P R O J E C T S TAT U S
05 14 project status
Athabasca Region Industrial Heartland Region Cold Lake Region
Sourced from Alberta regulators and corporate disclosures. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.
Peace River Region Northwestern Saskatchewan
navigator.oilsandsreview.com For more detailed project data, visit oilsandsreview.com. To explore oilsands projects using our interactive web tool, visit the Canadian Oilsands Navigator.
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
Horizon
Updated: Mar 2014
Canadian Natural says that Horizon achieved strong and reliable operating performance for all of 2013. The 2013 fourth-quarter production volumes of 112,273 barrels per day represents a 35 per cent increase from 2012 fourth-quarter levels, which the company says indicates a stepchange in safe, steady and reliable production. The overall Phase 2/3 expansion is 34 per cent physcially complete, and projects under construction continue to trend at or below cost estimates. 135,000
2008
Operating
5,000
2014
Construction
Phase 2A
12,000
2015
Construction
Phase 2B
45,000
2016
Construction
Phase 3
80,000
2017
Construction
Reliability - Tranche 2
Kearl
COLD LAKE REGION
NEW EXPORT PIPELINES
Phase 1
110,000
2013
Operating
Phase 2
110,000
2015
Construction
Phase 3
80,000
2020
Approved
Phase 4 Debottleneck
45,000
TBD
Phase 1
Approved
Jackpine 100,000
2010
Operating
Phase 1B
100,000
TBD
Approved
Expansion
100,000
2017
Muskeg River
START-UP
Phase 1
TBD
On Hold
Base Operations
Updated: Feb 2014
Suncor says that during the fourth quarter, maintenance was completed at its Upgrader 2 vacuum tower and related units. The company says that hot bitumen infrastructure commissioned in the third quarter of 2013 has increased the takeaway capacity of bitumen and unlocked additional mining production.
Updated: Feb 2014 Operating Operating
TBD
Construction
Centrifuge Tailings Management
TBD
Aurora South Train 1
100,000
2016
Approved
Aurora South Train 2
100,000
2018
Approved
TBD
2023
Announced
Mildred Lake Mine Extension (MLX) Teck Resources Limited Frontier
Updated: Feb 2014
The Canadian Environmental Assessment Agency estimates the federal review schedule for the project application to be approximately two years, so 2015 would be the earliest approval would be granted. Teck says that an exploration program is planned at Frontier in the winter of 2014 to provide additional data to support the regulatory review process and ongoing engineering work. Phase 1
74,600
2021
Application
Phase 2
84,000
2024
Application
Phase 3
79,300
2027
Application
Phase 4 Equinox
39,400
2030
Application
Total E&P Canada Ltd. Joslyn North Mine
Updated: Mar 2013
Project partner Suncor Energy says an updated timing for the Joslyn sanction decision will be made available when it is ready. Phase 1
100,000
2021
Approved
NORTH ATHABASCA REGION — IN SITU Athabasca Oil Corporation
100,000
Application
2006
•
Phase 2
TBD
1978
Approved
Suncor Energy Inc.
120,000
116,300
Operating
On Hold
Approved Updated: May 2012
290,700
TBD
TBD
Construction
Stage 3 Expansion
2002
100,000
TBD
Base Mine Stage 1 & 2 Expansion
115,000
Phase 1
2017
20,000
Mildred Lake/Aurora
155,000
Shell has informed regulators that it is indefinitely halting work on the Pierre River project. The company has asked that the regulatory approval process be suspended.
160,000
Alberta has issued the final terms of reference for Syncrude’s MLX project.
Expansion & Debottlenecking
Updated: Feb 2014
Updated: Feb 2014
Syncrude Canada Ltd.
Commercial
Pierre River
REGULATORY STATUS
Suncor considers Voyageur South to be a “longer-term” project and has not confirmed a start-up date.
Approved Updated: Mar 2014
Minority partner Marathon Oil Corporation says its income from the Athabasca Oil Sands Project was significantly lower in the fourth quarter of 2013 compared to the third quarter of 2013, primarily as a result of lower price realizations.
Birch
Updated: Mar 2014
Athabasca will be reducing its workforce by 15 per cent. The layoffs, focused primarily in its Calgary office, will largely affect employees directly or indirectly tied to projects that are not being funded in the near term. Phase 1
12,000
TBD
Dover West Carbonates (Leduc)
Announced Updated: Dec 2013
A fourth production cycle for the TAGD pilot test was scheduled for the fourth quarter of 2013. Athabasca had been encouraged by results so far. Phase 1 Demonstration
6,000
2016
Phase 2 Demonstration
6,000
TBD
Dover West Sands & Clastics
Approved Application Updated: Nov 2013
Athabasca Oil Corporation is awaiting regulatory approval for the Dover West Sands Phase 1. Phase 1
12,000
2016
Application
Phase 2
35,000
2019
Announced
Phase 3
35,000
2020
Announced
Operating
Phase 4
35,000
2022
Announced
Operating
Phase 5
35,000
2024
Announced
294,000
1967
Operating
4,000
2007
Operating
Millennium Debottlenecking
23,000
2008
North Steepbank Extension
180,000
2012
OILSANDS REVIEW | MAY 2014
NEW INFORMATION THIS MONTH
Voyageur South
Updated: Dec 2013
Phase 1A
Steepbank Debottleneck Phase 3
CAPACITY
Debottleneck
Shell Albian Sands
Millennium Mine
•
Suncor says that project activities in 2014 are expected to focus on the completion of detailed engineering, the procurement across all areas of the project and the construction of mine and extraction infrastructure including pilings and foundations.
