OIlsands Review Project Status May 2012

Page 1

P R O J E C T S TAT U S

05.12 PROJECT STATUS

Athabasca Region Industrial Heartland Region Cold Lake Region

Sourced from company releases, the Energy Resources Conservation Board and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.

Peace River Region Northwestern Saskatchewan

For even more details on all of these projects, visit www.oilsandsreview.com.

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

Canadian Natural Resources Limited Horizon

Updated: Apr 2012

Canadian Natural reports that it has successfully completed unplanned maintenance on the fractionating unit in its primary upgrading facility and restarted operations. The outage lasted from February 5 to March 13. ­

Phase 1

­ ­ ­

135,000

2008

Operating

Phase 2A

10,000

2014

Approved

Phase 2B

45,000

TBD

Approved

Phase 3

80,000

TBD

Approved

SOUTH ATHABASCA REGION

INDUSTRIAL HEARTLAND REGION

COLD LAKE REGION

NEW Export Pipelines

CURRENT PROJECT

­

North Steepbank Extension

­

Steepbank Debottleneck Phase 3

­

Fort Hills

New information this month

START-UP

REGULATORY STATUS

180,000

2012

Operating

4,000

2007

CAPACITY

Operating Updated: Nov 2011

Current capital expenditures for Fort Hills are around design base memorandum engineering. ­

Debottleneck

­

Phase 1

­

Voyageur South

­

Phase 1

25,000

TBD

Approved

165,000

2016

Approved

120,000

TBD

Updated: Nov 2010 Application

Syncrude Canada Ltd.

Imperial Oil Limited •

SASKATCHEWAN REGION

PEACE RIVER REGION

NORTH ATHABASCA REGION — MINING •

NORTH ATHABASCA REGION

Kearl

Updated: Apr 2012

­

Mildred Lake/Aurora North & South

Updated: Mar 2012

Imperial Oil says that construction of Kearl Phase 1 is approximately 87 per cent complete and progressing on schedule. Reassembly of modules reduced in size to be transported on U.S. interstate routes continues at site.

Canadian Oil Sands reports that front-end engineering and design is now complete for its $4.6-billion Mildred Lake mine train replacements. The target in-service date for the $1.6-billion Syncrude Emissions Reduction Project has now been extended into the first quarter of 2012.

­

Phase 1

110,000

2012

Construction

­

Aurora South Train 1

100,000

2016

Approved

­

Phase 2

110,000

2015

Construction

­

Aurora South Train 2

100,000

2018

Approved

­

Phase 3 Debottleneck

70,000

2020

Approved

­

Base Mine Stage 1 & 2 Expansion

290,700

1978

Operating

­

Stage 3 Expansion

116,300

2006

Operating

Shell Albian Sands ­

Jackpine

Updated: Jan 2012

The Canadian Environmental Assessment Agency recently invited public comment on a revised draft agreement to establish a joint panel for review of the Pierre River Mine project, as well as revisions to the existing joint panel agreement for the review of the Jackpine Mine expansion project.

Teck Recources Limited •

Frontier

Updated: Apr 2012

­

Expansion

100,000

2017

Approved

The Canadian Environmental Assessment Agency has announced that a period of public comment is underway and participant funding is being allocated. Comments are being accepted until June 4.

­

Phase 1A

100,000

2010

Operating

­

Phase 1

75,000

2021

Application

­

Phase 1B

100,000

TBD

Approved

­

Phase 2

80,000

2024

Application

­

Muskeg River

­

Commercial

155,000

2002

Operating

­

Phase 3

80,000

2027

Application

­

Expansion & Debottlenecking

115,000

TBD

Approved

­

Phase 4 Equinox

40,000

2030

Application

­

Pierre River

­

Phase 1

100,000

2018

Application

­

Phase 2

100,000

TBD

Application

Updated: Jan 2012

Updated: Jan 2012

Suncor Energy Inc. •

Base Operations

Updated: Apr 2012

Suncor reported in March that one of its two upgraders was being taken down for unplanned maintenance due to fractionator performance issues. The work was expected to take three to five weeks to complete and is not anticipated to result in changes to production guidance. In the fourth quarter of 2011, Suncor began to mine ore from the North Steepbank Extension. ­

Millennium Debottlenecking

­

Millennium Mine

23,000 294,000

Total E&P Canada Ltd. ­

Joslyn North Mine

Updated: Nov 2011

Project partner Suncor Energy says that current capital expenditures are around geological, engineering, regulatory and environmental studies. ­

Phase 1

­

Joslyn South Mine

­

Phase 1

­

Northern Lights Mine

100,000

2018

Approved Updated: Dec 2010

100,000

TBD

Announced Updated: Nov 2010

2008

Operating

­

Phase 1

57,250

TBD

On Hold

1967

Operating

­

Phase 2

57,250

TBD

On Hold

may 2012 | OILSANDSREVIEW.COM 37