P R O J E C T STATUS
project status
02 13
Athabasca Region Industrial Heartland Region Cold Lake Region
Sourced from company releases, the Energy Resources Conservation Board and the Daily Oil Bulletin, with files from Strategy West. For changes and updates, please contact Deborah Jaremko at djaremko@junewarren-nickles.com. Disclaimer: Oilsands Review accepts no liability for errors or inaccuracies in the information provided in this report.
For more detailed project data, visit oilsandsreview.com. To explore projects in the Athabasca oilsands region using our interactive web tool, visit the Canadian Oilsands Navigator at navigator.oilsandsreview.com.
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
Peace River Region Northwestern Saskatchewan
NORTH ATHABASCA REGION
SASKATCHEWAN REGION
SOUTH ATHABASCA REGION
INDUSTRIAL HEARTLAND REGION
COLD LAKE REGION
NEW Export Pipelines
PEACE RIVER REGION
CURRENT PROJECT
NORTH ATHABASCA REGION — MINING
•
New information this month
CAPACITY
REGULATORY STATUS
START-UP
Fort Hills
Updated: Dec 2012
Suncor and partner Total continue to review development timelines for Fort Hills.
Canadian Natural Resources Limited Horizon
Updated: Dec 2012
Debottleneck
Canadian Natural says it continues its strategy of staged expansion to 250,000 barrels per day and work remains on track. Projects currently under construction are trending at or below estimates.
Phase 1
Phase 1
Voyageur South
25,000
TBD
165,000
2016
Approved Approved Updated: May 2012
135,000
2008
Operating
Phase 2A
10,000
2014
Construction
Phase 2B
45,000
TBD
Approved
Phase 3
80,000
TBD
Approved
Tranche 2
5,000
2012
Operating
Syncrude has announced it is embarking on a new mine extension project at Mildred Lake, which will be known as the MLX project. Canadian Oil Sands says MLX will leverage investment in the two mine trains currently being constructed, enabling Syncrude to extend the life of Mildred Lake mining operations by about a decade. Project scoping is underway, and pending regulatory approval, construction and spending would commence in the next 10 years.
Imperial Oil Limited •
Kearl
Updated: Jan 2013
Imperial Oil says that start-up of Kearl is underway—which was supposed to start operating in December—but is delayed due to cold weather and earlier issues with transportation of modules from Korea.
Phase 1
110,000
2013
Construction
Phase 2
110,000
2015
Construction
Phase 3 Debottleneck
70,000
2020
Approved
Jackpine
Expansion
100,000
2017
Application
Phase 1A
100,000
2010
Operating
Phase 1B
100,000
TBD
Approved
Muskeg River Commercial
Expansion & Debottlenecking
Pierre River
Phase 1
120,000
TBD
Application
Syncrude Canada Ltd. Mildred Lake/Aurora
Updated: Oct 2012
Aurora South Train 1
100,000
2016
Approved
Aurora South Train 2
100,000
2018
Approved
Base Mine Stage 1 & 2 Expansion
290,700
1978
Operating
Stage 3 Expansion
116,300
2006
Operating
Frontier
Updated: Dec 2012
A decision from the federal joint review panel on the Jackpine project is expected in May 2013.
Teck Resources Limited
Shell Albian Sands •
Suncor considers Voyageur South to be a “longer-term” project and has not confirmed a start-up date.
Phase 1
75,000
2021
Application
Phase 2
80,000
2024
Application
Phase 3
80,000
2027
Application
Operating
Phase 4 Equinox
40,000
2030
Application
Approved
Total E&P Canada Ltd.
Updated: Nov 2012 155,000 115,000
2002 TBD
Updated: Aug 2012
A joint review panel of the Canadian Environmental Assessment Agency and Energy Resources Conservation Board has been established to review the proposed Pierre River mine project. The timeline for the joint review panel to submit its report is 550 days (18 months) from coming into force in July 2012.
Phase 1
100,000
2018
Application
Phase 2
100,000
TBD
Application
Suncor Energy Inc. Base Operations
Updated: Oct 2012
Teck says it received the final supplemental information requests relating to the Frontier regulatory application in Q3/2012 and anticipates responding in early 2013.
Updated: Dec 2012
Joslyn North Mine
Updated: Jul 2012
Project partner Suncor Energy says submit development plans will be submitted to the companies’ respective boards of directors for a sanctioning decision in 2013.
Phase 1
100,000
2018
Approved
NORTH ATHABASCA REGION — IN SITU Athabasca Oil Corporation Birch
Updated: Dec 2012
AOS says $28.9 million was spent at Birch in the first nine months of 2012, mainly on drilling of one water and 22 delineation wells. In addition, the company shot 54 square kilometres of 3D seismic. Winter delineation drilling and seismic programs are being evaluated for 2013.
Suncor says it has started up its new Millennium Naphtha Unit and has run it at full rates. The unit is expected to stabilize secondary upgrading capacity and provide flexibility during maintenance activ ities for secondary upgrading units in the future.
Millennium Debottlenecking
2008
Operating
Millennium Mine
294,000
1967
Operating
AOS says regulatory approval for the demonstration project is anticipated imminently. The design basis memorandum is complete and the engineering design specification work is well underway. Construction is also ongoing on a TAGD-related heater assembly facility near Strathmore, Alta.
North Steepbank Extension
180,000
2012
Operating
Phase 1 Demonstration
6,000
2015
Application
Steepbank Debottleneck Phase 3
4,000
2007
Operating
Phase 2 Demonstration
6,000
TBD
Application
40 OILSANDS REVIEW | February 2013
23,000
Phase 1
12,000
TBD
Dover West Carbonates (Leduc)
Announced Updated: Dec 2012
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
Dover West Sands & Clastics
REGULATORY STATUS
Updated: Dec 2012
In the first nine months of 2012, AOS acquired approximately 30,000 acres of oilsands leases contiguous to its existing Dover West assets. The company says its Dover West Sands project could now eventually support development up to 270,000 barrels per day. Regulatory approval and internal sanction for the first 12,000-barrel-per-day phase are expected in 2013. AOS says it is leveraging work done on FEED for its Hangingstone project for Dover West.