Updated: Feb 2014
Imperial Oil says that Kearl gross bitumen production continues to ramp up. Production was impacted during the fourth quarter by harsh winter weather and equipment reliability issues that are being addressed. Production rates of 100,000 barrels per day have been reached, and ongoing activities to stabilize performance at these higher levels are progressing. The Kearl expansion project was 72 per cent complete at year-end and remains on target for a 2015 start-up.
32
INDUSTRIAL HEARTLAND REGION
CURRENT PROJECT
Imperial Oil Limited
•
SOUTH ATHABASCA REGION
Fort Hills
Canadian Natural Resources Limited
Phase 1
SASKATCHEWAN REGION
PEACE RIVER REGION
NORTH ATHABASCA REGION — MINING •
NORTH ATHABASCA REGION
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
Terre de Grace
10,000
TBD
Dover
Approved
Updated: Feb 2014
Brion Energy and the Fort McKay First Nation have reached an agreement regarding the Dover project, and all objections to the Alberta Energy Regulator’s approval have been removed. Dover North Phase 1
50,000
2016
Approved
Dover North Phase 2
50,000
2018
Approved
Dover South Phase 3
50,000
2021
Approved
Dover South Phase 4
50,000
2023
Approved
Dover South Phase 5
50,000
2025
MacKay River
Approved
35,000
2015
40,000
2018
Approved
40,000
2020
Approved
Phase 4
35,000
2022
Approved
6,000
2017
Application
Phase 2
6,000
TBD
Application
Saleski
Updated: May 2013
Carbonate Pilot
3,000
2017
Application
Sunrise
Updated: Feb 2014
Husky says that Sunrise was 85 per cent complete at the end of the year and is advancing as planned toward start-up in the second half of 2014. Initial engineering is underway for the next phase of the project. Phase 1
60,000
2014
Construction
Phase 2A
70,000
2018
Approved
Phase 2B
70,000
2020
Approved
Imperial Oil Limited Aspen
Updated: Feb 2014
Alberta has issued the final terms of reference for Imperial’s Aspen project.
Canadian Natural Resources Limited Birch Mountain
Updated: Dec 2013
Canadian Natural says Birch is in the planning stages. Phase 1
60,000
2019
Announced
Phase 2
60,000
2023
Announced
Cenovus Energy Inc. East McMurray
Updated: Dec 2013
Cenovus says this project remains part of its portfolio of long-term development opportunities. 30,000
TBD
Steepbank
Announced Updated: Dec 2013
Cenovus says this project remains part of its portfolio of long-term development opportunities. 30,000
TBD
Telephone Lake
Announced Updated: Feb 2014
Cenovus says a dewatering pilot project designed to remove an underground layer of non-potable water sitting on top of the oilsands deposit was successfully concluded during the fourth quarter of 2013. Approximately 70 per cent of the top water was removed during the pilot and replaced with compressed air. Regulatory approval for the Telephone Lake project is anticipated in the second quarter of 2014. Phase A
45,000
TBD
Application
Phase B
45,000
TBD
Application
Phase 1
45,000
2020
Application
Phase 2
45,000
TBD
Application
Phase 3
45,000
TBD
Application
Ivanhoe Energy Inc. •
Tamarack
Updated: Mar 2014
Ivanhoe Energy says that it has suspended activity on the Tamarack project based on the uncertainty that there is no timeline defined by the Alberta Energy Regulator for a new regulatory framework for shallow SAGD projects, and that there is no clarity as to a path for approval for its Tamarack application. Until there is greater regulatory certainty as to a path to approval, Ivanhoe will limit Tamarack spending to only essential items. Phase 1
20,000
2017
Application
Phase 2
20,000
TBD
Application
Koch Exploration Canada Corporation Dunkirk
Updated: Feb 2014
Alberta has issued the proposed terms of reference for Koch’s Dunkirk SAGD project, one of the first steps in the regulatory process. Phase 1
30,000
2018
Announced
Phase 2
30,000
TBD
Announced
Marathon Oil Corporation Birchwood
Updated: Apr 2013
Marathon filed its regulatory application in 2012. Regulatory approval and project sanctioning were expected in 2013.
E-T Energy Ltd. Poplar Creek
Updated: Feb 2014
The E-T Energy Poplar Creek pilot project is no longer operating, but the expanded field test is able to proceed subject to regulatory approval and financing. Experimental Pilot
Phase 1
Husky filed the regulatory application for its Saleski pilot in early May 2013.
Construction
Phase 3
Updated: Feb 2014
Husky Energy Inc.
Updated: Oct 2013
Phase 2
Phase 1
REGULATORY STATUS
The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. Grizzly Thickwood is one of five impacted projects.
Brion Energy Corporation
Phase 1
START-UP
Thickwood
Updated: Mar 2013
BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources.
Phase 1
CAPACITY
Grizzly Oil Sands ULC
BP p.l.c.
Pilot
CURRENT PROJECT
1,000
2012
Suspended
Phase 1
10,000
TBD
Announced
Phase 2
40,000
TBD
Announced
Demonstration
12,000
2017
Application
Oak Point Energy Ltd. Lewis
Updated: Jan 2013
The ERCB and Alberta Environment have approved Oak Point’s Lewis project, which is estimated to have a capital cost of $65 million. Pilot
1,720
TBD
Sprung Structures
Approved
Warehousing
Add additional space immediately. Lease or purchase.
