LIST OF DRAWINGS
MORRIS INSURANCE HEADQUARTERS
SHEET #
DRAWINGS
A0.1 A1.1 A2.1 A2.2 A2.3 A2.4 A3.1 A3.2 A4.1 A4.2 A5.1 A6.1 A6.2 S2.1 S2.2
COVER PAGE SITE PLAN MAIN FLOOR PLAN SECOND FLOOR PLAN MAIN FLOOR RCP SECOND FLOOR RCP E/N BUILDING ELEVATIONS W/S BUILDING ELEVATIONS BUILDING SECTIONS AA,BB BUILDING SECTION CC/SCHEDULES WALL SECTIONS PLAN DETAILS SECTION DETAILS FRAMING PLAN SECOND FLOOR FRAMING PLAN ROOF
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
CONSTRUCTION SCHEDULE W1 EXTERIOR WALL - 1st FLOOR - CAVITY WALL ON FRAMED GWB 90mm BRICK VENEER 25mm AIR SPACE 75mm RIGID INSULATION C/W MECHANICAL FASTENERS PEEL AND STICK AIR/VAPOUR BARRIER OVER PRIMED SURFACE 13mm EXTERIOR GRADE GYPSUM 92mm STEEL STUDS @ 400mm O.C. 16mm GYPSUM BOARD
W2 STAIRWELL WALLS - 1st FLOOR - CAVITY WALL ON CONCRETE BLOCK 90mm BRICK VENEER 25mm AIR SPACE 75mm RIGID INSULATION C/W MECHANICAL FASTENERS THERMOFUSIBLE AIR/VAPOUR BARRIER 200mm (nominal) CONCRETE BLOCK C/W JOINT REINFORCING/
W3 EXTERIOR WALL - 2nd FLOOR - EIFS STUCCO SYSTEM ON FRAMED GWB 5mm ACRYLIC STUCCO 125mm RIGID INSULATION PEEL AND STICK AIR/VAPOUR BARRIER OVER PRIMED SURFACE 13mm EXTERIOR GRADE GYPSUM SHEATHING 92mm STEEL STUDS @ 400mm O.C. 16mm GYPSUM BOARD
W4 STAIRWELL WALLS - 2nd FLOOR - EIFS STUCCO SYSTEM ON CONCRETE BLOCK 5mm ACRYLIC STUCCO 125mm RIGID INSULATION THERMOFUSIBLE AIR/VAPOUR BARRIER 200mm (nominal) CONCRETE BLOCK
P1 PARTITION WALL CONSTRUCTION (ALL NON-MARKED WALLS) 16mm GYPSUM BOARD 92mm STEEL STUDS @ 400mm O.C. 16mm GYPSUM BOARD
P5 COLUMN ENCASEMENT ASSEMBLY 2x16mm GYPSUM BOARD 42mm STEEL STUDS
No.
Description
Date
P6 2-HOUR FIRE-RATED PARTITION WALL CONSTRUCTION 2x16mm GYPSUM BOARD 92mm STEEL STUDS 2x16mm GYPSUM BOARD
P7 REINFORCED CAST IN PLACE CONCRETE ELEVATOR WELL CONSTRUCTION 16mm GYPSUM BOARD 22mm STEEL FURRING CHANNELS @ 400mm O.C. 190mm CAST IN PLACE CONCRETE
P8 ALTERNATE COLUMN ENCASEMENT ASSEMBLY 1x16mm GYPSUM BOARD 42mm STEEL STUDS
PT1 PARAPET CONSTRUCTION - EIFS STUCCO SYSTEM ON FRAMED GWB 5mm ACRYLIC STUCCO 125mm RIGID INSULATION PEEL AND STICK AIR/VAPOUR BARRIER OVER PRIMED SURFACE 13mm EXTERIOR GRADE GYPSUM SHEATHING 92mm STEEL STUDS @ 400mm O.C. 16mm GYPSUM BOARD PEEL AND STICK AIR/VAPOUR BARRIER OVER PRIMED SURFACE 69mm RIGID INSULATION
R1 ROOF CONSTRUCTION 5mm EPDM ROOFING MEMBRANE 120mm RIGID INSULATION VAPOUR BARRIER 13mm EXTERIOR GRADE GYPSUM SHEATHING 38mm CELLULAR STEEL DECK
MORRIS INSURANCE HEADQUARTERS COVER PAGE
P2 PLUMBING PARTITION WALL CONSTRUCTION (300mm WIDE) 16mm GYPSUM BOARD 92mm STEEL STUDS @ 400mm O.C. 84mm VOID SPACE 92mm STEEL STUDS @ 400mm O.C. 16mm GYPSUM BOARD
F1 MAIN FLOOR CONSTRUCTION 100mm REINFORCED CAST IN PLACE CONCRETE
P3 CONCRETE BLOCK PARTITION WALL CONSTRUCTION 16mm GYPSUM BOARD 22mm STEEL FURRING CHANNELS @ 400mm O.C. 200mm (nominal) CONCRETE BLOCK C/W JOINT REINFORCING
F2 SECOND FLOOR CONSTRUCTION 62mm CONCRETE TOPPING 38mm CELLULAR STEEL DECK
Project Number
0001
Date Drawn by
26/04/2019 JOSHUA PERRAS
Checked by
ANDRE LUCENA
A0.1 P4 REINFORCED ELEVATOR WELL PARTITION 190mm CAST IN PLACE CONCRETE
K1 KAWNEER SYSTEM CURTAIN WALL 150x50mm ALUMINUM FRAME 25mm DOUBLE-GLAZING PANEL
Scale
1 : 20
55000
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
10000
9000
-150
1000 (TYP.)