Phase 1
12,000
2015
Application
Phase 2
35,000
2018
Announced
Phase 3
35,000
2020
Announced
Phase 4
35,000
2022
Announced
Phase 5
35,000
2024
Announced
CURRENT PROJECT
Updated: May 2012
Pilot
10,000
TBD
Approved
REGULATORY STATUS
Thickwood
Updated: Dec 2012
At the end of Q3/2012 Grizzly part owner Gulfport Energy said a regulatory application for the Thickwood project was expected by year-end 2012.
Phase 1
6,000
2017
Application
Phase 2
6,000
TBD
Application
Husky Energy Inc. Saleski
Updated: Dec 2012
Husky plans to submit a regulatory application for the Saleski project in 2013.
Carbonate Pilot
TBD
2016
Sunrise
Terre de Grace
BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources.
START-UP
Grizzly Oil Sands ULC
BP p.l.c.
CAPACITY
Announced Updated: Dec 2012
Husky says Sunrise continues to meet its construction milestones and remains on schedule for first oil in 2014. All significant contracts for Phase 1, including the central processing facility, have now been converted to lump sum payment. Over 85 per cent of the project costs are now fixed. Planning, design and engineering for the next phase of development continues.
Phase 1
60,000
2014
Construction
Phase 2
50,000
2016
Approved
Phase 3
50,000
TBD
Approved
Phase 4
50,000
TBD
Approved
40,000
TBD
Canadian Natural Resources Limited
Birch Mountain
Updated: Jul 2012
Canadian Natural says geological scoping is underway.
Phase 1
60,000
2019
Announced
Phase 2
60,000
2023
Announced
Cenovus Energy Inc.
East McMurray
Phase 1
Steepbank
Phase 1
•
Telephone Lake Borealis
Updated: Aug 2012 30,000
TBD
Announced Updated: Aug 2012
30,000
TBD
Announced Updated: Dec 2012
Cenovus says it continues to progress the Telephone Lake regulatory application while it operates its dewatering pilot, with water production and air injection proceeding as planned.
Phase A Phase B
45,000 45,000
TBD TBD
Application Application
Dover Operating Corp. Dover
Updated: Dec 2012
Athabasca Oil Corporation is planning a likely sale of its stake in the Dover project to partner (and Dover OpCo owner PetroChina) once the previously determined decision trigger mechanism of regulatory approval is granted.
Dover North Phase 1
50,000
2016
Application
Dover North Phase 2
50,000
2018
Application
Dover South Phase 3
50,000
2020
Application
Imperial Oil Limited
Aspen
Phase 1
Updated: Sep 2012 Announced
Ivanhoe Energy Inc. Tamarack
Updated: Dec 2012
Ivanhoe is responding to a third round of supplemental information requests from regulators regarding its project application. Approval is now anticipated in 2013.
Phase 1
20,000
2016
Application
Phase 2
20,000
TBD
Application
Marathon Oil Corporation
Birchwood
Updated: Jul 2012
Marathon said that based on results of completed appraisal drilling, a regulatory application would be filed in 2012.
Demonstration
12,000
2016
Application
N-Solv Corporation
Dover
Updated: Jun 2012
Reports are that first results from a $60-million N-Solv field test are expected in spring 2013.
Demonstration Plant
500
2013
1,720
2013
Construction
Oak Point Energy Ltd.
Dover South Phase 4
Dover South Phase 5
Mackay River
50,000 50,000
2022 2024
Application
Lewis
Application
Pilot
Updated: Apr 2012
Updated: Mar 2012 Application
SilverWillow Energy Corporation Audet
ERCB project approval granted January 2012. Dover OpCo says construction is underway.
Updated: Dec 2012
Phase 1
35,000
2014
Construction
Phase 2
40,000
2017
Approved
SilverWillow says engineering consultants have been selected to prepare preliminary engineering design and cost estimates for Audet production facilities and infrastructure, to conduct environmental baseline studies and to provide support for the regulatory application, which is expected to be filed in the second half of 2013.
Phase 3
40,000
2019
Approved
Approved
Southern Pacific Resource Corp.
Phase 4
35,000
TBD
E-T Energy Ltd.
Poplar Creek
Updated: Oct 2012
E-T Energy has reinstated Bruce McGee as CEO based on his technological expertise as it works on pilot operations to support a new commercial project application. Its previous application was denied by the ERCB in 2012.
Experimental Pilot
Pilot
12,000
2016
STP-McKay
Announced
Updated: Oct 2012
Southern Pacific says operations are progressing as planned, with the first of the well pairs now being converted from steam circulation to bitumen production.
Phase 1
Phase 1 Expansion
12,000
2012
Operating
6,000
2014
Application
1,000
2007
Operating
Phase 1
10,000
TBD
Announced
Phase 2A
12,000
2017
Application
Phase 2
40,000
TBD
Announced
Phase 2B
6,000
2017
Application
FEbruary 2013 | OILSANDSREVIEW.COM 41
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
CURRENT PROJECT
Suncor Energy Inc.
CAPACITY
START-UP
West Ells
Firebag
Updated: Dec 2012
Suncor reports it has achieved first oil from Firebag Stage 4, approximately three months ahead of schedule. Production has now reached 130,000 barrels per day.
Cogeneration and Expansion
25,000
2007
Operating
Stage 1
35,000
2004
Operating
Stage 2
35,000
2006
Operating
Stage 3
42,500
2011
Operating
Stage 3-6 Debottleneck
23,000
TBD
Application
Stage 4
42,500
2012
Operating
Stage 5
62,500
2018
Approved
Stage 6
62,500
2019
Approved
Lewis
Phase 1
40,000
TBD
Phase 2
40,000
TBD
MacKay River
MR2
40,000
2016
Application
Phase 1
33,000
2002
Operating
Updated: Dec 2012
Sunshine says construction on West Ells remains on schedule and on budget. The access road is now complete and ready for heavy hauls, and pilings for the central processing facility have commenced. Some of the major equiptment is in transit. Civil construction of the central processing facility is 40 per cent complete, with facilities engineering 75 per cent complete. The first SAGD well pair has been spudded.
A Phase 1
5,000
2013
Construction
A Phase 2
5,000
2014
Approved
A Phase 3
20,000
2018
Announced
B Phase 1
20,000
2020
Announced
B Phase 2
20,000
TBD
Announced
C Phase 1
30,000
TBD
Announced
SOUTH ATHABASCA REGION — IN SITU Alberta Oilsands Inc. Clearwater West
Updated: Nov 2012
Phase 1 Pilot
Application
Phase 2
Sunshine Oilsands Ltd.
