 360 380 380
360 380 380 380
380 380 380 380
0.45 0.45
340 340
360 360
380 380
380 380
CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B) CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B) CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B) CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B) CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B) CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B) CEM I, IIA, IIB-S, IIB-V, IIIA D) CEM I, IIA, IIB-S, IIB-V, IIIA D) CEM I, IIA, IIB-S, IIB-V, IIIA D) IIB-V+SR, IIIA+SR, IIIB+SR, IVB-V CEM I, CEM I-SR 0, CEM I-SR 3, II-S, II-V, IIIA, IIIB IIA-L or LL class 42,5 IIA-L or LL class 32,5 All in Table 1 IIIB+SR IVB-V IIB-V+SR, IIIA+SR, CEM I-SR 0, CEM I-SR 3 All in Table 1 IIIB+SR IVB-V IIB-V+SR, IIIA+SR, CEM I-SR 0, CEM I-SR 3 All in Table 1 IIIB+SR
Except where a different consistence class has been specified. In this case, the concrete conforms to the specified consistence class or target value. B) Only if specifically permitted under BS 8500-1:2015+A1:2016, 4.2.3a). C) See 6.3.2 for requirements for aggregates. D) With a maximum proportion of ggbs 55% unless a higher proportion is specifically permitted under BS 8500-1:2015+A1:2016, 4.2.3a). E) The concrete contains an air-entraining admixture to give minimum air content by volume at delivery of 4.0%, 4.5%, 5.5% or 6.5% with aggregate of 40 mm, 20 mm, 14 mm and 10 mm aggregate size respectively at delivery. A)
It is in the section of E41 , indicating the application of each type of finishes for the contractors to follow and refer to specific documents. Portland Cement is the most common cement that used in the UK, which composed more than 95 percent of 16 •
© The British Standards Institution 2016
BS 8500-1:2015+A1:2016
Cement and combination typesA)
Broad designation B)
Composition
CEM I CEM I-SR 0
Portland cement Sulfate-resisting Portland cement
Comprises cement and combination types (see BS 8500-2:2015+A1:2016, Table 1) CEM I CEM I-SR 0
Cement and combination types
CEM I-SR 3 IIA
IIB-S
Licensed copy:Nottingham Trent University, 18/03/2018, Uncontrolled Copy, © BSI
9.2
IIB-V IIB+SR IIIAD) IIIA+SR
IIIB F) IIIB+SR
IVB-V G)
Portland cement with 6% to 20% fly ash, ground granulated blastfurnace slag, limestone, or 6% to 10% silica fume C) Portland cement with 21% to 35% ground granulated blastfurnace slag Portland cement with 21% to 35% fly ash Portland cement with 25% to 35% fly ash Portland cement with 36% to 65% ground granulated blastfurnace slag Portland cement with 36% to 65% ground granulated blastfurnace slag with additional requirements that enhance sulfate resistance Portland cement with 66% to 80% ground granulated blastfurnace slag Portland cement with 66% to 80% ground granulated blastfurnace slag with additional requirements that enhance sulfate resistance Portland cement with 36% to 55% fly ash
CEM I-SR 3 CEM II/A-L, CIIA-L, CEM II/A-LL, CIIA-LL, CEM II/A-S, CIIA-S, CEM II/A-V, CIIA-V, CEM II/A-D CEM II/B-S, CIIB-S CEM II/B-V,CIIB-V CEM II/B-V+SR, CIIB-V+SR CEM III/A, CIIIA CEM III/A+SR E), CIIIA+SR E)
CEM III/B, CIIIB CEM III/B+SR E), CIIIB+SR E)
CEM IV/B-V, CIVB-V
There are a number of cements and combinations not listed in this Table that may be specified for certain specialist applications. See BRE Special Digest 1 [1] for the sulfate-resisting characteristics of other cements and combinations. See IP 17/05 [5] for the use of high ggbs content cements and combinations in secant piling applications. B) The use of these broad designations is sufficient for most applications. Where a more limited range of cement or combinations types is required, select from the notations given in BS 8500-2:2015+A1:2016, Table 1. C) When IIA or IIA-D is specified, CEM I and silica fume may be combined in the concrete mixer using the k-value concept; see BS EN 206:2013, 5.2.5.2.3. D) Where IIIA is specified, IIIA+SR may be used. E) “+SR” indicates additional restrictions on the chemical composition of cement or ggbs related to sulfate resistance. See BS 8500-2:2015+A1:2016, Table 1, footnote D. F) Where IIIB is specified, IIIB+SR may be used. G) IVA cements and combinations with a siliceous fly ash should be classified as II-V. A)
lime, silica, alumina and iron oxide. The British Standard document stated a list of factory-produced cement that contain a proportion of Portland cement. They will produce concrete that possess different colour and strength. © The British Standards Institution 2016
•
33
81
9.3
CONCRETE
25400 Confetti CQ 107 • • •
• • • •
•
125 • • •
E10 Mixing/casting/curing in situ concrete
DESIGNATED CONCRETE For use for visually exposed elements including specified floor slabs, columns, and walls. Refer to drawings for clarification. Designation: RC40. Fibres: None. Aggregates: - Size (maximum): 20 mm. - Coarse recycled aggregates: Permitted at a mass fraction not exceeding 15% of coarse aggregate. Details to be submitted to CA for approval. - Additional aggregate requirements: No more than 20% to pass through a 10mm sieve. Aggregate types to be consistant for the entirity of the contract. Special requirements for cement/ combinations: minimum 325kg/m3 cememnt content . Consistence class: S3. Chloride class: Cl 0.40. Admixtures: Details of proposed admixtures to be given to the CA allowing two weeks for comment by the CA before their use in the concrete. Additional mix requirements: Mix should achieve a consistent light grey colour free from blemishes or discolouration. Refer to other clauses related to visual concrete. When materials have been determined no changes can be made to the mix proportions or the water/cement ratio. A single readymix source is to be used for the entirity of the contract. SUBSTITUTION OF STANDARDIZED PRESCRIBED CONCRETE FOR DESIGNATED CONCRETE General: Conform to BS 8500-2, clause 9. Substitution: In accordance with BS 8500-1, Table A.14. - Proposals: Submit for each substitution, stating reasons. Site mixing: If standardized prescribed concretes are made on site conform to BS 80002.1, subsections 2,3 and 4..
182N CONCRETE FOR SUNDRY TYPES OF IN SITU WORK • Specified in other sections of this specification as follows: - E60 Precast/Composite concrete floors/roof decks - F30 Accessories/Sundry items for brick/block/stone walling - F31 Precast concrete sills/lintels/copings/features - Q10 Kerbs/edgings/channels - Q40 Fencing - Q50 Site/street furniture/equipment - R12 Drainage below ground - R13 Land drainage • Concretes specified in this section which are equivalent to or better than the above may be used in lieu, subject to approval.
5 Dec 2016
Ver. 1
M I X E S : A G G R E G AT E S
Aggregates can be both naturally occurred or secondary recycled. For natural aggregates in the UK, they are mainly sand and gravel, marine aggregates and crushed rocks. Recycled aggregates are defined as materials resulting from the crushing of demolition waste and reprocessing of construction waste or damaged material on site. They are usually crushed concrete and brick masonry.
There are 2 types of form in coarse aggregates, the angular and the rounded. This variation in shape , surface smoothness and porosity will affect the workability and the surface finish of the concrete The angular aggregates work well in interlocking which give a higher strength concrete. However, the rough and variable surfaces affect the demand of water in the mixture, and might led to patches on surfaces, commonly called as ‘aggregate bridge’. The rounded gravels have a more constant surface, making them more suitable for fine finishes . To avoid aggregate bridges, it is preferably specify the size as 20mm aggregates or to limit the stone passing a 10mm sieve to not more than 20per cent.
The Confetti project used recycled coarse aggregates
E10 / 2
AGGREGATE BRIDGE
82
9.4
C O LO U R S
25400 Confetti CQ 107 • • •
• • • •
•
125 • • •
E10 Mixing/casting/curing in situ concrete
DESIGNATED CONCRETE For use for visually exposed elements including specified floor slabs, columns, and walls. Refer to drawings for clarification. Designation: RC40. Fibres: None. Aggregates: - Size (maximum): 20 mm. - Coarse recycled aggregates: Permitted at a mass fraction not exceeding 15% of coarse aggregate. Details to be submitted to CA for approval. - Additional aggregate requirements: No more than 20% to pass through a 10mm sieve. Aggregate types to be consistant for the entirity of the contract. Special requirements for cement/ combinations: minimum 325kg/m3 cememnt content . Consistence class: S3. Chloride class: Cl 0.40. Admixtures: Details of proposed admixtures to be given to the CA allowing two weeks for comment by the CA before their use in the concrete. Additional mix requirements: Mix should achieve a consistent light grey colour free from blemishes or discolouration. Refer to other clauses related to visual concrete. When materials have been determined no changes can be made to the mix proportions or the water/cement ratio. A single readymix source is to be used for the entirity of the contract. SUBSTITUTION OF STANDARDIZED PRESCRIBED CONCRETE FOR DESIGNATED CONCRETE General: Conform to BS 8500-2, clause 9. Substitution: In accordance with BS 8500-1, Table A.14. - Proposals: Submit for each substitution, stating reasons. Site mixing: If standardized prescribed concretes are made on site conform to BS 80002.1, subsections 2,3 and 4..
182N CONCRETE FOR SUNDRY TYPES OF IN SITU WORK • Specified in other sections of this specification as follows: - E60 Precast/Composite concrete floors/roof decks - F30 Accessories/Sundry items for brick/block/stone walling - F31 Precast concrete sills/lintels/copings/features - Q10 Kerbs/edgings/channels - Q40 Fencing - Q50 Site/street furniture/equipment - R12 Drainage below ground - R13 Land drainage • Concretes specified in this section which are equivalent to or better than the above may be used in lieu, subject to approval.
