Oilsands Review Project Status August 2012

Page 1

P R O J E C T S TAT U S

PROJECT STATUS 08.12

Athabasca Region Industrial Heartland Region Cold Lake Region

Sourced from company releases, the Energy Resources Conservation Board, and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.

Peace River Region Northwestern Saskatchewan

NORTH ATHABASCA REGION

For even more details on all of these projects, visit www.oilsandsreview.com.

CURRENT PROJECT

CAPACITY

START-UP

SASKATCHEWAN REGION

SOUTH ATHABASCA REGION

INDUSTRIAL HEARTLAND REGION

COLD LAKE REGION

NEW Export Pipelines

PEACE RIVER REGION

REGULATORY STATUS

CURRENT PROJECT

New information this month

CAPACITY

START-UP

REGULATORY STATUS

NORTH ATHABASCA REGION — MINING

­

Canadian Natural Resources Limited

Suncor says current work on Fort Hills includes progressing design basis memorandum engineering, site preparation and procurement for long-lead items. The company expects to present development plans to the board of directors for sanction in 2013.

­

Horizon

Updated: May 2012

Canadian Natural says that during the first quarter, a third ore preparation plant and associated hydrotransport unit were successfully integrated into operations. The infrastructure is expected to increase reliability going forward by allowing the company to maintain steady feedstock to the upgrader with two of the three ore preparation plants continually on stream. ­

Phase 1

135,000

2008

Operating

­

Phase 2A

10,000

2014

Approved

­

Phase 2B

45,000

TBD

Approved

­

Phase 3

80,000

TBD

Approved

­

Tranche 2

5,000

2012

Operating

Imperial Oil Limited ­

Kearl

Updated: May 2012

Imperial Oil says that construction of Kearl Phase 1 is 90 per cent complete and is progressing to expected start-up in late 2012. ­

Phase 1

110,000

2012

Construction

­

Phase 2

110,000

2015

Construction

­

Phase 3 Debottleneck

70,000

2020

Approved

Shell Albian Sands •

Jackpine

Updated: Jun 2012

The joint review panel reviewing the proposed Jackpine mine expansion has extended its period of public comment to August 3. ­

Expansion

100,000

2017

Application

­

Phase 1A

100,000

2010

Operating

­

Phase 1B

100,000

TBD

Approved

­

Muskeg River

Updated: May 2012

Twenty per cent project owner Marathon Oil Corporation says that production rates were down during Q1 due to reliability issues. ­

Commercial

155,000

2002

­

Expansion & Debottlenecking

115,000

TBD

Pierre River

Fort Hills

­

Debottleneck

­

Phase 1

­

Voyageur South

­

Phase 1

­

2016

Approved Approved Updated: May 2012

120,000

TBD

Application

Mildred Lake/Aurora North & South

Updated: May 2012

Construction is underway on a number of major projects including mine train replacement and relocation, the Aurora North Tailings Management Project, the Syncrude Emissions Reduction Project and the Centrifuge Tailings Management Project. ­

Aurora South Train 1

100,000

2016

Approved

­ ­

Aurora South Train 2

100,000

2018

Approved

Base Mine Stage 1 & 2 Expansion

290,700

1978

­

Stage 3 Expansion

Operating

116,300

2006

Operating

Teck Recources Limited ­

Frontier

Updated: May 2012

The Canadian Environmental Assessment Agency has announced that a period of public comment is underway and participant funding is being allocated. Comments are being accepted until June 4. Teck says that no field exploration activities are planned in 2012 and the key focus will be on supporting the regulatory application review, the consultations with stakeholders and the ongoing engineering studies. ­

Phase 1

75,000

2021

Application

­

Phase 2

80,000

2024

Application

­

Phase 3

80,000

2027

Application

­

Phase 4 Equinox

40,000

2030

Application

Approved

­

Joslyn North Mine

Updated: May 2012

Project partner Suncor Energy says that current capital expenditures are around further design work, drilling and site preparation. The partners plan to submit development plans to their respective boards of directors for sanction in 2013.

­

Phase 1

100,000

2018

Application

­

­

Phase 2

100,000

TBD

Application

NORTH ATHABASCA REGION — IN SITU

Phase 1

100,000

2018

Approved

Athabasca Oil Corporation

Suncor Energy Inc. ­

TBD

Syncrude Canada Ltd.

Total E&P Canada Ltd.

A joint review panel of the Canadian Environmental Assessment Agency and the Energy Resources Conservation Board has been established to review the proposed Pierre River mine project.

25,000 165,000

Suncor considers Voyageur South to be a longer-term project and has not confirmed a start-up date.

Operating

Updated: Jun 2012

Updated: May 2012

Base Operations

Updated: May 2012

­

Birch

Updated: May 2012

Suncor is now mining volumes from the North Steepbank Extension. The company expects that its Millennium Naphtha Unit (MNU) project will be fully operational by mid-year. In April, Suncor announced its upgrader had successfully returned to normal operations following a brief shutdown due to a fractionated performance issue. Suncor has started commissioning assets associated with its tailings reduction operations infrastructure project and anticipates to start using these assets during Q2.