Harper
Updated: May 2012
Sunshine says that steam cycle injection operations at Harper have proved thermally induced oil mobility.
Updated: Dec 2012
Alberta Oilsands says it has restructured key consultants to consolidate costs as it pushes to permit the Clearwater project. The company has retained Petrospec Engineering to spearhead and project manage the ongoing project application process with regulators.
Application
Updated: Nov 2012
REGULATORY STATUS
4,350
TBD
Application
25,000
2016
Announced
Athabasca Oil Corporation Hangingstone
Updated: Dec 2012
AOS has sanctioned the first phase of its $536 million Hangingstone SAGD project at a projected cost of $44,700 per flowing barrel. SAGD drilling is expected to commence mid-2013.
Phase 1
12,000
2014
Construction
Phase 2
35,000
2017
Announced
Phase 3
35,000
2019
Announced
BlackPearl Resources Inc.
Carbonate Pilot
1,000
2011
Legend Lake
Operating Updated: Dec 2012
Sunshine says regulatory approval for Legend Lake is anticipated in the first half of 2013.
A Phase 1
10,000
2016
Application
A Phase 2
20,000
TBD
Announced
B Phase 1
20,000
TBD
Announced
Thickwood
Updated: Dec 2012
Sunshine says FEED for Thickwood is approximately 10 per cent complete. Approval is anticipated in the first half of 2013.
A Phase 1
10,000
2015
Application
Blackrod
Updated: Dec 2012
BlackPearl says its Blackrod SAGD pilot continues to operate in-line with expectations. Regulatory approval has been received to drill a second horizontal well pair, which will be done Q1/2013. The project management team for the first commercial phase is being assembled and will determine the EPC contractor as one of its initial decisions.
Phase 1
20,000
2015
Application
Phase 2
30,000
2018
Application
Phase 3
30,000
2021
Application
Pilot
800
2011
Operating
Canadian Natural Resources Limited
Gregoire Lake
Updated: Jul 2012
Canadian Natural says geological scoping is underway.
A Phase 2
20,000
2018
Announced
B Phase 1
20,000
2021
Announced
Engineered Fabric Building Solutions
Phase 1
40,000
2021
Announced
Phase 2
40,000
2025
Announced
Fitness Facilities
Available immediately from inventory. Lease or purchase.
Calgary, Alberta
www.sprung.com/oilgas 42 OILSANDS REVIEW | February 2013
1.403.601.2292 Toll Free:
1.800.528.9899
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
Grouse
REGULATORY STATUS
Updated: Dec 2012
Canadian Natural says timing of Grouse has been adjusted to accommodate the potential inclusion of recently acquired lands adjacent to the company’s Kirby area and provide a more balanced capital expenditures profile going forward. First steam at Grouse is now expected between 2017 and 2019.
Commercial
50,000
TBD
Kirby North
•
CAPACITY
START-UP
Foster Creek
REGULATORY STATUS
Updated: Dec 2012
Phase F is now approximately 65 per cent complete, and Cenovus says progress continues to be made on G and H. The company plans to submit a regulatory application for Phase J in 2013.
Future Optimization
15,000
TBD
Announced
Phase A
24,000
2001
Operating
Phase B Debottleneck
6,000
2003
Operating
Phase C Stage 1
10,000
2005
Operating
Phase C Stage 2
20,000
2007
Operating
Phase D
30,000
2009
Operating
Application Updated: Dec 2012
Canadian Natural has budgeted approximately $205 million for Kirby North in 2013 to progress detailed engineering, order modules and construct camp facilities. Project sanction is targeted for the first half of 2013. To accomodate the acquisition of lands adjacent to the Kirby area that Canadian Natural may include in the project, first steam at Phase 1 is now anticipated in 2016.
Phase 1
40,000
2016
Application
Phase 2
40,000
2019
Application
Kirby South
CURRENT PROJECT
Updated: Dec 2012
Phase E
30,000
2009
Operating
Canadian Natural says construction of Phase 1 continues to progress ahead of plan and is now 74 per cent complete, with 89 per cent of capital expenditures committed.
Phase F
45,000
2014
Construction
Phase 1
40,000
2013
Construction
Phase G
40,000
2015
Approved
Phase 2
20,000
2020
Application
Phase H
40,000
2016
Approved
Phase J
50,000
2019
Announced
•
Narrows Lake
Cavalier Energy Inc. Hoole
Updated: Dec 2012
Cavalier submitted the regulatory application for the first phase at Hoole in November 2012. Assuming regulatory approval and favourable market conditions, construction is expected to begin in 2014, with first production in 2015.
Phase 1
10,000
2015
Application
Phase 2
30,000
TBD
Announced
Phase 3
30,000
TBD
Announced
Phase 4
30,000
TBD
Announced
Cenovus Energy Inc. •
Christina Lake
Updated: Dec 2012
Site preparation is underway, with construction of the Phase A plant scheduled to begin in Q3/2013.
Phase 1
45,000
2017
Construction
Phase 2
45,000
TBD
Approved
Phase 3
40,000
TBD
•
Pelican Lake Grand Rapids
Approved Updated: Dec 2012
Cenovus says it anticipates regulatory approval for the commercial Grand Rapids pilot in 2013.
Phase A
60,000
2017
Application
Phase B
60,000
TBD
Application
Phase C
60,000
TBD
Application
600
2011
Updated: Jan 2013
Phase E is about 65 per cent complete, and Phase F construction is advancing. Engineering and design work is underway for Phase G, and Cenovus plans to file the regulatory application for Phase H in 2013.
Future Optimization
12,000
TBD
Announced
Pilot
Phase 1A
10,000
2002
Operating
West Kirby
Phase 1B
8,800
2008
Operating
Phase 1
Winefred Lake
Phase 1
Phase C
40,000
2011
Operating
Phase D
40,000
2012
Operating
Phase E
40,000
2013
Construction
Operating Updated: Aug 2012
30,000
TBD
Announced Updated: Aug 2012
30,000
TBD
Announced
Connacher Oil and Gas Limited
Algar
Updated: Oct 2012
Phase F
50,000
2016
Approved
Phase G
50,000
2017
Approved
Connacher has sold two subsidiaries for proceeds of approximately $200 million, which the company says positions it to “execute a meaningful capital program” including projects designed to increase production and improve netbacks at Algar and Great Divide Pod 1. This could increase production by as much as 5,000 barrels per day over the next 15–24 months.
