ABPL20033 - Construction Analysis, Semester 2 - 2021
Jessie
Sun, 1174124, 27/09/2021 Limestone House, Tutorial 18 ASSIGNMENT 2 FLIPBOOK SECTION 2D: CONSTRUCTION SEQUENCE & DETAILS
Subject
coordinator: Dr Alberto Pugnale
Tutor:
Dr Atefeh Zohourian
(Jiaqi)
a
Before the commencement of project construction, all relevant authority permits shall be obtained
a.a a.b a.c a.d
The contractor shall do a tharough inspection of the site as the matter of priority to tendering any conditions likely to affect the performance and extent of the contract.
All work shall comply to the requirement of the authority. Work not covered by requirements of the authority much comply with Australian Standard.
Alteration requirement shall firstly approved before the construction and not be deemed.
All requirements for construction shall be inspected and complied with building engineering survey.
b
Demolition of pre-existing structure. Excavation and clearance of the surrounding in target site area for site preperation
b.a b.b b.c
Site boundary is identified and embraced by construction site fences and safety cones.
Temporary site offices are implemented on site. All debris, building rubbles, surface vegetation and top soil shall be removed.
c
Geotechnical engineer Macgregor shall complete the soil testing and soil report which determing the minimum safe permanent and temporary batter angle of the foundation of site
Notes and detail of existing site condition may refers to site investigation report No. 2163414 c.a
e.a e
Underground utility mapping
The construction team shall acknowledge the most recent information about pipes and cables network underground to eliminate the risks of blind digging.
d
Trenches are dug for footing and pipe system
d.a d.b d.c d.d
Caution should be taken when service trench or other excavation occurs.
Trenches are dug, detail refers to Limestone Residence structural drawings.
Footings shall be clear up with square corners and cleaned.
All water must be removed from footing excavation.
EB2 Edge beam 450 150
10mm Ableflex expansion joints
Garage infill slab
e.b e.c e.d e.e
Contractor shall establish any pipework connect to the existing pipe system prior commencement. Any pipe penetrations through fire rated building member shall be filled with fire sealant or fire collar. Any wire penetration through fire rated wall shall be sealed.
All pipes shall be capped to avoid foreign objects entering the pipe system. Pipes are labeled with 150mm colour identification bands in accordance with AS1345. All electrical wire shall be concealed with PVC conduit.
Pipework layout and detail refers to Hydraulic Sercies Drawing. Pipework shall follows the Australian/New Zealand Standard 3500.2.3-Plumber and Drainage. Electrical system layout and detail refers to Electrical Services Drawing.
Site preperation for slab on ground
Basement slab Blinding concrete
Basement level 450 Compacted sand bedding
Downpipe infiltrationtopit Kuni seal
Basement slab Gracel Backfill
Compacted sand bedding
SF1 Strip footing N16 Starter bars
Typical packing sand compacted to98% maximum dry density is laid as subgrade for a minimum depth of 200mm. Class 4 fine crushed rock compacted to 98% maximum dry density is laid in 150mm depth layer if soil is soft or moisture, in accordance to AS1289. Refer also geotechnical engineers report.
f.b f.c f.d
50mm compacted sand bedding on 150mm subgrade layer.
The entire surface is to be proof rolled using polythene membrane as vapour barrier. Footing shall be poured with blinding concrete refers to Foundation Notes and Soil Report.
500
Refer to DWG-S05-Bs1a 600
Water membraneproofing 300
Blinding concrete with bearing capacity of 15MPa 100mm embedded in compact subgrade
Refer to DWG-S04-FD01
f
f.a
Safety cone b.b Site office c Soil
b.a
f.b f.c d e f.d a b c Soil stockpile Stockpile of the soil from excavation Bulldozer Utilized on-site for trench excavation Site soil classification Class P/M STAGE 1 Stie Preperation & Footing
d. Trench Soil stockpile e. Capped pipe
a
Formwork is constructed to embrace the ground floor slab as preperation for pouring concrete
a.a a.b a.c
All formwork shall be used in accordance with AS 3610 and manufacturer’s specification. Formwork shall remain in position to cure for minimum 28days after concrete is poured to ensure concrete is set.
