Domestic Agency Procurement Highlights

Procurement highlights key

¢ R&D, manufacturing, installation milestones ¢ Major contracts ¢ ITER Organization-Domestic Agency milestones ¢ Completed package

Advertisement

The figures on the following pages are adjusted annually for changes in credit value due to Procurement Arrangement Refinements (PAR) and Additional Direct Investments (ADI) related to Project Change Requests. Please note that 2020 figures supersede all previously published figures.

Poloidal field coil #6 travels along the byways of the ITER Itinerary, taking four days to reach ITER. Adding to the weight of the coil (400 tonnes), the transport frame and trailer bring the total load to 800 tonnes.

DOMESTIC AGENCY PROCUREMENT HIGHLIGHTS

ITER CHINA (CN-DA)

www.iterchina.cn

PROCUREMENT ARRANGEMENTS*

Fourteen PAs signed since 2007 representing…

100%

in number

100%

of the total value of CN-DA in-kind contributions

Over 85 design or fabrication contracts related to ITER procurement have been signed with laboratories and industry.

Chinese procurement highlights in 2020

MAGNET SYSTEMS Toroidal Field Conductor

¢ All conductor unit lengths delivered

Poloidal Field Conductor

¢ All conductor unit lengths delivered

Magnet Supports

¢ 10 of 18 gravity supports delivered to IO ¢ Correction coils: batch 2 and 3 supports delivered to IO; thermal shield for batch 1 and 2 also delivered ¢ Poloidal field (PF) coil supports: clamps and pipes for PF1 delivered to RF-DA

Feeders

¢ Three batches (77 components) delivered, including four correction coil in-cryostat feeder rings ¢ Another 10 cryostat feedthroughs and coil terminal boxes in fabrication

Correction Coils

¢ All 6 bottom correction coils (BCCs) manufactured ¢ BCC1 and BCC5 delivered to IO ¢ Top correction coils: series production underway ¢ Side correction coil (SCC) qualification ongoing; start of SCC case enclosure welding imminent

Correction Coil and Feeder Conductors

¢ All correction coil and feeder conductors delivered

POWER SYSTEMS Pulsed Power Electrical Network (PPEN)

¢ All components of PPEN sub-package delivered

AC/DC Converters

¢ All main components of AC/DC converters delivered ¢ Most DC busbar supports and spares also delivered

Reactive Power Compensation

¢ Cable and cable trays plus all reactive power compensation components delivered

BLANKET Blanket First Wall

¢ Insulation coating for first wall components successfully developed and accepted by IO ¢ MRR completed for first wall full-scale prototype fabrication

Blanket Shield Block

¢ 316(L)N forgings completed for shield block #18 (SB18) ¢ Second hot helium leak test facility developed and commissioned ¢ Low friction coating demonstrated for SB components

FUEL CYCLE Gas Injection System

¢ 58 gas injection system manifold spools manufactured and delivered ¢ PDR for gas valve boxes closed; FDR preparation ongoing

Glow Discharge Cleaning

¢ Sandwich design feasibility review completed

DIAGNOSTICS Diagnostics

¢ Neutron flux monitor #07 support frame plus tools and spare delivered to IO; installation completed ¢ Divertor Langmuir probe preliminary design ongoing ¢ Preliminary design of remaining neutron flux monitors ongoing ¢ FDR closures ongoing for EQ#12 port integration and radial X-ray camera

BEIJING

% of ITER system procured by China

7.5%

65%

100%

80%

100%

100%

100%

55%

100%

12.6%

50.2%

100%

100%

3.2%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Does not include Complementary Diagnostic Arrangements

ITER INDIA (IN-DA)

www.iter-india.org

PROCUREMENT ARRANGEMENTS*

Fourteen PAs signed since 2007 representing…

100%

in number

100%

of the total value of IN-DA in-kind contributions

50 design or fabrication contracts related to ITER procurement have been signed with industry and R&D organizations since 2007.