Phase H
50,000
2019
Announced
Pod 2
Long on expertise, short on bureaucracy
10,000
2010
Operating
experience • exceLLence • execution
As SAGD specialists, PROJEX brings proven rigor to oil sands thermal engineering projects. What we don’t bring is red tape and bureaucracy. Give us a call. We’d welcome the chance to show you the PROJEX difference. Contact Scott Rempel at 403.705.4151.
FEbruary 2013 | OILSANDSREVIEW.COM 43
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
CURRENT PROJECT
•
Hangingstone Pilot
Connacher received regulatory approval for the two-phase, 24,000-barrel-per-day expansion at Great Divide in September 2012. The company says the approval allows it to advance its evaluation of project costs, timing and financing alternatives.
Pilot
Approved
Great Divide
Expansion 1A
Updated: Oct 2012
12,000
2014
CAPACITY
START-UP
REGULATORY STATUS
Updated: Dec 2012 11,000
1999
Operating
Koch Exploration Canada Corporation Muskwa
Updated: Jun 2012
Expansion 1B
12,000
2016
Approved
Koch’s Canadian subsidiaries are seeking a strategic investor to advance development and monetize certain oilsands interests including the Muskwa asset.
Pod 1
10,000
2007
Operating
ConocoPhillips Canada Limited
Pilot
10,000
2015
Application
Laricina Energy Ltd.
Surmont
Germain
Updated: Oct 2012
Updated: Dec 2012
Phase 1
27,000
2007
Operating
Laricina says Germain construction continues on time and on budget. Detailed engineering is complete, approximately 60 per cent of modules have been installed and 80 per cent of module fabrication is complete. Regulatory consultation for the 150,000-barrel-per-day expansion is continuing as planned, and approval is anticipated in 2013.
Phase 2
109,000
2015
Construction
Phase 1 CDP
Pilot
1,200
1997
Operating
ConocoPhillips Canada says engineering for Surmont 2 is expected to be complete and the majority of materials and equipment delivered to site by year end, in anticipation of peak construction in 2013.
Devon Canada Corporation
Jackfish
Updated: Oct 2012
Devon says ramp-up of Jackfish 2 is now approximately two-thirds complete, while construction of the Jackfish 3 project is now approximately 40 per cent complete.
Phase 1
35,000
2007
Operating
Phase 2
35,000
2011
Operating
Phase 3
35,000
2015
Construction
Jackfish East
Expansion
20,000
2018
Pike
Updated: Sep 2012 Announced Updated: Jul 2012
Devon filed the regulatory application for all three phases of the Pike project in June 2012. The company says facility construction and SAGD drilling for the first phase will begin in late 2013 or early 2014, pending corporate approvals. The company has also submitted its environmental impact assessment report for the project.
1A
35,000
2016
Application
1B
35,000
2017
Application
1C
35,000
2018
Application
Grizzly Oil Sands ULC Algar Lake
Updated: Dec 2012
Construction on the first phase at Algar reportedly remains on track for commissioning in Q1/2013 with first production by mid-year.
Phase 1
5,500
2013
Construction
Phase 2
5,500
2014
Approved
May River
Updated: Dec 2012
Grizzly says it anticipates full-field development of its May River asset to ultimately produce more than 75,000 barrels per day using SAGD and its ARMS development model. Part owner Gulfport Energy says 20–25 core holes will be drilled at May River this winter, following which sufficient exploration will have occured to submit the SAGD application.
Phase 1
6,800
TBD
Announced
Phase 2
6,800
TBD
Announced
Harvest Operations Corp. BlackGold
Updated: Dec 2012
5,000
2013
Construction
Phase 2
30,000
2015
Application
Phase 3
60,000
TBD
Application
Phase 4
60,000
TBD
Saleski
Application Updated: Dec 2012
Laricina has filed a project update to the Saleski Phase 1 regulatory application to reflect the change of well configuration to a single horizontal well cyclic SAGD from a dual-well SAGD process.
Experimental Pilot
Phase 1
1,800
2011
Operating
10,700
2015
Application
MEG Energy Corp. •
Christina Lake
Updated: Dec 2012
MEG anticipates it will increase production at Christina Lake by about 20 per cent in 2013 compared to 2012 thanks to its RISER initiative (which includes enhanced modified steam and gas push), and start-up of Phase 2B in the second half of the year.
Phase 1 Pilot
3,000
2008
Operating
Phase 2A
22,000
2009
Operating
Phase 2B
35,000
2013
Construction
Phase 3A
50,000
2016
Approved
Phase 3B
50,000
2018
Approved
Phase 3C
50,000
2020
Approved
Surmont
Updated: Dec 2012
MEG’s environmental impact assessment report for Surmont was filed in late October, while the regulatory application was filed in September. Public consultation is ongoing.
Phase 1
41,000
2018
Application
Phase 2
41,000
TBD
Application
Phase 3
41,000
TBD
Application
Nexen Inc. •
Long Lake
Updated: Dec 2012
CNOOC’s bid to acquire Nexen has been approved by the Canadian government and is expected to close imminently.
Harvest says 15 SAGD well pairs have now been drilled, and engineering is now 80 per cent complete. The site has been cleared and graded and now piling and foundation work is underway. Phase 2 of the project is now in the regulatory process, with approval now anticipated in 2013.
Long Lake South (Kinosis) Phase 1
40,000
TBD
Approved
Long Lake South (Kinosis) Phase 2
40,000
TBD
Approved
Phase 1
10,000
2014
Construction
Phase 1
72,000
2008
Operating
Phase 2
20,000
TBD
Application
Phase 2
72,000
TBD
Approved
Phase 3
72,000
TBD
Application
Phase 4
72,000
TBD
Announced
Husky Energy Inc. McMullen
Updated: Dec 2012
Husky says that 32 slant wells have been drilled for primary production development at McMullen. The company says the air injection pilot is continuing as planned, with further testing planned for Q4/2012.
Air Injection Pilot-Experimental
755
2012
Operating
Japan Canada Oil Sands Limited •
Hangingstone
Updated: Dec 2012
Osum Oil Sands Corp. Sepiko Kesik
Updated: Dec 2012
Alberta Environment has issued the proposed terms of reference for the Sepiko Kesik project. Sepiko Kesik would use SAGD in Grosmont bitumen carbonate formation.