5 Dec 2016
Ver. 1
The colour of concrete is based on the light absorption qualities of the finest particles in the mixes. The tone of colour will lighten with a higher water/ cement ratio, vice versa. The tone might change lighter due to surface carbonation after the construction. The time of construction also affect the tone of the concrete. Formwork needs to remain in place for longer period in cold winters as the concrete needs more time to gain strength. The water vapour of the cement cannot escape , therefore, condenses and saturates on the surface, making the concrete darker in tone. However, water vapour leaves the concrete more quicker and easier in the summer, forming a lighter tone of colour.
PIGMENT SPECTRUM
To colour the concrete, another possible way is to introduce pigment to the mix. The pigment dominates the colour as it is finer than the cement. The pigments rage colour from red oxide to brown oxide to yellow oxide.
E10 / 2
However, as the project of Confetti just require the concrete in light grey colour, no pigment is needed. It can be achieved by controlling the ratio of cement, aggregates and water as well as the duration concrete drying.
(Centre for Interpretation of The Battle of Atoleiros / Gonçalo Byrne Arquitectos)
83
concrete concrete surface surface its its visual visual impact impact Influencing the surface texture and colour shade with formwork components. Influencing the surface texture and colour shade with formwork components.
9.5
WA L L
FINISHES: FORMWORK
Fair-faced concrete is concrete in its – visibly – finest form. It is also one of the biggest challenges in formwork engineering. Reliably producing concrete of istheconcrete desired infair-faced concrete category greatof experience working with the right engineering. formwork equipment. If the aim is to Fair-facedfinishes concrete its – visibly – finest form. Itrequires is also one the biggestinchallenges in formwork Reliably producing achieve an immaculate appearance, then having the right formwork sheets is important for achieving the best concrete finishes. concrete finishes of the desired fair-faced concrete category requires great experience in working with right formwork equipment. If the aim is to achieve an immaculate appearance, then having the right formwork sheets is important for achieving the best concrete finishes.
Boards, rough-cut
Boards, planed
Boards, rough-cut Boards, Texture planed sheet Texture 3-SO sheet 3-SO Features: Features: rough, board-type surface smoothFeatures surface with proFeatures: Features: (in addition Features to 3-SO (in addition to 3-SO structure with dark-coloured nounced wood texture rough, board-type surface smooth surface with27pro21 mm and 21 mm): mm and 27 mm): dark-coloured concrete with dark-coloured structure nounced woodconcrete texture brushed surface–brushed surface lighter after several repeat uses lighter after repeat dark-coloured concrete –extra varnish concrete extraseveral varnish sealant on one sealant on one very strong uses after lighter after absorbency several repeat uses lighter sideseveral repeat side low pore board-like formation character hardlystrong any pores on the archivery absorbency uses created board-like character created knots, resin pockets, grooves etc.by recessed tectural surface low pore by formation hardly any pores on the archirecessed (resultsgrooves in (results in knots,texture resin pockets, cause varying absorption knots, resin pockets, tectural surface Influencing the surface andetc.colour shade with formwork components. ribbed finish)etc.ribbed finish) cause varying absorption behaviour knots, resin pockets, etc. cause varying absorption very low absorbency very low absorbency wood sugar sometimes behaviour cause varying absorption behaviour normal pore formation normal pore formation wood prevents concrete hardening wood sugar sometimes Fair-faced concrete is concrete behaviour in its –sugar visiblysometimes – finest form. It is also one of the biggest challenges in formwork engineering. Reliably producing light-coloured concrete light-coloured concrete dust formation on the surface prevents concrete hardening sugar sometimes prevents concrete hardening concrete finishes of the desiredwood fair-faced concrete category requires great experience in working with the right formwork equipment. If the aim is to wood then fibres may be left behind formation on the surface prevents concrete hardening achieve an immaculate appearance, having the right formwork sheets is important for achieving the bestdust concrete finishes. on the surface wood fibres may be left behind
Form-facing – to give the fair-faced concrete surface its visual impact
Dokaplex formwork Dokaplex sheet formwork sheet Features: Features: crosswise glue-bonded birch crosswise glue-bonded birch plywood plywood identically phenolic resin- phenolic resinidentically coated on both coated sides on both sides used in wall andused floor-slab in wall and floor-slab formwork formwork sheet for smoothsheet fair-faced for smooth fair-faced concrete surfaces concrete surfaces cut edge is sealed cut edge is sealed low absorbencylow absorbency structureless surface structureless surface normal pore formation normal pore formation light-coloured concrete light-coloured concrete
on the surface
Formwork sheet 3-SO Boards, rough-cut Formwork sheet 3-SO Features: ply sheetFeatures: (spruce) made of Features: rough, board-type surface crosswise glue-bonded ply sheet (spruce) madetimbers of structure with dark-coloured low proneness to cracking, crosswise glue-bonded timbers due to theconcrete thinner face layers low proneness to cracking, lighter after several repeat uses glue-coated surface due to the thinner face layers very strong absorbency boilproof, alkali-proof, glue-coated surface water hardly any pores on the archiand weathering-resistant boilproof, alkali-proof, water tectural surface glue-bonding and weathering-resistant knots, resin pockets, etc. slight board-type surface glue-bonding cause varying structure (depending onabsorption timber slight board-type surface behaviour moisture content) structure (depending on timber woodand sugar sometimes used on wall moisture content) floor-slab prevents concrete hardening formwork used on wall and floor-slab wood fibres may be left behind consistently high timber formwork on the surface quality consistently high timber smooth concrete faces quality uniform concrete faces smooth slightly absorbent surface uniform concrete faces low poreabsorbent formationsurface slightly Formwork sheet 3-SO
6 | Fair-faced concrete 6 | Fair-faced concrete
low pore formation Features: ply sheet (spruce) made of crosswise glue-bonded timbers low proneness to cracking, due to the thinner face layers glue-coated surface boilproof, alkali-proof, water and weathering-resistant glue-bonding slight board-type surface structure (depending on timber moisture content) used on wall and floor-slab formwork consistently high timber
ProFrame panel Boards, planed ProFrame panel Xlife sheet Xlife sheet Features: Features: 3-ply formwork of Features: Features:sheet made Features: smooth surface with prospruceformwork 3-ply sheet made of birch crosswise glue-bonded crosswise glue-bonded birch nounced wood texture used particularly spruce plywood often forplywood dark-coloured concrete – constructional applications used particularly often forforce-orientated force-orientated glue-bonding glue-bonding lighter after several repeat urea-melamine resin adhesive constructional lines applications lines uses surface with extra adhesive PUfront (concrete-facing urea-melamine resin frontan(concrete-facing side) side) low pore formation varnish sealant sanded surface with extra PUand and an rearlayer covered with plastic rear covered with plastic knots, resin pockets, with corundum on etc. varnish sealant layer sanded skin particles skin cause varying absorption one side with corundum particlessurface on non-absorbent non-absorbent surface behaviour boilproof and weatheringone side sheet for smoothsheet concrete for smooth concrete wood sugar sometimes resistant surfaces glue-bonding boilproof and weatheringsurfaces prevents concrete hardening high-quality all-round resistant high glue-bonding numbersTPU ofhigh repeat uses of repeat uses numbers dust formation on the surface edge protector screwed ontoTPU panel fromonto rear panel from rear high-quality all-round screwed uniform concrete faces, with pore formation normal pore formation normal edge protector slight wood texturefaces,concrete light-coloured light-coloured concrete uniform concrete with is used in Framax Xlife, inAluis used Framax Xlife, Aluslight wood texture Framax Xlife, Frami XlifeXlife, and Frami Xlife and Framax Column formwork KS Xlife Column formwork KS Xlife available as panel loose sheetsas loose sheets available ProFrame
Features: 3-ply formwork sheet made of spruce used particularly often for constructional applications urea-melamine resin adhesive surface with an extra PU varnish sealant layer sanded with corundum particles on one side boilproof and weatheringresistant glue-bonding high-quality all-round TPU edge protector uniform concrete faces, with
Xface sheet Xface sheet Features: Features: crosswise glue-bonded birch crosswise glue-bonded birch plywood plywood side has concrete-facingconcrete-facing side has hard-wearing hard-wearing synthetic resin synthetic resin rear is phenolic-resincoating; rear is coating; phenolic-resincoated coated non-absorbent surface non-absorbent surface for smooth concrete sheet for smoothsheet concrete finishes finishes normal pore formation normal pore formation light-coloured concrete light-coloured concrete available available as loose sheetsas loose sheets screwed onto the panel from screwed onto the panel from the rear the rear used in timber-beam used in timber-beam formwork, formwork, tableforms and tableforms and timber-beam timber-beam floor formwork floor formwork
The formwork is critical in the visual appearance of concrete and it is the most important element of the finishing process. As concrete itself is a liquid rock that has no shape or form, it need to be placed into mould and confined by formwork to shape into elements such as walls, columns and floors. The surface of formwork that contacts with the wet concrete imprint texture, smoothness or roughness of the formed face and gives the concrete its surface quality. There are different kind of formwork surfaces in order to create different textures on concrete. Information on the left are some of the examples of formworks and textures from Doka that compose a fair-faced finishes. Some can create veneer texture through timber layer while some can form patterns . Therefore, the surface of the material need to be clean to imprint the patterns.
Fair-faced concrete Fair-faced |7 concrete | 7
Fair-faced concrete brochure, Doka GmbH
84
•
110 •
Provide details to the CA 5 days before erecting temporary works. Full design details, drawings and calculations, are required for comment by the Engineer for all temporary support systems. Three paper copies of all details for comment are to be issued allowing ten working days for preparation of comments by the Engineer. LOADINGS Requirement: Design and construct formwork to withstand the worst combination of the following: - Total weight of formwork, reinforcement and concrete. - Construction loads including dynamic effects of placing, compacting and construction traffic. - Wind and snow loads.