No.
Description
Date
BUILDING
39000
9000
4800 x2400 PARKING STALL
4800 x4800 PARKING STALL
PROPERTY LINE GRASS
MORRIS INSURANCE HEADQUARTERS
3000
-300
6000
SITE-HARDCORE
1000 1000
SITE PLAN CONCRETE
Project Number
0001
Date Drawn by
6000
26/04/2019 JOSHUA PERRAS
Checked by
ANDRE LUCENA
39000
A1.1 1 A1.1
SITE PLAN 1 : 100
Scale
1 : 100
A
2
1
A4.1
A4.1
B
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
C
D
E
F
20920
4200
2895
5410
W1
1-
2-
W2
A6.1 ---
W1
600
1
A5.1
D102B
A6.1 ---
3655
3
D1NSB
4760
NORTH STAIR
2
W1
P2
WASHROOM
VESTIBULE
101
102
D1NSA
1945
1NS
UP
3 P1
D101
108
OFFICE
P3
103
D102A
2000
OFFICE
4415
RECEPTION
P1
110
1 A4.2
1
HALL
P1
A4.2
1300
109 P1
P1
2970
No.
Date
D103
P7
1648
1016
4 A6.1
2210
P1
D104 1300
D105
D107
14160
D108
4
Description
4415
D106A
P4
OFFICE
D1SS
SOUTH STAIR
OFFICE
105
1SS
107
OFFICE P1
104
UP
3
VESTIBULE
A6.1
106
1945
5 1
P3
A5.1
D106B
840
6 W2
7 W1
1800
2000
5160
2105
MORRIS INSURANCE HEADQUARTERS
2 A5.1
2500
MAIN FLOOR PLAN Project Number
2
1
A4.1
A4.1
0001
Date Drawn by
26/04/2019 JOSHUA PERRAS
Checked by
1 A2.1
MAIN FLOOR PLAN
Checker
A2.1
1 : 50
Scale
1 : 50
A
2
1
A4.1
A4.1
B
C
D
E
F
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
20920 4760
4200
2895
5410
3655
3 A5.1
W4 W3
1
600
G2 DN
NORTH STAIR
2 W3 P2
WASHROOM
MEACHANICAL ROOM
201
202
3
2NS D2NS
1945
P3
2000
P6
P1
D202
D201 4415
P3
P6
KITCHEN 203
OFFICE 205
1
1
A4.2
HALL 2
P1
P1
2700
P6
A4.2
P1
206
No.
Description
Date
1145
D205
4
14160
D203
D204
P4
4415
P1
OFFICE SOUTH STAIR
D2SS
204
2SS P1
DN
5 1945
G1 1
P3
A5.1
W3
840
6 7 W3
W3 2
W4
A5.1
MORRIS INSURANCE HEADQUARTERS SECOND FLOOR PLAN
2 A4.1 1
Project Number
0001
A4.1
Date Drawn by
26/04/2019 JOSHUA PERRAS
Checked by
1 A2.2
ANDRE LUCENA
SECOND FLOOR PLAN
A2.2
1 : 50
Scale
1 : 50
A
B
C
D
E
F
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
1 991
1950
OPEN TO ABOVE
1007
2600
2340
969
2
662
668
2600
2600
1049
1158
2000
3
1244
2600
2600
4
No.