Japan Canada Oil Sands owner JAPEX has sanctioned the Hangingstone expansion project. Project partner Nexen is expected to sanction its share of the development early in 2013.
Phase 1
30,000
2018
Announced
Phase 2
30,000
TBD
Announced
Expansion
44 OILSANDS REVIEW | February 2013
35,000
2016
Application
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
Statoil
Corner
CAPACITY
START-UP
REGULATORY STATUS
Devon Canada Corporation
Kai Kos Dehseh
Updated: Oct 2012
Statoil says its next projects will be an expansion to Leismer, and the Corner project. Corner will be sanctioned late in 2013 or early in 2014. The company has appointed a new president of its Canadian operations, Stale Tungesvik.
CURRENT PROJECT
40,000
2017
Approved
Walleye
Updated: Jun 2012
Devon filed its regulatory application for Walleye in June 2012. The company says construction will start in 2013.
Phase 1
9,000
2016
10,000
TBD
30,000
2006
Application
Husky Energy Inc.
Corner Expansion
40,000
TBD
Application
Caribou
Hangingstone
20,000
TBD
Application
Demonstration
Leismer Commercial
10,000
TBD
Approved
Tucker
Phase 1
Leismer Demonstration
10,000
2010
Operating
Leismer Expansion
20,000
TBD
Approved
Leismer Northwest
Updated: May 2012 Operating
Imperial Oil Limited Cold Lake
Updated: Dec 2012
Imperial says that the Nabiye expansion is progressing on schedule. Facility construction is underway and drilling has commenced on two production pads.
TBD
Application
Leismer South
20,000
TBD
Application
Phase 1-10
110,000
1985
Operating
Thornbury
40,000
TBD
Application
Phase 11-13
30,000
2002
Operating
Thornbury Expansion
20,000
TBD
Application
Phase 14-16
40,000
2014
Construction
Chard
Phase 1
Meadow Creek
Updated: Nov 2012 40,000
TBD
Announced
Phase 1
40,000
TBD
Approved
Phase 2
40,000
TBD
Approved
Updated: Nov 2012
Wildwood
Updated: Oct 2012
Surmont filed its regulatory application in early October, almost exactly one year after being incorporated as a company. Phase 1
Osum Oil Sands Corp.
Taiga
Updated: Oct 2012
Osum received regulatory approval for the 35,000-barrel-per-day Taiga project. The company says it is now considering financing options.
Phase 1
23,000
2016
Approved
Phase 2
22,000
2017
Approved
Pengrowth Energy Corporation
Surmont Energy Ltd.
Approved
20,000
Suncor Energy Inc.
Updated: Nov 2010
12,000
2015
Application
Lindbergh
Updated: Dec 2012
Pengrowth’s board of directors has committed $55 million for critical path-related, long-lead equipment for the Lindbergh project thanks to encouraging pilot performance. More details on the timing and scope of the commercial project are expected early in 2013.
Phase 1 Commercial
12,500
2015
Application
Phase 2 Commercial
17,500
2016
Announced
Value Creation has submitted an environmental assessment report for the Advanced TriStar project.
Pilot
1,200
2012
Operating
ATS-1
15,000
2016
Application
Royal Dutch Shell plc
ATS-2
30,000
2018
Application
ATS-3
30,000
2020
Application
•
TriStar
Pilot
Value Creation Inc. Advanced TriStar
Updated: Dec 2012
Updated: Oct 2012 1,000
2014
Application
COLD LAKE REGION — IN SITU Cold Lake
Updated: Dec 2012
Baytex says it will build facilities and drill one SAGD well pair in 2013. Following successful oper ations of this pilot, the company will proceed with construction of the 5,000-barrel-per-day first commercial phase in 2014.
Commercial
5,000
2016
Approved
Pilot
1,200
TBD
Approved
Birchwood Resources Inc.
Sage
Updated: Jun 2012
Birchwood has released its public disclosure document and has held an open house with area residents, some of whom were concerned by the development.
Pilot
5,000
2015
Announced
Canadian Natural Resources Limited Primrose & Wolf Lake
Updated: Dec 2012
Canadian Natural has completed additional pad drilling at Primrose on schedule and drilled on budget. These wells are expected to come on production in 2013.
Primrose East
Orion
Updated: Jun 2012
Shell is looking to sell the Orion property, reportedly to focus on in situ operations at Peace River.
Phase 1
10,000
2007
Operating
Phase 2
10,000
TBD
Approved
PEACE RIVER REGION — IN SITU Andora Energy Corporation
Baytex Energy Corp. •
32,000
2008
Sawn Lake
Updated: Dec 2012
Andora Energy majority owner Pan Orient Energy says activities are currently underway to commence steam injection at Sawn Lake in Q2/2013, with production anticipated in Q4/2013.
SAGD Demonstration
1,400
2013
Approved
Baytex Energy Corp. •
Cliffdale
Updated: Dec 2012
Subject to regulatory approvals, Baytex anticipates development of a new 15-well thermal module to begin in Q1/2013, building on the 10-well module that has been operating since Dec. 2011.
Pilot
1,900
2010
TBD
TBD
Operating
Murphy Oil Company Ltd.
Cadotte
Pilot
Seal/Cadotte
Pilot
Updated: Nov 2012 Application Updated: Nov 2012 TBD
2012
Operating
Northern Alberta Oil Ltd. Sawn Lake
Operating
Updated: Dec 2012
Primrose North
30,000
2006
Operating
Primrose South
45,000
1985
Operating
Company owner Deep Well Oil & Gas says WorleyParsons has launched preliminary engineering work on the Sawn Lake pilot project. The work will include a pilot plan, process flow diagrams, material balances for hydrocarbons, sulphur and water, description of the capacity and content of emissions.
Wolf Lake
13,000
1985
Operating
CSS Pilot
700
TBD
Approved
FEbruary 2013 | OILSANDSREVIEW.COM 45
P R O J E C T S TAT U S
CURRENT PROJECT
CAPACITY
START-UP
REGULATORY STATUS
CURRENT PROJECT
CAPACITY
START-UP
Fort Hills
Penn West Petroleum Ltd. Harmon Valley South
Updated: Dec 2012
Updated: Dec 2012
Suncor and partner Total continue to review development timelines for Fort Hills.