1/4 HORIZONTAL Sprung Structures 540752 Calgary, Alberta
www.sprung.com/oilgas
1.403.601.2292 Toll Free:
1.800.528.9899
MAY 2014 | OILSANDSREVIEW.COM
33
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
CURRENT PROJECT
Prosper Petroleum Ltd. Updated: Dec 2013
Prosper Petroleum filed its regulatory application for the Rigel SAGD project in November 2013. 10,000
2017
Application
SilverWillow Energy Corporation •
Audet
Updated: Mar 2014
The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. SilverWillow Audet is one of five impacted projects. SilverWillow has announced a strategic review process to enhance shareholder value. Pilot
12,000
2017
STP-McKay
Phase 1
Updated: Mar 2014
Operating
Stage 4
42,500
2012
Operating
Stage 5
62,500
2018
Approved
Stage 6
62,500
2019
Approved
Stage 3-6 Debottleneck
23,000
TBD
40,000
TBD
Phase 2
40,000
TBD
MacKay River
Operating
Phase 1
2016
Application
Debottleneck
Phase 2A
12,000
2018
Application
MR2
Phase 2B
6,000
2018
Application Updated: Oct 2013
N-Solv says hot oil is currently being circulated into the reservoir to open a path between the injection well and the producer well. Propane or butane injection on the solvent-only production pilot is expected to begin in the first quarter of 2014. Operations will continue until 2015. Demonstration Plant
500
2013
Firebag
Operating Updated: Feb 2014
Suncor says that production at the Firebag complex had fully ramped up with daily production rates reaching approximately 95 per cent of capacity in the fourth quarter of 2013; however, production was reduced throughout the quarter due to a third-party natural gas outage and subsequent curtailments that impacted the Fort McMurray region.
Announced Announced Updated: Feb 2014
Suncor says it continues to progress a debottleneck of the MacKay River facility that is intended to increase production capacity by approximately 20 per cent for a total capacity of 38,000 barrels per day by 2015. Suncor also continues to work toward a 2014 sanction decision of the MacKay River expansion project.
2012
Dover
Application Updated: Aug 2013
Phase 1
6,000
Suncor Energy Inc.
34
2011
12,000
Phase 1 Expansion
Updated: Feb 2014 42,500
After the MacKay River expansion and debottlenecking at both Firebag and MacKay River, Lewis is expected to be Suncor’s next area of in situ development focus.
Application
Southern Pacific says early results indicate inflow control devices on wells at its STP-McKay thermal project have the potential to generate meaningful improvements in production and steam to oil ratios. One well pair has seen an 87 per cent production increase and significant drop in steam to oil ratio since the device was installed.
REGULATORY STATUS
Stage 3
Lewis
Southern Pacific Resource Corp. •
START-UP
Firebag (continued)
Rigel Phase 1
CAPACITY
33,000
2002
Operating
5,000
2015
Construction
20,000
2017
Application
Sunshine Oilsands Ltd. •
Harper
Updated: Mar 2014
Alberta’s enactment of the Lower Athabasca Regional Plan in 2013 created new conservation areas that impacted the Harper project. Sunshine received compensation from the government in December 2013. Carbonate Pilot
1,000
TBD
Legend Lake
Suspended Updated: Dec 2013
Sunshine says regulatory approval for the first 10,000-barrel-per-day phase was expected in 2013. The company is completing field work for its environmental analysis, which will support work for significant commercial expansion. Phase A1
10,000
2016
Application
Stage 1
35,000
2004
Operating
Phase A2
30,000
TBD
Announced
Stage 2
35,000
2006
Operating
Phase B1
30,000
TBD
Announced
Cogeneration and Expansion
25,000
2007
Operating
Phase B2
30,000
TBD
Announced
OILSANDS REVIEW | MAY 2014
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
Thickwood
REGULATORY STATUS
Updated: Feb 2014
CURRENT PROJECT
•
10,000
2015
Approved
Phase A2
30,000
2017
Announced
Phase B
30,000
2021
Announced
West Ells
Updated: Mar 2014
Sunshine suspended construction at West Ells in summer 2013 due to lack of financing and has not yet been able to meet requirements to restart. Phase A1
5,000
2014
On Hold
Phase A2
5,000
2014
Announced
Phase A3
30,000
2018
Announced
Phase B
20,000
2025
Announced
Phase C1
30,000
TBD
Announced
Phase C2
30,000
TBD
Announced
SOUTH ATHABASCA REGION — IN SITU Athabasca Oil Corporation •
Hangingstone
Phase 1
12,000
2015
Construction
Phase 2
40,000
2017
Application
Phase 3
30,000
2018
Application
BlackPearl Resources Inc. •
Blackrod
Updated: Mar 2014
BlackPearl says that it has been steaming the second pilot well pair since November with expectations to convert this well pair to SAGD operation in March. The company is testing a commercial well design after incorporating learnings from the first pilot well pair. Pilot
800
2011
Operating
Phase 1
20,000
2015
Application
Phase 2
30,000
2018
Application
Phase 3
30,000
2021
Application
REGULATORY STATUS
Gregoire Lake
Updated: Dec 2013
Canadian Natural says Gregoire Lake is in the planning stages. Phase 1
60,000
TBD
Phase 2
60,000
TBD
Grouse
Announced Announced Updated: Dec 2013
Canadian Natural says Grouse is in the planning stages. First production is expected between 2017 and 2019. Commercial •
50,000
2018
Kirby
Application Updated: Mar 2014
Canadian Natural says that at the end of the fourth quarter of 2013, steam was being circulated in 36 well pairs on six pads to initiate the SAGD process at Kirby South. Subsequent to the fourth quarter of 2013, 15 well pairs have been converted to SAGD production as planned. The wells at Kirby South are responding as expected, and production is targeted to grow to 40,000 barrels per day in the fourth quarter of 2014. All evaporators, steam generators and oil-treating vessels are in service, and the first shipment of crude oil produced was delivered during the fourth quarter of 2013, with production averaging 1,500 barrels per day for the quarter. Production ramp-up continues as expected, with current production of approximately 7,000 barrels per day. Canadian Natural says corporate sanction for Kirby North Phase 1 is anticipated in mid-2014, and engineering is approximately 97 per cent complete.