Slab formwork is installed underneath the area of concrete pouring to carry the load.
Side formwork is installed to embrace the concrete.
b
All material, workmanship, fabrication and eraction for structural steel work shall comply with AS 4100 Steel Structure Code
b.a b.b b.c b.d b.e b.f
Lower reinforcement is laid, Anti-bursting reinforcement is installed to ensure full development at slab corners.
Bar chair shall placed in position by profile height.
Tendon is placed and tied with the bar chair.
Anchorage and grout vent is installed in the following. Encased beams and columns shall be wrapped in SL41 wrapping mesh.
Steel rebar above ground need to be capped for safety and labeled in colour.
c
Pouring Concrete
c.a c.b c.c c.d
All concrete shall be mechanically vibrated in accordance with AS 3600.
Concrete properties are transported to site and mix on site to make sure concrete is fresh. The compounds of concrete mixture shall comply with AS 3799.
Concrete shall be graded with specified strength in accordance to AS 1379. SLUMP test is necessary for concrete to determine its preperty in relation to its consistency. This concrete testing shall comply with AS 1012.3.1-1988.
Concrete shall comfirm with the following (Table refers to Limestone Residence structure drawings):
Pouring Concrete
d.a d.b d.c
f
Beams and slab shall be poured together in one operation.
Concrete cure must commence within 2 hours of placement.
Cncrete must be cured for a minimum of 7 days after pouring to allow it setting.
f.a f.b f.c f.d f.e f.f
Steel supportance for formwork
d b Stand in tendon
Side formwork will be removed after concrete is set e
SLUMP Concrete Testing
-Slump is a method of testing and dertermining the concrete properties related to the consistency of concrete.
-Comply with AS1012.3.1-1998
-Tools: standard slump cone, small scoop, bullet-nosed rod, ruler, slump plate.
Dealing with tendon
The former will be removed from the tendon. Block and jaws will be inserted.
Stressing and measuring the elongation Strand end is cut off after measurement. Socket will be filled with mortar
Bleeding air through the tendon to clean up foreign elements.
Grouting into the tendon
Denotes downled construction joint
Detail
Ground floor
N-12 Bars at top Water stop seals
and grout vent f Measure elongation c Soil
Reliable 20-120mm Repeat test Outside range
Slab formwork
WT.04 detail refers to WT02
Ground floor slab
Ground floor
20mm screed, 1:100 falls to drain to architect require ments
Vertical bar into slab as intermedia to connect the vertical structure for basement and groundfloor slab
N16-200 Starter bars at top and bottom
Vertical reinforcing to project 400mm out of wall top edge. Bars shall be cut off and center into grout sleeve
Refer to DWG-S11-GF2
Capped steel rebar
Tendon tied to bar chair
b.b b.c
Refer to DWG-S12-GF17
True Shear Collapsed Zero
Concrete Composition
-Normal class concrete may refers to AS 1379
-Typical concrete composition including water, cement, aggregates and admixture.
-Water is mixed with cement powder to form a paste which hold the aggregates together.
-Water/Cement ratio=0.5
-Hydration is the chemical reaction process which harden the cement paste.
-Fine aggregates(fine and coarse sans) or coarse aggregate(stone, gravel, crushed rock screening) are added to concrete mix to improve durability.
-Aggregates must be graded by testing the voids.
-Strength and durability of concrete are affected by cement type, W/C ratio, temperature, compaction and curing.
Reinforced concrete
A combination use of concrete and steel.
Reinforcement concrete
Effective depth The depth of a concrete section measured from the compression face to the centrold of the tension reinforcement
Cover
The amount of concrete required to protest steel reinforcement from fire and corrosion.