Indian procurement highlights in 2020

CRYOSTAT Cryostat

¢ Completion and acceptance of cryostat upper cylinder (IC milestone) ¢ Base section and lower cylinder installed in Tokamak pit; welding for joining base to lower cylinder in final stage ¢ Manufacturing of top lid and all loose items (except top lid fasteners) completed in India. All major sectors shipped to IO

% of ITER system procured by India

100%

CRYOGENIC SYSTEMS Cryolines & Cryodistribution

¢ Lower pipe chase cryolines completed ¢ More than 90% of cryoline header elements installed at B2 level of the Tokamak Building ¢ Incoming inspection and installation carried out for the cryoplant termination cold box (CTCB) ¢ Cold circulators manufactured; shipment to IO in progress ¢ Manufacturing and shipment of other cryolines in progress; installation continues at ITER site

100%

HEATING & CURRENT DRIVE SYSTEMS Diagnostic Neutral Beam (DNB) Power Supply and Beam Line 100%

¢ Manufacturing of beam source and beam line components in advanced stage. FAT completed for the Indian Test Facility calorimeter ¢ Dummy assembly performed for the extractor and accelerator system grid mounting flanges to check for adherence to alignment requirements ¢ Hot helium leak tests performed for the first time on angled plasma grid segments, bias plate segments, and extractor grid segments (25 bar @ 150 °C) and on neutralizer panels (25 bar @ 80 °C) ¢ FDR for the DNB vacuum vessel held; chit resolution underway

NBTF components (beam dump & 100 kV power supply) 2%

¢ All NBTF components completed

Ion Cyclotron Radio Frequency (RF) Power Sources 100%

¢ In-house development of 3dB hybrid combiner and other transmission line components in progress ¢ Review of tender for driver and final stage amplifier for IO deliverables ongoing

Ion Cyclotron Heating & Current Drive RF Power Supply (8 out of 18) 44%

¢ Upgrade of controller hardware for high voltage power supply R&D unit in progress

Electron Cyclotron High Voltage Power Supply 30%

¢ Installation of 55kV, 110A main high voltage cathode power supply at ITER India lab in progress

Electron Cyclotron RF Gyrotron Power Sources (2 gyrotrons out of 24) 8%

¢ Contract signed for test gyrotron; design and manufacturing activities launched ¢ Factory testing of test gyrotron tube in progress, along with the matching optic unit

COOLING WATER SYSTEMS Heat Rejection System, Component Cooling Water System, Chilled Water System 100%

¢ Final consignments of pipes, pipe fittings and spares delivered to IO ¢ CCWS-2A water polishing units (first part) delivered after successful FAT ¢ FAT completed successfully for CCWS-2A water polishing units (last part) ¢ Stage-II of the contract completed ¢ Experimental pool scrubber tank (PST-X): design, manufacturing and FAT completed successfully as part of the Task Agreement

VACUUM VESSEL In-Wall Shielding (IWS) Block Assemblies 100%

¢ In-wall shielding blocks for all nine vacuum vessel sectors plus field joints manufactured ¢ All deliveries to KO-DA and EU-DA completed successfully ¢ SAT completed for all block assemblies delivered to EU-DA (5 vessel sectors); IWS SAT completed for three KO-DA vessel sectors out of four

DIAGNOSTICS Diagnostics

¢ PDR-related activities continued for upper port #09 ¢ Activities initiated toward final design of X-ray crystal spectroscopy (XRCS) survey system ¢ Experimental activities in lab carried out ¢ Design activities of several other systems/components progressing

3.1%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Does not include Complementary Diagnostic Arrangements

ITER JAPAN (JA-DA)

www.fusion.qst.go.jp/ITER/english/iter.html

PROCUREMENT ARRANGEMENTS*

Thirteen PAs signed since 2007 representing…

72%

in number

90%

of the total value of JA-DA in-kind contributions*

More than 800 design or fabrication contracts related to ITER procurement have been signed with industry since 2007.

Japanese procurement highlights in 2020

MAGNET SYSTEMS Toroidal Field Conductor

¢ All conductor unit lengths delivered

Toroidal Field Magnet Windings (9 out of 19)

¢ Two toroidal field coils (#12, #13) delivered to IO ¢ Another JA-DA coil is ready for shipment; three others are in the coil insertion phase

Toroidal Field Magnet Structures

¢ Seventh toroidal field coil structure (TFCS) set delivered to EU-DA ¢ Three other TFCS sets are under assembly with JA-DA winding packs

Central Solenoid Conductor

¢ All conductor unit lengths delivered

HEATING & CURRENT DRIVE SYSTEMS ITER & Neutral Beam Test Facility (NBTF) High Voltage Bushing and Accelerator

¢ Procurement of high voltage bushing completed

Neutral Beam Power Supply System for ITER and NBTF

¢ Installation work 100% completed for power supply components ¢ High-voltage test underway

Electron Cyclotron Radio Frequency Power Sources (8 gyrotrons out of 24)