Updated: Mar 2014
Athabasca says that construction at Hangingstone was 59 per cent complete at year-end 2013. First steam is now expected in the first quarter of 2015, one quarter later than previously scheduled.
START-UP
Canadian Natural Resources Limited
Alberta has issued the final terms of reference for Sunshine’s Thickwood expansion project. Phase A1
CAPACITY
KS1 - Kirby South
40,000
2013
Operating
KN1 - Kirby North
40,000
2016
Approved
KN2 - Kirby North
60,000
2022
Application
Cavalier Energy Inc. •
Hoole
Updated: Mar 2014
Cavalier owner Paramount Resources says the company anticipates that regulatory approvals for the initial 10,000-barrel-per-day phase of its Hoole project will be received by mid-2014. Frontend engineering and design work was completed in 2013. Phase 1
10,000
2017
Application
Phase 2
35,000
TBD
Announced
Phase 3
35,000
TBD
Announced
Cenovus Energy Inc. Christina Lake
Updated: Feb 2014
Cenovus says the Phase F expansion is on schedule and on budget with about 44 per cent of the project complete and engineering, procurement and plant construction work continuing. Engineering work also continues for Phase G. Phase 1A
10,000
2002
Operating
Safety first. Safety is our top priority because lives depend on it. We are proud of our record of more than 7 million continuous safe work hours in the Canadian region. We focus on Safety & Assurance for every project we design, build and deliver. Learn more at wgmustang.ca
MAY 2014 | OILSANDSREVIEW.COM
35
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
Christina Lake (continued) Phase 1B
Updated: Feb 2014 8,800
2008
Operating
Phase C
40,000
2011
Operating
Phase D
40,000
2012
Operating
Phase E
40,000
2013
Operating
Optimization (Phases C, D, E)
22,000
2015
Approved
Phase F
50,000
2016
Construction
Phase G
50,000
2017
Approved
Phase H
50,000
2019
Foster Creek
Express Integrated Technologies (EIT) engineers and fabricates custom-
designed equipment for the process and power industries, including mid-stream processes, cogeneration equipment, and Once-Through Steam Generators for in-situ oil production.
Phase A
•
Operating
2003
Operating
Phase C Stage 1
10,000
2005
Operating
Phase C Stage 2
20,000
2007
Operating
Phase D
30,000
2009
Operating
Phase E
30,000
2009
Operating
Phase F
45,000
2014
Construction
Phase G
40,000
2015
Construction
Phase H
40,000
2016
Construction
Phase J
50,000
2019
Application
Future Optimization
15,000
TBD
Grand Rapids
Pilot
50 mm BTU/hr and Larger Canadian Pre-Assembly and Installation
2001
6,000
Announced Updated: Mar 2014
Cenovus has received regulatory approval for the full commercial Grand Rapids project. The company expects to make a decision on the timing of development later this year. Once a decision is made to proceed with Grand Rapids, Cenovus says it will be able to rely on existing infrastructure, including roads, power and camps at its Pelican Lake conventional heavy oil operation.
SAGD and CSS Applications U.S. Manufacturing Facilities
24,000
Phase B Debottleneck
Calgary office specifically serves the needs of the Canadian oil sands market.
Custom Innovative Designs
Application Updated: Feb 2014
Phase F is on schedule and on budget with 90 per cent of the project complete, and first production is expected in the third quarter of 2014, with full ramp-up to be completed within 12–18 months. Phase G is 66 per cent complete, with initial production expected in 2015. Phase H is 35 per cent complete, and first production is expected in 2016. Cenovus has adjusted timelines for achieving full production capacity at these expansions as it delays optimization projects until it has had more time to assess new operating strategies.
EIT Canada Ltd’s
Once-Through Steam Generators
REGULATORY STATUS
600
2011
Operating
Phase A
60,000
2017
Approved
Phase B
60,000
TBD
Approved
Phase C
60,000
TBD
Narrows Lake
Approved Updated: Feb 2014
Cenovus says that site construction, engineering and procurement are progressing as expected, with overall progress for Phase A reaching 16 per cent completion at the end of 2014. Phase A
45,000
2017
Construction
EIT also Engineers and Fabricates
Phase B
45,000
TBD
Approved
Phase C
40,000
TBD
• • • • •
West Kirby
Heat Recovery Steam Generators Waste Heat Recovery Units Process Fired Heaters Simple Cycle Catalyst Systems Aftermarket Services
Approved Updated: Dec 2013
Cenovus says this project remains part of its portfolio of long-term development opportunities. Phase 1
30,000
TBD
Winefred Lake
Announced Updated: Dec 2013
Cenovus says this project remains part of its portfolio of long-term development opportunities. Phase 1
30,000
TBD
Announced
Phase 1
72,000
2008
Operating
Kinosis (K1A)
40,000
TBD
Construction
Kinosis (K1B)
40,000
TBD
Approved
CNOOC Limited Long Lake
Please contact us to learn more about our in-house engineering and fabrication capabilities.