Reinforcing concrete
Side formwork
Bar spacing
The center to center spacing for parallel reinforcing bars.
STAGE 2 Ground Floor Slab
a
Intermediate Floor Structure
Intermediate floor structure consists of timber framing in constructing groundfloor and first floor.
a.a a.b
All timber frame including bracing shall comply in accordance with AS. 1684 unless specification or noted by contractor.
All timber work shall be stress graded(MPa), F graded(F)and hazard class analyzed(H).
Relevant Australian Standards:
AS/NZS 1748 Timber Stress-graded Product requirements for mechanically stress-graded timber
AS 2082 Visually stress-graded hardwood for structural purposes
AS 2858 Timber softwood-visually stress-graded for structural purposes AS2878 Timber classification into strength groups AS 3519 Timber Machine Proof Gradding
b
Constructing intermediate ground floor in his study
b.a b.b b.c
490mm height cold zone void is left inbetween structural slab and intermediate ground floor of his study. 10mm packer set upon concrete plinth and an Oriented Strand Board is laid over on packer. The OSB is 12mm thick which is vapour permeable 240mm height joist laid upon OSB in accordance to
c
Constructing intermediate floor in the corridor
c.a c.b c.c c.d c.e c.f
Vertical timber frame and bracing is construction but not showing in this section.
Scaffolding is erected for easier and safer construction process
300x63 F16 hyspan(FB3) is constructed along the edge of corridor.
A series of 140x45 floor joist (FJ3) is laid in a direction of south to north next to hyspan. 200x13 unequal steel angle(UA) is connected with floor joist by flat heat steel EA countersunk screw.
Hoop iron stap in 30 degree nailed by minimum of 3 nails, to support the and connect hyspan and floor joist.
Stress Grading MGP
MGP is a mechanical stress grading system for plantation softwoods. MGP stand for Machine Graded Pine. It measures such as stiffness, compressive strength and shear strength of plantation softwood. This grading system follows AS/NZS517
F Stress Grading System
F stress grading is a classification system established by visual, mechanical or machine grading assessment. F stands for Forces. Most Australian timber except from plantation softwood is graded by F-grading system. This grading system follows AS 2858.
Grade Stamp
After wood is graded, a grade stamp will stamped on it surface.
OSB(Oriented Strand Board)
Hoop Iron Stap min 3 nail to each straps at 450mm centers
Detail Base detail 3mm stopping bed
Steel EA countersunk fixing into packers flush and sand
FB3
Detail His study GF
30 30
200x13 EA steel angle toe cut back
Steel angle paint finish
Osb have up to 50 layers of wood chips oriented in all directions and compressed and glued together. It is stronger and denser than plywood. This material has no soft spots and has better shear strength. Also it is more afordable and resource-efficient.
All timber shall be free of gum veins, pockets, knots holes and splits within 250 of any connection
OSB boards from the airtight membrane to the floor zone, all joints to be taped to ensure an air tight layer and to comply with passive house requirements
Detail Intermediate floor
WT.04 150 thick RC plinth wall Refer to DWG-AR810-A
N12 Bars at top 2-FJ4 2-FJ4
Marine packingplyfor isolation requirement
240 joistheight Refer to DWG-CD101
OSB Void
N16-200 Starter bars at top and bottom Ground floor slab
Refer to DWG-S11-GF2
STAGE 3
Unequal Angle (UA) Floor Joist connection EA countersunk screw
a
a.a a.b a.c
Positioning timber bracing in accordance to AS1684 The Saw cut is marked in position of timber bracing and cut in optimum angle of 45 degree(no less than 30 degree or greater than 60 degree) between top and bottom plate. Horizontal frame on wall on top and bottom of window space(L13 and L14)
Timber framing and joists on his study roof is connected with vertical structures.
b.a
The roof framings in a direction from north to south are L12, RB10, RB21 and FBR2. The roof framing in a direction from west to east on the edge is 2/19x45 F7 KD pine(FBR1)(grade refers to stage 3 notes). Timber joist R3 is laid in the middle.
ties @450
with joist hangers at L12 end.