120X FORMWORK DETAILS • All timber used in formwork shall have a valid Forest Stewardship Council (FSC) 'Chain of Custody Certificate' or other documentary evidence (which has been or can be 25400 Confetti CQ independently verified) of its source and supply chain as agreedE20 withFormwork the CA. for in situ concrete • Provide the following: Details of forms for all 'fair faced' visual concrete finishes shown on drawings,(FINE alongSMOOTH) with a method statement indicated the approach needed to achieved the 630X SPECIAL FINISH/FF1 required standard of finish, comment from the design team. Contractor to allow for All 'fair faced' wallforsurfaces. • Location: input into formwork design by the design To the match the sample image given in theteam. tender pack. Formwork panels and layouts • Finish: are to be agreed by the design team - contractors are to make allowances for the design to make proposals for formwork layouts. 124N team FALSEWORK Special requirements: • Falsework shall comply with the requirements of BS 5975: 2008 Code of practice for It is works envisaged this finish willthe require double-layered plywood shuttering, with a resin temporary procedures and permissible stress design of falsework and HSE faced top layer, and lapped joints. Whole use sheets plywood are be used as Construction Information Sheetformwork No 56: Safe erection, andofdismantling of to falsework far as is possible. Contractor's 125N SHOP DRAWINGS proposals and method statements for this finish are to be discussed with the design team.shop drawings for the following: All visual concrete and allow for fully annotated • Provide Contractor to allow for inspection of forms by CA before rebar is fixed, and make the- input from the isdesign team. arrangements for this in advance to prevent delaying pours. All formwork must be thorough cleaned with plastic faced tools, and is to be 127N PROJECTING FORMWORK protected from rain and standing water on site. No metal must be in contact with the • Where adjacent concrete elements have connecting reinforcement at construction joints formwork face. projecting through suitably designed formwork. leave reinforcement Cuts to formwork are to minimised, but where necessary must be made with sharp • The ends of the projecting bars are to be covered for safety. saw blades, with no tearing or damage to edges . • Permissible deviation of surfaces: 19 Dec 2016- Sudden irregularities (maximum): 1 mm. Ver. 1 E20 / 1 - Gradual irregularities (maximum): 3 mm when measured from the underside of a 1 m straightedge, placed anywhere on surface. • Variations in colour: - Permitted: Those caused by impermeable formwork linings. - Not permitted: Those caused by contamination, grout leakage, leaching of tannins from formwork, inconsistent concrete mix, staining of the formwork, and replacement of formwork panels. • Cover spacers: To be the concrete type, in a colour matching the proposed mix . • Surface blemishes: - Permitted: Blowholes less than 5 mm in diameter and at an agreed frequency. - Not permitted: Voids, honeycombing, segregation and other defects. • Formwork tie holes: In a regular pattern to be agreed by the design team, and filled with matching mortar . 750 •
According to the structural specification document, the formwork this project using is a double layered plywood to create a fair-faced finish. The timber should be in qualified to FSC which ensure the sustainability of the whole project, even in its construction process. The concrete finish of TWA flight centre is used as a precedent and being record in a document by the architect. This is to visualize the appearance of building to the client. The photos on the right shows the process of using shuttering and formwork to form the concrete walls.
ARRISES, MARGINS AND JUNCTIONS Requirements: Arrises are to have a 15mm, 45 degree chamfer..
19 Dec 2016
Ver. 1
E20 / 6
85
9.6
P RECEDENTS:
PHILLIP EXETER ACADEMY LIBRARY
â&#x20AC;&#x153;The quality of concrete work will largely determine PROJECT BRIEF LOCATION: Exeter, USA
the quality of architectureâ&#x20AC;?
Louis Kahn
ARCHITECT: Louis Kahn YEAR OF COMPLETION: 1972
CONSTRUCTION The concrete work was left both uncovered and untouched once the formwork had been removed. The holes and the joint of the formwork became part of the visual effects on concrete surface. The architect carefully designed every form panels and tie and ensure the contractors are able to follow his design as well as avoiding bugholes and honeycombing in the finished concrete.
INTRODUCTION: The building has brick wall on the exterior, covering the reinforced concrete structure in the interior. Staircases and walls in the central hall are made of concrete. It provides workspaces for students and houses books and rare collections. (Phillips Exeter Academy, n.d.)
This preserves the natural finish of the material without using any other materials to furnish the concrete after the formwork had taken down and shows that mindful design on formwork can create aesthetic effects on concrete finishes. 86
9.7
P RECEDENTS:
ABERDEEN LANE CONSTRUCTION FORMWORK: Brich plywood sheets that have sanded and coated with two layers of lacquer before arrive on site.
PROJECT BRIEF LOCATION: Islington, London ARCHITECT: Azman Owens Architects YEAR OF COMPLETION: 2003 INTRODUCTION: The house is designed for a family of six to establish a residential neighbourhood in a lane that dominated by workshops and studios. It is built in wall-to wall insitu concrete with marble smooth finish, giving a clean and seamless surface.
PROCESS: Panels are lightly oiled with high-performance chemical release agent and screw fixed to the back of them. The strong backs and waling to support the form were designed with no tie bolts over the body of the form work. These all minimize the roughness on the formwork and allow the concrete to dried without surface obstacles. The surface is then sanded and polished.
87
9.8
F INISHES
TYPES
The structural and civil engineering consultancy, Price & Myers specify the finishes of Insitu concrete according to the British Standard. It is in the section of E41 , indicating the application of each type of finishes for the contractors to follow and refer to specific documents. 25400 Confetti CQ
E41 Worked finishes to in situ concrete
E41 Worked finishes to in situ concrete To be read with Preliminaries/ General conditions. NOTE New clauses that have been added to the standard NBS are identified with the suffix N. Clauses where an editorial change has been made are identified with the suffix X. 210 •
TAMPED FINISH Surface on completion: Even array of parallel ribs.
310X SMOOTH FLOATED FINISH To receive levelling screed • Surface on completion: Even with no ridges or steps. 520X SURFACE SEALER For exposed concrete walls and columns • Manufacturer: Nufins. - Product reference: Curecote Super Acrylic Curing Membrane. • Substrate: - Moisture content: As recommended by sealer manufacturer. Test relative humidity to BS 8203, Annex A where required to verify suitability. - Condition prior to application: Cured, clean and free from contaminants. • Application: As recommended by manufacturer.
1 TAMPED FINISH
It is created by raising and lowering a beam or a brush on the surface of concrete to create a rough surface with even ridges. It is commonly used in traffic roads construction.
2 SMOOTH FLOATED FINISH
It is produced by a timber or trowels of steel that create a smooth surface. It is usually used in internal space as the smooth concrete surface might become slippery when it is wet. 88
Technical Datasheet Curecote Super Acrylic Curing Membrane Description Curecote Super is a clear styrene acrylic curing and sealing compound designed for application to freshly cast concrete to provide a highly efficient curing membrane. The applied coating remains on the concrete surface to provide a dust free abrasion resistant surface which readily accepts the application of many subsequent finishes. Curecote Super may also be used as a clear sealer on aged concrete to dustproof and provide a surface which is more easily cleaned.
Advantages
Cures and seals concrete in one application.
Prevents dusting of concrete surfaces.
Inhibits efflorescence and acts as an anti-carbonation
Nufins, Kingston House, 3 Walton Road, Pattinson North, District 15, Washington, Tyne & Wear. NE38 8QA 13 0086-CPD-594215
Applications
Curing agent and sealer for new concrete floors which will
EN 1504-2 Surface protection system for concrete Coating
subsequently receive a coating.
Anti-carbonation coating.
Permeability to Water Vapour
Curing agent for concrete cast from formwork.
Curing agent and sealer for freshly cast concrete Components.
Class 2
Adhesive bond strength
≥0.8 MPa
Dangerous substances
Complies with 5.4
Dust proofing/sealer for aged concrete floors.
Technical Information Coverage Curing Efficiency Recommended Spray Pressure
3 POWER FLOAT TREATMENT
It is a method at achieved by using machine,troweller, instead of human power. It provides a direct finished wearing surface that leaves a smooth and very dense surface. It is only suitable for internal usage.
5-6m²/litre
Viscosity
50 centipoise
Over 80% efficient when tested to ASTM 309
Flow Cup
15 Seconds @20oC, B4 Ford Cup
Typically 50-60 psi (3.3-4.0 BAR) Minimum 40 psi (2.7 BAR)
S.G.
0.9
Permeability to Carbon Dioxide
sD >50m
A Head Office: Kingston House, 3 Walton Road, Pattinson North, Washington, Tyne & Wear, UK T: +44(0) 191 416 8360 F: +44(0) 191 415 5966 W: www.nufins.com E: info@usluk.com
It is applied after the concrete is hardened and dried completely. The building used the product of an acrylic curing membrane for sealing the surface of concrete walls and columns.
0086
coating.
SURFACE SEALER
According to the information of the manufacturer, Nufins, it provides a curing membrane that provide a dust free resistance surfaces that ready to accept the application of other subsequent finishes anti-carbonation coating. The contractors should follow the instructions and suggested applications of the manufacturer in order to apply the product correctly and use its full potential.
Company Issue: 1/2018
89
9.9
S ANDING
The following show the treatment after the formwork is taken down. The insitu concrete is sanded in this project to give a fair faced finish to the columns, walls and slabs. Ideally , the project team want the pre-cast concrete staircases follow the fine finishes of the insitu concrete. However, the quality of staircases are not as expected, RAW FINISH
it appears as a raw finish as those on the insitu concrete before sanding. It is not acceptable as the staircases are made of pre-cast concrete, meaning that it is manufactured off site and the manufacturer should have more flexibility in doing a fine finish on them. The quality differences make the aesthetic of elements in the design not unified. Therefore, further sanding are required to modify the finish, leading to an extra task in the programme.
BEFORE SANDING
This demonstrates that finishes can affect the appearance of a building even though they are made of the same material. Therefore, a design is not just stating the material of a certain element of building but also the details of treatment and formation of the material. Otherwise, contractors and manufacturers might have different interpretation and the building is not able to have the expected result as the design. FAIR FACED FINISH (WALL & FLOOR)
FAIR FACED FINISH (COLUMNS)
AFTER SANDING
AFTER SANDING
REAL QUALITY RAW FINISH
EXPECTED QUALITY FINE FINISH
90
9.10
2
EFFLORESCENCE
3
SURFACE DISCOLOURATION
CAUSES
GROUT LOSS
& BLEMISHES
Movement of formwork at those locations that the support system are not rigid enough to resist the hydrostatic pressure of the wet concrete
Early removal of the formwork when the concrete has not fully hardened and occurs in cold, damp conditions
Concrete is poured directly onto the fair face formwork near the top and is allowed to travel down the face to the bottom of the pour or rust stain causing by acid.