Updated: Nov 2013
Connacher Oil And Gas Limited •
Great Divide
Updated: Mar 2014
Connacher says that full-year 2013 production averaged 11,783 barrels per day (2012 was 11,881 barrels per day). Production was slightly below 2012 as the impact of its 2013 capital program wasn’t realized until the fourth quarter of 2013. 2013 fourth-quarter production was lower due to scheduled interruptions during the commissioning of new well pairs and a temporary reduction in natural gas supply in northern Alberta. Preventative maintenance was advanced and performed during the fourth quarter of 2013 and also reduced production. Actual Great Divide production averaged 13,661 barrels per day for the first two months of 2014. Pod One
10,000
2007
Operating
Algar
10,000
2010
Operating
Expansion 1A
12,000
TBD
Approved
Expansion 1B
12,000
TBD
Approved
ConocoPhillips Canada Limited Surmont
Updated: Feb 2014
Alberta has issued the final terms of reference for ConocoPhillips Canada’s Surmont 3 project. Pilot
www.ExpressGroupHoldings.com 36
OILSANDS REVIEW | MAY 2014
1,200
1997
Operating
Phase 1
27,000
2007
Operating
Phase 2
109,000
2015
Construction
P R O J E C T S TAT U S
CAPACITY
REGULATORY STATUS
START-UP
Surmont (continued)
Updated: Feb 2014
Phase 3 - Tranche 1
45,000
2020
Announced
Phase 3 - Tranche 2
45,000
TBD
Announced
Phase 3 - Tranche 3
45,000
TBD
Announced
Devon Canada Corporation Jackfish
Updated: Feb 2014
Devon says that construction of the Jackfish 3 project is now nearly complete, with plant start-up expected in the third quarter of 2014. Phase 1
35,000
2007
Operating
Phase 2
35,000
2011
Operating
Phase 3
35,000
2014
Jackfish East Expansion
REDA HotlineSA3 HIGH-TEMPERATURE ESP SYSTEMS
Construction Updated: Sep 2012
20,000
2018
Pike
Announced Updated: Mar 2013 REDA, Hotline, and HotlineSA3 are marks of Schlumberger. © 2013 Schlumberger. 13-AL-0009
CURRENT PROJECT
Devon says the Pike project continues to move through the regulatory process. 1A
35,000
2016
Application
1B
35,000
2017
Application
1C
35,000
2018
Application
Grizzly Oil Sands ULC •
Algar Lake
Updated: Mar 2014
Grizzly owner Gulfport Energy says first steam was achieved during the fourth quarter of 2013. Continuous operation of the main boiler and steam injection into the reservoir commenced in January 2014. Grizzly expects first production at Algar Lake during the first quarter of 2014.
•
Phase 1
5,500
2014
Phase 2
5,500
TBD
May River
Operating Approved Updated: Mar 2014
Grizzly corporate part owner Gulfport Energy says that in the fourth quarter of 2013, the company submitted an initial 12,000-barrel-per-day SAGD development application with the regulatory authorities covering the eastern portion of the May River lease. Phase 1
6,000
2016
Application
Phase 2
6,000
TBD
Application
Harvest Operations Corp. •
BlackGold
Updated: Mar 2014
Harvest says that due to extreme winter conditions, the project scaled back construction activities during the first quarter of 2014. The company anticipates resuming full construction activities in the second quarter of 2014 and has revised the project schedule accordingly. Harvest anticipates construction completion of the central processing facility in the second half of 2014 with first steam expected in the fourth quarter of 2014. Regulatory approval for Phase 2 was received in December 2013. Phase 1
10,000
2014
Construction
Phase 2
20,000
TBD
Approved
Husky Energy Inc. McMullen
Updated: Feb 2014
Husky says that CHOPS production from 27 wells located on three well pads commenced during the fourth quarter of 2013, and at the air injection pilot three additional horizontal production wells were placed on production. Thermal Conduction Pilot
755
2012
Operating
Japan Canada Oil Sands Limited Hangingstone
Updated: Feb 2014
Construction is underway. Bantrel has been awarded a contract to provide engineering, procurement and construction services for the field facilities component of the project. Expansion
20,000
2016
Hangingstone Pilot Pilot
Construction Updated: Dec 2012
11,000
1999
10,000
2015
Operating
Koch Exploration Canada Corporation Muskwa Pilot
Updated: Sep 2013 Application
Laricina Energy Ltd. •
Germain
Updated: Mar 2014
Laricina says it continues start-up operations as select wells are converted from steam to production. Operations and facilities have normalized after a third-party pipeline break in fall 2013 resulted in a stoppage in steaming and start-up, followed by a plant upset. As a result of the interruptions, the benefit of the steam previously injected to heat the reservoir was mostly lost, delaying ramp-up. The reservoir is once again responding as expected, and bitumen production is starting to ramp up from the initial wells. Phase 1 CDP
•
5,000
2013
Operating
Phase 2
30,000
2018
Application
Phase 3
60,000
TBD
Application
Phase 4
60,000
TBD
Saleski
Extreme-temperature environments require extremely reliable ESPs. Selecting the right ESP system to handle the high temperatures and abrasive conditions of a SAGD well is essential to efficient thermal recovery. REDA Hotline ESPs have a proven history of success in Canada and now help produce more SAGD oil than all other artificial lift methods combined. The thirdgeneration HotlineSA3 ESP system carries on this tradition, introducing a unique system architecture designed to increase ESP run life, reduce installation time, and operate in wells up to 250 degC. Find out more at