AS 1684.4
Type A Bracing
RB21 STAGE 4 Vertical Structures Above Ground
Hardboard shall be nailed to framed using 30 x 2.8mmn galvanized flat-head nails. The maximum stud spacing = 600 mm. Bracing panel minimum width = 900mm
Metal Bracing
Top Plate
Welding
Welding is a fabrication method that connects metals by coalescence, simply describe as melting two pieces of steel and by adding a filler material in the joint.
Welding is used in fabriation of members, attatchment of components, splicing and joining of structural elements or bacrivation of sub-assemblies for later erection on site.
Nogging Common Stud
Bottom Plate
Jamb Stud
Two weld types: Fillet Weld (FW)
A fillet weld has an approximately triangular weld pool and joins two workpieces that are not in the same plane and that form a tee, a lap or a corner joint. The advantage of fillet weld is that up 8mm FW can be done in a single operation.
17 58 South elevation L12 R3 FBR2 RB21 FBR2
Roof Framing
SHS steel post(C8) is placed in position to support furture chimney construction.
SHS steel post(C1) is placed to support future wall and masonry veneer construction.
250 PFC steel beam(L10) located in north-south direction to support masonry skin over(under development). 100min end bearing on chimney. 8mm cleat. It is 2M20 bolted to L17 which is a 250 PFC(250x10 PL welted to bottom flange) flow along the curve wall on the north. UA steel beam (L9) is placed in position with 300min end bearing.
Steel angle shelf lintal (SA.01) constructed to support masonry veneer.
200x10th EA steel post(C7) cutted to 175x200x10mm angle for glazing fixing.
50x5 EA struts PWA
Butt Weld(BW)
c C7 C1
Measuring wall for bracing and Identify bracing type
Welding
c.b
b Legend Mark FBR1 R3 RB10 RB21 L12 L13 L14 C1 C7 C8 L9 L10
c.a b c.c
a FJ3
R3 L14
c.e c.d
DS L13 L10 C1 FBR1
Fillet Weld Butt Weld
c.c
Size+Comment
Cutting timber board in optimum angle of 45 (30min, 60max) for bracing
b1 b2 t b2 b1 t bf d t t b d d t b AS/NZS
140x45
CRS,
L12 R3 FB1 DS TS Provide hanger to L15 behind Refer to DWG-S22-8 Detail Roof connect to wall Universal Beam (UB) ParallelChannelsFlange (PFC) Unequal(UA)Angle Equal(UA)Angle SquareSectionsHollow (SHS)
3679.1:2009 Steel Section
A butt weld is a weld between two coplanar workpieces. It has stronger load capacity than fillet weld C8 L12
Timber framed wall for his study is constructed at this stage. Framing detail and position refers to structural drawing. Wall(WT.01) timber framed is construsted with type ‘A’ bracing(1 per linear meter)
2/190x45; F7 KD pine 140x45; F16 Hyspan 310 UB 46; F16 Hyspan 2/140x45; F16 Hyspan 200x45;F16 Hyspan 200x45 F16 Hyspan 200x45; F16 Hyspan 100x6.0 SHS; Steel post 200x13 EA; Steel post 150x6 SHS;100min end bearing on chimney, 8mm cleat 150x90x8 UA 250 PFC
Steel post
c.a c.b c.c c.d c.e L9 SA.01
a
Roof System
Safety hazard must be taken prior the commencement of roof construction. Scaffold shall construct for work such as roof faming and gutter.
b Constructing roof beyond corridor
b.a b.b b.c b.d b.e b.f b.g b.h
Timber roof framing system is fixed back to sub-structure as required.
OSB fixed to the outside of timber fr Parapet next to the courtyard has also fixed a layer of timber canopy Parapets are wraped with colourbond steel flashingto match metal roofing(RF-01) with termina tion bar. Parapets are also capped with rainwater capping(RW-01).