Penn West and its partner have received regulatory approval to proceed with the Harmon Valley South pilot.
Phase 1
145,000
TBD
Pilot
Phase 2 & 3
145,000
TBD
Seal Main
Commercial
Pilot
TBD
TBD
Approved
Voyageur Upgrader 3
Updated: Sep 2012 Application
Suncor and partner Total have agreed to an immediate minimum spend program on Voyageur. A go/no-go decision on the project is now expected in Q1/2013.
75
2011
Operating
Phase 1
127,000
2016
Approved
Phase 2
63,000
TBD
Approved
Dawson
Updated: Jul 2012
Experimental THAI Demonstration
10,000
2013
Construction
Phase 2
10,000
TBD
Announced
Royal Dutch Shell plc
Syncrude Canada Ltd.
Mildred Lake/Aurora
Base Plant Stage 1 & 2 Debottleneck
Stage 3 Debottleneck
Stage 3 Expansion (UE-1)
Peace River
Updated: Dec 2011
12,500
1986
Operating
Carmon Creek - Phase 1
40,000
2015
Application
Carmon Creek - Phase 2
40,000
2018
Application
Southern Pacific Resource Corp.
Red Earth
Updated: Oct 2012
Updated: Oct 2012
Syncrude has announced it is embarking on a new mine extension project at Mildred Lake, which will be known as the MLX project. Canadian Oil Sands says MLX will leverage investment in the two mine trains currently being constructed, enabling Syncrude to extend the life of Mildred Lake mining operations by about a decade. Project scoping is underway, and pending regulatory approval, construction and spending would commence in the next 10 years.
Alberta’s environmental assessment director has deemed complete Shell Canada’s environmental impact assessment report for the Carmon Creek expansion. Cadotte Lake
On Hold Updated: Dec 2012
2015
Petrobank says it is awaiting regulatory approval to initiate cold production on its two well demonstration project to condition the reservoir prior to THAI operations.
On Hold
10,000
Petrobank Energy and Resources Ltd.
REGULATORY STATUS
250,000
1978
Operating
75,000
TBD
Announced
100,000
2006
Operating
SOUTH ATHABASCA REGION — UPGRADER Nexen Inc. •
Long Lake
Updated: Dec 2012
CNOOC’s bid to acquire Nexen has been approved by the Canadian government and is expected to close imminently.
Southern Pacific has yet to release its future development plans for the Red Earth project.
Phase 1
58,500
2008
Operating
Commercial
10,000
TBD
Announced
Phase 2
58,500
TBD
Approved
Pilot
1,000
2009
Operating
Phase 3
58,500
TBD
Application
Pilot Expansion
3,000
TBD
Announced
Phase 4
58,500
TBD
Announced
Value Creation Inc.
NORTH ATHABASCA REGION — UPGRADER
Advanced TriStar
BP p.l.c.
Terre de Grace
Updated: May 2012
Updated: Dec 2012
Value Creation has submitted an environmental assessment report for the Advanced TriStar project.
BP says that ongoing appraisal activities include delineation drilling, seismic acquisition and appraisal of water sources.
ATS-1
12,750
2016
Application
ATS-2
25,500
2018
Application
25,500
2020
Pilot
8,400
TBD
Approved
Canadian Natural Resources Limited
ATS-3
•
TriStar
Canadian Natural says it continues its strategy of staged expansion to 250,000 barrels per day and work remains on track. Projects currently under construction are trending at or below estimates.
Pilot
Phase 1
INDUSTRIAL HEARTLAND REGION — UPGRADER
Horizon
Updated: Dec 2012
Application Updated: Oct 2012
840
2014
Application
114,000
2009
Operating
Phase 2A
10,000
2014
Construction
Phase 2B
45,000
TBD
Approved
Project partners North West Upgrading and Canadian Natural Resources have sanctioned the project, with above-ground construction to begin in spring 2013.
Phase 3
80,000
TBD
Approved
Phase 1
77,000
2016
Approved
Tranche 2
5,000
2012
Operating
Phase 2
77,000
TBD
Approved
Phase 3
77,000
TBD
Approved
158,000
2003
Operating
91,000
2011
Operating
North West Upgrading Inc.
Ivanhoe Energy Inc. Tamarack
Updated: Dec 2012
Ivanhoe is responding to a third round of supplemental information requests from regulators regarding its project application. Approval is now anticipated in 2013.
Phase 1
34,784
2016
Application
Suncor Energy Inc. Base Operations
Updated: Dec 2012
Suncor says it has started up its new Millennium Naphtha Unit and has run it at full rates. The unit is expected to stabilize secondary upgrading capacity and provide flexibility during maintenance activ ities for secondary upgrading units in the future.
Redwater Upgrader
Updated: Nov 2012
Shell Albian Sands
Scotford Upgrader 1
Commercial
Expansion
Updated: Jul 2012
Value Creation Inc.
Heartland
Updated: Dec 2012
Construction was suspended in September 2008. Value Creation says it remains committed to the project and is seeking a development partnership.
Millennium Coker Unit
97,000
2008
Operating
Phase 1
46,300
TBD
On Hold
Millennium Vacuum Unit
35,000
2005
Operating
Phase 2
46,300
TBD
Approved
U1 and U2
225,000
1967
Operating
Phase 3
46,300
TBD
Approved
46 OILSANDS REVIEW | February 2013
S TAT I S T I C S
02 13 statistics Taking a close look at the inputs to and outputs of the oilsands industry. For suggestions or data contributions, please contact Deborah Jaremko, djaremko@junewarren-nickles.com.