slb.com/hotlineSA3
Application Updated: Mar 2014
Laricina says the pilot continues to provide a road map for Saleski Phase 1. Recently the company drilled a 700-metre sidetrack well in the Grosmont C zone that is currently in the first simultaneous steam injection and production cycle in the two Grosmont C zone wells testing block steaming and production. In the Grosmont D zone, an application was approved to drill a new well intended to progress the recovery process and optimize production. Experimental Pilot
1,800
2011
Operating
MAY 2014 | OILSANDSREVIEW.COM
37
P R O J E C T S TAT U S
FIND IT
CURRENT PROJECT
•
CAPACITY
REGULATORY STATUS
START-UP
Saleski (continued)
Updated: Mar 2014
Phase 1
10,700
2016
Approved
Phase 2
30,000
2017
Announced
Phase 3
60,000
2020
Announced
Phase 4
60,000
2023
Announced
Phase 5
60,000
2026
Announced
Phase 6
60,000
TBD
Announced
MEG Energy Corporation Christina Lake
Updated: Feb 2014
MEG says that Phase 2B achieved first production in the fourth quarter of 2013. Phase 1 Pilot
3,000
2008
Operating
Phase 2A
22,000
2009
Operating
Phase 2B
35,000
2013
Operating
Phase 3A
50,000
2016
Construction
Phase 3B
50,000
2018
Approved
Phase 3C
50,000
2020
Surmont
Need a drill collar? Need a hotel in High Level? Need safety personnel? Need to meet compliance standards? Need plant maintenance? Need a warehouse? Need a1/2 tarp? VERTICAL Need hydraulic repair? JWN Need environmental analysis? Need a 487551-5851 control valve? Need mud additives?
ALL THE SMALL PARTS AND BIG PLAYERS ARE FOUND ON
Approved Updated: Oct 2013
Phase 1
41,000
TBD
Application
Phase 2
41,000
TBD
Application
Phase 3
41,000
TBD
Application
OSUM Oil Sands Corp. Sepiko Kesik
Updated: Jul 2013
OSUM says it anticipates regulatory approval for Sepiko Kesik in 2014, requiring financing in 2015-16. Phase 1
30,000
2018
Application
Phase 2
30,000
2020
Application
Statoil Kai Kos Dehseh
Updated: Feb 2014
Statoil and partner PTTEP have entered into a transaction where the KKD asset will be split between the two firms, which currently own 60 per cent and 40 per cent, respectively. Statoil will continue as operator and now 100 per cent owner of the Leismer and Corner projects while PTTEP will own 100 per cent of the Thornbury, Hangingstone and South Leismer areas. Leismer Demonstration
10,000
2010
Operating
Corner
40,000
2017
Approved
Leismer Commercial
10,000
TBD
Approved
Leismer Expansion
20,000
TBD
Approved
Corner Expansion
40,000
TBD
Application
Hangingstone
20,000
TBD
Application
Leismer Northwest
20,000
TBD
Application
Leismer South
20,000
TBD
Application
Thornbury
40,000
TBD
Application
Thornbury Expansion
20,000
TBD
Application
40,000
TBD
Suncor Energy Inc. Chard Phase 1
Updated: Nov 2012
Meadow Creek
Announced Updated: Nov 2012
Phase 1
40,000
TBD
Approved
Phase 2
40,000
TBD
Approved
12,000
2015
Surmont Energy Ltd.
Utilize an ever-expanding database of Canadian oilfield service and supply companies (and a powerful set of search filters) to access 11,000 companies in over 1,300 categories.
Wildwood Phase 1
Updated: Oct 2012 Application
Value Creation Inc. Advanced TriStar
Updated: Feb 2014
The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. Advanced TriStar is one of five impacted projects. ATS-1
15,000
2016
Application
ATS-2
30,000
2018
Application
ATS-3
30,000
2020
TriStar
Application Updated: Feb 2014
Value Creation says it is funded for the TriStar project but has not yet decided on a construction timeline. Pilot
1,000
TBD
Approved
COLD LAKE REGION — IN SITU Baytex Energy Corp. Gemini
Updated: Dec 2013
Baytex says the SAGD well pair for its Gemini SAGD pilot was drilled in the third quarter of 2013, and the company remains on track for steaming by early 2014.
COSSD.COM
38
OILSANDS REVIEW | MAY 2014
Pilot
1,200
2014
Operating
Commercial
5,000
2017
Approved
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
CURRENT PROJECT
Sage
Pilot
Updated: Jan 2013
Birchwood has filed its regulatory application for the $230-million Sage project. Propak Systems of Airdrie, Alta., will execute modular surface facility construction. 5,000
2015
Primrose & Wolf Lake
Updated: Mar 2014
Wolf Lake
13,000
1985
Operating
Primrose South
45,000
1985
Operating
Primrose North
30,000
2006
Operating
Primrose East
32,000
2008
Operating
Walleye
Updated: Mar 2014
Devon says work on the Walleye project is currently on hold. Phase 1
9,000
2017
10,000
TBD
Application
Husky Energy Inc. Caribou Demonstration
Updated: Nov 2010
Tucker Phase 1
Pilot
Approved
30,000
2006
Operating
Cold Lake
Phase 1-10
110,000
1985
Operating
Phase 11-13
30,000
2002
Operating
Phase 14-16
40,000
2014
Construction
OSUM Oil Sands Corp. Taiga
Pilot
Phase 1
23,000
2016
Approved
Phase 2
22,000
2018
Approved
Pengrowth Energy Corporation Lindbergh
Pilot
Pilot
Commercial •
Experimental THAI Demonstration Phase 2
Operating
2015
Application Updated: Mar 2014
TBD 10,000
2014
Operating
TBD
Announced
Peace River
Updated: Dec 2013
Cadotte Lake
12,500
1986
Operating
Carmon Creek - Phase 1
40,000
2017
Construction
Carmon Creek - Phase 2
40,000
2018
Approved
Southern Pacific Resource Corp. Red Earth Pilot Expansion Commercial
Phase 3
20,000
2018
Announced
Approved
2011
Shell has sanctioned the Carmon Creek project, which will be the most significant project ever undertaken in the Peace River region.