Thermal insulation(IN-02) is located inside metal roofing.
A ventilation roof space is left in between metal roofing and OSB for water drainage. Weathertight membrane(SA-01) is layered outside OSB.
140mm internal roof thermal insula tion(IN-02) is located inbetween structure framing. Another layer of air tight mem brane is covered inside.
A 120mm depth profiled box gutter is fixed on 18mm OSB in between two parapets to fall 1:200 to east parapet sump. A 300x50mm slot for rainwater overflow to eastern wall of bedroom 4.
c Constructing roof beyond his study, courtyard and pond.
c.a c.b c.c c.d c.e
Roof frame(RB10) is fixed with vertical structure for future timber timber cladding.
Roof above courtyard has a 2 degree fall angle from south to north for discharge. Rafters and purlins are ‘z’ purlins are flxed for roof construction.
Steel post (RB4, RB6 and RB30) is fixed. Metal roofing(RF-01) with insulation(IN-02) is fixed on the top. A 3mm TK aluminium sheet for water deflection is folded into angle to close rib ends.
His study roof
d Constructing his study roof
d.a d.b d.c d.d
A layer of OSB is fixed above the structural frame (R3). Then, weatherproof membrane(SA-01) is layered above.
18mm condensation drainage zone is left above.
Anticon 55 lightduty blanket to metal deck
Scaffolding
Temporary structure used to support wor crew in construction
d.d d.e d.f
Timber cladding (CD-01) is laid at the outtermost of the roof. It is fastened to metal decking with solar PV cell clips to all ribs at 300mm CTS.
18x42mm hardwood battens fastened to roof clips. A continous vermin proof mesh is laid under timber cladding and wrapped into the gutter at the bottom of slope roof.
Caulking on backing strip RW-01
‘Z’ purlin
Parapet on packer set to fall to main roof
SA-01
Vapour permeable weatherproof membrane
RB10
Sump level
drainage zome Anticon 55 lightduty blancket
Scissor Lift
Construction device to lift up worker for safety highlevel working
Roof structural framing
Timber plate,M12nailing bolts
Timber packing M10 bolt
Cleat dropper back to PFC,1-M16 bolt
75x10m m EA cleat 190x45 ceiling joists, 6mm cleat plate, 2-M12 Bolts
Shelf angle
10mm Cleat weld to droppwe 2-M16 bolts to shelf angle
Refer to DWG-S31-1
Waterproofing Relevant Australian Standards:
AS 4654.1-2021 Waterproofing membranes for external above-ground use-Materials
AS 4654.2-2012 Waterproofing membranes for external above-ground use-Design and installation
AS 3740-2010 Waterproofing of Domestic Wet Areas.
Detail
STAGE 5
RF-02 Continous vermin proof mesh CD-02 weatherproof membrane
OSB
Gutter
a
External Wall(cladding included) & Window system & External door
External wall for his study
a.a a.b a.c a.d a.e
All external walls for his study room is W.T01. Insulation(IN-01) is positioned within structural frames. OSB(OSB-01) is fixed on the external side of structural framing.
Weatherproof membrane(SA-01) is layered outside of OSB. Airtight membrane(SA-03) is layered inside the insulation.
18mm vertical battens is left for drainage. A total 56mm gap from membrane to the outter layer of timber cladding(CD-01).
b Constructing external roof beyong his study
b.a b.b
Same thermal insulation(IN-01) as wall insulation is positioned inbetween roof joist(R3). Airtight membrane, continous from wall, cover benearth the roof insulation is laid.
c Window construction in his study
c.a c.b c.c c.d c.e c.f
Window on the north facade is marked as W.GF-06. Window on the east facade is maded as W.GF-07. Window on the south facade is marked as W.GF-08.
All three windows are inward tilt and turn(TTP).
Triple glazed unit (GL-01) with argon filling and warm edge spacers. Surrounding frame for window is concealed behind cladding.