¢ FAT gyrotron #3 completed ¢ Gyrotrons #6 and #7 manufactured ¢ Finalized fabrication and tests of #5-#8 anode/body power supply and control cubicles ¢ Two sets of magnets and matching optics units delivered to IO

Electron Cyclotron Equatorial Launcher

¢ Cooling water feedthrough prototype test completed; prototype of millimetre wave propagation under preparation ¢ Final design of equatorial launcher in progress

REMOTE HANDLING Blanket Remote Handling System

¢ Feasibility study for new requirements such as humid in-vessel atmosphere completed

DIVERTOR Outer Target

¢ Plasma-facing unit prototypes (for high heat flux testing) and full-scale prototypes: contracts placed ¢ Contract placed for hot helium leak test facility design ¢ Contracts for series production materials placed (tungsten monoblocks, 316L tubes and forgings, XM-19 forgings)

TRITIUM PLANT Atmosphere Detritiation System

¢ Progress on qualification activities: manufacture of integration system test rig ongoing ¢ Detritiation system joint procurement (phase II) signed with IO; joint procurement activities proceeding

DIAGNOSTICS Diagnostics

¢ Contract awarded for microfission chamber end-processing of mineral insulated cable ¢ Structural design of edge Thomson scattering beam dump progressing ¢ FDR held for poloidal polarimeter retroreflector ¢ IR thermography: neutron and gamma ray irradiation tests for grasses advancing ¢ Thermal cycle tests completed for metal mirrors of divertor impurity monitor

TOKYO

% of ITER system procured by Japan

25%

47%

100%

100%

100% 33%

59%

33%

71%

100%

100%

50%

14.2%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Includes Complementary Diagnostic Arrangements

ITER KOREA (KO-DA)

www.iterkorea.org

PROCUREMENT ARRANGEMENTS*

Eight PAs signed since 2007 representing…

89%

in number

95%

of the total value of KO-DA in-kind contributions

177 design or fabrication contracts related to ITER procurement have been signed with universities, laboratories and industry since 2007.

Korean procurement highlights in 2020

VACUUM VESSEL Main Vessel (2 of 9 segments)

¢ First vacuum vessel sector (S#6) delivered to the ITER site (IC milestone) ¢ Activities progressing well on Sector #7 (98% complete), Sector #8 (92.4%), and Sector #1 (85%)

Equatorial Ports and Lower Ports

All lower port stub extensions delivered to sector workshops ¢ Neutral beam port in-wall shielding and field joint ex-wall shielding delivered to the port workshop and IO ¢ Vacuum vessel gravity support superbolt and insert manufacturing contract concluded in FebruaryBLANKET

Blanket Shield Block

¢ Successful testing and certification of first production unit ¢ Series production underway; all row 6 shield blocks in manufacturing

POWER SYSTEMS AC/DC Converters

¢ FAT completed for AC/DC converters CCU/L-2,3,4,5,6 and CS-2,3,4,5 ¢ Delivery of AC/DC converters VS1-2, CCS-2,3 CCU/L-2,3,4,5,6 and CS-2,3,4 ¢ Installation activities progressing on AC/DC converters VS1-1,2 CCS-1,2,3 CCU/L-1,2,3,4 and CS-1,2,3

MAGNET SYSTEMS Toroidal Field Conductor

¢ All conductor unit lengths delivered

THERMAL SHIELD Vacuum Vessel Thermal Shield and Cryostat Thermal Shield

¢ Delivery of thermal shield for vacuum vessel sector #6 accomplished (IC milestone) ¢ Thermal shield completed for all nine vacuum vessel sectors; shipments to ITER proceeding ¢ Cryostat thermal shield completed; shipments to ITER proceeding

ASSEMBLY TOOLING Machine Assembly Tooling

¢ Frame and radial beams delivered to IO; sector lifting tool and upending tool passed all functional tests ¢ Central column, bottom cylinder, and in-pit working floor delivered to IO ¢ Ownership of 12 tools transferred to the ITER Organization

TRITIUM PLANT Tritium Storage & Delivery

¢ PDR held in July; panel report approved in September ¢ Full-scale experimental getter bed performance test under practical operating conditions ongoing

DIAGNOSTICS Diagnostics

¢ Manufacturing contract established for neutron activation system package #1 ¢ Thermal cycling and steam ingress test conducted for vacuum ultraviolet spectrometer first mirror

% of ITER system procured by Korea

21.20%

100%

49.82%

40.62%

20.18%

100%

99.90%

94.24%

1.99%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Does not include Complementary Diagnostic Arrangements

ITER RUSSIA (RF-DA)

www.iterrf.ru

PROCUREMENT ARRANGEMENTS*

Twelve PAs signed since 2007 representing…

100%

in number

100%

of the total value of RF-DA in-kind contributions

MOSCOW

800 design or fabrication contracts related to ITER procurement have been signed with industry since 2007.