Application
Operating
75 10,000
Royal Dutch Shell plc
Construction
TBD
Construction Updated: Dec 2013
Dawson
2017
2007
TBD
Petrobank says it commenced CSS steaming operations at one of the two horizontal THAI production wells in late December 2013 and initiated steaming operations at the second well in mid-February 2014. First production is expected in May 2014. The company is planning a nine-month production cycle followed by a second steam and production cycle. With success of these two CSS wells, Petrobank intends to prepare and submit an application for full field CSS development.
2015
10,000
TBD
Petrobank Energy And Resources Ltd.
17,500
10,000
Approved Updated: Dec 2013
Pilot
11,240
Phase 2
TBD
Penn West has announced that in 2014, it will divest its oilsands assets in the Peace River region as part of a strategy to prioritize light oil development.
Phase 2
Phase 1
700
Seal Main
Phase 1
Shell had previously put its Orion asset up for sale, but says it has not received any offers that reflect its value and has ended sale activities.
Operating Updated: Dec 2013
Harmon Valley South
Operating
Updated: May 2013
TBD
Penn West has announced that in 2014, it will divest its oilsands assets in the Peace River region of Alberta as part of a strategy to prioritize light oil development. These assets comprise the Peace River Oil Partnership, which was established in 2010 with an affiliate of China Investment Corporation.
2012
Orion
TBD
Penn West Petroleum Ltd.
1,260
Royal Dutch Shell plc
On Hold Updated: Feb 2014
Sawn Lake
Updated: Mar 2014
Alberta has issued the final terms of reference for Pengrowth’s Lindbergh expansion project. The company says the pilot continues to perform exceptionally well, with production volumes from the two well pairs at Feb. 1, 2014, at approximately 1,900 barrels per day, with an instantaneous steam to oil ratio of approximately two. Construction of Lindbergh’s first commercial phase remains on schedule and on budget, with 65 percent of the capital committed or spent as of March 3, 2014.
Updated: Apr 2013
Southern Pacific says the CSS pilot at Red Earth is currently shut in. 3,000
TBD
Announced
10,000
TBD
Announced
SASKATCHEWAN REGION — IN SITU Cenovus Energy Inc. Axe Lake
Updated: Dec 2012
Cenovus Energy acquired the Axe Lake project in fall 2012. The company has not yet announced plans for the asset, stating only that it is a good “bolt-on” addition to the emerging Telephone Lake project, which is adjacent. Commercial
30,000
TBD
On Hold
NORTH ATHABASCA REGION — UPGRADER
PEACE RIVER REGION — IN SITU
BP p.l.c.
Andora Energy Corporation Sawn Lake
Terre de Grace
Updated: Dec 2013
Andora majority owner Pan Orient Energy says that drilling of the first SAGD well pair has been completed, final site preparation and construction is underway, and equipment for the facility is ready for installation. Steam injection at the Sawn Lake SAGD demonstration project is scheduled for the end of January 2014, with production anticipated early in the second quarter of 2014. 1,400
2014
Construction
Baytex Energy Corp. Cliffdale
Updated: Feb 2014
A hearing has wrapped up in Peace River relating to public concerns about health impacts of air pollution from bitumen storage tanks associated with Baytex’s cold production in the region. The hearing panel is expected to make its final comments public on the Alberta Energy Regulator website. Pilot
Updated: Nov 2012
Company owner Deep Well Oil & Gas has announced the completion of its first SAGD well pair for the demonstration project at Sawn Lake. Work is anticipated to begin shortly on the building of the steam-generation, water-handling, oil-treating, water-source and disposal facilities, along with pipeline tie-ins between the production facility and water-source wells. Steam operations are expected to begin in early January, with first oil production anticipated in the first half of 2014.
Updated: Jul 2013
OSUM says engineering work is underway and some long-lead items have been ordered. Project sanction was expected in 2013. Financing is required.
Demonstration
TBD
Northern Alberta Oil Ltd.
Updated: Feb 2014
Imperial says that the Nabiye expansion was 65 per cent complete at the end of the fourth quarter of 2013. Plant construction progressed somewhat slower than planned due to lower contractor productivity and harsh winter conditions. Target start-up, although under pressure, remains year-end 2014.
Pilot
TBD
Operating
Murphy says the two-well pilot is showing promise, with the second well showing the best response. Production in early 2014 had reached as high as 670 barrels per day with a steam to oil ratio of 1.8:1.