AOSC says the updated contingent resources on its Birch holdings total 1.9 billion barrels. The company plans to submit its Birch regulatory application in late 2012 based on additional drilling and 3-D seismic.

­

Millennium Debottlenecking

2008

Operating

­

Millennium Mine

294,000

1967

Operating

AOSC says production testing continues while it works on the TAGD pilot. An update from the TAGD proof of concept is expected in Q2. The company has responded to the first round of supplemental information requests from regulators and has launched work on its design basis memorandum.

­

North Steepbank Extension

180,000

2012

Operating

­

Phase 1 Demonstration

6,000

2015

Application

Operating

­

Phase 2 Demonstration

6,000

TBD

Application

­

Steepbank Debottleneck Phase 3

36 OILSANDS REVIEW | AUGUST 2012

23,000

4,000

2007

­

Phase 1

­

Dover West Carbonates (Leduc)

12,000

TBD

Announced Updated: May 2012


P R O J E C T S TAT U S

CURRENT PROJECT

­

CAPACITY

REGULATORY STATUS

CURRENT PROJECT

Updated: May 2012

Husky Energy Inc.

START-UP

Dover West Sands & Clastics

AOSC says construction of an all-weather access road to the Dover West area is 85 per cent complete, with one bridge remaining to be built. Completion is expected in Q3.

­

Saleski

­

Carbonate Pilot

­

Phase 1

12,000

2015

Application

­

Sunrise

­

Phase 2

35,000

2018

Announced

­

Phase 3

35,000

2020

Announced

BP p.l.c. ­ ­

Terre de Grace Pilot

Updated: Mar 2012 10,000

TBD

Approved

Canadian Natural Resources Limited •

Birch Mountain

Updated: Jun 2012

CAPACITY

START-UP

REGULATORY STATUS

Updated: May 2012 TBD

2016

Announced Updated: May 2012

Husky says Phase 1 construction remains on schedule for first production in 2014. All 49 horizontal well pairs have been completed. Construction of the camp is nearing completion and occupancy is expected in Q2. Detailed engineering for facilities and supporting infrastructure continues, as well as early engineering for the next phase. ­

Phase 1

60,000

2014

Construction

­

Phase 2

50,000

2016

Approved

­

Phase 3

50,000

TBD

Approved

­

Phase 4

50,000

TBD

Approved

Canadian Natural says first steam for Phase 1 is expected in 2019, 2023 for Phase 2.

Ivanhoe Energy Inc.

­

Announced

­

Announced

Ivanhoe says it has received a second round of supplemental information requests regarding its project application from the ERCB. It continues to expect approval in 2012.

­

Phase 1 Phase 2

60,000 60,000

2019 2023

Cenovus Energy Inc.

Tamarack

Updated: May 2012

­

Phase 1

20,000

2013

Application

Cenovus says it continues to search for a strategic transaction to support development of the Telephone Lake project.

­

Phase 2

20,000

TBD

Application

­

­

Birchwood

­

Demonstration

12,000

2016

1,720

2013

­

­

Telephone Lake Borealis

Phase A Phase B

Updated: May 2012

45,000 45,000

TBD

Application

TBD

Application

Dover

Updated: Apr 2012

Dover OpCo says the project is in the final stages of the regulatory review process. ­

Phase 1

­

Subsequent Phases

­

Mackay River

Updated: Sep 2011 Application

Oak Point Energy Ltd.

Dover Operating Corp. ­

Marathon Oil Corporation

50,000

2015

Application

200,000

TBD

Application

­

Lewis

­

Pilot

Updated: Mar 2012 Application

SilverWillow Energy Corporation •

Audet

Updated: Jun 2012

ERCB project approval was granted in January 2012. Dover OpCo says construction is underway.

SilverWillow says for the remainder of 2012 it will focus on analyzing samples and data from this year’s drilling program. It will also be conducting an environmental baseline assessment and preparing preliminary engineering design for a pilot SAGD project to enable preparation of a regulatory application, which is expected to be filed in the second quarter of 2013.

­

­

Phase 1

Updated: Apr 2012

35,000

2014

Construction

­

Phase 2

40,000

2017

Approved

­

Phase 3

40,000

2019

Approved

­

Phase 4

35,000

TBD

Approved

Pilot

12,000

2016

Announced

Southern Pacific Resource Corp. •

STP-McKay

Updated: July 2012

Southern Pacific says it has commenced steam injection at the STP-McKay project. First oil is expected within three to four months. ­

Phase 1

­

Phase 1 Expansion

The ERCB has released its decision on the 10,000-barrel-per-day project application. It says E-T has not demonstrated the technology is capable of obtaining or sustaining commercial production rates and the application is not approved. The ERCB says E-T can reapply based on more performance data, which the company says it has (the application did not include data from the current test).