SOLUTION EFFECTS
1
S TA I N S
A skin of concrete mortar has hardened over the joints or the concrete is bare and honeycombed between panels
Surface discolouration of white efflorescence and lime stain over the concrete surface
Patches and flow lines appear on the surface in different colour or tone as the normal concrete surface colour.
The formwork should brace and secure the corners to prevent movement
The formwork should be maintained in place until the concrete has achieved 10N (Newton)
Wash with dilute hydrochloric acid or sand down with fine sandpaper
91
9.11
SOLUTION
EFFECTS
CAUSES
1
D E T E R I O R AT I O N
METAL CORROSION
2
ALKALI- SILICA REACTION
3
FREEZE-THAW
Oxygen or water exposure of steel, corrosive chemical environment surrounding reinforcing steel & improper placement or concrete coverage of steel reinforcement
A chemical reaction between the alkali in cement and high-silica content aggregate forms a gel around the aggregate which prevents proper bond between them
Extreme cold weather might freeze the moist in concrete and produces pressure in the capillaries and pores of the concrete. If the pressure exceeds the tensile strength of the concrete, the cavity will dilate and rupture.
When steel corrodes, the resulting rust occupies a greater volume than the steel. This expansion creates tensile stresses in the concrete, which can eventually cause cracking and spalling
In the presence of water, the gel expend and creates tension cracking around surface. Thus, promotes water intrusion which can lead to metal corrosion and spalling
Aggregate can eventually cause significant expansion and cracking, scaling, and crumbling of the concrete
• Using concrete with a low water-to-cement ratio • Adequate concrete cover over steel reinforcement
Select aggregates and silica content carefully in the concrete mix can help preventing the event
• Using high-strength concrete mix designs that incorporate air-entraining admixtures • Specialty coatings and water repellents can also minimize water absorption 92
Roof terrace balustrade guarding as spec ref L30.560
Ea B
C
D
Eb
310
E
Ec
3457
A
Detail E - 300
Roof-Terrace Floor 55.324
13
12
Detail A - 300
Stair 1 Drawing 310
3
Detail G - 300
2750
3400
Metal Stud and Plasterboard partitions as spec ref K10.115 W 02
W 16
X501 COMPUTER SUITE
X502 COMPUTER SUITE
X508 STAIR 1
X509 STAIR 1 LOBBY
Fifth Floor 51.924
15
19 18 17 16
Detail B - 300
15
Detail F - 300
14 13 12
3230
3230
11
2945
10 9 8
X401 COMPUTER SUITE
7
X402 COMPUTER SUITE
X408 STAIR 1
6 5
X409 STAIR 1 LOBBY
4 3 1
15
19 18 17 16
Detail C - 300 13
3230
10
2945
23151
12 11
3230
9
W 13
1
X301 COMPUTER SUITE
W 09
8
X302 COMPUTER SUITE
6
7
X308 STAIR 1
5 4
X309 STAIR 1 LOBBY
3 Third Floor 45.464
Third Floor 45.590
2
DRAWINGS
1
15
20 19 18 17 16 15 14 13
3234
W 05
12
2949
11
3400
M AIN
15 14
10 9 8
This section includes some of the reduced printouts of the main drawings produced by the architect.
X201 LRC
X208 STAIR 1
7 6 5
X209 STAIR 1 LOBBY
4
Second Floor HE Second Floor 42.320 42.230 42.200
3 2
Ground Floor 42.064
1
14
Second Floor CONFETTI 41.820
20 19 18 17
Detail D - 300
16 15 14 13
3300
12
3300
2890
11 10 9 8 7
X101 CAFE First Floor 38.930
X108 STAIR 1
6
Timber stage platform
First Floor HE 39.060
5
X109 STAIR 1 LOBBY
4 3 2
Ground Floor 38.764
1 20 First Floor Confetti 38.360
19 18 17 16
Detail H - 300
Detail K - 300
15 14 12
3300
11 10
2700
3300
13
3300
10
Timber stage platform
2
Fourth Floor 48.694
9 8
X101 RECEPTION
7 6
ED 02
5
X008 STAIR 1
X009 STAIR 1 LOBBY
4
X005 WC LOBBY
3
Ground Floor Ground Floor HE 35.630 35.630
2
16
35.440
Ground Floor 35.464
1
Detail O - 301
Ground Floor Confetti 34.740
Lower Ground Floor 32.800
A
B
C
D
E
Ea
Eb
Ec
GENERAL
7
8
9
10
11
12
13
14
15
16
17
18
19
2806
1736
1736
100 148
420
2740
837
X004 MTG 2 8 m2
ED 03
3
1135
2597.5
MJ
3947.5(17 1/2 bricks)
U/S 2.76
DP
AVCL
SP 2.23
CH 3.36
U/S 2.78
SH 0.19 HH 3.03
1in12
4
5
10
AVCL
AVCL
Wall Construction - Brickwork Outer / RC Wall Inner 102.5 Black Brick as F10/110, 50mm cavity 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Rainscreen Insulation Exposed concrete finish Existing Wall HE Centre 215mm Existing Solid brick wall 25mm cavity depth Metal studs at 600mm centres - K10/165A 12.5mm Plasterboard
Existing Wall Confetti Insulation to be agreed with Structural Engineer Exposed concrete finish
K J II H G
24/08/17 18/08/17 30/05/17 17/08/17 30/05/17 12/05/17
Change to the slab edge following the SE info Amendments to drawings following the Cladding info Change to the 1st floor café/kitchen area Amendments to HEC stair 2 following the SE info Amendments to drawings following the Topo Survey and SE info
MLD MLD MLD MLD MLD MLD
F E D C B A
19/01/17 10/01/17 23/12/16 09/12/16 30/11/16 25/11/16
Change to doors and Stair 1 Lobby Spec Refs added Amendments to drawings Amendments to drawings Amendments to drawings Amendments to drawings
MLD MLD MLD MLD MLD MLD
DESCRIPTION
BY
REV. DATE
Type 1
PARTITION Wall Type 1 2no.layer of 12.5mm Soundblock either side,16mm Resilient Bar fixed to one side, 92mm C studs with 50mm Isover between studs. Skim finish to both sides of partition.
Type 2
PARTITION Wall Type 2 1no. Layer of 15mm Soundbloc either side of 92mm C Studs with 50mm Isover APR between studs. (Use 15mm Soundbloc MR in WC Areas) Skim finish to both sides of partition.
Type 3
Type A
Type 1*
Amendments to substation and meeting room layout Amendments to substation layout Amendments to substation layout Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1
MLD MLD MLD MLD
1.50 in A1 201R
PARTITION Wall Type 1 - without16mm Resilient Bar
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
F
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group PROJECT
Confetti CQ Campus 60 minutes fire resistance Wall
17
Plasterboard on dabs to achieve min 60 minutes fire rating Existing wall
Movement joint
PARTITION Wall Type 3 1no. Layer of 15mm Soundbloc MR either side of 70mm C Studs with 50mm Isover APR between studs. Skim finish to both sides of partition. PARTITION Wall Type A 3no. Layers 15mm Soundbloc either side of BG 146mm C Stud at 300mm Centres within 148mm Head and base channels. 75mm Isover APR between studs with Skim finish to both side of partition.
T
H
14 13 12 11 10 9 8
503.5
497
3a
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns Wall Construction - Blockwork Outer / SFS Inner 100mm fairfaced medium density blockwork - F10/225 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns
DH 2.05
HH 2.05 SH 0.87 DH 2.05
04/01/18 19/12/17 08/11/17 18/09/17
Architects, Landscape & Interior Design
4959
G
HH 2.05 SH 0.87
190
O N M L
1 6-20 Bath Street, Nottingham NG1 1 DF
6128
F
UP
PROPOSED GROUND FLOOR GA PLAN -1:50 Key Walls
7718
E Ground Floor 35.440
X017 PLANT ROOM 30 m2
32.78
N
U/S 3.14
1492
D
Ee
ED 04
MLD
eq.
1646
C
29/01/18 Amendments to internal doors ID008 MLD 16/01/18 MJ, CFB, Bricks setting out and downpipe position added MLD Amendments to internal wall partitions,dimensions updated
GROUND FLOOR PLAN
H003
3562
Col
llery H002 Ga CH 2.99
223 3 SCH 2.8
B
G
Ground Floor 35.630
FFL 35.44
2279
C 222
CH 2.99
ID 019
CH 2.76
35.47
X010 STAIR 2
Lift
14/02/18 Amendments to internal partitions
Q P
17
1800
X011 STAIR 2 LOBBY
Ground Floor 35.048
3751
2
3491
3
SH 0.88 HH 2.97
4
R
SH 0.88 HH 2.97
5
DH 2.04
6
SH 0.86 HH 2.03
7
U/S 2.27
8
DH 2.05
FFL 35.63
9
1
A
AVCL
215
eq.