North American Carbon Steel Prices
Bitumen Royalty Valuation at Hardisty, Alta.: $C/m3
Condensate
985 kg/m 3 3.5% sulphur bitumen Brent**
$140 $120
$80 $60 $40 $20
Dec
Nov
Oct
Sep
Aug
Nov
Sep
Aug
Jul
Jun
May
Apr
Mar
Oct
Trade
300 250 200 150 100 50
Nov
Oct
Sep
Aug
Jul
Jun
May
Dec 3
Apr
Oct 1
Mar
Sep 3
Feb
0
May 1 Jun 1 Jul 2 2012
Jan 2012
$0
Construction
350
Dec 2011
wtd price (US$/bbl)
$100
Forestry, fishing, mining, oil and gas
SOURCE: ALBERTA HUMAN RESOURCES AND EMPLOYMENT
West Texas Intermediate*
Light sour
$20
Alberta Labour Force Statistics SOURCE: FLINT HILLS RESOURCES LTD./ ENERGY INFORMATION ADMINISTRATION * WTI spot price at Cushing, OKLA. **Europe spot price
Cold Lake blend
$40
$0
Monthly Crude Oil Prices: May 2012 – Dec. 2012 Bow River
$60
Nov
Oct
Sep
Aug
Jul
Jun
Apr
May
Mar
Feb
Jan 2012
Dec 2011
$100
1015.0 kg/m3 bitumen
$80
Feb
$200
$100
Jan 2012
$300
Calculated using NetThruPut Monthly WCS Index
Dec 2011
$400
SOURCE: CANADIAN ASSOCIATION OF PETROLEUM PRODUCERS
SOURCE: CANADIAN ASSOCIATION OF PETROLEUM PRODUCERS
$500
Western Canadian Select
Jul
Bitumen Royalty Valuation at Hardisty, Alta.: $US/bbl
$600
$0
$600
Jun
Dec
Nov
Oct
Sep
Jul
Aug
Jun
May
Apr
Mar
Feb
Jan 2012
0
$700
May
$1.00 $0.50
$800
Apr
$1.50
Mar
$2.00
Reinforcing Bar
$900
Feb
$2.50
number of people (unadjusted, thousands)
C$/GJ
$3.00
Structural Sections and Beams
$1,000
Jan 2012
$3.50
Hot Rolled Coil
SOURCE: MEPS International
$4.00
SOURCE: NATURAL GAS EXCHANGE INC.
Monthly averages to December 21, 2012
US$/tonne
Natural Gas: Spot Prices at AECO Trading Hub in Alberta
FEBRUARY 2013 | OILSANDSREVIEW.COM 47
S TAT I S T I C S
Public Offerings of Crown Oilsands Rights Athabasca Sale Month
Hectares
Hectares
Peace River $/Hectare
Hectares
$/Hectare
0
$0.00
0
$0.00
5,888
$27.18
Aug 2011
768
$15.89
1,024
$340.25
0
$0.00
Sep 2011
924
$279.79
0
$0.00
0
$0.00
Oct 2011
0
$0.00
584
$379.37
0
$0.00
Nov 2011
NO PUBLIC OFFERING NOTICES
Dec 2011
29,108
$1,913.50
0
$0.00
0
$0.00
Jan 2012
0
$0.00
128
$560.50
512
$613.18
Feb 2012
0
$0.00
1,152
$621.19
0
$0.00
44,800
$16.02
0
$0.00
1,792
$44.47
0
$0.00
0
$0.00
1,536
$1,052.00
512
$138.13
768
$101.04
9,165
$44.16
Jun 2012
0
$0.00
701
$737.35
0
$0.00
Jul 2012
11,816
$258.84
1,024
$339.49
0
$0.00
Aug 2012
512
$273.47
256
$1,227.49
0
$0.00
Sep 2012
832
$119.14
512
$2,123.33
1,024
$115.96
Oct 2012
0
$0.00
256
$317.97
0
$0.00
Nov 2012
1,024
$136.70
256
$2,876.76
0
$0.00
Mar 2012* Apr 2012 May 2012**
Dec 2012
SOURCE: government of alberta
Jul 2011
Cold Lake $/Hectare
NO PUBLIC OFFERING NOTICES
*Includes Athabasca region oilsands permits from Mar. 24 sale. **Includes Peace River region permits from May 2 sale.
FirstEnergy Oilsands, Integrated and Large Cap Indexes Integrated
Large Cap
Source: FirstEnergy Capital Corp.
Oilsands
140
120
100
80
La
In 60
O
Dec*
Nov
Oct
Sep
Aug
Jul
Jun
May
Apr
Mar
Feb
Jan 2012
Dec
Nov
Oct
Sep
Aug
Jul
Jun
May
Apr
Mar
Feb 2011
40
*Recorded until Dec. 19, 2012.
Index launched Jan. 1, 2007. FirstEnergy complimentary indexes are available daily on the homepage at firstenergy.com. FirstEnergy Capital Corp. is a member of the Canadian Investor Protection Fund and IIROC.
48 OILSANDS REVIEW | FEBRUARY 2013
S TAT I S T I C S
Thermal Oilsands Project Steam to Oil Ratios (Steam Injected:Oil Produced)
8.0
Baytex Energy Corp. Cliffdale Pilot
141.80 (Aug) 138.07 (Sep)
BlackPearl Resources Inc. Blackrod Canadian Natural Resources Limited Primrose & Wolf Lake
7.0
Cenovus Energy Inc. Christina Lake
steam injected:oil produced
Cenovus Energy Inc. Foster Creek Cenovus Energy Inc. Pelican Lake Grand Rapids
6.0
Connacher Oil and Gas Limited Algar Connacher Oil and Gas Limited Great Divide ConocoPhillips Canada Limited Surmont
5.0
ConocoPhillips Canada Limited Surmont Pilot Devon Canada Corporation Jackfish Husky Energy Inc. Tucker
4.0
Imperial Oil Limited Cold Lake Japan Canada Oil Sands Limited Hangingstone Pilot MEG Energy Corp. Christina Lake
3.0
Nexen Inc. Long Lake Pengrowth Energy Corporation Lindbergh Pilot
2.0
Royal Dutch Shell plc Orion Royal Dutch Shell plc Peace River
Statoil Leismer Suncor Energy Inc. Firebag Suncor Energy Inc. MacKay River
0
Apr 2012
May 2012
Jun 2012
Jul 2012
Aug 2012
SOURCE: ERCB
Southern Pacific Resource Corp. STP-McKay
1.0
Sep 2012
Alberta Crude Bitumen and Synthetic Crude Production 2010-12 Source: Alberta Energy Resources conservation Board
Crude bitumen
Synthetic crude
40,000
35,000
30,000
20,000
15,000
10,000
5,000
Jul
Aug
Jun
May
Apr