­

Phase 2A

­

Phase 2B

6,000

­

Phase 1

10,000

TBD

Announced

­

Phase 2

40,000

TBD

Announced

Suncor says that ramp-up of the Firebag Stage 3 expansion is proceeding in line with expectations. Construction of Stage 4 is also proceeding. During Q1, Suncor says it focused on construction of two new well pads, central processing facilities and cogeneration units.

­

Pilot

2007

Operating

­

E-T Energy Ltd. •

Poplar Creek

Updated: Jun 2012

1,000

12,000

2012

Operating

6,000

TBD

Application

12,000

2015

Application

TBD

Application

Suncor Energy Inc. ­

Firebag

Cogeneration and Expansion

Updated: May 2012

25,000

2007

LOCAL PEOPLE WITH GLOBAL STRENGTH

FEATURE LISTING:

Leading businesses have come to rely on Colliers International to advance their interests in real estate. With a greater sense of drive, as well as local market expertise, we’ll help you move swiftly along the right track—to accelerate your success.

FOR SALE LEASE, FT. MCMURRAY, AB, CANADA

Colliers Macaulay Nicolls Inc. 3555 Manulife Place, 10180 - 101 Street Edmonton, AB T5J 3S4

Operating

KUUSAMO DEVELOPMENTS - MACKENZIE PARK > 400 MacKenzie Blvd., Ft. McMurray > 1,500–29,000 SF > IB - Business Industrial > Grade Loading Contact: Ken Shebib, CCIM

780 420 1585

780 881 6297

www.collierscanada.com

www.collierscanada.com/5981

AUGUST 2012 | OILSANDSREVIEW.COM 37


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

CURRENT PROJECT

SOUTH ATHABASCA REGION — IN SITU

­

Stage 1

35,000

2004

Operating

­

Stage 2

35,000

2006

Operating

­

Stage 3

62,500

2011

Operating

­

Stage 3-6 Debottleneck

23,000

TBD

Application

­

Stage 4

62,500

2013

Construction

­

Stage 5

62,500

2018

Approved

­

Stage 6

62,500

2019

Approved

­

Lewis

­

Phase 1

40,000

TBD

Updated: Dec 2010

­

Phase 2

40,000

TBD

­

MacKay River

Application Application Updated: Feb 2012

CAPACITY

START-UP

REGULATORY STATUS

Alberta Oilsands Inc. •

Clearwater West

Updated: Jun 2012

Alberta Oilsands says it has responded to a third round of supplemental information requests from the ERCB regarding the project application. The company expects the regulator will hold a public hearing into the project, due in part to its proximity to the Fort McMurray airport. ­

Phase 1 Pilot

­

Phase 2

4,350

TBD

Application

25,000

2016

Announced

Athabasca Oil Corporation ­

Hangingstone

Updated: May 2012

In early March, AOSC responded to its second round of supplemental information requests from the ERCB. The company anticipates regulatory approval in Q3, and has placed orders for more than 75 per cent of long-lead items required for construction. AOSC says tenders received conform to budget and schedule.

Suncor has commenced production from a new phase of six wells at MacKay River and initiated steam injection into additional wells. Production from these developments is expected to offset natural declines in the future.

­

Phase 1

12,000

2014

Application

­

Phase 2

35,000

2017

Announced

­

MR2

40,000

2016

Application

­

Phase 3

35,000

2019

Announced

­

Phase 1

33,000

2002

Operating

BlackPearl Resources Inc. •

Sunshine Oilsands Ltd. ­

Harper

Updated: May 2012

Sunshine says that steam cycle injection operations at Harper have proved thermally induced oil mobility. 1,000

2011

Blackrod

Updated: Jun 2012

BlackPearl says production from the pilot has reached commercial production rates. The company has filed the regulatory application for the full 80,000-barrel-per-day project. ­

Phase 1

20,000

2016

Application

­

Phase 2

30,000

2018

Application

Application

­

Phase 3

30,000

2021

Application

Announced

­

Pilot

800

2011

Operating

­

Carbonate Pilot

Operating

­

Legend Lake

­

Phase 1

10,000

2016

­

Phase 2

10,000

TBD

­

Phase 2 Expansion

10,000

TBD

Announced

­

Phase 3

20,000

TBD

Announced

­

Phase 3 Expansion

10,000

TBD

­

Thickwood

Updated: May 2012

Announced Updated: May 2012

Sunshine Oilsands has submitted the regulatory application for its Thickwood SAGD project, anticipating project start-up in 2015. ­

Phase 1

10,000

2015

Application

­

Phase 2

20,000

2018

Announced

­

Phase 2 Expansion

20,000

2021

Announced

­

West Ells

Updated: May 2012

Sunshine says that following regulatory approval, its external reservoir engineering firm, GLJ Petroleum Consultants, considers the project to have a high degree of certainty of implementation and that development will proceed.