THL 35.64
point Insertion
STN/142 35.51
Ground Floor 35.630 10
ID 018
3
1700 1184
35.048
X020 MTG 3 9 m2
5 U/S 2.37
ED 14
Ground Floor 34.740
Ground Floor 35.630
ID 017
314
X014 SERVER 16Ground m2 Floor
Ground Floor 35.048
20
1010
3a ID 010
NEW IS 004 3532
Type 1*
X002 MTG 1 9 m2
1184
3471 2778
ID 021
1532
535
6
535
763 5
ID 015
768
4
148
Type 2
ID 012
2000
2617
800 1135 1095 400 800
221
3
X012 clnrs cpbd 3 m2
IS 003
148
32.86
4
2
X018 Staff Corridoor
X018 NEW STORE (86m2)
Type 1*
221 B
2950
ID 016
2000
IS 002
Ground Floor 35.048
ID 009
Ground Floor 35.630
1736
2810
Mechanical riser
Type 1*
3248
35.61
1092
Type 1*
ID 011
X015 COMMS 13 m2
140
Ec
11857
2000
324
224
1496
1110
252
4642
1696
1000 1200
10932
400
Ea
1215
1010
338
Bl
ID 022
3574
Ed
Ground Floor 35.630
1225
422
1
X003 OFFICE 26 m2
Eb
312
B
1010
3070
925
640 800
220
600
3650
A 3554
600
Indicative location of reception desk by others
1500
ID 014
ID 013 1736
HH 2.98 SH 1.1 5
W 01
34.63
314
3a
e
Type 1*
1100MM HIGH
ir Storag Under Sta
Electrical riser
1in10
3306
400
1178
X019 Mtg cpbd
450
1930
Secure line
5789 LOWWALL
1in15
Ground Floor 35.630
CH 2.84
2552
36.60
2
DH 2.03
IS 001
DH 1.97
2a
- 3steps
1in12
1184 ID 008
1343
400
1854
400
ID 007
34.828
3545
Ground Floor 35.048
1in12
3390
Type 1*
UP 82
1656 138
1828
4596
1500
34.910
- 3steps
UP
1010
5000
Ground Floor 35.464
CH 3.68
1202
2500
34.71
1
220 A
2
CH 3.39
3
34.910
34.68
4
Ground Floor 35.630
1010
234
1110
496 400
.48
311
Type 1*
et MMC cabin
In Abeyance
820
1408 ID 006
3546
ID 003 ID 002
U/S 3.1 4
17
Floor
35.464
100
ID 005 499
walls 500 300
ID 001
Ground Floor 35.464
X009 STAIR 1 LOBBY Type 1*
8 STN/12 36.04
X001 RECEPTION 130 m2
X005 WC LOBBY
1979
410
5
3700
- 3steps
CH 2.37
6
1010
Ground Floor 35.048
34.74
4742
7
ID 004
15 m2
Type 1*
.50
X008 STAIR 1
2 17 mGround
FFL
8
Ground Floor 35.464
34.69
X006 WC CHANGING (MALE WC)
10 9
X007 WC CHANGING (FEMALE WC)
.76 1600 34
W 01
DH 2.1 0
Type 1*
34.910
ork 140 Blockw
3200
Type 3
1a
310
10
DH 2.05
13
12
X016 SUBSTATION 20 m2
X013 CONTROL ROOM 8 m2
5038
Ground Floor 35.464
34.66
W 03
1000
11
34.69
MJ
50
ED 02
34.61
9215
Step +0.04
ED 12
3546
ED 01
3
300 bricks)
0 to Fit approx. 250
552
1810
4
W 02
bricks)
300
1000
923
1
1/2 6413 (28
34.74
2000
E 15740(71
34.70
1000
2951
F
03 5 123 10 579 19
1000
1200
400
800
600
3160
A - 306
34.82
10534 1000
35.20
Ground Floor 35.300
Plan Detail
Ground Floor 35.600
4452
bricks) 9215(41
4550
34.90
Ea
See drawing 2588-306 for recessed downpipe details
D 301
Eb
Ee
6752
Ed
421
Ec
35.10
E
35.09
35.71
35.70
35.60
35.46
D
35.20
1492
35.24
C
35.32
1646
e ng out Lin Bricks Setti
330
422
35.00
G 223
3562
C 222
.12
35.46
35.63
35.80 B
2279
35.28
35.86
35.91 A
ARRANGEMENT DRAWINGS
2176
10.1
Bricks Setting out Line
ID 001, etc W001, etc ED01, etc IS01, etc
- Internal Door Codes (Refer to drawing 320) - Window Codes (Refer to drawings 322-323) - External Door Codes (Refer to drawings 323) - Internal Screene Codes (Refer to drawings 321)
DRAWING
Ground Floor GA Wall Types and Setting Out PROJECT NUMBER
SCALE
DATE
2588
1:50 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
201
R
Construction MLD
This drawing is copyright and remains the property ofAllan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
94
Final setting out of Roof-Terrace to be confirmed : Top of Coping 58.922
Roof terrace balustrade guarding as spec ref L30.560
A
B
3562
C
1646
D
1492
310
Ea
E
Eb
4550
1
5- Balustrade System to be confirmed by client 2951 Ec Ed
4452
3599
2279
443.5
2- Terrace Roof System build-up + Thermal performance, Roof Falls, Drainage to be confirmed following details from Roof subcontractor
497
3
Detail A - 300 Top of Coping 55.775
Detail E - 300
13
SSL 55.024
JT3 .5x35 35 JT3 .5x35 35
Top of Coping Top of Masonry 55.547 55.462
Roof-Terrace Floor 55.324
12
GENERAL NOTES
GENERAL NOTES
External Walls Wall Construction - Corten Outer / SFS Inner 30mm Deep Corten Cassettes 69mm Air Gap with Vertical Rails on HH Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm 6752 SFS Zone, Filled with RW45 Insulation Ee 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns U-Value = 0.18W/m2K
Semi−intensive Green Roof Covering System construction -350mm concrete deck to Structural Engineer's details -3mm vapour control layer - 50 mm thick upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -1.60 tapered insulation zone to form the fall -1.5mm fully-adhered single ply membrane as S45.110A -roof barrier/protection layer(s) -drainage layer, filtration layer, substrate to depth required -80mm semi-intensive green roof covering as Q37.120A U-Value <0.15W/m2K.
Wall Construction - Brickwork Outer / SFS Inner 102.5 Black Brick as F10/110 50mm Air Gap with Brick Ties and Support Brackets 150mm Rockwool DuoSlab Insulation 12.5 KnaufWindliner Sheathing Board 150mm SFS Zone, Filled with RW45 Insulation 12.5mm Plywood and 12.5mm GB Plasterboard and skim + exposed concrete columns U-Value = 0.18W/m2K
12
Terrace Roof System construction -350mm to 6th floor and 275mm to 5th floorconcrete deck to Structural Engineer's details -3mm vapour control layer -tapered zone for pedestal to allow falls from one side to the other of 1.60 tapered insulation zone to form the fall ( within the pedestal zone) - 50 mm thick upstand to be used around the perimeter of the roof on the internal façade of parapets A minimum distance of 300 mm should be maintained between the top of the insulation upstand and the bottom of the horizontal roof insulation. -1.5mm fully adhered single-ply membrane as S42.110A -50mm Ballast (paving slabs on support) as Q37.140 U-Value <0.15W/m2K.
13
MJ (1 9.200) 54.647
External Curtain Walls Various Systems - refer to windows schedule Drawings CFB 322-324 U-Value = 0.15W/m2K G-value of glass = 0.35
Stair 1 Drawing 310
Type 2
3
Top of Coping Top of Masonry 53.447 53.362
Type A
2750
3400
Type 2
X501 COMPUTER SUITE
Detail B - 300
Detail I - 300
Detail G - 300
X502 COMPUTER SUITE
X508 STAIR 1
Fifth Floor 51 .924
X509 STAIR 1 LOBBY
X504 FIFTH FLOOR TERRACE
19
15
SSL 51 .624
MJ (1 6.200) 51 .647
13
18 17 16 51 .074
15
Type 2
14
CFB
Type 2 Detail F - 300
13
50.394
2945
10 9 8
Type 1
4
X402 COMPUTER SUITE
X408 STAIR 1
6 5
49.374 4
Detail C - 300
X409 STAIR 1 LOBBY
3
X404 SEMINAR ROOM
Existing Confetti Building
2 1
15
MJ (1 3.275) 48.722
48.694 19 18
Proposed masonryCFB to be built off existing gable - cut bricks to be removed to start new wall New step + cover Flashing to abutment to color match brick as H27 - 440
17 16 47.844
15
Type 2
Type 2
Type 1
13
Type A
12 11
3230
47.1 64
3230
10
2945
23293
14
9 8
4
7
1
X301 COMPUTER SUITE
6
X302 COMPUTER SUITE
5
X308 STAIR 1
46.1 44 4
X309 STAIR 1 LOBBY
3 Third Floor 45.590
1
Detail J - 300
X304 SEMINAR ROOM Timber stage platform
2 45.464
15
20
MJ (9.750) 45.1 97
19 18 17 16 44.444
Wall Construction - Brickwork Outer / RC Wall Inner -102.5 Black Brick as F10/110, 50mm cavity -50mm Air Gap with Brick Ties and Support Brackets -150mm Rockwool DuoSlab Rainscreen Insulation -100mm SFS Zone, Filled with RW45 Insulation -200mm thick concrete wall to Structural Engineer's details Exposed concrete finish U-Value = 0.18W/m2K
19200(256 bricks)
Fourth Floor 48.694
Ground Floor Construction Solid Concrete Ground Based Floors - Vinyl floor finish as floor finishes drawings 401-402 -75mm screed as spec ref M10.130 - Underfloor Heating Systems refer to M+E Engineer's details -0.5mm separation layer lapped (minimum 150mm) -50mm perimeter Insulation overlap min.150mm from bottom of wall insulation to top of insulation upstand -130mm Kingspan Kooltherm K103 Floor Board insulation under concrete slab as spec ref M10.290A -0.9mm damp proof membrane -275mm thick concrete slab to Structural Engineer's details -well compacted sub base to Structural Engineer's details U-Value = 0.11W/m2K