Windows are silled by aluminium sill progile to suit reveal. Caulking on backing strip between timber sill and window frame.
External flyscreen(FSP-01) is constructed outside the window panel. 19x45mm timber frame species to match the external timber cladding. The flyscreen is not fixed into frame but concealed externally.
Window frame has 20mm sash clearance above, 5mm shadowline andn ventilation gap with vermin proof mesh behind connected from roof.
d Construction of window and external wall on the north facade of corridor
d.a d.b d.c
Window on the north facade of the corridor is marked as W.GF-11.
2 layers of fixed triple glazed panel, 3 on ground floor, 5 on first floor.
15mm thick skirting tile is fixed to mullion capping on the external side of window frame. Gypsum board(GB-01) is fixed to framing beneath the window frame.
f External surface of corridor floor
12mm TK MDF countersunk is fixed into packers. f.a
Code BL-01 BL-02
BL-04 BL-07
Legend Limestone Veneer Limestone Veneer
Limestone Blocks Self supporting Limestone Tiles
e External surface around pond Stone paving(PV-02) is laid for external wall Stone tile(TL-02) on sand cement screed on vertical wall and ground floor of water pond.
e.a e.b
Window frame W.GF-06 W.GF-07
g Masonry work is constructed BL-04
Comment External or internal wall, 10mm joint Match the appearance of BL-01, substrate by CD-10 and OSB
Block size: 100(D)x660/850(W)x 290(H)mm, 10mm joint Joints: As per BL-01, CD-10 substrate
BL-01
BL-02 BL-07
GB-01
PV-02 TL-02
STAGE
6
Airtight memberane for west facade walll
W.GF-06 W.GF-07
a
STAGE 7
Internal partitions, Rough-in service ceiling, Wall lining structures
Rough-in services installed in floors, walls and ceilings. Once electrical services positioned into service zone, an internal wall and ceiling will positioned.
a.a
100mm service zone is left for rough- in service line(P21) for his study.
a.b b Roof ceiling constructed at this stage.
An 12mm internal timber wall lining(WL-01) will be fixed in secrete nailed profile with concealed screws. Vertical internal wall is supported by horizontal timber frame at 450cc.
b.a b.b b.c
Timber cladding (CD-01) panel is fixed back to 32x42mm frame with stainless steel countersunk socket head screws.
Timber cladding is fixed along the roof frame (RB10 refers to stage5 section drawing)
Timber cladding is fixed on rafter above courtyard in a angle of 45 degree.
c Developing the construction of floor in the corridor
c.a c.b
Thermal insulation is positioned inbetween structural framing(FJ3) for firstfloor corridor. 19mm thich, 100mm (visible) width timber floor is nailed into substrate OSB board and full polyurethane glue bed.
Thermal insulation(IN-04) in laid above groundfloor slab of the corridor. Polythene separation layer in laid between insulation and screed. Reinforced screed(SC-01) is poured above the insulation as the secondary groundfloor slab. 30mm layer of sand cement screed tile bed is poured above. Stone floor tile is laid on sand cement screed in a size of 300mmWx600L
Electrical wire
P21-10A double (DSSO) for main supply
Horizontal noggings to suit hardwood wall lining Vertical service battens
Indoor corridor floor
Reinforced screed and cement is poured on floor
Electrical service
Prepering for rough-in
Finishing trades, Joinery, Appliances
Joinery is measured and customized off-site in a factory. Joinery is delivered onsite and installed into position.
b Gap between tiles shall screed for resiliance and durability. Internal wall and ceiling is painted with finished painting.
c Basic servies including air condition, heating system and exhausted fans are installed accordingly.Furnitures and shelvs are placed in his study.
d Switches and powerpoints are installed in position(refers to Electrical Service drawing)
e Adjustable louvres are installed and fixed on roof beyond His study
Adjustable Louvre His study external finishing
Timber floor is laid over His study room.
19mm thickness Hydrowood Eucalyptus
Timber board has a visible width of 100mm, but in random length.