Description
Date
1750
OPEN TO ABOVE
690
2600
1244
805
2600 2600
OPEN TO ABOVE
1033
5
2000
2600
6 7
CEILING SCHEDULE
1 A2.3
MAIN FLOOR RCP
MORRIS INSURANCE HEADQUARTERS MAIN FLOOR RCP
1200x600 T-BAR SYSTEM
1 : 50
Project Number
0001
Date
26/04/2019
GYPSUM ON METAL STUD
Drawn by
JOSHUA PERRAS
Checked by TROFFER LIGHT - PARABOLIC RECTANGULA 2 LAMP - 120V
DOWNLIGHT - RECESSED CAN 152mm INCANDESCENT 120V
ANDRE LUCENA
A2.3 Scale
1 : 50
A
B
C
D
E
F
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
1120
622
1 2600
1950
625
1276
603
2600
2600
2000
2340
991
1240
1244
622
3
2007
1893
717
635
2
2600
1244
735
2000
1001
1158
1007
2600
630
2600
1317
2600
4 OPEN TO ABOVE
Description
Date
368
No.
2600
2600
1244
643
2000
614
5
2000
2600
368
6
7
CEILING SCHEDULE
1 A2.4
SECOND FLOOR RCP 1 : 50
1200x600 T-BAR SYSTEM
MORRIS INSURANCE HEADQUARTERS SECOND FLOOR RCP
GYPSUM ON METAL STUD
Project Number
0001
Date TROFFER LIGHT - PARABOLIC RECTANGULA 2 LAMP - 120V
26/04/2019
Drawn by
Author
Checked by DOWNLIGHT - RECESSED CAN 152mm INCANDESCENT 120V
ANDRE LUCENA
A2.4 Scale
1 : 50
7
6
5
4
3
2
1
T.O. PARAPET
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
108702 T.O. ROOF DECK
600
2000
846
108102
7410
SECOND FLOOR SLAB
2600
1364
103964
MAIN FLOOR SLAB
1 A3.1
1065
EAST ELEVATION
1065
1065
1 : 50
F
1065
310
1065
1065
1065
100000
1065
No.
8830
E
D
C
B
Description
Date
A
T.O. PARAPET 108702 T.O. ROOF DECK 108102
SECOND FLOOR SLAB
MORRIS INSURANCE HEADQUARTERS
103964
E/N BUILDING ELEVATIONS Project Number
0001
Date Drawn by MAIN FLOOR SLAB
26/04/2019 JOSHUA PERRAS
Checked by
ANDRE LUCENA
100000
A3.1 2 A3.1
NORTH ELEVATION 1 : 50
Scale
1 : 50
1
2
3
4
5
6
7
T.O. PARAPET 108702 T.O. ROOF DECK
SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
600
2000
846
108102
7410
SECOND FLOOR SLAB
2600
1364
103964
MAIN FLOOR SLAB 100000 1065
1 A3.2
1065
1065
1065
310
1065
1065
1065
1065
8830
WEST ELEVATION
No.
Description
Date
1 : 50
A
B
C
D
E
F
T.O. PARAPET 108702 T.O. ROOF DECK
600
2000
846
108102
7410
SECOND FLOOR SLAB
1364
103964
MORRIS INSURANCE HEADQUARTERS
2600
W/S BUILDING ELEVATIONS Project Number
0001
Date
26/04/2019
MAIN FLOOR SLAB 1000
1000
1210
1210
320
1210
1210
100000
Drawn by
JOSHUA PERRAS
Checked by
2 A3.2
ANDRE LUCENA
A3.2
SOUTH ELEVATION 1 : 50
Scale
1 : 50
7
6
5
4
3
2
1
T.O. EL RF DK 109602 T.O. PARAPET
R1
108702 T.O. ROOF DECK
SCHOOL OF APPLIED BUILDING SCIENCE
108102
ARCHITECTURAL TECHNOLOGY
2A6.2 ---
W3
W3
P6
3 A6.2
R1
F2
SECOND FLOOR SLAB 103964 4 A6.2
W1 P1
P1
W1
MAIN FLOOR SLAB 100000 B.O. FOUNDATION 99400 B.O. ELEV WELL 98800
1 A4.1
7
Section AA
6
5
No. R1
4
3
2
Description
Date
1
1 : 50
T.O. EL RF DK 109602
1R1
A6.2 ---
T.O. PARAPET PT1
108702 T.O. ROOF DECK 108102
W4
P4
P7
F2
W3
F2
SECOND FLOOR SLAB 103964
W2
MORRIS INSURANCE HEADQUARTERS BUILDING SECTIONS AA,BB
W1
Project Number
MAIN FLOOR SLAB 100000 B.O. FOUNDATION 99400 B.O. ELEV WELL
0001
Date Drawn by
26/04/2019 JOSHUA PERRAS
Checked by
ANDRE LUCENA
98800
A4.1 2 A4.1
Section BB 1 : 50
Scale
1 : 50
A
B
C
D
E
F SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
T.O. EL RF DK 109602 T.O. PARAPET 108702 T.O. ROOF DECK
PT1
108102
W3
P1
W3
P1
P1
K1
SECOND FLOOR SLAB 103964
P1
W1
P1 W1
No.