Mar
Feb
Jan 2012
Dec
Oct
Nov
Sep
Aug
Jul
Jun
Apr
May
Feb
Mar
Dec
Jan 2011
Oct
Nov
Sep
Aug
Jul
Jun
Apr
May
Mar
0 Feb 2010
million barrels
25,000
FEBRUARY 2013 | OILSANDSREVIEW.COM 49
S TAT I S T I C S
Bitumen Synthetic Plant Operations: External Energy
Bitumen Synthetic Plant Operations: Oilsands
(10 3 m3)
Gas
(MWh)
Electric
(10 3 m3)
(MWh)
Albian Sands
purchased
74,608.0
47.0
74,747.3
1,391.0
generated
0.0
121,320.0
0.0
110,064.0
CNRL Horizon
purchased
59,073.4
4,650.9
60,615.3
1,564.0
generated
0.0
72,863.0
0.0
73,832.0
Imperial Oil purchased (Kearl Mine) generated
--
888.0
--
2,950.0
--
0.0
--
0.0
purchased
7,375.2
43,485.3
3,612.3
7,215.3
(Nexen)
generated
0.0
78.4
0.0
78.4
Shell Jackpine
purchased
24,145.0
29,721.0
21,738.3
23,957.0
generated
0.0
0.0
0.0
0.0
Shell Scotford
purchased
160,567.3
6,278.5
162,671.3
27,635.1
generated
0.0
89,127.4
0.0
90,125.4
purchased
109,012.0
89,846.0
106,387.0
116,039.0
OPTI
Suncor
generated
0.0
218,392.0
0.0
234,094.0
purchased
33,032.0
0.0
35,355.1
0.0
generated
0.0
59,260.9
0.0
59,138.9
purchased
162,055.7
30,775.1
166,080.1
35,481.3
(Mildred Lake) generated
0.0
195,480.0
0.0
178,878.6
Syncrude (Aurora)
Syncrude Williams Energy
purchased
921.9
2,573.9
797.7
2,410.4
generated
0.0
0.0
0.0
0.0
August 2012 Barrels
Grade*
September 2012 Barrels
Grade*
Albian Sands mined
62,000,958.9
11.14%
58,249,113.1
11.08%
processed
48,683,470.4
10.69%
51,120,402.2
10.69%
46,027,855.4
11.56%
38,176,216.0
11.31%
46,147,891.5
11.36%
38,584,995.4
11.08%
CNRL Horizon mined processed Jackpine Mine mined
32,289,764.2
11.95%
27,621,844.2
12.19%
processed
36,252,889.9
11.66%
28,995,434.9
11.36%
mined
111,724,996.2
11.20%
86,069,277.8
11.10%
processed
111,724,996.2
11.20%
86,069,277.8
11.10%
mined
74,880,106.1
11.21%
65,518,171.5
11.01%
processed
74,880,106.1
11.21%
65,518,171.5
11.01%
mined
62,078,870.2
10.43%
57,536,568.2
11.27%
processed
63,782,698.7
10.41%
63,175,100.3
11.11%
Suncor
SOURCE: ALBERTA ENERGY RESOURCES CONSERVATION BOARD
September 2012
Electric
SOURCE: ALBERTA ENERGY RESOURCES CONSERVATION BOARD
August 2012 Gas
Syncrude (Aurora)
Syncrude (Mildred Lake)
* Grade is a measurement of mass per cent bitumen in oilsands.
Alberta Crude Bitumen Production (non-primary) Commercial in situ schemes production rates per calendar day (bbls/d), listed in descending order of production for last month of data set
t Cenovus Energy Inc. rCanadian Natural Resources Limited Suncor Energy Inc.
August 2012
September 2012
Three-Month Average
153,769.5
150,573.0
148,508.7
Foster Creek
127,433.5
125,968.6
124,213.1
125,871.69
Primrose/Wolf Lake
90,924.2
93,110.6
116,455.8
100,163.56 112,524.51
I
1
117,657.8
114,970.2
58,100.2
62,693.1
71,266.1
64,019.79
Jackfish
55,007.5
53,206.8
29,385.4
45,866.56
Surmont
21,077.2
22,734.5
26,398.3
23,403.34
Leismer
16,267.3
16,959.8
16,469.9
16,565.68
Long Lake
33,751.8
15,461.6
14,639.5
21,284.30
Great Divide
5,330.6
5,253.2
10,698.3
7,094.07
Christina Lake
31,211.9
30,242.7
9,910.9
23,788.48
Tucker
9,464.3
9,424.7
9,646.7
9,511.87
Peace River
4,559.5
7,867.9
7,568.5
6,665.31
Hilda Lake/Orion
2,518.4
3,697.8
4,547.5
3,587.92
Hangingstone
5,825.0
4,743.1
4,534.3
5,034.15
Lindbergh pilot
1,239.1
1,191.3
1,400.7
1,277.04
Cliffdale pilot
402.5
277.4
493.1
391.0
ConocoPhillips Canada Limited
Surmont pilot
488.7
530.2
406.3
475.09
Suncor Energy Inc.
MacKay River
31,747.2
18,427.3
308.2
16,827.55
Blackrod
305.7
339.0
282.4
309.0
I
Seal Main pilot
452.9
367.3
281.8
367.32
I
Cenovus Energy Inc.
Grand Rapids pilot
213.2
150.3
182.4
181.99
Southern Pacific Resource Corp.
STP-McKay
---
55.4
53.5
36.29
Baytex Energy Corp.
Harmon Valley pilot
15.7
34.0
38.4
29.4
E-T Energy Ltd.
Poplar Creek
ConocoPhillips Canada Limited
Connacher Oil and Gas Limited
t MEG Energy Corp. rHusky Energy Inc. Shell Canada Limited t Shell Canada Limited rJapan Canada Oil Sands Limited Pengrowth Energy Corporation
rBaytex Energy Corp.
rBlackPearl Resources I Penn West Petroleum Limited
r
rConnacher Oil and Gas Limited Murphy Oil Company Ltd.
I
TOTAL
50 OILSANDS REVIEW | FEBRUARY 2013
Firebag
150,950.43
104,945.5
t Statoil Canada Ltd. rNexen Inc.
I
July 2012
Christina Lake
t Cenovus Energy Inc. rDevon Canada Corporation
I
Project Cold Lake
Algar Seal/Cadotte pilot
I
1
I
1
I
1
I
1
5.0
8.2
8.8
7.34
5,830.7
6,376.0
---
4,068.88
27.7
6.3
---
11.32
760,914.9
747,357.9
712,668.9
740,313.89
I I
I I
I
I
SOURCE: ALBERTA ENERGY RESOURCES CONSERVATION BOARD
Operator Imperial Oil Limited