Canadian Natural Resources Limited •

Gregoire Lake

Updated: Jun 2012

Canadian Natural says first steam for Phase 1 is expected in 2021, and 2025 for Phase 2. ­

Phase 1

40,000

2021

­

Phase 2

40,000

2025

Grouse

Announced Announced Updated: Jun 2012

Regulatory application filed in May. Canadian Natural says it plans to file a regulatory expansion for an expansion at Grouse in 2012. ­

Commercial

Kirby North

50,000

2018

Application Updated: Jun 2012

Canadian Natural says construction preparation work is underway for Kirby North Phase 1, including construction of the main access road and site clearing for the plant. The company plans to complete the engineering design specifications for Phase 1 in 2012. ­

Phase 1

40,000

2016

­

Phase 2

40,000

2019

­

Kirby South

Application

­

A Phase 1

5,000

2013

Construction

­

A Phase 2

5,000

2014

Approved

­

A Phase 3

20,000

2018

Announced

­

B Phase 1

20,000

2020

Announced

Canadian Natural says construction of Phase 1 is 42 per cent complete and remains on-cost and onschedule for first steam in 2013. The fourth of seven well pads is being drilled, with wells reportedly confirming geological expectations.

­

B Phase 2

20,000

TBD

Announced

­

Phase 1

40,000

2013

Construction

­

C Phase 1

30,000

TBD

Announced

­

Phase 2

20,000

2020

Application

Long on expertise, short on bureaucracy

Application Updated: May 2012

experience • exceLLence • execution

As SAGD specialists, PROJEX brings proven rigor to oil sands thermal engineering projects. What we don’t bring is red tape and bureaucracy. Give us a call. We’d welcome the chance to show you the PROJEX difference. Contact Scott Rempel at 403.705.4151.

38 OILSANDS REVIEW | AUGUST 2012


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

Cavalier Energy Inc. ­

CURRENT PROJECT

­

Hoole

Updated: May 2012

Cavalier owner Paramount Resources says that during the first quarter, Cavalier continued to build its management team with the addition of key technical personnel. The Hoole project application is expected to be submitted in Q4.

Pelican Lake Grand Rapids

Phase A

60,000

2017

Application

Phase B

60,000

TBD

Application

­

Phase C

60,000

TBD

Application

­

Pilot

600

2011

Operating

2015

Announced

­

Phase 2

30,000

TBD

Announced

­

Phase 3

30,000

TBD

Announced

Connacher Oil And Gas Limited

­

Phase 4

30,000

TBD

Announced

Christina Lake

Updated: May 2012

Great Divide

­

Algar Pod 2

10,000

2010

Operating

­

Expansion 1A

12,000

2014

Application

­

Expansion 1B

12,000

2016

Application

­

Pod 1

10,000

2007

Operating

Phase 1

27,000

2007

Operating

­

Phase 2

109,000

2015

Construction

­

Pilot

1,200

1997

Operating

Phase 1A

10,000

2002

Operating

­

Phase 1B

8,800

2008

Operating

­

Phase C

40,000

2011

Operating

­

Phase D

40,000

2012

Construction

ConocoPhillips Canada Limited

­

Phase E

40,000

2013

Construction

­

Surmont

­

Phase F

50,000

2016

Approved

­

Phase G

50,000

2017

Approved

­

Phase H

­

Foster Creek

40,000

2019

Announced Updated: May 2012

Cenovus says it continues to work on fabrication and facility construction for Phase F, earthworks and site preparation for Phase G, and design engineering for Phase H. ­

Phase A

­

Phase B Debottleneck

­

Updated: Jun 2012

Connacher reports that, with its budget constrained for 2012, operational activities include increasing netbacks by reducing operating costs and increasing realized bitumen prices, maintaining production within its announced guidance, de-risking and preparing various short-term projects for bitumen production increases, and improving production with technology innovations such as SAGD+ at Algar and gas re-injection at Great Divide. The company’s strategic review process continues.

­

­

Updated: May 2012

­

10,000

Construction of Phase D is more than three-quarters complete and production is expected in the fourth quarter of this year. Construction of Phase E is more than 40 per cent complete, with production expected in the fourth-quarter of 2013. Site preparation continues for Phase F.

REGULATORY STATUS

­

Phase 1

­

START-UP

Cenovus drilled a second well pair at its Grand Rapids SAGD pilot in Q1.

­

Cenovus Energy Inc.

CAPACITY

Updated: Mar 2012

Devon Canada Corporation ­

Jackfish

Updated: Dec 2011

Devon reports that Jackfish 3 construction is now underway, and that Jackfish 2 volumes are ramping up ahead of plan and on target to reach capacity of 35,000 barrels per day by late 2012.

24,000

2001

Operating

6,000

2003

Operating

Phase C Stage 1

10,000

2005

Operating

­

Phase C Stage 2

20,000

2007

Operating

­

Phase D

30,000

2009

Operating

­

Phase E

30,000

2009

Operating

Devon filed the regulatory application for all three phases of the Pike project in June. The company says facility construction and SAGD drilling for the first phase will begin in late 2013 or early 2014, pending corporate approvals.