Description
Date
MAIN FLOOR SLAB 100000 B.O. FOUNDATION 99400 B.O. ELEV WELL 98800
1 A4.2
Section C 1 : 50
ROOM SCHEDULE
DOOR SCHEDULE
NUMBE R
NAME
AREA
1NS 1SS 2NS 2SS 101 102 103 104 105 106 107 108 109 110 201 202 203 204 205 206
NORTH STAIR SOUTH STAIR NORTH STAIR SOUTH STAIR WASHROOM VESTIBULE OFFICE OFFICE OFFICE VESTIBULE OFFICE OFFICE HALL RECEPTION WASHROOM MEACHANICAL ROOM KITCHEN OFFICE OFFICE HALL 2
13 m² 12 m² 13 m² 12 m² 19 m² 10 m² 28 m² 32 m² 25 m² 12 m² 41 m² 31 m² 20 m² 19 m² 19 m² 10 m² 11 m² 79 m² 72 m² 48 m²
MARK D1NSA D1NSB D1SS D2NS D2SS D101 D102A D102B D103 D104 D105 D106A D106B D107 D108 D201 D202 D203 D204 D205
TYPE MARK D2 D2 D2 D2 D2 D4 D1 D1 D3 D3 D3 D1 D1 D3 D3 D4 D4 D4 D3 D3
FAMILY M_Single-Flush M_Single-Flush M_Single-Flush M_Single-Flush M_Single-Flush M_Single-Flush M_Door-Double-Glass M_Door-Double-Glass M_Single-Flush M_Single-Flush M_Single-Flush M_Door-Double-Glass M_Door-Double-Glass M_Single-Flush M_Single-Flush M_Single-Flush M_Single-Flush M_Single-Flush M_Single-Flush M_Single-Flush
HEAD WIDTH HEIGHT FINISH 915 915 915 915 915 762 1700 1700 813 813 813 1700 1700 813 813 762 762 762 813 813
2134 2134 2134 2134 2134 2134 2100 2100 2134 2134 2134 2100 2100 2134 2134 2134 2134 2134 2134 2134
FRAME MATERIAL
WINDOW SCHEDULE Comments FIRE RESISTENCE RATING OF 45MIN FIRE RESISTENCE RATING OF 45MIN FIRE RESISTENCE RATING OF 45MIN FIRE RESISTENCE RATING OF 45MIN FIRE RESISTENCE RATING OF 45MIN DOUBLE DOOR DOUBLE LEAF GLAZING DOUBLE DOOR DOUBLE LEAF GLAZING
TYPE MARK G1 G2
FAMILY M_Fixed with Trim Louver_window_family_object_4856
SILL WIDTH HEIGHT HEIGHT COUNT 915 914
1220 1524
915 915
1 1
MORRIS INSURANCE HEADQUARTERS BUILDING SECTION CC/SCHEDULES Project Number
DOUBLE DOOR DOUBLE LEAF GLAZING DOUBLE DOOR DOUBLE LEAF GLAZING
0001
Date Drawn by
26/04/2019 JOSHUA PERRAS
FIRE RESISTENCE RATING OF 2HR
Checked by
ANDRE LUCENA
A4.2 Scale
1 : 50
A
6
2
1 SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
T.O. PARAPET 108702
R1
R1
T.O. PARAPET
T.O. PARAPET
108702
108702 R1
PT1
PT1
PT1
T.O. ROOF DECK
T.O. ROOF DECK
T.O. ROOF DECK
108102
108102
108102
C1
C1
C2
K1
No.