Timber board is substrate by OSB board(reders to stage7 section)
Timber board painted with timber finish (PA-03)
Timber floor finish(PA-03)
Colour of timber floor finish is clear with the gloss level of Satin.
Coating quantity in accordance with manufaturers ‘Product Data Sheet’
Painting timber finishPA-09 finish painted on timber cladding wall in 2 coats.
TF-01
Roof beam RB7
70 115O/Athick 9mm OSB 700x70xposi strut Blackbutt cladding to match CD-01 19 39.269
755Louvre 45 665 spacing Drip edge Detail Louvre section
450 R.L.
R.L. 38.600 755-8xCladdingboards 450 LVL
Screed gap between tile
Screeding between tile to enhence the resiliance and durability of brick veneer. Finish with NIL
Cleaning courtyard and garden space
Construction waste and scraps shall remove from the garden as well and deliver off site
STAGE 8
a
f Excess material are cleaned for the whole house and garden space. Waste discarded from the construction space.
90 665
Refer to DWG-CD134 BL-01 CD-01
Cleaning
All scarps remove from inside and cleaning of floor
Timber floor(TF-01)
Double pit sediment &CPT filtration device
Maintenance access to surface
A
Soil Report
A soil testing and report shall complete by geotechnical engineer prior of construction to identify the soil type.
Class P/M
Class P=Problem Including soft soils, such as soft clay or loose sand; reactive substance in soil; moisture soil condition etc.
Class M=Moderately Reactive Moderately reactive with moderate ground movement around 20-40mm
Pond overflow to civil drainage
Temporary site office
100Stormwater pipe from above
100 Back water pipe from above 100 greasy pipe from above
FW from above 100 overflow penetration 100Water closet from above
100stormwater pipe from above
Soil stockpile
Stockpile of the soil from excavation
Safety cone Safety site
boundary
Concrete mixer truck Concrete components inside to ensure concrete is fresh for pouring
Waste and demolish Waste dirt and demolish scrap is left on the side of construction area for delivery truck to transport off the site
Compact fills
Compact fills as substructure as per NCC 3.2.2.1 Excavation for footing compliance
3 2
STAGE 1 Stie Preperation &
Footing
Slab formwork
Steel supportance underneath
Typical Detail Flexible service pipe in slab
CB3
Service pipe
Pipe work from below is capped to avoid foreign substance
500 400
CB1 CB1
1200 400 567
CB1 CB2
All service pipe shall wrapped with approved foam laggine
Slab fabric is cut away to allow for service pipe penetration. Additional 4-N12 bars, 600mm long layered one to each side of pipe work
Refer to DWG-S12
Side formwork
Bar chair spacing 0.9-1.0m intervals
Placing tendon and tied to bar chair
Steel bar is capped for safety
CB1 CB2
Pouring concrete slab Beams and slab shall be poured together in one operation
STAGE 2 Ground Floor Slab
A 3 2