­

Phase F

45,000

2014

Construction

­

1A

35,000

2016

Application

­

Phase G

40,000

2015

Approved

­

1B

35,000

2017

Application

­

Phase H

40,000

2016

Approved

­

1C

35,000

2018

Application

Announced

Grizzly Oil Sands Ulc

­

Phase I

Narrows Lake

45,000

2017

Updated: Jun 2012

­

Phase 1

35,000

2007

Operating

­

Phase 2

35,000

2011

Operating

­

Phase 3

35,000

2015

Pike

­

Construction Updated: Jun 2012

Algar Lake

Updated: May 2012

­

Phase 1

43,333

2016

Approved

Part-owner Gulfport Energy says Grizzly’s Algar construction is on track for commissioning in Q4, with first production in mid-2013. Grizzly also believes it has delineated sufficient resource at Thickwood Hills to support commercial development of the property and plans to submit a project regulatory application in 2012.

­

Phase 2

43,333

TBD

Approved

­

Phase 1

5,650

2013

Construction

­

Phase 3

43,334

TBD

Approved

­

Phase 2

5,650

2014

Approved

Narrows Lake regulatory approval granted in late May. Sanction by partners Cenovus and ConocoPhillips Canada anticipated later this year.

SOUND SOLUTIONS 822403 Learn how our Quantitative Interpretation (QI) expertise in the oil sands improves reservoir understanding and enhances recovery. sound-qi.com

Sound QI Inc 1/4h · tqc SOUND SCIENCE. SOUND RESULTS. SOUND QI. no stacking

AUGUST 2012 | OILSANDSREVIEW.COM 39


P R O J E C T S TAT U S

CURRENT PROJECT

­

CAPACITY

START-UP

May River

REGULATORY STATUS

Updated: Apr 2012

Grizzly has closed its acquisition of May River from Petrobank Energy and Resources. Development plans are under review. ­

Phase 1

10,000

2013

Application

­

Subsequent Phases

90,000

TBD

Disclosed

Harvest Operations Corp.

CURRENT PROJECT

CAPACITY

REGULATORY STATUS

START-UP

MEG Energy Corporation ­

Christina Lake

Updated: May 2012

MEG says it has achieved a significant reduction in its steam to oil ratios through the introduction of infill wells and non-condensable gas injection. For Phase 2B, MEG says detailed engineering is more than 96 per cent complete, and all materials and modules have been ordered, with delivery and onsite construction expected to continue through 2012 and into 2013. The company says the project remains on schedule and budget. For Phase 3, MEG says engineering work is underway to determine the optimum size and schedule of project phases. ­

Phase 1 Pilot

3,000

2008

Operating

Harvest says its 2012 activities for BlackGold will consist of module assembly, facility construction and drilling of 15 SAGD well pairs.

­

Phase 2A

22,000

2009

Operating

­

Phase 2B

35,000

2013

Construction

­

Phase 1

10,000

2014

Construction

­

Phase 3A

50,000

2016

Approved

­

Phase 2

20,000

2015

Application

­

Phase 3B

50,000

2018

Approved

­

Phase 3C

50,000

2020

­

Surmont

­

BlackGold

Updated: May 2012

Husky Energy Inc. ­

McMullen

Updated: May 2012

Approved Updated: May 2012

Husky says that during Q1, 24 slant wells drilled in 2011 were put on cold production. At the air injection pilot, three horizontal well producers were drilled to further evaluate the resource.

MEG plans to file its regulatory application for Surmont in the second half of 2012. ­

Phase 1

60,000

2018

Announced

­

­

Phase 2

60,000

TBD

Announced

Air Injection Pilot-Experimental

755

2012

Construction

N-SOLV Corporation

Japan Canada Oil Sands Limited ­

Hangingstone

Updated: Jan 2012

Dover

Updated: Jun 2012

JACOS owner Japan Petroleum Exploration is delaying a decision on an expansion at Hangingstone until mid-2012 due to a delay in regulatory approval.

Reports are that first results from a $60-million N-Solv field test are expected in spring 2013.

­

Expansion

Nexen Inc.

­

Hangingstone Pilot

­

Pilot

35,000

2016

11,000

1999

Application Updated: Jan 2012 Operating

Koch Exploration Canada Corporation

­ •

Demonstration Plant

500

2012

Long Lake

Announced Updated: Jun 2012

Nexen says it has reached two key milestones in its strategy to fill the Long Lake upgrader: first production from one new well pad (ahead of schedule) and steam injection into another. The company says ramp-up is continuing at yet another pad and construction is underway on two more.

Updated: Jun 2012

­

Long Lake South (Kinosis) Phase 1

40,000

TBD

Approved

Koch’s Canadian subsidiaries are seeking a strategic investor to advance development and monetize certain oilsands interests including the Muskwa asset.