16
7
X401 COMPUTER SUITE
Floors Construction (1st, 3rd, 4th, 5th) -275mm concrete deck to Structural Engineer's details -10mm latex levelling screed - Vinyl floor finish as floor finishes drawings 401-402
11
3230
3230
Type A
15
Detail L - 300
12
Third Floor 45.464
Second Floor Construction (LRC) -275mm concrete deck to Structural Engineer's details -3mm vapour control layer -50 mm Kooltherm as spec ref M10.290B -75mm screed as spec ref M10.130 - Vinyl floor finish as floor finishes drawings 401-402
14
51 .924
Type 2
15
Type 2
CFB
Type 1
14
Type 1 Type A
16200(216 bricks)
11
3400
2949
3234
12 43.764 10 9 8
X208 STAIR 1
6 5
42.744
X209 STAIR 1 LOBBY
4
Detail D - 300
X204 SEMINAR ROOM 13275(177 bricks)
7
X201 LRC
3
Second Floor HE Second Floor 42.320 42.230 42.200
2 1
14
Second Floor CONFETTI 41 .820
42.064
42.064
MJ (6.525 41 .972
41 .964
20 19 18 16 41 .074
Ground Floor 41 .820
Type 2
15
Type 2
14
8 7
Detail H - 300
Detail K - 300
X108 STAIR 1
6
Timber stage platform
5
39.424
X109 STAIR 1 LOBBY
4
X104 SEMINAR ROOM
12/05/17 Amendments to drawings following the Topo Survey and SE info 23/01/17 Stair 1 amended 10/01/17 Spec Refs added 23/12/16 Amendments to drawings
MLD
REV. DATE
1.50 in A1 220I
MLD
MLD MLD MLD
DESCRIPTION
BY
3 2 1
38.764
38.764 20
38.568
19
First Floor Confetti 38.360
MJ (2.997) 38.297
18 17 16 37.774
Type 2
15
14
Type 2
6525(87 bricks)
First Floor HE 39.060
9750(130 bricks)
9
X101 CAFE First Floor 38.930
11
3300
2897
3300
40.41 4
MLD MLD MLD MLD
C B A
13
10
28/02/18 Change to RoofTerrace Structure, internal partitions, external wall build-up 22/01/18 MJ, CFB, Bricks setting out and downpipe position added 10/11/17 Change to RoofTerrace external wall and roof build-up 25/10/17 Change to the slab edge following the Cladding & Windows info. Amendments to Stair 1 30/05/17 Drawing status updated to construction
D
Type 1
12
I H G F E
CFB
17
Refer to GA Floor Plan drawings (2588 201-207)
Type 2
13
SECTION AA
Ground Floor 38.360
Architects, Landscape & Interior Design
Type 2
1 6-20 Bath Street, Nottingham NG1 1 DF
11
3300
37.1 1 4 10
2700
2850(38 bricks)
12
3300
3300
13
9 8 7
X101 RECEPTION
Detail O - 301
X008 STAIR 1
6 5
36.1 24
X009 STAIR 1 LOBBY
4
X005 WC LOBBY
X007 WC CHANGING (FEMALE WC)
X013 CONTROL ROOM
T
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
F
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group
3
Ground Floor Ground Floor HE 35.630 35.630
2
16
35.440
1
Ground Floor 35.464
35.464
Level (0.00) 35.447
PROJECT
Confetti CQ Campus
Ground Floor 35.048
SSL 34.985
Ground Floor 34.770
Ground Floor Confetti 34.740
DRAWING
GA Section AA
Lower Ground Floor 32.800
2279
A
3562
B
1646
C
1492
D
4550
E
Ea
4452
Eb
2951
Ec
6752
Ed
Ed
PROJECT NUMBER
SCALE
DATE
2588
1:50 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
220
I
Construction MLD
This drawing is copyright and remains the property ofAllan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
95
6752
Ee
2951
Ed
300 F
5738(25 1/2 bricks)
Top of Coping 58.922
Ec MJ
300 E
4452
2587(11 1/2 bricks)
Top of Coping Top of Masonry 58.622 58.537
Top of Masonry 58.837
Top of Masonry 55.462
Roof-Terrace Floor 55.324
Top of Coping 55.547
CFB
SSL 55 .024
X102 KITCHEN 19m GRAB AND GO
MJ (1 9.200) 54.647 X112 clnrs cpbd
3400
CFB Top of Masonry 53.362
Top of Coping 53.447
W 20
MJ
MJ W 02
1523 MJ (1 6.200) 51 .647
3230
CFB
W 18
W 14
MJ (1 3.275) 48.722
Fourth Floor 48.694
Second Floor HE Second Floor 42.320 42.230 42.200
41.70
41.70
MJ (9.750) 45 .1 97
CFB
(216 bricks)16200
45.31
(256 bricks)19200
Third Floor 45.590
3234
Third Floor 45.464
Advertisement Hoarding
Second Floor CONFETTI 41 .820
MJ (6.525 41 .972
3300
(130 bricks)9750
CFB
40.49
First Floor 38.930
First Floor HE 39.060
(87 bricks)6525
Advertisement Hoarding
MJ (2.997) 38.297
m o (38 bricks)2850
3300
First Floor Confetti 38.360
Ground Floor Ground Floor HE 35.630 35.630
Ground Floor Confetti 34.740
34.68
34.33
34.16 ED 1 0 Lower Ground Floor 32.800
220
WEST ELEVATION ALONG CONVENT STREET - 1:100
221
A
2
Top of Masonry 58.837
Top of Masonry 59.662
B
3649
1
Top of Coping 58.922
3554
2950
3
Top of Coping 59.747
4
Top of Coping 58.922
D
C
222 C B
A
Top of Coping 55.775
e
W 09
W 13
W 05
W 01
ELEVATION 1
ED 01
ED 02
35.464 35.287
35.78
MJ
34.95
6752
ED 1 2
Ed
ED 1 3
33.85
E
W 03
Level (0.00) 35.447
35.440
m W 06
(177 bricks)13275
46.80
Roof detail not fully Visible from ground level
3230
23293
CFB
46.74
301 D
Top of Coping 59.747
W 16
Fifth Floor 51 .924
49.84
t n
Top of Masonry 59.662
9215(41 bricks)
X114 NEWRAISED COURTYARD
X103 CAFE SERVERY 80 m
223 G Ea
6740(30 bricks)
ED 09
6525(29 bricks)
X101 CAFE 150 m
void
4550
Eb Top of Coping 58.922
ED 07
3599
X104 SEMINAR ROOM 30 m
MJ
2951
4452
Ed
Ec
330
4550
Eb
Ea
E
D
C
A
B
223 G
222 C
Setting out Line
3599
In Abeyance
W 21 Top of Coping 55 .775
C
Roof-Terrace Floor 55.324 SSL 55.024
2388
X104 SEMINAR ROOM 30 m
3400
X101 CAFE 150 m
X102 KITCHEN 19m GRAB AND GO
Fifth Floor 51 .924
51.00
3230
W 15
3300
Second Floor CONFETTI 41 .820
First Floor 38.930
First Floor HE 39.060
o
I
09/11/17 Amendments to Roof construction and window W06 position
MLD
H G
06/11/17 Incorporating Brickworks setting out 20/10/17 Change to window dimensions following Cladding and SE info
MLD MLD
F E D
11/10/17 Incorporating cladding subcontractors setting out 30/05/17 Drawing status updated to construction 12/05/17 Amendments to drawings following the Topo Survey and SE info 19/01/17 Doors amended 23/12/16 Amendments to drawings 09/12/16 Amendments to drawings
TE MLD MLD
Oversailing lintel
MJ (1 6.200) 51 .647
51.00
CFB
Shelf angle
W 12
C B A
REV. DATE
MLD MLD MLD
DESCRIPTION
BY
MJ (1 3.275) 48.722
CFB
47.89
46.08
MJ (9.750) 45.1 97
CFB
W 01
MJ (6.525 41 .972
Architects, Landscape & Interior Design 1 6-20 Bath Street, Nottingham NG1 1 DF T
01 1 5 841 841 8
E
design@allanjoycearchitects .co.uk
F
01 1 5 950 71 61
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group
CFB
W 05
W 04
First Floor Confetti 38.360
MJ (2.997) 38.297
PROJECT
Confetti CQ Campus Elevations Sheet - 1
2850(38 bricks)
3300
DRAWING W 01
Ground Floor Ground Floor HE 35.630 35.630
Level (0.00) 35 .447
35.440
35.79
35.78 35.50
Ground Floor Confetti 34.740
Lower Ground Floor 32.800
Vertical and horizontal cladding joint as elevations and section H43 cladding specification
16200(216 bricks)
N Second Floor HE Second Floor 42.320 42.230 42.200
CFB
9750(130 bricks)
23293 Third Floor 45.590
3234
Third Floor 45.464
3230
Fourth Floor 48.694
12/01/18 MJ, CFB, Bricks setting out and downpipe position added MLD 05/12/17 Amendments to windows W 05- W06- W11MLD W14-W19-W17
19200(256 bricks)
X112 clnrs cpbd
Setting out Line
K J
MJ (1 9.200) 54.647
13275(177 bricks)
void
Cavity Fire Barrier 60 minute fire protection
6525(87 bricks)
X114 NEWRAISED COURTYARD
X103 CAFE SERVERY 80 m
Movement joint
1.50 in A1 230K
ED 1 4
35.11 34.68
3649
1
3554
220 A
2
2950
3
221 4 B
PROJECT NUMBER
SCALE
DATE
2588
1:100 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
230
K
Construction MLD
This drawing is copyright and remains the property ofAllan Joyce Architects Ltd
SOUTH ELEVATION ALONG LOWER PARLAMENT STREET -1:100
Generally do not scale drawings. All dimensions to be checked on site.