Updated: Jun 2013
Imperial Oil Limited
•
2011
Seal/Cadotte
Devon Canada Corporation •
Updated: Feb 2013 TBD
Cadotte
Application
Canadian Natural has withdrawn its application for a low-pressure steamflood at Primrose East— where bitumen emulsion has seeped to surface—after the Alberta Energy Regulator informed the company the application would be denied. The regulator determined it would be premature to approve the application, given that the investigation into the four leaks at the site that occured in spring 2013 is ongoing.
REGULATORY STATUS
Murphy Oil Company Ltd.
Canadian Natural Resources Limited •
START-UP
Harmon Valley
Birchwood Resources Inc.
Pilot
CAPACITY
2,000
2011
Operating
Updated: Mar 2013
BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources. Pilot
8,400
TBD
Approved
Canadian Natural Resources Limited •
Horizon
Updated: Mar 2014
Canadian Natural says that Horizon achieved strong and reliable operating performance for all of 2013. The 2013 fourth-quarter production volumes of 112,273 barrels per day represent a 35 per cent increase from 2012 fourth-quarter levels, which the company says indicates a step-change in safe, steady and reliable production. The overall Phase 2/3 expansion is 34 per cent physcially complete, and projects under construction continue to trend at or below cost estimates. Phase 1 Reliability - Tranche 2
110,000
2009
Operating
5,000
2014
Construction
MAY 2014 | OILSANDSREVIEW.COM
39
P R O J E C T S TAT U S
CURRENT PROJECT
•
CAPACITY
START-UP
Horizon (continued)
REGULATORY STATUS
Updated: Mar 2014
Phase 2A
12,000
2015
CURRENT PROJECT
45,000
2016
Construction
Phase 3
80,000
2017
Construction
Tamarack
Advanced TriStar
Updated: Mar 2014
Ivanhoe Energy says that it has suspended activity on the Tamarack project based on the uncertainty that there is no timeline defined by the Alberta Energy Regulator for a new regulatory framework for shallow SAGD projects, and that there is no clarity as to a path for approval for its Tamarack application. Until there is greater regulatory certainty as to a path to approval, Ivanhoe will limit Tamarack spending to only essential items. Phase 1
34,784
2017
Application
Suncor Energy Inc.
REGULATORY STATUS
Updated: Feb 2014
The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. Advanced TriStar is one of five impacted projects.
Ivanhoe Energy Inc. •
START-UP
Value Creation Inc.
Construction
Phase 2B
CAPACITY
ATS-1
12,750
2016
Application
ATS-2
25,500
2018
Application
ATS-3
25,500
2020
TriStar
Application Updated: Feb 2014
Value Creation says it is funded for the TriStar project but has not yet decided on a construction timeline. Pilot
820
TBD
Approved
INDUSTRIAL HEARTLAND REGION — UPGRADER North West Upgrading Inc.
Base Operations
Updated: Feb 2014
Suncor says that during the fourth quarter, maintenance was completed at its Upgrader 2 vacuum tower and related units. The company says that hot bitumen infrastructure commissioned in the third quarter of 2013 has increased the takeaway capacity of bitumen and unlocked additional mining production. U1 and U2
•
Redwater Upgrader
Updated: Mar 2014
Through some extremely cold winter weather and some spring-like melt conditions, North West says good construction progress continues at the Sturgeon Refinery site. Engineering and procurement activity is well advanced, with a related contact list available at goo.gl/6YlFNa. Phase 1
50,000
2017
Construction
225,000
1967
Operating
Phase 2
50,000
TBD
Approved
35,000
2005
Operating
Phase 3
50,000
TBD
Approved
Millennium Vacuum Unit Millennium Coker Unit
97,000
2008
Operating
Syncrude Canada Ltd. Mildred Lake/Aurora
Updated: Feb 2014
Alberta has issued the final terms of reference for Syncrude’s MLX project. Base Plant Stage 1 & 2 Debottleneck
250,000
1978
Operating
Stage 3 Expansion (UE-1)
100,000
2006
Operating
75,000
TBD
Announced
Stage 3 Debottleneck
CNOOC Limited Long Lake
Updated: Nov 2013 58,500
•
Scotford Upgrader 1
Updated: Mar 2014
Minority partner Marathon Oil Corporation says its income from the Athabasca Oil Sands Project was significantly lower in the fourth quarter of 2013 compared to the third quarter of 2013, primarily as a result of lower price realizations. Commercial
155,000
2003
Operating
Expansion
100,000
2011
Operating
Value Creation Inc. Heartland
Updated: Mar 2013
Reports are that Value Creation could be up and running within 18 months of project sanction, but funding remains unclear.
SOUTH ATHABASCA REGION — UPGRADER
Phase 1
Shell Albian Sands
2009
Operating
Wherever you are, you’re never that far from business ethics and anti-corruption advice. Norton Rose Fulbright’s Business Ethics and
Phase 1
46,300
TBD
On Hold
Phase 2
46,300
TBD
Approved
Phase 3
46,300
TBD
Approved
Master distributors of Shengli Oilfield Freet Steel Pipe Co., Ltd. Vacuum insulated tubing.
Anti-Corruption Team, is at the forefront of this rapidly evolving area of national and international law. We advise and represent clients of all sizes and in all industry sectors, wherever you are in the world.
Law around the world nortonrosefulbright.com
Paul Drager, QC 403.267.8261 paul.drager@nortonrosefulbright.com Eugene J. Bodnar 403.267.8368 gene.bodnar@nortonrosefulbright.com
CSTL is also able to provide coated tubing and OCTG.
#402, 1040 – 7th Ave S.W. Calgary, AB T2P 3G9 Tel: 403-460-9980 | www.cstl.ca