Russian procurement highlights in 2020

POWER SYSTEMS Switching Network, Fast Discharge Units, DC Busbar and Instrumentation

¢ Four batches of coil power supply systems delivered to ITER; others in manufacturing ¢ FDR held for DC busbars (toroidal) and fast discharge unit resistors

% of ITER system procured by Russia

100%

MAGNET SYSTEMS Toroidal Field Conductor

¢ All conductor unit lengths delivered

Poloidal Field Conductor

¢ All conductor unit lengths delivered

Poloidal Field Magnet No.1

¢ Preparation for impregnation completed, clamp assembly prepared; winding coil acceptance tests carried out ¢ Transport frame tested; delivery documentation in preparation

19.3%

20%

100%

BLANKET Blanket First Wall 40%

¢ Coordination with IO on manufacturing and control documentation for full-scale prototype ¢ Trial manufacturing/testing of full-scale prototype elements (fastening system and electrical connection elements, finger cases, beam, central bolts) ¢ Hot isostatic pressing (HIP) of steel/bronze bimetallic covers done ¢ Longevity plasma testing of the thermal armour mockups (stage 2020) carried out; intermediate products manufactured

Blanket Module Connectors 100%

¢ 530 bimetallic pedestals and corresponding inserts manufactured; 142 pedestals delivered ¢ Intermediate products manufactured for test blanket module connectors

DIVERTOR Dome

¢ Full-scale prototype manufactured and prepared for delivery to IO; pre-shipment tests realized ¢ Pilot manufacture of semi-finished dome elements; longevity plasma testing of thermal armour mockups (stage 2020)

Plasma-Facing Component Tests

¢ High-heat flux testing of dome plasma-facing units in preparation ¢ Quality assurance documentation approved by IO

100%

100%

VACUUM VESSEL Upper Ports

¢ Lateral upper ports/port stub extensions #01, #07, #13, #15, #17 manufactured ¢ Central upper ports/port stub extensions #16, #14 delivered to KO-DA ¢ Lateral upper ports/port stub extensions #03, #11, #09, #05, #01, #13 delivered to IO

Port Plug Test Facility (PPTF)

¢ Manufacturing started for dummy plug and handling system, non-nuclear stand #3 components ¢ Handling system MRR passed

100%

100%

DIAGNOSTICS Diagnostics 17%

Port Plug Integration Engineering

¢ 3D models of upper port #02, #07, and #08 structures updated to final design level ¢ Mockup manufactured for #02 gas/water inlet pipe (version 3); manufacture of #07 structure underway ¢ Equatorial port plug #11 structure (stage 1) manufactured; preparations made to manufacture structures for diagnostics systems integration ¢ Integration site subsystems created for testing of mockups for diagnostics system integration (stage 4) ¢ Front and back rack designs, rack locking systems developed for lower port #08 integration

Diagnostics

¢ Neutron flux monitor: data acquisition system prototype tested jointly with ITER-like fission chambers under intensive neutron flux at IBR-2 (JINR, Dubna); prototype detector unit developed and tested ¢ Mockups, components created for CXRS (Charge eXchange Recombination Spectroscopy) and vertical neutron camera; testing carried out ¢ Architecture developed for high field side reflectometer data collection and management system ¢ Functional mockup unit prototype manufactured for H-alpha and spectroscopy; mockups created for neutral particle analzyer and divertor Thomson scattering

HEATING & CURRENT DRIVE SYSTEMS Electron Cyclotron Radio Frequency Power Sources (8 gyrotrons out of 24)

¢ Final FAT for set #5 carried out; manufacturing completed on set #6 ¢ Materials for set #7 purchased

33%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Does not include Complementary Diagnostic Arrangements

US ITER (US-DA)

www.usiter.org

PROCUREMENT ARRANGEMENTS*

Seventeen PAs signed since 2007 representing…

100%

in number

100%

of the total value of US-DA in-kind contributions

WASHINGTON DC

The US has awarded more than 600 design or fabrication contracts to US industry, universities, and national laboratories in 46 states plus the District of Columbia since 2007.