­

Long Lake South (Kinosis) Phase 2

40,000

TBD

Approved

­

Phase 1

72,000

2008

Operating

­

­

Phase 2

72,000

TBD

Approved

­

Phase 3

72,000

TBD

Application

­

Phase 4

72,000

TBD

Announced

Muskwa

Pilot

10,000

2015

Application

Laricina Energy Ltd. •

Germain

Updated: Jun 2012

Laricina says detailed engineering is 80 per cent complete. Procurement of long-lead items is complete, piling commenced in January and modules began being transported to the site in March. The company has applied to add a fourth once-through steam generator and associated equipment due to anticipated reservoir behaviour.

Statoil •

Kai Kos Dehseh

Updated: Jun 2012

Statoil says its next projects will be an expansion to Leismer, and the Corner project. Corner will be sanctioned in late 2013 or in early 2014.

­

Phase 1 CDP

5,000

TBD

Construction

­

Corner

40,000

2017

Approved

­

Phase 2

30,000

2015

Application

­

Corner Expansion

40,000

TBD

Application

­

Phase 3

60,000

TBD

Application

­

Hangingstone

20,000

TBD

Application

­

Phase 4

60,000

TBD

Application

­

Leismer Commercial

10,000

TBD

Approved

­

Saleski

­

Leismer Demonstration

10,000

2010

Operating

­

Leismer Expansion

20,000

TBD

Approved

­

Leismer Northwest

20,000

TBD

Application

­

Leismer South

20,000

TBD

Application

Updated: May 2012

Laricina says an additional well pair has been drilled at the pilot, awaiting tie-in for steaming in Q2. Production and injection cycles are ongoing. The company has responded to the first round of supplemental information requests from the regulator regarding the commercial project application. ­

Phase 1

­

Pilot

40 OILSANDS REVIEW | AUGUST 2012

10,700

2014

Application

­

Thornbury

40,000

TBD

Application

1,800

2011

Operating

­

Thornbury Expansion

20,000

TBD

Application


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

Suncor Energy Inc. ­

Chard

­

Phase 1

Updated: Dec 2010 40,000

TBD

Announced

­

Meadow Creek

­

Phase 1

40,000

TBD

Updated: Dec 2010 Approved

­

Phase 2

40,000

TBD

Approved

Surmont Energy Ltd. ­

Wildwood

­

Phase 1

Updated: Apr 2012 12,000

2015

Announced

Value Creation Inc. ­

Advanced TriStar

Updated: May 2012

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

­

Phase 11-13

30,000

2002

Operating

­

Phase 14-16

40,000

2014

Construction

Koch Exploration Canada Corporation •

Gemini

Updated: Jun 2012

Koch’s Canadian subsidiaries are seeking a strategic investor to advance development and monetize certain oilsands interests including the Cold Lake (Gemini) asset. ­

Stage 1

1,200

TBD

Approved

­

Stage 2

10,000

TBD

Approved

Osum Oil Sands Corp. ­

Taiga

Updated: Apr 2012

The ERCB has scheduled a public hearing into the Taiga project for May 23.

Value Creation says it is preparing the regulatory application for the Advanced TriStar project.

­

Phase 1

23,000

2016

Application

­

ATS-1

15,000

2016

Announced

­

Phase 2

22,000

2017

Application

­

ATS-2

30,000

2019

Announced

Pengrowth Energy Corporation

­

ATS-3

30,000

2022

Announced

COLD LAKE REGION — IN SITU Birchwood Resources Inc. •

Sage

Updated: Jun 2012

Birchwood has released its public disclosure document and has held an open house with area residents, some of whom were concerned by the development. ­

Pilot

5,000

2015

Announced

Canadian Natural Resources Limited •

Primrose & Wolf Lake

Updated: Jun 2012

Canadian Natural says its near-term priorities at Primrose include maximizing steam-plant utilization by adding pads, a future facility debottleneck/expansion, assessment of a potential Grand Rapids formation expansion, and optimization of steaming techniques to improve on the 15 per cent recovery factor. Two pilots will be conducted in 2012.

­

Lindbergh

­

Phase 1 Commercial

12,500

2014

Application

­

Phase 2 Commercial

17,500

2016

Announced

­

Pilot

1,200

2012

Operating

Royal Dutch Shell plc •

Orion

­

Phase 1

10,000

2007

Operating

Phase 2

10,000

TBD

Approved

­

Primrose East

32,000

2008

Operating

­

Primrose North

30,000

2006

Operating

PEACE RIVER REGION — IN SITU

­

Primrose South

45,000

1985

Operating

Wolf Lake

13,000

1985

Operating

Devon Canada Corporation •

Walleye

Updated: Jun 2012

Andora Energy Corporation •

Sawn Lake

­

­

Northern Alberta Oil Ltd.