96
10.2
D E TA I L
DRAWINGS 30
1
100mm Benchmark Quadcore Karrier Vertically laid or similar fixed with a minimum of 2 Nr fasteners per panel per rail U-Value = 0.18W/m2K
W 13
35mm Benchmark Metallic Recessed Fix Cassette or similar
100 mm Infill SFS fixed to the structure
FFL = 45.464
FFL = 45.464
Aluminium Fixing Plate
W 05
30
275mm concrete deck to Structural Engineer's details
FACADE SECTION CORTEN CLADDING DETAIL
Curtain Walling System Frameless Window insert to Curtain Walling System
1.20 in A1 301
Mullion fixing to Curtain walling System
Waterproof membrane
FFL = 42.230
Cavity barriers and smoke stop for Curtain Walling to suit site. Bracket Structural Fixing to Structural Engineers Details
30
FFL = 42.930
Acoustic Insulation
REV. DATE
Perforated Cor-Ten Cassette Screen setback 25mm from adjacent Corten cladding panels
DESCRIPTION
BY
Architects, Landscape & Interior Design 16-20 Bath Street, Nottingham NG1 1DF T
0115 841 8418
E
design@allanjoycearchitects .co.uk
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group
Window pod PIR board and fire rated canister applied insulation
PROJECT
Outer sill flashing with interface to recessed fix cassette
Confetti CQ Campus
FFL = 38.930 30
FFL = 38.930
Corten gutter system with interface to recessed fix cassette
DRAWING
Facade Section Corten Cladding Detail PROJECT NUMBER
SCALE
2588
1:20 @ A1
Jul-16
DRAWING NUMBER
REVISION
STATUS
BY
Preliminary
MLD
301 Facade Elevation
1
Facade Section Detail 1 - 1
DATE
This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
97
70 8
70 x 8mm PPC MS Flat Bar neatly welded at joints
General Notes
- All dimensions to be confirmed on site prior to commencing any fabrication. - Top of all handrails to be 1100mm min. above pitch line of stairs and above finished landing level. - All handrails to be nominal 40mm satin stainless steel. - Wall handrails to be supported on stand off wall brackets; continuos around half landings; extend 300mm past top and bottom of flight and be returned to wall. -Exposed fasteners shall be of same materials, color and finish as material to which applied. -Exposed surfaces throughout project shall have same inherent texture and color for similar locations.
40mm diameter satin finish SS circular handrail mechanically fixed from below to PPC MS Angle support
1300
40
8 x 8mm PPC MS Angle Support factory welded to vertical balusters minimum one either end and then equally spaced between at max 1.2m centres
Maintain consistent gap between each section of the balustrade system. 50mm Refer to drawing 314 for location
1000
6mm Treads fixed with countersunk fixings to stringer Vinyl flooring to treads with contrasting nosings as spec L30.250B to treads and risers
01
Treads and landings from 6mm folded plate to SE details
8
70x8mm PPC MS balusters welded to top and bottom rails with 150, 100 or 50mm spacings in random arrangement. Layout shown to provide design intent.
*
8
250 x 10mm stringer to SE details
Detail Section 03 ( 1.20 )
Balustrade system fixed through PPC MS flat welded between balusters and fixed with countersunk fixings to stringer and with spacers behind to provide offset gap of 5mm. Spacing to align with handrail fixings above.
Detail Section 01 ( 1.10 )
BALUSTRADE DETAILS
70 x 6mm SS Flat Bar notched and welded at join with newels
01
Detail Section 02 ( 1.10 ) REV. DATE
*
DESCRIPTION
BY
1.10 in A2 319
Architects, Landscape & Interior Design 16-20 Bath Street, Nottingham NG1 1DF T
0115 841 8418
E
design@allanjoycearchitects .co.uk
F
0115 950 7161
W
www.allanjoycearchitects .co.uk
CLIENT
Confetti Media Group PROJECT
Confetti CQ Campus DRAWING
Balustrade details (Stair 2 HEC) PROJECT NUMBER
SCALE
2588
1:10@ A2
DRAWING NUMBER
REVISION
319 3D View
DATE
Jun-17
STATUS
BY
Preliminary
MLD
3D View This drawing is copyright and remains the property of Allan Joyce Architects Ltd Generally do not scale drawings. All dimensions to be checked on site.
98
RC DETAILS WALL 1.50 in A1/ 1.100 in A3 By structure engineer: Price & Myers
99
This drawing is the property of Verteks Associates Ltd and is issued on the condition it is not reproduced, retained or disclosed to any unauthorised person, either wholly or in part without the written consent of Verteks Associates Ltd .
G.1075
A.1075
C.1075
K3.1075
K3.1075
D.1075
A.1075
B.1075
B.1075
B.1075
A.1075
B.1075
C.1075
C.1075
D.1075
A.1075
B.1075
A.1075
K2.1075
K2.1075
B.1075
A.1075
B.1075
B.1075
B.1075
A.1075
B.1075
A.1075
C.1075
B.1075
B.1075
A.1075
C.1075
C.1075
D.1075
D.1075
A.1075
B.1075
B.1075
K1.1075
K1.1075
B.1075
FFL Roof 55 390
IF IN DOUBT ASK DO NOT SCALE THIS DRAWING
Note : Top of parapet to be advised when roof build up has been determined
01 4005
A.1075
Drawing Number top of windpost 57 190
This drawing should be read in conjunction with all relevant design drawings, calculations and system manufacturers instructions. All dimensions are to be checked by the contractor and any errors or omissions reported prior to commencement of any fabrication and/or installation. Any discrepancies are to be notified immediately.
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
1095
290
1095
1095
300
1095
1095
1095
180
180
44mm MAX
600
600
600
300
1200
1200
900
900
300
600
600
900
300
600
300 300
600
600
600
300
600
620
305
300
600
300
1200
900
900
600
300
600
600
600
300
1200
300
905
900
300
500 180
600
2750 G.2730
2750 A.2730
Notes :
300
500
900
Dims on panels are to modules.
5th SSL 51 914
180
180
600
500
180
A.3210
3230
44mm MAX
G.3210
300 300
Denotes fixing reference. Read in conjunction with fixing schedule
180
3230
2750 A.2730
900
Note : Frame width of corner glazing is subject to reveal depth tbc by glazing contractor
3230
3230
600
W12
W12
B.3210
3230
300
A.3210
B.2730
2750
2750 B.2730
2750 B.2730
600
3230
600
A.3210
300
600
C.3210
530
300 305
2750
2750
A.2730
3230 A.3210
B.2730
K2.2730 3230 K2.3210
600
3230
2750
K2.2730
600
3230
300
K2.3210
600
300
B.3210
2750 B.2730
300
600
3230 B.3210
900
530
A.3210
2750
A.2730
2750 B.2730 B.3210
3230
2750 B.2730 3230 A.3210
3230
3230
2750 B.2730
2750
2750 A.2730
300
305
W15
4th SSL 48 684
180
300
650 A.630
900
600
B.3210
300
300
A.3210
650 A.630 650 C.630
600
300
600
650 C.630
600
3230
2750 A.2730
300
600
C.3210
600
600
650 B.630
600
300
2750
2750
B.2730
B.3210
600
3230
A.2730
A.3210
600
A.3210
B.3210
600
650 A.630
B.3210
3230
C.2730
300 300
3230
600
3230
2750
300
3230
900
3230
600
B.3210
3230
B.2730
2750
2750
2750
B.2730
A.2730
2750 A.2730
600
B.3210
590
300
300
3230
B.2730
2750
2750 B.2730
2750 K1.2730
300
650 A.630 650 B.630
600
600
B.3210
4th SSL 48 684
600
3230
B.3210
FFL Fourth 48 694
290
K1.3210
600
3230
2750 K1.2730
A.2730 300
3230
5th SSL 51 914
3230
FFL Fifth 51 924
K1.3210
2750
A01
W16
Associated Drawings : 4000 - system detail
44mm MAX
180
300
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
W13
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
3520
180
W09
GA CORTEN CLADDING
180
1200
600
905
600
G.3500
A.3500
290
B.270
300
K3.270
600
290
600
K3.270
600
290
A.3500
300
D.270
B.3500
600
290
B.3500
900
B.3500
600
A.3500
390
300
3rd SSL 45 454
500
180
44mm MAX
Note : Frame width of corner glazing is subject to reveal depth tbc by glazing contractor
600
800
J.3090
B.3090
600
305
3110
3110
3110
3110
600
K3.3090
600
K3.3090
3110
3110
300
B.3090
900
B.3090
300
A.3090
600
3110
3110 C.3090
3110 A.3090
3110 900
555
900
B.3090
600
Issued for approval P5 further omments incorporated pw 05.10.17 P4
ISSUED FOR APPROVAL Comments incorporated
P3
ISSUED FOR APPROVAL Hidden Elevations added
pw 28.09.17
P2
ISSUED FOR APPROVAL new modules 300 600 900
pw 14.09.17
P1
ISSUED FOR APPROVAL First Issue
pw 07.09.17
180
2nd SSL 42 065
180
H.535
300
390
C.3090
3110 B.3090
600
3110
3110
3110
390
555 F.535 555 C.535
600
A.3090
F.3090
B.3090
03 4002
3110
180
3110
01 4002
300
C.3500
600
B.3500
600
B.3500
900
B.3500
300
B.3500
530
305
C.3500
600
A.3500
300
K2.3500
600
K2.3500
B.3500
300
B.3090
600
900
A.3500
1065 B.1045 600
B.3500
B.3500 600
1065 A.1045
A.3500 300
C.1045
B.3500 600
1065
A.3500
C.3500
B.3500
600
300
A.3090
300 300
B.3090
B.3090
900
A.3090
600
A.3090
C.3090
B.3090
300 300
900
3110
B.3500
600
3110
B.3500
600
3110
600
3110
600
3110
B.3500
300
3110
A.3500
C.3500 3110 900
A.3090
1065
600
1065 A.1045
600
C.1045
3110 590
300
1065 B.1045
600
1065 B.1045
K1.3090
2nd SSL 42 065
