ARC242Montanari
3. Material List & Cost Analysis 4. Equipment Requirements 5. Project Detail (Filter Design) 6-14. Procedural Storyboard
2
Roof Components (Continued)
Foundation Item
Quantity
Price Per Unit
Total Price
8x8x16 CMU Block
4
$1.59
$6.36
<20 lbs Quikrete
1
$4.98
$4.98
5’ Sill Sealer
1
$4.69
$4.69
6” Anchor Bolts
4
$3.09
$12.37
Flooring Item
Quantity
Price Per Unit
Total Price
Item
Quantity
Price Per Unit
Total Price
2x4x8’ Wood
2
$2.84
$5.68
1”x6” Tongue & Groove Soffit Boards 25 sq. ft. Black Felt/Tar Paper
5
$3.57
$17.85
1
$14.20
$14.20
12’ Drip Edge
1
$4.69
$4.69
Water Runoff Item
Quantity
Price Per Unit
Total Price
Gutter Spikes
3
$3.66
$10.97
Downspout
1
$8.34
$8.34
>1’6” Wide Carpet 3/4"x4'x8' OSB
1 2
$6.24 $22.97
$6.24 $45.94
Elbow
3
$2.35
$7.05
Gutter Straps
2
$1.52
$3.04
Base Board 7’
1
$12.52
$12.52
8’ Gutter Length
1
$5.23
$5.23
Rebond Carpet Padding (Sq. Ft.)
6
$2.88
$17.28
4” Vinyl Gutter End Cap
1
$2.97
$2.97
Wall Components
Fasteners Item
Quantity
Price Per Unit
Total Price
Box of Nails
1
$2.48
$2.48
$63.15
Box of Roofing Nails
1
$7.97
$7.97
$16.17 $8.47
$32.34 $118.58
Box of Drywall Screws
1
$4.37
$4.37
Box of Finishing Nails
1
$1.48
$1.48
1
$43.96
$43.96
2 2
$13.30 $7.39
$13.30 $14.78
Price Per Unit
Total Price
15
$4.21
2 14
60 sq. ft. Tyvek/Vapor Barrier 35 sq. ft. Gypsum Board 2x10x8’ Wood Header
Item 2x6x8’ Wood (Frieze, Treated, Sill) ½x4x8’ Plywood Vinyl Siding
Quantity
Roof Components
Filter Item
Quantity
Price Per Unit
Total Price
1x4x8’ Wood
3
$2.04
$6.12
18” Slide Track & Roller
4
$7.49
$29.96
24x36 Glass
2
$13.00
$26.00
Item
Quantity
Price Per Unit
Total Price
2x8x8’ Rafters 25 sq. ft. Shingles
2 1
$5.72 $27.50
$11.44 $27.50
Subtotal
$595.32
Tax
X 8.25%
Soffit Vent
1
$1.49
$1.49
Total
$644.43
Totals
3
Hand Tools
Power Tools
Equipment
Framing Hammer
Drill + Bit Set
Safety Glasses
Screwdrivers - Basic Set
Miter Saw
Calculator
Adjustable Wrench
Circular Saw
Saw Horse
Combination Square
Nail Gun
50â&#x20AC;&#x2122; Extension Cord
Tin Snips
Compressor
Step Ladder
Utility Knife Hand Saw Speed Square Tape Measure Level Pliers
4
1: Construct the frame of the filter according to the dimensions of the wall opening. 2: Construct the wooden panels by cutting out slant pieces of a width of 1/2". Then attach them to a 3" wide frame. 3: Construct a mirror image of the wooden panel to create the second filter piece. 4: Attach the railing rollers to the filter frame in the wall opening. 5: Insert the wooden panels and glass panels in the railing systems to complete the filter.
5
6
1
(1) 4 CMU blocks are arranged in an â&#x20AC;&#x153;Lâ&#x20AC;? shaped pattern to form a base.
4
(4) A termite shield and sill sealer is rolled onto the CMU. The 2x6 sill plate is bolted down to the CMU. The sill plate should be offset 1/2â&#x20AC;? from the side of the CMU so that the sheathing will be flush.
3
2
(3) Before the Quikrete hardens, 5 anchor bolts will be placed into the cores of the CMU.
(2) Quikrete is poured into the CMU cores in preparation of the anchor bolts.
5
6
(5) 2x10 Headers are placed on top of the sill plate and toenailed down. The headers should be flush with the side of the sill plate.
(6) 2x6 joists are attached using 2 joist hangers. A rear header is attached to stabilize the joists.
7
7
8
9
(7) Attach žâ&#x20AC;? OSB Sheathing to Joist System.
(8) Construct the stud wall system. Attach the 2x6 studs to the sole plate according to the location of the wall opening. Construct the corner system as illustrated in the graphic. Construct the window frame and attach to the stud wall system.
(9) Attach the sole plate of the stud wall system to the floor sheathing.
8
10
11
(11) Attach Tyvek weather barrier to the exterior OSB wall sheathing.
(10) Attach ½” exterior OSB wall sheathing to the studs.
9
12
13
(12) Attach 2x8 rafter to the double header by cutting a birds mouth cut into the rafters where needed. Attach the 2x8 frieze board to the end of rafters. Attach 2x8 lookouts to the rafters where needed.
(13) Attach the 1x6 tongue and groove soffit boards and the soffit vent to the underside of the rafters. Attach 3/4â&#x20AC;? OSB roof sheathing to the top of the rafters.
10
14
(14) Attach vinyl panel siding to the exterior walls, and cover corner with edge trim piece.
15
(15) Attach 1x10 fascia board to frieze board. Attach gutter system using gutter spikes and brackets to the fascia board.
16
(16) Layer OSB roof sheathing with roofing felt. Attach composite asphalt shingles to the OSB roof sheathing through the roofing felt.
11
17
18
19
(17) Attach 2x4 ceiling joists to the double header and rafters.
(18) Attach the gypsum board to the interior wall studs and ceiling joists. Stretch the carpet pad and carpet to the floor OSB sheathing.
(19) Attach the base board/trim to the bottom of the interior walls.
12
20
(20) Construct wooden frame to the dimensions of the wall opening insert into wall opening.
23
22
21
(21) Attach interior filter rail system to the edge of the wall opening. Insert glass panels into railing system.
(22) Attach exterior filter rail system to the edge of the wall opening. Insert wooden filter pieces into the railing system.
(23) Attach 2x4 support post to the rear corner of the construction.
13
24
(24) Completed construction of wall section.
14
Jeff Montanari - Spring 2013 - Southern Illinois University