9,000

2015

Application

Husky Energy Inc. ­

Caribou

­

Demonstration

­

Tucker

­ Updated: Nov 2010 10,000

TBD

Approved Updated: Feb 2012

Production at Tucker has increased significantly, exiting 2011 at over 9,000 barrels per day versus 4,000 barrels per day the previous year. Husky says it has addressed subsurface challenges by remediating older wells with new completion and stimulation techniques and initiating revised start-up procedures. ­

Phase 1

30,000

2006

Operating

Imperial Oil Limited ­

Cold Lake

Updated: May 2012

Imperial says drilling has been completed at Cold Lake on a three-well cyclic solvent process pilot that is expected to start up in late 2013. ­

Phase 1-10

110,000

1985

Operating

Updated: Jun 2012

Andora Energy majority owner PanOrient Energy Corp. anticipates that activities related to the Sawn Lake asset will come into focus over the remainder of 2012, with a clear course of action to be communicated shortly after the sale of assets in Thailand, which occured in mid-June.

Devon filed its regulatory application for Walleye in June. The company says construction will start in 2013. Phase 1

Updated: Jun 2012

Shell is looking to sell the Orion property, reportedly to focus on in situ operations at Peace River.

­

­

Updated: May 2012

Pengrowth achieved first steam at the Lindbergh pilot in February. The company says the reservoir is responding to steam injection and production performance so far indicates good oil mobility, straightforward treating and minimal solids production, all of which are encouraging at this early stage. Full SAGD operations are expected in Q2.

SAGD Demonstration

1,400

TBD

Sawn Lake

Approved Updated: Mar 2012

Company owner Deep Well Oil & Gas says DeGolyer & MacNaughton Canada has completed its reservoir modelling for a proposed horizontal cyclic steam stimulation pilot at Sawn Lake, concluding the project would yield commercial viable extraction. Deep Well is currently preparing a pilot plan and options for capitalization. ­

CSS Pilot

700

TBD

Approved

Petrobank Energy And Resources Ltd. ­

Dawson

Updated: May 2012

Petrobank says it has concluded that the Dawson reservoir would benefit from being pre-conditioned for THAI operations by producing conventional cold heavy oil from the current horizontal production wells. The two-well THAI pilot is now expected in 2013, with commercial development to follow, subject to operational success. ­

Phase 2

­

THAI Demonstration-Experimental

10,000

TBD

Announced

TBD

2013

Construction

AUGUST 2012 | OILSANDSREVIEW.COM 41


P R O J E C T S TAT U S

CURRENT PROJECT

CAPACITY

START-UP

REGULATORY STATUS

Royal Dutch Shell plc ­

Updated: Dec 2011

Alberta’s environmental assessment director has deemed complete Shell Canada’s environmental impact assessment report for the Carmon Creek expansion. Cadotte Lake

­

Carmon Creek - Phase 1

­

Carmon Creek - Phase 2

12,500

1986

Operating

40,000

2015

Application

40,000

2018

Application

Southern Pacific Resource Corp. ­

Red Earth

Updated: May 2012

Southern Pacific is analyzing results from its latest CSS test at Red Earth. The company says it will finalize future development plans by the end of Q2. ­

Commercial

­ ­

10,000

TBD

Announced

Pilot

1,000

2009

Operating

Pilot Expansion

3,000

TBD

Announced

SASKATCHEWAN REGION — IN SITU Oilsands Quest Inc. •

Axe Lake

Updated: Jun 2012

Oilsands Quest says that some of the bids received to acquire, restructure or recapitalize its business could, if subject to further negotiation, be capable of being brought before the court for approval. The company and its court-appointed monitor, Ernst & Young Inc., have agreed that the best interests of Oilsands Quest and its stakeholders will be best served if Ernst & Young takes over operational responsibilities, including completion of a transaction. ­

Commercial

TBD

On Hold

­

Reservoir Test

600

2008

On Hold

­

SAGD Pilot

TBD

TBD

On Hold

30,000

NORTH ATHABASCA REGION — UPGRADER Terre de Grace

­

Pilot

START-UP

REGULATORY STATUS

Updated: Mar 2012 8,400

­

Mildred Lake/Aurora North & South

Updated: May 2012

Construction is underway on a number of major projects including mine train replacement and relocation, the Aurora North Tailings Management Project, the Syncrude Emissions Reduction Project and the Centrifuge Tailings Management Project. ­

Base Plant Stage 1 & 2 Debottleneck

­

Stage 3 Debottleneck

­

Stage 3 Expansion (UE-1)

250,000

1978

Operating

75,000

TBD

Announced

100,000

2006

Operating

SOUTH ATHABASCA REGION — UPGRADER Nexen Inc. •

Long Lake

Updated: Jun 2012

Nexen says it has reached two key milestones in its strategy to fill the Long Lake upgrader: first production from one new well pad (ahead of schedule) and steam injection into another. The company says ramp-up is continuing at yet another pad and construction is underway on two more. ­

Phase 1

58,500

2008

Operating

­

Phase 2

58,500

TBD

Approved

­

Phase 3

58,500

TBD

Application

­

Phase 4

58,500

TBD

Announced

Value Creation Inc. ­

Advanced TriStar

Updated: May 2012

Value Creation says it is preparing the regulatory application for the Advanced TriStar project. ­

ATS-1

12,750

2016

Announced

­

ATS-2

25,500

2019

Announced

­

ATS-3

25,500

TBD

Announced

INDUSTRIAL HEARTLAND REGION — UPGRADER

BP p.l.c. ­

CAPACITY

Syncrude Canada Ltd.