US procurement highlights in 2020

COOLING WATER SYSTEM Tokamak Cooling Water System

¢ Continued piping and fittings fabrication (via Arrangement with IO) ¢ Awarded remaining non-ESPN hardware required for First Plasma (FP) ¢ Continued progress in procuring ESPN hardware required for FP (via Arrangement with IO)

MAGNET SYSTEMS Central Solenoid (CS) Modules, Structure and Assembly Tooling

¢ First central solenoid module successfully completed testing ¢ Twelve deliveries of structural components and assembly tools to ITER site

Toroidal Field Conductor

¢ All conductor unit lengths delivered

DIAGNOSTICS Port-Based Diagnostic Systems

¢ Low field side reflectometer completed final design review

HEATING & CURRENT DRIVE SYSTEMS Ion Cyclotron Transmission Lines

¢ Transmission lines and matching system in development, using simulation tools and high-power tests in a dedicated lab

Electron Cyclotron Transmission Lines

¢ FDR completed (Part 1) ¢ Awarded fabrication contract for the H3 chiller system ¢ Awarded waveguide manufacturing development contracts

% of ITER system procured by US

100%

100%

8%

14%

88%

88%

FUEL CYCLE Vacuum Auxiliary and Roughing Pump Stations 100%

¢ PDR for roughing pump stations Part I of the cryostat and non-active service vacuum system roughing pumps and related I&C ¢ Awarded contract for the manufacture of cryogenic guard vacuum system

Pellet Injection System 100% Disruption Mitigation System up to a capped value

¢ Fabricated test hardware for shattered pellet injector experiments at JET and KSTAR

TRITIUM PLANT Tokamak Exhaust Processing System

POWER SYSTEMS Steady State Electrical Network

¢ All components delivered

88%

75%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Includes Complementary Diagnostic Arrangements

FUSION FOR ENERGY (EU-DA)

www.fusionforenergy.europa.eu

PROCUREMENT ARRANGEMENTS*

Thirty-nine PAs signed since 2007 representing…

80%

in number

94%

of the total value of EU-DA in-kind contributions

PORTUGAL ESTONIA

IRELAND UNITED KINGDOM DENMARK

LATVIA LITHUANIA

NETHERLANDS BELGIUM GERMANY

LUXEMBOURG POLAND

CZECH REPUBLIC SLOVAKIA

FRANCE

SWITZERLAND AUSTRIA

HUNGARY

SLOVENIA CROATIA ROMANIA

SPAIN ITALY BULGARIA

The EU has awarded 725 design or fabrication contracts related to ITER procurement to universities, laboratories and industry since 2007.

MALTA GREECE

CYPRUS

EU procurement highlights in 2020

BUILDINGS Building Construction, Tokamak Pit Excavation and Drainage, Ground Support Structure, Seismic Isolation Pads 100%

¢ Anti-seismic bearings completed ¢ Excavation and ground support completed ¢ Assembly Building completed (IC milestone) ¢ Limited crane access between Assembly Hall and Tokamak Building (RFE 1B stage 2) achieved (IC milestone) ¢ Tokamak Building access granted in L3 West area (T4-T5) to allow for feeder installation to begin (IC milestone) ¢ Site Services Building handed over to IO ¢ Contract signed for the completion of the Tritium Building (TB18) ¢ Contract signed for electrical equipment (TB13)

Architect Engineer Services 100% ITER Headquarters 53.5%

¢ Headquarters building completed

% of ITER system procured by the EU

MAGNET SYSTEMS Toroidal Field Conductor

¢ All conductor unit lengths completed

Toroidal Field Magnet Windings and TF Coils (10 out of 19)

¢ Complete FAT for PA work scope for first EU toroidal field coil (IC milestone) ¢ 3 coils delivered to IO, 5 others in different stages of production ¢ 10 out of 10 winding packs completed; 8 delivered to insertion facility

Pre-Compression Rings

¢ All pre-compression rings completed in 2020

Poloidal Field Conductor

¢ All conductor unit lengths completed

Poloidal Field Magnets No. 2-6

¢ PF5 ready for cold test (IC milestone) ¢ PF6 manufactured and delivered to IO (IC milestone) ¢ Impregnation completed on PF2; double pancake winding has begun for PF4

HEATING & CURRENT DRIVE SYSTEMS Power Supply Heating Neutral Beam

¢ All NBTF power supplies completed, installed and transferred to IO

Neutral Beam Test Facility (NBTF) Components

¢ MITICA vacuum vessel completed, installed and transferred to IO ¢ Rotating platform for MITICA beam source installed ¢ SPIDER cesium ovens completed