900
K1.3090
3110
B.3090
FFL Second 42 230
590
300
3110
600
3110
K1.3500
B.3500
3rd SSL 45 454
K1.3500
Module
FFL Third 45 464
44mm MAX
180
525
Description
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
W04
3135
3135
W05
02 W05 4002
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
3135
Revision
pw 03.10.17
Revised By
Date
180
600
300
900
600
300
300
900
390
900
525
375 300
600
C.3115
A.3115
B.3115
B.3115
A.3115
H.745
765
765 F.745 765 C.745
C.3115
A.3115
A.3115
B.3115
C.3115
600
600
300
900
G.3115
600
B.3115
A.3115
B.3115
B.3115
A.3115 300
B.3115
600
B.3115
300
K3.3115
600
B.3115
A.3115
900
B.3115
290
K3.3115
600
B.3115
300
C.3115
1st SSL 38 920
K1.3115
A.3115
FFL First 38 930
K1.3115
Module
600
305
300
600
600
500
1st SSL 38 920
180
900
600
300
305
600
600
180
500
180
114°
300
FFL First 38 930
540 G.520
600
540 B.520
900
540 B.520
375
K3.520 540
525
K3.520
900
540
390
540 B.520
900
540 A.520 540 C.520
300 300
540 B.520
1200
540 E.520 540 C.520
600
H.520
300
540
530
540 F.520 540 C.520
605
540 A.520 540 A.520 540 C.520
600
540 D.520
600
540 A.520 540 B.520
600
540 K2.520
300
K2.520
900
540
600
540 B.520
600
540 B.520
300
540 A.520 540 B.520
900
540 C.520
300
B.520
600
540
900
B.520
600
540 A.520 540
300
540 A.520 540 C.520
600
540 B.520
600
540 C.520
300
B.520
600
540 A.520 540
300
540 B.520
600
540 A.520 540 B.520
900
B.520 540 A.520 540 B.520
290
600
540
K1.520
540 A.520 540 300
540 K1.520 540 C.520
Module 38 930
Module 38 390
1.100 in A3 By manufacturer: Horbury Building System
114°
315
Module 38 390
320
Underside Soffit and Gutter 38 234
Return elevation to masonry
01 1000
A
01 4004
Convent St Elevation - West
1:100 01
4006
4007
Lower Parlament St Elevation - South
03 1000
1:100
16 6
500
1650
180
180
180
300
93
° 600
180
180 180
600
Confetti Campus Nottingham
Package
Rainscreen Cladding Title
GA Corten Cladding
600
300
900
180
900
180
375
180
525
180
900
180
390
180
600 300
9915 overall Corten
01 4008
Cad File Name
1428
2
3
Approved
Scale
06.09.17
1
Drawn By
Checked
PW
Date
A
B
C
D
E
Ea Dims to skewed grid noted at intersection with face of Corten
900
180
12892 overall Corten
300 300
180
1200
180
600
180
300
180
525
180
605
180
600
180
600
180
600
180
300
180
900
180
600
180
600
180
300
180
900
180
300
180
600
180
900
180
600
180
300
180
600
180
600
180
300
180
600
180
300
180
600
180
900
180
180
290
300
400
180
95°
180
900
Return elevation to masonry
A
600
Section through Corten above Gutter at First Floor
Tel: 01709 515 044 ● Fax: 01709 515 066
Project
1990
180
SOUTH GROVE HOUSE ● SOUTH GROVE ● ROTHERHAM ● S60 2AF
typ 1:100 section
Return elevation to glazing
6
01
02 1000
HORBURY BUILDING SYSTEMS LTD
Drawing Number
1:100
1428-1000
Paper Size
A3 P5 Revision
100
Drawing Number
1428-4000
IF IN DOUBT ASK DO NOT SCALE THIS DRAWING
150mm Rainscreen Duo Slab
This drawing is the property of Verteks Associates Ltd and is issued on the condition it is not reproduced, retained or disclosed to any unauthorised person, either wholly or in part without the written consent of Verteks Associates Ltd .
150mm SFS with 150mm RWA45 Insulation in cavity
Module
This drawing should be read in conjunction with all relevant design drawings, calculations and system manufacturers instructions. All dimensions are to be checked by the contractor and any errors or omissions reported prior to commencement of any fabrication and/or installation. Any discrepancies are to be notified immediately.
20
A01
Denotes fixing reference. Read in conjunction with fixing schedule
Module
Notes :
Associated Drawings : Horizontal Rail 60x40x2mm TBC
180 180
Bracket VB/180 with Adaptor FOR ZONES 200-235mm Breather Membrane (to be confirmed) 12.5mm Thick CP Board: Knauf Windliner with taped joints Corten Cladding Panel
CORTEN CLADDING TYPICAL DETAILS
Vapour Control Layer
60
25
12.5
150mm Rainscreen Duo Slab
3
Internal Finishes:25mm Timber baton, 12.5mm Plywood,12.5mm BG Plasterboard with skim finish 12.5
150mm SFS with 150mm RWA45 Insulation in cavity
30
220
218.5 468.5
150
218.5
1
01 4000
Vertical Section
1:5
C1
Construction issue no comments
pw 05.10.17
P3
ISSUED FOR APPROVAL Horizontal Rail
pw 28.09.17
P2
ISSUED FOR APPROVAL insulation note corrected
pw 20.09.17
P1
ISSUED FOR APPROVAL First Issue
pw 29.08.17
Description
Revised By
Date
150
1
468.5
12.5
Revision
1.5 in A3 By manufacturer: Horbury Building System
69
250
180
180
HORBURY BUILDING SYSTEMS LTD
Bracket Adaptors do not generally penetrate insulation zone
SOUTH GROVE HOUSE ● SOUTH GROVE ● ROTHERHAM ● S60 2AF Tel: 01709 515 044 ● Fax: 01709 515 066
Project
30
Confetti Campus Nottingham
Package
20
PVC Isolation tape between dissimilar metals
Rainscreen Cladding Horizontal Rail 60x40x2mm TBC Title
Module
Module
Angle Adaptor in Sliding point configuration
02 4000
Plan Section
System Details Corten Cladding Typical Detail
Module
1:5
Angle Adaptor in Fixed point configuration ( 1No this type per horizontal rail)
Cad File Name
1428
Drawn By
Approved
PW
Date
Scale
29.08.17
Drawing Number
Checked
SR 1:5
1428-4000
Paper Size
A3 C1 Revision
101
S ERVICES
10.3
DRAWING
THIS IS A CAD DRAWING - DO NOT HAND MODIFY - DO NOT SCALE - PHOTOCOPYING MAY DISTORT. COPYRIGHT IN THIS DRAWING IS THE PROPERTY OF MIES BUILDING SERVICES. IT MUST NOT BE REPRODUCED, AMENDED OR USED FOR THE EXECUTION OF ANY WORKS WHETHER IN CONNECTION WITH THE PROPOSED WORKS FOR WHICH IT HAS BEEN PREPARED OR OTHERWISE WITHOUT THE EXPRESS CONSENT IN WRITING OF MIES BUILDING SERVICES.
CORRIDOR SECTION AA 1:10 SCALE
2a
3a
SERVICES LEGEND CHW PIPEWORK
ELECTRICAL CROSSOVER ZONE
LPHW PIPEWORK MCWS/BCWS PIPEWORK
315Ø SUPPLY DUCTWORK
475 375
100
100
100
500
AGD PIPEWORK ELECTRICAL CONTAINMENT ZONE
1050 28Ø CONDENSATE DRAINAGE FROM FCU'S
SUPPLY DUCTWORK 15x15Ø LTHW F&R
28x28Ø CHW F&R
EXTRACT DUCTWORK
900
275
150 PIPEWORK CROSSOVER ZONE
WC EXTRACT DUCTWORK LIGHT FITTING LV/FIRE CONTAINMENT DATA/ELV CONTAINMENT SUB MAIN CONTAINMENT
ABBREVIATIONS DENOTES LOW LEVEL DENOTES HIGH LEVEL DENOTES CHILLED WATER SERVICE DENOTES ABOVE GROUND DRAINAGE DENOTES LOW PRESSURE HOT WATER DENOTES BOOSTED COLD WATER SERVICE DENOTES MAINS COLD WATER SERVICE DENOTES LOW VOLTAGE DENOTES EXTRA LOW VOLTAGE
LL HL CHW AGD LPHW BCWS MCWS LV ELV 2615
SERVICES LAYOUT IN PLAN
Notes: 1. For corridor services setting out, please refer to section dimensions. 2. All dimensions are in millimetres unless stated otherwise. 3. All measurements to be checked on site. 4. Any errors or omissions are to be brought to the attention of the engineer before work commences.
X207 ACCESSIBLE WC
X204 SEMINAR ROOM 30 m2
A
X206 MALE WC
Rev
Updated as per clients comments
16/02/18
Description
Date
EXIT
EXIT
X208 STAIR 1
1.50 in A0 By Miles Building Services
X209 STAIR 1 LOBBY
EXIT X201 LRC 172 m2
Resource House, Electrical riser
Phoenix Business Park, Nottingham, NG8 6AR
tel: 0115 978 5874 fax: 0115 978 1078 www.mies-bs.com
Status:
X203 LRC 50 m2
X205 COMPUTER SUITE 51 m2
CONSTRUCTION Client:
NOTTINGHAM TRENT UNIVERSITY
Project:
CONFETTI CQ CAMPUS
Lift
X210 STAIR 2
X211 STAIR 2 LOBBY
Drawing Title:
CO-ORDINATED SERVICES LAYOUT SECOND FLOOR
Scale:
Project No:
1:50
(A0)
Drawn:
1427 Checked:
TH
JG
Drawing Number:
A0
MIES-1427-ME209
Date:
16/02/18 Approved:
JG Rev:
A
102
11
R EFERENCES
• Bennett, D. (2007). Architectural insitu concrete. London: RIBA. • BS 8500-2:2015+A1:2016 Concrete - Complementary British Standard to BS EN 206: Part 2:Specification for constituent materials and concrete • BS 8500-2:2015+A1:2016 Concrete - Complementary British Standard to BS EN 206: Part 1: Method of specifying and guidance for the specifier • Concrete stair details by Milbank • Confetti CQ Campus Feasibility Report by Allan Joyce Architect • Confetti CQ Campus social media • Construction programme by Stepnell • Confetti CQ Campus NBS Specification • Detail drawings by Allan Joyce Architect • Detail drawings of Corten cladding • Detail drawings of Curtain wall by Acorn Aluminium • Fair-faced concrete formwork calatog by Doka • General drawings by Allan Joyce Architect • Phillips Exeter Academy. (n.d.). Construction and Materials. [online] Available at: https://www.exeter. edu/academics/library/about/design-library/construction-and-materials [Accessed 27 Mar. 2018]. • Services layouts by Mies Building Services • 6-week programme by Stepnell
103
BEFORE
AFTER