FD WT.02 WT.01 WT.06 WT.02 FB30 RB7 STAGE 3 Vertical Structures Above Ground SA.01 SA.03 C1 C8 C1 DS DS DS L10 DCJ DCJ C1 C2 C3 Denotes doweled construction joint 100x6.0 SHS steel post C2 DS TS C2 DS DS DS DS DS DS DS DS L14 L13 L14 L12 DS DS DS DP DP L9 Slab formwork Steel supportance underneath GFJ1 GFJ1 2-FJ4 2-FJ4 FJ3 Intermediate ground oor in His study Plan 1:50 3 2 A 2 200 100 30 200 100 30 350 Slab edge Timber mullion 16mm thick base plate 6 CFW fixed to colum, 3-M16 “chemset” anchors 100min Detail C7 Refer to DWG-S12 Delivery truck Timber framing and steel profile transfered on site
Mark
Framing
Size+Comment
140x45; MGP10; Floor joist 140x45; MGP10; Floor joist 100x36; MGP10;F16 Hyspan treated; Balcony joist 2/190x45; F16 Hyspan 300x63; F16 Hyspan 2/140x45; F16 Hyspan 2/190x45; F16 Hyspan; Cantilever to support DS over 1/240x45 & 1/240x35 F16 Hyspan 2/190x45 F16 Hyspan 2/240x45 F16 Hyspan 140x45; F7 KD pine; Ceiling joist 2/140x45; F16 Hyspan 2/130x36; F16 Hyspan 150x100x10 UA 200x45 F16 Hyspan 250 PFC 250 PFC
Pryda FT300; MPG10; Floor joist 130x36; F16 Hyspan
Double 45 wide studs(90/140) Triple 45 wide studs(90/140) 50x3.0CHS; Steel dropper
STAGE 4 Intermediate Floor Structure
CJ1 TB7 TB8 L1 L6 L16 L17 Floor
FT1
Column DS TS C9
FJ2 FJ3 FJ6 FB2 FB3 FB5 FB8 FB29 FB30 FB31
Joist
WP1
Legend A 3 2 FJ6 FB31FB27 TB8 TB7 C9 WT.02 WT.01 1-M12 Masonry anchors(underdevelopment) 2/140x45 hyspan top plate L10 Section Intermediate floor framing Refer to DWG-S23-2 Section 1 Section 1 L1 L17 L16 WT.01 WP1 TB8 TB7 TB7 TB7 TB8 TB8 WP1 L6 CJ1 FB27 FB31 FJ6 DS/0ver C9 C9 C9 2-FT1 FB2 DS/0ver FB8 FJ2 WT.02 FB1 FB5 FJ2 L16 FB2 DP/Under WT.01 TS/Under DS/Over DS/Under DS/Under DS/Under DS/Under FJ2 FB30 DP DP FJ3 FJ3 FJ3 FJ3 FJ3 FJ3 FJ3 FJ3 FJ3 FB6 FJ3 FJ3 FJ3 FJ3 FB6 FB6 FB3 FB6 FJ3 FB3
Timber framing system fixed back to sub-structure A 3
CD-02
585mm widthGutter
SA-01
650 Timber
Soaker flashing to SKL-01
Gutter to discharge into pond
58 degree fall 17 degree fall
1:200 Roof capping 30x3 thick aluminium angle fixed to top of cladding board Capped bent ribbed roof Vapour permeable weathertight membrane
2300 Refer to DWG-AR376
400 Sump
His study Roof struction Plan 1:50
STAGE 5 Roof system
2
SKL-01
Ridge line 50mm minimum dutter depth
cladding
Timber stud profiles
Timber studs, rafters, joints and beams are transported on site.
STAGE 6 External Wall & Window & Door Perspective 1 Refer to DWG-CD31 Perspective 1
A 3 2
SKL-06 BL-02 W.GF-11 W.GF-10
Refer to DWG-AR383 Detail Window Frame Refer to DWG-AR414-2 Detail Window Frame Slab formwork Steel supportance underneath
17degree fall 2290 580 GL-02 SKL-01 820 685 GL-02 SKL-06 2degree fall
SKL-01
W.L1-01
A 3 2 STAGE 7 Internal partitions, Rough-in service ceiling, Wall lining structures W.T25 W.T25 WL-01 TF-03 IN-06 TF-01 TF-02 OSB Screed Waterproof membrane TL-03 IN-04 SC-01 TL-01 FB3 FJ3 Plasterboard ceiling
Timber decking(TF-03)
Timber decking is laid on balcony floor
Timber board has 100mm width and 19mm thickness.
Timber decking has painted PA-12 finish.
Paint Finish(PA-12)
Paint finish for external timber cladding 3 layers of coat on deck
Balcony
Bedroom 2
Ensuite 2
A 3 2
His study
WIR
Stone paving is installed and organized in the courtyard
Ensuite 1
STAGE 8 Finishing trades, Joinery, Appliances