Neutral Beam Assembly, Testing, Active Compensation & Correction Coils Neutral Beam Source and High Voltage Bushing Neutral Beam Pressure Vessel, Magnetic Shielding Ion Cyclotron Antenna Electron Cyclotron Control System

¢ First batch of cubicles delivered to IO site

Electron Cyclotron High Voltage Power Supply

¢ Second power supply set completed and delivered to IO ¢ MV AC cells (switchgears) for electron and ion cyclotron systems completed and delivered to IO

Electron Cyclotron Upper Launchers Electron Cyclotron Radio Frequency Power Sources (6 gyrotrons out of 24)

¢ Procurement Arrangement for the Electron Cyclotron Radio Frequency Gyrotrons signed in September

VACUUM VESSEL Main Vessel (5 of 9 segments)

¢ Final assembly phase started for Sector #5 ¢ Outer shell welding started for Sectors # 4, #9, #3 and #2 ¢ Risk and schedule optimization plans launched

20%

53%

100%

18%

100%

35%

64.7%

100% 41% 100% 60% 40%

62%

76% 25%

56%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Does not include Complementary Diagnostic Arrangements

EU procurement highlights in 2020 % of ITER system procured by the EU

DIVERTOR Inner Vertical Targets 100%

¢ First full-scale prototype (FSP) successfully completed; test assembly of a second FSP completed and ready for high heat flux testing

Cassette Body 100%

¢ Design, engineering and qualification phases for Stage I cassette body series production completed

Divertor Rail 100%

BLANKET Blanket First Wall

¢ Framework contracts signed for series production ¢ Framework contracts signed for beryllium material procurement ¢ Call for tender launched for copper-chromium-zirconium alloy material procurement ¢ Procurement Arrangement for Blanket Manifolds signed in May

REMOTE HANDLING In-vessel Divertor Remote Handling System

¢ Deep into the cassette toroidal mover final design; launched cassette multifunctional mover final design

Cask and Plug Remote Handling System

¢ Completed preliminary design of MA-1 units, started the others

Neutral Beam Remote Handling System

¢ Manufacturing the crane prototype in support of final design

In-Vessel Viewing System

¢ Started prototyping in support of final design

Common Technologies

¢ Camera demonstrator built and operated ¢ Multiplexer electronics generation 1 completed ¢ GENROBOT framework software integration into DTP2 (Divertor Test Platform 2) started

POWER SYSTEMS Steady State Electrical Network (SSEN) and Pulsed Power Electrical Network (PPEN): Detailed System Engineering Design Installation and Commissioning

¢ LV and MV load centres for all First Plasma non-nuclear buildings are operational (IC milestone)

Emergency Power Supply SSEN Components 47.4%

100%

100%

100%

100%

100%

100% 100%

100% 25%

FUEL CYCLE Front End Cryo-Distribution: Warm Regeneration Lines

¢ Warm generation line package completed in 2020

Front End Cryo-Distribution: Front End Cryopump Distribution

¢ FDR of cold valve boxes

Cryopumps, Torus (6) and Cryostat (2)

¢ Qualification of special technologies

Cryopumps, Neutral Beam

¢ Supply of all cryopanels and thermal radiation shields ¢ Qualification of charcoal coating process

Leak Detection

¢ Award of leak detection system contract

TRITIUM PLANT Water Detritiation System

¢ Water holding tanks and emergency tanks completed

Hydrogen Isotope Separation System

CRYOPLANT Cryoplant: LN2 Plant and Auxiliary Systems

¢ Completion of mechanical installation

100%

100%

100%

100%

100%

100%

100%

50%

DIAGNOSTICS Diagnostics 25%

¢ Four Complementary Diagnostics Arrangements (CDA) signed, completing all CDA arrangements envisaged ¢ All remaining outer vessel coils delivered to IO, completing the CDA ¢ First batch of inner vessel coil platforms delivered to IO site ¢ PDRs held for low field side collective Thomson scattering, radial neutron camera in-port plug systems, diagnostic pressure gauges, and magnetics software ¢ FDR held for vacuum vessel electrical feedthroughs

RADIOACTIVE MATERIALS Waste Treatment and Storage Radiological Protection

¢ Call for tender for the supply of environmental and beryllium radiological and environmental monitoring systems

100% 100%

Abbreviations • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization • IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review • SAT Site Acceptance Tests * Does not include Complementary Diagnostic Arrangements

In the congested environment of the Assembly Hall, every square metre of space must be exploited. Coordinators are using 4D planning methods (3D plus time) to organize activities performed on critical machine components.

This article is from: