Oilsands Review Project Status May 2014

Page 1

P R O J E C T S TAT U S

05 14 project status

Athabasca Region Industrial Heartland Region Cold Lake Region

Sourced from Alberta regulators and corporate disclosures. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.

Peace River Region Northwestern Saskatchewan

navigator.oilsandsreview.com For more detailed project data, visit oilsandsreview.com. To explore oilsands projects using our interactive web tool, visit the Canadian Oilsands Navigator.

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

Horizon

Updated: Mar 2014

Canadian Natural says that Horizon achieved strong and reliable operating performance for all of 2013. The 2013 fourth-quarter production volumes of 112,273 barrels per day represents a 35 per cent increase from 2012 fourth-quarter levels, which the company says indicates a stepchange in safe, steady and reliable production. The overall Phase 2/3 expansion is 34 per cent physcially complete, and projects under construction continue to trend at or below cost estimates. 135,000

2008

Operating

5,000

2014

Construction

Phase 2A

12,000

2015

Construction

Phase 2B

45,000

2016

Construction

Phase 3

80,000

2017

Construction

Reliability - Tranche 2

Kearl

COLD LAKE REGION

NEW EXPORT PIPELINES

Phase 1

110,000

2013

Operating

Phase 2

110,000

2015

Construction

Phase 3

80,000

2020

Approved

Phase 4 Debottleneck

45,000

TBD

Phase 1

Approved

Jackpine 100,000

2010

Operating

Phase 1B

100,000

TBD

Approved

Expansion

100,000

2017

Muskeg River

START-UP

Phase 1

TBD

On Hold

Base Operations

Updated: Feb 2014

Suncor says that during the fourth quarter, maintenance was completed at its Upgrader 2 vacuum tower and related units. The company says that hot bitumen infrastructure commissioned in the third quarter of 2013 has increased the takeaway capacity of bitumen and unlocked additional mining production.

Updated: Feb 2014 Operating Operating

TBD

Construction

Centrifuge Tailings Management

TBD

Aurora South Train 1

100,000

2016

Approved

Aurora South Train 2

100,000

2018

Approved

TBD

2023

Announced

Mildred Lake Mine Extension (MLX) Teck Resources Limited Frontier

Updated: Feb 2014

The Canadian Environmental Assessment Agency estimates the federal review schedule for the project application to be approximately two years, so 2015 would be the earliest approval would be granted. Teck says that an exploration program is planned at Frontier in the winter of 2014 to provide additional data to support the regulatory review process and ongoing engineering work. Phase 1

74,600

2021

Application

Phase 2

84,000

2024

Application

Phase 3

79,300

2027

Application

Phase 4 Equinox

39,400

2030

Application

Total E&P Canada Ltd. Joslyn North Mine

Updated: Mar 2013

Project partner Suncor Energy says an updated timing for the Joslyn sanction decision will be made available when it is ready. Phase 1

100,000

2021

Approved

NORTH ATHABASCA REGION — IN SITU Athabasca Oil Corporation

100,000

Application

2006

Phase 2

TBD

1978

Approved

Suncor Energy Inc.

120,000

116,300

Operating

On Hold

Approved Updated: May 2012

290,700

TBD

TBD

Construction

Stage 3 Expansion

2002

100,000

TBD

Base Mine Stage 1 & 2 Expansion

115,000

Phase 1

2017

20,000

Mildred Lake/Aurora

155,000

Shell has informed regulators that it is indefinitely halting work on the Pierre River project. The company has asked that the regulatory approval process be suspended.

160,000

Alberta has issued the final terms of reference for Syncrude’s MLX project.

Expansion & Debottlenecking

Updated: Feb 2014

Updated: Feb 2014

Syncrude Canada Ltd.

Commercial

Pierre River

REGULATORY STATUS

Suncor considers Voyageur South to be a “longer-term” project and has not confirmed a start-up date.

Approved Updated: Mar 2014

Minority partner Marathon Oil Corporation says its income from the Athabasca Oil Sands Project was significantly lower in the fourth quarter of 2013 compared to the third quarter of 2013, primarily as a result of lower price realizations.

Birch

Updated: Mar 2014

Athabasca will be reducing its workforce by 15 per cent. The layoffs, focused primarily in its Calgary office, will largely affect employees directly or indirectly tied to projects that are not being funded in the near term. Phase 1

12,000

TBD

Dover West Carbonates (Leduc)

Announced Updated: Dec 2013

A fourth production cycle for the TAGD pilot test was scheduled for the fourth quarter of 2013. Athabasca had been encouraged by results so far. Phase 1 Demonstration

6,000

2016

Phase 2 Demonstration

6,000

TBD

Dover West Sands & Clastics

Approved Application Updated: Nov 2013

Athabasca Oil Corporation is awaiting regulatory approval for the Dover West Sands Phase 1. Phase 1

12,000

2016

Application

Phase 2

35,000

2019

Announced

Phase 3

35,000

2020

Announced

Operating

Phase 4

35,000

2022

Announced

Operating

Phase 5

35,000

2024

Announced

294,000

1967

Operating

4,000

2007

Operating

Millennium Debottlenecking

23,000

2008

North Steepbank Extension

180,000

2012

OILSANDS REVIEW | MAY 2014

NEW INFORMATION THIS MONTH

Voyageur South

Updated: Dec 2013

Phase 1A

Steepbank Debottleneck Phase 3

CAPACITY

Debottleneck

Shell Albian Sands

Millennium Mine

Suncor says that project activities in 2014 are expected to focus on the completion of detailed engineering, the procurement across all areas of the project and the construction of mine and extraction infrastructure including pilings and foundations.

Updated: Feb 2014

Imperial Oil says that Kearl gross bitumen production continues to ramp up. Production was impacted during the fourth quarter by harsh winter weather and equipment reliability issues that are being addressed. Production rates of 100,000 barrels per day have been reached, and ongoing activities to stabilize performance at these higher levels are progressing. The Kearl expansion project was 72 per cent complete at year-end and remains on target for a 2015 start-up.

32

INDUSTRIAL HEARTLAND REGION

CURRENT PROJECT

Imperial Oil Limited

SOUTH ATHABASCA REGION

Fort Hills

Canadian Natural Resources Limited

Phase 1

SASKATCHEWAN REGION

PEACE RIVER REGION

NORTH ATHABASCA REGION — MINING •

NORTH ATHABASCA REGION


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

Terre de Grace

10,000

TBD

Dover

Approved

Updated: Feb 2014

Brion Energy and the Fort McKay First Nation have reached an agreement regarding the Dover project, and all objections to the Alberta Energy Regulator’s approval have been removed. Dover North Phase 1

50,000

2016

Approved

Dover North Phase 2

50,000

2018

Approved

Dover South Phase 3

50,000

2021

Approved

Dover South Phase 4

50,000

2023

Approved

Dover South Phase 5

50,000

2025

MacKay River

Approved

35,000

2015

40,000

2018

Approved

40,000

2020

Approved

Phase 4

35,000

2022

Approved

6,000

2017

Application

Phase 2

6,000

TBD

Application

Saleski

Updated: May 2013

Carbonate Pilot

3,000

2017

Application

Sunrise

Updated: Feb 2014

Husky says that Sunrise was 85 per cent complete at the end of the year and is advancing as planned toward start-up in the second half of 2014. Initial engineering is underway for the next phase of the project. Phase 1

60,000

2014

Construction

Phase 2A

70,000

2018

Approved

Phase 2B

70,000

2020

Approved

Imperial Oil Limited Aspen

Updated: Feb 2014

Alberta has issued the final terms of reference for Imperial’s Aspen project.

Canadian Natural Resources Limited Birch Mountain

Updated: Dec 2013

Canadian Natural says Birch is in the planning stages. Phase 1

60,000

2019

Announced

Phase 2

60,000

2023

Announced

Cenovus Energy Inc. East McMurray

Updated: Dec 2013

Cenovus says this project remains part of its portfolio of long-term development opportunities. 30,000

TBD

Steepbank

Announced Updated: Dec 2013

Cenovus says this project remains part of its portfolio of long-term development opportunities. 30,000

TBD

Telephone Lake

Announced Updated: Feb 2014

Cenovus says a dewatering pilot project designed to remove an underground layer of non-potable water sitting on top of the oilsands deposit was successfully concluded during the fourth quarter of 2013. Approximately 70 per cent of the top water was removed during the pilot and replaced with compressed air. Regulatory approval for the Telephone Lake project is anticipated in the second quarter of 2014. Phase A

45,000

TBD

Application

Phase B

45,000

TBD

Application

Phase 1

45,000

2020

Application

Phase 2

45,000

TBD

Application

Phase 3

45,000

TBD

Application

Ivanhoe Energy Inc. •

Tamarack

Updated: Mar 2014

Ivanhoe Energy says that it has suspended activity on the Tamarack project based on the uncertainty that there is no timeline defined by the Alberta Energy Regulator for a new regulatory framework for shallow SAGD projects, and that there is no clarity as to a path for approval for its Tamarack application. Until there is greater regulatory certainty as to a path to approval, Ivanhoe will limit Tamarack spending to only essential items. Phase 1

20,000

2017

Application

Phase 2

20,000

TBD

Application

Koch Exploration Canada Corporation Dunkirk

Updated: Feb 2014

Alberta has issued the proposed terms of reference for Koch’s Dunkirk SAGD project, one of the first steps in the regulatory process. Phase 1

30,000

2018

Announced

Phase 2

30,000

TBD

Announced

Marathon Oil Corporation Birchwood

Updated: Apr 2013

Marathon filed its regulatory application in 2012. Regulatory approval and project sanctioning were expected in 2013.

E-T Energy Ltd. Poplar Creek

Updated: Feb 2014

The E-T Energy Poplar Creek pilot project is no longer operating, but the expanded field test is able to proceed subject to regulatory approval and financing. Experimental Pilot

Phase 1

Husky filed the regulatory application for its Saleski pilot in early May 2013.

Construction

Phase 3

Updated: Feb 2014

Husky Energy Inc.

Updated: Oct 2013

Phase 2

Phase 1

REGULATORY STATUS

The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. Grizzly Thickwood is one of five impacted projects.

Brion Energy Corporation

Phase 1

START-UP

Thickwood

Updated: Mar 2013

BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources.

Phase 1

CAPACITY

Grizzly Oil Sands ULC

BP p.l.c.

Pilot

CURRENT PROJECT

1,000

2012

Suspended

Phase 1

10,000

TBD

Announced

Phase 2

40,000

TBD

Announced

Demonstration

12,000

2017

Application

Oak Point Energy Ltd. Lewis

Updated: Jan 2013

The ERCB and Alberta Environment have approved Oak Point’s Lewis project, which is estimated to have a capital cost of $65 million. Pilot

1,720

TBD

Sprung Structures

Approved

Warehousing

Add additional space immediately. Lease or purchase.

1/4 HORIZONTAL Sprung Structures 540752 Calgary, Alberta

www.sprung.com/oilgas

1.403.601.2292 Toll Free:

1.800.528.9899

MAY 2014 | OILSANDSREVIEW.COM

33


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

CURRENT PROJECT

Prosper Petroleum Ltd. Updated: Dec 2013

Prosper Petroleum filed its regulatory application for the Rigel SAGD project in November 2013. 10,000

2017

Application

SilverWillow Energy Corporation •

Audet

Updated: Mar 2014

The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. SilverWillow Audet is one of five impacted projects. SilverWillow has announced a strategic review process to enhance shareholder value. Pilot

12,000

2017

STP-McKay

Phase 1

Updated: Mar 2014

Operating

Stage 4

42,500

2012

Operating

Stage 5

62,500

2018

Approved

Stage 6

62,500

2019

Approved

Stage 3-6 Debottleneck

23,000

TBD

40,000

TBD

Phase 2

40,000

TBD

MacKay River

Operating

Phase 1

2016

Application

Debottleneck

Phase 2A

12,000

2018

Application

MR2

Phase 2B

6,000

2018

Application Updated: Oct 2013

N-Solv says hot oil is currently being circulated into the reservoir to open a path between the injection well and the producer well. Propane or butane injection on the solvent-only production pilot is expected to begin in the first quarter of 2014. Operations will continue until 2015. Demonstration Plant

500

2013

Firebag

Operating Updated: Feb 2014

Suncor says that production at the Firebag complex had fully ramped up with daily production rates reaching approximately 95 per cent of capacity in the fourth quarter of 2013; however, production was reduced throughout the quarter due to a third-party natural gas outage and subsequent curtailments that impacted the Fort McMurray region.

Announced Announced Updated: Feb 2014

Suncor says it continues to progress a debottleneck of the MacKay River facility that is intended to increase production capacity by approximately 20 per cent for a total capacity of 38,000 barrels per day by 2015. Suncor also continues to work toward a 2014 sanction decision of the MacKay River expansion project.

2012

Dover

Application Updated: Aug 2013

Phase 1

6,000

Suncor Energy Inc.

34

2011

12,000

Phase 1 Expansion

Updated: Feb 2014 42,500

After the MacKay River expansion and debottlenecking at both Firebag and MacKay River, Lewis is expected to be Suncor’s next area of in situ development focus.

Application

Southern Pacific says early results indicate inflow control devices on wells at its STP-McKay thermal project have the potential to generate meaningful improvements in production and steam to oil ratios. One well pair has seen an 87 per cent production increase and significant drop in steam to oil ratio since the device was installed.

REGULATORY STATUS

Stage 3

Lewis

Southern Pacific Resource Corp. •

START-UP

Firebag (continued)

Rigel Phase 1

CAPACITY

33,000

2002

Operating

5,000

2015

Construction

20,000

2017

Application

Sunshine Oilsands Ltd. •

Harper

Updated: Mar 2014

Alberta’s enactment of the Lower Athabasca Regional Plan in 2013 created new conservation areas that impacted the Harper project. Sunshine received compensation from the government in December 2013. Carbonate Pilot

1,000

TBD

Legend Lake

Suspended Updated: Dec 2013

Sunshine says regulatory approval for the first 10,000-barrel-per-day phase was expected in 2013. The company is completing field work for its environmental analysis, which will support work for significant commercial expansion. Phase A1

10,000

2016

Application

Stage 1

35,000

2004

Operating

Phase A2

30,000

TBD

Announced

Stage 2

35,000

2006

Operating

Phase B1

30,000

TBD

Announced

Cogeneration and Expansion

25,000

2007

Operating

Phase B2

30,000

TBD

Announced

OILSANDS REVIEW | MAY 2014


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

Thickwood

REGULATORY STATUS

Updated: Feb 2014

CURRENT PROJECT

10,000

2015

Approved

Phase A2

30,000

2017

Announced

Phase B

30,000

2021

Announced

West Ells

Updated: Mar 2014

Sunshine suspended construction at West Ells in summer 2013 due to lack of financing and has not yet been able to meet requirements to restart. Phase A1

5,000

2014

On Hold

Phase A2

5,000

2014

Announced

Phase A3

30,000

2018

Announced

Phase B

20,000

2025

Announced

Phase C1

30,000

TBD

Announced

Phase C2

30,000

TBD

Announced

SOUTH ATHABASCA REGION — IN SITU Athabasca Oil Corporation •

Hangingstone

Phase 1

12,000

2015

Construction

Phase 2

40,000

2017

Application

Phase 3

30,000

2018

Application

BlackPearl Resources Inc. •

Blackrod

Updated: Mar 2014

BlackPearl says that it has been steaming the second pilot well pair since November with expectations to convert this well pair to SAGD operation in March. The company is testing a commercial well design after incorporating learnings from the first pilot well pair. Pilot

800

2011

Operating

Phase 1

20,000

2015

Application

Phase 2

30,000

2018

Application

Phase 3

30,000

2021

Application

REGULATORY STATUS

Gregoire Lake

Updated: Dec 2013

Canadian Natural says Gregoire Lake is in the planning stages. Phase 1

60,000

TBD

Phase 2

60,000

TBD

Grouse

Announced Announced Updated: Dec 2013

Canadian Natural says Grouse is in the planning stages. First production is expected between 2017 and 2019. Commercial •

50,000

2018

Kirby

Application Updated: Mar 2014

Canadian Natural says that at the end of the fourth quarter of 2013, steam was being circulated in 36 well pairs on six pads to initiate the SAGD process at Kirby South. Subsequent to the fourth quarter of 2013, 15 well pairs have been converted to SAGD production as planned. The wells at Kirby South are responding as expected, and production is targeted to grow to 40,000 barrels per day in the fourth quarter of 2014. All evaporators, steam generators and oil-treating vessels are in service, and the first shipment of crude oil produced was delivered during the fourth quarter of 2013, with production averaging 1,500 barrels per day for the quarter. Production ramp-up continues as expected, with current production of approximately 7,000 barrels per day. Canadian Natural says corporate sanction for Kirby North Phase 1 is anticipated in mid-2014, and engineering is approximately 97 per cent complete.

Updated: Mar 2014

Athabasca says that construction at Hangingstone was 59 per cent complete at year-end 2013. First steam is now expected in the first quarter of 2015, one quarter later than previously scheduled.

START-UP

Canadian Natural Resources Limited

Alberta has issued the final terms of reference for Sunshine’s Thickwood expansion project. Phase A1

CAPACITY

KS1 - Kirby South

40,000

2013

Operating

KN1 - Kirby North

40,000

2016

Approved

KN2 - Kirby North

60,000

2022

Application

Cavalier Energy Inc. •

Hoole

Updated: Mar 2014

Cavalier owner Paramount Resources says the company anticipates that regulatory approvals for the initial 10,000-barrel-per-day phase of its Hoole project will be received by mid-2014. Frontend engineering and design work was completed in 2013. Phase 1

10,000

2017

Application

Phase 2

35,000

TBD

Announced

Phase 3

35,000

TBD

Announced

Cenovus Energy Inc. Christina Lake

Updated: Feb 2014

Cenovus says the Phase F expansion is on schedule and on budget with about 44 per cent of the project complete and engineering, procurement and plant construction work continuing. Engineering work also continues for Phase G. Phase 1A

10,000

2002

Operating

Safety first. Safety is our top priority because lives depend on it. We are proud of our record of more than 7 million continuous safe work hours in the Canadian region. We focus on Safety & Assurance for every project we design, build and deliver. Learn more at wgmustang.ca

MAY 2014 | OILSANDSREVIEW.COM

35


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

Christina Lake (continued) Phase 1B

Updated: Feb 2014 8,800

2008

Operating

Phase C

40,000

2011

Operating

Phase D

40,000

2012

Operating

Phase E

40,000

2013

Operating

Optimization (Phases C, D, E)

22,000

2015

Approved

Phase F

50,000

2016

Construction

Phase G

50,000

2017

Approved

Phase H

50,000

2019

Foster Creek

Express Integrated Technologies (EIT) engineers and fabricates custom-

designed equipment for the process and power industries, including mid-stream processes, cogeneration equipment, and Once-Through Steam Generators for in-situ oil production.

Phase A

Operating

2003

Operating

Phase C Stage 1

10,000

2005

Operating

Phase C Stage 2

20,000

2007

Operating

Phase D

30,000

2009

Operating

Phase E

30,000

2009

Operating

Phase F

45,000

2014

Construction

Phase G

40,000

2015

Construction

Phase H

40,000

2016

Construction

Phase J

50,000

2019

Application

Future Optimization

15,000

TBD

Grand Rapids

Pilot

50 mm BTU/hr and Larger Canadian Pre-Assembly and Installation

2001

6,000

Announced Updated: Mar 2014

Cenovus has received regulatory approval for the full commercial Grand Rapids project. The company expects to make a decision on the timing of development later this year. Once a decision is made to proceed with Grand Rapids, Cenovus says it will be able to rely on existing infrastructure, including roads, power and camps at its Pelican Lake conventional heavy oil operation.

SAGD and CSS Applications U.S. Manufacturing Facilities

24,000

Phase B Debottleneck

Calgary office specifically serves the needs of the Canadian oil sands market.

Custom Innovative Designs

Application Updated: Feb 2014

Phase F is on schedule and on budget with 90 per cent of the project complete, and first production is expected in the third quarter of 2014, with full ramp-up to be completed within 12–18 months. Phase G is 66 per cent complete, with initial production expected in 2015. Phase H is 35 per cent complete, and first production is expected in 2016. Cenovus has adjusted timelines for achieving full production capacity at these expansions as it delays optimization projects until it has had more time to assess new operating strategies.

EIT Canada Ltd’s

Once-Through Steam Generators

REGULATORY STATUS

600

2011

Operating

Phase A

60,000

2017

Approved

Phase B

60,000

TBD

Approved

Phase C

60,000

TBD

Narrows Lake

Approved Updated: Feb 2014

Cenovus says that site construction, engineering and procurement are progressing as expected, with overall progress for Phase A reaching 16 per cent completion at the end of 2014. Phase A

45,000

2017

Construction

EIT also Engineers and Fabricates

Phase B

45,000

TBD

Approved

Phase C

40,000

TBD

• • • • •

West Kirby

Heat Recovery Steam Generators Waste Heat Recovery Units Process Fired Heaters Simple Cycle Catalyst Systems Aftermarket Services

Approved Updated: Dec 2013

Cenovus says this project remains part of its portfolio of long-term development opportunities. Phase 1

30,000

TBD

Winefred Lake

Announced Updated: Dec 2013

Cenovus says this project remains part of its portfolio of long-term development opportunities. Phase 1

30,000

TBD

Announced

Phase 1

72,000

2008

Operating

Kinosis (K1A)

40,000

TBD

Construction

Kinosis (K1B)

40,000

TBD

Approved

CNOOC Limited Long Lake

Please contact us to learn more about our in-house engineering and fabrication capabilities.

Updated: Nov 2013

Connacher Oil And Gas Limited •

Great Divide

Updated: Mar 2014

Connacher says that full-year 2013 production averaged 11,783 barrels per day (2012 was 11,881 barrels per day). Production was slightly below 2012 as the impact of its 2013 capital program wasn’t realized until the fourth quarter of 2013. 2013 fourth-quarter production was lower due to scheduled interruptions during the commissioning of new well pairs and a temporary reduction in natural gas supply in northern Alberta. Preventative maintenance was advanced and performed during the fourth quarter of 2013 and also reduced production. Actual Great Divide production averaged 13,661 barrels per day for the first two months of 2014. Pod One

10,000

2007

Operating

Algar

10,000

2010

Operating

Expansion 1A

12,000

TBD

Approved

Expansion 1B

12,000

TBD

Approved

ConocoPhillips Canada Limited Surmont

Updated: Feb 2014

Alberta has issued the final terms of reference for ConocoPhillips Canada’s Surmont 3 project. Pilot

www.ExpressGroupHoldings.com 36

OILSANDS REVIEW | MAY 2014

1,200

1997

Operating

Phase 1

27,000

2007

Operating

Phase 2

109,000

2015

Construction


P R O J E C T S TAT U S

CAPACITY

REGULATORY STATUS

START-UP

Surmont (continued)

Updated: Feb 2014

Phase 3 - Tranche 1

45,000

2020

Announced

Phase 3 - Tranche 2

45,000

TBD

Announced

Phase 3 - Tranche 3

45,000

TBD

Announced

Devon Canada Corporation Jackfish

Updated: Feb 2014

Devon says that construction of the Jackfish 3 project is now nearly complete, with plant start-up expected in the third quarter of 2014. Phase 1

35,000

2007

Operating

Phase 2

35,000

2011

Operating

Phase 3

35,000

2014

Jackfish East Expansion

REDA HotlineSA3 HIGH-TEMPERATURE ESP SYSTEMS

Construction Updated: Sep 2012

20,000

2018

Pike

Announced Updated: Mar 2013 REDA, Hotline, and HotlineSA3 are marks of Schlumberger. © 2013 Schlumberger. 13-AL-0009

CURRENT PROJECT

Devon says the Pike project continues to move through the regulatory process. 1A

35,000

2016

Application

1B

35,000

2017

Application

1C

35,000

2018

Application

Grizzly Oil Sands ULC •

Algar Lake

Updated: Mar 2014

Grizzly owner Gulfport Energy says first steam was achieved during the fourth quarter of 2013. Continuous operation of the main boiler and steam injection into the reservoir commenced in January 2014. Grizzly expects first production at Algar Lake during the first quarter of 2014.

Phase 1

5,500

2014

Phase 2

5,500

TBD

May River

Operating Approved Updated: Mar 2014

Grizzly corporate part owner Gulfport Energy says that in the fourth quarter of 2013, the company submitted an initial 12,000-barrel-per-day SAGD development application with the regulatory authorities covering the eastern portion of the May River lease. Phase 1

6,000

2016

Application

Phase 2

6,000

TBD

Application

Harvest Operations Corp. •

BlackGold

Updated: Mar 2014

Harvest says that due to extreme winter conditions, the project scaled back construction activities during the first quarter of 2014. The company anticipates resuming full construction activities in the second quarter of 2014 and has revised the project schedule accordingly. Harvest anticipates construction completion of the central processing facility in the second half of 2014 with first steam expected in the fourth quarter of 2014. Regulatory approval for Phase 2 was received in December 2013. Phase 1

10,000

2014

Construction

Phase 2

20,000

TBD

Approved

Husky Energy Inc. McMullen

Updated: Feb 2014

Husky says that CHOPS production from 27 wells located on three well pads commenced during the fourth quarter of 2013, and at the air injection pilot three additional horizontal production wells were placed on production. Thermal Conduction Pilot

755

2012

Operating

Japan Canada Oil Sands Limited Hangingstone

Updated: Feb 2014

Construction is underway. Bantrel has been awarded a contract to provide engineering, procurement and construction services for the field facilities component of the project. Expansion

20,000

2016

Hangingstone Pilot Pilot

Construction Updated: Dec 2012

11,000

1999

10,000

2015

Operating

Koch Exploration Canada Corporation Muskwa Pilot

Updated: Sep 2013 Application

Laricina Energy Ltd. •

Germain

Updated: Mar 2014

Laricina says it continues start-up operations as select wells are converted from steam to production. Operations and facilities have normalized after a third-party pipeline break in fall 2013 resulted in a stoppage in steaming and start-up, followed by a plant upset. As a result of the interruptions, the benefit of the steam previously injected to heat the reservoir was mostly lost, delaying ramp-up. The reservoir is once again responding as expected, and bitumen production is starting to ramp up from the initial wells. Phase 1 CDP

5,000

2013

Operating

Phase 2

30,000

2018

Application

Phase 3

60,000

TBD

Application

Phase 4

60,000

TBD

Saleski

Extreme-temperature environments require extremely reliable ESPs. Selecting the right ESP system to handle the high temperatures and abrasive conditions of a SAGD well is essential to efficient thermal recovery. REDA Hotline ESPs have a proven history of success in Canada and now help produce more SAGD oil than all other artificial lift methods combined. The thirdgeneration HotlineSA3 ESP system carries on this tradition, introducing a unique system architecture designed to increase ESP run life, reduce installation time, and operate in wells up to 250 degC. Find out more at

slb.com/hotlineSA3

Application Updated: Mar 2014

Laricina says the pilot continues to provide a road map for Saleski Phase 1. Recently the company drilled a 700-metre sidetrack well in the Grosmont C zone that is currently in the first simultaneous steam injection and production cycle in the two Grosmont C zone wells testing block steaming and production. In the Grosmont D zone, an application was approved to drill a new well intended to progress the recovery process and optimize production. Experimental Pilot

1,800

2011

Operating

MAY 2014 | OILSANDSREVIEW.COM

37


P R O J E C T S TAT U S

FIND IT

CURRENT PROJECT

CAPACITY

REGULATORY STATUS

START-UP

Saleski (continued)

Updated: Mar 2014

Phase 1

10,700

2016

Approved

Phase 2

30,000

2017

Announced

Phase 3

60,000

2020

Announced

Phase 4

60,000

2023

Announced

Phase 5

60,000

2026

Announced

Phase 6

60,000

TBD

Announced

MEG Energy Corporation Christina Lake

Updated: Feb 2014

MEG says that Phase 2B achieved first production in the fourth quarter of 2013. Phase 1 Pilot

3,000

2008

Operating

Phase 2A

22,000

2009

Operating

Phase 2B

35,000

2013

Operating

Phase 3A

50,000

2016

Construction

Phase 3B

50,000

2018

Approved

Phase 3C

50,000

2020

Surmont

Need a drill collar? Need a hotel in High Level? Need safety personnel? Need to meet compliance standards? Need plant maintenance? Need a warehouse? Need a1/2 tarp? VERTICAL Need hydraulic repair? JWN Need environmental analysis? Need a 487551-5851 control valve? Need mud additives?

ALL THE SMALL PARTS AND BIG PLAYERS ARE FOUND ON

Approved Updated: Oct 2013

Phase 1

41,000

TBD

Application

Phase 2

41,000

TBD

Application

Phase 3

41,000

TBD

Application

OSUM Oil Sands Corp. Sepiko Kesik

Updated: Jul 2013

OSUM says it anticipates regulatory approval for Sepiko Kesik in 2014, requiring financing in 2015-16. Phase 1

30,000

2018

Application

Phase 2

30,000

2020

Application

Statoil Kai Kos Dehseh

Updated: Feb 2014

Statoil and partner PTTEP have entered into a transaction where the KKD asset will be split between the two firms, which currently own 60 per cent and 40 per cent, respectively. Statoil will continue as operator and now 100 per cent owner of the Leismer and Corner projects while PTTEP will own 100 per cent of the Thornbury, Hangingstone and South Leismer areas. Leismer Demonstration

10,000

2010

Operating

Corner

40,000

2017

Approved

Leismer Commercial

10,000

TBD

Approved

Leismer Expansion

20,000

TBD

Approved

Corner Expansion

40,000

TBD

Application

Hangingstone

20,000

TBD

Application

Leismer Northwest

20,000

TBD

Application

Leismer South

20,000

TBD

Application

Thornbury

40,000

TBD

Application

Thornbury Expansion

20,000

TBD

Application

40,000

TBD

Suncor Energy Inc. Chard Phase 1

Updated: Nov 2012

Meadow Creek

Announced Updated: Nov 2012

Phase 1

40,000

TBD

Approved

Phase 2

40,000

TBD

Approved

12,000

2015

Surmont Energy Ltd.

Utilize an ever-expanding database of Canadian oilfield service and supply companies (and a powerful set of search filters) to access 11,000 companies in over 1,300 categories.

Wildwood Phase 1

Updated: Oct 2012 Application

Value Creation Inc. Advanced TriStar

Updated: Feb 2014

The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. Advanced TriStar is one of five impacted projects. ATS-1

15,000

2016

Application

ATS-2

30,000

2018

Application

ATS-3

30,000

2020

TriStar

Application Updated: Feb 2014

Value Creation says it is funded for the TriStar project but has not yet decided on a construction timeline. Pilot

1,000

TBD

Approved

COLD LAKE REGION — IN SITU Baytex Energy Corp. Gemini

Updated: Dec 2013

Baytex says the SAGD well pair for its Gemini SAGD pilot was drilled in the third quarter of 2013, and the company remains on track for steaming by early 2014.

COSSD.COM

38

OILSANDS REVIEW | MAY 2014

Pilot

1,200

2014

Operating

Commercial

5,000

2017

Approved


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

CURRENT PROJECT

Sage

Pilot

Updated: Jan 2013

Birchwood has filed its regulatory application for the $230-million Sage project. Propak Systems of Airdrie, Alta., will execute modular surface facility construction. 5,000

2015

Primrose & Wolf Lake

Updated: Mar 2014

Wolf Lake

13,000

1985

Operating

Primrose South

45,000

1985

Operating

Primrose North

30,000

2006

Operating

Primrose East

32,000

2008

Operating

Walleye

Updated: Mar 2014

Devon says work on the Walleye project is currently on hold. Phase 1

9,000

2017

10,000

TBD

Application

Husky Energy Inc. Caribou Demonstration

Updated: Nov 2010

Tucker Phase 1

Pilot

Approved

30,000

2006

Operating

Cold Lake

Phase 1-10

110,000

1985

Operating

Phase 11-13

30,000

2002

Operating

Phase 14-16

40,000

2014

Construction

OSUM Oil Sands Corp. Taiga

Pilot

Phase 1

23,000

2016

Approved

Phase 2

22,000

2018

Approved

Pengrowth Energy Corporation Lindbergh

Pilot

Pilot

Commercial •

Experimental THAI Demonstration Phase 2

Operating

2015

Application Updated: Mar 2014

TBD 10,000

2014

Operating

TBD

Announced

Peace River

Updated: Dec 2013

Cadotte Lake

12,500

1986

Operating

Carmon Creek - Phase 1

40,000

2017

Construction

Carmon Creek - Phase 2

40,000

2018

Approved

Southern Pacific Resource Corp. Red Earth Pilot Expansion Commercial

Phase 3

20,000

2018

Announced

Approved

2011

Shell has sanctioned the Carmon Creek project, which will be the most significant project ever undertaken in the Peace River region.

Application

Operating

75 10,000

Royal Dutch Shell plc

Construction

TBD

Construction Updated: Dec 2013

Dawson

2017

2007

TBD

Petrobank says it commenced CSS steaming operations at one of the two horizontal THAI production wells in late December 2013 and initiated steaming operations at the second well in mid-February 2014. First production is expected in May 2014. The company is planning a nine-month production cycle followed by a second steam and production cycle. With success of these two CSS wells, Petrobank intends to prepare and submit an application for full field CSS development.

2015

10,000

TBD

Petrobank Energy And Resources Ltd.

17,500

10,000

Approved Updated: Dec 2013

Pilot

11,240

Phase 2

TBD

Penn West has announced that in 2014, it will divest its oilsands assets in the Peace River region as part of a strategy to prioritize light oil development.

Phase 2

Phase 1

700

Seal Main

Phase 1

Shell had previously put its Orion asset up for sale, but says it has not received any offers that reflect its value and has ended sale activities.

Operating Updated: Dec 2013

Harmon Valley South

Operating

Updated: May 2013

TBD

Penn West has announced that in 2014, it will divest its oilsands assets in the Peace River region of Alberta as part of a strategy to prioritize light oil development. These assets comprise the Peace River Oil Partnership, which was established in 2010 with an affiliate of China Investment Corporation.

2012

Orion

TBD

Penn West Petroleum Ltd.

1,260

Royal Dutch Shell plc

On Hold Updated: Feb 2014

Sawn Lake

Updated: Mar 2014

Alberta has issued the final terms of reference for Pengrowth’s Lindbergh expansion project. The company says the pilot continues to perform exceptionally well, with production volumes from the two well pairs at Feb. 1, 2014, at approximately 1,900 barrels per day, with an instantaneous steam to oil ratio of approximately two. Construction of Lindbergh’s first commercial phase remains on schedule and on budget, with 65 percent of the capital committed or spent as of March 3, 2014.

Updated: Apr 2013

Southern Pacific says the CSS pilot at Red Earth is currently shut in. 3,000

TBD

Announced

10,000

TBD

Announced

SASKATCHEWAN REGION — IN SITU Cenovus Energy Inc. Axe Lake

Updated: Dec 2012

Cenovus Energy acquired the Axe Lake project in fall 2012. The company has not yet announced plans for the asset, stating only that it is a good “bolt-on” addition to the emerging Telephone Lake project, which is adjacent. Commercial

30,000

TBD

On Hold

NORTH ATHABASCA REGION — UPGRADER

PEACE RIVER REGION — IN SITU

BP p.l.c.

Andora Energy Corporation Sawn Lake

Terre de Grace

Updated: Dec 2013

Andora majority owner Pan Orient Energy says that drilling of the first SAGD well pair has been completed, final site preparation and construction is underway, and equipment for the facility is ready for installation. Steam injection at the Sawn Lake SAGD demonstration project is scheduled for the end of January 2014, with production anticipated early in the second quarter of 2014. 1,400

2014

Construction

Baytex Energy Corp. Cliffdale

Updated: Feb 2014

A hearing has wrapped up in Peace River relating to public concerns about health impacts of air pollution from bitumen storage tanks associated with Baytex’s cold production in the region. The hearing panel is expected to make its final comments public on the Alberta Energy Regulator website. Pilot

Updated: Nov 2012

Company owner Deep Well Oil & Gas has announced the completion of its first SAGD well pair for the demonstration project at Sawn Lake. Work is anticipated to begin shortly on the building of the steam-generation, water-handling, oil-treating, water-source and disposal facilities, along with pipeline tie-ins between the production facility and water-source wells. Steam operations are expected to begin in early January, with first oil production anticipated in the first half of 2014.

Updated: Jul 2013

OSUM says engineering work is underway and some long-lead items have been ordered. Project sanction was expected in 2013. Financing is required.

Demonstration

TBD

Northern Alberta Oil Ltd.

Updated: Feb 2014

Imperial says that the Nabiye expansion was 65 per cent complete at the end of the fourth quarter of 2013. Plant construction progressed somewhat slower than planned due to lower contractor productivity and harsh winter conditions. Target start-up, although under pressure, remains year-end 2014.

Pilot

TBD

Operating

Murphy says the two-well pilot is showing promise, with the second well showing the best response. Production in early 2014 had reached as high as 670 barrels per day with a steam to oil ratio of 1.8:1.

Updated: Jun 2013

Imperial Oil Limited

2011

Seal/Cadotte

Devon Canada Corporation •

Updated: Feb 2013 TBD

Cadotte

Application

Canadian Natural has withdrawn its application for a low-pressure steamflood at Primrose East— where bitumen emulsion has seeped to surface—after the Alberta Energy Regulator informed the company the application would be denied. The regulator determined it would be premature to approve the application, given that the investigation into the four leaks at the site that occured in spring 2013 is ongoing.

REGULATORY STATUS

Murphy Oil Company Ltd.

Canadian Natural Resources Limited •

START-UP

Harmon Valley

Birchwood Resources Inc.

Pilot

CAPACITY

2,000

2011

Operating

Updated: Mar 2013

BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources. Pilot

8,400

TBD

Approved

Canadian Natural Resources Limited •

Horizon

Updated: Mar 2014

Canadian Natural says that Horizon achieved strong and reliable operating performance for all of 2013. The 2013 fourth-quarter production volumes of 112,273 barrels per day represent a 35 per cent increase from 2012 fourth-quarter levels, which the company says indicates a step-change in safe, steady and reliable production. The overall Phase 2/3 expansion is 34 per cent physcially complete, and projects under construction continue to trend at or below cost estimates. Phase 1 Reliability - Tranche 2

110,000

2009

Operating

5,000

2014

Construction

MAY 2014 | OILSANDSREVIEW.COM

39


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

Horizon (continued)

REGULATORY STATUS

Updated: Mar 2014

Phase 2A

12,000

2015

CURRENT PROJECT

45,000

2016

Construction

Phase 3

80,000

2017

Construction

Tamarack

Advanced TriStar

Updated: Mar 2014

Ivanhoe Energy says that it has suspended activity on the Tamarack project based on the uncertainty that there is no timeline defined by the Alberta Energy Regulator for a new regulatory framework for shallow SAGD projects, and that there is no clarity as to a path for approval for its Tamarack application. Until there is greater regulatory certainty as to a path to approval, Ivanhoe will limit Tamarack spending to only essential items. Phase 1

34,784

2017

Application

Suncor Energy Inc.

REGULATORY STATUS

Updated: Feb 2014

The Alberta Energy Regulator says it will defer decisions on applications for in situ oilsands projects in the new “shallow thermal area” of the Athabasca region until it has developed formal regulatory requirements. Advanced TriStar is one of five impacted projects.

Ivanhoe Energy Inc. •

START-UP

Value Creation Inc.

Construction

Phase 2B

CAPACITY

ATS-1

12,750

2016

Application

ATS-2

25,500

2018

Application

ATS-3

25,500

2020

TriStar

Application Updated: Feb 2014

Value Creation says it is funded for the TriStar project but has not yet decided on a construction timeline. Pilot

820

TBD

Approved

INDUSTRIAL HEARTLAND REGION — UPGRADER North West Upgrading Inc.

Base Operations

Updated: Feb 2014

Suncor says that during the fourth quarter, maintenance was completed at its Upgrader 2 vacuum tower and related units. The company says that hot bitumen infrastructure commissioned in the third quarter of 2013 has increased the takeaway capacity of bitumen and unlocked additional mining production. U1 and U2

Redwater Upgrader

Updated: Mar 2014

Through some extremely cold winter weather and some spring-like melt conditions, North West says good construction progress continues at the Sturgeon Refinery site. Engineering and procurement activity is well advanced, with a related contact list available at goo.gl/6YlFNa. Phase 1

50,000

2017

Construction

225,000

1967

Operating

Phase 2

50,000

TBD

Approved

35,000

2005

Operating

Phase 3

50,000

TBD

Approved

Millennium Vacuum Unit Millennium Coker Unit

97,000

2008

Operating

Syncrude Canada Ltd. Mildred Lake/Aurora

Updated: Feb 2014

Alberta has issued the final terms of reference for Syncrude’s MLX project. Base Plant Stage 1 & 2 Debottleneck

250,000

1978

Operating

Stage 3 Expansion (UE-1)

100,000

2006

Operating

75,000

TBD

Announced

Stage 3 Debottleneck

CNOOC Limited Long Lake

Updated: Nov 2013 58,500

Scotford Upgrader 1

Updated: Mar 2014

Minority partner Marathon Oil Corporation says its income from the Athabasca Oil Sands Project was significantly lower in the fourth quarter of 2013 compared to the third quarter of 2013, primarily as a result of lower price realizations. Commercial

155,000

2003

Operating

Expansion

100,000

2011

Operating

Value Creation Inc. Heartland

Updated: Mar 2013

Reports are that Value Creation could be up and running within 18 months of project sanction, but funding remains unclear.

SOUTH ATHABASCA REGION — UPGRADER

Phase 1

Shell Albian Sands

2009

Operating

Wherever you are, you’re never that far from business ethics and anti-corruption advice. Norton Rose Fulbright’s Business Ethics and

Phase 1

46,300

TBD

On Hold

Phase 2

46,300

TBD

Approved

Phase 3

46,300

TBD

Approved

Master distributors of Shengli Oilfield Freet Steel Pipe Co., Ltd. Vacuum insulated tubing.

Anti-Corruption Team, is at the forefront of this rapidly evolving area of national and international law. We advise and represent clients of all sizes and in all industry sectors, wherever you are in the world.

Law around the world nortonrosefulbright.com

Paul Drager, QC 403.267.8261 paul.drager@nortonrosefulbright.com Eugene J. Bodnar 403.267.8368 gene.bodnar@nortonrosefulbright.com

CSTL is also able to provide coated tubing and OCTG.

#402, 1040 – 7th Ave S.W. Calgary, AB T2P 3G9 Tel: 403-460-9980 | www.cstl.ca

40

OILSANDS REVIEW | MAY 2014