W4
Description
Date
W3 F2 F2
SECOND FLOOR SLAB
SECOND FLOOR SLAB
SECOND FLOOR SLAB
103964
103964
103964
C1
C1
MORRIS INSURANCE HEADQUARTERS
W2 W1
F1
F1
F1
WALL SECTIONS MAIN FLOOR SLAB
MAIN FLOOR SLAB
MAIN FLOOR SLAB
100000
100000
100000
Project Number
0001
Date Drawn by
26/04/2019 JOSHUA PERRAS
Checked by
1 A5.1
WALL SECTION 1 : 25
2 A5.1
CURTAIN WALL SECTION 1 : 25
3 A5.1
STAIR WALL SECTION
ANDRE LUCENA
A5.1
1 : 25
Scale
1 : 25
B
E
SCHOOL OF APPLIED BUILDING SCIENCE
W1
ARCHITECTURAL TECHNOLOGY
CAVITTY WALL
240
W2
1
1 W1
600
W1
P5 240
STEEL COLUMN HSS 152x152x9.5
STAIRWELL WALLS
2
2
PLUMBING WALL P3
No. 1 A6.1
PLAN DETAIL 1
2
1 : 10
A6.1
Description
Date
PLAN DETAIL 2 1 : 10
F
F
1065
K1
MORRIS INSURANCE HEADQUARTERS
K1 P1
P5
ALUMINUM CURTAIN WALL MULLION 150x50mm
310
ALUMINUM CURTAIN WALL MULLION 150x50mm
5
4
PLAN DETAILS
ALUMINUM BRAKESHAPE STEEL COLUMN HSS 152.4x152.4x9.5
290
Project Number
0001
W1
Date Drawn by
240
26/04/2019 JOSHUA PERRAS
Checked by
3 A6.1
PLAN DETAIL 3 1 : 10
4 A6.1
PLAN DETAIL 4
ANDRE LUCENA
A6.1
1 : 10
Scale
1 : 10
2
7
PARAPET CAP
PARAPET CAP
SCHOOL OF APPLIED BUILDING SCIENCE T.O. PARAPET
ARCHITECTURAL TECHNOLOGY
T.O. PARAPET
108702
108702
PT1 PT1
R1
R1
T.O. ROOF DECK
T.O. ROOF DECK 108102
692
108102
W4
STEEL BEAM W310x32.7
W3
REINFORCED BOND BEAM LINTEL BLOCK
240
90
K1
1 A6.2
SECTION DETAIL 1
2
1 : 10
A6.2
No.
SECTION DETAIL 2
Description
Date
1 : 10
6 2
1
PARAPET CAP
W3
PT1 R1
F2
SECOND FLOOR SLAB
SECOND FLOOR SLAB 103964 364
87
364
87
103964
MORRIS INSURANCE HEADQUARTERS
CHANNEL C150x15.6
SECTION DETAILS Project Number
STEEL BEAM W310x32.7
0001
240
Date
W1
26/04/2019
W1
Drawn by
JOSHUA PERRAS
Checked by
3 A6.2
SECTION DETAIL 3 1 : 10
4 A6.2
ANDRE LUCENA
A6.2
SECTION DETAIL 4 1 : 10
Scale
1 : 10
A
B
C
D
E
F SCHOOL OF APPLIED BUILDING SCIENCE ARCHITECTURAL TECHNOLOGY
20920
4760
2895
5410
3655
C150x16
600
1
4200
1945
2
OWSJ - 16K3 (TYP.)
No.
Description
Date
4415
4
14160
4415
3
C150x16
C150x16
1945
5
840
6 7
MORRIS INSURANCE HEADQUARTERS FRAMING PLAN SECOND FLOOR
1 S2.1
SECOND FLOOR FRAMING PLAN
Project Number
0001
1 : 50
Date Drawn by
26/04/2019 JOSHUA PERRAS
Checked by
ANDRE LUCENA
S2.1 Scale
1 : 50
SCHOOL OF APPLIED BUILDING SCIENCE
A
B
C
D
E
ARCHITECTURAL TECHNOLOGY
F
20920
4760
4200
2895
5410
3655
600
1
1945
C150x16
2
OWSJ - 12K3 (TYP.)
4415
3
Date
1945
5
840
6 7
OWSJ - 12K3 (TYP.)
4415
C150x16
4
Description
14160
No.
MORRIS INSURANCE HEADQUARTERS FRAMING PLAN ROOF Project Number
1 S2.2
0001
ROOF FRAMING PLAN 1 : 50
Date Drawn by
26/04/2019 JOSHUA PERRAS
Checked by
ANDRE LUCENA
S2.2 Scale
1 : 50