The government had been started the scheme to have toilets in every house, whether they can afford and if they couldn’t, the govt.
will pay for construction of toilet. This mainly applies in villages.
But when it comes to the construction of it. The village head has the responsibility to call labours and contractor in village and
assure the construction of it. And the drainage system they formed is soak pit system.
The depth of soak pit should be between 1.5m and 4m deep, but never less than 2m above the groundwater table. It should be at a
safe distance from a drinking water source, i.e. more than 30m