Peace River

­

CURRENT PROJECT

TBD

Approved

Canadian Natural Resources Limited

North West Upgrading Inc. ­

Redwater Upgrader

Updated: Feb 2012

Final sanction is anticipated in 2012. ­

Phase 1

77,000

2013

Approved

Canadian Natural says that during the first quarter, a third ore preparation plant and associated hydrotransport unit were successfully integrated into operations. The infrastructure is expected to increase reliability going forward by allowing the company to maintain steady feedstock to the upgrader with two of the three ore preparation plants continually on stream.

­

Phase 2

77,000

2018

Approved

­

Phase 3

77,000

TBD

Approved

­

Operating

­

Twenty per cent project partner Marathon Oil Corporation says volumes were down from the Athabasca Oil Sands project during Q1 due to reliability issues. Alberta’s environmental impact assessment director has deemed complete the environmental impact assessment report for Shell Canada’s Quest carbon capture and storage project from the Scotford upgrader.

­

Horizon

Phase 1

Updated: May 2012

114,000

2009

­

Phase 2A

10,000

2014

Approved

­

Phase 2B

45,000

TBD

Approved

­

Phase 3

80,000

TBD

Approved

­

Tranche 2

5,000

2012

Operating

Ivanhoe Energy Inc. ­

Tamarack

Updated: May 2012

Ivanhoe says it has received a second round of supplemental information requests regarding its project application from the ERCB. It continues to expect approval in 2012. ­

Phase 1

34,784

2014

Application

Suncor Energy Inc. ­

Base Operations

Updated: May 2012

Suncor is now mining volumes from tne North Steepbank Extension. The company expects that its Millennium Naphtha Unit (MNU) project will be fully operational by mid-year. In April, Suncor announced its upgrader had successfully returned to normal operations following a brief shutdown due to a fractionated performance issue. Suncor has started commissioning assets associated with its tailings reduction operations infrastructure project and anticipates to start using these assets during Q2. ­

Millennium Coker Unit

97,000

2008

Operating

­

Millennium Vacuum Unit

35,000

2005

Operating

­

U1 and U2

225,000

1967

Operating

­

Fort Hills

Updated: May 2012

Suncor says current work on Fort Hills includes progressing design basis memorandum engineering, site preparation and procurement for long-lead items. The company expects to present development plans to the board of directors for sanction in 2013.

Shell Albian Sands Scotford Upgrader 1

­

Commercial

­

Expansion

Updated: May 2012

158,000

2003

Operating

91,000

2011

Operating

Value Creation Inc. ­

Heartland

Updated: Nov 2010

Construction was suspended in September 2008. ­

Phase 1

46,300

TBD

On Hold

­

Phase 2

46,300

TBD

Approved

­

Phase 3

46,300

TBD

Approved

new export pipelines Enbridge •

Northern Gateway

Updated: Jun 2012

The joint review panel conducting the Gateway review has finalized the schedule for the remaining public hearings. The questioning phase of the of the final hearings will start in September. Final arguments will take place April 2013, with report and findings to follow in December 2013. Alberta to Kitimat, B.C.

525,000 plus 70,000 diluent line

2017

Application

Kinder Morgan Canada •

Trans Mountain Expansion (TMX)

Updated: Jun 2012

­

Phase 1

145,000

TBD

On Hold

Regulatory application to be filed late in 2013. Kinder Morgan confirms committed shippers as BP Canada, Canadian Oil Sands Limited, Cenovus Energy Inc., Devon Canada Corporation, Husky Energy, Imperial Oil Limited, Nexen, Statoil Canada and Tesoro Canada.

­

Phase 2 & 3

145,000

TBD

On Hold

­

­

Voyageur Upgrader 3

Updated: May 2012

Suncor says that current work is on validating project scope, developing the project execution plan, engineering and progressing site preparation. The company and its partner plan to submit development plans to their respective boards of directors for sanction in 2013. ­

Phase 1

127,000

2016

Approved

­

Phase 2

63,000

TBD

Approved

42 OILSANDS REVIEW | AUGUST 2012

Edmonton to Burnaby, B.C., Washington Expansion up State and offshore to 850,000

2017

Announced

TransCanada Pipelines •

Keystone Expansion

Updated: Jun 2012

The U.S. Department of State has confirmed its expectation to issue a decision on the Keystone XL pipeline, with its realigned route around the Nebraska Sand Hills, by the first quarter of 2013. Cushing, Okla., to U.S. Gulf Coast

500,000

TBD

Application